Production Planning
Production Planning
Production Planning
machines:
Ans: The following are the ten steps involved to schedule ‘n’ jobs on two machines:
Step 3) Construct a job array, called sequencing matrix. To construct the matrix the jobs
to be processed are recorded row head wise, the machines to be employed to process the
jobs are recorded column head wise and the processing time of each job is recorded
against the under the respective machine.
Step 4) Scan the job array and identify the smallest processing time.
Step 7) Repeat steps 4, 5, 6 and 7 for remaining processing times, placing the jobs next to
first or next to last until all jobs are scheduled.
Step 8) Calculate the total elapsed time to process all jobs through the two machines.
START
Does the No
smallest
time occur
on first Schedule the job
corresponding to the
Yes smallest time as close
to the end of the job
Schedule the job corresponding to the sequence as possible
smallest time as close to the beginning of
the job sequence as possible.
No Have all
jobs been
scheduled
Yes
Calculate start and finish time of
each job on machine A
STOP
b) Five jobs A, B, C, D and E are required to be processed on two machines M1 and
M2. Each job has to be processed on machine M1 and then on machine M2. The
order of the completion of jobs has no significance. The processing time hours for
five jobs on the two machines is as under:
Job
Machine A B C D E
Machine #1 4 17 14 9 11
Machine #2 5 7 12 2 6
Ans: The smallest time in the job array is 2 hours and it appears for the first stage. The
corresponding job D therefore is scheduled last and its entry is made in the last cell of the
sequencing bar.
The next smallest time is 4 hrs and it occurs on the job A which is present in the sequence
of Machine #1. Therefore the entry is made in the first cell of the sequencing bar.
A D
Deleting the job schedule leaves us with 3 more entries in the array.
The next smallest time is 6 and is present in the job E, which is present in the sequence of
Machine #2. Therefore the entry is made in the last but one cell of the bar.
A E D
Deleting the job schedule leaves us with 2 more entries in the array.
The next smallest time is 7 and is present in the job B, which is present in the sequence of
Machine #2. Therefore the entry is made in the 3rd cell of the bar.
A B E D
Since the last job is left unscheduled, it is therefore placed in the empty cell:
Therefore the optimum sequence, therefore is A, C, B, E & D
A C B E D
2. What is Production Planning and Control? What are its key functions? How does
PPC contribute to the two basic objectives namely “long term growth of business”
and “Profit of the company”?
Ans: Introduction: Production Planning is a centralized activity (normally conducted in
the office) and includes such functions as order preparation, material control, process
planning, tools control and scheduling. Production control, on the contrary, a diffused
activity (usually conducted in the shops) and includes such functions as dispatching,
progressing and expediting.
Long term growth of business and profitability are the two basic objectives of an
organization. For long term growth, the company must have enough orders and for
enough orders it must have large number of satisfied customers.
1) Timely delivery
2) Advance communication in case of expected late shipments
3) Short lead time in emergency
4) Consistent and good quality of products
5) Competitive price.
Good production planning and control is necessary to meet these essentials of customers’
satisfaction. Good PPC system is also necessary to minimize waiting time costs, overtime
costs, inventory costs and other manufacturing overheads. Goods PPC system helps to
improve utilization or resources morale of the employees.
3) (a) How does Production Planning differ from Production Control?
Ans:
Production Planning: It is the determination, acquisition and arrangement of all
facilities necessary for future production of items. In other words, production planning is
essentially a pre-production activity, associated with the design of the production system.
1) Planning involves collection and maintenance of1) Control involves dissemination of data,
data regarding time standards, materials and preparation of reports regarding output, machine
their specifications, machines and their process and labour utilization, labour efficiency,
capabilities, drawing and operational layouts percentage defectives etc.
etc.
2) Planning is seeing that requirements-tools,2) Control is seeing that the requirements are
machines, men, instructions, authorizations and actually made available at the right place in the
the like-well be available at the right time and in right quantities.
the right quantities and are of proper quality.
3) Planning involves preparation of load charts and3) Control involves actual seeing that the jobs are
fitting various work orders into uncommitted started and completed as per schedule prepared
time available on the company’s facilities (men by scheduling cell of the PPC.
or machines).
