The Optimal Investment Scale and Timing: A Real Option Approach To Oilfield Development
The Optimal Investment Scale and Timing: A Real Option Approach To Oilfield Development
= (3)
We will assume that the value of developed reserve V(P) is linear with P, so that the quality
parameter will be constant (independent of P), differing only across the alternatives of scale.
The motivation for the name "business model" is drawn from the reserves transactions market. For
example, in the United States the average price paid for one barrel of developed reserve is 33% of
the wellhead oil price, which Gruy et al. (1982) named the one-third rule of thumb
12
.
In order to understand the model better, let us examine the case without the option to wait, that is,
the case at expiration (the legal constraint set by the government agency).
Figure 1 shows the NPV(P) linear chart for three different development alternatives.
12
This one-third rule of thumb was used also in Paddock, Siegel and Smith (1988) to perform a numerical example.
However, they model the option value as a function of F(V), not F(P) as here. In addition, they did not devote any
discussion on the properties of the proportionality factor q as here. In our paper, this quality factor has a key role
because it captures the differences of alternatives of scale on the benefit side in the simplest way possible.
8
Figure 1 - NPV Functions and the Optimal Exercise at Expiration
Note that the slope of NPV
k
(P) is one key difference between the alternatives and it is given by
tg(
k
) = q
k
B, so that the economic quality of the developed reserve is related to the slope of
NPV
k
(P). The other difference between the alternatives is the investment, given by the Y-intercept
of the NPV lines, that is, NPV
k
(P = 0) = D
k
.
At expiration (t = T), the traditional NPV rule holds, that is, to exercise the alternative with higher
NPV. This is presented in Figure 1 above by the envelope NPV function (thicker lines), and will be
one boundary condition of our model.
Figure 1 also shows the oil prices at which we would be indifferent between two alternatives. P
0, 1
is
the indifference point between exercising alternative 1 (A
1
) and not investing (alternative 0). P
1, 2
is
the indifference point between exercising alternatives A
1
and A
2
(equal NPVs for these
alternatives). P
2, 3
is the indifference point between alternatives A
2
and A
3
.
9
Before expiration (t < T), due to oil price uncertainty, the "wait and see" policy can be optimal even
if all alternatives have positive NPVs because the option to delay the exercise can be more valuable
than the immediate exercise of any alternative. Before the presentation of the differential equation
for the option value, it is useful at this point to discuss conceptually some results in order to
understand better the boundary conditions for this model in the next section.
Dixit (1993a), working with perpetual options, stated that if the (upper) option curve smooth pastes
the NPV of alternative A
2
at P*
2
, the optimal rule shall be "wait if P < P*
2
, and exercise the higher
NPV alternative in the opposite case". However, Dcamps, Mariotti and Villeneuve (2003) disagree
with this conclusion for perpetual options. We also found at least for the finite-lived options case
that the existence of intermediate waiting regions is possible and even common. Figure 2
illustrates this issue, showing an example where intermediate waiting regions appear between the
exercise regions of the alternatives A
1
, A
2
and A
3
.
Figure 2 - Optimal Decision Map: Investing and Waiting Regions
10
The waiting regions are shaded in Figure 2. In this example, the time to expiration is two years. At
expiration (t = T = 2 years), the NPV rule holds and the reader can compare the indifference points
P
0, 1
, P
1, 2
, P
2, 3
, from Figure 2 with the ones shown in Figure 1. In Figure 2 at t = 0, the decision rule
is
13
: wait if P (0, 22); invest in alternative A
2
if P [22, 27.6]; wait again if P (27.6, 31); and
invest in alternative A
3
if P [31,). So, the decision rule is not to invest in the higher NPV
alternative if P P*
2
(the threshold to invest in A
2
), as in Dixit (1993a). There is an intermediate
waiting region that in this example at t = 0 is in the range P (27.6, 31). The existence of
intermediate waiting regions for a given t < T will depend on the parameters, in particular the
volatility - higher volatility can make it optimal for us to wait for the higher scale alternative A
3
, the
intermediate waiting and investing regions disappearing.
By observing the asymptotic behavior of this intermediate waiting region in Figure 2, we can
conjecture that the existence of this region is possible in the perpetual option case as well.
