Basics of Submarine System Installation and Operation
Basics of Submarine System Installation and Operation
Submarine Cable
Inter-island Network
Submarine Cable
Terminal Stations
offset today by current market oversupply of repeatered production capability and inventory
Coastal Networks
The choice between repeatered & repeaterless must be made on a case by case basis
Festoon
ADM
ADM
SLTE
N x STM-1o
ADM
N x STM-64
Ocean Cable
Shore Section
PFE
)
Ocean ground
SLTE Submarine Line Termination Equipment.
PFE Power Feed Equipment (pushes constant current of ~1.5 A across undersea cable link from CS to CS)
LINE PAIR #1
Undersea Cable
SLTE
SDH Terminal
Cable Station
SLTE
SDH Terminal
Line Current
1
To SDH Equipment
1- N
Line Amplifier
N
High Performance Optical Equipment DWDM Wavelength Terminating Equipment
2.5G ORX
OH FEC ENCODER INS OH FEC ENCODER INS OH TIMING GENERATOR OH FEC ENCODER INS OH TIMING GENERATOR OH FEC INS ENCODER OH TIMING GENERATOR OH FEC COD
WME 10.8G
SCR MUX
ORX Shelf
STM-16 STM-16 STM-16 STM-16
E/O CONV. E/O 2.5GCONV. OTX E/O 2.5G CONV. OTX E/O 2.5GCONV. OTX OH
Timing Generator
TRM
OH
FEC
TRM
OH
FEC
OH
TRM
OH
Timing Generator
DECODER
FEC
WME 10.8G
2.5G OTX
OH
TRM
OH
FEC
DECODER
DSCR DMUX
OH FEC DEC
Source NEC
SDH Multiplex Equipment Network Protection Equipment High Performance Optical Equipment Wavelength Terminating Equipment Line Amplifier Optical Line To Undersea Cable
SDH
TLA
PR1
800 mm
PR2
800 mm
PM
800 mm
LT
800 mm
SW
800 mm
TL1
800 mm
TL2
800 mm
COM
FAN
FAN
CONV(6) CONV(7) CONV(8) CONV(9 ) OPE & MONI & C/V SENSOR
SW&RETURN
TEST LOAD
CONV(4)
CONV(5)
BLANK
HV PFE Configuration
Cable Station and Beach Manhole 2025 Taft Street - Hollywood, Florida
The optronic connection that starts at Optical Distribution Frame (ODF) in the Cable Station and then continues to the ODF at the City Service Point, the Telehouse. Then a separate connection of the circuit is made to the frame of the carrier who will then take traffic back to the end customer premise. Cable Station
Submerged Plant Beach Manhole Shore Section Land Sections Terminal Station Terminal Station Equipment
Branching Unit Cable
Network Management
Terminal Station
Land Section Beach Manhole Optical & Power Feed Transmission Equipment Equipment
Repeater
Cable Ship
Submarine Cable
South America Physical Map South America ERZ border at 12 nmi South American Crossing Segments are mostly outside of the ERZ
CS Long Lines
LONG LINES YEAR OF BUILD: 1963 LENGTH: 155.91 BREADTH: 21.19 DRAUGHT: 8.17 DEPTH: 13.87 FLAG: UNITED STATES OF AMERICA SHIPBUILDER: DEUTSCHE WERFT HAMBURG COUNTRY OF BUILD: FEDERAL REPUBLIC OF GERMANY STATUS: IN SERVICE/COMMISSION
Service, Operations & Maintenance System Provisioning Station & NOC Operations Cable Maintenance agreement (Cable recover, splicing, repair, relay, rebury) Network Upgrades
Land Plant
Fiber Cable
Copper/Stainless Steel Bimetal Armor Core Tube Filling Compound Lightpack TM Fiber Bundle 4-48 Fibers Color Coded Binder High Density Polyethylene Jacket Helical Lay Wire Strength Members
Source - Tycom
Power Cable
#6 Copper Conductor Strand Screen Insulation Semiconductor Layer Copper Tape Polyethylene Jacket
Source - Tycom
SDH Network Protection Equipment SDH Multiplex Equipment Line Monitoring Equipment Network Management Equipment Power Feed Equipment Synchronization Equipment Test Equipment
Terminal Stations
Typically terminate undersea signals, and interface with domestic network Most often very close to beach Construction & features very similar to other telecom offices, such as Central Offices, but include some unique aspects In multi-point coastal systems, costs can become significant element of network cost. Large stations cost $10-$15M. Very small stations <$5M. Permissions and Rights Of Ways associated with construction and beach access, plus actual civil construction, together often dominate overall network construction schedule In small, regional networks, alternate more efficient options (prefabricated huts) may be possible