4) Planning involves preparation of all necessary4) Control involves actual issue of forms and paper
forms and paper work work.
5) Planning involves designing suitable feedback5) Control involves keeping track of what is
as to what may happen. happening and collecting information as to what
6) Planning involves forward thinking as to the has happened.
remedial action to be taken if the job fails6) Control involves suggesting remedial action
behind schedule. when the job is falling behind schedule.
Planning therefore, is a centralized activity (in Control is thus a diffused activity (in the shops)
the office) and includes such function as and includes functions such as dispatching,
materials control, tools control, preprocess progressing and expediting.
planning and scheduling.
(b) What type of information is necessary for efficient functioning of PPC
department? Which department in the organization originates this information?
Ans: Introduction: The efficiency of Production Planning and Control department
depends upon the information it gets from other departments and the accuracy of such
information. To prepare load and schedule chat, it must know the preventive maintenance
schedule. To give realistic delivery date, it must know the work content of each job.
Production Planning and Control department generally requires the following
information:
i) Having factors of production for the peak demand and utilizing extra capacity
to manufacture products of non-seasonal nature or taking up subcontract work
etc.
ii) Having factors of production for the least demand and meeting requirements
of extra capacity by overtime or by holiday working or by hiring capacity or
by sub-contracting etc. Production planning and control and the purchasing
function under such a situation assumes very important role in the company.
If the work is highly repetitive and the number of workmen is not very large, the work of
planning may be performed directly by the line staff, there being thus no formal PPC
department in the company. And in manufacturing units where plant and machinery is
laid out as per sequence of operations and there is little difference in machine capacity for
different products, the PPC may be sub-division of the manufacturing department.
In firms, where either the product variety is very large or where machine capacities are
different for different products, or where plant and machinery is laid out as per function
in different departments not related to each other, PPC should be set up as an independent
department with the head of the department responsible to the managing director, General
manager, or works manager, depending upon the magnitude and complexity of the
planning functions and the size of the firm.
DEGREE OF CENTRALISATION:
Degree of centralization implies extent to which planning activities are performed by
PPC. Two systems in general are available:
Decentralized planning gives line staff sense of participation and opportunity to use their
experience but it takes away lot of their valuable time in performing planning functions
The trend today is towards the blend of “Centralized” and “Decentralized” system, called
semi-centralized planning. It combines the merits of both the systems and it especially
gives better results in a large industrial complex.
Under semi-centralized planning, the scheduling of operations within the pre-fixed period
and allotment of work to men and machines is done by line staff while overall co-
ordination of materials ordering, sub-contract work planning, progressing and follow-up,
capacity planning man power planning, maintenance planning etc, is done centrally by
the staff specialists.
Each cell may be headed by a senior engineer and supported by planning assistant(s) and
clerk(s).
A representative production planning and control department of a medium size firm is
illustrative in the following figure.
General
Manager
6) (a) “Data given on the process sheet can be put to lot many uses in the organization”
Discuss.
Ans: Introduction: Process planning is the process of establishing the shortest and most
economical path that each part is to follow from the point it is received as raw materials until it
leaves as furnished part or a finished product. Process planning indicates operations to be
performed and their sequence; specified the machine tool for each indicated operation; shows the
necessary tooling (jigs and fixtures, cutting tools, cams and templates, measuring instruments,
and gauges) for each indicated operation; gives manufacturing data such as speeds and feeds;
sometimes the specifications of the skill for each operation. The document which incorporates
this vital information is called process sheet or route sheet.
Text: The information contained in the process sheet can be put to a variety of uses:
(i) Scheduling: The scheduling cell of PPC can obtain for each operation the set-
up and the processing time. This information helps them to prepare load and
schedule charts
(ii) Materials Movement: The Shop supervisor and the dispatch clerk can know
where the jobs require to be sent for the next operation.
(iii) Cost Reduction and Cost Control: A process sheet gives an idea of the
tooling (standard tools, jigs and fixtures, templates, gauges and measuring
instruments) which could be arranged prior to the starting of the operation.
