MBA 6113 (AHS) Assignment FT 3
MBA 6113 (AHS) Assignment FT 3
MBA 6113 (AHS) Assignment FT 3
SL:
ID:
Name:
Sec:
1. Apply Critical Path Method to the network diagram below to identify the all the available paths and their duration. Also, check mark the critical path of the project. Provide your answer in the table, below.
SL
Path
Path Calculation
Duration
CP
2. Draw the Project Schedule / Gantt Chart, for the above network diagram in question number six. Identify the Finish to Start (FS) Dependency and the Critical Activity (CA). Provide your answer in the table, below. Project Schedule / Gantt Chart (Activities in Days) Activity A B C D E F G H I J D Y 1 6 3 8 7 5 4 4 2 1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 CA