Turbo Generators PDF
Turbo Generators PDF
PROCESS OF
TURBO GENERATORS
MANUFACTURING PROCESS OF TURBO GENERATORS
A Mini Project Work
BACHELOR OF TECHNOLOGY
In
ELECTRICAL ENGINEERING
By
“An engineer with only theoretical knowledge is not a complete engineer. Practical
knowledge is very important to develop and apply engineering skills”. It gives me a great
pleasure to have an opportunity to acknowledge and to express gratitude to those who
were associated with me during my training at BHEL.
1. BHEL-An Overview
2. Introduction
3. Stator
4. Rotor
5. Excitation System
6. Cooling system
9. Conclusion
10. References
CHAPTER 1
BHEL-AN OVERVIEW
BHEL-AN OVERVIEW
The first plant of what is today known as BHEL was established nearly 40 years
ago at Bhopal & was the genesis of the Heavy Equipment industry in India.
BHEL is today the largest Engineering Enterprise of its kind in India with excellent
track record of performance, making profits continuously since 1971-1972
BHEL business operations cater to core sectors of the Indian Economy like
Power
Industry
Transportation
Transmission etc.
BHEL has 14 units spread all over India manufacturing boilers, turbines,
generators, transformers, motors etc. Besides 14 manufacturing divisions the
company has 4 power sector regional centres, 8 service centres and 18 regional
offices and a large number of project sites thus enable the Company to promptly
serve its customers and provide them with suitable products, systems and
services efficiently and at competitive prices. The high level of quality & reliability
of its products is due to the emphasis on design, engineering and manufacturing
to international standards by acquiring and adapting some of the best
technologies from leading companies in the world, together with technologies
developed in its own R&D centres.
Against the picturesque Shivalik foot hill of the Himalayas and on the banks of the
holy Ganga in Ranipur near Hardwar are located the two manufacturing plants of
BHEL: Heavy Electrical Equipment Plant (HEEP) and Central Foundry Forge Plant
(CFFP) employing about 10000 people.
Located immediately south of HEEP is the Central Foundry Forge Plant setup.
The Heavy Electrical Equipment Plant was set up in technical collaboration with
M/s Prommash-export of USSR. The construction of the plant commenced in
1962 and the production of equipment was initiated in early 1967. In 1976, BHEL
entered into a collaboration agreement with M/s Kraftwerk Union A.G. of West
Germany for design, manufacture, erection and commissioning of large size steam
turbines and turbo generators of unit rating up to 1000MW.
The BHEL plants in Haridwar have earned the ISO-9001 AND 9002 certificates for
its high quality and maintenance. These two units have also earned the ISO-14001
certificates.
CHART SHOWING DIFFERENT BLOCKS OF BHEL, HARIDWAR
HARIDWAR
FACTURING) BLOCK
BLOCK-5: CONDENCER FABRICATION & FORGR BLOCK
STAMPING SHOP)
INTRODUCTION
2. INTRODUCTION
2.1 TURBOGENERATOR:
*Faraday’s Law:
E.M.F. (Voltage) is induced in a closed path due to change of flux linkages and is
proportional to rate of change of flux linkages. The change in flux linkages can be
caused by change in flux in a stationary coil or by motion of coil with constant flux
or both.
E = −N dϕ/dt
2.3 SIZING OF GENERATOR MODULE:
P=K.As.Bδ.D2 L .ns
Here
P = MW output
ns = Rated speed
MW Rating:
Speed:
2.7.1 STATOR
Stator frame
Stator core
Stator winding
End cover
Bushings
Generator terminal box
2.7.2 ROTOR
Rotor shaft
Rotor winding
Rotor retaining ring
Field connection
STATOR
STATOR
3. STATOR
1. Stator frame
2. Stator core
3. Stator winding
4. Stator end cover
5. Bushings
6. Generator terminal box
For the reduction of hysteresis loss, silicon alloyed steel is used since it has low
value of hysteresis coefficient (Kh) for the manufacture of core. The composition
of silicon steel is
Steel-95.8%
Silicon-4.0%
Impurities-0.2%
Since the eddy current loss depends on the square of thickness of the lamination.
Hence to reduce eddy current loss core is made up from thin laminations which
are insulated from each other. The thickness of lamination is about 0.5mm.
The stator winding of Turbo Generator is three phase two layer lap winding with
the pitch of winding so adjusted as to reduce the 5th and 7th harmonics. The
number of slots for generation of three phase power must be a multiple of 3 or 6.
Each stator slot accommodates two stator bars.
The bar consists of a large number of separately insulated strands which are
transposed to reduce the skin effect losses.