This cuts down set-up time and reduces labour cost and overheads.
(iv) Costing: Costing group can use the information to determine pre and post
production cost of each component.
(v) Method of Working: Method study engineer without going on the shop floor
can know as to how presently the part is being manufactured.
(vii) Shop efficiency: Operation wise time data given in the process sheet is also
helpful to the shop personnel to know whether the shop performance is in line
with the expected performance.
(b) A Small pump shaft is to be manufactured from a round bar on four machines in
a workshop. It is first cut to length on a power hack-saw which can produce 12
pieces per hour. The cut pieces are then “faced to length” and “centered” on a
special facing and centering machine. Once this machine is set-up (taking 30
minutes), the operator can complete 30 pieces per hour. Faced and centered pieces
are next moved to the copying lathe. It takes 45 minutes to set up the copying lathe
and 3 minutes to turn each piece. The final operation is cutting of the keyways on a
special purpose key-way milling machine. It takes 8.50 minutes to cut hey-way on
each piece. 8.0 minutes are required to set-up the hack-saw and 10 minutes to set-up
the key-way milling machines. After cutting the key-ways the parts are debarred
and inspected.
Draw up a process sheet for the manufacture of this part. Though tooling and
gauges do not require to be indicated yet their relative position on the process sheet
should be shown.
Sol:
PTO
Part Name: Pump Shaft
Process Sheet Part No. : P0401125
Set Up Time
Op. No. Operation Description Machine Tooling Set up Std min
1 Power Hack Saw 80 60
Cutting it to Length
2 Spiral Machine 30 60
Faced to length & Center 12
3 Lathe Machine 45 3
Copying Lathe 30
4 Key way milling 10 8.50
Cutting Keyways
Machine
REVISION DATE:
7 (a) Why is it necessary to record the progress of work? What different methods
are available to collect information?
Ans: Introduction: Progressing is the process of checking actual performance against
the production plan and reporting exceptional deviations to the concerned authorities for
the corrective action. Progressing function consists in keeping a watch on flow of
materials, recognition of delays and interruptions, taking steps to rush up the remaining
operations and communicating possible delays to the customer (wherever necessary)
It is sometimes argued that progressing is only a substitute for poor planning. Should a
driver take his hands off the steering wheel because the road is straight? Should a pilot
divert his attention from the control board because the weather is fine? No! They can’t do
this, similarly, progressing is required even if the material control and process planning
functions are discharged satisfactorily, scheduling is done properly, manufacturing orders
are released. There are usually a number of factors which tend to push the schedules off
the mark. Some of the notable ones are as under:
(b) Explain with a diagram any two methods to collect data on progress of work.
Ans: Daily Production Report: It is prepared by the supervisor, this is another method
of obtaining feedback. A daily production report contains fixed space to record:
This report may be prepared either by the shop supervisor or the patrolling inspector
and is collected at the end of the shift or the next day by the progress clerk of the PPC
department. This method is best suited for large workshop having a process type of
layout producing number of non-standard parts.
SECTION : Gear Shop
DATE : 12.11.04
DAILY PRODUCTION REPORT SHIFT : First Shift
Machin Operator’s Part Name & Hours Worked Qty. First Inspection Tole Idle
e Name Code No. produc Qty. OK OK Rej Code Hours
From To ed _
507 A.R. Yande Double Gear: 7AM 3.30 PM 78 20 20 - -
29 teeth ½ Hr
508 -do- Cam Shaft Gear 7AM 3.30 PM 42 18 17 1 E
(Op. No. 80) ½ Hr
509 Manjit Idler Gear 7AM 3.30 PM 60 15 15 - G
This method is suitable for tool rooms, jobbing shops or workshops producing one or few
numbers of a component.
Hungarian method is the most efficient method for solving an assignment problem
involving minimum objective. Though its standard procedure is for balanced problems,
minimization problem, free from restrictive, but it can be applied to even special
situations by adopting additional steps.
