Exercises
Exercises
. Given the diagram below, find: (a) critical path (b) How long it will take to complete the project.
C A 10 1 7 B 3 E 7 11 5 2 5 D 5 G 4 3 6 F
2.Given the following network: (a) What is the critical path? (b) How long it will take to complete the project? (c) Can activity B is delayed without delaying the completion of the project? If so, how many days?
D 2
A
7
E
4 G 5 6 H 6
8 1 10 B
5 7
3. Given the following information regarding a project concerning an initial public offering (IPO) : Activity A TE (Weeks) 3 Preceding Activities none
1 3 4 4 5 2 3
none a a b b c, e f
Draw the PERT network and the Gantt chart. What is the critical path? When will the offering be available (completion of the project) What is the critical path to event 4 (legal documents, end of activities c and e)? What is the earliest time that this event can be reached? (e) What is the effect on the project if activity e (approvals) takes an extra week? Two extra weeks? Three extra weeks? 4. Construct a network for the following training and development project: Activity A B C D E F G H TE (Weeks) 3 5 14 5 4 7 8 5 Preceding Activities none none a a b b d, e g, f
(a) Draw the PERT network and the Gantt chart. (b) Find the critical path? (c) Assume activity a (hire trainers) took five weeks. Replan the project. (d) From where would you suggest transferring resources, and to what activities, so that the original target training date may be maintained?