Gantt Chart: Legend: Critical Path Not Critical Path Slack Time
Gantt Chart: Legend: Critical Path Not Critical Path Slack Time
1/1
Process Doc Contract Plan/Get data Perform tasks Write report
1/15
2/1
2/15
3/1
3/15 4/1
4/15 5/1
5/15
Test/deliver
Pakistan Institute of Management Legend: Red = critical path; Blue = not critical path; Green = slack time
GANTT CHART
RESOURCE LEVELING Resource leveling aims to minimize the period-by-period variations in resource loading by shifting tasks within their slack allowances.
Main Planning Activities; Defining and agreeing Scope statement Creating WBS (upto WP level) Defining activities and their predecessors Estimating resources (Time, People, Equipment, Materials etc., and associated Risks etc) Draw network diagram, determine CP and Float/Slack Make GANTT chart and do Resource Levelling Make Project Management Plan
3
4 4 3 3
8
4 8 5 8
19
10 18 11 19
32
11 29 12 31
47
12 41 11 42
63
15 56 7 49
BCWS = 91
ACWP = 83 CV=BCWP-ACWP SV=BCWP-BCWS CPI=BCWP/ACWP SPI=BCWP/BCWS Estimated time to complete Estimated cost at completion -10 -18 0.9 0.8 15 289 (original plan of 12 months divided by SPI of 80%) (original plan of 254 divided by CPI of 90%)
BAC
ETC
BCWP TIME