Basic Principles:
The Hungarian method is based on the following properties:
(i) If a constant element is added or subtracted from every element of any row or
column in the given cost matrix, an assignment that minimizes the total cost in
the original matrix also minimizes the total cost in the revised matrix.
(ii) In an assignment matrix, solution having zero total cost is the optimal
solution.
Assumptions:
(ii) Tasks differ in their work contents and facility in their capabilities
(iv) As only one task can be assigned to each facility, the assignment matrix must
be of n x n size. (In case the matrix is not square, dummy rows or columns,
equal to the difference, are added).
Step 2: Select the smallest element in each row and subtract it from every element of
that row.
Step 3: Select the smallest element in each column of the reduced matrix obtained
from step 2 and subtract it from every element of that column.
Step 4: Cover all zero elements by minimum number of straight lines (horizontal and
vertical lines only). If the number of lines drawn is equal to n(number of
rows/columns), the solution is optimal and proceed to Step 7. if the number of lines
drawn is smaller than n, go to step 5.
Step 5: Select the smallest uncovered element (i.e., smallest element not covered by
the lines), subtract it from all uncovered elements including itself, and add it to the
elements covered twice (i.e. elements located at the intersection of any two lines), and
reproduce other elements (i.e. elements through which only one line passes) as they
are.
Step 6: Repeat steps 4 and 5 until an optimal solution is obtained.
Step 7: Given the optimal solution make the job assignments as follows:
(a) Examine the rows one by one starting with the first row until a row with
an exclusive zero (i.e. row with exactly one zero) is found. Mark the zero
by enclosing it in a square indicating assignment of the task to the facility.
Cross out all zeroes (if any) in the column as they cannot be used to make
other assignments.
(b) Examine next the columns for any mutual exclusive zero and mark each as
above, crossing out the remaining zeroes in that row.
(c) Repeat steps (a) and (b) successfully until either of the following
conditions occur:
i. All zeros have been marked / crossed and each row contains one
marked zero. This means that the optimal solution has reached.
ii. All zeros have not been marked / crossed. The remaining
unmarked zeros lie at least two in each row and column. This
means that more than one optimal solution exists.
(b) A drawing office incharge has four tasks and equal number of draught men. His
estimate of time for each job – draught men combination is given (in hours) in the
following matrix:
Draughtmen
Processing time (Hours)
Jobs D1 D2 D3 D4
J1 25 25 20 15
J2 35 20 15 20
J3 25 15 20 18
J4 30 10 25 20
Find out the optimal assignment.
Sol:
Step1: “Express the problem into n x n assignment matrix”. This step has already done in
the case problem.
Step2. “Subtract the smallest element in each row from every element in its row so as to
obtain atleast one zero in each row.”
15, 15, 15 & 10 are the smallest in 1st, 2nd, 3rd and 4th rows respectively. Subtraction of the
smallest element in the row from every element in its row gives rise to an assignment
matrix shown in the following table.
Draughtmen
Processing time (Hours)
Jobs D1 D2 D3 D4
J1 10 10 5 0
J2 20 5 0 5
J3 10 0 5 3
J4 20 0 15 10
Step 3. Subtract the smallest element in each column of assignment matrix obtained in
step 2 from every element in its column. This step gives rise to yet another assignment
matrix…
Draughtmen
Processing time (Hours)
Jobs D1 D2 D3 D4
J1 0 10 5 0
J2 10 5 0 5
J3 0 0 5 3
J4 10 0 15 10
Connect all zeros in the assignment matrix obtained in step 3 by minimum number of
straight lines. Min 4 straight lines are required to connect all zeros.
Step 4.
(a) “Examine the rows one by one, starting with the first row until with an exclusive
zero (i.e. row with exactly one zero) is found. Mark the zero by enclosing it in a
square indicating assignment of the task to the facility. Cross out all zeros in the
same column as they cannot be used to make other assignments.
(b) Examine next the columns for any mutual exclusive zero and mark each as above,
crossing the remaining zeros in that row.
Here…
1) Row J1 has two exclusive zeros which occur at Junction J1 D1 and J1 D4 hence
the allocation of task J1 is postponed for the time being.
