Project Report Water Logging Thane

Download as pdf or txt
Download as pdf or txt
You are on page 1of 79

PROJECT REPORT ON REPETITIVE WATER LOGGING IN THANE CITY ENGINEERING SOLUTIONS AND ENVIRONMENTAL MANAGEMENT PLAN

(SPONSORED BY THE MMR ENVIRONMEN IMPROVEMENT SOCIETY) T

(DRAFT FINAL REPORT)

INDEX
TABLE OF CONTENTS CHAPTER 1 PREAMBLE
1.1NEVER BEFORE SITUATION 1.2SUGGESTIONS BY MMREIS 1.3OBJECTIVES OF THE PROJECT 1.4METHODS OF OBTAINING DATA 1 1 2 2

1.4.1MAPS ...................................................................................................................................2 1.4.2IDENTIFICATION OF WATER LOGGING SPOTS...................................................................................2 1.4.3IDENTIFICATION OF OBSTRUCTIONS IN THE WATERCOURSES ........................................................ 3 ............................................ 3 3 3 4 1.4.4INFORMATION REGARDING KHARLAND DEVELOPMENT ...................................................................3 1.4.5ESTIMATES OF ECONOMIC LOSSES BECAUSE OF WATER LOGGING 1.5SUBMISSION OF INTERIM REPORTS : 1.6FURTHER GUIDENCE OF MMREIS 1.7HIGHLIGHTS OF INTERIM REPORTS

CHAPTER 2 EXECUTIVE SUMMERY


2.1.GENERAL 2.2.FIELD WORK BY HARIYALI 2.3.OBSERVATIONS 2.4.BASELINE ENVIRONMENTAL STATUS 2.5.SUGGESTIONS FOR EMP. 2.6.ENGINEERING SOLUTIONS 5 5 6 7 8 10

CHAPTER 3 THANE CITY : PRESENT STATUS


3.1HISTORY 3.2TOPOGRAPHY 3.3DEMOGRAPHY 3.4INFRASTRUCTURE 12 12 12 13

12

3.4.1STORM WATER DRAINAGE SYSTEM ............................................................................................13 3.4.2WATER SUPPLY ....................................................................................................................13 3.4.3SEWERAGE...........................................................................................................................13 3.4.4ROADS, FLYOVERS, SUB-WAYS AND RAILWAYS .........................................................................13

Index Page i

3.5SERVICES

14

3.5.1ELECTRICITY SERVICES..........................................................................................................14 3.5.2TELEPHONES .......................................................................................................................14 3.5.3GAS LINES ........................................................................................................................14 3.6HEALTH SERVICES 15 3.7LAND USE PATTERN 15 3.7.1NON-DEVELOPED AREA..........................................................................................................15 3.7.2DEVELOPED AREA ................................................................................................................15 3.7.3FOREST AREAS.....................................................................................................................16 3.7.4LAKES ................................................................................................................................16

CHAPTER 4 STORM WATER DRAINAGE SYSTEM


4.1NATURAL WATERCOURSES (WC) 4.2CATCHMENT AREA 4.3CARRYING CAPACITY 4.4OBSTRUCTIONS 17 17 17 18

17

4.4.1UTILITIES.............................................................................................................................18 4.4.2STRUCTURES ........................................................................................................................18 4.4.3DUMPING OF SOLID WASTE......................................................................................................19 4.4.4LIMITATION DUE TO ESTURIAN MECHANISM................................................................................ 19 4.5IDENTIFIED REPETITIVE WATER LOGGING SPOTS 19 4.6INTER-CONNECTION WITH SEWERAGE 20 4.7STORM WATER DRAINAGE PLAN OF TMC 20

CHAPTER 5 NATURE & CAUSES OF REPETITIVE WATER LOGGING IN TMC AREA


5.1IDENTIFICATION OF WATERCOURSES (WCS) 5.2FLOODING SITUATION ON 26TH JULY 2005. 5.3CAUSES OF REPETITIVE WATER LOGGING 21 24 25

21

5.3.1IDENTIFIED WATER LOGGING SPOTS........................................................................................... 25 5.3.2CAUSES FOR IDENTIFIED WATER LOGGING SPOTS......................................................................... 25 5.4PICTORIAL GLIMPSES OF CAUSES OF WATER LOGGING 28

CHAPTER 6 TECHNICAL ANALYSIS


6.1DESIGN CRITERIA 6.2USE OF DIFFERENT MODELS 33 33

33

Index Page ii

6.3DESIGN OF STORMWATER DETENTION

35

CHAPTER 7 EFFECTS OF WATER LOGGING IN THANE CITY


7.1EFFECTS ON INFRASTRUCTURE AND SERVICES 36

36

7.1.1ROADS................................................................................................................................36 7.1.2WATER SUPPLY.....................................................................................................................36 7.1.3TRANSPORT..........................................................................................................................36 7.1.4ELECTRICITY SUPPLY..............................................................................................................36 7.1.5EDUCATION..........................................................................................................................36 7.1.6RAILWAYS............................................................................................................................36 7.1.7COMMUNICATION SERVICES.....................................................................................................37 7.1.8HEALTH...............................................................................................................................37 7.2EFFECT ON INDUSTRIES AND SLUMS 37 7.2.1INDUSTRIES..........................................................................................................................37 7.2.2SLUMS.................................................................................................................................37 7.3LOSS OF HUMAN & BOVINE LIFE 38 7.4ENVIRONMENTAL LOSSES 38 7.5ECOLOGICAL LOSSES 38 7.6SOCIO ECONOMIC LOSSES 38 7.6.1SOCIAL................................................................................................................................38 7.6.2ECONOMIC...........................................................................................................................38

CHAPTER 8 BASELINE ENVIRONMENT AL STATUS


8.1WATER POLLUTION 8.2AIR POLLUTION 8.3SOLID WASTE MANAGEMENT 8.4WETLANDS, MUDFLATS AND MANGROVES 8.5FOREST 8.6RECLAMATION 8.7ROADSIDE TREES 8.8ECOLOGY AND MARINE HABITAT 40 41 41 42 42 43 43 43

40

CHAPTER 9 ENVIRONMENTAL MANAGEMENT PLAN (EMP)


9.1PURPOSE OF EMP 9.2STORM WATER MANAGEMENT (ACTION: TMC) 9.3SOLID WASTE MANAGEMENT (ACTION: TMC AND SUITABLE NGO) 44 44 45

44

Index Page iii

9.4BIO-MEDICAL WASTE (ACTION : TMC & NGO TO BE IDENTIFIED BY TMC) 9.5SEWERAGE (ACTION: TMC) 9.6WATER SUPPLY (ACTION: TMC) 9.7HEALTH (ACTION: TMC & NGOS/HOSPITALS ) 9.8SLUMS (ACTION: TMC) 9.9RAILWAYS (ACTION: CENTRAL RAILWAY AND TMC) 9.10ROADS (ACTION: TMC) 9.12ELECTRIC SUPPLY: (ACTION: MSEDCL) 9.13TELEPHONE SERVICES (ACTION: MTNL) 9.14 WATER BODIES ( ACTION : TMC ) 9.15 DEVELOPMENT PLAN ( ACTION : TMC ) 9.16RISK AND INSURANCE ( ACTION TMC, INSURANCE COMPANIES ).

45 46 46 46 47 47 47 48 48 48 48 49

CHAPTER 10 ENGINEERING SOLUTIONS


10.1TRAINING OF MAJOR WATER COURSES 10.2PROVIDING ROAD SIDE STORM WATER DRAINS 10.3CONTROL BY TOWN PLANNING AND DEVELOPMENT DEPARTMENT OF TMC 10.4CLEANING OF WATER COURSES 10.5SHIFTING OF UTILITIES 10.6CONSTRUCTION OF DETENTION PONDS 10.7CONTROL ON SOLID WASTE IN THE WATER COURSES 10.8DEVELOPMENT OF LOW LYING AREAS AND SLUMS 10.9SEWERAGE NETWORK 10.10 HYDRAULIC MODELLING OF CREEKS 10.11TUNNELING AS OPTION 10.12INTERLINKING OF LAKES 62 62 62 63 63 63 63 64 64 64 64 65

62

CHAPTER 11 ACTION PLAN FOR TMC


11.1IMMEDIATE ACTION POINTS 11.2MEDIUM TERM STRATEGY 11.3LONG TERM STRATEGY 66 67 68

66

ACKNOWLEDGEMENT COMBINED LAYOUT OF THANE CITY

69 71

Index Page iv

Index Page v

CHAPTER 1 : PREAMBLE

CHAPTER 1 PREAMBLE
1.1 NEVER BEFORE SITUATION The deluge of July 2005 in Mumbai, Thane and surrounding area created an unprecedented situation resulting in heavy losses of lives, property, infrastructure and services and severe environmental damages. This prompted HARIYALI an NGO, dedicated to environmental protection and up-gradation, to undertake a survey of public perceptions about nature, causes and effects of deluge in Thane and about preventive measures that could be taken to minimize losses, if such a situation recurs in future (Ann-I P.60 to 85). Hariyali believed that public participation in such projects will yield maximum results. Hence Hariyali involved over 600 NSS students of various colleges in and around Thane to interview over 8200 families in Thane Municipal Corporation (TMC) area, using objective questionnaire specially prepared for the purpose. An Experts Committee, including technocrats, economists and social leaders, was formed to provide guidance in the study and to scrutinize and analyse the data compiled from the response sheets received (Ann-I - P.12) Shri K.D.Lala, City Engineer, TMC, kindly agreed to be a Member on the Committee (Ann-I - P.6) Meanwhile, Hariyali submitted a proposal to MMREIS in November 2005 seeking financial assistance. The Sub-Committee of MMREIS suggested to modify the proposa l. 1.2 SUGGESTIONS BY MMREIS While appreciating the efforts of Hariyali, the MMREIS made following suggestions:a] Deluge being rare phenomenon, Hariyali should attempt to prepare a project report on repetitive water logging during last 20 years in Thane city. b] While approach of Hariyali in eliciting public participation in the project on deluge in Thane is commendable, what is most required is engineering solutions (E.S.) for preventing repetitive water logging and minimizing losses. Hariyali should also prepare an Environmental Management Plan (EMP) for mitigating the impact of repetitive water logging. c] As the implementing agency will be TMC, it is necessary that the TMC should be actively associated with the Project work. TMC engineers should also be involved in the collection of information and preparation ofthe report. As per the above suggestions a modified proposal was submitted to MMREIS by end of November, 2005.

Project by : Hariyali, Thane, Sponsored By : MMREIS

CHAPTER 1 : PREAMBLE

1.3

OBJECTIVES OF THE PROJECT a] To identify causes and locations of repetitive water logging in Thane City in the last about 20 years. b] To undertake study of flood prone areas and to assess impact of water logging. c] To recommend Engineering Solutions for preventing water logging in Thane City. d] To prepare environmental management plan for Thane City with reference to water logging.

1.4

METHODS OF OBTAINING DATA 1.4.1Maps The TMC had two separate maps showing Thane City and Mumbra, Kalawa, Diva area under its jurisdiction. Both the maps were of different scales. Hariyali combined the two maps, made them of same scale and used it as a base map for the study. EICHER maps were used to superimpose on the base map various locations and roads in TMC area. A map of Administrative Zones of TMC has been collected from TMC and reproduced in Annexure III. Similarly TMC had maps showing many (but not all) watercourses. Of these, major Watercourses were marked on the base map as shown in Annexure III (Page 97). The counter map showing watercourses in Thane City proper were available with TMC. Hariyali picked up certain important contours from this map to superimpose on the Base map. The countor maps of Mumbra, Kalwa and Diwa area were, however, not available. 1.4.2Identification of water logging spots As a pre-requisite to formulate EMP for Thane city, the members of the Experts Committee formed by Hariyali interviewed officers in 19 infrastructure and service providing organizations to know the impact of water logging on their services. The information of locations of repetitive water logging spots was obtained from them. These locations were confirmed during discussions with the ground level engineers of various Prabhag of TMC and also during physical visits to the spots. The locations of repetitive water logging spots were then marked on the base map.

Project by : Hariyali, Thane, Sponsored By : MMREIS

CHAPTER 1 : PREAMBLE

1.4.3Identification of Obstructions in the watercourses Some of the major watercourses were visited extensively by the NSS students during preliminary survey and photographs of the same are reproduced in Annexure II. The Members of the Expert Team of Hariyali discussed the causes of water logging with the ground level engineers of TMC and made extensive visits to the watercourses and water logging spots to verify the situation. The table on repetitive water logging spots presented in Chapter 9 is a result of all these efforts. 1.4.4Information regarding Kharland development The information about Kharland development schemes in Thane City, Kalwa, and Mumbra region was obtained from the Irrigation Department of GOM. The Expert Committee of Hariyali visited the sites before marking the Kharland area on the base map. 1.4.5Estimates of Economic Losses because of Water Logging These were obtained from the Resource Persons in various infrastructure and service providing organizations interviewed during secondary survey. 1.5 SUBMISSION OF INTERIM REPORTS : Hariyali presented Part I of the Project Report on 19 December 2005 showing the results of the Preliminary Survey of 8200 families & survey of 9 important watercourses, both conducted by NSS students. Part II of the Project Report presented on 11 September, 2006 comprised various maps of TMC area prepared by Hariyali depicting administrative zones, repetitive water logging spots identified in each zone, 25 major watercourses flowing through TMC area, GTS levels and water bodies like Thane creek and Ulhas creek. EICHER and maps of TMC were used for preparation of the maps showing watercourses and water bodies. The repetitive water logging spots were identified in consultation with TMC engineers and the Resource Persons interviewed (Ann-I - P.13). The Part II report also included assessment of impact of water logging on various organizations and services and matrix for EMP and Engineering Solutions. 1.6 FURTHER GUIDENCE OF MMREIS While Considering Part II of the project Report, the sub-Committee of MMREIS suggested that Hariyali should also identify causes of each location of repetitive water logging in consultation with the ground level engineers of TMC and after physically visiting the spots, if needed, and to recommend ES and EMP for

Project by : Hariyali, Thane, Sponsored By : MMREIS

CHAPTER 1 : PREAMBLE

each such location. Accordingly, the members of the Expert Committee held discussions with the engineers of each Prabhag of TMC, made extensive visits to survey major watercourses and submitted Supplementary Report to the SubCommittee of MMREIS in December, 2006 (Ann-I, P.37 to 59). 1.7 HIGHLIGHTS OF INTERIM REPORTS Highlights of Part I of the Project Report, Part II of the Report and Supplementary Report are given in Annexure I of the accompanying volume.