Source The David Ross Group http://www.davidrossgroup.com
Undersea Plant
Undersea Plant
OPTICAL FIBER
STRENGTH WIRES
LW
(Lightweight)
SPA
(Special Purpose Armor)
LWA
(Light Wire Armor)
SA
(Single Armor)
DA-HS
(Double Armor, High Strength)
DA-HA
(Double Armor, High Impact)
Rock Armor
Source Tycom
Typical Application
Beach Joint to 400 Meter Depth 400 to 900 Meter Depth Buried 900-2,000 Meter Depth >2,000 Meter Depth
Lightweight cable
Used in deep water where hazards are minimal Comes in three outer diameters
10-12 mm, used in non-repeatered systems 17-19 mm, used in several recent repeatered systems 21-23 mm, used in repeatered systems wherever the additional size is deemed necessary or desirable
One optical amplifier per fiber Costs strongly dependent on number of fiber pair Cost also dependent on performance Spacing (between repeaters) set for system performance / cost, and typically 50-80km Shorter spacing generally yields higher ultimate capacity In long (many thousand km) systems, often largest single component network cost
Cab l e Termi na t i on
Approx. 230
Approx. 265
Approx. 250
Cab l e
Appr ox . 1500
Appr ox . 1400
(be tween PIN t o PIN)
Appr ox . 1500
Source - NEC
Locking Plate
Heat Transfer Plate Supervisory Erbium Amplifiers Pump Unit Control Circuit Power Supply
Source Tycom
33cm (13)
Repeater Housing
Undersea Plant
Equalizer
Performance designed to match needs of system Inserted at periodic intervals as needed One equalizer per fiber Cost strongly dependent on number of fiber pair Higher capacity systems generally require more exotic equalization
Pressure Housing
Source - NEC
Undersea Plant
Branching Unit
All currently produced are three-terminal One or more fiber pair may be branched Fiber connections or powering may be switchable from a shore terminal or NOC for restoration or security Wavelength branching (Optical Undersea AddDrop Mutiplexing) has been done on a limited basis Cost is strongly dependent on degree of complexity and number of fiber pair
Approx. 4600
Approx. 1245
Cable Termination
Housing Unit
(Pressure Housing)
Approx. 480
Cable
Tail Cable
Approx. 1260
1700
Source - NEC
Undersea Plant
Marine Installation
Uses specially designed cable-laying vessels and tools Costs strongly dependent on
Water depth Types of cable and protection employed Bottom characteristics Burial depth required Number of shore landings and branching units Number of cable and pipeline crossings Distance of lay from cable factory Weather
Wet Plant Dry Plant Terminal Stations & Backhaul Marine Work Network Operations Center
Work might begin earlier via an ITP IF purchaser guarantees payment for all supplier expenses prior to secure contract
Todays oversupply market offers huge discounts for purchasers, but minimal opportunities for vendor finance
Network Upgrades
Network upgrades to increase capacity by adding wavelengths are planned and contracted (price-capped) at the time of the initial system construction. Typically, but not always, the same supplier installs and upgrades the network Terminal stations must be sized for the ultimate capacity of the system, often requiring tens of thousands of square feet. In high-capacity WDM systems, upgrading to the ultimate design capacity may take many years, and will often cost more than the initial undersea system installation. Since technology and prices change over time, purchasers often obtain better prices (than originally contracted) at the time they are needed
Life-Cycle Costs $
Revenue Possible Revenue Projection
(further study required)
Construction Begins with ITP Supply & OA&M Contract Cost Finance & Supply Contract Closure
First Revenue
Time
Net Cash FlowBreak-even Dependent On Demand & Revenue
100%
Service
Final Acceptance
Cumulative Costs