2) Row J2 has 1 exclusive zero which occurs at junction J2 D3 hence Job J2 is
assigned to D3.
3) Row J3 has two exclusive zeros which occur at Junction J3 D1 and J3 D2 hence
the allocation of task J1 is postponed for the time being.
4) Row J4 has 1 exclusive zero which occurs at junction J4 D2 hence Job J2 is
assigned to D2.
5) With the allocation of J2 and J4 we have 2 jobs left out unassigned. Looking at
the matrix again, we see that the Under J3 there are 2 zeros out of which the
position D2 is already assigned to J4 and cannot be reassigned to J1 as this is a
mutual exclusive zero assignment matrix. So the only position left out is J3D1.
Hence the job J3 is assigned to D1.
6) With the allocation of Job J3 to D1 we are left out with J1. Considering the
exclusive assignment matrix. The Job J1 can only be assigned to D4. Hence
J1D4.
J1 D4 15
J2 D3 15
J3 D1 25
J4 D2 10
11 (a) what is critical ratio scheduling? What advantages does this technique have
over other technique?
Ans:
Introduction: Critical ratio scheduling is a technique for establishing and maintaining
priorities among the jobs-be it in a production control department for the purpose of
scheduling or expending in a purchase department for the purpose of “Purchase order
follow up” or in any other department of the company. The technique utilities concept of
ratios called Critical ratios which provide time relationship between when a
product/part/material is required and when it can be made available/supplied.
Definition: A Critical ratio in its simplest form, may be stated as the ration of “time when
a product is required“to the “time when the product can be supplied”.
For E.g.,
= 2.
A critical ratio of 2 implies that the time available to deliver the product is twice the time
required to manufacture the product, similarly, a critical ratio of ½ will mean that the time
available to deliver the product is half of the time required to manufacture the product.
This also suggests that the processing time must be reduced to half of the normal
expected time otherwise the product will not be delivered on time.
A critical ratio of
(i) Greater than one means that there is sufficient time and job can be completed
ahead of the schedule.
(ii) Equal to one implies that job is just on schedule and requires to be closely
watched.
(iii) Less than one suggests that the job is critical and needs to be expedited to
complete it on schedule.
In general, the smaller the critical ratio, the more critical the job is from delivery point of
view.
Make automatic adjustment in the shop schedule when there are changes in
demand and job progress.
(b) Write few typical critical ratios and explain what they signify?
Ans:
1) A total of 20 work orders completed over last one quarter were analyzed and
following data on ineffective timer per operation (days) was obtained:
Calculate
(i) The average time per operation the component stayed on the
shop floor due to waiting queuing, hunting, job splitting, change
in priorities, power failure, machine break down etc.
(ii) What total lead time should be considered for component with
the following details?
N.B: The Company works two shifts per day, each shift of 8 hrs duration.
Sol:
(a) Expected ineffective time per operation is
N
EIT = ∑ Xi, P(Xi)
1
20 Total: 2.600
N N
TLT = P + ∑ (W + T) + ∑ S+QR
1 1 HXE
Where,
Operations
= 2.60 x 5
= 13 days
T = Transit time between operations x No. of operations
= 0 (Transit time assumed to be insufficient)
And
N
∑ S+QR = 12 + 18 / 60 X 300
1 HXE 16 X 0.80
= 7.97 days
Therefore,
TKT = 7 + 13 + 7.97
= 28 days.
1 1320 840 60 4
2 480 120 30 15
3 520 80 40 10
4 785 235 50 30
Calculate critical ratio for each of the items and decide on the action to be taken.
Sol:
Critical ratios for above items have been calculated in the table below:
Lead time Lead Time
S.No available (LTA required Critical ratio
3 520 - 80 / 40 = 11 10 11 / 10 = 1.10
From the above critical ratios, we can conclude that progress of item
(i) At serial 1 is more than satisfactory. The item is likely to get completed on
time and not much of attention is required to be paid to it.
(ii) At serial 2 is unsatisfactory. The item has become critical either because its
consumption has risen above its average or the job has been delayed. In any
case, its progress must be accelerated to avoid potential stock out.