*******

Project by : Hariyali, Thane, Sponsored By : MMREIS

CHAPTER 2 : EXECUTIVE SUMMERY

CHAPTER 2 EXECUTIVE SUMMERY


2.1. GENERAL 2.1.1The Deluge of 2005 prompted Hariyali to undertake a study of over 8200 families in the area of Thane Municipal Corporation(TMC) to know their perceptions about nature of deluge in their locality, its causes, effects and possible solutions. Hariyali approached MMREIS for funding. The SubCommittee of MMREIS suggested to study repetitive water logging spots in TMC area and to suggest ES and EMP with particular reference to water logging in Thane City. This became the objective of the Project (Paragraphs 1.1 to 1.7) 2.1.2TMC area includes Thane city, Mumbra and Kalawa area. Most of the Watercourses flowing in Thane city are natural watercourses flowing from Yeoor hills/Sanjay Gandhi National Park in the North and West to Thane creek or Ulhas creek in the East. In Kalawa area they flow from Parsik hills to Thane creek and in Mumbra, from Mumbra hills to Ulhas river (3.2,3.4.1). 2.1.3There is no underground storm water drainage system but only roadside gutters, open or covered, for collecting local run-off (3.4.1). 2.1.4Existing sewerage facility, covering about 40% population, has been overloaded. There are 5 Sewerage Treatment Plants, all overloaded (3.4.3). 2.1.5The network of distribution of electricity services, telephone lines and gas pipe lines is underground, many times through watercourses (3.5). 2.1.6TMC has presently 35 rainfed lakes ( 3.7.4). 2.2. Field Work by Hariyali 2.2.1With the help of maps available in TMC and on the basis of EICHER, Hariyali, identified 25 major watercourses in TMC area, although the actual no of watercourses are many more. Hariyali prepared a base map of TMC area showing Thane, Kalawa and Mumbra and superimposed therein identified major watercourses, water bodies, GTS levels and water logging spots (1.4). 2.2.2Hariyalis Experts Team interviewed 19 resource persons from various infrastructure and service providing organizations to assess the impact of water logging on their services. With the help of these resource persons and the engineers of TMC, 75 water logging spots were identified in TMC area, of which about 65 are of repetitive nature. Hariyalis team inspected all the spots (1.4 & 4.5). 2.2.3Hariyalis Experts Team also visited each of the 25 major watercourses identified and took photographs of the flow of the watercourse.

Project by : Hariyali, Thane, Sponsored By : MMREIS

CHAPTER 2 : EXECUTIVE SUMMERY

2.3. Observations 2.3.1It was observed that a steep gradient available in the initial part of the watercourse (from over 35 m. GTS to about 24 m GTS) gets converted into flatter gradients after the watercourse enters the developed area. While the initial catchment area has high run-off, less time of concentration and less travel time, the catchment area in the latter part of the watercourse has moderate run off, medium time of concentration and more travel time. The carrying capacity of the watercourses has been considerably reduced during their travel in the developed area due to non-removal of silt including boulders in the watercourse, encroachments within and on the banks of watercourses, dumping of solid wastes, obstruction due to utilities, inadequate cross drainage, incorrect alignment of the watercourses, etc. These were also the common reasons for water logging during high run-off in the monsoon (4.2, 4.3 & 4.4) 2.3.2In slum areas, drainage lines are let out into the watercourses. Also overflow connections in the existing sewer lines are many times made into the watercourses (4.6). 2.3.3The Integrated Nalla Development Plan prepared by TMC, to be executed in next 3 years, includes review of carrying capacity of all watercourses and taking remedial action, including provision of holding ponds with flap gates (4.7). 2.3.4With a view to facilitating analysis of major causes of flooding, the 75 water logging spots have been broadly classified on the basis of their proximity to the creek, to the watercourses or to the forest boundary or on the basis of structures in the vicinity such as slums or normal/high rise buildings (5.3.1). 2.3.5Apart from the common reasons indicated above, the water logging occurred at some spots in the vicinity of the creek/s because the development levels are less than the highest high tide level of 1.9 m (GTS) and the area gets affected due to back water surge from the creek into the watercourse (5.3.2.). 2.3.6 In the vicinity of the forest boundary, the high velocity of the water current brings down boulders and silt during monsoon which gets deposited in the watercourse when it enters flat grounds. The structures in and around the watercourse make it impossible to bring the machinery for de-silting and in many cases, even manual cleaning of the watercourse is extremely difficult (5.3.2.) 2.3.7The water logging spots in the vicinity of the watercourses are because of extremely reduced carrying capacity of the watercourse due to encroachments of structures, utilities, solid waste dumping, as also inadequate capacity of railway culverts, skewed alignment, inadequate cross-drainage, etc. The size of railway

Project by : Hariyali, Thane, Sponsored By : MMREIS

CHAPTER 2 : EXECUTIVE SUMMERY

culverts constructed many years before has not been increased to meet the high co-efficient of run-offs of the increasing population (5.3.2 & 9.17). 2.3.8Major reasons for water logging spots in the slum area are structures making it difficult to de-silt the watercourse and solid waste dumping by the people because of absence of solid waste disposal facility (5.3.2 & 9.17). 2.3.9In the area of multi-storied buildings and normal structures, there are some water logging spots because the developers have turned the watercourse by 90 degrees or more for his convenience and there are compound walls or concrete paths or parking area on the watercourse making de-silting impossible (5.3.2 & 9.17). 2.3.10Some saucer type low lying area such as Krantinagar in the vicinity of creek, face the problem of water logging during heavy rains because there is no outlet for water and there is back water surge during high tide and heavy rains (5.3.2 & 9.17). 2.3.11The consultants working for TMC appear to have considered rainfall of 50 mm for one hour while suggesting storm water design systems. However, each catchment area is subjected to various rainfall intensities and duration curve. It is therefore suggested that the TMC may take up a detailed study of rainfall intensity and duration curves in different catchment areas and prepare a master plan for storm water drainage system (6.1 & 6.2). 2.3.12There is a scope to design storm water detention facilities by utilizing the bunds constructed by Khar Land Development Division in the Irrigation Department of GOM (6.3). 2.3.13The water logging in TMC area affects adversely on various infrastructure and services such as roads, transport, railways, water supply, electricity supply, telecommunication services, education and health services and on industries. The flooding and water logging also sometimes result in losses of human and bovine life, environmental losses and socio-economic losses (7.1 to 7.6) 2.4. Baseline Environmental Status 2.4.1The environmental status of water bodies such as lakes andcreeks and Ulhas river is not satisfactory. The TMC has now taken up steps to monitor the quality of water in lakes with reference to important indicators. TMC also appears to have mooted a creek conservation program with the help of selected NGOs and professional bodies but it is necessary to study in detail the important hydrological aspects of the water bodies and this would require a joint study by all the corporations and councils bordering Ulhas creek and Ulhas river. They

Project by : Hariyali, Thane, Sponsored By : MMREIS

CHAPTER 2 : EXECUTIVE SUMMERY

may take help of CWPRS for hydraulic modelling to reassess the assimilative capacities of the adjoining water bodies (8.1). 2.4.2The base line status of the solid waste management in Thane city is not up to the mark. In various slum areas, inaccessible for Ghantagadi, there is no arrangement for collection of solid waste. Most of the solid waste collected by TMC is dumped on the dumping ground. Inadequate machinery for collection, treatment and disposal of solid waste and lack of knowledge and lack of cooperation of people are the main reasons for this position (8.3). 2.4.3Bio-medical waste from big hospitals is presently collected and scientifically disposed off by one NGO, viz., Enviro-vigil. However, there is no provision for collection and disposal of bio-medical waste generated by individuals, private clinics, pathological laboratories, etc (8.3). 2.4.4Absence of recognizing khar land as no development zonehas resulted into allowing constructions in kharland area. This has affected existence of mangroves (8.4). 2.4.5The erosion of soil and boulders create repetitive water logging spots near forest boundaries (8.5 ). 2.4.6Uncontrolled development in the creek vicinity with disregard to development levels cause repetitive water logging in the area besides damage to flora and fauna (8.6). 2.5. Suggestions for EMP. 2.5.1TMC should collect data regarding generation, collection and disposal of bio-medical waste (9.4.3). 2.5.2TMC should take steps to improve the efficiency of the sewage treatment plants (9.4). 2.5.3The work of de-silting of watercourses is taken up only once before monsoon. The de-silting of watercourses up to the invert level should be done three times, viz., in May, November and February every year (9.2). 2.5.4Budgetary provision for storm water drainage should be adequately enhanced (9.2.9). 2.5.5A stormwater drain inventory should be maintained and a project for such drainage should be planned and implemented(9.2). 2.5.6A programme of shifting utilities in the watercourses should be pursued vigorously (9.2). 2.5.7Segregation of solid waste into bio-degradable and recyclable wastes should be enforced at every level and rules be framed for providing penalties (9.3).
Project by : Hariyali, Thane, Sponsored By : MMREIS

CHAPTER 2 : EXECUTIVE SUMMERY

2.5.8Community awareness and capacity building program for solid waste disposal should be taken up in association with NGO (9.3). 2.5.9Adequate bins should be provided and frequency of transportation of containers of solid waste should be increased (9.3). 2.5.10Centers should be opened for collection of bio-medical waste from private clinics and public (9.4). 2.5.11Data on generation and disposal of bio-medical wastes should be collected (9.4). 2.5.12Program should be taken up for stopping leakages from joints of sewerage lines and water supply lines (9.5 and 9.6). 2.5.13Sewerage plan for the city and a plan for treatment and disposal of sewerage should be prepared (9.5). 2.5.14 A cell should be created in Water Dept at Head Office to monitor and rectify leakages in water supply lines (9.6). 2.5.15Rusted water supply lines should be replaced/repaired (9.6). 2.5.16Capacity building programs should be taken in association with NGOs to control epidemics (9.7). 2.5.17Slum dwellers in and around watercourses should be rehabilitated under a project of nalla development or under SRA/SRD, whichever is applicable (9.8). 2.5.18TMC should initiate action for setting up a Standing Committee to establish co-ordination with Central Railway for modification and maintenance of six railway culverts (9.9). 2.5.19TMC should design formation levels for all roads with due regard to HFL of surrounding water bodies (9.10). 2.5.20Rainwater harvesting technique by taking bores in roadside drains should be used to minimize run-offs (9.10). 2.5.21Even during monsoon potholes on the roads should be temporarily repaired (9.10). 2.5.22TMC should undertake study of possibility of interlinking all lakes for flood assimilation (9.14). 2.5.23New development should be 0.6m above HFL and any new development of plot should be not less than 4.9m(GTS) (9.15). 2.5.24Any new development between design width of once in 2 years and once in 10 years should be free of structures (9.15).

Project by : Hariyali, Thane, Sponsored By : MMREIS

CHAPTER 2 : EXECUTIVE SUMMERY

2.5.25Any new development in area with design width of once in 10 years and once in 100 years should be with stilt arrangement (9.15). 2.5.26Wet land and mangroves should be protected and a program for plantation of mangroves should be taken up (9.15). 2.5.27A plan and map showing minimum level of reclamation should be prepared and enforced (9.15). 2.5.28Plantation of trees near the origins of watercourses in the forest land should be taken up to reduce soil erosion (9.16). 2.5.29Contour trenches should be provided at appropriate places on the hills to arrest entry of boulders into the watercourses (9.16). 2.5.30Also provision of geo-fabrics to stop entry of boulders into the watercourses should be thought of as an alternative and cost thereof should be worked out (9.15). 2.5.31Insurance companies may consider evolving deluge risk insurance and TMC may consider subsidizing its premium (9.16) 2.6. Engineering Solutions 2.6.1Design criteria of rainfall intensity of once in 10 years should be used to improve carrying capacity by training the major watercourses (10.1). 2.6.2Pumping stations should be provided in the requisite area for pumping out the run-off (10.1). 2.6.3Wherever even manual cleaning is not possible, on-line submersible pumps should be provided for cleaning of watercourses (10.1). 2.6.4Every road should have side-drains with sufficient fall and free flow (10.2). 2.6.5It should be made mandatory for architects to submit plans for development levels of front roads, locations and levels of watercourses, internal storm water drainage arrangement and plinth levels (10.3). 2.6.6Proposed development level of any plot in TMC area should not be less than 4.9m (GTS) (10.3). 2.6.7All utilities in the watercourses should be shifted in next 3 years and in case of utilities crossing the road, separate duct should be provided (10.5). 2.6.8Detention ponds with non-return flaps should be provided on the banks of Thane and Ulhas creeks, in co-ordination with Kharland Dept of GOM, to absorb unusual run-off (10.6).

Project by : Hariyali, Thane, Sponsored By : MMREIS

10

CHAPTER 2 : EXECUTIVE SUMMERY

2.6.9TMC should design and provide a complete sewerage scheme for entire area (10.9). 2.6.10Study of hydraulic modeling of Thane and Ulhas creeks may be taken up by all Councils and Corporations by appointing a suitable agency (10.10). *******

Project by : Hariyali, Thane, Sponsored By : MMREIS

11

CHAPTER 3 : THANE CITY PRESENT STATUS

CHAPTER 3 THANE CITY : PRESENT STATUS


3.1 HISTORY The ancient city of Thane, capital of the Shilahara kings of Konkan, was apparently a land grant from Ankisara Devraja, sovereign of the city of Tagara. According to European travelers, it was a well developed port. The Portugese came to the city in 1530 and ruled it for 200 years before it was captured by Marathas in 1739. The city is known for the first railway line in the country (Mumbai to Thane in 1853). In 1863, the first Municipal Council was formed. As a result of growth of population the status of Municipal Corporation was granted to Thane city and surrounding areas in 1982. 3.2 TOPOGRAPHY Thane city is situated at an altitude of 15' to 150' and the latitude of 19' 10" to 19' 50" and at the longitude of 72' 56" to 73' 50". It is at a distance of 33 km from CST(VT) in Mumbai. The area under jurisdiction of TMC can be broadly categorized as: a] Areas within the limits of the original Thane Municipal Council. b] Areas towards the North, bounded by Sanjay Gandhi National Park, Ulhas river and creek. c] Areas to the East beyond Thane creek merged to form the TMC Kalwa, Mumbra and Diva. The city, spread over an area of 127 sq. km, has a large creek front (Thane creek and Ulhas creek) of over 10 km. The general topography of TMC comprises about 50 GTS contours in hilly areas sliding down to 10 GTS contours at Eastern Express Highway. The average invert of the creeks is 2 GTS. The average yearly rainfall for last 10 years is about 2500 mm. 3.3 DEMOGRAPHY As a result of industrialization, urbanization and proximity to Mumbai, the city has witnessed unmanageable immigration of people from all sections of the society and from all over the country. The notable demographic characteristic are :a] The average annual growth rate over the last 7 decades is approximately 4 %. b] Highly populated area of the city is its central region. c] Literacy rate in the city is 56%. The same is higher in male population than in the female.
Project by : Hariyali, Thane, Sponsored By : MMREIS

12

CHAPTER 3 : THANE CITY PRESENT STATUS

The total population of the TMC area was 12.61 lakhs in 2001 and is estimated to grow up to 19.7 lakhs, 26.11 lakhs and 33.66 lakhs by 2011, 2021 and 2031 respectively. About 35% population lives in slums. 3.4 INFRASTRUCTURE 3.4.1Storm water drainage system This infrastructure in Thane city comprises roadside drains emptying into natural watercourses flowing from hilly region towards creek. There is no underground storm water drainage system provided by the Corporation in TMC area. By and large, it can be stated that the TMC has provided roadside open gutters for collecting the local run-off from roads and abutting areas. 3.4.2Water supply The present water requirement of TMC is 335 MLD which is met from different sources such as MIDC, MJP, BMC and Shahad Temghar Water Authority. Most of the supply is for domestic and commercial purposes and only a small component of 5 MLD is for industries. The piped water supply is made through distribution system with a network of Elevated Service Reservoirs (ESR). Due to complexities of distributed water getting mixed with direct supply, the system gets affected. The TMC has undertaken an augmentation program for rectification. The future demand for water supply has been proposed to be met from dam across river Shai to be developed by TMC as its own scheme. 3.4.3Sewerage Only 40% population is presently covered with sewerage facility. The existing system was developed by MJP (MWSSB) in two stages. Existing sewer network has been overloaded, blocked at many places, thus resulting in overflow of sewage on roads as well as into Nallas. As regards sewage treatment, five Sewage Treatment Plants (STP) provide the primary treatment to the sewage. The STPs are generally overloaded and also some of the units in the plants are non-functional. 3.4.4Roads, Flyovers, Sub-ways and Railways The Eastern Express Highway with its flyovers, multi-lanes and service roads symbolizes modern urban infrastructural development. The Ghoadbundar road, the LBS Marg and other link roads connecting Mumbai and Pune are transport hubs. The total length of the roads in Thane city is 280 kms, about 30 km of CC roads and 250 km of Tar roads.

