Stimating: B D A - M 2005
Stimating: B D A - M 2005
ESTIMATING
Introduction
In accordance with the requirements of the State Contract Act, the State Highway Engineer
must prepare full, complete, and accurate plans, specifications and estimates of cost before
entering into any contract. The estimate, known as the “Engineers Estimate”, lists the total
quantity and estimated price for each item, and is used as a basis for requesting authority to
advertise a project. After bids are received, the Engineer’s Estimate is used as a basis for
determining if the bid estimates are reasonable.
The Bridge Cost Estimates Branch provides the item costs for the Engineers Estimate for all
bridge and highway related structures. This cost estimate data, along with the special provisions
and contract plans, make up the Structure’s portion of the PS&E package.
General
Revised Estimates
When any changes such as quantity, cost, or scope of work are made it is the responsibility of
the Design Branch Leader and Project Engineer to advise all interested parties as successive
estimates are made during the development of a project.
ESTIMATING 11-1
BRIDGE DESIGN AIDS • MARCH 2005
Quantity Calculations
Quantity calculations are to be submitted to the Bridge Cost Estimates Branch along with
the Estimate Summary sheets. Calculations for Marginal “Blue Sheet” Estimates are
retained in Cost Estimates Branch until the contract is awarded, at which time they are
forwarded to the Resident Engineer’s Pending File for the Structure Representative’s use
during the course of construction.
Escalation Factor
Structure estimates are prepared on the basis of prices which are valid on the day the
estimate is made. As part of their procedure in developing their planning program, the
Districts periodically apply an escalation factor according to the cost index to these estimates
as necessary to cover inflation.
Mobilization Factor
Structure estimates generally include an item for mobilization. The value of this item is
estimated at 10% of the total cost of bid items. If a particular kind or size of a project does
not require a separate item for mobilization, the unit price for one or more of the major
items of work will be inflated to cover the contractors cost for mobilization.
Contingency Factors
A contingency factor is added to all estimates to cover the costs of unforeseen design
changes and the uncertainty of early quantity estimates. Contingency factors are shown
below:
Planning Estimates 25% Contingency
General Plan Estimates 20% Contingency
Marginal Estimate – Final PS&E 5% Contingency
Stage Construction
It is sometimes necessary to build a bridge in stages. The most common case is replacing
a bridge on existing alignment. This will increase the cost about 25% and the construction
time about 75%. The plans must show the width of each stage and indicate how traffic is
to be handled during each stage of construction.
11-2 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
Traffic Control
This item of work is defined and estimated by the Districts. However, it is important that the
bridge designer understands how traffic will affect the work and relay this information to Cost
Estimates either verbally or by notes on the plans or estimate. At the Plans and Quanties (P&Q)
stage of project delivery, all traffic considerations shall be included in the memo to specifications
engineer/estimator. Usual situations are “Work 9 AM – 3 PM only” or “All work at night or on
weekends.” This and other items concerning work in traffic should be discussed with the District
Project Engineer at an early stage. More expensive types of work that can be done quickly
without traffic control may be justified by the savings in traffic control costs. Design shall submit
lane closure charts when available to cost estimates.
Working Days
The Cost Estimates Branch determines the number of working days necessary to construct the
bridge portion of the contract work for PS&E. Design shall submit information regarding
restrictions and constraints to cost estimates. At the District’s request, working days will be
provided for Advanced Planning and General Plan stages.
Design Branch Leaders are responsible for assuring that the cost record and the Status agree.
Cost changes that are a result of price changes made by Cost Estimates are also to be recorded.
ESTIMATING 11-3
BRIDGE DESIGN AIDS • MARCH 2005
11-4 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
Note: See “Sources of Quantities for Standard Details” shown in SECTION 11.
