Building Layout
Building Layout
Building Layout
150
Section 1
Preparing to Build
they will issue a building permit, Figure 6-1. A surveyor provides a survey of the site and locates stakes to indicate the boundaries, also called property lines. If there is a plot plan, it indi-
cates the location of the structure and distances to property lines on all sides. Surveyors should always locate the property lines. They should also draw the plot plan, if one is required.
Learning Objectives
After studying this chapter, you will be able to: Explain the operation of the builders level and level-transit. Explain the basic operation of a laser level system. Demonstrate proper setup, sighting, and leveling procedures. Measure and lay out angles using leveling equipment. Read the vernier scale. Use a plumb line.
Technical Vocabulary
Benchmark Builders level Building lines Building site Carpenters level Cut Datum Dumpy level Elevation Fill Grade Grade leveling Laser level Leveling rod Line of sight Lots Measuring tape Optical level Plumb Property line Station mark Steel tape Transit Vernier scale
Before construction of a foundation or slab for a building can begin, the carpenter must know where the structure will be located on the property. This requires a series of steps involving the use of measuring tapes and building layout instruments. The place where a building is to be constructed is called a building site. Often, these sites are in communities where there are streets and where small tracts of land are broken up into smaller parcels called lots. If the building site is a city lot, placing the building requires more steps. Most communities have strict requirementsbuildings must be set back a certain distance from the street and maintain minimum clearances from adjoining properties. The local code must be carefully checked for these requirements before layout begins.
Building site: The place where a building is to be constructed. Lots: Small tracts of land broken up into smaller parcels.
149
Chapter 6
Building Layout
151
152
Section 1
Preparing to Build
The work of an engineer or surveyor protects the owner and builder from costly errors in measurement.
carpenter will usually select one that is marked in feet, inches, and eighths of an inch. Surveyors, on the other hand, require a tape graduated in feet and decimal parts of a foot.
them with stakes. Building lines are the lines marking where the walls of the structure will be. These lines must conform to code requirements on distance of the structure from boundary lines of the property. Once the property lines are known and marked by the surveyor, the building lines can be found by measuring distances with a tape. See Figure 6-3. Be sure to observe proper setbacks and clearances. Carefully check the local code to ensure compliance. To start: 1. Locate the surveyors stakes marking the lot corners. Often, these are 2 2 wood stakes driven ush with the surface of the ground. A small nail driven in the top of the stake marks the exact corner of the property. 2. Measure the setback to locate the front building line. Use a tape to measure the distance. To be accurate, the tape measurement must be perpendicular to the building line. String a line from stake-to-stake as needed. 3. Locate and mark the setbacks on the other three sides of the lot. Building lines must always be within these boundaries.
A
1 2
Street
B
Figure 6-2. Measuring tape. ALong tapes for layout use are made in lengths of up to 300. BMeasuring tapes are made with different systems and graduations. 1. Metric. 2. Feet and decimal graduations. 3. Feet, inch, and eighthinch graduations. 4. Feet and inches with feet repeated at each inch mark. (The Stanley Co.; Keuffel & Esser)
10'
Steel tape: Tape that comes in lengths of 50 to 300. It is used for measurements and layouts involving long distances. Also called measuring tape. Measuring tape: Tape that comes in lengths of 50 to 300. It is used for measurements and layouts involving long distances. Also called steel tape.
Building lines: The lines marking where the walls of a structure will be located.
Figure 6-3. A simple rectangular structure can be laid out by taking measurements, using lot lines as reference points.
Chapter 6
Building Layout
153
154
Section 1
Preparing to Build
8'-0"
10'-0"
90
6'-0"
Figure 6-4. To check whether a corner is square, mark 6 along one building line and 8 on the intersecting building line. If the distance between the marks is 10, the corner is square.
