1 Course Name 2 Candidate Name Ashar Milind Mahesh Rashmi: Module 56/ PGPPM
1 Course Name 2 Candidate Name Ashar Milind Mahesh Rashmi: Module 56/ PGPPM
210-03-31-8104-2123 PGPM 22
19th February 2011
Project Identification :
Construction of a new international cricket facility outside a mega city. It should have the following facilities1. Capacity of spectators- 80,000 2. Play facility for- Day & Night play. 3. 6 directional T.V. camera platforms. 4. Safety of players from the spectators.
5. Pavilion for V.I.P with a seating capacity for 300. 6. Adequate parking space for all. Time available- 16 months inclusive of monsoon. Other details- Cost of construction is to be recovered in 5 years. The average cost per ticket will be Rs100/- & there will be 4 matches per season. Note- all figures taken for calculations are based on assumptions except those provided. All conditions are also assumed regarding the project execution & nature of work. Calculation of approximate projected revenue to be earned by the stadium in a period of 5 yearsCapacity of spectators (excluding V.I.P seats) Capacity for V.I.P pavilion Assumed total capacity= 80,000 300 80,300
Assumed cost per ticket1. Average cost per ticket for spectators- Rs100/2. Average cost per ticket for V.I.P seats- Rs200/Assumed revenue of the stadium per match: It is assumed that the stadium will not always be packed to capacity. So we will take an average of the tickets expected to be sold.
Average capacity covered for 4 matches per season for spectators1st Match2n d Match3r d Match4th Match-
100% of total capacity. 80% of total capacity. 60% of total capacity. 50% of total capacity.
Therefore- Average seats filled for spectators= (100+80+60+50) 4=72.5% or say 73%.
Average capacity covered for 4 matches per season for V.I.P pavilion1st Match2n d Match3r d Match4t h Match-
100% of total capacity. 100% of total capacity. 80% of total capacity. 75% of total capacity.
Therefore- Average seats filled for the V.I.P pavilion=(100+100+80+75)4=88.75% or say 89%. Based on the above assumed data the revenue expected per match is-
= {(73% x 80,000) x Rs100/-} + {(89% x 300) x Rs200/-} = Rs58, 93,400/- per match. Assumed revenue expected per seasonRevenue expected= 4 matches per season x Rs58, 93,400/= Rs2, 35, 73,600/Assumed revenue expected in a 5 year periodRevenue= 5 years x Rs2, 35, 73,600/= Rs11, 78, 68,000/Since the cost of construction is to be recovered in five years based on the above given assumptions which have been considered taking a pessimistic point of view that all the seats in the stadium will not always be booked to capacity so the entire cost of the project should not exceed the derived value of revenue recoverable within a period of five years. Therefore the total cost of construction should not exceed Rs11, 78, 68,000/- & for this period the maintenance cost should be zero. The technical aspects of the construction design; planning & execution should keep in mind the above figure so that the ultimate cost should be within this limit.
FEASABILITY STUDIES The major construction projects are undertaken to meet the particular needs of a client. Generally, a client is well informed and clear about what he needs, but sometimes what he thinks he wants and what he really needs may actually be different. The first step in the development of a project is to analyze the needs of the client. This requires a critical examination of the needs through feasibility studies. The feasibility study evaluates project potential by examining technical feasibility, economic viability and financial implications. The subject to be covered in the feasibility report of a construction project will depend upon the purpose of the report and the nature of the project. For example, the feasibility report of an industrial project may include the following aspects:
1. Proposed product features. 2. Demand survey it includes prospective customers, consumption pattern, existing market, government policy, demand forecast and sale potential. 3. Technical studies These cover production process selection, construction methodology, location study, power and local resources availability, means of transportation, scope of work, wastage disposal arrangement, construction cost estimates, preliminary time plan,
resource forecasts, outline project organization, and statement of project time and cost objectives. 4. Financial implications It contains sales forecast, project budget, capital costs, profitability trend, payback period, net present worth, cash flow forecast, and sources of financing. 5. Economic viability It highlights social implications and cost benefit analysis. 6. Summary of recommendations.
