Backfilling
Backfilling
Backfilling the wrong way often costs more than doing it right
BY R. T. BUCK BARTLEY
ackfillingan essential step in basement constructionis all too often the beginning of basement destruction. Done improperly, backfilling causes problems that may start before the builder leaves the site and may remain long after hes gone. But the problems can be avoided by taking a few simple precautions. There are four key elements to proper backfilling: Protecting the foundation wall from damage during backfilling Using the right backfill materials Compacting the backfill Final finishing the subgrade to ensure that water drains away from the foundation Done correctly, these four steps help to ensure that a well-built basement functions the way its supposed to, providing the homeowner with dry, usable living space.
Figure 1. Vertical or horizontal bracing can be used to protect walls from damage during backfilling. Vertical braces can be made from steel pipe (drawing a) or lumber (drawing b). Horizontal bracing (drawing c) works well for straight walls up to 48 feet long.
above the footing. Then toenail 3x12s diagonally across the corners as shown. Add 2x4 cleats and kickers to prevent slippage and flex. This system works well for walls up to 48 feet long. Beyond that length additional intermediate vertical bracing is needed, attached to pier pads, footings, or wood stakes firmly driven into the ground. Although most building codes require that foundation walls be adequately braced before backfilling, most home builders dont use braces for poured concrete walls. They believe that the concrete is strong enough to resist p re s s u re caused by backfilling. And they may get by without damaging the wall. But too often a wall gets pushed in (Figure 2). Sometimes this happens during the winter when concrete doesnt gain strength quickly because of low temperat u re s. Sometimes its because the excavating contractors equipment gets too close to the wall. And sometimes rain saturates the area around the foundation soon after its backfilled, increasing soil presFigure 2. Backfilling pushed in this unbraced wall and sures enough to cracked it. The diagonal crack was repaired by the home cause a wall failure. builder but the wall still leaked when the owner moved in. Fixing the problem required excavation, pushing out the Whatever the wall, and installing new waterproofing at a cost much cause, the home greater than doing the job right the first time. builder is left with
tion is bracing with lumber using scaffold boards or 3x12s as shown in Figure 1b. If the slab and pier pads cant be used for bracing, horizontal bracing as shown in Figure 1c is usually adequate. Attach 3x 12s to all four walls, parallel to and about 4 feet
a costly problem. Fixing it will require pushing out the bow in the wall and repairing the crack with epoxy injection. As insurance against a wall failure, having two carpenters work a couple of hours bracing the wall is a good investment.
Figure 3. Backfilling with soil full of tree roots leaves a porous fill that can cause basement leakage. The fill cant be properly compacted and will settle with time.
Figure 4. Splash blocks often dont carry water from downspouts beyond the backfilled area. Then water from the roof saturates the backfill.
trough caused by settlement and s t a rted leaking t h rough shri n kage cracks in the foundation wall. Co r recting the faulty dra i n a g e stopped the leaking . Be careful when compacting backfill. Some compactors are powerful enough to damage the wall. One way to avoid this problem is to place the backfill in 6-inch-thick lifts and have the laborers tamp it with foot pressure or hand rammers. Vibrating plate compactors also can be used for granular backfill without damaging the wall. It takes more time to compact thin layers, but the method provides insurance against wall damage and against call-backs related to drainage problems.
the foundation saturates the soil and makes basement leakage more likely. If the house is set high enough on the lot, getting the correct grade for drainage isnt difficult. Too often, howe ve r, houses are built too low. Then instead of the code-re q u i re d 8-inch minimum between the sill plate and exterior grade level, the house might be built with the finished grade only 4 to 6 inches below the plate. To avert this problem, avoid making the excavation too deep and set footing elevations high enough. Avoiding basement leakage is a lot like preventing a roof from leaking. You need to keep the water moving and prevent it from collecting in one spot. Correct backfilling methods help to accomplish this goal. Buck Bartley is a general contractor in Silver Spring, MD. Hes a former p resident of the Poured Concre t e Wall Contractors Association, now called the Concrete Foundation Association. Publication # C910315
Copyright 1991, The Aberdeen Group. All rights reserved