If the building is small, such as a 24 garage, a carpenters level, line level, framing square, and rule are accurate enough for laying out and checking the building lines. But, as size increases, special leveling instruments are needed for greater accuracy and efciency.
edge, level, and square, then leveling instruments should be used. The optical device of these instruments operates on the basic principle that a line of sight is a straight line that does not dip, sag, or curve. Any point along a level line of sight will be at the same height as any other point. Through the use of these instruments, the line of sight replaces the chalk line, line level, and straightedge. The builders level, also called a dumpy level or optical level, is shown in Figure 6-5. It consists of an accurate spirit level and a telescope assembly attached to a circular base that swivels 360. Leveling screws are used to adjust the base after the instrument has been mounted on a tripod. The telescope is xed so that it does not move up or down, but it rotates on the base. This permits any angle in a horizontal plane to be laid out or measured. The transit is like the builders level in most respects, Figure 6-6. However, the telescope can be pivoted up and down 45 in each direction. Using this instrument, it is possible to accurately measure vertical angles. The transit is also used to determine if a wall is perfectly plumb (vertical) by sighting the vertical crosshair while pivoting the scope up and down. Its vertical movement also simplies the operation of aligning a row of stakes, especially when they vary in height. In use, both the builders level and transit are mounted on tripods, Figure 6-7. Some models,
Index vernier
like the one shown, have legs whose length can be independently adjusted. This feature makes the tripod easier to level on sloping ground. It also permits the legs to be shortened for easier handling and storing. When sighting over long distances, use a leveling rod. See Figure 6-8. It is a long rod marked off with numbered graduations. It allows differences in elevation between the position of the level and various positions where the rod is held to be easily read. The rod is especially useful for surveying. The person operating the level can make the readings or the target can be adjusted up and down to the line of sight and then the person holding the rod (rod holder) can make the reading.
Figure 6-6. A transit can be used to lay out or check both level and plumb lines. It can also be used to measure angles in either the horizontal or vertical planes. (David White)
Tripod head
Leg clamp
Leg
Lens
A
Eyepiece
Figure 6-8. Leveling rod with target. The target can be moved up or down to match the line of sight of the transit. (David White)
Tie strap
Carpenters level: Tool used for laying out and checking the building lines. Builders level: An optical device used by builders to determine grade levels and angles for laying out buildings on a site. Also called a dumpy level or an optical level. Transit: Optical leveling instrument commonly used for building layout. Line of sight: A straight line that does not dip, sag, or curve. Any point along a level line of sight is at the same height as any other point. Plumb: Exactly perpendicular or vertical; at a right angle to the horizon or oor.
Ground spike
Leveling screws
Figure 6-7. Tripod legs hinge at top and are adjustable for use on uneven terrain. (David White)
Leveling rod: A long rod marked off with numbered graduations that is used, along with a builders level or transit, to sight differences in elevation over long distances.
Figure 6-5. The builders level is used to sight level lines and lay out or measure horizontal lines. (David White)
Chapter 6
Building Layout
155
156
Section 1
Preparing to Build
The rod shown in Figure 6-8 has graduations in feet and decimal parts of a foot. This is the type used for regular surveying work. Rods are also available with graduations in feet and inches. When sighting short distances (100 or less), a regular wooden or metal folding rule can be held against a wood stake and read through the instrument. This procedure will be satisfactory for jobs such as setting grade stakes for a footing. Always be sure to hold the stake and rule in a vertical position.
Working Knowledge Leveling instruments and equipment will vary somewhat, depending on the manufacturer. Always carefully read and study the instructions for a given brand.
Always set the tripod on rm ground with the legs spread well apart. When it is set up on a oor or pavement, take extra precautions to ensure that the legs will not slip. For precision work, permit the instrument to reach ambient (air) temperature before making readings. When the lenses collect dust and dirt, clean them with a camel hair brush or special lens paper. Never use force on any of the adjustments. They should easily turn by hand. Have the instrument cleaned, lubricated, and checked yearly by a qualied repair station or by the manufacturer.
Bubble
Figure 6-10. The bubble of the level vial will generally move in the same direction as the left thumb. This bubble needs to move left.
Sighting
Most builders levels have a telescope with a power of about 20. This means that the object being sighted appears to be 20 times closer than it actually is. The procedure for sighting is easy to learn: 1. Line up the telescope by sighting along the barrel and then look into the eyepiece, Figure 6-11. 2. Adjust the focusing knob until the image is clear and sharp. 3. When the crosshairs are in approximate position on the object, Figure 6-12, tighten the horizontal-motion clamp. 4. Make the nal alignment by turning the tangent screw.