Project by : Hariyali, Thane, Sponsored By : MMREIS

13

CHAPTER 3 : THANE CITY PRESENT STATUS

There are in all 760 roads in the city. In addition to State Transport Service, private buses, cars and taxis ease the pressure of transport. Within the Corporation area Thane Municipal Transport, Auto-rickshaws and private cars serve the needs of the growing population. Thane station on the Central Railway is an important station where most of the trains halt on their way to all parts of India. Thane is also a major station for local trains connecting the city to the-suburbs of Mumbai, and townships up to Kasara and Karjat. 3.5 SERVICES 3.5.1Electricity Services Earlier the Maharashtra State Electricity Board and now Maharashtra State Electricity Distribution Company Ltd (MSEDCL) has been providing and supervising supply of electricity to domestic, commercial and industrial consumers in TMC area. The MSEDCL has one Circle Office, 3 Divisional Offices and a number of Sub-offices in Thane to supervise and maintain the distribution net work. The entire net work of distribution of 11 kv electricity power from the Sub-station at Colour-chem, Wagle Estate to the consumers in TMC area is through underground cables. Wherever feasible, the small feeder Sub- stations have been installed by MSEB/MSEDCL in the residential/commercial/industrial complexes to facilitate supply of electricity. The Company has recently taken up some steps to reduce losses in power distribution. 3.5.2Telephones Mahanagar Telephone Nigam (MTNL) has presently 8 exchanges in TMC area and one more need based exchange is being opened at Pokharan Road No. 2. Almost all the telephone cables are underground. Only in the slum area or in other areas where it is not possible to give connection through underground cables, MTNL has laid overhead cables for telephone lines. Every year before monsoon, MTNL takes up work related to precautionary measures to prevent leakages & to avoid water logging in the telephone exchange area. The new technology of jelly filled cables has been introduced to avoid seepage of water through cables/joints, etc. and over 90% of copper cables have been replaced by jelly filled cables. 3.5.3Gas Lines Till recently the cooking gas supply to the residents of Thane city was through LPG cylinders. During the year 2006, Mahanagar Gas Nigam Ltd.

Project by : Hariyali, Thane, Sponsored By : MMREIS

14

CHAPTER 3 : THANE CITY PRESENT STATUS

has installed District Regulating Stations (DRS) in Thane city for distribution of gas through the networks of pipelines. The first DRS was installed near Tarangan on Eastern Express Highway and the Mahanagar Gas Nigam has planned to open 5 more DRS at different locations in Thane city. All the pipelines for gas supply are underground, either through the Nallas, roadside drains or through a separate trench dug for the purpose. 3.6 HEALTH SERVICES There are 20 private hospitals, 565 private dispensaries and 60 maternity homes. TMC operates 5 Municipal hospitals, 20 dispensaries and 2 mobile dispensaries. There are 2 Government hospitals. Many hospitals have advanced facilities. Various health care programs, especially for women and children are conducted by TMC, such as family planning, special care for pregnant women and newly born infants, vaccination drives, etc. 3.7 LAND USE PATTERN 3.7.1Non-developed Area The nondeveloped areas of TMC comprise 32% forest land, 33% agricultural land, 11% creeks, tanks & Nallas, 11% low-lying and 13% vacant land capable of being developed. 3.7.2Developed Area As regards developed areas, the distribution is residential 38%, industrial 28%, defense 6%, open spaces 1%, commercial, godowns, office area, etc, 5%, health and education 3%, for railway, S.T. depots etc. 7% and remaining 12% for other purposes. The developed area of the city is about 25sq.km. and non-developed is 103 sq. km. inclusive of marshy land, forest, creeks, tanks and watercourses, agricultural land and vacant land. The residential and industrial areas are 10 sq. km. and 7 sq. km. respectively. Intermingling of 30% of the industrial areas with residential areas causes pollution in the city. The playgrounds, gardens and other open spaces serving as recreational centers occupy only about 1% of the developed area and only 0.16 % of the total city area. As of now, there are 47 gardens, 9 childrens parks, 9 open grounds, 3 picnic spots and 12 transport islands in the city. Dadoji Kondeo stadium is a remarkable sign of the development of the city. Agricultural areas are getting reduced on account of development pressure. From 53% it is now approximately 33% of the total city area. Wetlands, swamps and mangroves occupy about 9%

Project by : Hariyali, Thane, Sponsored By : MMREIS

15

CHAPTER 3 : THANE CITY PRESENT STATUS

of the city area with the blessed existence of creeks, Ulhas river and various lakes. 3.7.3Forest Areas Of the 32% forest land, 40% area is truly afforested, the rest being barren in the absence of afforestation projects. Part of barren forest land has been occupied by hutment colonies, quarries, stone crushing operations and brick kilns, which have posed a threat to the landscape and ecology. 3.7.4Lakes Thane was known as city of lakes with more than 100 lakes. At present, TMC has about 35 rain fed lakes and a few of them have become major recreational attractions. The overall water quality of lakes has been found deteriorated and TMC is making efforts to improve the state of lakes by undertaking Lake Beatification Remediation Program with the support of MOEF, GOI. *******

Project by : Hariyali, Thane, Sponsored By : MMREIS

16

CHAPTER 4 : STORM WATER DRAINAGE SYSTEM

CHAPTER 4 STORM WATER DRAINAGE SYSTEM


4.1 NATURAL WATERCOURSES (WC) There are many natural watercourses in TMC area flowing from hilly region through the city to meet Thane/Ulhas creek. The watercourses flowing from Yeoor hills pass through Thane city and those from Parsik hills pass through Kalwa and Mumbra. Hariyali has identified 25 major watercourses (Nallas) in TMC area, 20 in Thane and Kalwa area and 5 in Mumbra. All these major watercourses have been physically verified by the members of the Expert Committee and have been shown in the map (P.51) Apart from 25 major WCs identified by Hariyali, there are many small or minor watercourses starting either from hills or from some lake (like Upavan) or from locations where two road side drains meet. In Mumbra alone, as against 5 major WCs identified by Hariyali, there are as many as 30 cross-drainage. The total length of WCs in Thane City, Kalwa and Mumbra is about 81 kms, 13.5kms and 14.1 kms respectively. 4.2 CATCHMENT AREA Considering ridge on west of Thane City from MCGM boundary up to end of Owla, all (WC1 on south to WC16 on north), the watercourses, start from hills at RL more than 35m (GTS) and drop down to about 24m (GTS). After crossing water pipe lines, the watercourses drop down to about 5m (GTS) near railway lines, meeting the Thane Creek & Ulhas Creek at average 3m (GTS). Thus a steep gradient in the initial part of these watercourses gets converted into flatter gradients in the further course. Similar configuration exists for WCs in Kalwa starting from Parsik hills and WCs in Mumbra from Mumbra hills. The catchment areas on the upstream of WCs in Thane and Kalwa are relatively large. In Mumbra, the slope of hills near the new bye pass road is very steep and the WCs flowing across this road have relatively small catchment areas. Each watercourse has developed topographically its own catchment area having length ranging from 7 km to 11 km and width 2 km to 5 km, total drop 25 m to 50 m. The nature of catchment in TMC area is obviously with less time of concentration, less travel time and considerably high runoff in the initial 50% part. The remaining 50% part is with medium time of concentration, more travel time with addition of little less runoff than earlier part. 4.3 CARRYING CAPACITY Considering the nature of catchments stated above, it is observed that for WC1 to WC6, sufficient carrying capacity exists to achieve initial considerable quantity of runoff in the undeveloped area of the watercourse. However, in the further course of their travel in the developed area, the carrying capacity in these

Project by : Hariyali, Thane, Sponsored By : MMREIS

17

CHAPTER 4 : STORM WATER DRAINAGE SYSTEM

watercourses has been totally affected and reduced due to non-removal of silt, encroachments within and on the banks of the watercourses, indiscriminate dumping of solid waste, changing the alignment of the watercourses, obstructions due to utilities and such other reasons, both on upstream of Highway and downstream too. As regards WC 7 to WC 16 the carrying capacity is so far unaffected on upstream of Ghodbundar Road (undeveloped area) but due to inadequate cross drainage and few of the above reasons, it is reduced in the downstream of Ghodbundar Road (developed area). As regards watercourses in Kalwa (WC17 to WC21), the natural carrying capacities on upstream of KalwaMumbra road appear to have remained unaffected but downstream the same have been totally affected due to few of the above reasons. The carrying capacities of watercourses in Mumbra, (WC22 to WC25), appear to have been affected due to inadequate cross drainage arrangements along Mumbra-Panvel road and few of the above reasons. The initial natural carrying capacities of all the watercourses in the hilly portion of TMC have not been maintained. The main reason is disregard to the hydraulics of the watercourses while developing the TMC areas in last many years. Obviously, after the deluge of July 2005 there is a need to re-design the cross sections of all the watercourses for revised values of the storm frequencies. In this context the TMC has appointed consultants to fix up design frequencies and redesign the roadside drains, small watercourses and major watercourses and work out revised carrying capacities for implementation of Integrated Nalla Development Project. 4.4 OBSTRUCTIONS 4.4.1Utilities The utilities such as telephone cables, electric cables are laid underground, many times passing through the watercourses causing severe obstruction to the flows. In many cases, even TMC water supply lines are laid in across the storm water drains which cause not only obstruction to the flow but also pose a threat of contamination of drinking water. The pileup of utilities becomes stumbling block in the watercourses (Ann-II Page 91) and once the utilities are laid down in watercourses, they are seldom removed even after they become non- functional or of no use. 4.4.2Structures Structures on the covered watercourses on both or either banks, is a common feature in TMC areas. These are not only hutments but also G+4 buildings with permanent constructions. In a few cases there are structures in the watercourse itself. The watercourses become inaccessible for machine cleaning because of the structures on the banks. Many times
Project by : Hariyali, Thane, Sponsored By : MMREIS

18

CHAPTER 4 : STORM WATER DRAINAGE SYSTEM

developers divert the watercourses for their convenience which also obstructs the flow of water. 4.4.3Dumping of solid waste The residents, shopkeepers and industrial units in the vicinity of watercourses daily dump plastics and solid waste into the watercourse (Ann-II Page 88). The floating population such as pedestrians, vehicle riders, hawkers, families visiting gardens, parks, lakes etc. throw plastic raps of eatables, plastic cups, thalis etc. into so called Nallas. 4.4.4Limitation due to esturian mechanism Major watercourses are either directly meeting the Thane Creek/Ulhas Creek/Ulhas River or let out in the open fields near such Creek/River. Both the creeks join Arabian Sea and the tidal variations in the sea affect the creeks and the watercourses. If the high tide coincides with the high intensity of rainfall with long duration, the tidal flows from Arabian sea into Thane/Ulhas Creeks result into backwater curve in considerable portion of the watercourses. The effect of this phenomenon is resultant rise in the water levels in a substantial portion of land adjoining the creek. This obviously results in the creation of water logging spots along watercourses. 4.5 IDENTIFIED REPETITIVE WATER LOGGING SPOTS Hariyali has identified 75 repetitive water logging spots after discussions with the field engineers of TMC and classified them into following categories. Sr. No. 1 2 3 4 5 6 7
Creek Vicinity Nalla Vicinity Low Lying Area

Category

Number of water logging spots


17 29

Forest Boundary Slum Area In the vicinity of normal or High rise Buildings. Water logging spots with less severity

2 11 5 1 10

Total

75

Thus about 2/3rd of the water logging spots are in the vicinity of creeks/watercourse. It is however surprising to note that as much as 1/6th of the water logging spots exist near forest boundaries, mainly because of reduction in the carrying capacity of the watercourses as explained in Para 4.3 above.

Project by : Hariyali, Thane, Sponsored By : MMREIS

19

CHAPTER 4 : STORM WATER DRAINAGE SYSTEM

4.6

INTER-CONNECTION WITH SEWERAGE The phenomenon of letting out the drainage lines into the watercourses in slum areas exists. Even in sewered areas, many overflow connections from sewer lines have been made into the watercourses. While the sewage & sullage flowing in the Watercourses may not alone obstruct the flow of storm water during monsoon being a very small quantity compared to the runoff, it certainly causes back flow from watercourses into house drainage system. In addition, it creates hurdle in manual cleaning of watercourses.

4.7

STORM WATER DRAINAGE PLAN OF TMC As indicated in the City Development Plan, TMC has prepared in the year 2005 an Integrated Nalla Development Project (INDP) costing over Rs.270 crores, to be completed in three phases. In phase I TMC proposes to take a review of all watercourses to find out the adequacy of their carrying capacity with reference to runoff and catchment area, take remedial measures and repair works and to consider cost benefit analysis. Phase II will include drawing of suitable hydraulic and structural designs and appropriate construction methodology with reference to the intensity of rainfall and decided storm frequency. The implementation of the construction phase of the project will start simultaneously. Phase III consists of periodic site visits and consideration for stability certificates. TMC has already approved following consultants for detailing the above program. a] Dalal, Matt, Macdonald for Mumbra area. b] M/s Shah Technical consultants for Kalwa area. c] M/s Consulting Engineering Services for Thane city. The entire project is expected to be completed within next 4 years. As envisaged in INDP, the resultant outcome of the project will be removal of encroachments and utilities and consequent reduct on in water logging. The INDP also envisages, i a] provision of holding ponds in specific areas, providing flap gates near the creek; and b] arresting storm water run-off in the hilly areas with proper diversion *******

Project by : Hariyali, Thane, Sponsored By : MMREIS

20

CHAPTER 5 : NATURE AND CAUSES OF REPETITIVE WATER LOGGING IN TMC AREA

CHAPTER 5 NATURE & CAUSES OF REPETITIVE WATER LOGGING IN TMC AREA


5.1 IDENTIFICATION OF WATERCOURSES (WCs) WC 1 to WC 25 : As indicated in paragraph 4.1, there are many major and minor watercourses in TMC area of which 25 major watercourses have been identified and marked by Hariyali on the map (P.51). Brief description of the route of each major WC is given below:WC1.Many small natural watercourses originating in Sanjay Gandhi Udyan/Yeoor hills merge together at different places in Mulund (West) and become a major watercourse, identified as WC 1. It enters Thane (West), Check Naka and after crossing railway line again enters Mulund (East) area. Two repetitive water logging spots in Kopri Vibhag exist between WC 1 & WC 2. WC2.Originating in the hills on west side, this watercourse runs through Kisan Nagar in Wagle Estate area and Teen Hath Naka, runs parellel to the Eastern Express Highway for about 100 meters and crosses railway line. It further passes through Anand Nagar, Check Naka, Thane (East) and meets Thane creek in Mulund area. Five water logging spots have been identified in the vicinity of WC 2. Reasons for water logging are mainly silting, (including boulders), covering about 50% of the depth of watercourse, inadequate capacity of pipe culverts, utilities in the watercourses, etc. It is also observed that because of slums, there is no approach road for machine cleaning of the watercourse. WC3.This originates from Thane (East) railway station. After crossing through railway culverts it meets Thane creek. Two water logging spots are identified in its vicinity. WC4.This starts after box culverts on east side of Eastern Express Highway near Namdev Wadi and meets Thane creek after running through some densely populated area. There is a moderate run off in this watercourse since it does not originate in hills, and there are no water logging spots in its vicinity at present. However, major portion of this watercourse is covered and there are structures on it making it impossible to undertake de-silting operations either manually or by machines. After some years, therefore, the accumulated silt may stop the flow of storm water in this watercourse, if not properly desilted.

