Integrating Oracle Project Management 11.5.10 M With External Scheduling Tools
Integrating Oracle Project Management 11.5.10 M With External Scheduling Tools
SM
Founded in 1997 by former chief architect of Oracle Projects Former Oracle developers, consultants, support technicians and product marketing personnel 175+ successful customers Expert services Products to extend Oracles solution
Our Services
Implementation
Extensions
Library of proven successes for E&C, Govt Contractors, Prof Services industries
Our Products
OP3
Pre-packaged bi-directional integration between Primavera and Oracle Projects Used by USACE, Iraq PCO, Bollinger Shipyards and more.
Custom Dashboards and Reporting Invoice Consolidation and Printing Used by MasterCard, KCI, DAI, ASRC, Abt Associates and more
Released May 2005 Brings Projects into the Front Office Completely new functionality in HTML UI Used by Project Managers and Team Members
Planning Workplan, B&F, Staffing Plans Execution Issue& Change Management, Progress Monitor Project Performance, Exceptions, Status Organizational Portfolio Analysis
Why integration?
So where do the scheduling tools fit in the project planning and execution process?
Most organizations use tools like MS Project and Primavera for scheduling Oracle Projects does not support native scheduling. Objective: Protect investment in scheduling tools while exploiting the power of Oracle ERP
Define Dependencies
Define task dependencies
Assign Resources
Scheduling Tools
Generate Budget
Adjust Budget
Adjust/override generated lines Add contingency & other manual amts Plan in multiple currencies
Publish Workplan
Automatically notify all team members of published workplan
Define tracking of Generate based financials for the on Workplan project in financial Resources or breakdown structure Project Team Can be shared with Reqmts/Asgmts WBS, or separate
Collect Enter time, actuals Enter % complete, Progress against tasks, ETC date, status, etc.
Review progress for Roll progress up all tasks of the WBS task, deliverables, Override progress or estimated dates Report completion of work qtys number at any level Enter or process actions against Override derived of WBS actual costs for non- deliverable progress labor resources
Track & Resolve Issues Manage Issues & Improved UI to manage project Changes
issues
Capture Changes
Automatically implement cost/revenue impact to financial plan
Update Schedule
Use Scheduling Based on new task Tools to update task dates, extend resource assignment duration, dates request new resources, Push info back into or reassign tasks Oracle for further analysis and planning Oracle
Scheduling Tools
Project Management
Creating and Updating the Forecast and Managing the Project Performance
Generate Forecast Review Forecast Submit & Approve Forecast Re-publish Workplan
Automatically notify all team members of revised schedule and forecast
Create & Review forecasts Update Automatically Submit generated from and do mass forecast for Forecast multiple sources to adjustments by RBS
derive ETC Override systemgenerated forecast or WBS Compare different versions approval
Monitor Exceptions
Set up thresholds for exceptions Configure e-mail notifications for exceptions
Review total Review by task in Set up and review project costs, financial breakdown performance revenues, effort, structure, resource scores billing, earned in RBS, period, etc. value Drill down to Review traffic light transaction level for indicators for costs overall exceptions
Available from Oracle, bundled with 11.5.11 M Integration with desktop (standard) version only Easy to install and configure Versions supported: 2000/2002/2003
Available from Project Partners as a pre-packaged product, OP3 Integration with Enterprise version, running on Oracle db Easy to install and configure Versions supported: P3e and P3e/c 4.1 and 5.0
Planning Resources Projects Work Breakdown Structures Activity Resource Assignments Financial Plans Actuals
Receive planning resource list from Oracle Projects Build project plan with resources received from Oracle Projects Schedule project plan Send the scheduled project to Oracle Project Update the project plan in either application and receive in the other to keep the two projects in synch Attach the desktop project file (.mpp) to project in Oracle (optional)
Build project plan in Oracle Receive project plan along with the resources in MS Projects Schedule project plan Send the scheduled project to Oracle Project Update the project plan in either application and receive in the other to keep the two projects in synch Attach the desktop project file (.mpp) to project in Oracle (optional)
Resource Actual hours, ETC hours, Resource Actual Start/Finish Dates, Task Actual Start Finish Dates, Task Status, Progress Status, Progress Overview
Receive progress in MS Project Reschedule the project based on latest progress Send the rescheduled project to Oracle Project Collect progress for the next progress cycle and repeat the above steps
Receive resources, resource rates and financial tasks Create project plan with or without resource assignments Enter task costs/MS Projects computes task costs from resource assignments and rates Send task costs or task/resource assignments hours and costs as budget lines to a financial plan.