The strands of small rectangular cross-section are provided with braided glass
insulation and arranged side by side over the slot width. The individual layers are
insulated by vertical separator. In the straight slot portion the strands are
transposed by 540o.
The bar consists of hollow and solid strands distributed over the entire bar cross-
section so that good heat dissipation is ensured. At the bar ends, all the solid
strands are jointly brazed into a connecting sleeve and the hollow strands into a
water box from which the cooling water enters and exists via Teflon insulating
hoses. The strands are transposed by 540o in the slot portion.
3.5.3 INSULATION:
Insulation is basically done to prevent any kind of short circuit between the bar
and the stator core when the bar is assembled in the stator of the machine. The
stator bars are insulated with Micalastic (trade name) insulation.
The ends of the stator frame are closed by pressure containing end shields .The
end covers are made up of non-magnetic material (Aluminium castings) to reduce
stray load and eddy current losses. The end shields feature a high stiffness and
accommodates generator bearings, hydrogen coolers etc. The end shields are
horizontally split to allow for assembly. The end shield used at the turbine end
and exciter end side is different in construction for 500MW. The end cover used in
250 MW is similar in construction.
Fig. Bushings
3.8 GENERATOR TERMINAL BOX:
The phase and neutral leads of the three phase stator windings are brought out of
the generator through six bushings located in the generator terminal box at the
exciter end of the generator.
ROTOR
4. ROTOR
1. Rotating part of turbo generator
2. A high strength alloy steel single forging prepared by vacuum cast steel.
3. Longitudinal slots for housing field winding
4. Damper winding is provided which safeguards the asymmetrical and
asynchronous operative conditions.
5. Rotor of cylindrical type used in turbo generator.
6. Supported on two journal bearings.
7. Provision of axial fan for forced ventilation.
Fig. Rotor
The rotor winding is provided with a lateral gap pick up system of cooling in the
slot portion, ensuring uniform temperature distribution of the winding.
The individual bars are bent to obtain half turns. After insertion into the rotor
slots, these turns are brazed to obtain full turns. The series connected turns of
one slot constitute one coil. The individual coils are connected in a way that north
and south poles are obtained.
Fig.Rotor winding
4.3 INSULATION:
The insulation between the individual turns is made of layer of glass fibre
laminate. The coils are insulated from the rotor body with L-shaped strips of glass
fibre laminate with nomex interlines. Insulation between overhang is done by
blocks mad of HGL.
4.4 ROTOR SLOT WEDGES:
The rotor of turbo generator is rotating at a very high speed therefore to protect
the winding against the effects from centrifugal forces they are secured firmly by
rotor slot wedges. The slots wedges are made of copper alloy. They are also use
ad damper winding bars. The wedge and retaining ring act as damper winding in
case of asymmetrical and asynchronous operation. The ring is coated with silver
which acts as short circuit rings in damper windings.
To protect end winding of rotor from flying out from the rotor due to centrifugal
forces rotor retaining ring is used. Retaining rings are made from high tensile non-
magnetic alloy steel forgings in order to reduce stray losses. These act as short
circuit rings to the induced current to the damper system. To ensure low contact
resistance retaining rings are coated with nickel, aluminium, silver.
The field current is supplied to the rotor winding through radial terminal bolts and
two semicircular conductors located in the hollow bores of the exciter and rotor
shafts. The field connection provides electrical connection between the rotor
winding and exciter.
4.6.1 TERMINAL LUG:
The terminal lug is a copper conductor of rectangular cross section. One end of
terminal lug is braced to the rotor winding while the other end is screwed to the
radial bolt.
The field current leads located in the shaft bore is connected to the terminal lug
at the end winding through a radial bolt.
The leads are run in the axial directions from the radial bolt to the end of rotor.
They consist of two semicircular conductors insulated from each other by an
intermediate plate and from the shaft by tube.
The cooling air in generator is circulated by axial fans located on the rotor shaft. In
250 MW rotor two axial flow fans are located on both turbine as well as exciter
end side whereas in 500 MW axial fans are located on turbine end side only.
EXCITATION SYSTEM
5. EXCITATION SYSTEM
1. Pilot exciter
2. Main exciter
3. Rectifier wheel
4. Automatic voltage regulator
The three phase pilot exciter has a revolving field with permanent magnet poles.
The armature winding is housed on the stator. The three phase a.c. generated by
the pilot exciter is rectified and controlled by automatic voltage regulator to
provide variable D.C. for exciting the main exciter. The three phase main exciter
has stationary field with revolving armature. Thus three phase a.c. power is
produced in main exciter which is rectified by rotating rectifier bridge and is fed to
the field winding of the rotor (turbo generator) through dc leads.
