Shutdown Book 2007
Shutdown Book 2007
Shutdown Book 2007
HALDIA REFINERY
SHUTDOWN -2007
Issued By
1. SHUTDOWN SCHEDULE
2. SHUTDOWN SAFETY INSTRUCTIONS
3. SHUTDOWN CO-ORDINATORS
4. SHUTDOWN ORGANOGRAM
5. SAFETY ROTA PLAN
6. CRITICAL ACTIVITIES
7. EQUIPMENT TALLY
8. DETAILED JOB LIST
9. CRITICAL ERECTION ACTIVITIES
10. LIST OF AGENCIES
11. SPECIAL TOOLS AND TECHNIQUES FOR S/D JOBS
12. OEM SUPPORTS
13. CRITICAL ACTIVITY PLAN
14. SAFETY CHECK LIST
UNIT SHUTDOWN PLAN SEPT - OCT 2007
Units Days 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 38 39
FLARE 3+10+1
TPS / PCT 1+12+1
FCCU 3+20+4
HGU 3+14+3
PDA 5+20+5
NMP 5+17+3
CDU-I 2+15+3
CDU-II 2+14+3
CRU 9+16+4 #
KHDS 3+21+2
VDU-I 2+16+3
VDU-II 2+17+3
DHDS 3+18+2
MSQ 3+24+4
MSQ-87 3+25+2
FEU 2+22+3
SDU 28
HFU 3+21+3
VBU 3+19+3
CDW 3+21+5
• Each and every person moving/ working in shutdown area should wear personal protective
equipment like safety helmet, safety shoes etc.
• Dust Masks (NOSE FILTERS) to be used by person working in confined dusty area i.e.
inside furnace, columns, vessels, reactors, etc.
• Main header valves of fire hydrant are to be kept open during shutdown period. Nozzle
valves of fire hydrant are to remain closed during shutdown period.
• Foam extinguishers are to be provided in shutdown area at a distance of every five meters
and at every elevated platform near hot job area etc.
• While taking radiographs, the radioactive prone area is to be cordoned off.
• Oxygen masks are to be provided for personnel working in underground vessels with odour
and fumes.
• Safety goggle, face shield, hand gloves must be worn while working in chipping, grinding,
cutting, wielding, blinding jobs etc.
• Without valid fire permit /safety permit as well as clearance certificate no hot jobs should
be carried out.
• A running water hose is to be kept near not job area. If hot jobs are being carried on
elevated area, one running water hose is to be kept at ground level also.
• In case of fire, fire and safety department, CISF and medical section (First Aid) are to be
informed immediately on phone.
• Exhaust fan to be provided at manholes for personnel working inside the columns, vessel
and furnaces etc.
• All materials ( taken out from column/ vessel etc. after cleaning) where presence of
pyrophoric iron is expected to be identified by production and instruction to be given to
concerned maintenance group accordingly. All those materials to be buried to a designated
place only.
• 24-volt hand lamp to be used by person working inside columns, vessels, and furnace etc.
• Naphtha and petrol should not be used for washing purpose.
• While carrying out hot jobs, all the OWS old manholes are to be covered by wet gunny
bags.
• Lifting tools & equipment like chain pulley block, wire rope, sling etc should not be
allowed to use without valid test certificate.
• Fully stocked First aid box should be available in the shutdown office.
• A standby personnel should be always be outside the vessel / column manholes to pull out
the working personnel outside in case of emergencies.
• The personnel working inside a confined space should come out of the space immediately
in case of any discomfort in breathing.
Safety Rules for Elevated Locations
• While carrying out shutdown jobs at elevated places, steel scaffolding to be used, which
should be securely fastened with solid supports/ structural. Also, scaffolding should not be
overloaded with materials
• People working on elevated and projected structures are to wear safety belts around their
chests & fastened to a firm structure, pipe etc.
• Before using a ladder, it should be ensured that ladder components & joints are firm and in
good condition.
• Ladder should be based on a firm & even base. The pitch of a ladder should be approx. 4 to
1 i.e. for a ladder placed 6m up a vertical wall, the base of the ladder should be 1.5 m away
from the base of wall. Also, it should project at least 1 meter above any landing platform.
For better stability its top must be lashed in position to prevent slipping.
• Metal ladder should not be used where there is risk of accidental contact with live electrical
equipment.
• The ladder should be used cautiously, giving proper attention on slippery rings & shoe
soles. Also always face the ladder while climbing or descending.
• Always keep hands free while climbing. Tools & equipments should be carried on belt.
MANDATORY SAFETY PRECAUTIONS DURING SHUTDOWN
• Prior to boxing up of equipment (Columns, Vessels, Reactors, Furnaces, etc) the clearance
by concerned department, i.e. Production, Process, Mechanical, Civil, Inspection,
Electrical, Instrument is to be given by signing the follow up Chart displayed in the
shutdown office. It is to be made Mandatory Practice that no equipment will be boxed up
unless its box up clearance is signed by above departmental engineer.
• Action: All concerned deptts.
• At the time of final box up, the representative of Production & Maintenance have to be
physically present on the spot to avoid any abnormal happenings.
• Action: Production/ Maintenance
• As per the prevailing practice, all hot jobs clearance/ equipments entry permits are being
renewed after every 12 Hrs. It is to be ensured that at each renewal time, the hot job
place/equipments are FREE from gases and the same is documented.
• Action: Production
• If any permanent structure i.e. railing/grating/trench covers/drain manholes are removed,
the written clearance to be taken from site Engineers and metallic barricading(sufficiently
strong) of the area is to be done. The implementation responsibility lies with Production
Engineer in operating plant and with Shut down office.
• Action: Maintenance/Production.
• During Shutdown safety Inspector has to be present in the plant, keeping vigilance at work
site for unsafe practice. He will be empowered to stop the work if safety instructions are
not complied with and details to be recorded in the log book maintained in Shutdown
office.
• Action: Fire & Safety
• While awarding the job to the out side agencies, a clause is to be incorporated in SCC, that
any loss/ any damage to man/machine by contractor’s fault will be heavily penalized to
keep a check on unsafe practices.
• Action: Contract Cell/P&C (contract)
• During shutdown, plenty of safety banners & posters at every 10 mtr. Should be displayed
by F&S Deptt. To keep the people reminded about safety consciousness. The display
matters will be on both side in two languages i.e. Hindi & English.
• Action: Fire & Safety
• All hot job clearance should be signed by respective Field Engineer before starting of the
hot job. On completion of hot job, the work request/clearance are to submitted within 4
HRS to the originator.
• Action: Production/ Maintenance
Hand
tools
Safety
Non-Respiratory
Safety while working at height
SHUTDOWN-2007
B.B.Das, DMNM
Garage All Jobs D.K. Parua, MLE SMNM-I
J.Singh, MLE
FOB + LOB + OFFSITE B.Mallick, MLE
Mech. Maint FCCU + DHDS S.Sharma, MLE SMNM-I
Planning Materials M.S.Ghosh, SMLE
Elec. Maint Over all R P Shukla MNMEL-II( Archisman Roy)
Inst. Maint
SPC
G Sen , DMTM
Store section
J.J Thomas , SMTO
Materials
I Behera, SMTO
Purchase section
J SIKDAR , MTO
G.K.Sahu, SO (HR)
Welfare All Jobs Manager (HR)
B.Gupta, SO (HR)
Telecom/ AC/
Over all R S Vyas, SELE / S P Sahoo, SELE SMNMEL-II ( D P Ghosh)
Fire prot.
Elect Testing Over all A K Malik, SELE / V Joshi, ELE MNMEL-II( Archisman Roy)
SAFETY ROTA FOR SHUTDOWN - 2007
AREA DATE 08:00-12:00 Hrs. 12:00-16:00 Hrs 16:00-20:00 Hrs 20:00-08:00 Hrs
9/23/2007 B.K.Barik, PSE P.S.Yadav, O(ER) Santosh Kumar, PSE Praveen Kumar, QCO
9/24/2007 A.K.Soreng, DMIS B.K.Barik, PSE P.S.Yadav, O(ER) Santosh Kumar, PSE
9/25/2007 Praveen Kumar, QCO A.K.Soreng, DMIS B.K.Barik, PSE P.S.Yadav, O(ER)
9/26/2007 B.K.Barik, PSE A.K.Soreng, DMIS Santosh Kumar, PSE Praveen Kumar, QCO
9/27/2007 P.S.Yadav, O(ER) B.K.Barik, PSE A.K.Soreng, DMIS Praveen Kumar, QCO
9/28/2007 Santosh Kumar, PSE P.S.Yadav, O(ER) B.K.Barik, PSE A.K.Soreng, DMIS
9/29/2007 B.K.Barik, PSE Praveen Kumar, QCO P.S.Yadav, O(ER) Santosh Kumar, PSE
9/30/2007 A.K.Soreng, DMIS B.K.Barik, PSE Praveen Kumar, QCO P.S.Yadav, O(ER)
10/1/2007 Santosh Kumar, PSE A.K.Soreng, DMIS B.K.Barik, PSE Praveen Kumar, QCO
FOB
10/2/2007 B.K.Barik, PSE Santosh Kumar, PSE A.K.Soreng, DMIS Praveen Kumar, QCO
10/3/2007 P.S.Yadav, O(ER) B.K.Barik, PSE Santosh Kumar, PSE A.K.Soreng, DMIS
10/4/2007 Praveen Kumar, QCO P.S.Yadav, O(ER) B.K.Barik, PSE Santosh Kumar, PSE
10/5/2007 B.K.Barik, PSE A.K.Soreng, DMIS P.S.Yadav, O(ER) Praveen Kumar, QCO
10/6/2007 A.K.Soreng, DMIS B.K.Barik, PSE Santosh Kumar, PSE P.S.Yadav, O(ER)
10/7/2007 Praveen Kumar, QCO A.K.Soreng, DMIS B.K.Barik, PSE Santosh Kumar, PSE
10/8/2007 B.K.Barik, PSE P.S.Yadav, O(ER) A.K.Soreng, DMIS Praveen Kumar, QCO
10/9/2007 Santosh Kumar, PSE B.K.Barik, PSE P.S.Yadav, O(ER) A.K.Soreng, DMIS
10/10/2007 P.S.Yadav, O(ER) Santosh Kumar, PSE B.K.Barik, PSE Praveen Kumar, QCO
9/25/2007 H.K.Bora, DMPS S.Mandal, PSE S.Kumar, ACO Manas Biswas, DMIS
9/26/2007 B.Midya, QCO H.K.Bora, DMPS S.Mandal, PSE E.Gopinathan, IAM
9/27/2007 Manas Biswas, DMIS B.Midya, QCO H.K.Bora, DMPS S.Mandal, PSE
9/28/2007 H.K.Bora, DMPS Manas Biswas, DMIS S.Kumar, ACO B.Midya, QCO
9/29/2007 S.Mandal, PSE H.K.Bora, DMPS Manas Biswas, DMIS T.Ghosal, IAM
9/30/2007 B.Midya, QCO S.Mandal, PSE H.K.Bora, DMPS Manas Biswas, DMIS
TPS 10/1/2007 H.K.Bora, DMPS S.Kumar, ACO S.Mandal, PSE B.Midya, QCO
10/2/2007 Manas Biswas, DMIS H.K.Bora, DMPS S.Kumar, ACO S.Mandal, PSE
10/3/2007 S.Kumar, ACO Manas Biswas, DMIS H.K.Bora, DMPS B.Midya, QCO
10/4/2007 H.K.Bora, DMPS S.Mandal, PSE Manas Biswas, DMIS B.Midya, QCO
10/5/2007 S.Kumar, ACO H.K.Bora, DMPS S.Mandal, PSE Manas Biswas, DMIS
10/6/2007 B.Midya, QCO S.Kumar, ACO H.K.Bora, DMPS S.Mandal, PSE
10/7/2007 H.K.Bora, DMPS Manas Biswas, DMIS S.Kumar, ACO B.Midya, QCO
SAFETY ROTA FOR SHUTDOWN - 2007
AREA DATE 08:00-12:00 Hrs. 12:00-16:00 Hrs 16:00-20:00 Hrs 20:00-08:00 Hrs
9/25/2007 S.K.Mitra, SPNE (E&C) A.Haldar, PSE S.Sen, PSE J.Bag, PSE
9/26/2007 T. Sikdar, QCO S.K.Mitra, SPNE (E&C) A.Haldar, PSE S.Sen, PSE
9/27/2007 J.Bag, PSE T. Sikdar, QCO S.K.Mitra, SPNE (E&C) A.Haldar, PSE
9/28/2007 S.K.Mitra, SPNE (E&C) J.Bag, PSE S.Sen, PSE T. Sikdar, QCO
9/29/2007 A.Haldar, PSE S.K.Mitra, SPNE (E&C) J.Bag, PSE S.Sen, PSE
9/30/2007 T. Sikdar, QCO A.Haldar, PSE S.K.Mitra, SPNE (E&C) J.Bag, PSE
O/S 10/1/2007 S.K.Mitra, SPNE (E&C) S.Sen, PSE A.Haldar, PSE T. Sikdar, QCO
10/2/2007 J.Bag, PSE S.K.Mitra, SPNE (E&C) S.Sen, PSE A.Haldar, PSE
10/3/2007 T. Sikdar, QCO J.Bag, PSE S.K.Mitra, SPNE (E&C) S.Sen, PSE
10/4/2007 S.K.Mitra, SPNE (E&C) A.Haldar, PSE J.Bag, PSE T. Sikdar, QCO
10/5/2007 S.Sen, PSE S.K.Mitra, SPNE (E&C) A.Haldar, PSE J.Bag, PSE
10/6/2007 T. Sikdar, QCO S.Sen, PSE S.K.Mitra, SPNE (E&C) A.Haldar, PSE
10/7/2007 S.K.Mitra, SPNE (E&C) J.Bag, PSE S.Sen, PSE T. Sikdar, QCO
9/19/2007 S.Dey, SPSE S.C. Singh, SO(ER) A.P.Barua, DMIS S.Prabhu, PJE
9/20/2007 S.Das, SQCO S.Dey, SPSE S.C. Singh, SO(ER) A.P.Barua, DMIS
9/21/2007 S.Prabhu, PJE S.Das, SQCO S.Dey, SPSE S.C. Singh, SO(ER)
9/22/2007 S.Dey, SPSE S.Prabhu, PJE A.P.Barua, DMIS S.Das, SQCO
9/23/2007 A.P.Barua, DMIS S.Dey, SPSE S.Prabhu, PJE S.Das, SQCO
9/24/2007 S.C. Singh, SO(ER) A.P.Barua, DMIS S.Dey, SPSE S.Prabhu, PJE
9/25/2007 S.Dey, SPSE S.C. Singh, SO(ER) A.P.Barua, DMIS S.Das, SQCO
9/26/2007 S.Prabhu, PJE S.Dey, SPSE S.C. Singh, SO(ER) A.P.Barua, DMIS
9/27/2007 S.Das, SQCO S.Prabhu, PJE S.Dey, SPSE S.C. Singh, SO(ER)
9/28/2007 S.Dey, SPSE S.Das, SQCO S.Prabhu, PJE S.C. Singh, SO(ER)
FCCU /
9/29/2007 A.P.Barua, DMIS S.Dey, SPSE S.Das, SQCO S.Prabhu, PJE
VDU-II /
9/30/2007 S.C. Singh, SO(ER) A.P.Barua, DMIS S.Dey, SPSE S.Das, SQCO
MSQ
10/1/2007 S.Dey, SPSE S.C. Singh, SO(ER) A.P.Barua, DMIS S.Das, SQCO
10/2/2007 S.Prabhu, PJE S.Dey, SPSE S.C. Singh, SO(ER) A.P.Barua, DMIS
10/3/2007 S.Das, SQCO S.Prabhu, PJE S.Dey, SPSE A.P.Barua, DMIS
10/4/2007 y, SPSE
S.Dey, S.Das,, SQCO S.Prabhu,, PJE g , SO(ER)
S.C. Singh, ( )
10/5/2007 A.P.Barua, DMIS S.Dey, SPSE S.Das, SQCO S.Prabhu, PJE
10/6/2007 S.C. Singh, SO(ER) A.P.Barua, DMIS S.Dey, SPSE S.Das, SQCO
10/7/2007 S.Dey, SPSE S.Prabhu, PJE A.P.Barua, DMIS S.C. Singh, SO(ER)
10/8/2007 S.Das, SQCO S.Dey, SPSE S.Prabhu, PJE A.P.Barua, DMIS
10/9/2007 S.Das, SQCO S.C. Singh, SO(ER) S.Dey, SPSE S.Prabhu, PJE
10/10/2007 S.Dey, SPSE S.Das, SQCO S.C. Singh, SO(ER) S.Prabhu, PJE
1st CI-BI of GT 7 7
GT /
HRSG 2nd Maintenance of HRSG 7 7
1st CO-Stack 20 20
FCCU
2nd Regenerator 20 20
3rd 16-F-01 13 14
3rd PCT 14 19
FOB
FINAL LIST
1.0 FURNACE
1.1.0 Blinding / De-blinding, De-coking of Furnace, opening of Man-way, dropping of Burner Blocks,
erection of volumetric Scaffolding inside the furnace, opening of Convection Manholes, opening of
end-panels in Convection section, external manual cleaning of radiation tubes, Inspection of Furnace,
refractory / ceramic pad repair as per recommendations, replacement of guides & hangers, checking
of thermocouples, cutting of tubes , fitting of new tubes, welding of new joints, pre-SR X-ray, stress
relieving of joints, post SR X-ray, hydraulic pressure testing of coils, refractory repair of floor,
revisioning of Burners, revisioning of Air-registers, revisioning of Soot-blowers, peeps holes, damper
plates and boxing up of the furnace after completion of all activities in the Furnace
1.1.1 11- F - 01
a) Replacement of 4 tubes (Half Length) in 11-F-01.
b) Replacement of tube hangers and locking bars.
1.1.2 16-F-01
a) Replacement of 3 tubes (Half Length) in 16-F-01
2.1.0 Blinding / De-blinding, opening of manholes, air circulation inside the Column, gas test & man-entry,
opening of tray manways, erection of scaffolding inside the column (wherever required), unloading of
stractured packings from packed beds, manual cleaning of Column internals, Inspection, repair /
replacement as per inspection recommendations, fixing back columns internals (if required), box-up
of tray man ways and final box-up of column manholes after completion of all maintenance activities
in the columns.
3.0 REACTORS
3.1.0 Blinding/ De-blinding, opening of manholes, air circulation inside the Reactor, gas test & man entry,
opening of internals, erection of scaffolding inside the Reactor (wherever required), manual cleaning
of internals, inspection, repair/replacement as per inspection recommendations, refractory jobs as per
requirement, fixing back of internals, and final box-up of manholes after completion of all maintenance
activities in the Reactor.
5 PROJECT JOB
a) 11P 9B (HSD)-suction 10” dia gate valves- 2 nos. , discharge 10” dia gate valves –2
nos .
b) 11P10 (HSD) suction 12” gate valve –1 no, discharge 10” gate valve –1 no .
c) 11E11 :Shell side:( LPG+Naphtha) inlet 10” gate valve- 1 no,
Shell side outlet 14” gate valve –1 no
Tube side (HSD): inlet/outlet : 8” dia –2 nos.
d) 11E 11 A: Shell side:( LPG+Naphtha) inlet 10” gate valve- 1 no,
Shell side outlet 14” gate valve 1no
Tube side (HSD): inlet/outlet : 10” dia –2 nos.
e) 11E 09 A/B/C/D: Shell side:( HSD) inlet 8” gate valve- 2 no.