Project by : Hariyali, Thane, Sponsored By : MMREIS

21

CHAPTER 5 : NATURE AND CAUSES OF REPETITIVE WATER LOGGING IN TMC AREA

WC5.Originating near Khartan Road where two roadside drains meet, this watercourse is small in length with moderate velocity and its major portion is covered. There are structures on covered portion and also on the banks of the watercourse making it inaccessible for de-silting. The accumulated silt may get filled up to the brink of the watercourse in future causing water logging problems. No identified repetitive water logging spots exist at present, but deluge in 2005 did cause flooding in electronic market near Prabhat Theatre. WC6.Number of tributaries to this watercourse originate on hills on western side and merge into it after Karvalo Nagar. It flows by Ramachandra Nagar 2, Chandan Wadi, Civil hospital, and Yerawada jail compound wall to meet Thane creek. There are 12 identified water logging spots in the vicinity of this watercourse and its tributaries mainly because of structures on or within 10 feet from the watercourses. Silt including boulders, solid waste, etc. and utilities obstruct the flow. The WC 6 has a large catchment area on the hills with steep gradient. The de-silting work is taken up only once before the onset of monsoon. There after such silt and solid waste flowing through the watercourse get deposited when it reaches low lying areas in Junagaon, Sathe Nagar, Karvalo Nagar at the foot of the hills. Also with a low velocity in its further travel, coupled with common causes such as structures, accumulated silt, solid waste obstructing the flow, the low lying areas in Ambedkar Nagar, Uthalsar and Krantinagar get flooded. WC7.Its tributaries originate on hills on the west side and have a vast catchment area. They merge into one another at different locations and a single fairly wide watercourse is formed before reaching J. K. gram area. The slums and structures in Rupadevi Pada on and in close viciity of a tributary of WC 7 near the foot of the hills make it inaccessible for machine cleaning. Silt, solid waste, etc. accumulated in it cause water logging at some locations in Rupadevi Pada. Further down, around Majiwada village, the backwater effect during high tide appears to be causing water logging in the area. WC8.Two major tributaries of this watercourse start from Yeoor hills, one flowing through Kokani Pada, Vartak Nagar, Manpada and another through Kokanipada by Siddhachal towers and Jawahar Nagar. Both merge at Subhashnagar before crossing Ghodbundar road. Two more tributaries originate from the merging of road side drains. The WC 8 thereafter splits into two branches to meet Thane creek. One branch crosses the Eastern Express Highway and also creek road and is affected because of back water during high tide and high run-off. WC9.It starts near Balkum and running by the side of a road, meets Ulhas creek. There is no water logging spot in the vicinity of WC 9.

Project by : Hariyali, Thane, Sponsored By : MMREIS

22

CHAPTER 5 : NATURE AND CAUSES OF REPETITIVE WATER LOGGING IN TMC AREA

WC10.It flows from hills on the west through Wagle Industrial Estate, Manpada and crosses Ghodbundar road and runs through Kalpataru Industrial Estate and then through Kolshet Industrial area to be let out in the open shrubs near Ulhas creek. There are utilities in the watercourse near Ayush Nursing Home but thereafter there is open plot. There is only one flooding spot at Manpada south mainly because of narrow width of watercourse in the vicinity. There is a pipe culvert on the road parellel to Ghodbunder road. Structures on both sides of the watercourse result into the storm water spilling on roads during monsoon. WC11.Originating at Kolshet, this watercourse is small in length and is let out in the shrubs near the Ulhas creek. No water logging spot exists on this watercourse. WC12 & 13. From hills on the west, WC 12 flows through Panchpakhadi, crosses Ghodbunder road and after running for a small length along side of the Ghodhbunder road, it flows through Patlipada to meet Ulhas creek. WC13 is its branch after Patlipada running through open shrubs to the north to meet Ulhas creek. Near Bombay Chemicals on Brahma Complex road, in the vicinity of WC 12 & 13, there is a low lying area with no outlet for water, causing water logging during heavy rainfall. WC14.Starting from west hills near Vanipada, it crosses Ghodbunder road near Suraj Water Park and runs northward by the side of Goodlass Nerolac Paints factory to meet Ulhas creek at Wagh Bill. Two tributaries meet this watercourse: one from hills through reserved forests crosses Ghodbundar road before Ritu Enclave and merges into WC 14 after Kavesar. The other starts near Anandnagar which meets WC14 at Wagh Bill. No repetitive flooding spots exist on WC14 or on its tributaries. WC15.This too starts from hills in the west and flows northward through forest and crosses Ghodbunder road to meet Ulhas creek. Many tributaries flowing from the same hills meet this watercourse on the down side across the Ghodbunder road. Five water logging spots on different tributaries of this watercourse are mainly because of inadequate cross drainage and permanent structures on the tributary (Bhayandar Pada, Owala, Anandnagar & Vadavali ), utilities in the tributary and solid waste dumpings (Anandnagar) and eroded material blocking the watercourse (Vadavali & Anandnagar). WC16.This watercourse is small in length originating in hills and meets Ulhas creek.

Project by : Hariyali, Thane, Sponsored By : MMREIS

23

CHAPTER 5 : NATURE AND CAUSES OF REPETITIVE WATER LOGGING IN TMC AREA

WC17.This watercourse originates from Parsik hills from the South of Thane city and runs through Kalwa to meet Ulhas river. Flowing through Surya Nagar, it is the smallest watercourse andhas no water logging spots. WC18.This starts from the hills adjoining the slow trains track on Central Railway before Kalwa station and runs through Manish Nagar and Shastrinagar to meet the Ulhas river. Flooding spot at Shastrinagar is mainly because of backwater during high tide coupled with high run-off. A low level area in Manish Nagar also gets moderately water logged during heavy showers. WC19.It starts after Parsik Tunnel of fast line of railway track and runs through Mahatma Phule Nagar and Saibaba Nagar to meet Ulhas river. Repetitive but moderate water logging in the slum at Mahatma Phule Nagar was reported by hutment dwellers. There is a Nalla in reverse direction, duly trained to absorb high tide flow mixed with sewage from slums. WC20.From Parsik hills, it crosses railway line after Kalwa station and runs through Jai Bhim Nagar to meet Ulhas river. One location in Jai Bhim Nagar and one at Sea Rock Building get flooded when high tide condition coincides with high run- off. The water logging at New Shivaji Nagar, near Kalwa (East) station occurs apparently because of inadequate railway culvert. WC21.It starts from Parsik hills, crosses railway line and runs through Kharegaon to meet the Ulhas river. After crossing, a small cross section with 90 turn, it runs parallel to the road. The hutment dwellers have reported water logging every year. Also location at Budhaji Patil Marg in Kharegaon gets flooded because of silt and boulders. The area near railway line on Kalwa (East) after Kalwa station has also a water logging location apparently because of inadequate capacity of railway culvert. WC22.It starts from Mumbra hills and through Kausa region meets Ulhas river. Inshanagar, which has an identified flooding spot is a low lying area and is moderately subjected to high tide levels. Added to this problem is an inadequate cross drainage on the by pass highway. WC23, 24.& 25. All the three watercourses start from Mumbra hills and meet Ulahs river. No water logging spot was located in their vicinity. 5.2 FLOODING SITUATION ON 26th JULY 2005. The unprecedented heavy rains pouring continuously on 25th and 26th July, 2005 caused havoc in Thane, Kalwa and Mumbra, as in Mumbai. The watercourses which had already a reduced carrying capacity because of obstructions caused by silt, structures, solid waste, utilities, etc. were overloaded with high run-off from the hills for several hours and all the repetitive water logging spots and many 24

Project by : Hariyali, Thane, Sponsored By : MMREIS

CHAPTER 5 : NATURE AND CAUSES OF REPETITIVE WATER LOGGING IN TMC AREA

more were flooded for hours together. The collapse of structures, trees, etc., into the watercourses aggravated the situation. As many as 32 citizens in TMC area died during the deluge. Hariyali had conducted a survey of residents/shopping complexes/industrial units in TMC area to find out perceptions of the people about the nature, causes and effects of Deluge in July, 2005 and about the preventive measures that could be taken to minimize losses in case such a situation recurs in future. With the help of over 600 NSS students of various colleges in and around Thane, 8274 families having residence or work place in TMC were interviewed. Their responses were recorded in the objective questionnaire prepared for the purpose. About 47% of the families interviewed reported flooding in their locality and many of them had no electricity and no communication facility for two days. Nearly 32% of the respondents had no water supply on 25th & 26th July, 2005. Most of the affected respondents mentioned that apart from usual rains, failure of the drainage system was a major cause of flooding in their locality. As reported by the respondents, obstructions to flow of water were caused by garbage dumping, plastic menace, debris and structures in the watercourses. The respondents staying/working in the vicinity of Thane creek and Ulahs creek also gave reclamation of the creeks and constructions on such reclaimed land as major reasons for flooding. In Kausa area of Mumbra, the students and teachers in one college on the hill got stuck up in the college for 48 hours because of waist-deep water all round the college. The worst affected areas were Kausa, Mumbra, Talaopali, Jambhli Naka, Majiwada, Owala, Balkum, Saket, Rupadevi pada. Sathenagar and surrounding area in Railadevi Prabhag, Mahatma Phule Nagar at Kalwa, etc. Major findings of the survey in this connection are reported in Annexure I. 5.3 CAUSES OF REPETITIVE WATER LOGGING 5.3.1Identified water logging spots As indicated in paragraph 4.5 the water logging spots have been broadly classified on the basis of their proximity to the creek, to the watercourses or forest boundaries or on the basis of structures in the area such as slums or normal/high buildings. This is only a broad classification made to facilitate analysis and the categories are not mutually exclusive. 5.3.2Causes for Identified water logging spots The reasons for water logging enumerated under columns of the statement on page no 37 to 46 are summarized below. 5.3.2.1Area in the creek vicinity a] Development levels are less than the highest high tide level of 1.9m (GTS). The area, therefore, gets affected due to back water

Project by : Hariyali, Thane, Sponsored By : MMREIS

25

CHAPTER 5 : NATURE AND CAUSES OF REPETITIVE WATER LOGGING IN TMC AREA

levels in the watercourses joining the creek. (Examples : Saket, Vrindavan, Rabodi-Koliwada, Krantinagar, Majiwada village. Chendani Koliwada in Thane(East), Shastrinagar-Kalwa, Bhimnagar in Kalwa, Mahatma Fule Nagar in Kalwa, etc.) b] Unauthorized constructions in CRZ-2 areas. (Diva Dativali & other areas) c] In many cases the watercourses have become narrow in the down stream because of authorized or unauthorized structures (including multi-storied buildings) or deliberately narrowing of watercourse by developers. The high run-off from the hills flowing in relatively wider watercourse on the upstream is subjected to quite inadequate carrying capacity of narrower watercourse on the downstream, causing overflow particularly in low lying area. d] Inadequate cross sections of watercourses, inadequate cross drainage and silting of cross drains. (K.Villa, Khartan Road, etc.) 5.3.2.2Area in the vicinity of Forest Boundary a] The velocity of natural watercourse flowing from the hills during rainy season gets reduced when it reaches relatively plain area. It is observed that at the foot of the hills there are structures within 6 to 8 feet of both sides of watercourse spread over considerable length, making it inaccessible for machine cleaning. Even manually it is difficult to lift big boulders and carry them along the watercourses for de-silting. The accumulated silt, boulders and solid waste in watercourses (sometimes covering over 50% of its cross section) aggravate the situation during monsoon. When fresh load of boulders and silt is brought by the water current, the water overflows in the nearby areas. (Road no.22, Ambewadi Market, Rupadevi Pada, Vasant Vihar Circle, Vadavli, Ovala etc.) b] Solid waste and plastics are dumped by people residing in the close vicinity of watercourse and sullage flowing in the watercourse make manual cleaning still difficult. c] The utilities in the watercourse cause accumulation of silt, plastics and solid waste, further restricting the flow (Anandnagar). 5.3.2.3Area in the vicinity of watercourses a] Encroachment of structures:-

Project by : Hariyali, Thane, Sponsored By : MMREIS

26

CHAPTER 5 : NATURE AND CAUSES OF REPETITIVE WATER LOGGING IN TMC AREA

In the densely populated area, there are structures including slums and G + 4 buildings with rewa projections on the banks of watercourse and hotels, school buildings, commercial complexes etc. on the covered watercourse. This makes desilting extremely difficult (Ram Maruti Road, Anand NagarKopari, Teen hath Naka, Mental Hospital, Raghunath Nagar, Kausa & Kalwa). In some cases there are structures in the watercourse itself (Phule Nagar) (Ann-II Page 88). b] Utilities in the watercourses obstruct the flow (Srinagar, Bradma Company, Teen Hath Naka, Mental Hospital, Raghunath Nagar, SBI Circle in Wagle Estate, Kausa) (AnnII Page 91). c] Inadequate capacity of Railway culverts:The size of Railway culverts constructed many years before has not been increased to meet the needs of the high co-efficient of run-offs of the growing city. This causes water logging mainly in the areas surrounding watercourses in Thane East (Downside of Kopari, Anand Talkies, Chendani Koliwada). d] Inadequate carrying capacity and skewed alignment (Road No.34, TMT depot in Railadevi Prabhag). e] Inadequate cross-drainage, inadequate culverts (Kamgar Hospital, Bradma Company, Runwal Junction in Vartaknagar, etc.). f] Dumping of solid wastes by people (Ann-II Page 88). g] Watercourses covered by concrete footpaths making de-silting difficult (About 80% WC 4 is covered by footpath/structures). 5.3.2.4Water logging spots falling in slum areas Major reasons for water logging in this area are structures on the banks of watercourse making de-silting extremely difficult. Moreover, absence of facilities for disposal of solid wastes in slum area results in wholesale dumping of such waste in the watercourses. 5.3.2.5Water logging spots falling in the area of multi-storied buildings : Apart from the common reason of obstructions to the flow such as utilities in the watercourse and solid waste dumping by people, a specific cause observed under this category is narrowing and turning the watercourse 90 or so by the developer for his convenience, and also construction of compound wall, concrete

Project by : Hariyali, Thane, Sponsored By : MMREIS

27

CHAPTER 5 : NATURE AND CAUSES OF REPETITIVE WATER LOGGING IN TMC AREA

parking area or concrete play ground of school etc. on the watercourse (Tarangan, Shubharambh Society on WC 10, M H High school compound wall and its play ground, etc.). 5.3.2.6Water logging spots in low lying area Some saucer type low lying developed areas with higher level of roads face the problem of water logging during heavy rains every year because there is no proper outlet for water. (Krantinagar in Uthalsar Prabhag, Vitava area near bridge, Rupadevi Pada, Ambewadi Market, Nalpada in Vartak Nagar, Patlipada (North), Bombay Chemicals and Brahmand Complex in Majiwada, Manishanagar at Kalwa, Inshanagar at Mumbra.) 5.4 PICTORIAL GLIMPSES OF CAUSES OF WATER LOGGING (OBSTRUCTION IN THE WATERCOURSES) 5.4.1BOULDERS AND ROCKS ENTERING INTO THE WATERCOURSES AT THE ORIGIN

5.4.2UTILITIES P ASSING THROUGH, DUMPING OF GARBAGE, PLASTIC WASTE, ETC.