The feasibility report, if found favorable, is followed up with investment appraisal. The purpose of appraisal is to conduct an objective assessment for investment decision. It involves critical examination of the techno-economic analysis of feasibility findings, with particular reference to: Demand analysis Technical specifications feasibility Strength, weaknesses, opportunity and threat (SWOT) analysis Environments implications Financial analysis Economic analysis
Appraisal of feasibility stage enables a client to: a) Decide on the project concept, time and costs; b) Outline the approach needed to taking the project; c) Appoint key persons like construction project manager or project coordinator, to act as his representatives; and d) Nominate specialist-associated agencies such as the architect, designer and consultants, as per the requirements. Depending upon the nature and complexity of the project, the following may assist client in making decisions. a) Client representative these include the prospective project manager or his nominee and the related officials. b) Specialist these include the architects, engineers, planners, and finance management consultants. c) Concerned officials of administration and technical departments. The process of formulation of needs, collection of information, critical examination concept and re-examination of needs, may have to be repeated several times over before a project inception finally takes shape. Finally, the feasibility studies and its appraisal lead to the definition of the following aspects relating to the project: Broad scope of work involved. Project objectives. Outline execution methodology.
Preliminary time plan. Resource forecasts. Cash flow pattern and sources of funding. Outline organization. Potential risks and problem areas.
a) Architect and design engineers. b) Construction engineers from HVAC, civil, mechanical or electrical branches. c) Tendering staff, like the contracts managers and quantity surveyors. d) Specialists consultants, such as the town planners, geologists, and the environmentalists. e) Selected manager and the connected officials.
In this preparation stage, the project manager, assisted by the chief project planner, performs the key functions. These include, but are not limited to, the following: a) Participate in the finalization of design, drawings and specifications so as to formulate construction methodology. b) Prepare project execution preliminary plan and formulate the schedule for processing various contracts. c) Advise the client on an early purchase of the items of plant and equipment needing a long lead-time for procurement. d) Evolve the pre-tender construction plan for each tender package. e) Scrutinize the tender packages, including drawings and specifications, so as to minimize the discrepancies. f) Conduct the pre-tender briefing to contractors to ensure that the bidders understand the tender
documents and the work involved in each tender. g) Evaluate project costs and compile project budget including preliminary allocations for the various heads of expenditures. h) Compile a project directive covering the scope of work, work plan, organization, and the policies and procedures for implementing the project.
Execution Stage
Most of the construction projects are executed through the contract system. The contract documents define the contracted scope of the work of each contractor. They also provide the contractual relationship between the construction manager of the contractors and the project manager. The contract agreement is based on mutual trust between the contracting parties, both of whom have their share of responsibilities and obligations. In this process, disagreements sometimes arise. These may be on account of deviations in the scope of work and other factors like time delays, inflation and unforeseen circumstances. Contract provisions do provide a mechanism for the settlement of such disputes through arbitration.