ESTIMATING 11-5
BRIDGE DESIGN AIDS • MARCH 2005
Level 1 1 /2 : 1 2:1
H Height Height Height
Excav Backfill Excav Backfill Excav Backfill
at Face at Face at Face
3 3 3 3
mm mm m /m m /m mm m /m m /m mm m3/m m3/m
1200 1000 1.60 0.84 1500 2.43 1.17 1200 2.05 1.09
1800 1000 1.90 1.56 1500 2.98 2.04 1200 2.50 1.92
2400 1000 2.20 2.51 1500 3.55 3.16 1300 3.11 3.00
3000 1000 2.50 3.68 1600 4.31 4.53 140 3.78 4.32
3600 1000 2.80 4.98 1700 5.14 6.06 1500 4.51 5.79
4200 1100 3.30 6.34 1800 5.93 7.61 1600 5.23 7.29
4800 1100 3.63 8.15 1900 6.89 9.69 1700 6.07 9.31
5500 1200 4.19 10.37 2000 7.91 12.21 1800 6.98 11.75
6100 1200 4.53 12.65 2100 8.99 14.82 1900 7.94 14.28
6700 1300 5.29 15.36 2200 10.42 17.97 2000 9.21 17.32
7300 1400 6.10 17.73 2300 11.80 20.73 2100 10.45 19.98
7900 1500 6.99 20.05 2400 13.28 23.46 2200 11.79 22.61
8500 1600 7.94 22.84 2500 14.85 26.69 2300 13.21 25.73
9100 1700 9.20 26.60 2600 17.27 31.29 2400 15.34 30.12
9700 1800 10.74 30.43 2700 20.03 36.03 2500 17.81 34.63
10300 1900 11.91 33.77 2900 22.37 39.93 2600 19.54 38.39
10900 2000 13.14 37.28 3000 24.39 44.03 2700 21.35 42.34
300 1
300 r 2:
:1 o
1 /2
1
Height
Level
Height at at face
face of of wall
1
r 2:
wall
1/2
:1 o
1
Level 600
600 600
300 300 300 300
11-6 ESTIMATING
Preliminary Quantity Survey
Girders, Deck and Disphragms Only
( Calculate cap quantity separately )
0.65
0.60 Note:
Bent caps and Hinges are not 2.25 m
included in these quantities
Stem width = 355 mm
0.55 Girder Spacing = 2.0 m to 2.5 m
2.00 m
0.50
1.75 m
0.45 W
D
1.50 m
0.40
m3 per m2 of Deck
1.25m
0.25
10 15 20 25 30 35 40
Span Length – meters
ESTIMATING
Continuous Tee-Beam Superstructure Concrete
11-7
BRIDGE DESIGN AIDS • MARCH 2005
11-8
Preliminary Quantity Survey
Girders, Deck and Diaphragms Only
( Calculate cap quantity separately )
ESTIMATING
0.60
0.58 2.25 m
Note: Low Skew
Bent caps and Hinges are not
0.56 included in these quantities
Stem width = 200 mm 2.00 m
0.54 Girder Spacing = 2.0 m to 2.5 m 1.75 m
0.52
1.50 m
W
0.50 D
0.48
1.25m
m3 per m2 of Deck
0.46
1.00 m Depth
0.44
Use for Planning and
General Plan Estimates only
0.42 D= Bridge
W= Deck width
0.40
10 15 20 25 30 35 40 45 50
0.80
0.75 Note:
Use for Low Skew Structures,
0.70 d/s = 0.035-0.045
0.65
0.60
Simple Span
m3 per m2 of Deck
0.55
Use for Planning and
0.50 General Plan Estimates only
0.45 Continuous
0.40
10 15 20 25 30 35 40 45 50 55 60 65 70 75 80
Span Length – meters
ESTIMATING
CIP / PS Box Girder Superstructure Concrete
11-9
BRIDGE DESIGN AIDS • MARCH 2005
11-10
Preliminary Quantity Survey
Girders, Deck and Diaphragms Only
( Calculate cap quantity separately )
200
ESTIMATING
190 Note:
Stem width = 355 mm
Girder spacing = 2.0 to 2.5 m
1.00 m Depth
180
D/
S=
D/
S = 0.06
7
1.25 m Depth
170 0.0
D/ 71
S=
0.0
D/S
74 1.50 m Depth
=0
160 .08
0 1.75 m Depth
2.00 m Depth
150
210
D/S = 0.055
D/S = 0.059
190 Note:
Use for Planning and Stem width = 355 mm
ESTIMATING
11-11
BRIDGE DESIGN AIDS • MARCH 2005
11-12
Preliminary Quantity Survey
ESTIMATING
140
Note:
Apply to Normal and Low skew structure
130
Barrier Railing quantities not included
120
D/S = 0.035 - 0.045
110
100
Use for Planning and
90
20 30 40 50 60 70 80 90 100
30 Pa
M
=42
Prestressing Steel - Kilograms per square meter (deck area)
f'c
25
Pa
5M
=3
20 f'c = 28MPa f'c
15
5
= 0.03
d/s
0
10 0 .04
d/s =
50
= 0.0
5 d/s
Note: Use for planning and
general plan estimates only.