Project by : Hariyali, Thane, Sponsored By : MMREIS

28

CHAPTER 5 : NATURE AND CAUSES OF REPETITIVE WATER LOGGING IN TMC AREA

5.4.3HUTMENT COLONIES, UNAUTHORIZED PUCCA CONSTRUCTION ACROSS AND OVER THE WATERCOURSES

Project by : Hariyali, Thane, Sponsored By : MMREIS

29

CHAPTER 5 : NATURE AND CAUSES OF REPETITIVE WATER LOGGING IN TMC AREA

5.4.4UNAUTHORIZED CONSTRUCTIONS IN CRZ AREA, DUMPING IN THE CREEK AND DESTRUCTION OF MANGROVES

5.4.5UNNATURAL NARROWING DOWN OF WATERCOURSES ACROSS THE RUN-OFF

Project by : Hariyali, Thane, Sponsored By : MMREIS

30

CHAPTER 5 : NATURE AND CAUSES OF REPETITIVE WATER LOGGING IN TMC AREA

5.4.6CHOKING OF CULVERTS, RUN-OFF AREA, UNTRAINED NALLAS, ETC.

Project by : Hariyali, Thane, Sponsored By : MMREIS

31

CHAPTER 5 : NATURE AND CAUSES OF REPETITIVE WATER LOGGING IN TMC AREA

5.4.7MULTIPLE OBSTRUCTIONS

*******

Project by : Hariyali, Thane, Sponsored By : MMREIS

32

CHAPTER 6 : TECHNICAL ANALYSIS

CHAPTER 6 TECHNICAL ANALYSIS


6.1 DESIGN CRITERIA Rational method for calculating quantity of run off from the rainfall is as follows: Q = C x I x A Where Q C I A - is the flow in cumecs. - is the coefficient of run off. - is the intensity of rain fall in m/sec. - is the area to be drained in sq. m.

The magnitude of C may be as per CPHEEO manual. The I am function of travel time/duration of storm/frequency of occurrence. It is practical to adopt different intensities for roadside drains, small watercourses and major watercourses. The contribution time of 10 minutes, 20 minutes and 30 minutes respectively can also be adopted. Though CPHEEO manual suggests frequency of occurrence twice in a year, the same needs revision looking to weather changes/global warming, etc. Once in two years/once in 10 years could be the possible alternatives but needs to be related to cost of master storm water drainage plan. The exceptionally rare storm of July 2005 can not become criteria for design. The change from twice in one year to once in 10 years could lead to 50% more cost of the master plan. Intensity/duration frequency curve appears to have been considered by the consultants working for Thane Municipal Corporation. Generally 50 mm for one hour appear to have been adopted till recently. However, each catchment is subjected to various rainfall intensities and duration curve. The larger catchment having higher time of concentration results in severe condition for long duration even with low intensity of rainfall. Small catchment with high intensity and long duration are also quite critical. The catchment should be combined with tidal surges. This study may be carried out by TMC in detail with Geographical modeling, if necessary. Necessary data for the purpose may have to be collected and compiled by TMC. 6.2 USE OF DIFFERENT MODELS The data referred to above can be used to develop and calibrate hydrological catchment models to simulate run-off from rainfall, computational hydraulic river model to simulate build up of flow and its entry into micro drainage system, routing to macro and further on to sea. The use of models can provide a better insight into natural flooding mechanism and enable TMC to think on options for

Project by : Hariyali, Thane, Sponsored By : MMREIS

33

CHAPTER 6 : TECHNICAL ANALYSIS

flood alleviation. The design of the micro level storm water drainage system could be done on a sample basis for selected area for Thane city before considering its extension to other areas. Combination of physically distributed hydrological model including overland flows, unsaturated zone flows, groundwater flows, dynamically coupled with estuarine and creek hydraulic model has been evolved by experts. This will help comparison with traditional flood models. The tidal control and storage principle with respect to tidal gates, pumping requirements and storing capacities should be studied in general and its applicability to Thane city may be worked out in detail. From the technical literature available on the subject, attention is drawn to technical paper, Rain fall analysis for the design of storm water in Bombay by Mr. S.D. Chawathe, et al, which could be used for design intensities. Following formula may be applied for frequency of occurrence range of 5 to 10 year.

I =

( 7606.12 T ) (0.5680) ( t + 101.97 ) (1.4273)

I = intensity of rainfall in mm/hr. T = frequency of occurrence in months t = Concentrate time (duration of storm) in minutes. The calculated intensities for t of 10, 20 & 30 minutes and T of 10 years work out as below : Sr. No. 1. 2. 3. t in minutes 10 20 30 I mm/hr. 137 122 109 Locaion Road side drain Small Watercourse Major Watercourse

Optimization of frequency ( T ) against cost can be worked out by TMC for proper selection of I at different locations. For design and prediction purpose, MIKE URBAN system may be utilized to understand Storm water modeling - flooding water quantity, quality. Evaluating network capacity and bottlenecks. Prediction of local flooding. Hydraulic analysis of open channels, closed conduits and combination system. Storm water network analysis.

Project by : Hariyali, Thane, Sponsored By : MMREIS

34

CHAPTER 6 : TECHNICAL ANALYSIS

Analyse and design detention basins. Fully dynamic modeling of flows in storm water systems with open channels, pipes, streets, etc. Integrated storm water quantity and quality 6.3 DESIGN OF STORMWATER DETENTION The storm water detention facilities are distinguished from retention facilities. In case of retention, the run-off is captured with no release of water into downstream. These structures are envisaged in case of storm water design system. The detention ponds have outlet structures. Such ponds are provided for temporary storage of run-off with peak release rate to downstream which is substantially lower than the detention facility peak inflow rate. The conceptual design parameters involve an inflow run off hydrograph from tributaries to storage facility i.e. detention pond. A properly sized outlet has to be designed for a desired outflow hydrograph. The storage volume is obviously Q inflow minus Q outflow in relation to time and peak as follows.
Figure 1 : Design of Storm Water Definition

In the case of TMC, there is a scope to design these structures by utilizing the bunds constructed by Khar Land Department of Irrigation or elsewhere on similar basis. *******

Project by : Hariyali, Thane, Sponsored By : MMREIS

35

CHAPTER 7 : EFFECTS OF WATER LOGGING IN THE CITY

CHAPTER 7 EFFECTS OF WATER LOGGING IN THANE CITY


7.1 EFFECTS ON INFRASTRUCTURE AND SERVICES 7.1.1Roads The stagnation of flood water causes damage to the roads, and to sub-grade and sub-soil. Water logging and damaged roads are a major cause of increasing accidents during monsoon. 7.1.2Water supply The overflowing ETPs cause mixing of untreated wastewater with water bodies. This also contaminates ground water. Contamination of water increases on account of intermittent water supply and crossing of sewage lines. Shock loads of turbidity and contamination of water result in nonpotable water. 7.1.3Transport Damaged roads and potholes on the roads affect tyres, suspension springs and break liners of vehicles. In case of State transport buses in Thane reduction in milage cover is observed from 40, 000 km per day to 36,000 km per day. Other effects of flooding are increase in operation and maintenance cost, and traffic jams resulting in loss of time and loss of fuel. 7.1.4Electricity supply Infrastructure of electricity supply, mainly substations of electric supply and equipment like transformers, etc., get affected in areas like Saket, Vrindavan, Anandashram, Naupada, K.Villa, Rabodi, Koliwada, Majiwada. There are more cases of short circuit in the water logged area. 7.1.5Education Educational institutes in low lying areas get affected. Damage to furniture and educational equipments results from this water logging. The loss of time in teaching and learning causes rescheduling of the time table. 7.1.6Railways Six culverts below railway tracks at Mumbra, Kalwa and Thane are not enough to carry the runoff even in normal times. Water logging occurs in railway tracks at Mumbra, Kalwa and Kopri. The water logging affects the timings of the trains. It also increases the O & M cost of railway tracks.

Project by : Hariyali, Thane, Sponsored By : MMREIS

36

CHAPTER 7 : EFFECTS OF WATER LOGGING IN THE CITY

7.1.7Communication services Short circuits, damage to cables and water leakages render joints faulty. Leakages in MTNL installations and buildings too are caused by water logging. The telephone land lines and mobile services develop faults and bring down the efficiency. 7.1.8Health Whenever areas witness water logging on a higher scale, there is two-fold increase in the number of patients admitted in the nearby hospitals. Blood banks are put under strain as they have to provide blood in adequate quantity to the increased number of patients. General medical practitioners find it difficult to cope with the task of treating patients. The demand for prescribed medicines and curative medicines in affected localities result in the storage of such medicines. The spread of epidemics such as Dengue, Lepto, Gastro, Malaria occur due to flooding in localities such as Konkanipada. The TMC is required to conduct house to house survey in flood affected areas to treat patients, to take preventive measures and to conduct free medical check up. Consequently, severe strain is felt on health services, both private and public. 7.2 EFFECT ON INDUSTRIES AND SLUMS 7.2.1Industries Services such as transport, electricity, water supply, removing industrial waste are crucial to the efficient working of industry. Since they are affected, industry in turn is affected in the service to the customers. The small scale industries are more affected by water logging because of their resource-constraints. The machinery of small scale industries in low lying areas get submerged during intensive flooding causing loss of production for many days. 7.2.2Slums Slum dwellers constitute a significant source of man power. When they are themselves trapped in adverse circumstances due to water logging, their efficiency to discharge their services to the community is reduced. Water logging affects the services provided to the slum area more than in other places. Landslides, water logging and sinking of the ground, occur in slum areas particularly in Kalwa, Mumbra and Kausa. Deficiencies in construction aggravate this condition. Low lying area results in more water

Project by : Hariyali, Thane, Sponsored By : MMREIS

37

CHAPTER 7 : EFFECTS OF WATER LOGGING IN THE CITY

logging particularly in the slums, which causes damage to huts, hutments and household goods. 7.3 LOSS OF HUMAN & BOVINE LIFE Water logging results in loss of human and bovine life. Poor people having no shelter or rendered shelterless by flood fall victims to naturals furies. Epidemics make their life worse causing loss of human life before medical services reach poor locality. 7.4 ENVIRONMENT AL LOSSES The surrounding in which people have to live under the conditions of water logging lead to lack of hygiene, water pollution, air pollution, disruption in services, and outbreak of various diseases. Insanitary conditions continue for long time. Mosquitoes, flies and water logging go together. 7.5 ECOLOGICAL LOSSES Stormy weather and heavy rains during water logging sometimes result in uprooting of trees. The broken branches increase water logging. Unclean surroundings and pollutants pose a threat to plants and crops. 7.6 SOCIO ECONOMIC LOSSES 7.6.1Social Social relations are disturbed because of failure of communication systems due to irregular electricity supply and transport problems in the wake of water logging depression or boredom may result on account of deprivation of social life Cultural and intellectual quality is affected because of lack of social life. 7.6.2Economic Water logging causes extensive economic losses. As Indicated by the Resource Persons interviewed by the Experts Committee, the estimated losses caused by water logging in various services are as follows : 7.6.2.1The TMC is required to spend about Rs.3.5 to 4 crores annually to control and prevent spreading of diseases in flood prone areas. 7.6.2.2Economic impact of flooding is serious in case of wage earners. 7.6.2.3Water logging results in people spending more on medical services. 7.6.2.4Revenue loss to State Transport amounts to Rs.One lakh per day.

Project by : Hariyali, Thane, Sponsored By : MMREIS

38

CHAPTER 7 : EFFECTS OF WATER LOGGING IN THE CITY

7.6.2.5Operation and maintenance cost of S.T.buses increases by about Rs.Two crores per year. 7.6.2.6Loss of Rs.One crore is estimated for additional fuel for about 3000 trucks in Thane city. 7.6.2.7Repairs and maintenance losses of Rs.10 lakhs per year is borne by MSEB in Thane city. 7.6.2.8Additional maintenance cost of Rs.One and half lakh is incurred by MTNL, Wagale Estate. 7.6.2.9Railways have to spend about Rs.65 lakhs per year for rehabilitation of tracks within TMC area. 7.6.2.10Loss in terms of production by small scale industry amounts to about Rs.10 crores per annum. 7.6.2.11Loss in maintenance of sub-merged machinery in industries is about Rs.2 crore per annum. 7.6.2.12Removal of silt in industrial installations takes about 8 days resulting in loss of Rs.4 crores per year. *******

Project by : Hariyali, Thane, Sponsored By : MMREIS

39

CHAPTER 8 : BASELINE ENVIRONMENT AL STATUS

CHAPTER 8 BASELINE ENVIRONMENTAL STATUS


8.1 WATER POLLUTION Thane is surrounded by the Thane and Ulhas creeks and Ulhas estuary. The city has still 35 rain fed lakes which is a precious ecological gift. The Thane creek is connected to Ulhas estuary in the North through a very narrow connection. The Ulhas estuary consists of riverine, middle portion and seaward zone. It has dense mangroves and mudflats. Release of high amount of untreated sewage, industrial effluents, dumping of solid waste, reclamation and construction activities have caused deterioration in the water quality of Thane and Ulhas creeks and Ulhas river. The level of suspended solids has been increasing. Gradual lowering of salinity in the creek has been taking place. Gross neglect of lakes, sewage ingresses, dumping of solid waste have resulted in near disappearance of some lakes and bad quality of water in others. Thus human activity, eutrification, siltation, sedimentation, contamination, toxicity of the water, salinity, etc. have created ecological problems for Thane city. The TMC has taken steps to monitor quality of existing water bodies for important indicators such as S.S, BOD, pH, DO etc. Similar qualitative aspects of high tide zones like Kolshet, Balkum, Gaimukh, Saket etc. for above indicators have been checked for water bodies and pollution and kept on records. In case of few lakes the quality of water for indicators like DO at different levels, COD, BOD, NO, PO4, etc, has been monitored in a program of bio-remediation. The environmental status of all these water bodies is not satisfactory. A creek conservation program appears to have been mooted by TMC with the help of Enviro Vigil, NEERI, NIO, etc. The issues and indicators being considered are impact of human activity, toxic pollutants, habitat loss and status of DO, BOD, heavy metals, biological quality, fishery, wetlands, birds. The important hydrological aspects and hydraulics of these water bodies, however need to be studied in detail. In a typical configuration of Thane creek, Ulhas creek, Ulhas river and Arabian sea, the Corporations of Thane, Navi Mumbai, KalyanDombivali, Ulhasnagar and few other surrounding councils may have to take up a joint program for reassessing the assimilative capacities of all these water bodies. Help of CWPRS for hydraulic modeling may be taken by them. There is a close relation of the above aspects with the water logging spots identified by Hariyali. During water logging period the dry weather flow of sewage gets mixed with