Figure 6-11. Sighting a level line with a builders level. Both eyes are kept open during sighting. This reduces eyestrain and provides the best view. Hand signals tell the rod holder whether to raise or lower the target on the leveling rod. (Kasten-Weiler Construction)
Chapter 6
Building Layout
157
158
Section 1
Preparing to Build
Crosshairs
might be a stake with a nail in it or the intersection of two string lines marking the corner of a building line.
Vernier scale
40
60 45 30 15 0 15 30 45 60
30
60
50
70
80
Laying out corners with the transit requires an understanding of how the horizontal graduated circle is marked. It is divided into spaces of 1, Figure 6-13. When you swing (rotate) the telescope of the builders level or transit, the graduated circle remains stationary, but another scale, called the vernier scale, moves. It is marked off in 15-minute intervals. When laying out or measuring angles where there are fractions of degrees involved, you will use this vernier scale. Figure 6-14A shows a section of the graduated circle and the scale. It reads 75. Notice that the zero mark on the vernier exactly lines up with the 75 mark. Now look at Figure 6-14B. The zero mark has moved past the mark for 75, but is not on 76. You need to read along the vernier scale until you nd a mark that is closest to being directly over a degree mark on
60
70
80
90
50
75
to check alignment. The vertical and horizontal crosshairs should center on the top of the stake. Drive a nail in the top-center of the stake. 3. Place another stake at the correct setback for one side of the property line. You are now ready to stake out the building lines.
Staking a building
Staking out building lines requires two persons. When a builders level is used, the second person will use a rod that must be plumbed along the line of sight. Since a transit can pivot up and down, the second person uses a stake to locate corners along the building line. 1. Attach a plumb bob to the center screw or hook on the underside of the instrument. Some instruments have an optical plumb for zeroing in over a point. Shift the tripod until the point of the plumb bob is directly over the point marking the corner of the building lines. This is at point A on line AB, as shown in Figure 6-15. 2. Level the instrument before proceeding further. Recheck for plumb. 3. From point A (or station A), turn the telescope so the vertical crosshair is directly in line with the edge of a stake or rod held at point B. When using a transit, sight the telescope on the stake. 4. Use a measuring tape along line AB to locate distance to the corner. Drive a corner stake at this point. 5. Set the horizontal circle on the instrument at zero to align with the vernier zero and swing the instrument 90 (or any other required angle). 6. Position the rod or stake along line AC so it aligns with the crosshairs. 7. Locate the other corner along line AC using a measuring tape. 8. Move the instrument to point C, sight back to point A and then turn 90 to locate the line of sight to point D. 9. Measure the distance to point D and place a stake. 10. Use a measuring tape to check the diagonal distances. If these are equal, the building line is square. If the resulting gure is a rectangle or square, you have completed the layout. However, you may want to move the instrument to point D to check your work.
40
60 45 30 15 0 15 30 45 60
30
60
50
70
80
60
70
80
90
Figure 6-14. Reading the horizontal circle of a transit. AWhen the zero mark of the vernier is exactly on a degree mark, the reading is an even degree. In this case, the reading is 75. BWhen the zero mark is between degrees, read across the vernier to nd the minute mark that aligns with a degree mark. This reading is 75, 45. (David White)
360
1 45
the circle. That number is 45. The reading is 75, plus the number on the vernier, 45 minutes. Vernier scales will not be the same on all instruments. Study the operators manual for instructions about the particular model you are using.
90 = square corner = 1 quadrant 270 Measurements of a circle Circle 1 1 minute 1 quadrant = 360 = 60 minutes = 60 seconds = 1/4 circle or 90 90
Station mark: The reference point where a builders level or transit is set up when laying out building lines or nding grade levels and elevations. It must be a type of marker that will not be disturbed by any construction activity. Benchmark: A mark on a permanent object xed to the ground from which grade levels and elevations are taken for construction of a building. Sometimes ofcially established by government survey. Vernier scale: Device on a transit that measures minute portions of an angle.
180
Figure 6-13. The graduated circle of a transit corresponds to the 360 of a full circle; 90 represents a quadrant, which would give you a square corner for a building.