Shell side outlet 8” gate valve –2 no .
f) 11P03B (LPG+ Naphtha) : discharge valve 4” –1 no gate valve.
GR-10 (CDU-I)
Sl.No. Description
1 11B01/B101 platform structural supports are badly corroded. Some gratings of platform
are to be changed.
2 11E22A/B gratings are to be changed.
3 15E02 platform support beams have corroded badly. East side railing of the same has
badly corroded. All are required to be changed.
4 15B06 platform’s gratings are to be replaced at 6-7 locations.
5 11E23 A/B platform side railings & 5-6 nos of gratings are to be replaced.
6 13B01 bottom platform checkers plate is to be changed.
7 Approach platform for post desalter pump disch PSV isolation valve & post pf pump
disch PSV isolation valve are to be made.
U-16 (CDU-II)
Sl.No. Description
1 16C05 (de-ethaniser) monkey ladders with guards, platform railings, bracket and
channels are to be replaced.
2 16C09 (de-propaniser) top monkey ladder along with its guard is to be replaced.
Monkey ladder to be provided to approach PSV platform. Railing of topmost platform is
to be replaced.
3 16C04(stabilizer) top monkey ladder and its guard, railing of top platform is corroded
badly, some channels between ladder and column shell are also badly corroded and
needs to be replaced.
5 16C07(PF) top two monkey ladders & its guard is badly corroded. Side railings
of top two platforms are badly corroded.
6 16C01 & 16C07 PSV platform’s gap are to be provided with gratings & side
railings.
7 Service water valve and steam valve on the pipe rack above 16P16A/B are not
approachable
8 16F01/11F01/22F201 COT thermocouples are not approachable. Plat forms are
to be extended.
9 Gap near 16E43 is to be filled up with new grating
10 16F01 approach stair’s to be replaced completely as it is badly corroded and
unsafe.
RE-ORIENTATION REQUIREMENT w.r.t. SAFETY (SSCM)
Sl.No. Description
1 Near 11P06A/B Inst. JB is restricting to approach welding DB,to be relocated.
2 11P07B suc./disch. Valves are very nearer in which hands are touching on the hot lines
during operation, to be re-oriented.
3 23K102 MES inlet b/v to be rotated
4 23K02(corbline comp) inst panel is to be relocated.
SHUTDOWN JOB LIST
Final List
2.0 COLUMN
2.1 C-01A
2.2 C-01B
2.3 C-01C
2.4 C-110
2.5 C-108
2.6 C-02 - Repair/replacement of demister & frame, weld build up of M/H neck
2.7 C-04 - Repair/replacement of demister & frame
2.8 C-05
2.9 C-06
2.10 C-07 - Replacement of column.
Page 1 of 1
NOTE : - Removal of insulation and necessary scaffolding to be provided for all
nozzles to facilitate inspection.
3.0 VESSEL
Check-III activities i.e. opening of the covers, pulling out the tube bundle from the
shell, cleaning insertion, testing & boxing up, repair jobs including weld build up and
rectification of channel box & floating head covers, anode fixing, are to be performed
to the following including blinding / deblinding.
Two nos. of tube bundle for 32-E-06 to be kept ready for replacement.
4.1 32E112A/B
4.2 32E06A/A1
4.3 32E06B/B1
4.4 32E06C/C1
Page 2 of 2
4.5 32E06D/D1
4.6 32E06E/E1
4.7 32E06H/H1
4.8 32E06I/I1
4.9 32E10A
4.10 32E10B
4.11 32E10C
4.12 32E122
4.13 32E05A
4.14 32E05B
4.15 32E114A/B
4.16 32E114C/D
4.17 32E117
4.18 32E121A/B
4.19 32E115
4.20 32E107
4.21 32E08
4.22 32E116 A to F Air coolers
Water contact surfaces of all components of coolers & condensers (i.e. floating head,
channel box, channel cover tube sheet) to be painted as detailed below.
1 32-PSV-01K
2 32-PSV-02K
3 32-PSV-03K
4 32-PSV-04K
5 32-PSV-05K
6 32-PSV-06K
7 32-PSV-21K
8 32-PSV-22K
9 32-PSV-23K
10 32-PSV-24K
11 32-PSV-01 32-C-1-A
12 32-PSV-02 32-C-1-A
13 32-PSV-03 32-C-1B
14 32-PSV-04 32-C-1B
15 32-PSV-05 32-C-1-C
16 32-PSV-06 32-C-10
17 32-PSV-07 32-C-3
18 32-PSV-08 32-C-4
Page 3 of 3
19 32-PSV-09 32-B-1
20 32-PSV-10 32-B-1
21 32-PSV-11 32-B-2
22 32-PSV-12 32-B-2
23 32-PSV-3213 32-C-2
24 32-PSV-14 32-C-5
25 32-PSV-15 32-C-6
26 32-PSV-16 32-C-7
27 32-PSV-17 32-B-3
28 32-PSV-20 32-B-3
29 32-PSV-21 32-B-9
30 32-PSV-26 32-E-9
31 32-PSV-27 32-E-10-A
32 32PSV-28 32-E-10B
33 32-PSV-29 32-E-10-C
34 32-PSV-30 32-E-10-A
35 32-PSV-31 32-E-10-A
36 32PSV-32 32-E-10-C
37 32-PSV-33 32-E-3-A
38 32-PSV-34 32-E-3B
39 32-PSV-35 32-E-4
40 32-PSV-36 32-E-5
41 32-PSV-201 32-E-103
42 32-PSV-202 32-C-103
43 32-PSV-203 32-C-104
44 32-PSV-204 32-E-104
45 32-PSV-206 32-E-106
46 32-PSV-207 32-E-107
47 32-PSV-208 32-B-103
48 32-PSV-209 32-E-105
49 32-PSV-210 32-E-108
50 32-PSV-303 Asphal + PVMP
51 32-PSV-304 32-C-05
52 32-PSV-401 32-K-101
53 32-PSV-404A 32-B-01
54 32-PSV-404B 32-B-01
55 32-PSV-405A 32-B-02
56 32-PSV-405B 32-B-02
57 32-PSV-01 100-P-32-D-051
58 32-TSV-303 80-P-32
59 32-TSV-402A 32-E-106A
60 32-TSV-402B 32-E-106B
61 32-TSV-402C 32-E-106C
62 32-TSV-402D 32-E-106D
63 32-TSV-402E 32-E-106E
64 32-TSV-403 32-E-107
65 32-PSV-37 32-K-01
66 32-PSV-38 32-K-01
67 32-PSV-39 32-K-01R
68 32-PSV-40 32-K-01R
69 32-PSV-103A 32-C-101
70 32-PSV-106 32-E-101
Page 4 of 4
71 32-PSV-103B 32-E-101
72 32-PSV-104 32-E-110
73 32-PSV-105 32-E-110
Page 5 of 5
7.18 De-choking of ¾” evacuation line of all condensers of 32 E6 ( about 150 Meters)
7.19 De choking / inspection of 10 /12” propane vapour line ex 32C2/C4 to E6 condensers
for suspected chokage.
7.20 Dechoking of shell side inlet line to E-06 E/E1, D/D1 and C/C1.
7.21 Trap monitoring facility in C-110 steam sate lines is to be made functional.
7.22 Deblinding of P-05A suction line ex C-01
7.23 Following piping replacement jobs as anticipated by Inspection to be done.
a) Partial replacement of FO/FG/Atomising steam /purging steam lines may come for.
b) Major replacement of steam tracers. Approx 4000 Mt steam tracer line may come for
complete replacement. Please note that along with tracers, insulation repair jobs will
also be involved. Also provision shall be kept for new steam tracer headers as per
requirement.
c) The condensate steam piping shall come for replacement. Provision shall be kept for
approx 300 Mt of dia 2” CS piping replacement.
d) The leaky and externally corroded PSV discharge line of 32 B 01 & B-02 shall be
completely replaced. The isolation valves in the line shall be revisioned. Matl- dia 8”
Sch. 40 CS piping , approx length – 25 Mt.
e) The O/H lines of extractor 32 C 01 A/B/C, 32 C110 & columns 32 C 108/C-
02/04/05/06 may come for partial replacement.
f) The PSV inlet nozzles and steam vent nozzles above extractors/columns may come
for replacement.
g) The leaky dia 3” inlet line of 32 E 107 need replacement. Approx. length – 25 Mt.
h) The dia 40 mm SS 316 / CS propane piping near 32 B 01 / 02 may come for partial
replacement. Approx length – 50 Mt.
i) The pipes on overhead pipe-rack between U-32 & U-35 corridor (N-S) shall be
exposed by removing insulation, especially at support locations. Partial replacement
of some of the lines are anticipated. Scaffolding will be required as well.
j) The CW lines are in bad shape in most locations. The dia 8” CW line near 32 E 06
series is leaking. These CW lines will come for extensive repair. Positive isolation to
be ensured for any repair jobs.
k) It has been witnessed that repair of CW /FW lines are quite difficult as the isolation
valves are not holding in most of the areas. To overcome this perennial problem, it is
recommended that a phased revisioning of isolation valves to be planned.
Apart from above, sufficient provision shall be kept for replacement of pipes as detected
during shutdown inspection and approx. 200 mt each of dia 2”, 3” & 4” as well as 100 Mt of
dia 6” pipes shall be kept for above purposes.
8.1 Water side (floating side, channel box, channel cover, tube sheet) of unpainted
condensers & coolers to be painted using the following paint system : -
a) Surface preparation - Sand blasting to SA2½
b) Primer - Inorganic Zinc Silicate by spray application
(DFT 60 – 70μm single coat
c) Mist coat - HB epoxy by brush application (DFT 35 - 40μm
in one coat)
d) Finish paint - HB epoxy by brush application (DFT - 150μm in
two coats)
Total min. DFT : 250μm
8.2 100% removals & re-insulation of hot insulation lines of all process & utility
lines for requirement of line inspection, tracing steam replacement.etc.
Page 6 of 6
8.3 Painting of all bare lines, vessels & columns.
8.4 Repair / replacement of all damaged hot insulation of columns, exchangers, pipes
etc.
8.5 Repair/replacement of damaged refractory in F-01, including stack
8.6 Painting of stack and all structure of furnaces.
Page 7 of 7
9.15 Provision of suitable level gauge glass in place of existing PVC tube in B-07 tank and
providing level indication facility at field and also at DCS, with software alarm facility
9.16 Calibration of all internal float level trolls
9.17 Calibration / stroke checking of all control valves
9.18 Checking of all skin thermocouples
9.19 Total interlock checking for the unit
10.1 Hand lamps, floodlights & temporary electrical connections to be provided inside
furnace, column, vessels & other locations as per requirement.
10.2 Revisioning of motors & micro-switches of soot blower of 32F01.
10.3 Maintenance of following Motors.
Page 8 of 8
33 32PM102B "A" Schedule
34 32PM102C "A" Schedule
35 32PM110A1 "A" Schedule
36 32PM110A2 "A" Schedule
37 32PM110B1 "A" Schedule
38 32PM110B2 "A" Schedule
39 32PM102S1 "A" Schedule
40 32PM102S2 "A" Schedule
41 32KM-01 "B” Schedule
42 32KM-01R "B” Schedule
43 36PM01 "A" Schedule
44 36PM02 "A" Schedule
45 36PM03 "A" Schedule
46 36PM04 "A" Schedule
47 32PM05A "A" Schedule
48 32PM05B "A" Schedule
49 32PM05C "A" Schedule
50 32PM07A "A" Schedule
51 32PM07B "A" Schedule
52 32PM07C "A" Schedule
NOTE: For B-schedule maintenance, mechanical maintenance, will decouple and shift
motors to garage.
10.5 Checking of Lighting system including circuit checking, replacing fused lamps,
cleaning of light fitting glass, checking and sealing of JB, s and if required replacing
the defective light fittings etc.
10.6 Dressing and removal of unused cables.
11.1 Facility for online mixing of heavy extract and asphalt ex U-32 to produce bitumen
bypassing U-36.
11.2 Existing control valve in Cooling water make up line to 32-C-07 has to be converted
to flow control valve .
11.3 To provide shutdown valve(solenoid operated) based on High furnace box pressure,
Low fuel Oil supply pressure, etc for safety of operation.
11.4 Stack damper to be made pneumatic operated from DCS panel.
11.5 Relocation of anti-foam injection point in asphalt circuit I) at downstream of C-110
bottom line connection ii) At upstream of C-02 LCV, instead of present connection at
downstream..
11.6 Provision of depressurising ROV at B-03 outlet(3”) to flare, along with downstream
isolation facility. ROV is required to be operated from DCS, for safety of operations.
The ROV presently redundant on B-103 line can be utilised for this purpose.
11.7 Relocation of the common discharge valve of K-01/1R at E-6 inlet to safe location.
11.8 Dismantling and removal of redundant propane condenser E-02 and asphalt cooler
E-109 and associated piping, for decongestion of pump-house area, for safe
movement
11.9 Revival of P-110F and connect it to DAO mix service ex-C-01A/B/C/110 to C-108, for
running Unit at rated capacity.
11.10 Relocation of existing PDA furnace 32-F-01 box & coil purging of steam line isolation
valves to safe distance 15 M
11.11 Replacement of inter stage KOD of 32-K-01 for providing auto draining facility
11.12 Piping connections for installation of new propane compressor 32-K-101R
Page 9 of 9
11.13 Provision of minimum circulation line in DAO run down pumps
11.14 Modification of cooling water lines in U-32
11.15 Provision of C2-C2 circulation facility in 32-P-103A/B
11.16 Provision of back flushing facility for 32-E-117A
11.17 Process scheme for providing double isolation valves and flanged ends at high
pressure drain and vent points in U-32
11.18 Provision of ROVs at the suction lines of 32P110 A/B/C/D/E
11.19 Dismantling of redundant lines & equipments in U-32 (PDA)(in addition to PS244)
11.20 Dismantling of redundant lines & equipments in U-32 (PDA)
12.0 AF JOBS
--------------- xx -------------
Page 10 of 10
JOB LIST
NMP Extraction Unit
FINAL LIST
1.0 FURNACE
1.1.0 Blinding / De-blinding, De-coking of Furnace, opening of Man-way, dropping of Burner Blocks,
erection of volumetric Scaffolding inside the furnace, opening of Convection Manholes, opening of
end-panels in Convection section, washing of convection tubes, external manual cleaning of radiation
tubes, Inspection of Furnace, refractory / ceramic pad repair as per recommendations, checking of
thermocouples, hydraulic pressure testing of coils, refractory repair of floor, revisioning of Burners,
revisioning of Air-registers, revisioning of Soot-blowers, peeps holes, damper plates and boxing up of
the furnace after completion of all activities in the Furnace
Furnace 38 F 01 & 38 F 02
• The furnaces shall be offered for inspection after decoking and cleaning of convection zone.
Proper cleaning (washing or mopping) of coils to be done by DM water (service water & fire water
is not suited as the tubes are of SS 304 L metallurgy.
• Inspection of Decoking pot & connected piping to be done.
• As both the raffinate & extract furnace have SS 304L tubes in the radiation zone, passivation will
be required before opening.
• Inspection of convection coils after cleaning . Convection zone of 38 F 01 is made of SS 304 L
material & hence passivation will again be required.
• Inspection of APH of 38 F 01 to be done after cleaning by washing on outside & blowing air
inside the tubes.
• The thermocouple points are to be checked & repaired/replaced as per the need.
• The spigot /spigot sleeves shall be cleaned off any deposition.
• The burners shall be dropped to check the integrity of burner components etc.
• Refractory repairs of Floor, burner throats etc to be done.
• The FG / FO / Atomizing steam lines / purging steam lines connected to the furnaces shall be
exposed by removing insulation. These piping may come for partial replacement.
• The Air duct connecting F01 & F02 shall be opened, cleaned and offered for inspection.
• Provision of scaffolding & lighting inside the furnace for inspection and repair jobs
• After completion of all hot jobs, product coils of both the furnaces shall be hydrotested.
• Inspection of transfer lines after removal of insulation and passivation.
2.0 COLUMNS
2.1.0 Blinding / De-blinding, opening of manholes, air circulation inside the Column, gas test & man-entry,
opening of internals (wherever required), insulation removal around nozzles for thickness survey,
erection of scaffolding inside the Column (wherever required), manual cleaning of Column internals,
Inspection, repair / replacement (if required), re-fitting of Column internals, final box-up of the Column
after completion of all activities .
2.1.1 38-C-01
2.1.2 38-C-02
2.1.3 38-C-03
2.1.4 380-C-04
2.1.5 38-C-05
2.1.6 38-C-06
2.1.7 38-C-07
2.1.8 38-C-08
2.1.9 38-C-09
2.1.10 38-C-10
2.1.11 38-C-11
3.0 VESSEL
3.1.0 Blinding / De-blinding, opening of manholes, air circulation inside the vessel, gas test & man-entry,
opening of internals (wherever required), erection of scaffolding inside the vessel (wherever required),
manual cleaning of vessel internals, Inspection, repair / replacement (if required), re-fitting of vessel
internals, final box-up of the vessel after completion of all activities in the vessels.
Blinding / De-blinding, opening of covers, pulling out of tube bundles, hydro-blast cleaning of tube
bundles, Inspection, repair / replacement (if required), insertion of tube bundles, shell test, tube test
and final box-up of the equipment after completion of all activities of the heat-exchangers.
a) 38-E-01 A/B/C
b) 38-E-02 A/B
c) 38-E-03 A/B RETUBING OF 38-E-03A
d) 38-E-04
e) 38-E-05 A/B/C/D
f) 38-E-06
g) 38-E-07 A/B/C
h) 38-E-08
i) 38-E-09 A/B
j) 38-E-11
k) 38-E-12
l) 38-E-13
m) 38-E-14
n) 38-E-15 AIR FIN COOLER
o) 38-E-16
p) 38-E-17 Replacement of tube bundle
q) 38-E-18 AIR FIN COOLER
r) 38-E-19 A/B
s) 38-E-20
t) 38-E-21 A/B
u) 38-E-22 A/B
v) 38-E-23 A/B/C
w) 38-E-24
x) 38-E-25 Replacement of tube bundle
TOTAL : 40 Nos.
Blinding / De-blinding, opening of covers, hydro-blast cleaning of tube bundles, Inspection, repair /
replacement (if required), shell test, tube test and final box-up of the equipment after completion of all
activities of the heat-exchangers.
a) 38-E-10
Dismantling of entire equipment from location by means of crane, lowering to ground level,
carrying out of maintenance activities, testing, etc at ground level and erection back in
position by means of crane
4.3.0 Waterside of coolers/ condensers to be painted with self priming epoxy & followed by two coats of
chlorinated rubber paint after sand blast cleaning.
38-E-02 A/B, 38-E-03 A/B , 38—06 , 38-E-11, 38-E-12, 38-E-13 , 38-E-17 , 38-E-21 A/B,
38-E-22 A/B , 38-E-24 , & 38-E-25.