0
0 10 20 30 40 50 60 70 80 90
ESTIMATING 11-13
BRIDGE DESIGN AIDS • MARCH 2005
' L L
45
2 Span Box Girder
w/ equal spans
d/s= .030 to .050
40
u= 0.15 f 's = 1860 MPa
35
2MPa
Prestressing Steel - Kilograms per square meter (deck area)
f 'c =4
30
5MPa
f 'c =3 f'c = 28MPa
25
.0 30
20
s =0
d/
35
15 0.0
s=
d/
.0 40
10
=0
d/
s 50
0.0
.0 45 s=
=0 d/
5 s
d/
Note: Use for planning and
general plan estimates only.
0
0 20 40 60 80 100 120
11-14 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
45
3 /4 L L 3 /4 L
40
3 Span Box Girder
w/ 3 /4 L end spans
d/s= .030 to .050
35
Prestressing Steel - Kilograms per square meter (deck area)
30 f'c =42MPa
25
Pa
f 'c =35M
20
15 0.030
d/s =
.0 35
s =0
10 d/
.0 40
s =0 50
d/ .0
5 =0
d/s
Note: Use for planning and
general plan estimates only.
0
0 20 40 60 80 100 120
ESTIMATING 11-15
BRIDGE DESIGN AIDS • MARCH 2005
L L L
45
3 Span Box Girder
w/ equal spans
d/s= .030 to .050
40 u= 0.15 f ' s =1860 MPa
Prestressing Steel - Kilograms per square meter (deck area)
35
f'c = 42MPa
30
f'c = 35MPa
25
30
= 0.0 f'c = 28MPa
20 d/s
15 35
.0
s =0
d/ 0
0 .04 .050
10 s= =0
d/ d/s
5
0 .04
5 d/ s=
Note: Use for planning and
general plan estimates only.
0 20 40 60 80 100 120
11-16 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
3 /4 L L L 3 /4 L
45
35 f'c = 35MPa
f'c = 28MPa
30
25
30
0.0
20
s=
d/
15
5
0 .03
d/s =
10 0
0 .04 50
d /s = 0.0
s=
5 d/
5
0 .04
d/s= Note: Use for planning and
general plan estimates only.
0 20 40 60 80 100 120
ESTIMATING 11-17
BRIDGE DESIGN AIDS • MARCH 2005
45
4 Span Box Girder
w/ equal spans
d/s= .030 to .050
40 u= 0.15 f's =1860 MPa
Prestressing Steel - Kilograms per square meter (deck area)
35
f'c = 35MPa
30
25
30
0.0
s=
d/
20 f'c = 28MPa
15
.0 35
s =0 50
d/ 0.0
40
10 .0 s=
=0 d/
d/s
.0 45
5 =0 Note: Use for planning and
d/s general plan estimates only.
0 20 40 60 80 100 120
11-18 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
.05
225 Loading: HS 20-44 + 35 psf allowance
for future wearing surface.
Kilograms of Structural Steel per Square Foot (Deck Area)
.05
200 Concrete: fc = 9 MPa
nd ly
150
ning a ate on
P lan stim
for an E
Use eral Pl
.06
Gen
.06
125
.07
100 .07
Note:
75 Wts. of diaphragms, stiffeners, shear
connectors and wind bracing approximated.
Add 15% if Steel Bent Caps are used.
50
10 15 20 25 30 35 40 45 50
ESTIMATING 11-19
BRIDGE DESIGN AIDS • MARCH 2005
ks
Note:
rac
2t
ks
Quantities are for all
rac
2-
structural steel including
0-
8
E6
deck plates.
Use for all deck types
(steel, wood or concrete)
ck k
6
tra trac
-1
Thru Girders
2
E7
-1
0
E6
ck
ra
rt 4
- pe
e rs
rd
Gi
c k PLL .
De nd nly
ing a ates o
ann tim 2
for Pl lan Es
Use eral P
Gen
beams-per
Deck rolled beams - pertrack
track
0
25 50 75 100 125 150 175
Span Length – Feet
11-20 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
Marginal Estimates
The Marginal Estimate differs from the Advanced Planning and General Plan Estimates in that
it is based on quantity calculations prepared from checked design plans. This marginal estimate
is done at P&Q stage. Marginal Estimates for bridge items are segregated as follows:
A Marginal Estimate Form should be filled out for each structure, retaining wall, or sound wall
with separate bridge number. Whenever there are identical parallel structures or where more
than one structure is shown on a General Plan, only one Marginal Estimate Form should be filled
out.