Construction at the site of the contracted projects is supervised and carried out by two separate agencies. These are: the client team led by the project manager, and the contractor workforce managed by his construction manager. Both teams have the common goal of completing the project in time within specified costs and quality specification. However, their roles differ. It is the project manager who plays the dominant role. He represents the client and acts as the boss at site. He ensures smooth functioning at site and makes decisions when the] site faces problems. He manages the entire construction process so as to achieve the assigned project objectives. He manages the contractors employed at site, and the site activities, with the help of his supervisory team that reports to him for decisions; it is he who is accountable to the client for the construction of the project. The main functions of this constructions supervision team can be outlined as follows. 1. Scrutinize the contract documents to ensure that all amendments are incorporated into the drawings, specifications and bill of quantities held at site. 2. Scrutinize the contractor's plan of work, the mobilization plan, the construction and the quality control measures to ensure that they are in order. 3. Scrutinize the pre-work preparation of work to ensure a smooth start of construction activities 4. Scrutinize the work programmes to ensure that they are realistic, and monitor their progress regularly. 5. Scrutinize the quality of materials to ensure that they meet the contract specifications and also report any deviations. 6. Scrutinize the geotechnical investigations conducted by the contractor to ensure the adequacy of design parameters. 7. Scrutinize the fieldwork regularly to ensure proper layouts, work conformity as per drawings and specifications, and good standards of workmanship. 8. Scrutinize the safety measures and working conditions to ensure healthy environments and prevention of accidents. procedures
9. Hold review meetings to monitor progress, communicate observations, resolve problems and plan future works. 10. Scrutinize the payment of monthly bills of contractor to ensure correctness. 11. Exercise cost control and cost reduction measures. 12. Maintain project records, monitor the progress and submit management information reports at the predetermined frequency. 13. Report immediately to the project manager ale cases amounting to breach of contract, nonadherence to specifications, slow progress and lack of co-operation. 14. Take over the project on completion, as per the contract stipulations. The completion of the construction phase of the project includes certain follow-up actions necessary to ensure that the facility constructed functions satisfactorily. These are as follows. a) The post-completion maintenance is usually entrusted to an agency familiar with the construction. In most cases, the contractor responsible for construction is given this responsibility one year after completion; and this aspect is included in the scope of work of the contractor, b) A proper record of the operating instructions and as-built drawings is maintained. c) The staff and workers necessary for operating and maintaining the facility are trained prior to its taking over. d) The site is cleared of the left-outs of the construction and unwanted materials. e) The client fully safeguards his interests prior to rendering the completion certificate to the contractor, and also before making the final payments. After completion by the contractor, it is the project team of the client that hands over the project to him. The team also prepares a project completion report which includes the scope and schedule of work, the important events, the contract executed, the addresses of the suppliers of materials and equipment, the equipment maintenance manual, the as-built drawings, the costs involved, the problems encountered during execution, the lessons learned and the minor defects noticed at the time of handing over examines present project details.
Project Management Functions The overall aim of the management in an enterprise is to create within the enterprise, an environment that will facilitate the accompli-shment of its objectives. In doing this, a certain functions. Although the development of a theory and from disagreement among scholars and managers, a general pattern of functions which management has to perform, has emerged. Traditionally, ions are grouped under six headings, namely planning, organizing, staffing, and common to all these functions is the function of coordination. These functional areas, with some adjustments on account of the special characteristics of construction projects, are equally applicable in project management. The project
management fraction* of planning, organizing, procuring, leading and controlling are outlined below: Planning: Planning involves deciding in advance what is to be done, how and in what order it is to be done in order to achieve the objectives Planning aims at deciding upon the future course of action. A plan shows the committed course of action. Schedule depicts when the planned activities are to be carried, it puts the plan on calendar date scale. In brief, planning and scheduling involves the following: Crystallizing objectives. a) Collecting and synthesizing information. b) Developing alternative courses of action within specified constraints. c) Comparing alternatives in terms of objectives feasibility and consequences. d) Selecting and scheduling the optimum course of action. e) Establishing policies, procedures, methods, schedules, programmers, systems, standards and
budgets for accomplishing project objectives. Organizing: Organizing is the process of establishing a structural relationship among functions of people, so as to formulate effective machinery for streamlining the achievement of assigned objectives. Organizing involves the following main tasks: a) Dividing the work into component activities. b) Designing job structures. c) Defining performance targets and responsibilities. d) Allocating resources. e) Delegating authority commensurate with responsibility. f) Establishing structural relationship to secure coordination.
Procuring: it implies managing and keeping manned, the positions created by organization structure and providing them the right quality resources at the right time. These resources include people, materials, machinery and money. The connected project management tasks include the following: a) Preparing resource procurement schedules. b)Developing specifications for required resources. c) Deciding appropriate sources of procurement. d) Budgeting resources and arranging approvals and purchases. e) Preventing wastage during resource holding at site. f) Supplying on time required quality and quantity of resources to project construction sites.
