% Progress - 03 - July To 09 - July-2012 (Revised Format)
% Progress - 03 - July To 09 - July-2012 (Revised Format)
ACTIVITY
CF-24A SN. 1 2 3 4 5 6 7 8 9 10 DATE 3-Jul-12 4-Jul-12 5-Jul-12 6-Jul-12 7-Jul-12 8-Jul-12 9-Jul-12
ACTIVITY
CF-24A SN. 1 2 3 4 5 6 7 8 9 10 0 0 0.00% DATE 3-Jul-12 4-Jul-12 5-Jul-12 6-Jul-12 7-Jul-12 8-Jul-12 9-Jul-12
Cutting
Chainage 110+000 to 114+000 - 24A CHAINAGE FROM 111+075 111+075 111+075 111+075 111+075 111+075 TO 111+300 111+300 111+300 111+300 111+300 111+300 QUANTITY (Cum) 9500 9600 9500 9500 9500 9500
ACTIVITY
CF-24A SN. 1 2 3 4 5 6 7 8 9 10 DATE 3-Jul-12 4-Jul-12 5-Jul-12 6-Jul-12 7-Jul-12 8-Jul-12 9-Jul-12
General Filling
Chainage 110+000 to 114+000 - 24A CHAINAGE FROM 111+925 111+925 111+925 111+925 111+925 111+925 TO 112+250 112+250 112+250 112+250 112+250 112+250 QUANTITY (Cum) 6000 6540 4000 4000 4000 4000
ACTIVITY
CF-24A SN. 1 2 3 4 5 6 7 8 9 10 DATE
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
0 183,999 0.00%
Total Quantity as per Original Scope Quantity this Week % Progress this Week Cumulative % Progress
CF-24B SN. 1 2 3 4 5 6 7 8 9 10 DATE 3-Jul-12 4-Jul-12 5-Jul-12 6-Jul-12 7-Jul-12 8-Jul-12 9-Jul-12 Chainage 114+000 to 117+000 - 24B CHAINAGE FROM TO
0 0 0.00% 0.00%
Total Quantity as per Original Scope Quantity this Week % Progress this Week Cumulative % Progress
CF-24B Chainage 114+000 to 117+000 - 24B DATE 3-Jul-12 4-Jul-12 5-Jul-12 6-Jul-12 7-Jul-12 8-Jul-12 9-Jul-12 CHAINAGE FROM TO
Total Quantity as per Original Scope Quantity this Week % Progress this Week Cumulative % Progress
CF-24B Chainage 114+000 to 117+000 - 24B DATE 3-Jul-12 4-Jul-12 5-Jul-12 6-Jul-12 7-Jul-12 8-Jul-12 9-Jul-12 CHAINAGE FROM TO
Total Quantity as per Original Scope Quantity this Week % Progress this Week Cumulative % Progress
CF-24B Chainage 114+000 to 117+000 - 24B DATE 3-Jul-12 4-Jul-12 5-Jul-12 6-Jul-12 7-Jul-12 8-Jul-12 9-Jul-12 CHAINAGE FROM TO
QUANTITY (Cum)
SN. 1 2 3 4 5 6 7 8 9 10
QUANTITY (Cum)
SN. 1 2 3 4 5 6 7 8 9 10
QUANTITY (Cum)
SN. 1 2 3 4 5 6 7 8 9 10
QUANTITY (Cum)
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
0 0.00%
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
0 0.00%
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
0 0.00%
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
0 0.00%
ACTIVITY
CF-24C SN. 1 2 3 4 5 6 7 8 9 10 DATE 3-Jul-12 4-Jul-12 5-Jul-12 6-Jul-12 7-Jul-12 8-Jul-12 9-Jul-12
ACTIVITY
CF-24C SN. 1 2 3 4 5 6 7 8 9 10 0 0.00% DATE 3-Jul-12 4-Jul-12 5-Jul-12 6-Jul-12 7-Jul-12 8-Jul-12 9-Jul-12
Pavement Gatch
Chainage 117+000 to 121+000 - 24C CHAINAGE FROM TO QUANTITY (Cum)
ACTIVITY
CF-24C SN. 1 2 3 4 5 6 7 8 9 10 0 0.00% DATE 3-Jul-12 4-Jul-12 5-Jul-12 6-Jul-12 7-Jul-12 8-Jul-12 9-Jul-12
Sub Grade
Chainage 117+000 to 121+000 - 24C CHAINAGE FROM TO QUANTITY (Cum)
ACTIVITY
CF-24C SN. 1 2 3 4 5 6 7 8 9 10 0 0.00% DATE 3-Jul-12 4-Jul-12 5-Jul-12 6-Jul-12 7-Jul-12 8-Jul-12 9-Jul-12
Sub Ballast
Chainage 117+000 to 121+000 - 24C CHAINAGE FROM TO QUANTITY (Cum)
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