Project by : Hariyali, Thane, Sponsored By : MMREIS

40

CHAPTER 8 : BASELINE ENVIRONMENT AL STATUS

stagnated waters, Solid waste, floating material including medical waste also get mixed up with stagnated water. The polluted stagnated water finds way into adjoining watercourses and water bodies including lakes. The percolation of stagnated polluted water further causes pollution and contamination of ground water and water supply mains and branches. This obviously creates hygienic problems in the city. 8.2 AIR POLLUTION The concentration of sulphur dioxide, oxides of nitrogen, SPM and RSPM, Amonia, hydrogen sulphides has been found more in industrial area than in residential and commercial area. The TMC has been conducting studies of primary and secondary pollutants. The ambient air quality is also being monitored. The pollutants like SO2, NOX, SPM and RSPM have also been measured and monitored in Thane city. Ammonia, and H2S concentration are also being monitored in TMC area. As regards water logging in Thane city during rainy season it may not cause or add to the air pollution. In fact rains may subside the concentration of SPM etc. However, immediately after the spells of rains the polluted stagnant flood water may add odour and increase RSPM, etc. It further becomes cause of bacterial/virus increase in the air borne SPMS. A detailed study of this effect may be taken up by TMC. The approach could be similar to the studies of air borne particulate matter with microbes near the Sewage Treatment Plant locations. 8.3 SOLID WASTE MANAGEMENT The Thane Municipal Corporation has brought about some improvements in solid waste management such as sweeping of roads in the night, equipping the workers with proper tools and machines/vehicles, arrangement to separate organic from inorganic waste and entrusting the work of composting to an agency. Therefore, Thane was given the Clean City Award. Nevertheless, the city faces the problem of over accumulation of solid waste consisting of organic waste, bio-medical waste, plastic waste, dust and lot of dismantled material. The administration is not in a position to cope up with managing collection, treatment and disposal of solid waste due to inadequate machinery to handle increasing volume of the waste. Added to this is the lack of cooperation from public. Solid waste management is rendered worse by the material swept from roads and garbage thrown by public into road side drains with the resultant silting of the drains. Most of the collected quantity of solid waste is dumped on the dumping ground. The composting plant is out of operation due to complaints by the local
Project by : Hariyali, Thane, Sponsored By : MMREIS

41

CHAPTER 8 : BASELINE ENVIRONMENT AL STATUS

residents. Only about 50% to 60% of the solid waste is bio-degradable. The aerobic process of treatment was used for some time but unfortunately got discontinued. Silver line to this cloud is the bio-medical waste facility operated by an NGO Enviro Vigil. The base line status of solid waste management in Thane city is not up to the mark. During water logging of the spots identified by Hariyali, the poor status of solid waste management aggrevates the pollution of surrounding watercourses and water bodies. Similarly, contamination of ground water and drinking water supply becomes severe during water logging period. 8.4 WETLANDS, MUDFLATS AND MANGROVES Due to nearness of creeks TMC area has been by nature privileged with a good percentage of wetland, mudflats and mangroves as much as 9% of the city area. These lands are presently providing good holding capacities during situations of simultaneous high tides and high run-off. The mangroves which are specialized trees in saline and brakish waters exist in TMC area with good advantages of soil binder, protecting storm water damages and ecologically providing different aquatic life forms. They help controlling pollution of creek. There are two Khar land schemes in TMC area at Kharegaon and Ovala. These have provided good agricultural potential to farmers. Moreover, these projects have created good detention capacity during high flood. Surprisingly, TMC development plan has not been taking expected cognizance of this detention potential for the run-off. The TMC should make use of these lands for providing additional holding capacities by increasing heights of the bunds constructed by Khar land departments under the control of Irrigation Department of GOM. Instead, the absence of recognizing Kharland as no development zone has resulted into allowing construction in Kharland area. This has further affected the very existence of mangroves. It will be helpful to TMC in reducing the repetitive water logging spots in the creek vicinity if above situation is urgently corrected and additional holding capacities are provided in wet lands. 8.5 FOREST The TMC is blessed with more than 30% of its area under forest land with a wide scope for afforestation. Instead, some of the lands have become places for hutments and slums.

Project by : Hariyali, Thane, Sponsored By : MMREIS

42

CHAPTER 8 : BASELINE ENVIRONMENT AL STATUS

The erosion of soil and boulders from the forest land adds lot of siltation in the upstream portion of all the watercourses, though, steep slopes help quickly taking the initial run-off on downstream. The heavy siltation is creating repetitive water logging situation near forest lands. The plantation of trees to reduce soil erosion, providing contour trenches as also geo-fabrics to arrest entry of boulders in watercourses, may have to be taken up on priority basis. 8.6 RECLAMATION Uncontrolled development near the creek with total disregard to the development levels continues unabated in the TMC area. The entry of sullage in marshy lands has already reduced the agricultural areas from 53 sq. km to 30 sq. km in last 20 years. Unlike many other cities in India, the TMC is blessed with diverse ecological flora and fauna of forest as well as wet lands. Though urbanization needs reclamation, it should not be in unplanned manner and with disregard to hydraulics of watercourses and development levels. The repetitive water logging spots in the creek vicinity and also on upstream can be reduced by immediately taking up planned reclamation. 8.7 ROADSIDE TREES There is no visible effect of water logging spots on the road side trees. 8.8 ECOLOGY AND MARINE HABITAT The water logging does not directly affect flora and fauna of the locations. *******

Project by : Hariyali, Thane, Sponsored By : MMREIS

43

CHAPTER 9 : ENVIRONMENTAL MANAGEMENT PLAN (EMP)

CHAPTER 9 ENVIRONMENTAL MANAGEMENT PLAN (EMP)


9.1 PURPOSE OF EMP The EMP suggested in paragraphs 9.2 to 9.16 are actions in general for: a] Preventing or reducing the repetitive water logging in TMC area. b] Mitigation of hardships caused by water logging. The identified water logging spots and the EMP applicable to each such spot have been indicated in the statement enclosed to this Chapter (P to 46). .37 9.2 STORM WATER MANAGEMENT (Action: TMC) 9.2.1The TMC should plan and implement the program of de-silting of all watercourses up to invert level thrice in a year in the months of November, February & May. 9.2.2The program of shifting of utilities may be continued vigorously in respect all the watercourses. 9.2.3The TMC should plan and execute the programs of training of watercourses for improved carrying capacity for frequency of 1 in 10 years with suitable concentration time and duration. 9.2.4Roadside drains should be designed for higher intensity and less duration and the construction thereof should be implemented in a phased manner. 9.2.5A complete storm-water drain inventory with analysis should be maintained for monitoring and revision of the system. 9.2.6Before monsoon every year, a cell may be created at H.O. level to continuously monitor rainfall predictions of meteorological department and this cell should report to the City Eng ineer and the Municipal Commissioner. 9.2.7The TMC should conduct technical studies to find out expected quantum of flood in relation to runoff and high tides in different locations of TMC area. The study reports may be published every year during monsoon. The position at different locations should be monitored. 9.2.8A storm water drainage project should be prepared and implemented in next five years. This will also include demolition of structures in and on the banks watercourses, keeping in view possible rehabilitation of residents and shopping units in such structures.
Project by : Hariyali, Thane, Sponsored By : MMREIS

44

CHAPTER 9 : ENVIRONMENTAL MANAGEMENT PLAN (EMP)

9.2.9The budgetary provision for storm water drainage should to be suitably stepped up for implementing the suggestions made above. 9.3 SOLID WASTE MANAGEMENT (Action: TMC and suitable NGO) 9.3.1The segregation of solid waste into bio-degradable & recyclable wastes should be enforced scrupulously at the level of individual households/shops/units, at collection machinery and at final disposal level. It may be necessary to frame rules for providing penalties for lapses in this regard. 9.3.2At the locations where Ghantagadi can not go for garbage collection, adequate no. of litter bins should be provided and arrangements made to collect the garbage before it overflows. 9.3.3The frequency of transportation of container should be such that dustbin sites are cleared before they start overflowing. 9.3.4All organic/biodegradable waste may be composted by following suitable methods. 9.3.5Domestic hazardous waste, such as, used batteries, containers for chemicals and pesticides, etc, be disposed of by scientific land filling or any other suitable method. 9.3.6TMC should take up community capacity building and awareness program in association with suitable NGOs to nullify entry of any type of solid waste into road side drains and watercourses. 9.3.7With a view to avoiding entry of dung generated by cattleheds into the watercourses, owners should be prevailed upon to treat and produce manure or energy from dung. 9.4 BIO-MEDICAL WASTE (Action : TMC & NGO to be identified by TMC) 9.4.1TMC should plan opening of collection centers at appropriate places, such as hospitals, cluster of clinics, road squares, etc, for bio-medical wastes generated by private clinics, nursing homes and public at large and to plan for its collection and final disposal. 9.4.2TMC should initiate steps to prepare programs to make public aware of the hazards of bio-medical waste and of proper disposal of such waste. 9.4.3TMC should arrange for collection of data regarding generation and disposal of bio-medical waste.

Project by : Hariyali, Thane, Sponsored By : MMREIS

45

CHAPTER 9 : ENVIRONMENTAL MANAGEMENT PLAN (EMP)

9.5

SEWERAGE (Action: TMC) 9.5.1A time-bound program to stop leakages from joints should be worked, prepared out and implemented vigorously. 9.5.2TMC should finalise the sewerage plan for the entire city to avoid entry of sewage in open watercourses and to avoid body connection in sewer lines. The implementation of this plan should be ensured. 9.5.3With due consideration to the assimilative capacities of water bodies and treatment standards of MPCB, a plan for treatment and disposal of sewage should be prepared and implemented in a phased manner. 9.5.4A status report on sewage treatment plan should be prepared and steps should be taken to improve its efficiency.

9.6

WATER SUPPLY (Action: TMC) 9.6.1Priority is given to identify locations of contamination in the water supply distribution system and take preventive measures before monsoon. 9.6.2Identification of leakages in the water mains and distribution systems and their rectification should be attended to on a priority basis. 9.6.3TMC should also take up a program of identifying rusted pipes in the distribution system and prepare a plan for their replacement/rectification in a phased manner. 9.6.4A cell should be created in the Water Department at Head Office to monitor the program of leakage identification and rectification. 9.6.5A communication network for identification and reporting of leakage in the water supply distribution system may be created and published.

9.7

HEALTH (Action: TMC & NGOs/hospitals ) 9.7.1TMC should develop capacity building programs to take preventive measures to control epidemics. Assistance of NGOs, Rotary Clubs, Private doctors, Pathological laboratories etc, should be taken for testing of samples, house to house survey, free medical checkup, etc. 9.7.2Periodic meetings of NGOs, Rotary Clubs, etc, associated with the capacity building programs of Health Department should be convened to monitor programs. 9.7.3A plan for shifting of cattle sheds out of town should be drawn up and implemented.

Project by : Hariyali, Thane, Sponsored By : MMREIS

46

CHAPTER 9 : ENVIRONMENTAL MANAGEMENT PLAN (EMP)

9.8

SLUMS (Action: TMC) 9.8.1. The slum dwellers in and around watercourses, water bodies and on slopes of hills should be rehabilitated in a planned way to minimize losses of lives and structures due to floods and land slides. TMC should take immediate action to prevent further erection of unauthorized structures including slums in and around watercourses and water bodies.

9.8.2.

9.9

RAILWAYS (Action: Central Railway and TMC) 9.9.1. TMC should take a lead in setting up a Standing Committee to establish co-ordination at all levels between Central Railway and TMC for modification and maintenance of all the six railway culvert . s Maintenance of the railway culverts should be done well before monsoon.

9.9.2.

9.10 ROADS (Action: TMC) 9.10.1TMC should identify and design formation levels for all roads in the city. 9.10.2While designing road level, due regard should be given to HFL of all surrounding water bodies instead of only local watercourse in front. 9.10.3The HR Dept. of TMC should convene seminars/conferences of personnel in different departments and of architects, engineers, etc, concerned with construction of roads and buildings so as to update their knowledge and for mutual exchange of knowledge and information. 9.10.4The efforts to maximize the concrete roads should be continued. 9.10.5New technologies should be adopted for longer durability of tar roads even in flood prone areas. 9.10.6Rainwater harvesting technique by taking bores in the roadside drains could be used to minimize run-off going to the watercourses. 9.10.7TMC should prepare plan for promptly repairing the potholes even during monsoon, even though such repairs are of temporary nature. 9.11 TRANSPORT (Action : Maharashtra State Transport Corporation, Thane and Thane Municipal Transport Corporation.) 9.11.1Available modern technology should be adopted so as to minimize damages to the tyers, suspension springs, break liners, etc, during flooding.

Project by : Hariyali, Thane, Sponsored By : MMREIS

47

CHAPTER 9 : ENVIRONMENTAL MANAGEMENT PLAN (EMP)

9.11.2A plan of upkeep and maintenance of the entire fleet of vehicles before onset of monsoon should be drawn and implemented with a view to keeping efficiency of vehicles at high leve during monsoon. l 9.12 ELECTRIC SUPPL (Action: MSEDCL) Y: 9.12.1MSEDCL has been raising the levels of sub - stations in flood prone areas. This should be continued. 9.12.2Measures should be taken to prevent/minimize damage to pillars, cables, joints, etc. in floods prone areas. 9.13 TELEPHONE SERVICES (Action: MTNL) 9.13.1MTNL should raise the height of pillars above HFL in/and around water logging spots. 9.13.2The MTNL has been using modern technology for upgradation of cable joints to avoid leakages and to minimize disruption in services during flooding. This should be continued. 9.14 WATER BODIES ( Action : TMC ) 9.14.1TMC should study the possibility of interlinking all lakes in Thane city for flood assimilation as well as for improvement in groundwater level. 9.14.2A study of the extent of pollution, dilution, advection, convection in case of estuaries and dilution during runoff in lakes should be carried out. 9.14.3Catchment area development to avoid pollution of flooding in water bodies and lakes should be taken up. 9.15 DEVELOPMENT PLAN ( Action : TMC ) 9.15.1. Any new development in TMC area should be 0.6 m (2 feet) above HFL in relation to surrounding water bodies. Any development level of the plot should not be less than 4.9 m (GTS) 9.15.2. Any new development in TMC falling between design width of once in 2 years and once in 10 years should be free of any structures. Similarly, any development in area with design width of once in 10 years and once in 100 years should be provided with stilt arrangement. 9.15.3. In case of existing structures affected by backwater due to once in 100 years intensity, the developers/housing societies may be persuaded to convert the ground floor into stilt area.

Project by : Hariyali, Thane, Sponsored By : MMREIS

48

CHAPTER 9 : ENVIRONMENTAL MANAGEMENT PLAN (EMP)

9.15.4. TMC should prepare a plan for showing minimum level of reclamation and this plan should be enforced. No piecemeal reclamation should be resorted to. 9.15.5. Some area in open spaces should be earmarked to act as holding capacities for abnormal storm runoff and ingress of seawater. 9.15.6. For conservation of mangroves to work as buffers and for hydraulic assimilation, the TMC should ensure that wet land and mangroves are protected. 9.15.7. Growth of unauthorized habitats in violation of civic regulations is strictly prohibited. 9.15.8. Appropriate steps are taken for identifying and acquiring land for dumping and disposal of civic garbage taking into consideration the needs of at least next 25 years. 9.15.9. A well planned program for plantation of mangroves should be taken up by TMC. 9.15.10. Plantation of trees in the forest area and provision of suitable contour trenches should be taken up to reduce soil erosion and entry of boulders into the watercourses. 9.15.11. Provision of geo-fabrics to stop entry of boulders into the watercourses should also be considered. 9.16 RISK AND INSURANCE ( Action TMC, Insurance Companies ). 9.16.1Data pertaining to structures at risk due to water logging may be compiled and a risk management plan may be evolved. 9.16.2Study of risk assessment factors such as, hazards identification, hazards analysis, consequence analysis, risk determination, risk evaluation may be carried out. 9.16.3Insurance companies may consider evolving deluge risk insurance. While private people are expected to take such insurance, TMC may consider subsidizing the premium of deluge insurance policies. 9.17 EMP suggested for identified water logging spots are shown by indicating relevant paragraph numbers in the enclosed tables: (P.37 to 46)

*******

Project by : Hariyali, Thane, Sponsored By : MMREIS

49

CHAPTER 9 : ENVIRONMENTAL MANAGEMENT PLAN (EMP)

IDENTIFIED WATER LOGGING SPOTS IN TMC AREA SUGGESTED EMPs and ESs
Sr. No. IDENTIFICATION NO. I(15) CAUSES OF LOCATION & WATER PRABHAG LOGGING UTHALSAR 1. Developments levels of this area are mostly less than 3.5 m PRABHAG (G.T.S.) SAKET 2. Water logging of 6 during high tide and heavy rainfall. EMP main parameters for mitigation (Paragraph no.) 9. 15. 1. and 10.6 9. 15. 6. Engineering solutions (Paragraph No.) 10.4

1. & 2.