Directing or Leading: It involves influencing people so as to enable them to contribute to organizational goals efficiently and effectively. Direction implies the following tasks:
a) Providing effective leadership. b)Motivating participants behavior. c) Communicating instructions and orders.
d)Providing a suitable climate for subordinates' development. Controlling: Controlling involves monitoring of the performance and applying corrective measures in case of deviations from the plan. The process of control can be sub-divided into the following stages: a) Specifying the factors to be controlled. b) Stating the methods of measuring control factors. c) Evolving systems for generating performance data, d) Monitoring data received and formulating corrective options. e) Applying corrective measures put a plan on the scheduled path.
The matrix structure is viewed as a temporary organization having human and non-human resources with reduced vertical hierarchy so as to respond speedily in a changing complex situation for achieving the specified performance objectives. The managers in a project team are its key personnel. They are drawn from their parent departments and are Specialists in their field. They charged with the responsibility of their respective areas of activity. In this way, commutation and coordination between top management and project management is improved.
Following are the advantages of the matrix structure: a) It has a single project manager accountable or the whole project. The project management, working as a team, performs tie bane management functions of planning, organizing, staffing, directing, controlling and coordinating the project work. b) All managers owe their allegiance to the project manager, and not to their parent departmental heads. c) Personal commitment to objectives is the key no of matrix organization. It provides a climate for motivation, effectiveness and personal development. d) The specialist staff is employed effectively. The matrix organization balances their conflicting objectives by reducing the communication gap. e) The top management is freed from making routine decisions, as the decision-making machinery forms an integral part of the matrix structure. f) It provides enough flexibility to meet uncertain arid changing situations by establishing a project planning and control system at site to monitor the input flow of resources and the performance output.
However, if not properly conceived and directed, the matrix organization-can result in increased conflicts, lack of coordination, low productivity, and enhanced costs.
Structural Elec & Contracts Management Managem Services Planning Administrat Engineeri Mech ent Engineeri ion ng
Functional Representatives fr om Parent Depar tments
Manag er
The construction planning process is stimulated through a study of project documents. These documents includebut are not limited tothe available technical and commercial studies and investigations, designs and drawings, estimate of quantities, construction method statements, project planning data, contract documents, site conditions, working regulations, market survey, local resources, project environment and the client's organization. The planning process takes into account the strengths and weaknesses of the organization as well as the anticipated opportunities and risks. Planning follows a systematic approach. Various planning techniques are employed to systematize and transform the mental thought process into a concrete project plan. Generally, the following steps are involved in planning for a project: a) Define the scope of work to be performed. b) Identifying the activities involved, and assessing the approximate quantities of physical resources needed activity-wise. c) Preparing the logic or network diagram(s) to establish a relationship among activities, and integrating these diagram(s) to develop the project network or model. d) Analyzing the project network or model to determine project duration, and identifying critical and non-critical activities.
e) Exploring trade-off between time and cost to arrive at the optimal time and costs for completing the project. f) Exploring work options within specified time and resource constraints, and deciding on the project-work schedule, g) Establishing standards for planning and controlling men, materials, equipment, costs and income of each work package. h) Forecasting input resources, production costs and the value of the work done. i) Assigning physical resources like men, materials and equipment activity-wise, and allocating these to the organizational units earmarked for execution. j) Forecasting the project budget and budget allocations for achieving targets assigned to each organizational unit, k) Designing a control system for the organization. l) Developing the resources, time, and cost control methodology. m) Evolving an information communication system n) Computerizing the planning and control system.
Work-breakdown Levels
Corporate ManagementSummary planSub-project Project Management..ProjectMasterPlanTasks/work Package Managerial Levels.Task/Contract Plan..Work Packages Supervisor Level..Quarterly/MonthlyWorkProgrammeActivity
The breaking down of a task/work package into its constituent activities requires a study of the methodology of execution of the work package. Generally, known by the term method statement, this methodology is evolved by the planning engineer on the basis of his construction experience and discussions with the respective project engineers. Construction projects are best managed by work packages, which, in turn, are best planned and monitored by activities. A project planner uses activity as the common database for planning projects. Activity duration forms the basis for time planning and scheduling of project work. The
inputs of labour, materials and machinery needed for execution each activity enable preparation of resources forecasts. The activity sale price is used to determine income and cash flow forecasts. The activity base is vital for monitoring progress of the project work.
