Substation Commissioning Flowchart Vmar11
Substation Commissioning Flowchart Vmar11
(v.Mar11)
Initial Site Meeting Documentation to be provided by ASP/1 prior to commencement of works Permits (Council and/or RTA) Traffic Control Plans DBYD Plans Project Planning Form including nominated Anticipated Project Completion Date
Commencement of Works ASP/1 to notify ASP C/O of Milestone Inspections (4 days written notice reqd) (Must include major milestones ie.Substation piering, Sub landing, Sub testing)
Non Commissioning CTWs / APs Completion of any non commissioning works that require CTWs or APs APs 4 weeks notice CTWs 2 weeks notice
Request by ASP/1 for Commissioning (Minimum 5 weeks prior to Commissioning) Submission of completed TEI Sheets Submission of Substation Testing Sheets Submission of Operator Request Form Practical Completion Inspection (Minimum 2 weeks prior to Commissioning) All Substation works MUST be completed (only minor rectification works can be completed prior to commissioning) All paperwork MUST be submitted Satisfactory Practical Completion Inspection YES
NO
ASP/1 to Rectify / Complete works ASP/1 to book further PC Inspection once works have been completed or submit any outstanding paperwork ASP/1 to submit a new ORF with revised commissioning date. (Minimum 4 weeks notice required for rescheduled commissioning date)
Substation Commissioning