Chapter 7-Managing Risk
Chapter 7-Managing Risk
Chapter 7-Managing Risk
MANAGING RISK
Risk Management
A proactive attempt to recognize and manage internal events and external threats that affect the likelihood of a projects success.
What can go wrong (risk event). How to minimize the risk event s impact (consequences). What can be done before an event occurs (anticipation). What to do when an event occurs (contingency plans).
Managing Risk
Step 1: Risk Identification
Generate a list of possible risks through brainstorming, problem identification and risk profiling.
Macro risks first, then specific events
Risk Schedules
Transferring Risk
Paying a premium to pass the risk to another party.
Avoiding Risk
Changing the project plan to eliminate the risk or condition.
Sharing Risk
Allocating risk to different parties
Retaining Risk
Making a conscious decision to accept the risk.
Contingency Planning
Contingency Plan
An alternative plan that will be used if a possible foreseen risk event actually occurs. A plan of actions that will reduce or mitigate the negative impact (consequences) of a risk event.
Schedule Risks
Use of slack increases the risk of a late project finish. Imposed duration dates (absolute project finish date) Compression of project schedules due to a shortened project duration date.
Funding Risks
Changes in the supply of funds for the project can dramatically affect the likelihood of implementation or successful completion of a project.
Budget reserves
Are linked to the identified risks of specific work packages.
Management reserves
Are large funds to be used to cover major unforeseen risks (e.g., change in project scope) of the total project.
Time Buffers
Amounts of time used to compensate for unplanned delays in the project schedule.
Key Terms
Avoiding risk Budget reserve Change management system Contingency plan Management reserve Mitigating risk Risk Risk profile Risk severity matrix Scenario analysis Sharing risk Time Buffer Transferring risk
Chapter 7 Appendix
PERTPROGRAM EVALUATION REVIEW PERT TECHNIQUE Assumes each activity duration has a range that statistically follows a beta distribution. PERT uses three time estimates for each activity: optimistic, pessimistic, and a weighted average to represent activity durations.
Knowing the weighted average and variances for each activity allows the project planner to compute the probability of meeting different project durations.
(1)
(2)
(3)
Note the standard deviation of the activity is squared in this equation; this is also called variance. This sum includes only activities on the critical path(s) or path being reviewed.
(7.4)
Hypothetical Network
Z Values