PROJECT CONTROL PROCESS The project plan indicates the path charted to achieve the objectives of the project. During the implementation stage, the project control system aims at ensuring the execution of work as per the planned schedule and the application of necessary corrective measures, including re-planning, to achieve the project objectives. Even with the best of efforts, the probability of execution of a project exactly as per the original plan is negligible because the project implementation may undergo unpredictable resource problems and unforeseen time delays: These unforeseen factors demand constant vigilance and, from time to time, decisions have to be made for the smooth progressing of the project work. Like the guidance system of a missile, an effective control system corrects all deviations from the planned path. Planning and controlling, therefore, are inseparable. Control involves organizing the control responsibility centers, designing accounting and monitoring methodology, codifying data and developing the information systems so as to makedecisions speedily. It also includes identifying the problem areas, making risk-taking decisions to tackle the problem, organizing and directing resources needed to carry out these decisions, and measuring the results of these decisions against targeted expectations through organized and systematic feedback. An efficient control system improves productivity of men and materials, economizes employment of resources, enables understanding of time and cost behaviors, provides yard sticks for measuring performances, generates information for updating resource planning and costing norms, prevents pilferage and frauds and assists in formulating bonus or incentives schemes for motivating the people. The project control system covered in this book deals with the project control methodology; controlling the productivity, cost and time; developing the codification system, aim, finally, computerizing the project management information system.
Each level has certain features associated with it however, it may be noted that level categorization is a broad concept and at times their overlapping may become unavoidable. The work breakdown structure of a project forms the basis for listing of activities modification of systems, sorting data by hierarchy levels, structuring of work organization and managing similarscope multi-projects.
Sub-projects Level
Dividing the project work into independent large-volume mini projects or task groups derives sub-projects. For instance, in a housing project, each group of major works, which can progress in a systematic manner, without interference from other works, can be termed as a sub-project. The number of sub-projects in a project varies with the nature of the project. Each sub-project comprises one or more substantial work tasks. The sub-project level aids in identifying tasks.
Tasks Level
The project or sub-project work can be split up into various tasks. A task is an identifiable and deliverable major work. It is an entity in itself and can be performed without much interference from other tasks. A task is supported by its design package. Each task is assigned time and cost objectives and is provided with planned resources for accomplishing the task objectives. The task execution is entrusted to a task responsibility unit, headed by a manager or a senior engineer. Task level is used in the project-summary plan, the design-preparation plan and the contracttendering plan.
Work-packages Level
A project task can be further subdivided into one or more -work packages. Each work package contains a sizeable, identifiable, measurable, costable and controllable package of work. In the project master plan or the contracted works-control plan, each work package is assignee! Its performance objectives. These are generally stated in terms of its completion period, standard cost, resourceproductivity standards and the standard sale price. The measure of performance thus, gets closely linked with the execution of its work packages. Work packages form a common base for linking the key functions in project management. The work-package concept leads to the simple-management theory of managing, designing, estimating, planning, organizing, directing, communicating and controlling, using these work packages as the base lines.
Activity Level
A work package can further be broken down into various identifiable jobs, operations and processes, which consume time and possibly, other resources and are necessary for its completion. Each one of this is called an activity. As an example, the various activities involved in the construction of foundation of a residential building are listed. The breaking down of a work package into its constituent activities requires a study of the
methodology of execution of the work package. This methodology, generally known by the term method statement, is evolved by the concerned planning engineer using his construction experience and through his discussions with the respective project engineers.