38-E-02A/B
38-E-03A/B
38-E-06
38-E-11
38-E-12
38-E-13
38-E-17
38-E-21 A/B
38-E-22A/B
38-E-24
38-E-25
5.1.0 Blinding / De-blinding, lowering to ground, transportation to workshop, dismantling of PSVs/ TSVs,
repair / replacement / revisioning, testing of PSVs /TSVs as per details contained in data sheet,
erection of the PSVs back in position.
PSV Æ 25 Nos.
TSV Æ 17 Nos.
TAG NO. LOCATION
38-PSV-1903 38-P-14A/B
38-PSV-1904 38-P-14A/B
38-PSV-1901 38-P-15A/B
38-PSV-1902 38-P-15A/B
38-PSV-1103A 38-C-01
38-PSV-1105A 38-C-02
38-PSV-1201A 38-C-02
38-PSV-1201B 38-C-02
38-PSV-1202 38-V-06
38-PSV-1301A 38-C-07
38-PSV-1301B 38-C-07
38-PSV-1302A 38-C-06
38-PSV-1302B 38-C-06
38-PSV-1303 38-V-15
38-PSV-1601A 38-V-09
38-PSV-1601B 38-V-09
38-PSV-1602 38-V-01
38-PSV-1801 38-V-12
38-PSV-1802A 38-V-05
38-PSV-1802B 38-V-05
38-PSV-1803A 38-V-04
38-PSV-1803B 38-V-04
38-PSV-2001 38-V-16
38-PSV-2002A 6”-SH-38-1704-B2A
38-PSV-2002B 6”-SH-38-1704-B2A
38-TSV-1101 6”-WCR-38-1102-A3A
38-TSV-1102 6”-WCR-38-1101-A3A
38-TSV-1103 38-C-01
38-TSV-1104 8”-WCR-38-1103-A3A
38-TSV-1105 38-C-02
38-TSV-1302A ¾”-P-38-1367-A1A-IT
38-TSV-1302B ¾”-P-38-1370-A1A-IT
38-TSV-1602 38-E-06
38-TSV-1501 38-E-11
38-TSV-1601 38-E-12
38-TSV-1603 38-E-13
38-TSV-1106A 6”-TWR-38-1106-B2A
38-TSV-1106B 6”-TWR-38-1106-B2A
38-TSV-1201 38-E-17
38-TSV-1301 38-E-20
38-TSV-1901 38-E-22
38-TSV-1902 38-E-21
a) Revisioning of all AUDCO FG and Pilot Gas valves in F-01 and F-02 – 18 nos
b) Replacement of P-08A/B needle valve on steam quench to seal line
c) Replacement of P-08A seal cooler S/S outlet line needle valve
d) Replacement of P-08A suction drain valve
e) Replacement of P-08A casing drain needle valve
f) Replacement of P-05B casing drain needle valve
g) Replacement of P-18A steam quench to seal line needle valve
h) Replacement of P-07B suction drain to CBD valve
i) Repair/Replacement of P-02A steam quench line to seal valve 1” gland
j) Replacement of P-02A suction drain valve
k) P-09A steam quench line to seal 1” valve gland repair/replacement
l) Replacement of P-09A steam quench line to seal needle valve
m) Repair/replacement of P-09B 1” NRV bypass valve
n) Replacement of P-04B casing drain needle valve
o) Replacement of damaged root valve of PG on DM water make up line to E-25
p) Replacement of damaged PG drain valve on P-09A
q) Replacement of steam trap b/p b/v drain dia 1” u/s of MHP steam to PC 2003 at B/L
r) Replacement of C-09 stripping steam drain, as it is passing on fully closed condition
s) Replacement of all CW sample point drains dia ¾” and dia 1” ~ 20 nos.
As this is the first major M&I, no typical trend in deterioration / replacement is known. Also, no typical
experience exists for NMP induced corrosion. However, as NMP turns acidic in presence of water,
the following piping need to be inspected at great detail. Necessary arrangements like scaffolding,
insulation removal etc. shall be made to facilitate the same. The piping are :
7.1 Overhead lines connecting 38-C-10 to 38-V-04 , 38-C-01 to 38-V-07 , 38-C-03 to 38-V-09 , 38-C-04
to 38-V-05 , 38-C-08 to 38-V-09 , 38-C-09 to 38-V-05 , inlet line of 38-C-11(common PSV discharge
header).
7.2 Process lines: Both the transfer lines, 38-T-01/02 to 38-C-10 bottom , 38-V-05 bottom to 38-C-10,38-
V-09 to 38-C-10 , inlet & outlet lines of 38-V-08 , connected piping of the ejector systems.
7.3 The bottom outlet lines of 38-C-11 & recirculating quench water line of 38-C-11 , barometric legs to
hot welletc.
7.4 All pump suction & discharge piping upto pipe racks.
7.5 Condensate water circuit & cooling water circuit.
7.6 LPD & HPV jobs: Stagewise inspection & subsequent root welding of all the LPD & HPV of all the
critical lines.
7.7 Inspection of leaky clamped lines to be done.
7.8 Insulation of transfer line from F-01 to C-07 and F-02 to C-03 to be removed for complete inspection.
7.9 Sample cooler lines of C-06 and C-10 to be dechoked and made operable
7.10 All seal coolers in pumps P-8A/B, P-05A/B and P-18A/B to be taken out and cleaned and boxed up
7.11 Provision to be made for relocation of C-07 LCV to C-08 at technological platform for easier operation
and safe maintenance
7.12 Relocation of E-10 on technological platform for easy/safe maintenance
7.13 Replacement of all choked vent /sampling points from CW outlet of all coolers: E-11/E-12/E-13/E-
24/E-21A/B, E-22A/B
7.14 Replacement of P-04A casing drain line elbow portion for leak.
8.1 FO & FG lines from battery limit to furnace to be flushed with steam / inert gas
8.2 Dechoking/Replacement of flue gas sample point lines in F-01/F-02
8.3 E-05A S/S outlet first isolation valve gland and bonnet flange leak to be rectified
8.4 E-05C to E-05D S/S and T/S interconnecting flange gasket leak to be rectified
8.5 E-05A T/S outlet first isolation valve gland leak and d/s flange gasket leak to be rectified
8.6 E-05A S/S inlet valve gland leak to be rectified
8.7 Dechoking/thoroughness check of following lines:
• F-01 to C-07 transfer line
• F-02 to C-03 transfer line
• C-07 to C-08
• C-03 to C-04
8.7 Replacement of choked and corroded cooling water outlet vents point by 1” drain line with
isolation valve in coolers: E-02A/B, E-03A/B, E11, E12, E13, E24, E-21A/B and E-22A/B-
approx dia 1”-20m & 12Nos. 1” valve
8.8 MHP steam PV 2003 d/s b/v u/s flange leak
8.9 VM steam header b/v spectacle blind flange behind V-16 in Tech platform-1
8.10 E-22A/B ejector condensers VM steam line b/v gland leak to be replaced 4 nos
8.11 Foll leaks in P-08B to be attended- discharge b/v u/s and d/s flanges, NRV u/s and d/s
flanges, NRV spindle leak, min circ b/v gland
8.12 P-05B suction b/v flange leak to be attended
8.13 F-01 pass flow-2 FCV u/s b/v to be attended
8.14 P-06A discharge b/b u/s flange and its NRV u/s and d/s flange leak to be attended.
8.15 P-06 discharge b/v u/s flange leak to be attended
8.16 Foll leaks in P-03A to be attended- both flanges of NRV d/s spool piece and its discharge b/v
gland
8.17 P-03B discharge b/v gland leak to be attended
8.18 P-18B min circ b/v gland leak and discharge b/v u/s and d/s flanges leak , equalising valve
gland leak to be attended
8.19 P-18A min circ b/v u/s flange and gland leak, NRV top cover flange and spindle leak to be
attended
8.20 P-09A/B discharge b/v d/s flanges and gland leaks to be attended
8.21 P-11A/B discharge b/v u/s and d/s flanges (4Nos.) to eb attended
8.22 P-11B NRV flanges and discharge B/v bonnet leak and gland leak to be attended
8.23 HP steam to E-14 c/v (FV-1502) u/s drain first isolation valve d/s flange
gasket leak to be rectified
8.24 Rectification of gland leak from 1”VM steam valve to J-01A/B and J-02A/B (Total: 4Nos.)
8.25 Tracing Steam on IFO/FG/PG lines to F-01 and F-02 to be provided to prevent frequent
burner chokage (approx length: ~ 250m)-- Fuel Oil congealing problem
8.26 6” VM Steam second isolation valve at B/L u/s flange gasket replacement
8.27 HP steam root isolation valve of PT-2013 at B/L and damaged vent valve to be replaced
8.28 HP steam at B/L TI-2001 point flange leak to be rectified by replacing gasket
8.29 MHP Steam c/v at B/L (PV-2003) first isolation valve u/s bonnet flange leak to be attended
8.32 1” pressure equalising line from V-15 to E-16 gasket leak to be attended
8.33 MHP Steam to E-16 c/v (FV-1802) u/s flange gasket leak to be rectified
8.34 V-12 LCV (LV-1804) u/s valve u/s flange gasket leak to be rectified
8.35 HP Steam to E-10 (FC-1304) orifice root valve gland leak to be attended
8.38 C-07 LG 2” isolation valves gland leak and bonnet flange leak to be rectified.
8.39 Rectification of seal leak in P-02
8.42 Provision of 4” funnel with 2” header(~200 m length) for routing condensate from steam traps
of copper tubes from LG’s, etc, of all columns and vessels.
8.43 Condensate collection system from steam traps near F-01 pass flow c/v’s to be suitably
modified to avoid spillage
8.44 Dechoking of funnels and proper steam tracing on sampling points of all beds in C-02
8.45 Approx 25Nos. of defective small bore steam traps and around 30Nos of defective
condensate/steam ¾” valves are to be replaced.
8.49 Safe sampling point provision for raffinate and extract sampling like VBTar sampling point in
U-37-safety point
9.1 Rerouting C-07 LCV to technological platform for easier operation and maintenance – safety point
9.3 Revisioning / modifying existing Pilot Gas facility suitably along with provision of PRCV (self-
actuating), Pressure gauge, with fool-proof system in F-01/F-02, for safe operation of furnace.
9.4 Provision of K.O pot and strainers on FG/PG line to F-01/F-02 to arrest frequent carryover of liquid,
etc. affecting burner operation.
9.5 Provision for routing V-09 liquid to C-02 bottom at P-10A/B suction and/or P-15A/B suction.-pending
job.(related to solvent loss)
9.6 Provision of suitable strainer at Column outlet for arresting broken tray valves at C-09 and C-04, in
line with existing provision in C-07.
9.7 Replacement of connecting flue gas duct between F-02 to F-01 by larger diameter pipe, to avoid box
–presssurisation problem.
9.8 Provison for isolation valve on V-14 to V-04 transfer line suitably, for safe transfer of slop ex V-14-.For
ease of operation and better slop management.
9.9 Addl fire fighting facility in column nos. 38-C-02, C-03/04, C-05/06/07, C-08/09 & C-10 in Unit-38
9.10 Provision of bypass line for the NMP run down cooler 38-E-06
a) Rectification of TI-1303 (C-06 inlet temperature), TI-1441 (F-02 stack temperature) and
TI-1604 (C-03 inlet temperature)
b) Revisioning of c/v LV-2002 (V-16 LCV) & TCV-1202
c) Checking of DP’s of all beds of C-02: DP-1202/1203/1204/1205/1206/1027
d) Oxygen Analysers AI-1801 and AI-1441 to be attended and rectified
e) All draft gauges of F-01 and F-02 to be checked and calibrated
f) PI-1701, PI-1754, PX-1442 and PI-1441 to be checked and rectified
g) All skin thermocouples in F-01 and F-02 to be checked and repaired
h) Replacement of defective c/v LV-2002 (V-16 LCV)
i) (E-16 steam ) c/v FV 1802 to be attended for heavy passing
j) All sight glasses on CW line to seal coolers in P-05A/B and P-08A/B and P-18A/B to be
taken out and put back after cleaning.
k) Repair of all self actuating PCV’s on Inert Gas blanketing line to T-01A/B and T-02A/B
l) Rectification of FI-2101A (CW flow at B/L)
m) Revisioning of following control valves:
• PV-1301 (C-06 Pr Control)
• PV-1302 (C-07 Pr Control)
• PV-1605A/B (V-01 Pr control)
• PV-1210A/B (V-06 Pr Control)
• TV-1202 (Solvent to C-02 Temp Control)
n) Checking and Calibration of following:
• FI-1753/1752 (FD01A/B suction flow)
• FX-1754 (Combustion Air Flow)
• FI-1713/1709 (F-01 IFO inlet/Outlet flow)
• FI-1409/1406 (F-02 IFO inlet /Outlet Flow)
0) Following to be attended for frequent malfunctioning in rain:
• F-02 Pass Flows
• V-01 Level
• V-06 Level
Steam tracing to be checked. Civil maint. to do asbestos roping and celicote on the impulse
piping.
a) Hand lamps, floodlights & temporary electrical connections to be provided inside furnace, column,
vessels & other locations as per requirement.
f) Checking of Lighting system including circuit checking, replacing fused lamps/emergency lamps,
cleaning of light fitting glass, checking and sealing of JB’ s and if required, replacing the defective
light fittings etc.
a) INSULATION
• Removal of approx 300M insulation, for rectification of steam leak and re-insulate./replace all
damaged insulation
• Repair / replacement of all damaged hot insulation of columns, exchangers, pipes etc.
b) Painting of all bare lines, vessels & columns, as per colour code.
c) Painting of coolers / condensers.
d) Painting of stack and structure of furnaces.
e) All other jobs as per job list.
f) Area development in Furnace and ground floor of technological platform, near V-07, with
proper slope to avoid water-logging.
g) Concreting of base/area around samplig point in B/L after installation of sample draini tray
like in U-84
JOB LIST
for
FCCU
______________________________________________ _______Final List
1.0 FURNACE
1.1.0 Blinding / De-blinding, opening of Man-way, dropping of Burner Blocks, Erection of volumetric
Scaffolding inside the furnace, opening of Convection Manholes, opening of end-panels in
Convection section, water washing of APH module, external manual cleaning of radiation /
convection tubes, Inspection of Furnace, refractory / ceramic pad repair as per recommendations,
checking of thermocouples, cutting of tubes (if required), fitting of new tubes, welding of new
joints, pre-SR X-ray, stress relieving of joints, post-SR X-ray, hydraulic pressure testing of coils
using DM water, refractory repair of floor, revisioning of Burners, revisioning of Air-registers,
revisioning of Soot-blowers, peeps holes, damper plates and boxing up of the furnace after
completion of all activities in the Furnace
1.1.1 18-F-10
i) Scaffolding with metallic jallies should be erected in such away that all the top return bends,
middle of tubes are accessible. Through cleaning of all the return bends, tubes should be ensured
for visual inspection and thickness survey along with OD gauging.
iii) Replacement of diffuser plate of burner assembly with 6 mm thickness , SS 310 plate.
iv) Minor Ceramic fiber lining repair / replacements is anticipated. Moreover, refractory repair at floor
& burner mouth is also anticipated.
v) Internal insulation of hot air chamber of burner assy shall be renewed after painting.
vi) All the spigot supports to be inspected after thorough cleaning & removal of its external cover.
viii) External painting of heater & stack with heat resistant Al paint .
ix) Maintenance of soot blowers. To be dismantled from 18-F-10 and installed to 18-E-02.
i) The CO-Incinerator should be opened for internal inspection after thorough catalyst cleaning.
Refractory repair is anticipated in the flue gas distribution chamber, conical portion of the main
shell. Local refractory repair is anticipated at the burner mouth locations
ii) The damaged internal refractory lining of outlet duct of CO-Incinerator shall be repaired using
phosphate bonded refractory material (76 mm of H-W Greenlite 45-L + 76 mm of H-W LO
ABRADE CASTABLE with 3 wt% of SS 304 fibres.
iii) Damaged external painting shall be painted with one coat of Inorganic Zinc silicate coating (65-75
microns DFT / coat) after sand blasting followed by two coats of finish paints ( 20 microns DFT /
Coat) of heat resistant silicone Aluminium paint suitable upto 500 C. Approx area – 5 M2.
i) Refractory repair is anticipated mainly upto 50 meter height, inlet duct, bypass duct, and its blind
end. Complete renewal of refractory is anticipated mainly upto CO bypass duct height including
inlet duct. Moreover localised refractory damages are also anticipated at 70 – 80 meter height.
External patch repairs to be done wherever required using SS-316L , 5-6 mm thick). Refractory
material including lugs (Tata cast 15 Li (S), Lugs – SS-316L and dimension as per drawing) for
2007 shutdown to be used for above mentioned jobs.
ii) Replacement of stack drain line with dia 6” sch-40S , SS-316L pipe.
iii) Repair / replacement of stack access door as per original drawing using SS-316L material and
refractory lining by tata cast 15 Li (s) with ss-316L lugs.
i) Both the Air heaters including connected hot air line shall be offered for internal inspection.
Damaged external painting shall be painted with one coat of Inorganic Zinc silicate coating (65-75
microns DFT / coat) after sand blasting followed by two coats of finish paints ( 20 microns DFT /
Coat) of heat resistant silicone Aluminium paint suitable upto 500 C. Approx area – 2 M2.
2.0 COLUMN
2.1.1 Blinding / De-blinding, opening of manholes, air circulation inside the column, gas test & man-
entry, opening of tray manways, erection of scaffolding inside the column (wherever required),
unloading of structured packings from packed beds, manual cleaning of column internals,
Inspection, repair / replacement as per inspection recommendations, fixing back of columns
internals, box-up of tray manways and final box-up of column manholes after completion of all
maintenance activities in the Columns.
TOTAL : 08 NOS.
• Inspection approach for thickness survey of all the nozzle locations. Scaffolding erection for un-
approachable nozzles from outside. Insulation to be removed from all the nozzle locations for
thickness survey
• Mechanical buffing (from inside) of weld joint between top dome and shell in 18-C-10, 18-C-13,
18-C-14, 18-C-15, 18-C-16 & 18-C-18 to facilitate wet fluorescent magnetic particle inspection
(WFMPI) for suspected wet H2S cracking / H2 blistering.
• External insulation to be removed from top dome and shell locations corresponding to operating
temperature 50 – 120 C & 120 – 150 C to find out CUI. In case of deterioration, complete
insulation renewal may come. The shell surface shall be painted with High temperature AL paint
after proper manual cleaning.
3.0 REACTOR
Blinding / De-blinding, opening of manholes, air circulation inside the Reactor, gas test & man-
entry, opening of internals, erection of scaffolding inside the Reactor (wherever required),
manual cleaning of internals, Inspection, repair / replacement as per inspection
recommendations, refractory jobs as per requirement, fixing back of internals, and final box-up of
manholes after completion of all maintenance activities in the Reactor , External painting with
high temperature Al paint.
3.1.1
i) 18-R-01
ii) 19-R-04
4.0 REGENERATORS
Blinding / De-blinding, opening of manholes, air circulation inside the Regenerators, gas test &
man-entry, opening of internals, erection of scaffolding inside the Regenerators (wherever
required), manual cleaning of internals, Inspection, repair / replacement as per inspection
recommendations, refractory jobs as per requirement, fixing back of internals, and final box-up of
manholes after completion of all maintenance activities in the Regenerators.
