in; Amnon Basson Subject: FW: Ecodel list & Photos Showing Defect
Dear Sir, As discussed at site on 13.02.12 that you will start the rectification work in tower L & M from 15.02.12. you are requested to make sure to start the work as committed. Regards, Atul Saxena Construction Manager R & T Division Feedback Infrastructure Services Private Limited Mobile: +919868430471 -----Original Message----From: Atul Saxena Sent: 13 February, 2012 5:34 PM To: 'vinitgupta@ecodel.net' Cc: 'Rajesh Agrawal'; 'vpneoworld@logixgroup.in'; Amnon Basson Subject: Ecodel list & Photos Showing Defect
Dear Sir, As discussed in the meeting on 10 Feb 12 in Logix head office, Please find attached the copy and photo of defects list. You are requested to rectify the same as committed by you in the meeting. Regards, Atul Saxena Construction Manager R & T Division Feedback Infrastructure Services Private Limited
Mobile: +919868430471