Operations Level
An activity comprises one or more operations. Each operation contains a part of the work content of the activity. It generally has a particular type or a fixed group of resources associated with it. It is performed during the scheduled time duration of the activity. Some operations may start with the commencement of the activity, while others may take place during its time duration. In some situations, performance periods of operations may overlap. Operations are not considered during the network modeling and analysis stage except that the sum of the costs of operations equals the activity cost. They form the basis for allocation and scheduling of resources of each activity. A project planner uses activity as the common database for project planning. The activity duration forms the basis for time planning and scheduling of project work. Detailed information about resources such as men, materials and machinery needed for execution of each activity enables the preparation of resource forecasts. The activity sale price is used to determine the income; and cash-flow forecasts. The activity base is vital for monitoring the progress of the project work. The project will be phased into the following levels-
1. Foundation Work. 2. Superstructure-Gallery-1 3. Superstructure-Gallery-2 4. Superstructure-Gallery-3 5. Sanitary & Plumbing works. 6. Steel fabrication works. 7. Wood & aluminum works. 8. Electrical works. 9. Painting works. 10. Commissioning of the facility.
Work Break-down methodology 1. First PhaseThe foundation work will proceed from the commencement of the project after the site infrastructure has been made ready. In this phase only foundation work will proceed after layout has been given.
2. Second Phase- phase the superstructure for gallery one will start. There will be In the second no other work in this phase other than the completion of the superstructure with provision for concealed wiring. 3. Third the third phase the construction for the superstructure of gallery two will In Phasestart. During this period brickwork & plastering work will start for superstructure one along with provisions for concealed wiring & sanitary lines. 4. Fourth Phase- the superstructure work for gallery three will start along with In this phase brickwork & plastering for gallery two. Concealed wiring conduits to be laid in superstructure three & concealed wiring & sanitary provisions in superstructure two. Wood, aluminum & steel fabrication works to start in gallery one. 5. Fifth PhaseIn this phase the brickwork & plaster to start in gallery three. Electrical & sanitary lines which are concealed to be placed in gallery three. Wood, aluminum & steel fabrication works to be done in gallery three. 6. Sixth PhaseIn this phase wood, aluminum & steel fabrication works to be done in gallery three. Electrical wiring to be done in gallery one & gallery two. 7. Seventh Phase- the electrical wiring to be done in gallery two & painting work In this phase internal to be done in gallery one & two. 8. Eight this phase painting work to be done in gallery three while electrical & In Phasesanitary fitting to be fixed into position in gallery one & two. 9. Ninththis phase painting to be done on all external surfaces while electrical & In Phasesanitary fittings will be fixed in gallery three levels. All external connections of electrical & sanitary lines are to be connected in this phase. All glass fittings also to be done during this phase. 10.Tenth Phase- be commissioning of the entire facility during this phase & any There will corrections that need to be made will be done during this period. All lines electrical & sanitary are to be checked for its performance. Any defects detected during this will have to be corrected. After satisfactory performance of all the utilities will certificate will be provided for the facility to be put to use.
Consider a job involving 50 cubic metre of manual excavation over an area of 15 x 6 m. It is possible to organize work by employing 18 men for one day in two shifts, or three men for five days; or four men for four days to complete this task. If each man is paid Rs100 per day, and assuming that tools required for digging are brought by the workers, the time for completion of excavation and the corresponding labour costs for this activity can be tabulated as follows:
Cost ($)
The duration for this activity corresponding to the least cost of execution (Rs1500) should be taken as three days. It may be noted that the duration of an activity is correlated with time and its cost. The time and cost at the least cost point in termed as normal time and normal cost of the activity. Duration is estimated in terms of predetermined units of time: The unit of time can be a month, a week, a day or even an hour. The unit considered depends upon the plan type. The guidelines given below may be adapted for selecting the unit of time for assessment of duration of activities in the following: (i) Project Summary Schedule Months or weeks (ii) Project Master Schedule (iii) Detailed Work Programme Weeks Days or hours
The following conversion factors may be used for converting from one unit to another. (i) Working hours in a day (ii) Working days in a week (iii) Weeks in a year 8 hours 5 or 6 days 52 weeks
All activities in the network or schedule use same unit of time: The duration assessed in weeks include weekly holidays but exclude other holidays and non-productive period. Further, the seasonal and weather uncertainties are not considered; these are taken care of during scheduling stage. Overtime is not considered unless it is a standard practice. The assessed duration estimate is expressed in terms of unit of time, in the nearest whole number. Duration estimation is based on current practices: This implies that the estimation is based on the present knowledge of the method of transaction in an economical way; it may undergo a change with the passage of time or with improved techniques. Duration estimation is based on work being carried out under normal prevailing site conditions: This implies that estimation is based on the method of work under normal working conditions at the site using economical resources. Adjustments for time delaying factors like rainy season and bad weather are considered at the time of scheduling of work and resource Duration estimation methods presuppose that activity is performed in an organized manner: Working in an organized manner implies breaking down the activity into elements, matching optimum resources for each element, laying down a systematic method of execution, and specifying objectives and responsibilities so that the task is performed efficiently and enthusiastically. Duration is assessed preferably by the person responsible for its performance: This makes the duration estimate realistic and meaningful.