ESTIMATING 11-21
BRIDGE DESIGN AIDS • MARCH 2005
item. When calculations are complete, the two shall compare results and make necessary
corrections according to the following percent error allowance:
Barrier, piles, precast units, or any item paid as EACH ............. Zero % (Exact)
Concrete, bar reinforcing steel, and structural steel quantities ....................... 3%
All others ........................................................................................................ 5%
The close review of the plans required in the process of quantity take-off frequently results in the
discovery of errors or omissions. These must be brought to the designer's attention.
Tot. lengths
Weight per meter 0.994 1.552 2.235 3.042 3.973 5.06 6.404 7.907 11.38 20.24
11-22 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
For the more complicated structures or portions of structures, it is suggested that the estimator
and checker code (by number or letter) the reinforcing bars on the estimating prints prior to
quantity take-off. This will facilitate final checking of quantities and reduce the possibility of
omissions. An example is as follows:
A #13 @ 460mm
C #13 @ 460mm
ESTIMATING 11-23
BRIDGE DESIGN AIDS • MARCH 2005
The first character in the field identifies the major material used or the construction method:
C – Concrete
S – Steel
T – Timber
M – Masonry
P – P/S, P/C
I – P/S, CIP
The second and third characters describe the physical configuration of the main span:
BG – Box Girder IG – “I” girder
SL – Slab IU – Inverted U
SS – Seal Slab UG – “U” girder
DU – Deck Units WG – Welded girder
TG – “T” girder RB – Rolled beam
DT – Double T TD – Truss deck
IT – Inverted T TC – Truss Cantilever
BU – Bulb T
TB – Truss Bascule BW – Bin wall
TL – Truss lift PA – Pipe, arch
SU – Suspension P1 – Single pipe
AR – Arch P2 – Double pipe
LS – Log stringer B1 – Single box
The second and third characters (continued)
T1 – Type 1 wall B2 – Double box
T2 – Type 2 wall B3 – Triple box
T3 – Type 3 wall B4 – Quadruple box
T4 – Type 4 wall B5 – Quintuple box
T5 – Type 5 wall XX – None of the above
11-24 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
ESTIMATING 11-25
BRIDGE DESIGN AIDS • MARCH 2005
Bottom of girder
11-26 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
ESTIMATING 11-27
BRIDGE DESIGN AIDS • MARCH 2005
• PILE SUMMARY
DS - D0015
• CONCRETE SUMMARY
DS - D0050
11-28 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
CONCRETE REBAR
DESIGN H
(m3/m) (kg/m)
1200 1.17 63
1800 1.35 73
2400 1.84 103
3000 2.41 126
3600 3.41 151
Note: Use for Advanced Plan and General Plan studies only.
ESTIMATING 11-29
BRIDGE DESIGN AIDS • MARCH 2005
Note: Use for Advanced Plan and General Plan studies only.
11-30 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
Note: Use for Advanced Plan and General Plan studies only.
ESTIMATING 11-31
BRIDGE DESIGN AIDS • MARCH 2005
4
m .1m
5.5 = 6
m
m
4.3
4.9
3.5 s=
3.7
s CL Abut.
“S”
s=
s=
s=
3
"Y" [M]
2.5 1m
2
“Y”
