FIDIC Clauses (Red Book)
FIDIC Clauses (Red Book)
Definitions Headings and Marginal Notes Interpretation Singular and Plural Notices, Consents, Approvals, Certificates and Determinations
Contract Documents
5.1 5.2 6.1 6.2 6.3 6.4 6.5 7.1 7.2 7.3 Language/s and Law Priority of Contract Documents Custody and Supply of Drawings and Documents One Copy of Drawings to be Kept on Site Disruption of Progress Delays and Cost of Delay of Drawings Failure by Contractor to Submit Drawings Supplementary Drawings and Instructions Permanent Works Designed by Contractor Responsibility Unaffected by Approval
General Obligations
8.1 8.2 9.1 10.1 10.2 10.3 11.1 12.1 12.2 13.1 14.1 14.2 14.3 14.4 15.1 16.1 16.2 17.1 18.1 19.1 19.2 20.1 20.2 20.3 20.4 21.1 21.2 21.3 21.4 22.1 22.2 22.3 23.1 23.2 23.3 24.1 24.2 Contractor's General Responsibilities Site Operations and Methods of Construction Contract Agreement Performance Security Period of Validity of Performance Security Claims under Performance Security Inspection of Site Sufficiency of Tender Adverse Physical Obstructions or Conditions Work to be in Accordance with Contract Programme to be Submitted Revised Programme Cash Flow Estimate to be submitted Contractor not Relieved of Duties or Responsibilities Contractor's Superintendence Contractor's Employees Engineer at Liberty to Object Setting-out Boreholes and Exploratory Excavation Safety, Security and Protection of the Environment Employer's Responsibilities Care of Works Responsibility to Rectify Loss or Damage Loss or Damage Due to Employer's Risks Employer's Risks Insurance of Works and Contractor's Equipment Scope of Cover Responsibility for Amounts not Recovered Exclusions Damage to Persons and Property Exceptions Indemnity by Employer Third Party Insurance (including Employer's Property) Minimum Amount of Insurance Cross Liabilities Accident or Injury to Workmen Insurance Against Accident to Workmen
25.1 25.2 25.3 25.4 26.1 27.1 28.1 28.2 29.1 30.1 30.2 30.3 30.4 31.1 31.2 32.1 33.1
Evidence and Terms of Insurances Adequacy of Insurances Remedy on Contractor's Failure to Insure Compliance with Policy Conditions Compliance with Statutes, Regulations Fossils Patent Rights Royalities Interference with Traffic and Adjoining Properties Avoidance of Damage to Roads Transport of Contractor's Equipment or Temporary Works Transport of Materials or Plant Waterborne Traffic Opportunities for Other Contractors Facilities for Other Contractors Contractor to Keep Site Clear Clearance of Site on Completion
Labour
34.1 Engagement of Staff and Labour 35.1 Returns of Labour and Contractor's Equipment
Suspension
40.1 Suspension of Work 40.2 Engineer's Determination following Suspension 40.3 Suspension Lasting more than 84 days
Commencement of Works Possession of site and Access Thereto Failure to Give Possession Wayleaves and Facilities Time for Completion Extension of Time for Completion Contractor to Provide Notification and Detailed Particulars Interim Determination of Extension Restriction on Working Hours Rate of Progress Liquidated Damages for Delay Reduction of Liquidated Damages Taking-Over Certificate Taking-oOver of Sections or Parts Substantial Completion of Parts Surfaces Requiring Reinstatement
Defects Liability
49.1 49.2 49.3 49.4 50.1 Defects Liability Period Completion of Outstanding Work and Remedying Defects Cost of Remedying Defects Contractor's Failure to Carry Out Instructions Contractor to Search
Measurement
55.1 56.1 57.1 57.2 Quantities Works to be Measured Method of Measurement Breakdown of Lump Sum Items
Provisional Sums
58.1 Definition of "Provisional Sum" 58.2 Use of Provisional Sums 58.3 Production of Vouchers
Nominated Subcontractors
Definition of "Nominated Subcontractors" Nominated Subcontractors; Objection to Nomination Design Requirements to be Expressly Stated Payments to Nominated Subcontractors Certification of Payments to Nominated Subcontractors
60.1 60.2 60.3 60.4 60.5 60.6 60.7 60.8 60.9 60.1 61.1 62.1 62.2
Remedies
Default of Contractor Valuation at Date of Termination Payment after Termination Assignment of Benefit of Agreement Urgent Remedial Work
Special Risks
No Liability for Special Risks Special Risks Damage to Works by Special Risks Projectile, Missile Increased Costs arising from Special Risks Outbreak of War Removal of Contractor's Equipment on Termination Payment if Contract Terminated
Settlement of Disputes
67.1 67.2 67.3 67.4 Engineer's Decision Amicable Settlement Arbitration Failure to Comply with Engineer's Decision
Notices
68.1 Notice to Contractor 68.2 Notice to Employer and Engineer 68.3 Change of Address
Default of Employer
69.1 69.2 69.3 69.4 69.5 Default of Employer Removal of Contractor's Equipment Payment on Termination Contractor's Entitlement to Suspend Work Resumption of Work
Currency Restrictions Rates of Exchange Currency Proportions Currencies of Payment for Provisional Sums