4.1.1 18-RG-01
4.1.2 18-RG-02
i) Internal inspection of Catalyst lift line shall be offered after cutting the man-way at the top of
catalyst distributor. Moving “Julla” to be provided for Internal inspection of Lift Line, for possible
refractory / HEX mesh damage. Local repair is anticipated in abrasive resistant refractory lining
(Resco AA-22S, 19 mm thick). Moreover, external surface of catalyst lift line shall also be
inspected.
ii) Internal inspection of shell refractory lining condition after provision of scaffolding from bottom
upto the top. Metallic jallies are to be provided at different levels of scaffolding. Localized
refractory lining repair is anticipated at the bottom conical portion of RG-02. Resco cast 9Li (125
mm thick) is required for such repair and approx area is 5 M2.
iii) Inspection of all the cyclones (both external and internal) including their dip legs . Possible
refractory repair in the Ducts connecting Primary Cyclone to Secondary Cyclone and Secondary
Cyclone to Plenum chamber of RG-02. Refractory material (Resco 17E , 100 mm thick) may be
ensured for approx 2 M2 area
iv) Inspection of Air rings of both the Regenerators. Possible abrasive resistant refractory lining
repair (Resco AA-22A, 25 mm thick) at outer and inner air ring of RG-01 and Air ring of RG-02.
Approx quantity of anticipated repair – 5 M2 . Refractory material and Hex mesh (SS-304) shall
be kept ready.
v) Repair / replacement of Torch oil nozzles (SS 304H) in both the Regenerator. Replacement for 4
nos of nozzles as per M/s SWEC DRAWING.
vi) Repair of bulged / damaged liner of bottom manhole of Regenerator-II using SS-304 (6 mm
thick) material.
vii) Repair of top support weld joint of catalyst lift line. Modification of top support weld joint of catalyst
lift line as per SWEC approved drawing.
viii) Inspection of the bathtub distributor after catalyst cleaning. Minor refractory lining (Resco AA-
22A, Resco cat 9Li) repair is anticipated , approx area – 1 M2.
5.0 RISER
i) Riser bottom cover shall be opened for inspection of WYE stabilization steam ring.
ii) Material for stabilization steam ring shall be ensured as per SWEC drawing no 18-A1-411-014
(Main ring: Mat- SS-304H, Dia – 3” SCH XXS pipe 170 Rad,, Drain Nozzle: Strictly as per
SWEC drawing) for anticipated replacement / any eventuality.
iii) External abrasive resistant refractory lining (Resco AA-22S, 25 mm thick) of the subject steam
ring shall be renewed.
iv) All the welding joints of WYE-Segment should be offered for DP test. Buffing of welding of WYE-
segment also to be carried out to facilitate Ultrasonic Flaw Detection.
i) Provision shall be made for thorough internal assessment of VC lining condition as well as
abrasive resistant refractory lining with a movable trolley and proper lighting.
ii) Repairs are anticipated in protective sleeves of feed nozzles / HCO nozzles / slurry back wash
nozzle. with Stelliting electrode (Stellite 1 & 6).
iii) Replacement of VB naphtha nozzle of Riser as recommended earlier vide Inspection report
H/INSP/18.0 dated June 6, 2005.
iv) VC lining repair may come in riser pipe and accordingly Resco 17 E to be kept ready for any (for
approx 8 M2 areas having thickness of 100 mm).
v) Abrasive resistant refractory Resco AA-22S to be kept ready for repair in internal riser for (approx
4-5 M2 areas having thickness of 25 mm.)
i) Thorough inspection of ROT thermo well connections and this will necessitates cutting of cover
plate of both the horizontal gas tubes. Material for ROT CAP to be kept ready.
ii) Pre-Stripping steam ring including its drain nozzle (OD 60.3 mm, 8.74 mm thick, R200 (cold), SA
106 GR B) of both the Dipleg of LDD may come for replacement. Material for steam ring and its
drain nozzle to be kept ready.
iii) External abrasive resistant refractory lining (Resco AA-22S) of Pre-Stripping steam rings are also
to be renewed. Local repair of abrasive resistant refractory lining (Resco AA-22S) of DIP Legs of
LDD and vertical gas tubes of LDD are also anticipated.
5.1.3 Cyclones:
i) Arrangement should be made for internal inspection of cyclones using Rope ladder.
ii) Cleaning of External surface of Dip leg of both the cyclones for thorough visual inspection
and thickness survey.
iii) Inspection of Trickle valves to be done for suspected erosion of seating / sealing surface.
iv) Inspection of all the support locations to be done after thorough cleaning (coke deposits also
likely). Necessary scaffolding is to be prepared for inspection, wherever needed, to facilitate
inspection.
5.1.4 Stripper:
ii) Fluffing steam ring (CS, OD 88.9 mm, 7.62 mm thick, 6.5 mm & 5.9 mm drilled holes as per
BHPV drawing no PPPV-2120-01-A-000-Rev A1 SHT 6 of 7) located at the bottom of stripper
may come for repair / replacement.
iii) Anticipated repair / replacement nozzle of main Stripping steam ring as per BHPV drawing no:
PPPV-2120-01–A-000 – Rev A2 and as per details given below :
Main nozzle: SA 105, Length – 115 mm, Nozzle ID – 19.5, RO ID – 12.5 mm, Quantity - 10 nos
Drain nozzle: SA 105, Nozzle ID – 22 mm, RO ID – 6 mm, Length – 155 mm, Quantity - 3 nos
iv) Refractory lining (Resco 9Li, 100 mm thick) damage is anticipated at the Fluffing steam ring
location and the same shall be repaired, if required, with “Tapered plug” design as per SWEC
earlier recommendation using Resco cast 9Li refractory.
6.0 VESSEL
6.1.0 Blinding / De-blinding, opening of manholes, air circulation inside the vessel, gas test & man-
entry, opening of internals (wherever required), removal of external insulation of nozzle location
and inspection pockets provision at shell area especially at top and bottom for insulated vessels,
erection of scaffolding inside the vessel (wherever required), manual cleaning of vessel internals,
Inspection, repair / replacement (if required), re-fitting of vessel internals, hydrotesting as per
Factory Act, external painting , final box-up of the vessel after completion of all activities in the
vessels.
• Mechanical buffing of weld joints to top dome from inside in 18-B-11, 18-B-12, 18-B-13, 18-B-14,
18-B-19, 18-B-20 & 18-B-21 to facilitate wet fluorescent magnetic particle inspection (WFMPI) for
suspected wet H2S cracking / H2 blistering.
• Removal of external insulation of nozzle location and inspection pockets provision at shell area
especially at top and bottom for insulated vessels. In case of CUI, complete removal of insulation
and painting to be done followed by re-insulation.
• Internal cleaning to be carried out before offering for internal inspection and thickness survey.
• Opening and cleaning of Demister pad assembly in 18-B-11, 18-B-12, 18-B-13 18-B-19, 18-B-20,
18-B-21, 18-B-22, 19-B-03 & 19-B-20.
• External painting of vessels is to be done as per IOCL painting manual. External insulation job is
to be done as per inspection recommendation during shutdown
• 18-B-21 & 19-R-04 vent outlet flame arrestors at CO incinerator to be fitted back and its
connected piping to be dechoked
i) All the manholes of both the orifice chambers should be opened for internal inspection.
ii) Injection of pump-able thermal ceramic fiber through the existing 4 nos external threadolets at
each and every grid level of both the orifice chambers. Fiber lining details is as per BHPV
drawings nos. PPPV – 2120 11 – A-002 (Rev 3) & PPPV – 2120 12 – A-002(Rev 2).
iii) Man way opening through grid levels to be made by cutting welded segments of grids at its
central location & this is to be done for all the grid level of both the orifice chamber.
iv) Repair of damaged refractory lining should be carried out as per specifications given in BHPV
drawings nos. PPPV – 2120 11 – A-002 (Rev 3) & PPPV – 2120 12 – A-002(Rev 2).
vii) Two nos internal Retainer plate (CS & SS – 304H, 18 MM thick each) may come for replacement.
Dimension of plates are as per M/S BHPV drawings PP-2120 12 –A-000 Rev 4 .
i) Dia 96 inch bellow installed at the outlet of CO-Incinerator (Tag No- VA-359-1) should be
replaced with upgraded metallurgy (Inconel – 625 LCF) .100% radiography of weld joints shall be
carried out in addition to normal inspection procedures like fit up check, DP check.
ii) Inspection of all the other bellows installed in flue gas lines to be done after removal of external
protection covers . The 54” bellow in flue gas line ex RG-01 (Tag No VA-357-R1), which was
replaced in May / June –2003 with the then available SS-304 metallurgy may require replacement
with upgraded metallurgy (Inconel-625 LCF). Final decision shall be taken based on the
shutdown observation.
iii) Inspection of Bellows installed at the spent catalyst line as well as at the catalyst lift line to be
done after removal of external protection cover plates.
iv) Misaligned bellow between CO-Boiler outlet duct and inlet of Quench tower is to be rectified as
per ES opinion. This was not done in the last shutdown. Drawing to be supplied by ES deptt.
v) Other bellows ( 54” & 42”) in R/R section and bellows at the inlet of 17-P01 A/B/C to be offered
for inspection.
7.0 HEAT EXCHANGERS
i) 18-E-10A/B
ii) 18-E-11
iii) 18-E-12
iv) 18-E-13 A/B
v) 18-E-14
vi) 18-E-15
vii) 18-E-16 A/B
viii) 18-E-18 A/B
ix) 18-E-19 A/B
x) 18-E-21 A/B
xi) 18-E-23
xii) 18-E-24
xiii) 18-E- 25 A/B
xiv) 18-E-26
xv) 18-E-27
xvi) 18-E-28
xvii) 18-E-29
xviii) 18-E-30
xix) 18-E-31
xx) 18-E-32 A/B
xxi) 18-E-33 A/B
xxii) 18-E-34 A/B
xxiii) 18-E-35
xxiv) 18-E-36 A/B/C/D
xxv) 18-E-37
xxvi) 18-E-38 A/B
xxvii) 18-E-40 A/B/C/D/E/F
xxviii) 18-E-41
xxix) 18-E-42 A/B
xxx) 19-E-01
xxxi) 19-E-02
The following air fin coolers are to be offered for inspection as below.
• Cleaning of tube bundles by hydro jetting. Fan blade removal and scaffolding erection upto tube
height.
• As recommended earlier vide H/Insp/18.0 dated 14/08/2006, material availability for 18-EA-11
C/D (Two nos) may be ensured for anticipated replacement.
• As recommended earlier vide H/Insp/18.0 dated 29/12/2006, material availability for re-tubing of
18-EA-10 A/B (Two nos) may be ensured for anticipated replacement
• Tube ID measurement from both header ends. Therefore degree of cleaning shall be extremely
good.
• Visual inspection of internal condition of tubes is to be carried out before and after hydro jetting.
• Tube testing is to be carried out at respective test pressures. Individual ttube test arrangement
may be ensured for identification of leaky tube, if any. Approach from bottom and proper
illumination is required during hydro test.
Although the flue gas cooler (18-E-02) will be due for IBR inspection in April-2007 As a routine
practice, IBR authority will witness dry inspection as well as hydro testing at 37.5 kg/cm2 (g)
pressure. The following components are under the preview of IBR inspection.
ii) Through cleaning of bottom bends of economizer coils to be carried out before IBR inspection.
iii) Cleaning and inspection of downcomer / bank tubes/super heater coils /screen tubes/headers.
Casing plate to be cut for thorough inspection of Screen tubes, at top header location. 3 nos of
screen tubes, which were patch repaired earlier, shall be replaced in the shutdown. Material
specifications: (OD – 50.8 mm, 3.25 mm thick, SA 210 GR A1 HFS, IBR material and length and
shape as per drawing no HJ G317 0291 of M/s Thermax).
iv) Replacement of steam drum safety valves(2 Nos.). Super heater safety valve shall be overhauled
& tested at W/S.
v) Replacement of 29 nos of bank tubes, which were patch repaired earlier on account of localized
thinning caused by improper soot blowing.
vi) Leaky drain line of CO-Boiler is to be replaced using ASTM A 106 GR B, SCH-160 pipe.
vii) Anticipated replacement of one no. super heater coil (coil no 16, counting from top), which was
plugged during May / June 2003 shutdown .
viii) Replacement of manhole cover of Screen tube zone,if reqd, shall be as per Thermax’s existing
drawing.
ix) Replacement of gasket sealing at the rectangular joint between flue gas cooler and connecting
duct (Ex CO-Incinerator).
x) All the jobs shall be carried out by ibr approved agency and compliance with all the ibr rules and
requirements including material identification, repair procedure approval, stage wise
inspection/approval and final hydro test clearance.
xi) Hydro testing of flue gas cooler is to be carried out at 37.5 Kg/Cm2 g pressure using DM water .
SCSV/ RCSV / DDSVs shall be opened for inspection & maintenance. Partial replacement of
orifice plate, guides, disc may come after inspection. , hex-mesh, resco aa-22s and spares etc
to be kept ready. Checking and repair / replacement of hand wheel gear system.
Inspection of plug valve and possible replacement / repair of plug. Checking and repair /
replacement of hand wheel gear system
Scaffolding erection and, or insulation removal to be carried out for the following piping circuits for
inspection purpose. HPV and LPD locations are also to be offered for thorough inspection (after
insulation removal for insulated line). All the bends / reducers are to be exposed for inspection
purpose. Moreover, representative samples of main pipes are also to expose for inspection (Min.
10% of main pipe). Replacement recommendations, if any, shall be communicated after the
subject inspection. Moreover, Inspection pockets shall be provided in insulated lines.
a) SLURRY CIRCUIT
b) HEATER TRANSFER CIRCUIT
c) 18 C 10 OVERHEAD LINE UPTO MAIN FRACTIONATOR OVERHEAD RECEIVER CIRCUIT
d) HCO CIRCUIT (RECYCLE)
e) DEBUTANIZER COLUMN FEED CIRCUIT
f) ABSORBER OVERHEAD VAPOUR CIRCUIT
g) DEBUTANIZER OVERHEAD CIRCUIT
h) HCO PUMP AROUND CIRCUIT
i) OVERHEAD RECYCLE VAPOUR CIRCUIT
j) STRIPPER FEED AND ABSORBER FEED CIRCUIT
k) SPONGE ABSORBER FEED VAPOUR & OFFGAS FROM SPONGE ABSORBER CIRCUIT
l) LPG PRODUCT & DEBUTANIZER REFLUX CIRCUIT
m) FCCU FEED CIRCUIT
n) NAPTHA SPLITTER REFLUX & LCN PRODUCT CIRCUIT
o) OVERHEAD NAPTHA SPLITTER CIRCUIT
NOTE : All HPV & LPD of hydrocarbon lines shall be inspected and weld reinforcement will be done with
provision of additional valves wherever required.
The following pipelines shall be offered for internal inspection / cleaning and refractory repairs, if any.
- Flue gas lines Ex 18-RG-01 & 18-RG-02
- Flue gas lines Ex 18-B-04 & 18-B-05
- Reactor overhead line – coke removal job.
- Spent catalyst stand pipe
- Regenerated catalyst stand pipe
Replacement of distorted hanger rods of constant spring supports installed on flue gas line Ex 18-
RG-02 - 4 nos.
11.0 CIVIL JOBS
1) Complete insulation renewal at Super heater headers, Screen tube headers and at the
membrane panel casing locations.
2) Water side (channel head / channel box / partition plates etc.) components of coolers
/condensers to be painted with high build epoxy paint after proper surface preparation (Sa 2 ½)
15.0 AF JOBS
VALVE-GLAND JOBS
MISCELLANEOUS JOBS
1.1.5 Defective Skin thermo couple (TI 1225) of naphtha Super heater
(24-F-01) furnace to be replaced with new thermo couple. Filler rod
ER-347 to be used for welding purpose followed by DP testing. The
other thermo couple should be offered for Visual inspection & DP
testing and repair / replacement recommendation , if any, will be
issued only after inspection.
1.1.9 Bellows in the flue gas line should be offered for inspection after
casing removal and suitable cleaning.
1.1.12 External painting of heater and stack with heat resistant aluminium
paint after proper manual surface cleaning.
2.1.5 Two nos. water collector at the tube bottom and continuous
removal of water from furnace to be ensured.
2.1.7 Scaffolding from floor level upto radiation top is to be erected for
thorough inspection of catalyst tubes (visual, OD gauging,
thickness gauging, radiography) and assessment of refractory
condition. Metallic jallies to be provided at different level of
scaffolding for smooth and safe inspection. The following NDT
requirement may be arranged to facilitate the inspection.
2.1.9 Radiogrpahy – 60 nos weld joints of catalyst tube (OD – 136 mm)
after unloading the entire catalyst .
2.1.10 DP testing – 30 nos of weld joints of catalyst tubes (OD – 136 mm)
2.1.11 Total 35 nos of Catalyst tubes may come for replacement. All the
material including refractory and insulation for catalyst tube
replacement job is to be ensured as per Inspection report on HGU
shutdown vide H/INSP/24.0 dated September 16, 2006. During
replacement, TIG welding shall be carried out. 100 % radiography
(10 segment for each tube) to be carried out.
2.1.12 Refractory lining of inlet tube sheet of waste heat exchanger 24-E-
17 shall be removed for thorough inspection of ferrules.
Replacement of 264 Nos. ferrules. After inspection and ferrule
replacement, the refractory lining is to be renewed as per
specification given in Inspection report vide H/INSP/24.0 dated
September 11, 2006 (Anchor – SS-310, Height – 50 mm, dia- 6
mm, 33 nos + refractory Firecrete 95 or equivalent 75 mm thick.
Heat curing / dry out of refractory lining shall be as per approved
procedure. Reputed vendor, who has don similar job, may be
engaged.
2.1.13 The balance Calcium silicate insulation of feed inlet line (dia-8”)
shall be renewed at the next shutdown. Moisture barrier shall also
be provided.
2.1.14 Hot spot in burner blocks A2/7 & B2/7 to be suitably attended.
2.1.16 After casing/panels removal, all the bends of 24-E-11, 24-E-12 &
24-E-13 should be offered for visual inspection / thickness survey.
2.1.18 Cleaning and revisioning of 40 Nos. burners, 25 nos. off gas valves
& 25 Nos. air-registers. Replacement of aprox. 25 nos. Naptha
Valves.
2.1.19 Internal tube cleaning by acetone for all new 35 Nos. of tubes.
4.1.1. 24-AC-01
4.1.2. 24-AC-02
4.1.3. 24-AC-03
(Total – 3 Nos.)
5.0 Heat Exchangers (Check-III)
5.1 Blinding/ de-blinding, opening of the covers, pulling out of the tube bundle
from the shell (wherever required), cleaning of shell, hydroblasting of tube
bundle, repairing job, if any, Inspection, testing and boxing up are to be
performed for the following exchangers / coolers / condensers including
blinding/deblinding job.
Total no. – 38
6.0 Vessel
7.0 REACTORS:
7.1.1 24-R-01 – Passivation, buffing of weld joints (10m X 16” wide) for
insitu metallography & DP testing. catalyst replacement.