1.5
0.5
M ³ OF CONCRETE
3.6
3.4 CL Abut.
“S”
s = 3.7m
m
s = 4.3m
.5m
m
s = 4.9
"Y" [M]
6.1
s=5
3.2
s=
3 1m
225
2.8
5
225
225
25
#16 @ 22
@2
#22 @
“Y”
#19 @
2.6
#25
#29
2.4
Kg of Reinforcement
11-32 ESTIMATING
Precast Prestressed Concrete Slab Quantities
915 mm 1220 mm
Width Girder No. 13 Mass 13 Mass of Vol of Width Girder No. 13 Mass 13 Mass of Vol of
Typical Length Pf mm Strand Bar Reinf Conc Typical Length Pf mm Strand Bar Reinf Conc
Sections mm Kn Strands Kg Kg m3 Sections mm Kn Strands Kg Kg m3
.91m 1.22m
6096 917 3353 52.16 196.86 1.60 6096 1224 4267 66.23 265.36 2.16
.3m .3m
6401 1006 3658 59.88 204.57 1.68 6401 1339 4572 74.84 275.34 2.27
SI .91 SI 1.22
6706 659 2438 41.73 185.52 1.90 6706 863 3048 52.16 249.48 2.52
7010 721 2743 48.99 190.97 1.98 7010 935 3353 59.88 256.74 2.64
7315 783 2743 51.26 196.41 2.06 7315 1032 3658 68.04 264.00 2.75
.91m
7620 846 3048 59.42 201.85 2.16 1.22m
7620 1117 3658 71.22 271.71 2.87
.38m
7925 912 3353 67.59 207.30 2.24 7925 1202 3962 79.83 278.96 2.98
7" .38m 7"
8230 975 3353 70.31 212.74 2.32 8230 1286 4267 89.36 286.22 3.10
SII .91 SII 1.22
8534 1041 3658 79.38 218.18 2.41 8534 1375 4572 99.34 293.48 3.21
8839 1113 3962 89.36 223.62 2.49 8839 1464 4877 109.77 301.19 3.33
9144 1175 4267 99.34 229.07 2.58 9144 1553 5182 120.66 308.45 3.44
9449 1250 4572 110.22 234.51 2.67 9449 1647 5486 132.00 314.34 3.55
9754 1317 4572 113.40 239.95 2.75 9754 1740 6096 151.50 322.96 3.66
10058 1010 3353 86.18 258.10 3.20 10058 1335 4572 117.03 347.91 4.23
10363 1068 3658 96.62 264.00 3.30 10363 1397 4877 128.82 355.62 4.36
10668 1121 3658 99.34 269.44 3.39 10668 1473 4877 132.45 363.33 4.48
.91m 10973 1188 3962 110.68 275.34 3.49 1.22m 10973 1553 5182 144.70 371.04 4.61
.46m 9" .46m
11278 1250 4267 122.47 281.23 3.59 9" 11278 1633 5486 157.40 378.76 4.73
SII .91 11582 1308 4267 126.10 286.68 3.69 SII 1.22 11582 1713 5791 171.01 386.47 4.86
11887 1384 4572 138.35 292.57 3.78 11887 1811 6096 184.62 394.18 4.99
12192 1464 4877 151.50 298.02 3.88 12192 1918 6401 198.68 401.89 5.12
12497 1544 5182 165.11 303.91 3.98 12497 2020 6706 213.19 409.60 5.24
ESTIMATING
12802 1215 3962 129.28 319.79 4.14 12802 1633 5486 178.72 430.92 5.70
13106 1282 4267 142.43 325.68 4.24 13106 1718 5791 193.23 439.08 5.83
.91m 13411 1344 4572 156.04 332.04 4.34 1.22m 13411 1807 6096 208.20 447.25 5.97
13716 1415 4877 170.55 337.93 4.43 13716 1896 6401 223.62 455.41 6.10
.46m 12" .53m 12" 9"
14021 1477 4877 174.18 343.83 4.53 14021 1985 6706 239.50 463.13 6.24
SIV .91 SIV 1.22
14326 1540 5182 189.15 349.73 4.63 14326 2069 7010 255.83 471.29 6.38
14630 1606 5483 204.57 355.62 4.73 14630 2172 7315 272.61 479.46 6.51
11-33
BRIDGE DESIGN AIDS • MARCH 2005
11-34
Precast Prestressed Concrete Slab Quantities (cont.)
915 mm 1220 mm
Width Girder No. 13 Mass 13 Mass of Vol of Width Girder No. 13 Mass 13 Mass of Vol of
Typical Length Pf mm Strand Bar Reinf Conc Typical Length Pf mm Strand Bar Reinf Conc
Sections mm Kn Strands Kg Kg m3 Sections mm Kn Strands Kg Kg m3
ESTIMATING
9144 1291 4267 100.25 193.23 2.51 9144 1335 4267 99.79 196.86 2.85
9449 1357 4267 103.42 198.68 2.59 9449 1415 4267 103.42 202.31 2.94
2.44m 9754 1428 4267 106.60 204.12 2.68 2.44m 9754 1495 4267 106.60 207.75 3.04
D
10058 1504 4267 110.22 209.56 2.76 D
10058 1571 4877 125.65 213.19 3.13
Girder Depth 10363 1575 4877 129.73 215.01 2.84 Girder Depth 10363 1651 4877 129.73 218.64 3.23
D = .46m
10668 1647 4877 133.36 220.45 2.93 D = .46m
10668 1727 4877 133.36 224.08 3.33
