NASA: 190904main 092607 TL

This document is a daily schedule and log for the crew of the International Space Station. It details the activities of the Commander (CDR), Flight Engineer 1 (FE-1), and Flight Engineer 2 (FE-2) over a 24 hour period, including morning inspections, breakfast, exercise, experiments, maintenance tasks, crew conferences, media events, and planning meetings. Key events include testing a thruster, purging hardware, collecting plant experiment data, transferring cargo between modules, and preparing equipment for return to Earth.

Uploaded by

NASAdocuments
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views2 pages

NASA: 190904main 092607 TL

This document is a daily schedule and log for the crew of the International Space Station. It details the activities of the Commander (CDR), Flight Engineer 1 (FE-1), and Flight Engineer 2 (FE-2) over a 24 hour period, including morning inspections, breakfast, exercise, experiments, maintenance tasks, crew conferences, media events, and planning meetings. Key events include testing a thruster, purging hardware, collecting plant experiment data, transferring cargo between modules, and preparing equipment for return to Earth.

Uploaded by

NASAdocuments
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Page 1 of 2

Radiogram No. 6182u Form 24 for 09/26/07


ATTITUDE CONTROL THRUSTER [ДО] INHIBIT. TESTING PRIMARY ЛКЦ2Б36 WITH ВД-СУ MODE
DEACTIVATED AND БИТС POWERED OFF
GMT CREW ACTIVITY

06:00-06:10 CDR, FE-1 Morning inspection


06:00-06:05 FE-2 SLEEP - data logging
06:05-06:10 FE-2 Morning inspection
06:10-06:40 Post-sleep
06:40-07:30 BREAKFAST
07:30-07:45 Daily Planning Conference (S-band)
07:45-08:15 . Kentavr suit adjustments. Tagup with specialists (S-band)
08:15-09:15 FE-2 Physical Exercise (CEVIS)
08:15-08:35 FE-1 Elektron purge and power down
PLASMA-ISS. Hardware installation and setting up. Tagup with specialists (S-
08:15-09:30 CDR
band)
08:35-09:05 Sampling water from Elektron Water Supply System [СВО]
FE-1 Changeout of multi-filtration unit assembly for Elektron SVO (БКО #507024, b/c
09:05-09:35
00043063R (ФГБ1ПГО_4_406_1). Discard removed unit
09:15-10:45 FE-2 Physical Exercise (RED)
09:35-11:05 FE-1 Physical Exercise (TVIS) Day 2
09:45-10:00
10:10-10:25
CDR PLASMA-ISS. Experiment ops. Tagup with specialists (S-band)
10:30-10:45
10:55-11:10
11:05-11:25 FE-1 PLANTS-1. Data collection and downlink
11:20-11:35 PLASMA-ISS. Experiment ops. Tagup with specialists (S-band)
CDR
11:35-12:00 PLASMA-ISS. Hardware stow. Tagup with specialists (S-band)
11:45-11:55 PAO hardware setup
FE-1
11:55-12:40 Activation of Progress 361 (DC1)
12:00-12:40 CDR СОЖ Maintenance
12:10-13:50 FE-2 Hardware Pre-pack for Return on 10A
12:40-13:00 Removal and inspection of quick-release screw clamps, interface video
13:00-13:20 CDR, FE-1 ТКГ-СО1 [Progress-DC1] and СО1-СУ [DC1-DM] Transfer Hatch Closure
13:20-14:20 СО1-ТКГ [DC1-Progress] Hatch Leak Check
13:50-14:20 FE-2 ISS-15 FE-2/ ISS-16 FE-2 Crew Conference (Ku + S-band)
14:20-15:20 LUNCH
15:20-15:30 FE-1 Downlink DC1-to-Progress Interface Video (Ku + S-band)
15:20-15:30 CDR, FE-2 Crew prep for PAO
TV greetings dedicated to the 50th Anniversary of the first satellite launch (Ku +
15:30-15:50 .
S-band)
16:00-16:45 CDR Prep for Work
16:00-16:05 Payload status check
FE-2
16:05-16:15 CWC audit
Page 2 of 2

16:35-17:35 FE-1 Physical Exercise (TVIS) Day 2


16:45-17:20 CDR Physical Exercise (RED)
16:45-16:50 HAM radio setup
FE-2
16:50-17:00 HAM radio session
17:20-19:15 CDR Physical Exercise (TVIS) Day 2
17:20-17:25 Setting up v/camera
17:25-17:35 US hardware transfer to RS prior to Soyuz relocation
FE-2
17:35-17:55 PCS relocation
17:55-18:10 Questionnaire - journal entry
17:55-18:15 FE-1 IMS update
18:10-18:45 FE-2
Prep for Work
18:15-19:15 FE-1
18:45-18:50 MSG – daily deactivation of the SAME experiment
18:50-19:10 FE-2 Prep for Work
19:10-19:15 Transfer TVIS/RED/CEVIS/HRM data to MEC
19:15-19:30 Daily Planning Conference (S-band)
19:30-20:00 DINNER
20:00-20:30 Daily food prep
20:30-21:30 Pre-sleep
21:30-09:00 SLEEP
Task List FE-1 GSF-JAXA. ТБУ temperature monitoring (in the morning)
Note: See OSTP for references to US activities.
End of Radiogram