7.1.2 24-R-02 – DP testing (2m ), catalyst replacement.
7.1.3 24-R-03A/B - catalyst replacement.
7.1.4 24-R-104 - DP testing (3m) & catalyst replacement.
Total. – 16 Nos
12.1 Water wide (Channel head / Channel box / partition plates etc.)
components of coolers / condensers should be painted with high
built epoxy paint after proper surface preparation (SA 2 ½).
14.1 Hand lamps, flood light and temporary electrical connections are to
be provided inside Furnaces, Reactors / Vessels and at other
locations as per requirement.
ARU
________________________________________ _____________Final List
Blinding / De-blinding, opening of manholes, air circulation inside the column, gas test & man-
entry, opening of tray manways and internals (wherever required), erection of scaffolding inside
the column (wherever required), manual cleaning of internals, Inspection, repair / replacement as
per inspection recommendations, fixing back of internals, box-up of tray manways and final box-
up of equipment after completion of all maintenance activities.
All the nozzles shall be exposed by removing insulation and necessary scaffolding arrangement
shall be made to facilitate thickness survey of nozzles, wherever necessary.
The bottom dome is without insulation. Same shall be provided after fixing lugs etc.
2.0 VESSEL
Blinding / De-blinding, opening of manholes, air circulation inside the vessel, gas test & man-
entry, opening of internals (wherever required), erection of scaffolding inside the vessel (wherever
required), manual cleaning of vessel internals, Inspection, repair / replacement (if required), re-
fitting of vessel internals, final box-up of the vessel after completion of all activities in the vessels.
i) 26-V-01
ii) 26-V-02
iii) 26-V-04
iv) 26-V-06
v) 26-V-07
vi) 26-V-08
vii) 26-T-01
All the nozzles shall be exposed by removing insulation and necessary scaffolding arrangement
shall be made to facilitate thickness survey of nozzles, wherever necessary.
3.0 FILTER
Blinding / De-blinding, opening of manholes, air circulation inside the vessel, gas test & man-
entry, opening of internals (wherever required), erection of scaffolding inside the vessel (wherever
required), manual cleaning of vessel internals, Inspection, repair / replacement (if required), re-
fitting of vessel internals, final box-up of the vessel after completion of all activities in the vessels.
1. 26-FS-01
2. 26-FS-02A/B
3. 26-FS-03A/B
Blinding / De-blinding, opening of covers, pulling out of tube bundles wherever required,
hydro-blast cleaning of tube bundles, Inspection, repair / replacement (if required),
painting of all water side channel / channel cover / partition plates with high build epoxy
paint after proper surface preparation (SA 2½ ), replacement of sacrificial anodes as per
inspection recommendations, insertion of tube bundles, shell test, tube test and final box-
up of the equipment after completion of all activities of the heat-exchangers.
Exchangers - 26-E-02A/B & 26-E-03A/B
Coolers - 26-E-01 & 26-E-04 (Replacement, if material is available)
Air Coolers - 26-AC-05 & 26-AC-06
------------------------------------X------------------------------------X----------------------------------X-----------------------------------
THERMAL POWER STATION
Final list
1.0 TANK :
2.0 VESSEL :
Following PSV s / TSV s are to be sent to workshop for overhauling and testing:
VALVE JOBS :
7.1 De-silting and repairing of Process, TPS & DHDS cooling towers.
7.2 Repair of under water wooden structures in PCT & TPSCT sump.
7.3 Water side components of cooler & condensers are to be painted with appropriate paint system.
7.4 External painting of static equipment & piping where ever damaged for non existing are to be
done .
7.5 Removal of insulation from the lines as mentioned in Sl. No.5.0 & re-insulation after Inspection &
Maint job .
7.6 Insulation pockets are to be provided at critical locations as per recommendations of Reliability
Task Force.
7.7 Following lines are to be painted as per recommendation:
10 Un-insulated lines near CT area External As per Advanced paint system already
finalized
11 Un-insulated lines near DM External As per Advanced paint system already
plant finalized
12 Equipment near DM plant External As per Advanced paint system already
finalized
13 Sand filters in DM plant Internal IOZ silicate + Epoxy Zinc phosphate
+ HB epoxy
14 CT Risers External Advanced paint system already
finalized
15 CT headers to and from TPS External Advanced paint system already
finalized
Structurals are to be painted with SA 21/2 + IOZ silicate + Epoxy zinc phosphate + CT
epoxy paint system.
8.0 ELECTRICAL MAINTENANCE JOBS :
a. During check-III maintenance of Heat exchangers, deteriorated Stud / Nuts and all the
Gaskets are to be replaced with new ones.
b. Insulation of critical tap-off points at HP lines to be removed for inspection activities like
visual and DP testing.
d. Sacrificial anodes of the coolers and condensers are to be replaced with fresh ones-
approx. no-100 nos.
a Installation of welded valve in BFW Line of TPS for boiler No. 1, 2 & 3
b Enlargement of suction piping of 64P01L
Gas Turbine & HRSG
Shutdown Job List
Final List
Mechanical Jobs
11. Rectification of HRSG VM Steam drain traps and trap bypass line valve
(area near Tank dyke & Control room).
13. Repair / replacement of Huge expansion bellows between HRSG & HRSG
stack.
14. Repair / Replacement of Perforated casing bellows
Dia 1” drain line of superheater-II inlet header (12” dia) shall be replaced
With SA335 P22 , sch-80 material
Instrument Maintenance:
1. All Servo valve (IGV & Fuel control) filters are to be replaced.
2. Testing & Calibration of SO2 & dissolved O2 analyzers, pH & conductivity
analyzers of HRSG SWAS panel.
3. Any hook up job of DCS/PLC between existing and incoming panels.
4. Frequent failure of HRSG burners while lighting up to be rectified.
5. Defective pr. & Temp. Gauges to repaired/replaced. (Final list will be given
a week before s/dn).
6. All exhaust TC’s junction boxes are to be opened for checking TB
condition and
Tightness.
Electrical Maintenance:
Civil maintenance:
Project :
Process Modification :
.
1. Modification of CW I/L & O/L of oil cooler in GT
OFFSITE
Final list
1.0 VESSEL
TOTAL : 07 NOS.
ii. PARTIAL REPLACEMENT OF ACID FLARE TIP ALONG WITH RETENTION RING AND
FLAME STABILISER WITH INCONEL-625 METALLURGY.
iii. REPLACEMENT OF ALL THE PILOT BURNER ASSEMBLIES OF BOTH THE FLARES (4
NOS. IN HYDROCARBON FLARE & 3 NOS. IN H2S FLARE) WITH NEW ONES.(
METALLURGY-SS 304).
iv. EXTERNAL STEAM PIPE OF HYDROCARBON FLARE MAY COME FOR REPLACEMENT
(APPROX LENGTH – 1000 MM). MATERIAL: SS 316 PIPE. SIZE- Φ1” SCH-40.
v. REPLACEMENT OF DAMAGED WIND SHIELD OF BOTH THE FLARES WITH NEW ONE.
(METALLURGY-INCOLLOY 800H)
vii. SUPPORT FLATS ALONG WITH CENTRALLY LOCATED SUPPORT PIPE MAY COME
FOR COMPLETE REPLACEMENT.
viii. SUPPORTS OF STEAM / PILOT GAS /AIRLINES MAY COME FOR REPLACEMENT.
Page 1 of 1
M/PL/61
Page 2 of 2
M/PL/61
3.8.1 Dia.6” = 120 M - Circ. line of Tk-418 I/L to Tk-418 / Ex.U-11 to Tk-424
3.8.2 Dia.8” = 60 M - HSD to Barge
3.8.3 Dia.14” = 60 M - HSD under culvert
Page 3 of 3
M/PL/61
3.14.1 Dia.3” = 24 M -
3.14.2 Dia.4” = 30 M
3.18.1 Dia.2” = 120 M - Rich Amine ex. U-35 / Lean Amine to U-35
3.18.2 Dia.3” = 60 M - Ex. DHDS
Page 4 of 4
M/PL/61
3.20.1 Dia.1 ½” = 60 M
3.20.2 Dia.2” = 240 M
3.20.3 Dia.3” = 300 M
3.20.4 Dia.8” = 30 M (Plant air)
3.25.1 Dia.2” = 15 M
3.25.2 Dia 3” = 15 M
Page 5 of 5
M/PL/61
All support location shall be provided with extra reinforcement pad over the pipe
whever required.
Hydrotesting shall have to be done for all LPG, HYDROGEN and OFFGAS lines.
Hydrotesting of other lines should be done depending on availability of time.
TOTAL : 26 NOS.
Page 6 of 6
M/PL/61
6.1 Providing power connection for welding / grinding / sand blasting machines etc.
6.2 Providing light for all locations wherever required.
6.3 Arranging 4 Nos. walky-talky sets for flare tip job.
8.1 Repl of existing impellers & couplings of DHDS feed pumps 61-P-101A/B with higher
size impellers
8.2 Repl of existing impeller of HGU feed pump 61-P-102A with higher dia impeller
8.3 Flare line replacement
8.4 Modification in supports of MP steam line in Track-B pipe rack in Offsite
Page 7 of 7
Annexure-I
1.1.1 Following Cooling Water Lines (Above ground) shall be replaced (Annex-III)
Sl. No. Size Schedule Approximate
Length
1 3 INCH 80 5 MTRS
2 10 INCH 30 40 MTRS
3 18 INCH 30 50 MTRS
4 20 INCH 30 25 MTRS
1.1.2 Following Cooling Water Lines (Under ground) shall be replaced (Annex-III)
Sl. No. Size Schedule Approximate
Length
1 8 INCH 30 10 MTRS
2 12 INCH 30 20 MTRS
2.1.1 Following above ground Cooling Water Lines shall be replaced as per details in Annex-I.
Sl. No. Size Schedule/Thickness Approximate
Length
1 2” 80 150
2 3” 40 100
3 4” 40 125
4 6” 40 360
5 8” 40 300
6 12” 8 mm 150
7 16” 10 mm 100
8 20” 12 mm 080
9 24” 12 mm 090
10 28” 12 mm 030
2.1.2 Following under ground Cooling Water Lines shall be replaced as per Annex-II.
Sl. No. Size Schedule Approximate
Length
1 8 INCH 40 48 MTRS
2 10 INCH 40 12 MTRS
3 12 NCH 40 44 MTRS
4 12 INCH 30 14 MTRS
5 16 INCH 30 36 MTRS
6 18 INCH 30 24 MTRS
7 20 INCH 20 04 MTRS
8 24 INCH 20 56 MTRS
9 28 INCH 20 24 MTRS
Annexure-I
3.1.1 Approximate length of Cooling Tower riser pipes to be replaced—270 MTRS (Size-24 INCH).
UNIT - 31 :
UNIT - 32
Sl no Line location Approx Specification Matl
length
1 φ24” inlet header at n/e corner of the main 40 mtrs. φ24” / thk 12 mm API 5L / EFSW
platform
2 φ24” outlet header at n/e corner of the main 43 mtrs. φ24” /thk 12 mm API 5L / EFSW
platform
3 φ8” inlet line (last 2 mtrs including the bottom 18 mtrs. φ8” sch.40 A-106 Gr. B
bends up to the inlet nozzles of 32-E-06
condenser pairs)
4 φ8” outlet line (first 6 mtrs including the bottom 30 mtrs. φ8” sch.40 A-106 Gr. B
bends from the outlet nozzles of 32-E-06A/A1,
C/C1, D/D1, F/F1, I/I1 condenser pairs)
5 φ8” inlet /outlet circuits connected to condenser 24 mtrs φ6” sch 40 A-106 Gr. B
34-E-06B/B1
6 φ3” line going to pumps 32-P-110C/D/E up to 6 mtrs φ3” sch 40 A-106 Gr. B
isolation valve (balance already recommended)
7 φ12” line connected to main header at north of U- 6mtrs φ12 ” sch 30 API 5L / EFSW
32 (rose portion)
8 φ2” line to 32-K-01 6mtrs φ2” sch 80 A-106 Gr. B
9 φ3” inlet header to 32-K-01 15 mtrs φ3” sch 80 A-106 Gr. B
10 φ2” o/l header to 32-K-01 15mtrs φ2” sch 80 A-106 Gr. B
11 φ2” header portion to 32-P-04/5 6 mtrs φ2” sch 80 A-106 Gr. B
12 φ8” ETP treated water to 32-C-107 90 mtrs φ8” sch 40 A-106 Gr. B
13 φ6” ETP treated water to 32-C-107 16 mtrs φ6” sch 40 A-106 Gr. B
Annexure-I
UNIT -33
1) Cooling water Inlet/Outlet of 33-J-01.
Material – A 106 Gr. B, Size - Φ4”, Sch-40. Length- Approx.-10 M.
UNIT-34
Sl Line location Appro Specificati Matl
no x on
length
1 φ28” inlet header at n/w corner of the main platform 18 φ28” / thk API 5L /
mtrs. 12 mm EFSW
2 φ28” outlet header at n/w corner of the main platform 12 φ28” /thk API 5L /
mtrs. 12 mm EFSW
3 φ24” inlet sub header below 1st platform 30 φ24” /thk API 5L /
mtrs. 12 mm EFSW
4 φ20” outlet header at n/w corner of the main platform 30 φ20” /thk API 5L /
mtrs. 12 mm EFSW
5 φ6” outlet circuits connected to condenser 34-E-15D 16 mtrs φ6” sch 40 A-106 Gr. B
6 φ8” line to outlet sub header from u/g 16 mtrs φ8” sch 40 A-106 Gr. B
7 φ6” line from inlet sub header to u/g 14 mtrs φ6” sch 40 A-106 Gr. B
8 φ6” inlet line to 34-E-2/I 18 mtrs φ6” sch 40 A-106 Gr. B
9 φ12” inlet line to 34-E-16 10 mtrs φ12” / thk 8 API 5L /
mm EFSW
10 φ12” inlet line to 34-E-17D 10 mtrs φ12” / thk 8 API 5L /
mm EFSW
11 φ16” 2nd inlet sub header connected to coolers 37-E- 6 mtrs φ16” / thk API 5L /
15A/B/C 10 mm EFSW
12 φ12” reduced inlet header (down stream portion of main 35 mtrs φ12” / thk 8 API 5L /
header) at two locations mm EFSW
13 φ8” reduced inlet header ( down stream portion of main 12 mtrs φ12” sch 30 A-106 Gr. B
header)
Annexure-I
14 φ20” reduced outlet header (up stream portion of main 10 mtrs φ20” / thk API 5L /
header) 12 mm EFSW
16 φ6” inlet line of 34-E-10C at 2 locations 20mtrs φ6” sch 40 A-106 Gr. B
UNIT : 35
UNIT –37 :
Scheme
Sl. No. Name of the Scheme Execution By Agency
No.
Area : TPS
AF JOBS
73 RH0135 VR Burning in TPS Project Agency lined up
PROCESS MODIFICATION SCHEMES
74 58 Installation of welded valve in BFW Line of Maintenance Estimate clubbed with
TPS for boiler No. 1, 2 & 3 Maintenance job.
75 Enlargement of suction piping of 64P01L - do - Agency available
Area: GT
PROCESS MODIFICATION SCHEMES
76 Modification of CW I/L & O/L of oil cooler in Maintenance
GT
Area : OFF-SITE
AF JOBS
77 RH0136 VR Burning facility - Offsite jobs P&U Agency for motor repl job
(Electrical) / available; coupling repl to be
Maint. (Mech) done by Workshop
78 RH0161 Modernisation of 1st Gantry - Additional Project Estimate shall be prepared
jobs including facelifting after approval of additional
jobs
79 RH0218 Hook-up for Flare Gas Recovery System Maint. Agency available
PROCESS MODIFICATION SCHEMES
80 175 Repl of existing impellers & couplings of Maintenance To be done by Workshop
DHDS feed pumps 61-P-101A/B with
higher size impellers
81 Repl of existing impeller of HGU feed pump - do - - do -
61-P-102A with higher dia impeller
82 Flare line replacement - do - Civil: Agencies lined up;
Mech: Agency by Maint. Plg.
85 Tube bundles: - do - - do -
a) 11-E-08A
b) 11-E-14
c) 11-E-16
d) 11-E-17
e) 16-E-16
f) 16-E-36
g) 22-E-01A
h) 22-E-01B
i) 22-E-02
j) 25-E-09
k) 34-E-15D
l) 34-K-01A intercooler
m) 35-E-02 (duplex SS)
n) 37-E-02a
o) 38-E-03 A/B
p) 38-E-17
q) 38-E-25
r) 57-K-01A Intercooler
87 Vessel - do - - do -
a) 61-B-02
ADDITIONAL JOB LIST
CDU-I
11-F-01 :
Cleaning of convection zone with soda ash solution
Water washing of APH
EXCHANGER:
Maintenance of following exchangers
11-E-5A/B/C/D, 7A/B/C/D, 9A/B/C/D, 10A/B/C/D/E/F/G/H, 43
CDU-II
16-F-01 :
Cleaning of convection zone with soda ash solution
Water washing of APH
EXCHANGER :
Maintenance of following exchangers
16-E-8A/B/C/D, 10A/B/C/D, 11A/B, 12A/B, 13A/B/C/D, 14C/D,
VDU-I
EXCHANGER:
Maintenance of following exchangers
31-E-02A/B/C, 7,14A/B, 127,128
MISCELLANEOUS JOBS :
TAG JOBS :
FEU
EXCHANGER:
Maintenance of following exchangers
33-E-4, 5A/B, 6, 11C/D, 14
MISCELLANEOUS JOBS :
Tag Jobs :
• Rectification of tracing steam header East side of 33 E-8 long bolts /short bolt/
Missing bolts ( Approx 50 nos)
• 2 nos extended ¾” tracing steam lines from P-105 to be removed apx 20M.
• Redundant ¾” tracing steam line near C103 /104 to remove for ease of movement
• ¾” tracing condensate line –( hanging ) 10 M. near C5/C6 to be relocated.
• B04- steam heating coil leak to rectify.
• 33 E-2 (West side ) inlet line to check for leakage
• 10” PSV line ex 33-C2 to B-10 to be de-choked & thoroughness to ensure
SDU
EXCHANGER:
Maintenance of following exchangers
34-E-15A/B/C/D
HFU
EXCHANGER:
Maintenance of following exchangers
35-E-2, 102, 6, 7
VBU
EXCHANGER:
Maintenance of following exchangers
37-E-1A/B/C/D, 2A/B, 3
37-C01 :
Blinding / Deblinding jobs
Opening of 4 man holes.
Cleaning of column bottom trays 05 Nos.
Removal of coke from column bottom.
Dropping of BPC, cleaning and fixing back
Biox-up of column.
MISCELLANEOUS JOBS :
1.1 6” Sour gas battery limit valve – needs hot job for matching flange
1.2 3 Nos 6” B/L Gate valves on Fuel Gas line revisioning / replacement
1.3 6” Audco valve on FG line
1.4 CW return Battery limit valve to provide
1.5 Isolation valve on 3” CW return line of 37E03
1.6 37-P-4 : Suction B/V passing - to rectify
1.7 Rectification of 2” FG burner line from Audco valve to Individual burners
1.8 Repair of 37- E01 and E08 S/S blow down line to 6” blowdown main header before
NRV.