10973 1638 4877 136.99 225.89 3.01 10973 1807 5486 154.22 229.52 3.43
11278 1789 5486 158.76 231.34 3.10 11278 1882 5486 158.76 234.96 3.52
10668 1117 3658 99.79 238.59 3.36 10668 1193 3658 100.25 241.32 3.95
10973 1193 3658 102.51 244.49 3.46 10973 1273 3658 102.97 247.21 4.06
11278 1268 3658 105.69 250.39 3.56 11278 1353 4267 123.38 253.11 4.17
11582 1348 4267 126.55 256.28 3.66 11582 1415 4267 126.55 259.01 4.29
11887 1424 4267 129.73 262.18 3.75 11887 1495 4267 130.18 264.90 4.40
12192 1504 4267 133.36 268.08 3.85 12192 1580 4877 152.41 270.80 4.52
12497 1580 4877 156.04 273.97 3.95 12497 1664 4877 156.04 276.70 4.63
D = .61m 12802 1660 4877 160.12 279.87 4.04 D = .61m 12802 1749 5486 180.08 282.59 4.75
13106 1736 5486 184.16 285.77 4.14 13106 1833 5486 184.16 288.49 4.86
13411 1816 5486 18824 291.66 4.24 134.11 1918 5486 188.70 294.39 4.98
13716 1891 5486 192.78 297.56 4.34 13716 2003 6096 214.55 300.28 5.09
13411 1313 4267 146.51 317.52 5.04 13411 1375 4267 146.97 320.24 5.87
13716 1380 4267 149.69 323.87 5.15 13716 1446 4267 150.14 326.59 6.01
14021 1566 4267 153.32 330.22 5.27 140.21 1517 4877 166.92 332.94 6.15
14326 1513 4267 156.49 336.57 5.38 14326 1589 4877 179.17 339.29 6.29
14630 1580 4877 182.80 342.92 5.50 14630 1660 4877 182.80 345.64 6.42
14935 1647 4877 186.43 349.27 5.62 149.35 1731 5486 210.02 351.99 6.55
15240 1713 4877 190.51 355.62 5.73 15240 1802 5486 214.55 358.34 6.69
15545 1780 5486 218.64 361.97 5.85 15545 1873 5486 218.64 364.69 6.82
15850 1847 5486 222.72 368.32 5.96 15850 1945 6096 247.67 371.04 6.96
16154 1914 5486 227.25 374.67 6.08 16154 2016 6096 252.66 377.40 7.09
16459 1980 6096 257.19 381.02 6.19 16459 2087 6096 257.19 383.75 7.23
D = .81m 16764 2047 60.96 261.73 387.37 6.32 D = .81m 16764 2158 6706 288.04 390.10 7.36
17069 2114 6096 266.72 393.72 6.44 17069 2229 6706 293.48 396.45 7.50
17374 2181 6706 298.47 400.08 6.54 17374 2301 6706 298.47 402.80 7.62
17678 2247 6706 303.91 406.43 6.66 17678 2372 7315 331.58 409.15 7.77
17983 2314 6706 308.90 412.78 6.77 17983 2443 7315 337.02 415.50 7.89
18288 2381 7315 342.92 419.13 6.89 18288 2514 7315 342.92 421.85 8.04
18593 2448 7315 348.82 425.48 7.00 18593 2585 7925 377.85 428.20 8.16
18898 2514 7315 354.26 431.83 7.12 18898 2657 7925 383.75 434.55 8.30
19202 2581 7925 390.10 438.18 7.23 19202 2728 7925 390.10 440.90 8.43
BRIDGE DESIGN AIDS • MARCH 2005
BRIDGE DESIGN AIDS • MARCH 2005
Steel:
Reinforcing Bar Weights BDA 11-37
Piling Patterns – Retaining Walls BDD Section 6
Piling Patterns – Cantilever Abutment BDD Section 6
Railroad Track, Ballast, etc. BDD Section 12
ESTIMATING 11-35
BRIDGE DESIGN AIDS • MARCH 2005
11-36 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
Estimate "A"
Estimate
"D
Estimate "A"
"
"A"
90 Standard /90 Stirrup and Tie 180 Standard 135 Tie Hook
ESTIMATING 11-37
BRIDGE DESIGN AIDS • MARCH 2005
11-38 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
Listed by Section
ESTIMATING 11-39
BRIDGE DESIGN AIDS • MARCH 2005
11-40 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
ESTIMATING 11-41
BRIDGE DESIGN AIDS • MARCH 2005
11-42 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
ESTIMATING 11-43
BRIDGE DESIGN AIDS • MARCH 2005
11-44 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
ESTIMATING 11-45
BRIDGE DESIGN AIDS • MARCH 2005
6. Decks and Approach Slabs: In Environmental Area III, and some other corrosive environments,
the deck and approach slab reinforcing steel is to be epoxy-coated.