Dcamps, Mariotti and Villeneuve (2003) worked independently but with perpetual options and
proved mathematically that the waiting region around the indifference point between NPV
2
and
NPV
3
always occurs (non-empty region) if it is sometimes optimal to invest in alternative 2. They
showed that if "investment in the smaller scale project is sometimes optimal, ... the optimal
investment region is dichotomous.". In their proposition 3.2, they show that the indifference point
where NPV
2
= NPV
3
(i.e., P
2, 3
) does not belong to the exercise region. They proved that
proposition with the help of the concept of local time for the continuous semimartingale P applied
at this indifference point. This is true even without the option to switch analyzed in that paper.
Probably this conclusion from Dcamps et al (2003) is even more general, being also true for finite-
lived options except at the expiration, as our numerical simulations indicate for geometric Brownian
13
In case of indifference between wait or invest, we assume invest.
11
motion. However, for the mean-reversion case this can be not true due the discontinuity of the
thresholds curve for the high-scale cases (see our section 4.2).
The existence of this intermediate waiting region led to an apparently surprising result. In Figure 2,
at t = 0, if the oil price is US$ 30/bbl, the wait and see policy is optimal, but as the price drops to
US$ 27/bbl, it is optimal to invest in alternative A
2
. The intuition in this case is as follows: if the
price P is US$ 30/bbl, the hopefulness to invest optimally in the larger scale alternative A
3
is
sufficiently high (because P is close to the threshold P*
3
) to offset the value of exercising the "deep-
in-the-money" alternative A
2
. However, if the price drops to US$ 27/bbl, the probability for the
price hitting the threshold P*
3
before expiration is not high enough to justify the delay in the option
exercise of alternative A
2
.
Note also in Figure 2 that as time passes, e.g. at t = 1.5 years, a region appears of immediate
exercise of alternative A
1
. Together with this new exercise region appears a new intermediate
waiting region. We found that when a new optimal investment region appears, it always divides the
previous waiting region into two waiting sub-regions, so the exercise and waiting regions appear
together as time goes by. If the oil price follows a geometric Brownian motion, the emergence of
new exercise and new waiting regions together is a general result as time approaches expiration for
non-dominated scale alternatives
14
. This occurs because the thresholds curves are continuous (no
jumps) and at expiration there are three exercise regions (see Figure 1), which comprise the limit
(boundary) condition at expiration (t = T). We will see that for the mean-reversion model for oil
prices, due to the possibility of discontinuity in the threshold curves at expiration, some
intermediate waiting regions can never occur.
14
In our model, a higher development cost alternative j is non-dominated if it has higher economic quality q
j
than all
the lower development cost alternatives.
12
Let us define P*
k
and P**
k
, k < k
max
, as the lower and upper oil price levels (so that P*
k
< P**
k
) that
define the optimal exercise region for alternative A
k
during the period this region exists. For the
higher scale alternative k
max
, there is always P*
kmax
, but never a finite value of P**
kmax
. For the
other alternatives, P*
k
and P**
k
can exist only for time t very near expiration. At expiration t = T,
P*
k
collapses to P
k 1, k
and P**
k
collapses to P
k , k + 1
.
The existence of waiting regions reflects the real option value of the additional opportunity to invest
in a higher scale alternative. Figure 3 below illustrates this point by showing the option value F for t
= 0 and the payoffs (NPVs) for immediate exercise in each alternative.
Figure 3 - Option Value at t = 0 and Exercise Payoffs
Note that like in the Figure 2, Figure 3 shows that for t = 0 the threshold P*
1
does not exist (the
option value F is higher than NPV
1
P), there is an exercise region for alternative A
2
(between P
2
*
and P
2
**), and there is an intermediate waiting region between P
2
** and P
3
*. Dcamps, Mariotti
and Villeneuve (2003) showed for perpetual options that this region always exists (if sometimes it
13
is optimal to exercise alternative 2, as occurs in the figure). Numerically, the error can be small if
exercising the option (higher NPV as suggested by Dixit in 1993) rather than waiting in this
intermediate optimal waiting region. So, even not being strictly correct, the error from using Dixit's
insight can be small in practice. However, there can be a large range to the optimal waiting interval
(between P
2
** and P
3
*).