50
75, 45 Minutes
Chapter 6
Building Layout
159
160
Section 1
Preparing to Build
5'-2"
C B C
22 stake
Figure 6-15. Steps for laying out building lines. LeftLocate the instrument over a stake marking a corner. Line up 0 on the instrument circle with the building line AB. Swing the instrument 90 to establish line AC. RightMove the instrument to point C to establish point D. Rod must be used when the instrument is a builders level. Rod must be held plumb using a plumb line or carpenters level. A transit is a much better instrument in this operation since it is not necessary to use the rod. Simply swivel the transit telescope and sight on the corner stake.
In practice, you will nd that it is difcult to locate a stake in a single operation. This is especially true when using a builders level, where the line of sight must be dropped to ground level with a plumbed rod or straightedge. Usually, it is best to set a temporary stake, as in Figure 6-16. Mark it with a line sighted from the instrument. Then, with the measuring tape pulled taut and aligned with the mark, drive the permanent stake and locate the exact point as shown. All major rectangles and squares of a building line can be laid out using leveling instruments in the manner just described. After batter boards are set and lines attached, the carpenters level and square can be used to locate stakes for small projections and irregular shapes.
Figure 6-16. A temporary stake may be used to establish an exact point. First, set the temporary stake and mark the line of sight on it. Drive a second stake and transfer the mark from stake A.
Many points on the building site need to be set at certain elevations or grade levels. These points might include: The depth of excavation, such as for a basement. The nished height (elevation) of the foundation footings. The height (elevation) of foundation walls. The elevation of oors. Site features, such as proper grading to ensure that surface water is directed away from the building. Bearing elevation (point at which footings contact the earth) for footings in order to ensure adequate frost protection of the foundation. Establishing rise and run of steps and walkways as part of the exterior of the structure. Not all building sites are level. Finding the difference in the grade level between several points or transferring the same level from one point to another is called grade leveling. This operation is immediately useful to the excavator, who must determine how much earth must be removed to excavate a basement or trench a foundation footing. Grade leveling is also useful to determine how much earth must be deposited in a particular area to achieve a desired height or elevation at that location. When the leveling instrument has been set level, the line of sight will also be level. The readings can be used to calculate the difference in elevation, Figure 6-17. If the building site has a large slope, the instrument may need to be set up more than once between the points where you want to take readings. The rst reading is taken with the rod in one position. Then, the instrument is carefully rotated 180 to get the reading at a second rod position. This position may be higher or lower than the rst position. From a practical standpoint, it is simpler to work from a higher point on the site than a lower point. Depending on the actual slope, this measurement can often be made with a single reading. The term grade means the level of the ground. Elevation refers to the major structural levels
A B
5'-9"
A B
Figure 6-17. Establishing a grade level and nding the difference between two points on a building lot. Top Level the instrument and take a line of sight reading on point A. Mark down the rod reading. BottomSwing the telescope 180 and take a line of sight reading on the rod. Compare the two elevations. In this example, point A is 7 higher than point B.
of the building. More specically, these levels include the top of the footing, top of the foundation wall, and nish height of the rst oor. There should be a reference point (level) for all elevations established on the building site. It is called the benchmark, datum, or simply the beginning point. This point must remain
Grade leveling: Finding the difference in the grade between several points or transferring the same level from one point to another. Grade: Quality of lumber. Also, the height or level of a building site. Elevation: The height of an object above grade. Also, a type of drawing that shows the front, rear, and sides of a building. Datum: An established reference point for determining elevations in an area. Also called benchmark or simply the beginning point.
Chapter 6
Building Layout
161
162
Section 1
Preparing to Build
undisturbed during the construction of the building project. A stake driven at one corner of the lot or building site, or even a mark chiseled into concrete curbing, often serves as the benchmark.
