Toll Scenarios - by Sample Journey: Length (KM) Current Toll M7 Toll Lambert
Toll Scenarios - by Sample Journey: Length (KM) Current Toll M7 Toll Lambert
Toll Scenarios - by Sample Journey: Length (KM) Current Toll M7 Toll Lambert
Length (km)
Electorate Blue Mountains Campbelltown East Hills Granville Oatley Rockdale Smithfield
Current Toll
M7 Toll
$0.384 per km
Lambert Report
$0.500 per km
$ $ $ $ $ $ $
$ $ $ $ $ $ $
$ $ $ $ $ $ $
Current Toll
M7 Toll
$0.384 per km $ 8.06 $ 15.36 $ 8.45 $ 3.84 $ 15.36 $ 0.81 $ 1.38 $ 2.30 $ 0.88 $ 0.44 $ 10.50 $ $ $ 0.88 1.54 0.77
Lambert Report
$0.500 per km $ 10.50 $ 20.00 $ 11.00 $ 5.00 $ 20.00 $ 1.05 $ 1.80 $ 3.00 $ 1.15 $ 0.57 $ 0.57 $ $ $ 1.15 2.00 1.00
M2 M4 M5 M5 East M7 CCT LCT ED SHT SHB Southern Cross Dr General Holmes Dr Gore Hill Freeway Warringah Freeway Cahill Expressway
$ $ $ $ $ $ $ $ $ $ $ $ $ $
Barry O'Farrell backing the extension of the M7 distance tolling model across Sydney: My long term plan has always been the same, because no one complains about the M7 tolls, they complain about other tolls, so if we can get a fairer system across all existing tollways that would be a good outcome. (2BL, 3pm 22/2/12). Lambert report, commissioned by Barry O'Farrell, recommends 50 cent per kilometre toll: "Analysis undertaken by NSW Treasury suggests that applying a 50 cents per kilometre charge for the untolled portion of the network (including restoring tolls on the M4), and reforming the M5 Cashback scheme, might generate up to $780 million annually Lambert Report: Recommendation 13.9 Increase reliance on road pricing as a source of revenue, using any additional revenue to reduce vehicle taxes. In the short-term, introducing consistent tolling across all currently untolled sections of the Sydney Orbital Network with tolling reflecting the distance travelled, and incorporate a congestion price that varies by location and time of day." Page 2 of 2