Another insight from Figure 3 is that both the value-matching and smooth-pasting properties exist
at the optimal investment threshold not only for P
k
* but for the upper threshold P
k
** as well, if they
exist. For example, at P
2
** in Figure 3 the option curve F has the same slope as the straight payoff
line NPV
2
. This is not surprising because the case of waiting with P > P
2
** and exercising when P
drops to P = P
2
**, is like an option to abandon the opportunity to invest in the higher scale
alternative A
3
, by taking the irreversible decision to invest in A
2
. The smooth-pasting and value-
matching properties at optimal thresholds occur in practically every real options problem see
Dixit & Pindyck (1994) and Dixit (1993b).
In addition to be optimal "wait and see" policy in this intermediate waiting region, the option curve
value in this region can also indicate something about an optimal project scale. Imagine that the
feasibility study team is willing to study another scale alternative but is looking for an immediate
optimal investment. At t = 0, if P belongs to this intermediate waiting region, what is the optimal
scale project for an immediate investment exercise? It must have a quality q* equal to the derivative
of this option value, that is, q* must be equal to the derivative of the option value F(P, t) with
respect to P. This conclusion is derived from the smooth-pasting property at the optimal option
exercise. This project does not exist in the figure above, but the optimal scale in this case is an
intermediate scale between alternatives 2 and 3 with a payoff curve slope (given by the economic
quality q*) so that q
2
< q* < q
3
. So, there is an interesting practical link between the concept of
quality q and the smooth-pasting property for the optimal scale option exercise.
14
The solution shown in the Figures 2 and 3 must be found numerically, for example by using a
binomial approach and working backwards. In this setting we compare the option value of waiting
with the payoff from exercising the higher NPV alternative for every time t and every oil-price
value in the binomial tree. We will work with the partial differential equation approach for the
option value as function of the stochastic oil price and with the appropriate boundary conditions.
The discussion above facilitates understanding of the boundary conditions.
3. Geometric Brownian Motion, Mean-Reversion and the Differential Equations
3.1) Geometric Brownian Motion
By knowing the current oil price and the stochastic differential equation that governs its future
evolution we can determine both the optimal decision rule and the option value of the undeveloped
oilfield (the option to develop). The real option value is conditional on the optimal decision rule.
The optimal decision rule considers two control variables, the optimal timing to develop the oilfield
and the optimal production scale.
In addition to oil prices (P), the other state variable is the time (t), because we have here a finite-
lived real option, with t [0, T]. After the expiration time T, in case of non-development, the
oilfield returns to the government agency and is worth nothing.
Let F(P,t) be the real option value to develop and let the oil price (P) be given by the following
stochastic differential equation, known as geometric Brownian motion:
dz dt
P
dP
+ = (4)
where, is the drift of the process, is the volatility parameter and dz is the Wiener increment
defined as: N(0,1) t d = dz , with N(0,1) being the standard normal distribution.
15
Lemma: Let F(P, t) be the real option to develop the oilfield by choosing timing and scale from a
set of n investment alternatives, k = 0, 1, n, and NPV
k
(P) the net present value by exercising the
alternative of scale k (being NPV(k = 0) = 0). The following inequality holds:
F(P, t) NPV
k
(P) k {0, 1, n}, t [0, T] (5)
This lemma is derived by construction, given that the oil firm has the freedom to choose the
development timing (constrained by the legal limit T) and the scale from a set of alternatives found
in the feasibility study. Because the firm can exercise the higher NPV alternative, the option value
cannot be lower than the NPV of any alternative. This lemma will help in the boundary conditions
to define the existence of investment thresholds (see below).
Assuming that the oil market is sufficiently complete and that there are no arbitrage opportunities in
equilibrium, by using Ito's Lemma and contingent claims approach it can be shown that
15
the option
value follows the following partial differential equation (PDE), where r is the risk-free interest rate
and is the convenience yield of the commodity:
F r F F P ) r ( F P
2
1
t P PP
2 2
= + + (6)
where the subscripts (P, PP, and t) denote partial derivatives. Let the scale alternatives be ordered,
i.e., D
1
< D
2
<< D
n
. Eq. (6) is subject to the following boundary conditions Eq.(7 12):
F(0, t) = 0 (7)
F(P, T) = Max[NPV
k
(P)], for all k = 0, 1, n (8)
F(P
k
*(t), t) = NPV
k
(P
k
*, t), for t < T and for all k which exist P
k
*(t) (9)
15
See Black and Scholes (1973) or Merton (1973) for a financial option pricing methodology and Dixit and Pindyck
(1994) for a real options approach using contingent claims. The partial differential equation is the same as that of
Black-Scholes-Merton, the differences are in the boundary conditions.