Required grade elevation Pier footing Tripod Grade stake mark 1'-10" 2'-4" C Mark Building line 2'-4" F 1'-10"
Checking grade
Building sites are rarely perfectly level. All have high and low points. These highs and lows need to be determined before the height of the foundation is established. This job is easier when the site is fairly level, as in Figure 6-17. 1. Locate the instrument midway into the site, then level the instrument. 2. Take a line-of-sight reading on a rod held at one edge of the site. 3. From the position of the target on the rod, note the elevation (5-2 in Figure 6-17) and record it. Surveyors keep a notebook for such recording, since many people may need to refer to the readings. Carpenters generally jot readings on a piece of scrap lumber. Usually, they are the only ones needing to refer to the readings. 4. Rotate the telescope 180. Take a line-of-sight reading on the rod located at the opposite side of the site. 5. Note the elevation at the target position on the rod (5-9 in Figure 6-17). Record it as before. 6. Subtract the lower elevation from the higher one to nd the difference (7). This number is the actual vertical increase or decrease from one known point to another. When setting grade stakes for a footing or erecting batter boards, set the instrument in a central location on the site, as shown in Figure 6-18. The distances to the target (or rod) will be roughly equal. This will improve the accuracy of the readings taken for each corner. An elevation established at one corner can be quickly transferred to other corners or points in between. Figure 6-18. A central location for the instrument will make nding and setting grade stakes easier and more accurate.
Required grade elevation
Figure 6-19. Cut and ll stakes are used to tell the excavator how much material must be removed or added to reach grade level. The letter C means cut (remove) and the letter F means ll (add).
be necessary to set up the instrument in several locations. Figure 6-20 shows how reading from two positions is used to calculate, establish, or determine differences in grade at various locations on the plot. 1. Set up the instrument midway between two points on the plot. In Figure 6-20, these are identied as points A and B. 2. Take a line-of-sight reading at point A (or station A). Record the reading in the notebook. In this case, the reading is 5-8. 3. With the rod at point B and the instrument still at setup #1, take a second reading. Record the reading in the notebook. In this instance, the reading is 2-6. 4. Move the instrument to a point midway between points B and C. Level it as before. 5. Take a second reading on point B and record it. In this example, the reading is 6-0. 6. With the rod located at point C, take a reading by rotating the telescope 180. Note and record the elevation. In this case, the reading is 2-4. 7. Calculate the differences in grade level for each pair of stakes, as shown in Figure 6-20. 8. Add the resulting distances and subtract the minus sum from the plus sum to nd the difference in grade from one edge of the plot to the other. The result, in this example, is 6-10.
6'-0"
2'-4"
5'-8"
Cut: The process of removing material to achieve the desired grade. Fill: The process of adding material to achieve the desired grade.
Setup #1
Setup # 1 2 Sum
Figure 6-20. When there is a large slope on the property or when long distances are involved, the transit will need to be set up in two or more locations.
Chapter 6
Building Layout
163
164
Section 1
Preparing to Build
simply laser levelthe operating principle of the various units is essentially the same. They perform most of the functions of a conventional transit. However, they need only one person to carry out any layout operation. Some are designed to rotate 360, allowing the operator to establish level lines throughout the structure without moving the instrument.
Safety Note For safety, power output of the laser is controlled. Federal regulations limit Class II construction lasers to 1 milliwatt and Class IIIa units to less than 5 milliwatts. These levels are safe for the eyes so long as the user does not stare into the beam. Manufacturers cautions should be carefully observed.
Figure 6-22. A transit can be used to lay out or check points in a vertical plane.
A laser level can be set to emit a laser beam for a full 360 without being tended by an instrument person. Figure 6-24 shows the laser transmitter and its receiver. During use, the transmitter is untended. The receiver can be tended by a rod
90
Figure 6-23. Using the transit to plumb an object. First, align the vertical crosshair with the base. Then, swing the telescope to or near the top. Adjust the object for plumb as needed. Reposition the instrument at a 90 angle to the rst line and repeat the process. Figure 6-24. Laser level and receiver. The transmitter is at the right and the receiver is at the left. (SpectraPhysics Laserplane, Inc.)
Laser level: Leveling instrument that emits a level laser beam over 360without being attended. A receiver attached to a rod and attended by a rod holder makes a sound when the laser beam strikes it.