2. Accounting costs Production cost and earned (sales) value. The above cost terms are outlined in the following paragraphs. Activity direct cost: This is the cost that can be traced in full with the execution of a specific activity. It consists of costs of direct materials, direct labour, direct equipment and other direct costs. For example, in the activity of roof concreting, the following direct costs would be involved. Type of Costs Items of Costs Direct materials Cost of concrete and steel Direct labour Cost of labour employed Direct equipment Cost of equipment hired for placing ready mix Concrete Direct other expenses Formwork hiring and repair charges
Activity indirect cost: This is the cost that is incurred while performing an activity, but cannot be traced directly to its execution. In other words, all costs other than the direct ones fall in this category. These represent the apportioned share of supervision, general and administration costs, and are commonly referred to as overheads. Generally, the overheads charged to an activity are expressed as a percentage if its direct costs. Activity production cost this cost is the sum of direct cost and its apportioned indirect cost. It is built up as follows. Activity production cost: This cost is the sum of direct cost and its apportioned indirect cost. It is build up as follows. Cost Elements Amount 1. Direct material costs 2. Direct labour costs 3. Direct equipment and other expenses C 4. Direct costs (A + B + C) 5. Indirect costs 6. Production cost (D + E) A B D E F
Activity contract value: It is the contract value of the work done. It is the amount, which the client has agreed to pay for the satisfactorily completed works,
Network Elements
The two basic elements used in a network are activity and event. In addition, where necessary, many activities are introduced to maintain logic. Activity A project can be broken down into various operations and processes necessary its completion. Each of these operations or processes, which consume time and possibly, sources, is called an activity. Acquiring land, fixing steel, collecting materials, building a ill, constructing a roof and curing the concrete are examples of some of the common activities in a building construction project. The activities are represented by arrows pointing in the forward direction. The tail of the row
depicts the commencement of an activity and the arrowhead, its termination. The various ways by which the arrow of an activity 'A' can be drawn are: A 2 A 2 A 2
A 2 B 2
A 2
Notes: 1, The description of an activity is written above the arrow and its duration in the middle underneath. An activity involving excavation, and needing two units of time for its completion, would be shown as: Excavation 2 2. The length of the arrow is not drawn to scale. As far as possible, the arrow should be sufficiently long so that the description of the activity could be written over it. 3. Arrows are neither curved nor are they drawn in reverse direction.
1
G D 1 H F 2 E 3
A 2 C 2
3
The network logic shows that; activities A, B and C start at the same time; D follows the completion of A and B: E starts after C and D are completed; and, F follows C. The project over when E and F are completed. The points to note are;
(a) The activities A and 3 are concurrent (see Figs 4.2 and 4.3). To enable their description by event numbers, the dummy activity 'G' has been used.
A G B
1 2
Part of Network Showing that F Follows C, and E Starts after completion of C and D. The Dummy Activity H Provides The Logic Link.
D 1 H C 2 E 3 F 2
4 3
It is emphasized that the network should be drawn after the construction methodology is finalized. Accordingly, one should focus on the procedure of modeling and analysis network illustrated in the following paragraphs, rather than debate the method of construction.
define the scope of the network by fixing start and end events, stating suitable assumptions and laying own constraints.
(a) Start and end events: these define the extent of the network. The contract period of a contracted work commences from the time of handing over of site to the contractor; this can be taken as the start event. The clearance of site after completion of work is generally the last activity of a contract; its completion becomes the end event. For the major multi-project networks, there may be more than one start and end event.