(iii) At serial 3 is just satisfactory. The item needs to be closely monitored
(iv) At serial 4 is extremely critical. Every possible avenue should be explored to
expedite the remaining operations.
12 (a) What are make or buy decisions? What costs are considered while finding the
cost to make and cost to buy?
Ans: Introduction: Make or buy decisions generally concern items required to the
company’s own design. No firm can manufacture each and every item of its product. It is
neither possible nor desirable. Items which do not form the company’s product line are
always purchased from outside. An automobile firm for example requires to purchase raw
materials, forgings, castings, tyres, tubes, bulbs, wires, bearings, automotive wheels, etc,
from others. Similarly, an engineering firm needs to buy grinding wheels, oils and
greases; tools etc., since the manufacture of these items require totally a different
manufacturing process.
The exclusion of the above categories of items leaves the firm with items which require
to be manufactured to its design either at the home plant or to be purchased from outside
suppliers. The decision whether to make the item at the home plant or buy it from outside
vendors is referred to as “make-or-buy” decision.
Cost analysis refers to the determination of cost to make the item and cost to buy it. A
complete and correct assessment of the various elements of the cost is essential to make
sound economic decisions.
(b) Labour cost: Labour cost implies the wages and costs of other benefits
(Provident fund, E.S.I., bonus, gratuity etc.) payable to the workmen engaged on
the job. This cost however, requires to be considered only when additional labour
force needs to be employed while production capacity is available.
(c) Tooling cost: Jigs and fixtures generally require to be made if the item is to be
machined at the home plant. The jigs and fixtures once made maintain their
accuracy only for certain quantity, say “n” pieces, after which again a new set of
jigs and fixtures require to be made. The cost of tooling thus requires to be
amortized over “n” pieces and the annual cost of such tooling requires to be added
to “cost to make”.
At times, when an item is purchased from outside vendors, certain special cutting
tools (broaches, hobs, shaping cutters etc.) and jigs and fixtures require to be
supplied to the vendor free of cost. The cost of such tooling, therefore, requires to
be considered separately as tooling cost towards “cost-to-buy”
(d) Overhead cost: the bulk of cost associated with a make or buy decision is the
cost of production capacity. This is the area where most often mistakes are made.
These costly errors can be avoided by keeping a single fact in mind that the costs
which influence make or buy decisions are just the incremental costs the costs
which will be incurred if the part currently made is purchased or vice versa.
(e) Recoupment cost: Recoupment cost implies the setup costs (if the item is to be
manufactured at the home plant) or the procurement cost (if the item is to be
purchased). Set-up cost is the “preparation cost” of the machines and it varies
depending upon the number of production runs in a year. The procurement cost is
the cost of raising a purchase order and processing the deliveries from the
vendor(s) and it varies depending upon the frequency of receipts of the item from
the vendor(s).
(f) Outside operations cost: The item manufactured at the home plant may require
sub-contracting of certain operations such as rough blanking, heat treatment,
plating etc. The cost of such operations requires to be considered separately
towards “cost to make”
(g) Purchase cost: Purchase cost includes the price given to the vendor, packing and
forwarding, excise, sales tax, transport cost, control etc.
(h) Capacity cost: Capacity cost implies the cost of capacity rendered idle if the item
currently being manufactured is purchased. Such a cost requires to be added to
“cost to buy”.
Ans: Introduction: Good production planning and control system is a must for a firm to
enable it to make reliable promises and then to stick to them. It is also essential to devise
methods which will ensure selection of right equipment, right tooling and enable the shop
to make the job in the simplest but in the fool proof way. The following costs can be
controlled / avoided through better production, planning and control, which make it the
nerve center of a production unit.
(a)Waiting time: “Time waste is the easiest of all wastes and yet the hardest to correct
because it does not litter the floor” remarked Henry Ford once. This statement is as
true as death. Excessive waiting time is really a big hazard – a big expense.
A closer look around the department can enable us to spot some of these time leaks.