16
| | | |
B .
k
q
P
) t , P ( NPV
P
) t ), t ( P ( F
*
k k
*
k
=
|
|
.
|
\
|
+
(14)
Again, the subscripts (P, PP, and t) denote partial derivatives. Eq. (14) is subject to the same six
boundary conditions (Eqs.7-12) described in the previous sub-section.
Note that for mean-reverting processes, the convenience yield of the commodity is not constant, it
is a function of the oil price:
(P) =
|
|
.
|
\
|
P
) P P (
(15)
This non-constant convenience yield is a usual characteristic of mean reversion processes. The
parameter is endogenous in our model, and from a market point of view, is used in the sense
17
This equation corresponds to Eq.(4.9) in Kloeden & Platen (1992, p.119). See also an interesting discussion of this
process and comparison with other mean-reverting processes in Robel (2001).
18
See Dixit and Pindyck (1994) chapters 5 and 12 for similar examples of geometric mean reverting process.
20
described by Schwartz (1997, p.2): In practice, the convenience yield is the adjustment needed in
the drift of the spot price process to properly price existing futures prices. Note also that for the
mean-reversion model, the risk-adjusted discount rate appears, even assuming complete markets.
This feature does not occur with geometric Brownian motion because the convenience yield is
constant in that model. Here the convenience yield is a function of the risk-adjusted discount rate
for oil price risk.
See also Dias & Rocha (1999) for a discussion of the value of the convenience yield in mean-
reverting models highlighting the possibility of this parameters becoming negative for low oil
prices. Eq.(15) shows that (P) < 0 is possible for low values of P. In this case, there is the
possibility of discontinuity in the threshold curves at expiration because from the literature of
American options we know that the earlier option exercise is never optimal when the convenience
yield is negative or zero. We will address this question in Topic 4.2.
Figure 6 shows the option value at the current (t = 0) and at the expiration time, using volatility of
25% p.a. and for the numerical parameters for the mean reversion process presented in Section 4
below. Note again that at expiration we have three different exercise areas, each representing a
certain development alternative for the oilfield. The option at current time is exercised for the
alternative A
2
if the oil price is between US$ 22.90 and 28.30/bbl, there is a thin intermediate
waiting region between US$ 28.30 and 29.90/bbl, and for P US$ 29.90/bbl, it is optimal to
exercise scale alternative A
3
.
21
Figure 6 - Option Value of the Undeveloped Oilfield: Mean Reversion Model
4. Numerical Simulations and the Effect of Volatility
4.1) Geometric Brownian Motion
Consider three oilfield development alternatives, A
1
, A
2
and A
3
. The investment opportunity to
develop the oilfield expires in T = 2 years and the manager has to decide which is the optimal
timing for development as well the optimal production scale that maximize the investment option
value.
Let the following be the parameters for the base case
19
(MM = million): q
1
= 0.08, q
2
= 0.16, q
3
=
0.22, D
1
= US$ 400 MM, D
2
= US$ 1000 MM, D
3
= US$ 1700 MM, B = 400 MM bbl, r = 8% p.a.,
= 8% p.a., = 25% p.a.
20
and P
0
= US$ 20/bbl. With these parameters, the NPVs for immediate
exercise are NPV
1
= US$ 240 MM; NPV
2
= US$ 280 MM; and NPV
3
= US$ 60 MM.
19
Some values were estimated using available data about oil prices or using available related literature.
20
Based on the volatility estimation of Dias and Rocha (1999).
22
Table 1 shows the managerial flexibility value for having a certain number of development
alternatives. Note that the option value increases with the number of available alternatives,
reflecting the option value of additional managerial freedom in choosing the investment scale.
However, the rate of additional value is decreasing with the number of alternatives, so that in
practice after 3 alternatives the additional value may not compensate the time spent by the
feasibility study team in detailing additional scale alternatives.
Table 1: Managerial Flexibility Value .
Development Alternatives : Production Scale Option Value (US$ MM)
k = 2 : Medium Scale 310.98
k = 1 or 2 : Small or Medium Scale 322.65
k = 1 or 2 or 3: Small, Medium or Large Scale 323.33
Note also that these values are higher than the highest NPV alternative (NPV
2
= US$ 280 MM).