(b) Assumptions: these aim at reducing the size of the network by omitting unnecessary details. Suitable assumptions can also be made about the 'unpredictable'. (c) Constraints: these are the restrictions and limitations imposed by the management on the method of execution, such as priorities of the work and availability of resources
Determining Activities
The various stages in the execution of a project can easily be visualized by breaking down the work into major tasks or work packages. Each one of these can further be split into sub tasks and these tasks can be further sub-divided, this process continues till the desired level of activities is reached.
activities. c. The new activities should be incorporated, if visualized during the preparation of logic diagrams. d. Logic of all the activities should be verified for its correctness.
Numbering of Events
It is the last operation in the modeling of the network.
of the Latest Event Times, identification of the critical events and critical activities, (having zero float) and, finally, evaluation of the project duration by summing up the duration of critical activities along the critical path connecting the start and the end events.
Preceding Activity
Nil 2 3 143 154 2 5 Nil 4 6 Nil 5 7 Nil 6 8 Nil 7 9 Nil 8 10 Nil 9 11 Nil 10 12 Nil 11 13 Nil 12 14 Nil 13 15 Nil 14 16 Nil
The above chart shows the sequence of the various work activities that encompasses the project in totality.
given the primary focal 23rd Janof constructionFeb 07 9th the 07 of the point 07 5th Feb 07 24th so that Feb rest
8th Feb 07 7th Mar 07 12th Feb 07 11th Mar 07 8th Mar 07 21st Mar 07 12th Mar 07 25th Mar 07 7th Apr 07 5th May 07 11th Apr 07 8th May 07
22nd 7. Supply chain management & HR management Marco-ordinate26tha mannerApr 07 the to 07 4th Apr 07 in Mar 07 8th so that
13 Steelwork for Gallery G-3 production process 14 Concreting for Gallery G-2
periods have as such been assumed but lags between the 16th Jul 07can be used for the 13th Jun 07 9th Jul 07 13th Jul 07 phases
19 Aluminum & Steel Fabrication Gallery G-2 22nd Aug 07 18th Sep 07 5th Sept 07 26th Sept 07 20 Aluminum & Steel Fabrication Gallery G-1 22nd Aug 07 18th Sep 07 5th Sept 07 26th Sept 07 21 Aluminum & Steel Bibliography:in Fabrication Gallery G-3 22nd Aug 07 18th Sep 07 5th Sept 07 26th Sept 07 22 Electrical works Gallery G-2 23 Electrical works in Gallery G-1 24 Electrical works in Gallery G-3 25 PVC works in Gallery G-2 26 PVC works in Gallery G-1
26th Sep 07 6th Nov 07 1st Nov 07 19th Dec 07 26th Sep 07 6th Nov 07 1st Nov 07 19th Dec 07 26th Sep 07 6th Nov 07 1st Nov 07 19th Dec 07
2. Construction Project Management by Lt Col K.K.Chitkara Dec 07 15th Jan 08 14th Nov 07 27th Nov 07 26th
14th Nov 07 27th Nov 07 26th Dec 07 15th Jan 08 14th Nov 07 27th Nov 07 26th Dec 07 15th Jan 08 1st Jan 08 31st Jan 08 16th Jan 08 16th Feb 08 1st Feb 08 3rd Mar 08 17th Feb 08 17th Mar 08
Index1. EST-Early Start Time. 2. EFT-Early Finishing Time. 3. LST-Late Start Time/ LFT-Late Finish Time.
Conclusions:
1. The data that has been used in the project planning & sequencing has been taken from earlier projects or assumed as per the situation. 2. There will be variances in the planning & execution since the ground situation & the planning assumptions have certain conflicts. 3. The variances are to be carefully monitored during the project execution & corrected. 4. There have been lag periods provided to take care of contingencies that are bound to arise like stoppage of work due to rains, labor problems etc. 5. Foundations have been planned in a way to complete it before the monsoons so that when the monsoons arrive it will be indoor work mainly & will not hamper work schedules much.