Integration with Microsoft Project - Data Transfer from Oracle Projects to MS Project
Planning Resource List, Resource Burdened Rates Project Start/Finish Dates Work Breakdown Structure and Tasks
Task Numbers, Names, Start/Finish Dates, Durations, Task Type (workplan structure) Task Number, Name, Start Finish Date (for non-shared financial structure) Oracle specific task attributes in custom fields Service Type, Work Type, Task Organization, Task Manager, Billable/Chargeable flags, Transaction Start/Finish Dates
Integration with Microsoft Project - Data Transfer from Oracle Projects to MS Project (contd)
Planned hours, Scheduled Start/Finish dates Actual start/finish dates, Actual and ETC hours of tasks and resource assignments Oracle specific progress attributes in custom fields Task Status, Progress Status, Progress Overview, Progress Comments, Physical Percent Complete.
Integration with Microsoft Project - Data Transfer from MS Project to Oracle Projects
Project Start/Finish Dates Work Breakdown Structure and Tasks (workplan structure)
Task Numbers, Names, Durations, Constraints, Constraint Dates, Scheduled/Early/Late Start/Finish Dates, Free/Total Slacks Oracle specific task attributes in stored in custom fields Task Type, Service Type, Work Type, Task Organization, Task Manager, Billable/Chargeable flags, Transaction Start/Finish Dates
Dependencies with lead/lag times (workplan structure) Resource Assignments to workplan tasks (workplan structure)
Integration with Microsoft Project - Data Transfer from MS Project to Oracle Projects (contd)
Financial plan budget lines, planned hours, assignment cost Actual start/finish dates, Actual and ETC hours of tasks and resource assignments (for non-shared workplan structure only) Oracle specific progress attributes in stored in custom fields Task Status, Progress Status, Progress Overview, Progress Comments, Physical Percent Complete.
Planning Resources Projects Work Breakdown Structures Activity Resource Assignments Financial Plans Actuals
Planning Resource List including Resource Organizations, and Employee Data Project Start and Finish Dates Work Breakdown Structure and Tasks Classification Category/Codes as Enterprise Project Structure Codes Workplan Resource Assignments or Financial Plan Budget Lines as Resource Assignments Scheduled Start and Finish Dates for Tasks and Resource Assignments
-continued-
Task and Resource Assignment Planning, Estimate to Complete and Estimate At Completion Costs Project Manager Task Manager as Primary Resource Project Status, Project Type and Project Classification Categories/Codes as Project Codes Actual costs and quantities
Project Start and Finish Dates Work Breakdown Structure and Activities Activity Constraints, Constraint Dates and Duration Types Start and Finish Dates for Activities and Resource Assignments Early Start/Finish and Late Start/Finish Dates for Activities Milestones Resource Assignments to Workplan Resource Assignments or Financial Plan Budget Lines
-continued-
Activity Codes to update Task Organization, Task Type, Service Type, Work Type, Billable and Chargeable Flags Primary Resource as Task Manager Estimate to Complete and Estimate at Completion quantities Activity Codes to Update Progress Overview, Progress Status and Progress Comments Activity Percent Complete
2. 3.
OP3 synchronizes the project work schedules in the two systems and creates the budget version directly from a Primavera plan
3.
OP3 synchronizes actuals, estimates to complete and progress information between the systems and creates budget/forecasts directly from the updated Primavera plan
Initiates a project in Oracle Projects Uses OP3 Autolink capability to create a linked project in Primavera Uses Primavera to create WBS, activities, resources assignments and schedules the work Uses OP3 to update the linked project in Oracle Projects Reviews and approves the project in Oracle Projects Refines and finalizes the project work and schedule in Primavera and send the final updates to the project in Oracle Projects
Reviews the project workplan in Oracle Projects Uses OP3 to create working versions of the approved cost budget in Oracle Projects
Budgets created from workplan resource assignment units in Primavera and resource rates in Oracle Projects
Reviews the working versions of the cost budget in Oracle Projects Uses OP3 to create the baseline version of the approved cost budget
Enters & summarizes actual quantities and costs for resource assignments in Oracle Projects. Uses OP3 to transfer actuals to Primavera Enters Estimate to Complete (ETC) for the resource assignments and progress information for activities in Primavera Reschedules the project in Primavera with the latest actuals & ETC information Uses OP3 to send the latest schedule, progress & percent complete information to Oracle Projects Generates Earned Value and other reports in Oracle based on the actuals, estimate to complete and percent complete information received from Primavera
Reviews the updated project in Oracle Projects Uses OP3 to create working versions of the approved cost budget/primary cost forecast in Oracle Projects Reviews working versions of the cost budget and forecast in Oracle Projects Uses Oracle Projects to compare the latest versions of budget and forecast with the baseline version to monitor the financial performance of the project and take corrective action, if needed
Task Schedule, Other Task Attributes and Activity Codes in Primavera and Oracle Projects
Entering Progress and Estimate to Complete in Primavera and sending updates to Oracle Projects
Creating rolling forecasts in Oracle Projects based on the latest Actuals and Estimate to Complete
Thank you
For more information: www.ProjectP.com 650-712-6200