Figure 7 compares the oil price threshold curves with a change in the volatility parameters (15%
p.a. and 25% p.a.). A lower volatility means lower probability of changes in oil price evolution. In
this situation the option is exercised sooner (note how the exercise area for the development
alternatives becomes higher) because the option of waiting become less valuable. At t = 0, the
intermediate waiting and exercise regions appear only in the low volatility case. These regions
appear even for very high volatility values, but only at times near or very near expiration.
23
Figure 7 - Geometric Brownian Motion: The Effect of Volatility on the Thresholds
Table 2 shows the real option values at t = 0 and the optimal investment rule for different
volatilities (including an intermediate volatility not shown in Figure 7) and different current oil
prices.
Table 2: Option to Develop Values (US$ MM) and Optimal Action for Geometric Brownian Motion
Current Oil Price (US$/bbl)
Volatility (% p.a.) 15 25 30
15 85.89 wait 600 exercise A
2
942.21 wait
20 102.55 wait 600 exercise A
2
948.65 wait
25 122.29 wait 605.21 wait 958.72 wait
4.2) Mean-Reversion Process
We use the base case parameters from the previous section (except ) plus the specific parameters
of the mean reverting process: = 12% p.a., = 0.3466
21
, P = US$20/bbl
22
.
21
This reversion speed implies a half-life of about 2 years. Bradley (1998, p.59) finds a half-life of 1.39 years.
24
Before showing the threshold chart, it is important to calculate the break-even prices (for which
NPV
k
= 0), and the oil price that makes the convenience yield equal to zero, due to the possibility of
discontinuity in the threshold curves at expiration, as explained below.
The break-even prices for the three alternatives are: P
be1
= US$ 12.50/bbl; P
be2
= US$ 15.635/bbl;
and P
be3
= US$ 19.32/bbl, calculated with the equation P
be(k)
= D
k
/(q
k
B).
By using the Eq.(15) and the base-case parameters, it is easy to find that the oil price that makes the
convenience yield equal to zero is P = US$ 14.86/bbl. So, for oil prices equal to or lower than US$
14.86/bbl, it is never optimal to exercise the option before expiration. However, exactly at
expiration, if the oil price is in the range 12.50 P 14.86, even with 0, it is optimal to
exercise alternative A
1
because we have a non-negative NPV
1
and so exercising the option
increases the shareholder value if P > 12.5 in this numerical example. This means that there is a
discontinuity in the threshold curve at least for alternative A
1
: the threshold to invest in this
alternative at expiration is US$ 12.5/bbl, but at an infinitesimal time before the threshold for this
alternative jumps to a much higher value in order to avoid exercise with negative, zero or too low
values for the oil convenience yield (P).
In the presence of other scale alternatives, this individual behavior of alternative A
1
can make both
the intermediate exercise and waiting regions vanish even very shortly before expiration. This will
occur in our example for alternative A
1
.
Figure 8 compares the threshold curves for oil price and volatility effect (25% p.a. e 45% p.a.).
Note that the region for investment in alternative A
1
no longer exists except at expiration, even for a
22
Baker et al (1998, p.129) estimate the long run oil price as $18.86/bbl (in 1995 dollars) and used (pp.138-140)
US$20/bbl as the initial long run level in their model. This value is also adopted in Bradley (1998, pp.59-61) and
shown in Cortazar & Schwartz (1996, Figure 4). Econometric tests including more recent data point to a long-run level
higher than US$ 20/bbl.
25
time very near expiration. This is caused by the discontinuity of the threshold curve for this
alternative at expiration, as explained in the previous paragraphs. For alternative A
1
, the oil prices
region for optimal exercise at expiration implies either a negative convenience yield or values very
near zero. So, for alternative A
1
alone, a very small time before expiration requires a threshold
much higher than the upper oil price value that makes this alternative optimal at expiration.
However, at expiration, it is optimal to exercise alternative A
1
for a range of prices of 12.50 P <
18.75, shown as a vertical line at t = T.
Figure 8 - Investment and Waiting Regions for the Mean-Reversion Model
This issue of threshold curve discontinuity never occurs with geometric Brownian motion because
the convenience yield is constant (and positive) in that model. So, intermediate exercise and waiting
regions always occur at least for times very near expiration in that model, but the same is not true in
the mean-reversion model. Note also in Figure 8 that for the base-case volatility of 25% p.a., at t =
0, there is a thin intermediate waiting region between US$ 28.30 and 29.90/bbl and a region for
exercising alternative A
2
between US$ 22.90 and 28.30/bbl. Compare these regions from Figure 8
with the option chart in Figure 6.