I(52)

BALKUM PIPE 3. The run-off from road side is let LINE out in pipe drain at a invert lower than highest high tide. UTHALSAR PRABHAG. 1. Total area is below the highest high tide.

9.15.3 10.6 9. 15. 9.

3.

I (2)

VRINDAVAN 2. The developmental levels are SOCIETY. extremely on lower side. 1. Low lying area and extreme negligence by developer to bring development levels above high tide. 2. Surrounded by two Nallas subjected to tidal back water during heavy rainfall. 1. Inadequate cross section of near by Nalla 2. Encroachment by slums in the watercourse. 1. Back water of high tide during rainfall. 2. Low lying area & encroachment by slums. 3. The compound wall of central jail has reduced cross section of Nalla. 4. During high tide due to less carrying capacity & skew alignment, water spills out.

I (1)

UTHALSAR PRABHAG SHRIRANG SOCIETY

9. 15. 9. 9. 3. 6. & 9. 4. 2. 9. 3. 6. & 9. 4. 2.

10.1 10.6

I (20)

UTHALSAR PRABHAG K. VILLA

10.1 10.8

6.

I (21)

UTHALSAR PRABHAG, RABODI, KOLI WADA, KRANTI NAGAR

9. 3. 6. 10.1 9. 15. 7. & 9. 15. 3. 9. 8. 1. 9. 8. 2. 10.8

Project by : Hariyali, Thane, Sponsored By : MMREIS

50

CHAPTER 9 : ENVIRONMENTAL MANAGEMENT PLAN (EMP)

IDENTIFIED WATER LOGGING SPOTS IN TMC AREA SUGGESTED EMPs and ESs
Sr. No. IDENTIFICATION NO. LOCATION & PRABHAG CAUSES OF WATER LOGGING EMP main parameters for mitigation (Paragraph no.) 9. 15. 1. & 9. 15. 6 1. Saucer type low lying area with higher level of roads. 2. Low carrying capacity of Nalla. 3. Encroachment by Hotel & school building. 4. Desilting becomes difficult because of encroachment. 5. Water logging occurs for about 2 to 4 hours. NAUPADA PRABHAG BRAHMAN SOCIETY. II(16) I (5) 11. I (4) & 12. NAUPADA PRABHAG, KOPARI, DOWN SIDE 1. Proximity to railway tracks with inadequate capacity of railway culvert. 2. Desilting of culvert is not properly done. 9. 2. 1. 9. 2. 3. & 9. 2. 4. 10.6 Engineering solutions (Paragraph No.)

7.

I (22)

UTHALSAR PRABHAG MAJIWADA VILLAGE

Same as I (15), SAKET.

10.4

8.

II (6)

NAUPADA PRABHAG RAM MARUTI ROAD.

9. 15. 3.

10.1

9. & 10.

II (27)

9. 9. 1. & 9. 9. 2.

10.1 10.4

ANANDASHRAM 3. 1 to 2 hours water logging occur. NAUPADA PRABHAG, KHARTAN ROAD, CHENDANI KOLIWADA

1. Subjected to high tide. 2. Cross drainage culvert inadequate. 3. Less carrying capacity of cross
drainage & Nalla. 9. 3. 6. & 9. 4. 2 10.1

4. Encroachment hampering flow


conditions. Inadequate capacity of railway culvert.

13.

II (24)

9. 9. 1. & 9. 9. 2.

10.1 10.4

Project by : Hariyali, Thane, Sponsored By : MMREIS

51

CHAPTER 9 : ENVIRONMENTAL MANAGEMENT PLAN (EMP)

IDENTIFIED WATER LOGGING SPOTS IN TMC AREA SUGGESTED EMPs and ESs
Sr. IDENTI- LOCATION & No. FICATION PRABHAG NO. CAUSES OF WATER LOGGING EMP main Engineerin parameter g solutions s for (Paragraph mitigation No.) (Paragraph no.) 9. 2. 3. & 9. 9. 1. 9. 9. 2. 10.1

14.

I (11)

2. Affected by back water of creek. KOLIWADA, THANE (E) 3. Water from railway tracks leading to Hariyali tank spreads (CHENDANI) in low lying area.

KOPARI PRABHAG

1. Low level area.

15. & 16.

I (19) II (3) 10.1

17.

II (23)

KOPARI PRABHAG ANAND TALKIES

1. Inadequate capacity of culvert. 2. Affected by watercourse WC 1


& WC 2.

9. 3. 1 9. 3. 6. 9. 4. 2. & 9. 9. 1. 9. 9. 2. 9. 3. 1. & 9. 3. 6. 9. 4. 2. 10.1 10.1

3. Inadequate carrying capacity of


Nalla.

4. Skewed alignment of Railway


culvert & TMC Nalla. NAUPADA PRABHAG ANAND NAGAR RAILADEVI PRABHAG, ROAD NO.21 20. To 22. II (30) IV (48) IV (47) RAILADEVI 1. Due to slums Nalla has been PRABHAG diverted. ROAD No34, 2. Inadequate carrying capacity of watercourse. RAM NAGAR, HANUMAN 3. Silting due to boulders and soil erosion. NAGAR.

1. Improper level of highway


culvert.

18.

II (61)

2. Affected by WC 1 & WC 2 with


inadequate carrying capacity.

3. Encroachment by slums.
The road side drains are not provided & designed.

19.

II (29)

9. 2. 4. 9. 3. 6.

10.2

10.1 9. 4. 2 & 9. 8. 1 9.15.11

Project by : Hariyali, Thane, Sponsored By : MMREIS

52

CHAPTER 9 : ENVIRONMENTAL MANAGEMENT PLAN (EMP)

IDENTIFIED WATER LOGGING SPOTS IN TMC AREA SUGGESTED EMPs and ESs
Sr. IDENTI- LOCATION & No. FICATION PRABHAG NO. CAUSES OF WATER LOGGING EMP main Engineeri parameters ng for solutions mitigation (Paragra (Paragraph ph No.) no.) 9. 3. 6. 9. 4. 2 & 9. 8. 1 RAILADEVI PRABHAG RUPADEVI PADA (1) Low lying area. (2) The drop between invert level of Nalla & incoming drain is not adequate. (3) Encroachment and utilities have reduced carrying capacity of Nalla. (4) Silting due to eroded material from hills. (5) Dumping of solid waste. RAILADEVI PRABHAG KAMGAR HOSPITAL V (42) 26. RAILADEVI PRABHAG, INDIRANAG AR(Near Road No.22) (1) Proper cross drainage in the form of culvert is not constructed. (2) Pipe culvert wrongly provided improper invert level compared to Nalla invert level. (1) Silting of Nalla due to soil erosion. (2) Solid waste is dumped by the people in the Nalla. (3) Inadequate cross drainage and pipes. (1) Affected due to development of slums e.g. Ajinkya Tara slums. (2) The invert level of cross drainage and watercourse are reverse. (1) Inadequate capacity of culvert. (2) Flow affected due to utilities. Nil 10.1 (1) To avoid siltation & erosion grass cultivation in forest area is necessary. 9.2.2, 9.8.1, 9.3.6, 9.4.2 & 9.3.2. 10.1

23.

IV (31)

RAILADEVI PRABHAG, TMT DEPOT

(1) SAME AS ABOVE

24.

VI (44)

10.1

25.

II (40)

9. 3. 2. 9. 3. 6. 9. 4. 2.

27. V (43) & II (35) 28.

RAILADEVI PRABHAG SATHE NAGAR Road No.22 RAILADEVI PRABHAG, BRADMA COMPANY

9. 3. 2. 9. 3. 6. & 9. 4. 2.

10.2

29.

II (28)

9. 2. 2.

10.1

Project by : Hariyali, Thane, Sponsored By : MMREIS

53

CHAPTER 9 : ENVIRONMENTAL MANAGEMENT PLAN (EMP)

IDENTIFIED WATER LOGGING SPOTS IN TMC AREA SUGGESTED EMPs and ESs
SR. IDENTI- LOCATION & NO. FICATION PRABHAG NO. CAUSES OF WATER LOGGING EMP main Engineeri parameters ng for solutions mitigation (Paragra (Paragraph ph No.) no.) Nil 10.1

30.

II (67)

RAILADEVI PRABHAG, AMBEWADI MARKET RAILADEVI PRABHAG, SAMARTH NAGAR WAGALE ESTATE PRABHAG, TEEN HATH NAKA, MENTAL HOSPITAL WAGALE ESTATE PRABHAG,

(1) Area is totally saucer like area. (2) Difficult to remove the water. (1) Inadequate capacity of culvert.

31.

II (68)

Nil

10.1

32.

II (33)

(1) Affected due to nearness of Nalla WC 2. (2) Road side drains are inadequate. (3) Utilities are hampering the flow. (4) Silting of Nalla. (1) Low lying area. (2) Affected due to encroachment by slums. (3) Unauthorized construction has reduced carrying capacity resulting in narrowing in the Nalla. (4) Affected due to watercourse WC 2. (5) No road side gutter

9. 2. 2. 9. 2. 4. & 9. 2. 1.

10.2

33 & 34.

II (34) II (37)

9.3.2. 9.3.6. 9.8.1. & 9.2.4

10.1

RAGHUNATH NAGAR

35.

II (36)

WAGALE ESTATE PRABHAG, SBI CIRCLE WITH ROAD NO. 22. VARTAK NAGAR PRABHAG,

(1) Affected due to watercourse WC 2. (2) Flow affected due to utilities. (3) Soil erosion from hills results silting. (1) Inadequate capacity of culvert. (2) Nalla having narrow width on

9. 2. 2. 9.15.10

10.5

36.

IV (53)

Nil

10.1

Project by : Hariyali, Thane, Sponsored By : MMREIS

54

CHAPTER 9 : ENVIRONMENTAL MANAGEMENT PLAN (EMP)

MANPADA SOUTH

down stream result back water.

Project by : Hariyali, Thane, Sponsored By : MMREIS

55

CHAPTER 9 : ENVIRONMENTAL MANAGEMENT PLAN (EMP)

IDENTIFIED WATER LOGGING SPOTS IN TMC AREA SUGGESTED EMPs and ESs
SR. IDENTI- LOCATION & NO. FICATION PRABHAG NO. CAUSES OF WATER LOGGING EMP main Engineeri parameters ng for solutions mitigation (Paragra (Paragraph ph No.) no.) 9.15.10 9.15.11 10.1

37.

IV (62)

VARTAK NAGAR PRABHAG VASANT VIHAR CIRCLE

(1) Inadequate width of Nalla. (2) Erosion of soil and boulders from hills affect the flow.

38.

II (32)

VARTAK NAGAR PRABHAG MAJIWAD PAPER PRODUCTS

(1) Solid waste dumping in the Nalla by surrounding slum Locality. 9. 3. 2 9. 3. 6. & 9. 4. 2. (1) Low lying area. (2) Inadequate capacity due to encroachment affecting width of Nalla. (3) Slum area & solid waste disposal create problems in smooth flow. (1) Low lying area. (2) Solid waste dumped by people in slum area. 9. 3. 6. 9. 3. 2. & 9. 4. 2. 9. 8. 1. 9. 3. 2. 9. 3. 6. & 9. 4. 2. 9. 8. 1. (1) Improper capacity of culvert. (2) Alignment of Nalla is skew. Nil 10.1 10.1 10.1

39.

IV(45)

VARTAK NAGAR PRABHAG MAHATMA PHULE NAGAR. VARTAK NAGAR PRABHAG, HARDAS NAGAR VARTAK NAGAR PRABHAG, RUNWAL JUNCTION KORAS ROAD VARTAK NAGAR PRABHAG, SAMBHAJI

40.

II (63)

41.

II (64)

(1) Low lying area. (2) Solid waste dumping by people in slum.

9. 8. 1. 9. 3. 2. & 9. 3. 6. 10.1

42.

III (65)

Project by : Hariyali, Thane, Sponsored By : MMREIS

56

CHAPTER 9 : ENVIRONMENTAL MANAGEMENT PLAN (EMP)

NAGAR

Project by : Hariyali, Thane, Sponsored By : MMREIS

57

CHAPTER 9 : ENVIRONMENTAL MANAGEMENT PLAN (EMP)

IDENTIFIED WATER LOGGING SPOTS IN TMC AREA SUGGESTED EMPs and ESs
SR. IDENTI- LOCATION & NO. FICATION PRABHAG NO. 43. II (66) VARTAK NAGAR PRABHAG, NALPADA (1) Inadequate cross drainage. MAJIWADA 44. & IV (60) 45. KAJUPADA ( outside TMC) IV (59) PRABHAG BHAYANDARPADA, (2) Upstream of Ghodbundar road Nalla affected by structures of permanent nature on the Nalla. (1) To compel occupants of normal (G + 2 or more) buildings to treat the waste or to reuse it within their compound till regular sewerage system is provided by TMC. (2) 9.2.2., 9.8.1.,9. 8. 2. (1) Inadequate cross drainage. 46. IV(57) MAJIWADA PRABHAG ANAD NAGAR (2) Affected due to slum area. (3) Eroded material cause silting. (4) Solid waste dumping by surrounding people. (5) Affected flow due to utilities. (6) Upstream affected due to permanent structures on the Nalla. MAJIWADA PRABHAG, OWALA (1) Inadequate cross drainage. (2) Upstream affected due to permanent structures on Nalla. (1) Inadequate side gutter on roads. (2) Eroded material from Takardapada road block the watercourse & side drains. (3) Inadequate cross drainage. As above. 9. 3. 2. 9. 3. 6. 9. 4. 2. 9. 8. 2. 9. 15. 1 to 9.15.3. 9.15.10 10.1 10.8 10.1 10.8 CAUSES OF WATER LOGGING (1) Low lying area. (2) Solid waste dumping by people in slum. EMP main parameters for mitigation (Paragraph no.) 9. 8. 1. 9. 3. 2. & 9. 3. 6. 10.1 Engineering solutions (Paragraph No.)

10.1 10.8

47.

IV (58)

48.