0 0.00%
ACTIVITY
CF-25A SN. 1 2 3 4 5 6 7 8 9 10 DATE 3-Jul-12 4-Jul-12 5-Jul-12 6-Jul-12 7-Jul-12 8-Jul-12 9-Jul-12
ACTIVITY
CF-25A SN. 1 2 3 4 5 6 7 8 9 10 0 0.00% DATE 3-Jul-12 4-Jul-12 5-Jul-12 6-Jul-12 7-Jul-12 8-Jul-12 9-Jul-12
Cutting
Chainage 121+000 to 124+000 - 25A CHAINAGE FROM 130+200 130+200 130+200 130+400 130+400 130+400 TO 130+725 130+725 130+725 130+675 130+675 130+675 QUANTITY (Cum) 10800 11900 6280 10800 9000 12000
ACTIVITY
CF-25A SN. 1 2 3 4 5 6 7 8 9 10 DATE 3-Jul-12 4-Jul-12 5-Jul-12 6-Jul-12 7-Jul-12 8-Jul-12 9-Jul-12
General Filling
Chainage 121+000 to 124+000 - 25A CHAINAGE FROM TO QUANTITY (Cum)
ACTIVITY
CF-25A SN. 1 2 3 4 5 6 7 8 9 10 0 0.00% DATE
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
60780 0.00%
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
0 0.00%
Total Quantity as per Original Scope Quantity this Week % Progress this Week Cumulative % Progress
0 0.00% 0.00%
Total Quantity as per Original Scope Quantity this Week % Progress this Week Cumulative % Progress
Total Quantity as per Original Scope Quantity this Week % Progress this Week Cumulative % Progress
0 0.00% 0.00%
Total Quantity as per Original Scope Quantity this Week % Progress this Week Cumulative % Progress
0 0.00% 0.00%
CF-25B SN. 1 2 3 4 5 6 7 8 9 10 DATE 3-Jul-12 4-Jul-12 5-Jul-12 6-Jul-12 7-Jul-12 8-Jul-12 9-Jul-12
CF-25B SN. 1 2 3 4 5 6 7 8 9 10 0 0.00% DATE 3-Jul-12 4-Jul-12 5-Jul-12 6-Jul-12 7-Jul-12 8-Jul-12 9-Jul-12
CF-25B SN. 1 2 3 4 5 6 7 8 9 10 0 0.00% DATE 3-Jul-12 4-Jul-12 5-Jul-12 6-Jul-12 7-Jul-12 8-Jul-12 9-Jul-12
CF-25B SN. 1 2 3 4 5 6 7 8 9 10 0 0.00% DATE 3-Jul-12 4-Jul-12 5-Jul-12 6-Jul-12 7-Jul-12 8-Jul-12 9-Jul-12
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
0 0.00%
ACTIVITY
CF-25C SN. 1 2 3 4 5 6 7 8 9 10 DATE 3-Jul-12 4-Jul-12 5-Jul-12 6-Jul-12 7-Jul-12 8-Jul-12 9-Jul-12
ACTIVITY
CF-25C SN. 1 2 3 4 5 6 7 8 9 10 0 0.00% DATE 3-Jul-12 4-Jul-12 5-Jul-12 6-Jul-12 7-Jul-12 8-Jul-12 9-Jul-12
Pavement Gatch
Chainage 127+000 to 113+000 - 25C CHAINAGE FROM TO QUANTITY (Cum)
ACTIVITY
CF-25C SN. 1 2 3 4 5 6 7 8 9 10 0 0.00% DATE 3-Jul-12 4-Jul-12 5-Jul-12 6-Jul-12 7-Jul-12 8-Jul-12 9-Jul-12
Sub Grade
Chainage 127+000 to 113+000 - 25C CHAINAGE FROM TO QUANTITY (Cum)
ACTIVITY
CF-25C SN. 1 2 3 4 5 6 7 8 9 10 0 0.00% DATE 3-Jul-12 4-Jul-12 5-Jul-12 6-Jul-12 7-Jul-12 8-Jul-12 9-Jul-12
Sub Ballast
Chainage 127+000 to 113+000 - 25C CHAINAGE FROM TO QUANTITY (Cum)
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
Quantity ahieved this week Total Quantity as per Original Scope Progress % Achieved for this Week
0 0.00%
Total Quantity as per Original Scope Quantity this Week % Progress this Week Cumulative % Progress
0 0.00% 0.00%
Total Quantity as per Original Scope Quantity this Week % Progress this Week Cumulative % Progress
0 0.00%
Total Quantity as per Original Scope Quantity this Week % Progress this Week Cumulative % Progress
0 0.00%
Total Quantity as per Original Scope Quantity this Week % Progress this Week Cumulative % Progress
0 0.00%