26
The existence of these intermediate waiting regions between the optimal exercise of alternatives 2
and 3 (for = 25% at t = 0 and for = 45% at t > 1.2 in Figure 8, and in the other simulations we
performed) indicates that the conclusion is more general valid for other stochastic processes that
these waiting regions always occur if it is sometimes optimal to invest in alternative 2 (intermediate
scale alternative). This is a strong conjecture demonstrated only for the geometric Brownian motion
and perpetual options by Dcamps et al. (2003).
The real option to develop, considering all three scales options, is worth US$ 313.86 MM if the
current oil price is US$ 20/bbl. Table 3 shows the option values at t = 0 and the optimal investment
rule for different volatilities and different oil prices.
Table 3: Option Value (US$ MM) and Optimal Action for Mean-Reverting Process
Current Oil Price (US$/bbl)
Volatility (% p.a.) 15 25 30
15 126.21 wait 600 exercise A
2
940 exercise A
3
20 140.92 wait 600 exercise A
2
940 exercise A
3
25 158.45 wait 600 exercise A
2
940 exercise A
3
Comparing Tables 2 and 3, we can see the differences in the option values due to the hypothesis
about the oil price evolution. Options values for mean-reversion are higher for low initial prices
(lower than P ) and slightly lower for high initial oil prices.
Note in Table 3 that the option under the mean-reverting hypothesis is exercised immediately when
the current oil price is above the long-run equilibrium mean (US$20/bbl). This is due to the
expectation of the mean-reverting process, leading to a small probability for oil prices to be too far
from the mean
23
, decreasing the value of waiting for a higher scale alternative that has a threshold
23
The mean-reverting process is a stationary process with a bounded variance. The reversion speed is the force that
pulls back the oil price towards the long-run equilibrium mean. As far is the oil price from the equilibrium as higher is
the reversion force, like a spring force.
27
very far from the long-run equilibrium price to which the prices are attracted. Immediate exercise,
in this case, maximizes the option value.
However, for oil prices lower than the long-run equilibrium mean, the option is not exercised even
for the lower volatility case. In this case, the expectation that prices will revert to the mean
increases the option to wait. These results vary according to the parameters of the model (speed of
reversion, current price, long-run mean, volatility, and time to expiration) and should be taken with
caution. For example, at t = 0, Figure 8 shows that for the very high volatility case of 45% p.a.,
waiting is the optimal policy even for prices of US$ 25 or 30/bbl.
5. Concluding Remarks
This paper analyses the investment opportunity of developing an oilfield. It calculates the
investment option value and also the optimal developing timing and production scale, considering
oil price uncertainties and applying the real options approach.
The investment opportunity in the oilfield is analogous to an American call option on several assets
but with the same underlying oil price stochastic process and with different exercise prices and
different payoffs (different oil price functions) from the different scale alternatives. The payoff
(NPV) of exercising a specific alternative k is the value of the developed reserve using this scale
alternative minus the development cost of the alternative. The economic quality of the reserve
parameter distinguishes the scale alternatives on the benefit side.
The presence of managerial flexibilities, i.e., the options to choose when to develop the oilfield and
to set the optimal production scale, increases the investment option value.
We determine the oil price threshold curves for the exercising options. Instead of one threshold
curve as in standard (financial or real) American call options, we have regions for option exercise
28
and waiting regions. The existence of intermediate waiting regions has not been addressed before in
the real options literature and can occur with both stochastic processes that we analyzed.
According to oil price volatility and the stochastic process for the oil price, the area for exercising
the option can degenerate and the option to wait can dominate immediate development. An increase
(decrease) in the volatility parameter decreases (increases) the area for exercising the option for
both stochastic processes: geometric Brownian motion and mean reversion. This is due to the fact
that the option to wait for better conditions to commit to the investment (waiting for a higher scale)
is higher (lower) in such cases.
Finally, the mean-reverting process - frequently used in commodities modeling - presents different
results than geometric Brownian motion. Specific production scales can never be optimal before
expiration. This is caused by discontinuity of the threshold curves at expiration if the break-even oil
prices for these alternatives imply a negative or zero convenience yield. For geometric Brownian
motion, this issue never occurs because the convenience yield is constant (independent of the oil
price) and commonly assumed to be positive.
