0% found this document useful (0 votes)
511 views1 page

Substation Commissioning Flowchart Vmar11

The document outlines Ausgrid's substation commissioning procedure. It details the initial documentation required, notification of milestone inspections during construction, lead times for commissioning test works and access permits, the request process for commissioning including submission of test sheets and forms, and the practical completion inspection that must occur minimum 2 weeks prior to commissioning. Any outstanding works or paperwork found during the inspection must be rectified and rescheduled with minimum 4 weeks notice.

Uploaded by

bandara12
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
511 views1 page

Substation Commissioning Flowchart Vmar11

The document outlines Ausgrid's substation commissioning procedure. It details the initial documentation required, notification of milestone inspections during construction, lead times for commissioning test works and access permits, the request process for commissioning including submission of test sheets and forms, and the practical completion inspection that must occur minimum 2 weeks prior to commissioning. Any outstanding works or paperwork found during the inspection must be rectified and rescheduled with minimum 4 weeks notice.

Uploaded by

bandara12
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Ausgrid Substation Commissioning Procedure

(v.Mar11)

Initial Site Meeting Documentation to be provided by ASP/1 prior to commencement of works Permits (Council and/or RTA) Traffic Control Plans DBYD Plans Project Planning Form including nominated Anticipated Project Completion Date

Commencement of Works ASP/1 to notify ASP C/O of Milestone Inspections (4 days written notice reqd) (Must include major milestones ie.Substation piering, Sub landing, Sub testing)

Non Commissioning CTWs / APs Completion of any non commissioning works that require CTWs or APs APs 4 weeks notice CTWs 2 weeks notice

Request by ASP/1 for Commissioning (Minimum 5 weeks prior to Commissioning) Submission of completed TEI Sheets Submission of Substation Testing Sheets Submission of Operator Request Form Practical Completion Inspection (Minimum 2 weeks prior to Commissioning) All Substation works MUST be completed (only minor rectification works can be completed prior to commissioning) All paperwork MUST be submitted Satisfactory Practical Completion Inspection YES

NO

ASP/1 to Rectify / Complete works ASP/1 to book further PC Inspection once works have been completed or submit any outstanding paperwork ASP/1 to submit a new ORF with revised commissioning date. (Minimum 4 weeks notice required for rescheduled commissioning date)

Substation Commissioning