We will find some of our workmen waiting at that tool crib. Some may be waiting for
raw materials. Other may be waiting for the tools to be sharpened. Yet there may be
some waiting for prints and instructions for the next job. These little time leaks, if
considered in isolation, do no mean much but too many of these can certainly add to a
large amount, may be larger than few big ones. To reduce waiting time, each
supervisor must know as to when the job in hand must be completed and when next
job should get started so that necessary tools. Gauges, prints, materials, etc. for the
next job can be kept ready.
(b) Hunting Time: “An Operative in an engineering concern spends more than 2% of his
time in wandering or looking for the things he needs to do the jobs” we will find them
sharing their tools with other operators. Lot of operative’s time is wasted in searching for
straps, clamps, bolts, nuts and washers.” We can reduce this ineffective time by fixing
right place for everything and providing our men a set of everything they need well in
advance of starting of the job. Good production planning and control can convert some of
these time leaks into useful production hours.
(c) Stalling: “Workers usually try to coincide the end of their jobs with the end of the day by
stretching the jobs in hand”. A worker usually tends to delay the completion of job so that
he does not need to start a fresh job towards the end of the day. “why start now, I wont be
able to finish it in my shift” is the commonest attitude among our workmen. We can
somewhat avoid this by setting the system where by each workman knows when he is
expected to complete the job-in-hand and what is his next work assignment. Scientific
scheduling can do this!
(d) Interrupted workloads: “Unplanned over lapping of operations lead to idle machines
and job split-ups”. Interrupted work from the previous operation not only results in partial
utilization of the next machine but also seriously undermine morale of the shop. Careful
production planning can prevent such unnecessary losses of time.
(e) Costly overtime: “Poor planning is the common cause of overtime.” Prolonged overtime
is not merely the extra strain on the finance of the company but means much more.
Excessive overtime and hence extra time earnings make the workers accustomed to a new
standard of living and any action on the part of the management to reduce or discontinue
overtime is disliked by the workers. It is just not palatable to them. The mere knowledge
that the company intends to do away with the overtime make the workers slow down
their pace and thus the company is forced to overtime working. It then becomes a vicious
circle and once caught in it the company cannot come out of it. The result is of anybody’s
guess. The workers go on getting overtime day after day and month after month and thus
worsening the already worsened situation. The overall effect is thus the lowering of
efficiency – firstly because of accumulation of fatigue and secondly because of slackering
of pace to get overtime.
(g) Higher overhead costs: Since production planning anc control relieves supervisory
staff from a number of clerical responsibilities, they get more time for training of
workmen, troubleshooting, maintaining shop discipline and improvising methods of
work. At the same time they can handle more workmen and more machines, which
reduce supervisory overheads.
(h) Poor labour efficiency: “Workmen who get accustomed to working intermittently
never work continuously”. This is no exaggeration. It is a fact based on human
physiology and it holds good not only for workmen but also for supervisory
personnel. Many a times in large companies, jobs get delayed due to irregular
deliveries of materials, interruptions from the supervisors, improper loading and
scheduling, lack of sufficient volume of work etc. and as a result workmen are either
rendered idle or are utilized for part of the time. And if such delays are frequent,
workmen get accustomed to partial working and thus the efficiency of the shop floor
suffer a set back. They even do not work continuously when sufficient work is
available.
PPC can prevent such a situation by exercising better control on availability of tools
and materials monitoring a close control on work-in-progress on the shop floor, re-
allocating jobs from other machines by shifting idle operators to other machines,
changing the route, ensuring smooth movement of materials from and into the
different shops, and reporting cases of idle time of men and machines to enable the
scheduler to release new jobs.
(i) Investment in inventories: Good production planning and control can help the firm
to ensure continuity in production with minimum inventory investment. Stock outs
and higher inventory investment result if the requirements of materials are not
indented on time and also if materials on receipt are not allowed properly to the work
orders as per job priorities. Shop personnel can neither do forward planning of
materials nor can they keep track of receipts and issues of materials. Only a
centralized agency such as PPC can co-ordinate the activities of shops, stores
department and the buying department.
PRODUCTION
PLANNING &
CONTROL
Certainly production, planning and control is the nerve center of a production unit.