Acknowledgements: We would like to thank Petrobras for the financial support of this PUC-
Petrobras project, through the systemic research project named Pravap-14. We thank Thomas
Mariotti for the thorough discussions. Any error is ours.
29
Bibliographical References
1. Ames, W.F. (1977). Numerical Methods for Partial Differential Equations. Academic Press.
New York.
2. Baker, M.P.; Mayfield, E.S; Parsons, J.E. (1998): Alternative Models of Uncertain Commodity
Prices for Use with Modern Asset Pricing. The Energy Journal 19(1):115-148.
3. Batthacharya, S. (1978). Project Valuation with Mean-Reverting Cash Flow Streams. Journal
of Finance 33:1317-1331.
4. Black, F., and M. Scholes. (1973). The Pricing of Options and Corporate Liabilities. Journal of
Political Economy 81:637-659.
5. Bradley, P.G. (1998). On the Use of Modern Asset Pricing Theory for Comparing Alternative
Royalty Systems for Petroleum Development Projects. The Energy Journal 19(1):47-81.
6. Brennan, M.; Schwartz, E. (1978): Finite Difference Methods and Jump Processes Arising in
the Price of Contingent Claims: a Synthesis. Journal of Financial and Quantitative Analysis 13:
461-474
7. Brennan, M.; Schwartz, E. (1985). Evaluating Natural Resources Investments. Journal of
Business 58:135-157.
8. Brodie, M.; J. Detemple (1997): The Valuation of American Options on Multiple Assets.
Mathematical Finance 7(3):241-286
9. Capozza, D.R.; Y. Li (1994): The Intensity and Timing of Investment: The Case of Land.
American Economic Review 84(4):889-904
10.Childs, P.D.; S.H. Ott; A.J. Triantis (1998): Capital Budgeting for Interrelated Projects: A Real
Options Approach. Journal of Financial and Quantitative Analysis 33(3):305-335
30
11.Cortazar, G.; Schwartz, E. (1996): Implementing a Real Options Model for Valuing an
Undeveloped Oilfield. Working Paper, Catholic University of Chile, 16 pp.
12.Dcamps, J-P.; T. Mariotti; S. Villeneuve (2003): "Irreversible Investment in Alternative
Projects". Working Paper, Universit de Toulouse and London School of Economics and
Political Science, June.
13.Dias, M.A.G. (1998): "Investment under Uncertainty in Exploration & Production - Update and
Overview of the M.Sc. Thesis". Workshop on Real Options, Stavanger, May. See the discussion
on economic quality of a reserve at http://www.puc-rio.br/marco.ind/quality.html
14.Dias, M.A.G. (2001): Valuation of Exploration & Production Assets: An Overview of Real
Options Models. Forthcoming in Journal of Petroleum Science and Engineering.
15.Dias, M.A.G.; Rocha, K. (1999). Petroleum Concessions with Extendible Options: Investment
Timing and Value using Mean Reversion with Jumps to Model Oil Prices. Working Paper,
Petrobras and IPEA, at: http://www.puc-rio.br/marco.ind/extend.html
16.Dixit, A. (1993a). Choosing Among Alternatives Discrete Investment Projects Under
Uncertainty Economic Letters 41:265-268.
17.Dixit, A.K. (1993b): The Art of Smooth Pasting. Fundamentals of Pure and Applied
Economics. Harwood Academic Publishers.
18.Dixit, A.; Pindyck, R. (1994). Investment under Uncertainty. Princeton University Press.
19.Geltner, D.; Riddiough, T.; Stojanovic, S. (1996). Insights on the Effect of Land Use Choice:
The Perpetual Option on the Best of Two Underlying Assets. Journal of Urban Economics
39:20-50
20. Graham, J.R.; C.R. Harvey (2001): "The Theory and Practice of Corporate Finance: Evidence
from the Field". Journal of Financial Economics 60:187-243
31
21.Gruy, H.J.; Grab, F.A.; Wood, J.W. (1982). Determining the Value of Oil and Gas in the
Ground. Word Oil, CXCIV:105-108.
22.Kloeden, P.E.; E. Platen (1992): Numerical Solution of Stochastic Differential Equations.
Springer-Verlag Berlin Heidelberg.
