CX Flowchart
CX Flowchart
Cx PLAN REVIEW
- REQUEST NEEDED CHANGES FROM CM & A/E
Cx
DEVELOP Cx MANUAL
Cx & GC
EQUIPMENT DELIVERY
GC
APVD
PRE-INSTALL CHECK
GC
APVD
INSTALL EQUIPMENT
GC
REJ
REJ
Cx ARCHIVES
PRE-START CHECK
GC
APVD
EQUIPMENT START-UP
GC
APVD
FUNCTIONAL TEST
GC
APVD
OWNER TRAINING
MAY OCCUR A MINIMUM OF TWO WEEKS AFTER O&Ms ARE APVD AND EQUIPMENT IS DEBUGGED GC
APVD
PROJECT COMPLETE
- Cx BUDGET REVIEW - LESSONS LEARNED
FINAL Cx REPORT
Cx
REJ REJ
Cx ARCHIVES
REJ
Cx ARCHIVES
REJ
Cx ARCHIVES
CORRECT DEFICIENCIES
GC
Cx ARCHIVES
FLOWCHART LEGEND
DISPUTE PROCESS
Cx REJECTION UPHELD
NEGOTIATION & REMEDIATION
REFER TO UM STANDARD GENERAL CONDITIONS
=
RESUBMIT OR RETEST
PROCESS DOCUMENT
A/E = ARCHITECT/ENGINEER
=
Cx REJECTION
Cx REJECTION DISPUTED
DECISION
Cx REJECTION OVERRULED
Page 1
Cx Flowchart.vsd