Three phase pilot exciter is 16 pole revolving field units. The stator accommodates
three phase armature winding and magnetic poles are placed on the rotor. Thus
rotating flux is produced which cuts the stationary armature conductors and three
phase a.c. is generated.
Stator core
1. Silicon diodes
2. Aluminium heat sink
3. Fuses
4. RC circuit
The main component in the rectifier wheel is silicon diodes which are arranged in
rectifier wheel in three phase bridge circuit. The direct current from rectifier
wheel is fed to DC leads and then to the field winding of the rotor.
5.5 Flowchart of Brushless Excitation:
To alternator field
Thyristor Controlled
Bridge
COOLING SYSTEM
6. COOLING SYSTEM
Power output of electrical machine is given by
P=K.As.Bδ.D2 L .ns
Cold air
When the problem of increasing generator rating was talked in it became clear
that the air cooled machine did not provide the necessary scope for progress. Not
only in circulating the requisite of air through the machine but also because high
fan power required to circulate. Evidently to push up generator ratings hydrogen
is used as cooling medium.
Advantages of Hydrogen as Cooling Medium:
a) Increased efficiency: The density of H2 is only 0.07 times the density of air and
therefore the power required to circulate H2 is less than that required in air.
b) Increase in rating: H2 has a heat transfer coefficient 1.5 times and its thermal
conductivity is 7 times that of air. Consequently when H2 is used as a coolant,
the heat is more rapidly taken up from the machine parts and dissipated.
c) Elimination of fire hazard: The outbreak of fire inside the machine is
impossible as H2 does not support combustion.
d) Smaller size of coolers: The size of cooler required is smaller in size.
In large rating machines, hydrogen cooling is not sufficient to remove the entire
heat generated. For additional cooling, a Primary Water (PW) cooling system with
demineralised water flowing through the hollow stator conductors is used. The
rotor conductors are hydrogen cooled.
GENERATOR TECHNICAL
DATA
7. GENERATOR TECHNICAL DATA
Chapter 8
TESTING OF TURBO
GENERATOR
8. TESTING OF TURBO GENERATOR:
To ensure that all functional requirements are fulfilled, and to estimate the
performance of generator, the TURBO GENERATORS are required to undergo
some tests.
8.1 SHORT CIRCUIT TEST:
The machine is run at rated speed and drive motor input voltage and current are
noted and excitation is gradually increased in steps, at 20, 40, 60, 80, 100% rated
current of machine. The short circuit characteristics is plotted from short circuit
results by selecting X-axis as field current and Y-axis as % rated current.
The machine is run at rated speed and the motor input voltage and current are
noted and excitation is gradually increased in steps, at 20, 40, 60, 80, 90, 95, 100,
105, 110 and 120 % of rated voltage of machine. The open circuit characteristics is
plotted from open circuit results by selecting X-axis as field current and Y-axis as
% rated voltage.
This testing is basically done to check any short circuit between ant two
consecutive conductors of a bar. For this test all the bare conductors at both the
ends are separated from each other so that they do not short circuit. Then a live
wire is connected to a conductor and received from it consecutive conductor to
light a lamp. Hence if the lamp lights up it shows short circuit between the two
conductors due to improper insulation between them.
It shows insulation failure between the conductors, these conductors are then
replaced and bar is followed through all the previous processes. Similarly all the
conductors are checked for any short circuit.
Here,
Up = Excitation voltage
8.5 HELIUM TEST:
Helium test is done to check leakage within the bar and at the brazed portions.
Any minute leakage which couldn’t be checked by water test can easily be
observed by helium test because helium is one of the lightest gas.
In helium test, whole of the bar is wrapped in the polythene excluding the end
points. The helium gas at pressure of 11Kg/Cm2 is passed through the bar and a
probe connected to the gauge is inserted inside the polythene at different places.
The gauge will show deflection if there is any helium atom present. Gauge will
show reading even if 1 helium atom in 100000 atoms is present.
CHAPTER 9
CONCLUSION
CONCLUSION
Here we learnt about how the electrical equipments are being manufactured and
how they tackle the various problems under different circumstances. At least we
could say that the training at BHEL Haridwar is great experience for us and it really
helped us in making or developing our knowledge about turbo generator and
other equipment used in power generation.
REFERENCES
http://www.bhel.com/about_publication.php
http://en.wikipedia.org/wiki/Turbo_generator
http://en.wikipedia.org/wiki/Hydrogen-cooled_turbogenerator