Chapter 6
Building Layout
165
166
Section 1
Preparing to Build
holder, Figure 6-25, or it can be attached to an excavator or backhoe, Figure 6-26. Operators of excavating equipment can work the entire job site without stopping to check grade levels. The laser level continuously monitors grade, eliminating excess excavation.
ON THE JOB
Surveyor/Surveying Technician
Surveyors and surveying technicians establish ofcial land boundaries and the exact location and extent of building sites and other land uses. Survey parties, usually consisting of several surveying technicians under the direction of a party chief, traditionally use a variety of instruments to establish property boundaries and elevations. A licensed surveyor uses this information, combined with research in legal records and other sources, to prepare an ofcial map called a plat of survey that establishes the ofcial location of the property. Such a survey is often required before a deed can be issued in a property transfer. Surveyors are professionals who must meet educational and experience requirements and pass licensing examination. In the past, surveyors could be licensed by gaining experience on a survey party, then passing a licensing exam. However, most states today require a four-year degree in surveying or a related eld, such as civil engineering, in addition to the exam and eld experience. Surveying technicians often have some postsecondary training, usually in a community college certicate or associate degree program. High school courses in algebra, geometry, trigonometry, and drafting are good preparation. Technicians are usually responsible for using optical, physical, and electronic tools to make the needed measurements in the eld. While traditional tools such as theodolites and measuring tapes are still used, more and more survey parties are working with electronic distance-measuring devices and global positioning system receivers that use satellite data for precise location-nding. Advancement to party chief is possible with additional formal training and experience. Working conditions for survey parties can be extreme, since they are exposed to all kinds of weather conditions and may have to carry equipment for long distances in rugged terrain. Licensed surveyors often work in the eld, but also spend time indoors doing research, data analysis, and report writing. Approximately 2/3 of all surveyors and surveying technicians are employed by architectural and engineering rms or companies providing related services. Most of the remaining employment is provided by government at all levels, ranging from federal agencies, such as the U.S. Forest Service, to state and local planning departments and highway agencies. A relatively small number of surveyors are self employed.
Figure 6-26. A laser receiver can be attached to an excavating machine, speeding up the excavation process. (Spectra-Physics Laserplane, Inc.)
Figure 6-25. A rod holder moves the receiver up or down until it is on line of sight with the laser level. (Spectra-Physics Laserplane, Inc.)
The operator places the bucket or blade cutting edge on the benchmark or nished elevation. Then, the receiver is adjusted up or down on the machine and the operator tightens the clamp when the on-grade point is reached. The receiver catches the laser beam from the rotating transmitter and signals the operator whether measured surface is above, below, or on grade. The laser level is also adapted to other construction tasks to establish either level or plumb lines. Horizontal operations for which it might be used include leveling suspended ceiling grids and leveling raised-access computer oors. Vertical operations include plumbing partitions, curtain walls, posts, columns, elevator shafts, or any operation requiring a vertical reference point.
Chapter 6
Building Layout
167
Summary
The correct location on the building site must be identied before the foundation or slab can be constructed. Laying out a building involves locating the outside corners of the foundation, driving stakes, and then stretching building lines between stakes to mark where the walls will be. Measuring tapes can be used for layout work, but leveling instruments are more precise. Leveling instruments are also used to establish grades and elevations. Laser levels are replacing conventional transits and levels in building site layout. Their biggest advantage is requiring only one person to take measurements, rather than two.
8. True or False? The vernier scale is used to measure angles in fractions of a degree. 9. To position a leveling instrument without an optical plumb directly over a given point, a ______ is used. 10. When setting grade stakes for a building footing, the instrument should be set up in a ______ location. 11. True or False? A laser level can check the level of an entire structure from one position.
Curricular Connections
Mathematics. Make a study of the procedures you would follow and calculations you would make to determine the height of a agpole, tall building, or mountain, using a transit and trigonometric functions. Use the information to determine the height of at least one tall object in your community. Prepare a report for your class explaining the theory and how you proceeded.
Outside Assignments
1. Study the catalog of a supplier or manufacturer and develop a set of specications for a builders level. Be sure it includes a good carrying case. Also select a suitable tripod and measuring tape. Secure prices for all of the items. 2. Through drawings and a written description, tell how you would proceed to lay out a baseball diamond using a transit.