23.Majd, S.; Pindyck, R. (1987). Time to Build, Option Value, and Investment Decisions. Journal
of Financial Economics 18:7-27.
24.Merton, R.(1973). Theory of rational option pricing. Bell Journal of Economics and
Management Science 4 (4):141-183.
25.Paddock, J.; Siegel, D.; Smith, J. (1988).Option Valuation of Claims on Real Assets: The Case
of Offshore Petroleum Leases. Quarterly Journal of Economics 103:479-508.
26.Pindyck, R.S. (1988): Irreversible Investment, Capacity Choice, and Value of the Firm.
American Economic Review 78(5):969-985.
27.Pindyck, R.S. (1993): Investments of Uncertain Cost. Journal of Financial Economics 34:53-
76.
28.Robel, G.F. (2001): "Real Options and Mean-Reverting Prices". 5
th
Annual International
Conference on Real Options, UCLA, Los Angeles, July. Available at www.realoptions.org.
29.Rocha, K.M.C. (1996): "Decises de Investimentos Sequenciais em Regime de Incerteza"
(Sequential Investment Decisions in the Presence of Uncertainty). M.Sc. Dissertation, Dept. of
Industrial Engineering, Catholic University of Rio de Janeiro.
30.Smith, G.D. (1971). Numerical Solution of Partial Differential Equations. Oxford
Mathematical Handbooks. Oxford University Press.
31.Schwartz, E.S. (1997): Valuing Long Term Commodity Assets Working Paper, 7-97, UCLA,
23 pp.
32
32.Schwartz, E.; Trigeorgis, L. (2001). Real Options and Investment Under Uncertainty. Classical
Readings and Recent Contributions. MIT Press.
33. Tourinho, O. (1979). The Option Value of Reserves of Natural Resources. Doctoral
Dissertation, University of California at Berkeley.
34.Trigeorgis, L. (1996) Real Options: Managerial Flexibility and Strategy in Resource Allocation;
MIT Press.
33
Appendix A: Finite Difference Method in Explicit Form for Numerically Solving the Partial
Diferential Equation (PDE)
The finite difference method transforms the partial differential equation, Eq. (6) in the text, and its
respective boundary conditions into a difference equation that can be solved numerically.
By using a specific discretization mesh (time step, and oil price step), the explicit form converges to
the exact solution of Eq. (6) and it is easier and faster (especially for a low number of state
variables) than the implicit forms or the Monte Carlo simulations techniques associated with
optimization procedures.
Regarding the free-boundary problems defined in Eq. (6), the explicit form and the discretization
mesh can easily handle the optimization algorithm used to solve those optimal stopping time
problems, like the backward induction style of a stochastic dynamic programming approach.
Implicit forms, however, have to deal with a simultaneous system of equations together with the
optimization procedure.
Numerical solutions for partial differential equations can be found in Ames (1977) or Smith (1971).
Dixit and Pindyck (1994), Chapter 10, applies the same procedure (explicit form together with an
optimization algorithm) to solve an option-pricing problem about sequential investment.
Let F(P,t) at point (P,t) be represented by F
i,j
, where P = iP for i (0,m) and t = jt for j (0,n)
Assume the following partial derivative approximations:
F
PP
[F
i+1,j+1
- 2F
i,j+1
+ F
i-1,j+1
] / (P)
2
; F
P
[F
i+1,j+1
- F
i-1,j+1
] / 2P; F
t
[F
i,j+1
F
i,j
] / t (A1)
We use the central difference approximation to variable price (P), and forward difference
approximation to variable time (t). Applying these expressions in Eq.(6), we have the following
difference-equation:
1 j , i
0
i 1 j , 1 i i 1 j , 1 i i j , i
F p F p F p F
+ +
+ +
+
+ + = (A2)
34
t
1
r
2
i ) r (
i
2
1
p
2 2
P
i
+
=
+
t
1
r
2
i ) r (
i
2
1
p
2 2
P
i
t
1
r
t
1
i
p
2 2
P
0
i
+
+
= (A3)
We can apply the same procedure to the boundary conditions of Eq. (6). It can be shown
24
that the
solution to equation (A2) converges to the solution of Eq.(6) if all the p
i
coefficients in Eq.(A3)
are non-negative numbers. Therefore, we have to choose a discretization time-step, and a price-step
in order to guarantee that condition.
24
See the theorem in Ames (1977), page 65.
35