1.9 BPCV –01 droping for cleaning
1.10 Dechoking / inspection of 6” vertical transfer line from BPCV (Approx 20 M) after
opening flanges.
1.11 2” Slop line de-choking from P9/9R to Column bott.
1.12 De-choking of corrosion injection line upto C1 & C4 and providing break flanges for
ease of online maint.
1.13 ¾” leaky tracing steam line at B/limit pipe rack
1.14 Battery limit FO & FG damaged PG manifold to rectify
1.15 Tracing steam line leak near 37P114A inside Trench
1.16 Utility air line tap off for flue gas sampling redundant lines removal
1.17 Steam leak from tracing steam line of Slop header west side of F1
1.18 37E1D:Tube side I/l bleeder valve damaged wheel missing ( Repair)
1.19 About 750 nos of short and long bolts to be rectified. Point wise check list prepared
CIDW
EXCHANGER:
Maintenance of following exchangers
84-E-15, 16, 17, LO and SO coolers of 84-K-01A/B AND 84-K-02A/B
84-C01
Opening of top cover (dia 760mm) and removal of top dome. (m80x85mm- 24 nos studs). required bolt
tensioner for opening. projected stud length- 58mm, across face – 114mm. (torque 15700 nm)
Box up of the column man hole/hand hole and top coevr after inspection.
1. P 02 A motor to be provided.
2. Aviation warning lights of furnace to be rectified
3. F 01/ F 02/F 03 igniters to be rectified.
4. All fused lamps to be replaced.
5. Lighting arrangement to be done for checking P 14 B gearbox lube oil in night shift.
DHDS BLOCK
FCCU
Cleaning of 18-C-01 column inlet line horizontal portion after opening M/H.
VDU-II
82-F-01
FOB
LOB
TPS
FCCU
Replacement of CO-Stack
Replacement of CO-Duct bellow
Replacement of forged cone of regenerator lift line
Replacement of 18-EA-11 air cooler
Replacement of 18-EA-16 air cooler
HGU
ARU
OFFSITE
FCCU
1 REVISIONING OF MAB & WGC SWAMINA
FCCU
2 MISC S/D MAINT.JOB IN FCCU CITY CONSTRUCTION
FCCU
CHK-III & CHK-II MAINT OF HEAT EXCHANGER/AIR FIN
3 R M WORKS
COOLERS
FCCU
HIRING OF EXPERT FOR MAINT.OF SLIDE VALVES AT
4 Z&J
FCCU
FCCU
5 HIRING OF EXPERT FOR MAINT.OF MAB & WGC BHEL
FCCU
6 REPLACEMENT OF 96" DIA FCCU BELLOW ZENITH
FCCU
7 BLINDING / DEBLINDING OF VAPOUR LINE BAPAN ENTERPRISES
FCCU
DE-CHOKING OF AERATION POINTS OF 18-R-01 BY
8 THE TECHNIC
DRILLING
FCCU
9 FIELD SERVICE FOR DRY GAS SEAL 18-K-10 BURGMANN
HGU
10 ARU MISC.S/D MAIMT.JOB IN HGU & ARU
HGU
11 ARU MISC MAINT OF COLUMN/VESSEL/FURNACE/REACTOR
HGU
CHK-III & CHK-II MAINT OF HEAT EXCHANGER/AIR FIN
12 ARU ROYAL CONSTRUCTION CO
COOLERS
DHDS
DHDS
13 OVERHAULING OF 25-K-01A/B
HGU
14 REPLACEMENT OF CAT.TUBE & MISC.S/D JOB OF 24-F-02 AMAR 3ENGG
HGU
15 MISC.HOT JOB AT DHDS FOR HGU
SHU (U-
16 87) SKIMING OF CATALYST OF 87-R-01 DURING S/D-2007 CONTRACT RESOURCES
HGU
TO & FRO TRANSPORATION OF DRUMS & WOODEN
17 MSQ KALPANA ENTERPRISE
PLATFORMS
FOB
MISC.MAINT.JOBS OF FURNACE & COLUMN AT FOB
18 CITY CONSTRUCTION
DURING S/D-2007
FOB
19 MAINT OF 21-C-01 BAPAN ENTERPRISES
FOB
20 MAINT OF 21-R-01 / 22-R-02 PATRA CONSTRUCTION
FOB
21 MAINT.OF HEAT EXCHANGER OF CDU-I /II & SRU-III
FOB
22 MISC HOT JOB AT GR-10
FOB
23 MISC HOT JOB AT GR-16
FOB
24 MISC PIPING JOB AT GR-20
LOB
25 MAINT.OF HEAT EXCHANGEROF U-32 EXPO GAS CONTAINERS
LOB
26 REP / MAINT OF COLUMNS IN UNIT-32 & UNIT-38 EXPO GAS CONTAINERS
LOB
27 REP / MAINT OF VESSELS & TANKS IN UNIT-32 & UNIT-38 CHABILAL PARUA
LOB
28 REP / MAINT OF FURNACE STACK OF 32-F-01 A R ENGINEERS
LOB
29 REPLC.OF 31-F-01 STACK & DUCT A R ENGINEERS
LOB
30 PDA & NMP RELATED JOBS+TPS HEAT EXCH BHARAT ENGG
LOB
31 MAINT.OF HEAT EXCH OF U-31 / 33 / 34 / 35 / 37 / 84
LOB
COMPLETE RE-TUBING OF HEAT EXCHANGER 38-E-
32
11/12/13/24 AT LOB
LOB
33 MISC HOT JOB FOR LOB
LOB
34 MAINT.OF 37-C-01
LOB
35 MAINT.OF 84-C-01 CONTRACT RESOURCES
FOB LOB
REPLC.OF A/G , U/G C/W LINE & RISER PIPE OF PROCESS
36 TPS
COOLING TOWER DURING S/D-2007
TPS
37 MISC.MAINT.JOB AT TPS DURING S/D-2007
TPS
38 MAINT OF VESSEL IN TPS
O/S
39 REPLACEMENT OF FLARE LINES BHARAT ENGG
O/S
40 REP / REPLC OF SMALL BORE PIPE AT O/S AREA
O/S
41 REP / REPLC OF PIPING (6" TO 24") AT O/S AREA
O/S
42 MAINT.OF VESSEL AT O/S AREA M N MANNA
GT
43 BORESCOPIC INSPECTION OF FRAME-5 BGGT
GT
44 REPAIR OF SPARE OF FRAME-5 OF GT BGGT
GT
REMOVAL,CLEANING & FIXING BACK OF AIR FILTER OF
45 BAPAN ENTERPRISES
GT
GT
46 TROUBLE SHOOTING & STARTING ASSISTANCE FOR GT BGGT
VDU-II
47 REP / MAINT OF 82-F-01
GEN
OUTSOURCING MANPOWER TO SUPERVISE S/D JOBS
48
DURING SEPT-OCT ' 07 AT H/R
GEN
49 HYDROBLAST CLEANING OF EXCHANGER USHA HYDROBLAST
GEN
50 VALVE REVISIONING AMRUTHA
Sub:-
Page 1
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
T F S S M T W T F S S M T W T F S S M T W T F S
1 MAINT OF 11F01 19.5 days Fri 9/21/07 Wed 10/10/07 0%
2 Shutting down of furnace 48 hrs Fri 9/21/07 Sun 9/23/07 0%
3 Gas Test & Man entry 4 hrs Sun 9/23/07 Sun 9/23/07 0%
4 Provision of Scaffolding inside Furnace 36 hrs Sun 9/23/07 Tue 9/25/07 0%
5 Preliminary Inspection of Furnace & Mark 8 hrs Tue 9/25/07 Tue 9/25/07 0%
6 Cleaning of Radiation & Convection Tube 48 hrs Tue 9/25/07 Thu 9/27/07 0%
7 Detailed Inspection of furnace 16 hrs Thu 9/27/07 Fri 9/28/07 0%
8 Cutting & removal of Radiation Tubes (4 24 hrs Tue 9/25/07 Wed 9/26/07 0%
9 Insertion of tubes, Edge Preparation & Fi 24 hrs Tue 9/25/07 Wed 9/26/07 0%
10 Welding of new joints (08 Nos.) 72 hrs Wed 9/26/07 Sat 9/29/07 0%
11 Radiography of welded joints 24 hrs Sat 9/29/07 Sun 9/30/07 0%
12 Stress Releiving of New Joints (08 joints) 36 hrs Sun 9/30/07 Mon 10/1/07 0%
13 Post SR Hardness Checking of Weld join 8 hrs Mon 10/1/07 Tue 10/2/07 0%
14 Post SR Radiography of Welded joints 36 hrs Tue 10/2/07 Wed 10/3/07 0%
15 Spring hanger replacement 48 hrs Tue 9/25/07 Thu 9/27/07 0%
16 Ceramic Fibre Repair at Conv. Section 48 hrs Tue 9/25/07 Thu 9/27/07 0%
17 Hydraulic Pressure Testing of Furnace Co 24 hrs Wed 10/3/07 Thu 10/4/07 0%
18 Removal of scaffolding 24 hrs Thu 10/4/07 Fri 10/5/07 0%
19 Floor Repair / Burner Throat Repair 24 hrs Fri 10/5/07 Sat 10/6/07 0%
20 Final Inspection 4 hrs Sat 10/6/07 Sat 10/6/07 0%
21 Repair / replacement of Skin thermocoup 48 hrs Sun 9/23/07 Tue 9/25/07 0%
22 Revisioning of Damper Plates / Explosion 120 hrs Sun 9/23/07 Fri 9/28/07 0%
23 revisioning of Burner Blocks 120 hrs Fri 9/21/07 Wed 9/26/07 0%
24 Boxing up of Burner Blocks 16 hrs Sat 10/6/07 Sun 10/7/07 0%
25 Final Box up of Manway 8 hrs Sun 10/7/07 Sun 10/7/07 0%
26 Start up activities 72 hrs Sun 10/7/07 Wed 10/10/07 0%
Page 1
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
T F S S M T W T F S S M T W T F S S M T W T F
1 MAINT OF 16-F-01 18.33 days Fri 9/21/07 Tue 10/9/07 0%
2 Shutting down of furnace 48 hrs Fri 9/21/07 Sun 9/23/07 0%
3 Gas Test & Man entry 4 hrs Sun 9/23/07 Sun 9/23/07 0%
4 Provision of Scaffolding inside F 36 hrs Sun 9/23/07 Tue 9/25/07 0%
5 Preliminary Inspection of Furnac 8 hrs Tue 9/25/07 Tue 9/25/07 0%
6 Cleaning of Radiation & Convec 48 hrs Tue 9/25/07 Thu 9/27/07 0%
7 Detailed Inspection of furnace 16 hrs Thu 9/27/07 Fri 9/28/07 0%
8 Cutting & removal of Radiation T 16 hrs Tue 9/25/07 Wed 9/26/07 0%
9 Insertion of tubes, Edge Prepara 24 hrs Tue 9/25/07 Wed 9/26/07 0%
10 Welding of new joints (08 Nos.) 56 hrs Wed 9/26/07 Fri 9/28/07 0%
11 Radiography of welded joints 24 hrs Fri 9/28/07 Sat 9/29/07 0%
12 Stress Releiving of New Joints ( 36 hrs Sat 9/29/07 Mon 10/1/07 0%
13 Post SR Hardness Checking of W 8 hrs Mon 10/1/07 Mon 10/1/07 0%
14 Post SR Radiography of Welded 24 hrs Mon 10/1/07 Tue 10/2/07 0%
15 Spring hanger replacement 48 hrs Tue 9/25/07 Thu 9/27/07 0%
16 Ceramic Fibre Repair at Conv. 48 hrs Tue 9/25/07 Thu 9/27/07 0%
17 Hydraulic Pressure Testing of Fu 24 hrs Tue 10/2/07 Wed 10/3/07 0%
18 Removal of scaffolding 24 hrs Wed 10/3/07 Thu 10/4/07 0%
19 Floor Repair / Burner Throat Re 24 hrs Thu 10/4/07 Fri 10/5/07 0%
20 Final Inspection 4 hrs Fri 10/5/07 Fri 10/5/07 0%
21 Repair / replacement of Skin the 48 hrs Sun 9/23/07 Tue 9/25/07 0%
22 Revisioning of Damper Plates / 120 hrs Sun 9/23/07 Fri 9/28/07 0%
23 revisioning of Burner Blocks 120 hrs Sun 9/23/07 Fri 9/28/07 0%
24 Boxing up of Burner Blocks 16 hrs Fri 10/5/07 Sat 10/6/07 0%
25 Final Box up of Manway 8 hrs Sat 10/6/07 Sat 10/6/07 0%
26 Start up activities 72 hrs Sat 10/6/07 Tue 10/9/07 0%
Page 1
ID Task Name Duration Start Finish 7 Sep 16, '07 Sep 23, '07 Sep 30, '07 Oct 7, '07 Oct 1
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
1 MAINT OF 32-F-01 29 days Thu 9/13/07 Fri 10/12/07 0%
2 Shutting down of furnace 120 hrs Thu 9/13/07 Tue 9/18/07 0%
3 Gas Test & Man entry 4 hrs Tue 9/18/07 Tue 9/18/07 0%
4 Provision of Scaffolding inside F 24 hrs Tue 9/18/07 Wed 9/19/07 0%
5 Preliminary Inspection of Furnac 8 hrs Wed 9/19/07 Wed 9/19/07 0%
6 Cleaning of Radiation & Convec 48 hrs Sun 9/23/07 Tue 9/25/07 0%
7 Detailed Inspection of furnace 16 hrs Tue 9/25/07 Wed 9/26/07 0%
8 External Scaffolding 24 hrs Tue 9/18/07 Wed 9/19/07 0%
9 Dismantling of stack 72 hrs Wed 9/19/07 Sat 9/22/07 0%
10 Dismantling of refractory 96 hrs Wed 9/19/07 Sun 9/23/07 0%
11 Erection of stack 72 hrs Sat 9/22/07 Tue 9/25/07 0%
12 Marking of damaged casing plat 24 hrs Sun 9/23/07 Mon 9/24/07 0%
13 Cutting of damaged casing plate 48 hrs Mon 9/24/07 Wed 9/26/07 0%
14 Erection of plates 48 hrs Wed 9/26/07 Fri 9/28/07 0%
15 Welding of new casing plates 96 hrs Fri 9/28/07 Tue 10/2/07 0%
16 Surface cleaning 96 hrs Sun 9/23/07 Thu 9/27/07 0%
17 Lug welding 48 hrs Tue 9/25/07 Thu 9/27/07 0%
18 Painting of casing plate 120 hrs Thu 9/27/07 Tue 10/2/07 0%
19 Re lining with new ceramic fibre 96 hrs Sun 9/30/07 Thu 10/4/07 0%
20 Hydraulic Pressure Testing of Fu 24 hrs Thu 9/27/07 Fri 9/28/07 0%
21 Removal of internal scaffolding 16 hrs Thu 10/4/07 Fri 10/5/07 0%
22 Floor Repair / Burner Throat Re 24 hrs Fri 10/5/07 Sat 10/6/07 0%
23 Final Inspection 8 hrs Sat 10/6/07 Sat 10/6/07 0%
24 Repair / replacement of Skin the 48 hrs Sun 9/23/07 Tue 9/25/07 0%
25 Revisioning of Damper Plates / 120 hrs Sun 9/23/07 Fri 9/28/07 0%
26 Repair/Replc. of Explosion door 48 hrs Sun 9/23/07 Tue 9/25/07 0%
27 revisioning of Burner Blocks 120 hrs Sun 9/23/07 Fri 9/28/07 0%
28 Boxing up of Burner Blocks 16 hrs Sat 10/6/07 Sun 10/7/07 0%
29 Final Box up of Manway 8 hrs Sun 10/7/07 Sun 10/7/07 0%
30 Start up activities 120 hrs Sun 10/7/07 Fri 10/12/07 0%
Page 1
M A IN T O F H E A T E X C H A N G E R S & A I R F IN C O O L E R S A T P D A
D U R IN G S /D 0 7
1 30
O p e n in g
2 7 030
3 1 1 1 6 30
B u n d . P u llin g
4 15 4 8 6 030
5 19 7 10 8 1 6 30
H y d r o b la s t in g
6 23 11 13 10 4 8 6 3
7 27 15 17 13 7 10 8 6
8 31 19 21 17 11 13 10 8 In s p e c t io n
9 35 23 25 21 15 17 13 10
10 38 26 29 25 19 21 17 13 In s e rt io n
Days
11 38 29 32 29 23 25 21 17
12 38 32 35 32 26 29 25 21 S h e ll T e s t
13 38 32 38 35 29 32 29 25
14 38 32 38 38 32 35 32 29
Tube Tes t
15 38 32 38 38 32 38 35 32
16 38 32 38 38 32 38 38 35
B o x -U p
17 38 32 38 38 32 42 30 38
M A IN T . O F H E A T E X C H A N G E R S & A IR F IN C O O L E R S A T N M P D U R IN G
S /D 0 7
1 30 O p e n in g
2 7 30
3 11 7 30 B u n d . P u l l in g
4 16 11 7 30
5 21 16 11 7 30
H y d ro b la s t in g
6 26 21 16 11 7 30
7 31 26 21 16 11 7 33
In s p e c t i o n
8 34 31 26 21 16 11 7 7
D ays
9 38 34 31 26 21 16 11 11
In s e r t io n
10 42 38 34 31 26 21 16 16
11 42 38 38 34 31 26 21 21
S h e ll T e s t
12 42 38 42 38 34 31 26 26
13 42 38 42 42 38 34 31 31
Tu b e Te s t
14 42 38 42 42 38 38 34 34
15 42 38 42 42 38 42 38 38
16 42 38 42 42 38 42 42 42 B o x -U p
ID Task Name Duration Start Finish Sep 16, '07 Sep 23, '07 Sep 30, '07 Oct 7, '07 Oct 1
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
1 FCCU DHUTDOWN JOBS SEPT' 2007 632 hrs Sun 9/16/07 Fri 10/12/07 0%