Decks 300 mm thick and less:
Epoxy-coat the entire deck reinforcing.
Decks greater than 300 mm thick:
Concrete
11-46 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
ESTIMATING 11-47
BRIDGE DESIGN AIDS • MARCH 2005
Minor Concrete
1. Estimate in cubic meters.
2. This pay item will include necessary earthwork and reinforcing steel.
11-48 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
Slope Paving
1. Estimate the cubic meters of concrete. This pay item will include necessary earthwork and
reinforcing steel.
2. Estimate permeable material in cubic meters.
3. Estimate drainage inlets by each.
4. Estimate drain pipes in linear meters for each size and type.
5. Do not deduct for volumes occupied by reinforcing steel.
ESTIMATING 11-49
BRIDGE DESIGN AIDS • MARCH 2005
11-50 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
ESTIMATING 11-51
BRIDGE DESIGN AIDS • MARCH 2005
Earthwork
11-52 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
Case 2. If there is an item for Remove Concrete, either by M³ or LS, deduct the volume
of concrete only from the structure excavation volume.
Case 3. If there is an item for Bridge Removal, deduct the volume of concrete and related
excavation from the structure excavation volume.
If it would clarify the situation in either Case 2 or Case 3, draw a separate pay limit diagram on
the plans.
ESTIMATING 11-53
BRIDGE DESIGN AIDS • MARCH 2005
11-54 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
Roadway excavation
A
Grading plane
Structure excavation
600 mm min below girder
A 300 mm
300 mm
Grading plane
Structure backfill
Grading plane
Structure excavation
Improved channel
300mm
300mm
ESTIMATING 11-55
BRIDGE DESIGN AIDS • MARCH 2005
Joint Seals
Metal
11-56 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
Furnish Piling
1. Paid by the unit meters from specified tip to cut-off elevation. Battered piles are measured
as the total length of pile along the pile centerline.
2. A separate pay item is required for each type or class of piling.
Drive Piles
1. Paid by the unit each, for each type or class of pile.
ESTIMATING 11-57
BRIDGE DESIGN AIDS • MARCH 2005
11-58 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
Non-Standard Piling
Micropiles
1. Paid by the unit each.
2. Includes furnishing and installing the micropile (including casings, grout, reinforcement, and
anchorages).
ESTIMATING 11-59
BRIDGE DESIGN AIDS • MARCH 2005
CIP
CIP Column
Column
cut-off
elevation
cut-off
elevation
Limits of payment for furnish piling
Driven
Piling or
CISS
Concrete
Steel
Piling
Piling
Notes
1. The extension may or may not have the same reinforcing as the pile.
2. Pay limits shown here should also be included on the plans.
3. Calculate pile length to specified tip elevation.
4. Limits of embedment into soffit to be determined by the designer and shown on the plans.
5. CISS Pile Extensions may need to be cleaned and painted.
* Includes CISS concrete piles
11-60 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
Case 1 Case 2
Soffit
(Typ)
See
note 4
CIP
Column
cut-off
Limits of payment for CIDH concrete piling
cut-off elevation
elevation
Limits of payment for CIDH concrete piling
Notes
1. The extension may or may not have the same reinforcing as the pile.
2. Pay limits shown here should also be included on the plans.
3. Estimate pile length from cut-off elevation to specified tip elevation.
4. Limits of embedment into soffit to be determined by the designer and shown on the plans.
ESTIMATING 11-61
BRIDGE DESIGN AIDS • MARCH 2005
X mm
Specified Tip
Elevation for
Permanent
Steel Casing
Y mm**
11-62 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
W mm*
SOIL
See Note 1
ROCK
Y mm**
Notes
1. Specified Tip Elevation for Permanent Steel Casing and W mm CIDH concrete piling,
and cut-off elevation for Y mm CIDH concrete piling (Rock Socket).
* For diameters 1500 mm or less, the diameter of the CIDH concrete piling will be called
the same as the outside diameter of the casing (W=X). For diameter greater than 1500 mm,
the CIDH concrete piling diameter is equal to the inside diameter of the casting.
* CIDH Concrete Piling (Rock Socket) must be a standard diameter.
ESTIMATING 11-63
BRIDGE DESIGN AIDS • MARCH 2005
cut-off elevation
Z mm*
* Thickness and outside diameter should be shown in pile data table (see Memo to Designers 3-1).