IV (56)

MAJIWADA PRABHAG VADAVALI

As indicated against Sr.No.47

10.1 10.8

Project by : Hariyali, Thane, Sponsored By : MMREIS

58

CHAPTER 9 : ENVIRONMENTAL MANAGEMENT PLAN (EMP)

IDENTIFIED WATER LOGGING SPOTS IN TMC AREA SUGGESTED EMPs and ESs
SR. IDENTI- LOCATION & NO. FICATION PRABHAG NO. 50. II (55) MAJIWADA PRABHAG. BOMBAY CHEMICALS, BRAHMAND COMPLEX ROAD TO DEEPNAGAR MUMBRA & DIWA PRABHAG. RASHID COMPOUND MUMBRA & DIWA PRABHAG, INSHA NAGAR CAUSES OF WATER LOGGING (1) Low laying area. (2) No outlet for easy discharge of run-off. EMP main Engineering parameters for solutions mitigation (Paragraph (Paragraph no.) No.) As indicated against Sr.No.47

10.1

51.

II (69)

(1) Low lying area. (2) Development levels are wrong. (1) Low lying area. (2) Development levels are wrong. (3) Moderately subjected to high tide levels. (4) Cross drainage on by pass highway under construction is not properly designed. (1) Subjected to high tide conditions. (2) People from slum dump solid waste in the Nalla. (1) Low lying area. (2) Subjected to moderate water logging to some extent. (1) Subjected to high tide conditions. (2) People from slum area dump solid waste in Nalla. (1) Railway culvert is inadequate. (2) Silting due to erosion from hills.

9. 15. 1.

10.2

52.

I (70)

9. 15. 1 9. 15. 7. & 9. 8. 1. 9. 8. 2. 9. 3. 2. 9. 3. 6. & 9. 4. 2. 10.6 10.1

53.

I (9)

KALWA PRABHAG SHASTRI NAGAR KALWA PRABHAG, MANISHA NAGAR KALWA PRABHAG, BHIM NAGAR KALWA PRABHAG, NEW SHIWAJI NAGAR KALWA (E)

54.

II (7)

Nil

10.1

9. 3. 2. 9. 3. 6. 9.4.2. & 9.8.1 9. 2. 1 9. 9. 1. & 9. 9. 2. 10.1 10.6

55.

V (49)

56.

II (71)

IDENTIFIED WATER LOGGING SPOTS IN TMC AREA


Project by : Hariyali, Thane, Sponsored By : MMREIS

59

CHAPTER 9 : ENVIRONMENTAL MANAGEMENT PLAN (EMP)

SUGGESTED EMPs and ESs


S IDENTIR.N FICATION O. NO. LOCATION & PRABHAG CAUSES OF WATER LOGGING EMP main Engineeri parameters ng for solutions mitigation (Paragra (Paragraph ph No.) no.) 10.1 9. 2. 1.

57.

I (8)

KALWA PRABHAG, KHAREGAON, BUDHAJI PATIL MARG KALWA PRABHAG Sea ROCK BUILDING KALWA PRABHAG VITAVA BRIDGE KALWA DIWA PRABHAG DIWA DATIVALI & OTHER AREAS.

(1) Inadequate capacity of Nalla. (2) Due to Erosion from hills silting of Nalla.

10.1 Subjected to high tide conditions. (1) Low lying area. (2) Accumulation of silt on the road. (3) Existing bridge below high tide level appears to be low level causeway. (1) All unauthorized construction without consideration to development levels will cause flooding in this area in near future. (2) No regards to CRZ 2 regulations. 9. 2. 1. 10.3 9. 15. 3. 10.6

58.

II (73)

59.

III (74)

60.

I (75)

9. 8. 1. & 9. 8. 2. 10.3

61. & 62.

I (10) I (26)

MUMBRA, KUMBAR KOLIWADA, MUMBRA STATION. ULHAS NAGAR PRABHAG, AMBBEDKAR NAGAR

(1) Railway culverts inadequate. (2) Inadequate cross drainage

10.1 9.9.1 & 9.9.2

63.

V (50)

(1) Low lying area. (2) Solid waste dumping

9.3.1 9.3.2 & 9.3.6

10.1 10.7

Project by : Hariyali, Thane, Sponsored By : MMREIS

60

CHAPTER 9 : ENVIRONMENTAL MANAGEMENT PLAN (EMP)

IDENTIFIED WATER LOGGING SPOTS IN TMC AREA SUGGESTED EMPs and ESs
64. II (13) UTHALSAR PRABHAG VANDANA TACKIES (1) Inadequate cross-section (2) Solid waste dumping 9.3.1 & 9.3.6 10.7 (1)Solid waste dumping (2) Slum area 9.3.1 9.3.6 9.8.1 9.4.1 9.4.2 10.7 10.1 10.1

65.

II (61)

KOPARI PRABHAG AZAD NAGAR

*******

Project by : Hariyali, Thane, Sponsored By : MMREIS

61

CHAPTER 10 : ENGINEERING SOLUTION

CHAPTER 10 ENGINEERING SOLUTIONS


10.1 TRAINING OF MAJOR WATER COURSES 10.1.1The design criteria in terms of improvement of carrying capacity should be decided on the basis of intensity of rainfall once in 10 years for major watercourses. Accordingly, width of these watercourses and cross sections should be worked out. The watercourses should be provided with walling and bedding with suitable material like stone/R.C.C. walls and c.c. beds. 10.1.2As regards intensity of rainfall once in 100 years, the width and zone for each major watercourse should be calculated and no permission for any structure should be granted in this zone. 10.1.3As and when required, the pumping of run-off should be resorted to in the requisite area. For this purpose, the sites requiring such arrangement should be identified and pumping stations and pumping arrangement should be provided. 10.1.4On-line submersible pumps should be provided for de-silting of nallas wherever machine cleaning or even manual cleaning is not possible. 10.2 PROVIDING ROAD SIDE STORM WATER DRAINS 10.2.1Every road should have side-drains based on intensities suggested by TMC consultants by taking due cognizance of technical presentation by Mr. S.D. Chawathe et al, The camber for the road and drains have to act in a perfect manner of no stagnation of rain water on any part of the road. 10.2.2All road side drains emptying into watercourses should be provided with sufficient fall and free flow as far as possible. 10.2.3Based on 10.2.2, formation levels of the roads have to be decided and constructed. 10.3 CONTROL BY TOWN DEPARTMENT OF TMC PLANNING AND DEVELOPMENT

10.3.1It should be made mandatory for the architects to submit plans of formation level of roads in front, location of watercourses, invert levels of watercourses, proposed width of watercourses, proposed development levels, internal storm water drainage arrangement and proposed plinth levels. 10.3.2The proposed development level of any plot in TMC area should not be less than 4.9 m (GTS).

Project by : Hariyali, Thane, Sponsored By : MMREIS

62

CHAPTER 10 : ENGINEERING SOLUTION

10.3.3A plan showing proposed formation levels of roads in TMC area should be released. 10.3.4A plan showing areas covered with mangroves should be released by TMC. 10.3.5All these requirements should be incorporated in the Commencement Certificate issued by TMC for any structure. 10.3.6The TMC should design and incorporate locations of detention ponds on the development plan of TMC. 10.4 CLEANING OF WATER COURSES 10.4.1All the major watercourses should be provided with a side road of minimum width of 4 m. for plying of machinery and equipment for de-silting. 10.4.2The frequency of desilting program for watercourses should be three times a year. 10.4.3Similarly, all road side drains should be cleaned at least three times a year. 10.5 SHIFTING OF UTILITIES 10.5.1TMC should declare and coordinate program for shifting of utilities every year. 10.5.2In next three years, shifting of utilities should be completed. 10.5.3In case of cross drainage, the utilities along the roads should cross, free of culverts. 10.5.4In case of utilities crossing the road, a separate duct should be provided. 10.6 CONSTRUCTION OF DETENTION PONDS 10.6.1It is possible to provide for detention ponds on the bank of Thane and Ulhas creek as absorption capacities for unusual run -off. 10.6.2The TMC should coordinate with Khar land department of GOM and enforce CRZ regulation to enable providing such detention ponds. 10.6.3 Wherever needed and feasible, simple embankment structure on the bank may be thought of by TMC, to avoid entry of high tide water. 10.6.4The required non-return flaps sho be designed and provided. uld 10.7 CONTROL ON SOLID WASTE IN THE WATER COURSES 10.7.1No engineering solution will be effective until entry of domestic and other solid waste into the watercourses is totally stopped.

Project by : Hariyali, Thane, Sponsored By : MMREIS

63

CHAPTER 10 : ENGINEERING SOLUTION

10.7.2The TMC should float an awareness program with the help of suitable NGOs to prevail upon all the public in general not to dump solid waste into the watercourses and road side drains. 10.7.3TMC should prepare and implement a plan for collection, treatment and disposal of solid waste. 10.8 DEVELOPMENT OF LOW LYING AREAS AND SLUMS 10.8.1In near future, TMC should implement development of slums and of low lying areas so that sullage from slums is not let out in the watercourses and storm water is not accumulated in such areas. 10.8.2The necessary provisions for SRD/SRA application on the lines of Mumbai Mahanagar Palika should be made for these schemes. 10.9 SEWERAGE NETWORK 10.9.1It is utmost necessary for TMC to design and provide for a complete sewerage scheme with treatment and disposal methods. 10.9.2As a temporary solution in slum area, construction of shallow sewer to collect sullage from slums should also be considered. 10.9.3If required, short outfalls for disposal of effluents from STPs may be considered by TMC. 10.9.4For the above purpose pollutant carrying capacities of Thane/Ulhas creek should be worked out. 10.10 HYDRAULIC MODELLING OF CREEKS 10.10.1All Corporations and Councils abutting Thane and Ulhas creek should come together to study rainfall, run-off and estuarine mechanisms of the creeks. 10.10.2The agency like CWPRS may be appointed by all the above Corporations and councils jointly with NIO and NEERI to carry out such studies. 10.11 TUNNELING AS OPTION 10.11.1A deep interceptor or tunneling option with under ground reservoir and use of storm water for dilution of sewage may be studied on macro basis. 10.11.2This option will be quite costly. However, cost comparison may be kept on record.

Project by : Hariyali, Thane, Sponsored By : MMREIS

64

CHAPTER 10 : ENGINEERING SOLUTION

10.12 INTERLINKING OF LAKES 10.12.1The topography of TMC is suitable for preservation of lakes which are absorbent of run-off. 10.12.2Interlinking of lakes may be studied with due regards to surrounding creeks. 10.12.3The block cost of such a project may be worked out and kept on record. 10.12.4Engineering solutions for Identified water logging spots are shown by indicating paragraph numbers in the table in chapter 9 (P.47 to 56). *******

Project by : Hariyali, Thane, Sponsored By : MMREIS

65

CHAPTER 11 : ACTION PLAN FOR TMC

CHAPTER 11 ACTION PLAN FOR TMC


11.1 IMMEDIATE ACTION POINTS TMC should take immediate action, preferably before next Monsoon, on following action points: a] Twelve dead water pipelines should be removed from the watercourse near Ambewadi market in Railadevi Prabhag. b] Redesigning the watercourse near Bradma company( Railadevi Prabhag)in such a way that there are two streams from two sides of the road so as to prevent water logging at the low level near Bradma Company. c] Removal of collapsed wall from the Watercourse near Hiranandani Road at Patlipada North d] Removal of structures from within the Watercourse at K Villa (Uthalsar Prabhag) and Bhayandar pada in Majiwada Prabhag. e] Removal of blockage of cross-drainage at Hiranandani Road in Patlipada North. f] Request BMC for widening and training of culvert at Anandnagar on Eastern Express Highway and pursue the matter vigorously with them. g] Deepening of the watercourse at Ambewadi market near Road no 33, and at Rupadevi pada and Sathenagar in Railadevi Prabhag and at Kharegaon and Budhaji Marg in Kalawa Prabhag. h] Removal of water supply lines from the watercourse at Bradma Company in Railadevi Prabhag and near Shubharambha Society ( before Soham Hava Mahal ) in Uthalsar Prabhag and if the utilities in the watercourse contain such water supply lines near water logging spots at Rupalipada, ITI Naka, Teen Hath Naka and Mental Hospital, all falling in Railadevi Prabhag. i] Redesigning and reconstruction of drains at Khartan Road in Naupada Prabhag j] Redesigning of culverts to provide proper invert level in the watercourse near Civil Hospital and Kamgar Hospital and near Samartha Nagar in Railadevi Prabhag, at Manpada South and Runwal Junction-Koras Road in Vartak Nagar Prabhag and at Suraj Water Park in Majiwada Prabhag.

Project by : Hariyali, Thane, Sponsored By : MMREIS

66

CHAPTER 11 : ACTION PLAN FOR TMC

k] Redesigning and implementation of cross-drainage at Indiranagar in Railadevi Prabhag and at Bhayandarpada, Vadavali and Anandnagar in Majiwada Prabhag. l] Redesigning and training of downside of the watercourse up to the creek even in the marshy land in Bhayandapadain Majiwada Prabhag. m] Identifying pockets for undertaking public awareness programs for solid waste disposal and arranging such programs with suitable NGOs. Simultaneously arrangements should be made to provide bins for storage of solid waste and for its collection, transport and disposal. n] Enforcing the development levels by all the developers while taking up any new development works. 11.2 MEDIUM TERM STRATEGY 11.1.1TMC should take up a detailed survey of one watercourse originating in Railadevi Prabhag and meeting Thane creek to find out alternate solutions for minimizing water logging in its vicinity and mitigating the environmental problems such as water pollution, air pollution, etc. the work in this pilot project should include, inter alia, provision of sewer lines including shallow sewers, avoiding solid waste dumping by people by provision of training, imposing fines, provision of collection and transport of solid waste, providing removable dhapas on the watercourse running through the hutments, considering whether rehabilitation of slum dwellers is necessary for providing pathway enabling to ply the desilting machinery. Costs of such works could be worked out and, if necessary, the possibility of approaching a funding agency could be explored. 11.1.2TMC should consider construction of detention ponds as suggested in the Report. 11.1.3TMC should set up a Standing Committee for Co-ordination with Central Railway for modernization and de-silting of railway culverts. 11.1.4TMC should co-ordinate with Forest Dept for putting geo-fabrics on slopes near watercourses and for plantation of trees/ grass. Action to be initiated by TMC and take help of Hariyali for follow-up. 11.1.5TMC should seek co-operation of service providing bodies such as MTNL, MSEDCo, Mahanagar Gas Nigam, etc for shifting utilities from watercourses.

Project by : Hariyali, Thane, Sponsored By : MMREIS

67

CHAPTER 11 : ACTION PLAN FOR TMC

11.3 LONG TERM STRATEGY 11.1.6TMC should frame development regulations containing, among others, development levels of land with reference to HFL in relation to surrounding water bodies, development levels of roads etc and to enforce the regulations. 11.1.7TMC should seek co-operation of other Corporations and Councils for study of Thane and Ulhas creeks in the saucer type low lying areas as suggested in the Report. 11.1.8In the saucer type low lying areas planned program should be implemented on the lines of slum redevelopment strategy to nullify any water logging in such areas. 11.1.9The ideal situation of total absence of sewage and solid waste in the watercourses should be planned and achieved by TMC in the next 5 years. *******

Project by : Hariyali, Thane, Sponsored By : MMREIS

68

ACKNOWLEDGEMENT.

ACKNOWLEDGEMENT

Project by : Hariyali, Thane, Sponsored By : MMREIS

69

ACKNOWLEDGEMENT.

Project by : Hariyali, Thane, Sponsored By : MMREIS

70

COMBINED LAYOUT OF THANE CITY .

COMBINED LAYOUT OF THANE CITY

Project by : Hariyali, Thane, Sponsored By : MMREIS

71

You might also like