2 REGENERATOR JOBS 632 hrs Sun 9/16/07 Fri 10/12/07 0%
3 SHUTTING DOWN ACTIVITY 68 hrs Sun 9/16/07 Wed 9/19/07 0%
4 GAS TEST & MAN ENTRY 4 hrs Wed 9/19/07 Wed 9/19/07 0%
5 REMOVAL OF REMAINING CATA 16 hrs Wed 9/19/07 Thu 9/20/07 0%
6 ERECTION OF SCAFFOLDING 24 hrs Wed 9/19/07 Thu 9/20/07 0%
7 OPENING OF CYCLONE MANWA 48 hrs Wed 9/19/07 Fri 9/21/07 0%
8 PROVISION OF ROPE LADDER IN 8 hrs Sun 9/23/07 Mon 9/24/07 0%
9 GENERAL CLEANING OF REGEN 72 hrs Thu 9/20/07 Sun 9/23/07 0%
10 GENERAL INSPECTION OF REGE 120 hrs Sun 9/23/07 Fri 9/28/07 0%
11 MECH. HOT JOB & REFRACTORY 72 hrs Fri 9/28/07 Mon 10/1/07 0%
12 REPAIR / REPLACEMENT OF NO 48 hrs Fri 9/28/07 Sun 9/30/07 0%
13 SUPPORTING OF LIFT PIPE USIN 24 hrs Thu 9/20/07 Fri 9/21/07 0%
14 REMOVAL OF TIE RODS AT THE 24 hrs Fri 9/21/07 Sat 9/22/07 0%
15 CUTTING OF MANWAY OPENING 16 hrs Fri 9/21/07 Sat 9/22/07 0%
16 MAKING CAGE ARRANGEMENT 8 hrs Sat 9/22/07 Sat 9/22/07 0%
17 INSPECTION OF LIFT LINE 8 hrs Sat 9/22/07 Sun 9/23/07 0%
18 MARKING OF LENGTH OF LIFT P 8 hrs Fri 9/21/07 Sat 9/22/07 0%
19 CHIPPING OF REFRACTORY AT 24 hrs Sat 9/22/07 Sun 9/23/07 0%
20 HOLDING OF CATALYST DISTRIB 16 hrs Fri 9/21/07 Sat 9/22/07 0%
21 CUTTING OF 3 NOS. POCKETS A 16 hrs Fri 9/21/07 Sat 9/22/07 0%
22 REMOVAL OF 4 NOS. CLEATS AN 16 hrs Sat 9/22/07 Sun 9/23/07 0%
23 CUTTING OF LIFT PIPE (J-1) BY G 8 hrs Sun 9/23/07 Sun 9/23/07 0%
24 CUTTING OF LIFT PIPE (J-2) BY G 8 hrs Sun 9/23/07 Sun 9/23/07 0%
25 LOWERING DOWN & REMOVAL O 8 hrs Sun 9/23/07 Mon 9/24/07 0%
26 CUTTING OF LIFT PIPE (J-4) BY G 16 hrs Mon 9/24/07 Mon 9/24/07 0%
27 CUTTING OF LIFT PIPE (J-3) BY G 16 hrs Mon 9/24/07 Tue 9/25/07 0%
28 LOWERING DOWN & REMOVAL O 8 hrs Tue 9/25/07 Tue 9/25/07 0%
29 LIFTING OF RISER CATALYST DI 16 hrs Tue 9/25/07 Tue 9/25/07 0%
30 REPAIR OF HEXMESH AND RESC 24 hrs Tue 9/25/07 Wed 9/26/07 0%
31 EDGE PREPARATION AND DP O 16 hrs Tue 9/25/07 Wed 9/26/07 0%
32 ERECTION AND FIT-UP OF J3 16 hrs Wed 9/26/07 Wed 9/26/07 0%
Page 1
ID Task Name Duration Start Finish Sep 16, '07 Sep 23, '07 Sep 30, '07 Oct 7, '07 Oct 1
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
33 WELDING OF J3 WITH STAGE W 16 hrs Wed 9/26/07 Thu 9/27/07 0%
34 LOWERING OF BOTH THE PIECE 8 hrs Thu 9/27/07 Thu 9/27/07 0%
35 ERECTION AND FIT-UP OF J4 32 hrs Thu 9/27/07 Sat 9/29/07 0%
36 WELDING OF J3 & J4 WITH STAG 32 hrs Sat 9/29/07 Sun 9/30/07 0%
37 LIFTING OF RISER PIPE 8 hrs Sun 9/30/07 Sun 9/30/07 0%
38 ALIGNMENT AND FIT UP OF J2, J 16 hrs Sun 9/30/07 Mon 10/1/07 0%
39 WELDING OF J2, J5 & VERTICAL 24 hrs Mon 10/1/07 Tue 10/2/07 0%
40 RADIOGRAPHY INSIDE REGENE 16 hrs Tue 10/2/07 Wed 10/3/07 0%
41 RESCO LINING & CURING OF BA 24 hrs Wed 10/3/07 Thu 10/4/07 0%
42 REMOVAL OF CAGE FROM LIFT 8 hrs Wed 10/3/07 Thu 10/4/07 0%
43 WELDING OF MANWAY OPENING 16 hrs Thu 10/4/07 Thu 10/4/07 0%
44 FILLING OF CEREMIC BLANKET 24 hrs Wed 10/3/07 Thu 10/4/07 0%
45 APPLICATION OF REFRACTORY 16 hrs Wed 10/3/07 Wed 10/3/07 0%
46 WELDING OF 4 NOS. CLEAT ON 16 hrs Wed 10/3/07 Wed 10/3/07 0%
47 CLOSING OF 3 NOS. POCKET & N 16 hrs Wed 10/3/07 Thu 10/4/07 0%
48 FITTING OF LIFT LINE TURN BUC 16 hrs Wed 10/3/07 Thu 10/4/07 0%
49 REMOVAL OF LIFTING LUGS IN R 16 hrs Thu 10/4/07 Fri 10/5/07 0%
50 FITTING OF ALL CONNECTING P 16 hrs Thu 10/4/07 Fri 10/5/07 0%
51 WELDING OF ALL CONNECTING 16 hrs Thu 10/4/07 Fri 10/5/07 0%
52 REVISIONING OF PLUG VALVE O 72 hrs Thu 9/20/07 Sun 9/23/07 0%
53 FINAL CHECKING OF PLUG VALV 8 hrs Fri 10/5/07 Fri 10/5/07 0%
54 REMOVAL OF SCAFFOLDING FR 16 hrs Fri 10/5/07 Sat 10/6/07 0%
55 FINAL CLEANING 8 hrs Sat 10/6/07 Sat 10/6/07 0%
56 FINAL INSPECTION BY PS, PN, IN 8 hrs Sat 10/6/07 Sun 10/7/07 0%
57 BOX UP OF REGENERATOR & CY 24 hrs Sun 10/7/07 Mon 10/8/07 0%
58 DEBLINDING 24 hrs Sun 10/7/07 Mon 10/8/07 0%
59 START UP ACTIVITY 96 hrs Mon 10/8/07 Fri 10/12/07 0%
60 REACTOR JOBS 632 hrs Sun 9/16/07 Fri 10/12/07 0%
61 SHUTTING DOWN ACTIVITY 68 hrs Sun 9/16/07 Wed 9/19/07 0%
62 GAS TEST & MAN ENTRY 4 hrs Wed 9/19/07 Wed 9/19/07 0%
63 OPENING OF CYCLONE MANWA 48 hrs Wed 9/19/07 Fri 9/21/07 0%
64 OPENING / CUTTING OF RISER M 48 hrs Wed 9/19/07 Fri 9/21/07 0%
Page 2
ID Task Name Duration Start Finish Sep 16, '07 Sep 23, '07 Sep 30, '07 Oct 7, '07 Oct 1
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
65 PROVISION OF INSPECTION CAG 8 hrs Fri 9/21/07 Fri 9/21/07 0%
66 PROVISION OF ROPE LADDERS 8 hrs Fri 9/21/07 Fri 9/21/07 0%
67 REMOVAL OF REMAINING CATA 16 hrs Wed 9/19/07 Thu 9/20/07 0%
68 ERECTION OF SCAFFOLDING IN 72 hrs Thu 9/20/07 Sun 9/23/07 0%
69 GENERAL CLEANING OF REACT 48 hrs Sun 9/23/07 Tue 9/25/07 0%
70 GENERAL INSPECTION OF REAC 24 hrs Tue 9/25/07 Wed 9/26/07 0%
71 MECH. HOT JOB & REFRACTORY 168 hrs Wed 9/26/07 Wed 10/3/07 0%
72 REPAIR / REPLACEMENT OF NO 120 hrs Wed 9/26/07 Mon 10/1/07 0%
73 INSPECTION OF RISER & CYCLO 48 hrs Fri 9/21/07 Sun 9/23/07 0%
74 REPAIR JOBS IN RISER & CYCLO 96 hrs Sun 9/23/07 Thu 9/27/07 0%
75 DECHOKING OF HCO NOZZLES 120 hrs Wed 9/26/07 Mon 10/1/07 0%
76 REPLACEMENT OF VB NAPHTHA 48 hrs Wed 9/26/07 Fri 9/28/07 0%
77 REPAIR OF LDD TUBES, IF REQU 48 hrs Wed 9/26/07 Fri 9/28/07 0%
78 MECHANICAL & REFRACTORY J 96 hrs Wed 9/26/07 Sun 9/30/07 0%
79 FINAL INSPECTION OF RISER & 8 hrs Thu 9/27/07 Thu 9/27/07 0%
80 REMOVAL OF CAGE FROM RISE 24 hrs Thu 9/27/07 Fri 9/28/07 0%
81 REMOVAL OF SCAFFOLDING FR 16 hrs Wed 10/3/07 Wed 10/3/07 0%
82 FINAL CLEANING 8 hrs Wed 10/3/07 Thu 10/4/07 0%
83 FINAL INSPECTION BY PS, PN, IN 8 hrs Thu 10/4/07 Thu 10/4/07 0%
84 WELDING OF RISER MANHOLES 24 hrs Thu 10/4/07 Fri 10/5/07 0%
85 BOX UP OF REACTOR AND CYC 24 hrs Thu 10/4/07 Fri 10/5/07 0%
86 DEBLINDING 24 hrs Sun 10/7/07 Mon 10/8/07 0%
87 START UP ACTIVITY 96 hrs Mon 10/8/07 Fri 10/12/07 0%
88 ORIFICE CHAMBER JOBS 632 hrs Sun 9/16/07 Fri 10/12/07 0%
89 SHUTTING DOWN ACTIVITY 68 hrs Sun 9/16/07 Wed 9/19/07 0%
90 GAS TEST & MAN ENTRY 4 hrs Wed 9/19/07 Wed 9/19/07 0%
91 REMOVAL OF REMAINING CATA 8 hrs Wed 9/19/07 Wed 9/19/07 0%
92 CUTTING OF GRID MANWAYS 120 hrs Wed 9/19/07 Mon 9/24/07 0%
93 PROVISION OF ROPE LADDER F 8 hrs Mon 9/24/07 Tue 9/25/07 0%
94 GENERAL CLEANING OF ORIFIC 16 hrs Tue 9/25/07 Tue 9/25/07 0%
95 INSPECTION OF ORIFICE CHAMB 16 hrs Tue 9/25/07 Wed 9/26/07 0%
96 MECH. HOT JOB & REFRACTORY 72 hrs Wed 9/26/07 Sat 9/29/07 0%
Page 3
ID Task Name Duration Start Finish Sep 16, '07 Sep 23, '07 Sep 30, '07 Oct 7, '07 Oct 1
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
97 FINAL INSPECTION OF ORIFICE 16 hrs Sat 9/29/07 Sun 9/30/07 0%
98 WELDING OF GRID MANWAYS 96 hrs Sun 9/30/07 Thu 10/4/07 0%
99 BOX UP OF ORIFICE CHAMBER M 24 hrs Thu 10/4/07 Fri 10/5/07 0%
100 DEBLINDING 24 hrs Sun 10/7/07 Mon 10/8/07 0%
101 START UP ACTIVITY 96 hrs Mon 10/8/07 Fri 10/12/07 0%
102 CO-BOILER JOBS 632 hrs Sun 9/16/07 Fri 10/12/07 0%
103 SHUTTING DOWN ACTIVITY 68 hrs Sun 9/16/07 Wed 9/19/07 0%
104 GAS TEST & MAN ENTRY 4 hrs Wed 9/19/07 Wed 9/19/07 0%
105 REMOVAL OF REMAINING CATA 48 hrs Wed 9/19/07 Fri 9/21/07 0%
106 ERECTION OF INTERNAL SCAFF 24 hrs Thu 9/20/07 Fri 9/21/07 0%
107 OPENING AND CLEANING OF ST 72 hrs Wed 9/19/07 Sat 9/22/07 0%
108 CLEANING OF CO-BOILER TUBE 72 hrs Fri 9/21/07 Mon 9/24/07 0%
109 DRY INSPECTION OF COB 16 hrs Mon 9/24/07 Tue 9/25/07 0%
110 REPLACEMENT OF 03 NOS. SCR 48 hrs Tue 9/25/07 Thu 9/27/07 0%
111 REPLACEMENT OF 29 NOS. BAN 120 hrs Tue 9/25/07 Sun 9/30/07 0%
112 REPLACEMENT OF 01 NO SUPER 48 hrs Tue 9/25/07 Thu 9/27/07 0%
113 REPLACEMENT OF LEAKEY DRA 24 hrs Tue 9/25/07 Wed 9/26/07 0%
114 REPLACEMENT OF M/H COVER 24 hrs Tue 9/25/07 Wed 9/26/07 0%
115 BOX-UP OF STEAM DRUMS 16 hrs Sun 9/30/07 Sun 9/30/07 0%
116 INTERNAL HYDROTESTION 24 hrs Sun 9/30/07 Mon 10/1/07 0%
117 HYDROTESTING BY IBR 24 hrs Mon 10/1/07 Tue 10/2/07 0%
118 REMOVAL OF SCAFFOLDING 12 hrs Tue 10/2/07 Wed 10/3/07 0%
119 FINAL INSPECTION OF COB BY P 8 hrs Wed 10/3/07 Wed 10/3/07 0%
120 BOX UP OF COB MANHOLES 16 hrs Wed 10/3/07 Thu 10/4/07 0%
121 DEBLINDING 24 hrs Sun 10/7/07 Mon 10/8/07 0%
122 START UP ACTIVITY 96 hrs Mon 10/8/07 Fri 10/12/07 0%
Page 4
M A IN T . O F A IR F IN C O O L E R S A T F C C U D U R IN G S / D 0 7
1 10
O p e n i n g o f c o ve r s
2 3 10
H y d ro b la s t C le a n in g
3 5 3 1 10
In d i vi d u a l T u b e
T e s t in g
4 7 5 3 3 10
In s p e c t i o n
5 9 7 5 5 3 10 C o ve r B o x u p
6 11 9 7 7 5 3 1 H y d ro t e s t in g
Days
7 13 11 9 9 7 5 3 F in a l b o x u p
8 15 13 11 11 9 7 5
9 15 15 13 13 11 9 7
10 15 15 15 15 13 11 9
11 15 15 15 15 15 13 11
12 15 15 15 15 15 15 13
13 15 15 15 15 15 15 15
ID Task Name Duration Start Finish ep 17 Fri Sep 21 Tue Sep 25
3 12 9 6 3
1 CATALYST TUBE REPLACEMENT JOB 20 days Fri 9/21/07 Thu 10/11/07
2 SHUTTING DOWN/ STEAMING/ BLINDI 72 hrs Fri 9/21/07 Mon 9/24/07 0%
3 GAS TEST AND MANENTRY 4 hrs Mon 9/24/07 Mon 9/24/07 0%
4 ERECTION OF SCAFFOLDING 24 hrs Mon 9/24/07 Tue 9/25/07 0%
5 OPENING COLD COLT M/H 16 hrs Mon 9/24/07 Tue 9/25/07 0%
6 OPENING OF CATALYST TUBE - 60 No 24 hrs Mon 9/24/07 Tue 9/25/07 0%
7 UNLOADING OF CATALYST - 60 Nos. 72 hrs Tue 9/25/07 Fri 9/28/07
8 REMOVAL OF ROOF CORROGATED S 24 hrs Mon 9/24/07 Tue 9/25/07 0%
9 LOCKING OF PIG TAIL TUBE SPRINGS 16 hrs Mon 9/24/07 Tue 9/25/07 0%
10 REMOVAL OF PIG TAIL INSULATION 8 hrs Mon 9/24/07 Mon 9/24/07 0%
11 LOCKING CAT TUBE SPRING 16 hrs Mon 9/24/07 Tue 9/25/07 0%
12 DISMANTLING AND REMOVAL OF SPR 8 hrs Tue 9/25/07 Tue 9/25/07 0%
13 DISMANTLING AND REMOVAL OF SPR 8 hrs Tue 9/25/07 Tue 9/25/07 0%
14 CUTTING OF CATALYST TUBE - 35 JO 48 hrs Tue 9/25/07 Thu 9/27/07
15 CUTTING OF FURNACE ROOF & BOTT 48 hrs Tue 9/25/07 Thu 9/27/07
16 REMOVAL OF REFRACTORY MATERIA 48 hrs Tue 9/25/07 Thu 9/27/07
17 CUTTING OF PIG TAIL BY GRINDING - 24 hrs Mon 9/24/07 Tue 9/25/07 0%
18 LIFTING OF PIPE FROM TOP 48 hrs Wed 9/26/07 Fri 9/28/07
19 EDGE PREPARATOION AND DP TEST 48 hrs Thu 9/27/07 Sat 9/29/07
20 ERECTION OF NEW PIPE 96 hrs Thu 9/27/07 Mon 10/1/07
21 ALIGNMENT AND FIT UP OF CATALYS 96 hrs Fri 9/28/07 Tue 10/2/07
22 RADIOGRAPHY OF JOINTS 96 hrs Sat 9/29/07 Wed 10/3/07
23 WELDING OF JOINTS -35 Nos. 120 hrs Sun 9/30/07 Fri 10/5/07
24 RADIOGRAPHY OF JOINTS 72 hrs Wed 10/3/07 Sat 10/6/07
25 FIXING OF FURNACE ROOF & BOTTOM 24 hrs Tue 10/2/07 Wed 10/3/07
26 FIXING OF REFRACTORY MATERIAL A 48 hrs Wed 10/3/07 Fri 10/5/07
27 FIXING OF SPRING SUPPORT BEAM 48 hrs Tue 10/2/07 Thu 10/4/07
28 FIXING OF SPRING 48 hrs Wed 10/3/07 Fri 10/5/07
29 EDGE PREPARATOION AND DP TEST 48 hrs Thu 9/27/07 Sat 9/29/07
30 ALIGNMENT AND FIT UP OF PIG TAIL T 96 hrs Fri 9/28/07 Tue 10/2/07
31 WELDING OF PIG TAIL TUBES 48 hrs Sun 9/30/07 Tue 10/2/07
32 DP & RADIOGRAPHY OF PIG TAIL JOIN 16 hrs Tue 10/2/07 Wed 10/3/07
Page 1
ID Task Name Duration Start Finish ep 17 Fri Sep 21 Tue Sep 25
3 12 9 6 3
33 PROVIDING INSULATION ON PIG TAIL 24 hrs Wed 10/3/07 Thu 10/4/07
34 UNLOCKING OF PIG TAIL TUBES 24 hrs Thu 10/4/07 Fri 10/5/07
35 LOADING OF CATALYST 48 hrs Thu 10/4/07 Sat 10/6/07
36 INSPECTION OF FURNACE & TUBES 72 hrs Tue 9/25/07 Fri 9/28/07
37 REVISIONING OF BURNERS / DAMPER 96 hrs Tue 9/25/07 Sat 9/29/07
38 REVISIONING OF VALVES 96 hrs Tue 9/25/07 Sat 9/29/07
39 BOX-UP OF CATALYST TUBES 48 hrs Fri 10/5/07 Sun 10/7/07
40 BOX-UP OF COLD COLLECTOR 48 hrs Fri 10/5/07 Sun 10/7/07
41 REMOVAL OF SCAFFOLDING 12 hrs Sat 10/6/07 Sun 10/7/07
42 FURNACE FLOOR REPAIR 12 hrs Sun 10/7/07 Sun 10/7/07
43 BOX-UP OF FURNACE 8 hrs Sun 10/7/07 Mon 10/8/07
44 DEBLINDING ACTIVITIES 8 hrs Mon 10/8/07 Mon 10/8/07
45 START UP ACTIVITIES. 72 hrs Mon 10/8/07 Thu 10/11/07
Page 2
ue Sep 25 Sat Sep 29 Wed Oct 3 Sun Oct 7 Thu Oct 11 Mon O
3 12 9 6 3 12 9 6 3 12 9