11-64 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
Miscellaneous Pipes
1. Paid by the unit meter, for each size and type. Indicate thickness for steel pipes, and class for
pressure rating for asbestos and PVC pipes.
ESTIMATING 11-65
BRIDGE DESIGN AIDS MARCH 2005
Precast Girders
Prestressing Steel
3 × /HQJWK ×
I
= NJ
3 × /HQJWK ×
MDFN
= NJ
Pf or Pjack in KN
Length in meters
For RR loading add 7.5%
11-66 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
Concrete Barriers
1. Calculate quantities of each type separately. Paid by meters. Payment includes the bar
reinforcing steel and all bar reinforcing that extends into the barrier. For Types such as 25B,
26A, 732B, 736B earthwork is included.
2. Drill and bond dowels for Type R rail replacement is included in the price per meter of barrier.
Metal Railing
1. These are usually steel railings such as tubular hand railing, chain link railing, or cable railing.
2. Calculate quantities for each type separately in meters. This includes anchor bolts or post
pockets.
Temporary Railing
1. Estimate by meters for locations shown on the plans or required for falsework openings. Type
K should be in 6.1 meters increments.
2. The total length for payment includes the lengths each time it is used at (or moved to) a new
location.
3. Include pay quantity for K-Rail in “Advanced Planning Estimates” only. District will include
quantities with District Items at PS&E.
Structural Steel
ESTIMATING 11-67
BRIDGE DESIGN AIDS • MARCH 2005
Clean and Paint (Structural Steel, Steel Piling, Sign Structure, etc...)
1. Estimate by kilograms of steel sections to be painted.
2. Paid by Lump Sum.
Walls
Closure Walls
1. Estimate by square meter.
2. Specify alternative(s) if all three are not allowed.
3. Architectural treatment for closure wall is included in the cost per square meter of wall.
11-68 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
Sound Walls
ESTIMATING QUANTITIES
C
C
1.2 m
max
A A
C C
A A A A
A
C C
E* C
B* B
B
E E* E
1.2 m max Over 1.2 m E
Pile Cap
Case 3 Case 4
If wall is both Case 3 and 4, use Case 4
If the sound wall is sitting on a retaining wall or concrete barrier, all the support items are typically paid for separately. If a
sound wall is sitting on anything else, everything is included in the square meter price of the sound wall. However, all
quantities are needed for cost estimating.
ESTIMATING 11-69
BRIDGE DESIGN AIDS • MARCH 2005
Miscellaneous
Architectural Treatment
1. Estimate by square meter of area for each type to be treated.
2. Architectural treatment for Mechanically Stabilized Earth walls (MSE walls) and closure
walls is included in square meter cost of wall.
Asphalt Concrete
1. Estimate by tonne. (2,250 kg per m³)
2. Use Type B for overlays on concrete bridge decks.
3. If the roadwork also has AC (Type B), contact the District Designer to see if they will include
the quantity in their estimate. If so, note this on the Marginal Estimate Form.
11-70 ESTIMATING
BRIDGE DESIGN AIDS • MARCH 2005
Core Concrete
1. Calculate length of hole to be cored in meters for each diameter size core.
Deck Seal
1. Estimate by square meter. Use distance between rails plus 127 mm above finished surface
at each rail face. This is for a membrane seal.
2. See also Quantity Take Off for Deck Rehabilitation.
3. Also need item for clean deck, in square meters, on deck rehabilitation projects.
PTFE Bearings
1. Paid by the unit EACH, for concrete structures.
2. Paid by the unit kilograms of structural steel, for steel structures.
3. Multiple discs in a bearing assembly count as a single unit.
Remove Concrete
1. Estimate in cubic meters. Concrete will be removed to a depth of one meter below finished
grade unless shown otherwise.
2. See also Structure Excavation.
ESTIMATING 11-71
BRIDGE DESIGN AIDS • MARCH 2005
Soil Nails
1. Paid by length in the unit meter.
Tieback Anchors
1. Paid by the unit EACH.
Timber
1. Paid by cubic meter. Use nominal sizes and do not deduct for bevels or daps.
2. Do not estimate hardware such as nails, lag bolts, washers, etc.
3. Estimate structural metal, such as shapes, castings, eyebars, etc., by the kilogram and report
separately.
4. Estimate treated and untreated separately.
5. Estimate timber catwalks by meters.
11-72 ESTIMATING
Cost Estimates Home
California Home
Caltrans > Division of Engineering Services > SDS & EE > Structure Office Engineer > Cost Estimates
Forms