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Page 3
ue Sep 25 Sat Sep 29 Wed Oct 3 Sun Oct 7 Thu Oct 11 Mon O
3 12 9 6 3 12 9 6 3 12 9
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Page 4
M A IN T O F H .E . & A IR F IN C O O L E R S A T H G U D U R IN G S /D 0 7
1 30
O p e n in g
2 8 30
3 13 8 30 B u n d . P u llin g
4 18 13 8 3 30
H y d ro b la s t in g
5 23 18 13 8 8 30
6 29 23 18 13 13 9 33
In s p e c t io n
Days
7 35 29 23 18 18 15 9 3
In s e rt io n
8 41 38 29 23 23 23 15 9
9 41 38 35 35 29 30 23 15
S h e ll T e s t
10 41 38 41 41 35 36 30 23
11 41 38 41 41 38 41 36 30 Tube Tes t
12 41 38 41 41 38 41 41 36
B o x -U p
13 41 38 41 41 38 41 41 41
ID Task Name Duration Start Finish Sep 16, '07 Sep 23, '07 Sep 30, '07
T F S S M T W T F S S M T W T F S S M T
1
2 DHDS AIR FIN COOLERS 16 days Fri 9/14/07 Sun 9/30/07 0%
3 BLIBDING 24 hrs Fri 9/14/07 Sat 9/15/07 0%
4 OPENING OF PLUGS - 3264 Nos. 192 hrs Sat 9/15/07 Sun 9/23/07 0%
5 HYDROBLAST CLEANING 192 hrs Sun 9/16/07 Mon 9/24/07 0%
6 DRYING OF TUBES 192 hrs Mon 9/17/07 Tue 9/25/07 0%
7 INSPECTION BY IRIS TECHNIQUE 192 hrs Tue 9/18/07 Wed 9/26/07 0%
8 BOXUP OF PLUGS 192 hrs Wed 9/19/07 Thu 9/27/07 0%
9 HYDROTESTING OF BUNDLES 192 hrs Fri 9/21/07 Sat 9/29/07 0%
10 DEBLING 24 hrs Sat 9/29/07 Sun 9/30/07 0%
Page 1
M A IN T . O F H .E . & A IR F IN C O O L E R S A T A R U D U R IN G S /D 0 7
1 10
O p e n in g
2 3 10 B u n d . P u llin g
H y d ro b la s t in g
3 5 3 10
In s p e c t i o n
4 7 5 3 1 10 In s e r t i o n
S h e ll T e s t
5 8 7 5 3 3 10
Tube Tes t
Days
B o x -U p
6 8 8 7 5 5 3 10
7 8 8 8 7 7 5 3 2
8 8 8 8 8 8 7 5 4
9 8 8 8 8 8 8 7 6
10 8 8 8 8 8 8 8 8
M A IN T . O F H E A T E X C H A N G E R S A T F C C U D U R IN G S /D 0 7
1 40
8 030 O p e n in g
3 1 3 1 7 30
1 8 4 9 7030 B u n d . P u llin g
5 23 7 1 1 9 07 33
28 1 1 1 4 1 11 9 7 7
H y d ro b la s t in g
7 33 16 18 14 411 9 9
38 21 23 18 7 14 11 11
9 43 26 28 23 11 18 14 14 In s p e c t io n
Days
48 31 33 28 16 23 18 18
11 53 36 38 33 21 28 23 23 In s e rt io n
56 41 43 38 26 33 28 28
13 59 46 48 43 31 38 33 33
S h e ll T e s t
59 51 53 48 36 43 38 38
15 59 51 59 53 41 48 43 43
59 51 59 59 46 53 48 48 Tube Tes t
17 59 51 59 59 51 56 53 53
59 51 59 59 51 59 56 56 B o x -U p
19 59 51 59 59 51 59 59 59
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
S M T W T F S S M T W T F S S M
1 VALVE REPLACEMENT JOBS 12.33 days Mon 9/24/07 Sat 10/6/07 0%
2 STEAM VALVE - 600 Inch Dia 12 days Mon 9/24/07 Sat 10/6/07 0%
3 BLINDING OF CIRCUITS FOR HOT J 16 hrs Mon 9/24/07 Tue 9/25/07 0%
4 CUTTING OF JOINTS-600 IN.DIA 48 hrs Tue 9/25/07 Thu 9/27/07 0%
5 REMOVAL OF OLD VALVES 48 hrs Tue 9/25/07 Thu 9/27/07 0%
6 EDGE PREPARATION OF OLD PIPE 36 hrs Tue 9/25/07 Thu 9/27/07 0%
7 DP TESTING OF OLD PIPE 36 hrs Wed 9/26/07 Thu 9/27/07 0%
8 ERECTION OF NEW VALVES 72 hrs Thu 9/27/07 Sun 9/30/07 0%
9 WELDING OF JOINTS-600 IN.DIA 96 hrs Fri 9/28/07 Tue 10/2/07 0%
10 NDT OF JOINTS 96 hrs Sat 9/29/07 Wed 10/3/07 0%
11 SR OF JOINTS-600 IN.DIA 96 hrs Sun 9/30/07 Thu 10/4/07 0%
12 RADIOGRAPHY OF JOINTS 96 hrs Sun 9/30/07 Thu 10/4/07 0%
13 HYDROTESTING OF LINES 24 hrs Thu 10/4/07 Fri 10/5/07 0%
14 DEBLINDING OF CIRCUITS 16 hrs Fri 10/5/07 Sat 10/6/07 0%
15 CW VALVE - 700 Inch Dia 12.33 days Mon 9/24/07 Sat 10/6/07 0%
16 BLINDING OF CIRCUITS FOR HOT J 16 hrs Mon 9/24/07 Tue 9/25/07 0%
17 CUTTING OF JOINTS-700 IN.DIA 72 hrs Tue 9/25/07 Fri 9/28/07 0%
18 REMOVAL OF OLD VALVES 72 hrs Tue 9/25/07 Fri 9/28/07 0%
19 EDGE PREPARATION OF OLD PIPE 36 hrs Wed 9/26/07 Thu 9/27/07 0%
20 DP TESTING OF OLD PIPE 36 hrs Thu 9/27/07 Fri 9/28/07 0%
21 ERECTION OF NEW VALVES 72 hrs Fri 9/28/07 Mon 10/1/07 0%
22 WELDING OF JOINTS-700 IN.DIA 120 hrs Sat 9/29/07 Thu 10/4/07 0%
23 NDT OF JOINTS 120 hrs Sun 9/30/07 Fri 10/5/07 0%
24 HYDROTESTING OF LINES 24 hrs Fri 10/5/07 Sat 10/6/07 0%
25 DEBLINDING OF CIRCUITS 16 hrs Sat 10/6/07 Sat 10/6/07 0%
Page 1
H E A T E X C H A N G E R M A IN T . A T T P S D U R IN G S /D 0 7
1 10
O p e n in g
2 3 10 B u n d . P u llin g
H y d r o b la s t in g
3 5 3 10
In s p e c t io n
4 7 5 3 1 10 In s e r t io n
S h e ll T e s t
5 8 7 5 3 3 10
Tube Tes t
B o x -U p
6 8 8 7 5 5 3 10
Days
7 8 8 8 7 7 5 3 2
8 8 8 8 8 8 7 5 4
9 8 8 8 8 8 8 7 6
10 8 8 8 8 8 8 8 8
SHUTDOWN ACTIVITIES IN COOLING TOWER
CHECKING OF STRUCTURES 24
PARTITIONING OF CELLS
SHUTTERING 168
CONCRETING 168
Page 1
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07
S M T W T F S S M T W
1 HRSG JOBS 7.17 days Mon 9/24/07 Mon 10/1/07 0%
2 Opening of manhole of HR 16 hrs Mon 9/24/07 Tue 9/25/07 0%
3 Opening of manhole of ste 16 hrs Mon 9/24/07 Tue 9/25/07 0%
4 Removal of drum internals 24 hrs Tue 9/25/07 Wed 9/26/07 0%
5 Cleaning of vessel 24 hrs Wed 9/26/07 Thu 9/27/07 0%
6 Boxup of drum internals 24 hrs Thu 9/27/07 Fri 9/28/07 0%
7 Box up of steam drum mna 16 hrs Fri 9/28/07 Fri 9/28/07 0%
8 Erection of scaffolding 36 hrs Tue 9/25/07 Wed 9/26/07 0%
9 Cleaning of tubes 24 hrs Wed 9/26/07 Thu 9/27/07 0%
10 Internal Inspection 16 hrs Thu 9/27/07 Fri 9/28/07 0%
11 Dry Inspection by IBR 24 hrs Fri 9/28/07 Sat 9/29/07 0%
12 Internal Hydraulic Testing 16 hrs Sat 9/29/07 Sat 9/29/07 0%
13 Hydraulic Testing by IBR 24 hrs Sat 9/29/07 Sun 9/30/07 0%
14 Box up of HRSG 16 hrs Sun 9/30/07 Mon 10/1/07 0%
Page 1
ID Task Name Duration Start Finish Jun 17, '07 Jun 24, '07 Jul 1, '07 Jul 8, '07 Jul 15, '07 Jul 22, '07 Jul 29, '07 Aug 5, '07 Aug 12, '07 Aug 19, '07 Aug 26, '07 Sep 2, '07 Sep 9, '07 Sep 16, '07 Sep 23, '07 Sep 30, '07 Oct 7, '07
SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S
1 FLARE JOBS 2688 hrs Mon 6/18/07 Mon 10/8/07 0%
2 FLARE LINE REPLACEMENT 2688 hrs Mon 6/18/07 Mon 10/8/07 0%
3 Flare line Pre-Shutdown 1992 hrs Mon 6/18/07 Sun 9/9/07 0%
4 Pilling for supports alo 1464 hrs Mon 6/18/07 Sat 8/18/07 0%
5 Foundation for suppo 1392 hrs Tue 7/3/07 Thu 8/30/07 0%
6 Structural fabrication 720 hrs Wed 8/1/07 Fri 8/31/07 0%
7 Sand blasting & Paint 720 hrs Wed 8/8/07 Fri 9/7/07 0%
8 Erection and alignme 480 hrs Mon 8/20/07 Sun 9/9/07 0%
9 Flare line Pre-Shutdown 1104 hrs Mon 8/6/07 Fri 9/21/07 0%
10 Pre-Fabrication of all 720 hrs Mon 8/6/07 Wed 9/5/07 0%
11 Sand blasting & Paint 720 hrs Fri 8/10/07 Sun 9/9/07 0%
12 Transportation of pipe 480 hrs Wed 8/22/07 Tue 9/11/07 0%
13 Erection of pipe on st 72 hrs Sun 9/9/07 Wed 9/12/07 0%
14 Joint fit up and Weldi 168 hrs Wed 9/12/07 Wed 9/19/07 0%
15 NDT of all Joints as p 120 hrs Sun 9/16/07 Fri 9/21/07 0%
16 Flare line Shutdown Job 336 hrs Mon 9/24/07 Mon 10/8/07 0%
17 Blinding / Deblinding 72 hrs Mon 9/24/07 Thu 9/27/07 0%
18 Cutting of all old lines 72 hrs Thu 9/27/07 Sun 9/30/07 0%
19 Dismantling of pipes 72 hrs Fri 9/28/07 Mon 10/1/07 0%
20 Welding of hook up jo 48 hrs Mon 10/1/07 Wed 10/3/07 0%
21 Cutting of damaged s 48 hrs Sat 9/29/07 Mon 10/1/07 0%
22 Repair of support loca 48 hrs Sun 9/30/07 Tue 10/2/07 0%
23 Bevelling of old lines 48 hrs Fri 9/28/07 Sun 9/30/07 0%
24 Erection of pipes alon 48 hrs Mon 10/1/07 Wed 10/3/07 0%
25 Joint fit-up and weldin 72 hrs Tue 10/2/07 Fri 10/5/07 0%
26 Radiography of balan 48 hrs Thu 10/4/07 Sat 10/6/07 0%
27 Blinding / Deblinding 48 hrs Fri 10/5/07 Sun 10/7/07 0%
28 Start-up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
29 Flare tip replacement job 336 hrs Mon 9/24/07 Mon 10/8/07 0%
30 Shutting down / Blinding/ D 72 hrs Mon 9/24/07 Thu 9/27/07 0%
31 Revisioning of Devit and m 16 hrs Thu 9/27/07 Fri 9/28/07 0%
32 Lifting of scaffolding mater 24 hrs Fri 9/28/07 Sat 9/29/07 0%
33 Erection of scaffoldign out 16 hrs Fri 9/28/07 Sat 9/29/07 0%
34 Dismantling of Acid flare ti 8 hrs Thu 9/27/07 Thu 9/27/07 0%
35 Dismantling of Hydrocarbo 16 hrs Thu 9/27/07 Fri 9/28/07 0%
36 Cutting of Acid flare tip 8 hrs Thu 9/27/07 Fri 9/28/07 0%
37 Lowering of Acid flare tip 8 hrs Sat 9/29/07 Sun 9/30/07 0%
38 Grinding & edge preparati 8 hrs Fri 9/28/07 Fri 9/28/07 0%
39 Erection of Acid flare tip to 8 hrs Sun 9/30/07 Sun 9/30/07 0%
40 Fit up & welding of Acid fla 8 hrs Sun 9/30/07 Sun 9/30/07 0%
41 Lowering of Hydrocarbon f 16 hrs Sun 9/30/07 Mon 10/1/07 0%
42 Erection of Hydrocarbon fl 16 hrs Mon 10/1/07 Tue 10/2/07 0%
43 Alignment & boxup of Hyd 16 hrs Tue 10/2/07 Tue 10/2/07 0%
44 Erection of scaffolding insi 16 hrs Tue 10/2/07 Wed 10/3/07 0%
45 Lifting of other accessories 16 hrs Tue 10/2/07 Wed 10/3/07 0%
46 Revisioning of Burners & F 24 hrs Fri 9/28/07 Sat 9/29/07 0%
47 Fitting and welding of all a 16 hrs Wed 10/3/07 Wed 10/3/07 0%
48 Box-up of all connected lin 16 hrs Wed 10/3/07 Thu 10/4/07 0%
49 Dismantlingl of scaffolding 16 hrs Thu 10/4/07 Fri 10/5/07 0%
50 Lowering down of all scaff 16 hrs Fri 10/5/07 Fri 10/5/07 0%
51 Start-up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
Project: FLARE LINE -2 Critical Split Task Progress Milestone Critical Split Task Progress Milestone
Date: Thu 9/6/07 Critical Progress Baseline Summary Progress Critical Progress Baseline Summary Progress
Task Baseline Split Summary Task Baseline Split Summary
Page 1
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
S M T W T F S S M T W T F S S M T W
1 OFFSITE PIPING 13.83 days Mon 9/24/07 Mon 10/8/07 0%
2 3.1.3: LPG LINES(3", 80M) 13.83 days Mon 9/24/07 Mon 10/8/07 0%
3 Blinding / Deblinding 36 hrs Mon 9/24/07 Tue 9/25/07 0%
4 Steam & Water Washing 24 hrs Tue 9/25/07 Wed 9/26/07 0%
5 Final Blinding 8 hrs Wed 9/26/07 Thu 9/27/07 0%
6 Cold Cutting of pipes 24 hrs Thu 9/27/07 Fri 9/28/07 0%
7 Dismantling of old pipe 16 hrs Fri 9/28/07 Fri 9/28/07 0%
8 Erection of new pipe 24 hrs Fri 9/28/07 Sat 9/29/07 0%
9 Welding of new pipe 72 hrs Sat 9/29/07 Tue 10/2/07 0%
10 NDT 16 hrs Tue 10/2/07 Wed 10/3/07 0%
11 Hydrotest 24 hrs Wed 10/3/07 Thu 10/4/07 0%
12 Draining of water 16 hrs Thu 10/4/07 Fri 10/5/07 0%
13 Deblinding 12 hrs Fri 10/5/07 Fri 10/5/07 0%
14 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
15 3.3.1:NAPTHA LINES(2",24 M) 13.83 days Mon 9/24/07 Mon 10/8/07 0%
16 Blinding / Deblinding 36 hrs Mon 9/24/07 Tue 9/25/07 0%
17 Steam & Water Washing 24 hrs Tue 9/25/07 Wed 9/26/07 0%
18 Final Blinding 8 hrs Wed 9/26/07 Thu 9/27/07 0%
19 Cold Cutting of pipes 12 hrs Thu 9/27/07 Thu 9/27/07 0%
20 Dismantling of old pipe 8 hrs Thu 9/27/07 Fri 9/28/07 0%
21 Erection of new pipe 8 hrs Fri 9/28/07 Fri 9/28/07 0%
22 Welding of new pipe 24 hrs Fri 9/28/07 Sat 9/29/07 0%
23 NDT 12 hrs Sat 9/29/07 Sat 9/29/07 0%
24 Hydrotest 12 hrs Sat 9/29/07 Sun 9/30/07 0%
25 Draining of water 12 hrs Sun 9/30/07 Sun 9/30/07 0%
26 Deblinding 12 hrs Sun 9/30/07 Mon 10/1/07 0%
27 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
28 3.3.2:NAPTHA LINE(3",200 M) 13.83 days Mon 9/24/07 Mon 10/8/07 0%
29 Blinding / Deblinding 36 hrs Mon 9/24/07 Tue 9/25/07 0%
30 Steam & Water Washing 24 hrs Tue 9/25/07 Wed 9/26/07 0%
31 Final Blinding 12 hrs Wed 9/26/07 Thu 9/27/07 0%
32 Cold Cutting of pipes 48 hrs Thu 9/27/07 Sat 9/29/07 0%
Page 1
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
S M T W T F S S M T W T F S S M T W
33 Dismantling of old pipe 32 hrs Fri 9/28/07 Sat 9/29/07 0%
34 Erection of new pipe 48 hrs Sat 9/29/07 Mon 10/1/07 0%
35 Welding of new pipe 96 hrs Sat 9/29/07 Wed 10/3/07 0%
36 NDT 24 hrs Wed 10/3/07 Thu 10/4/07 0%
37 Hydrotest 24 hrs Thu 10/4/07 Fri 10/5/07 0%
38 Draining of water 24 hrs Fri 10/5/07 Sat 10/6/07 0%
39 Deblinding 12 hrs Sat 10/6/07 Sun 10/7/07 0%
40 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
41 3.3.3:NAPTHA LINES(4",60 M) 13.83 days Mon 9/24/07 Mon 10/8/07 0%
42 Blinding / Deblinding 36 hrs Mon 9/24/07 Tue 9/25/07 0%
43 Steam & Water Washing 24 hrs Tue 9/25/07 Wed 9/26/07 0%
44 Final Blinding 12 hrs Wed 9/26/07 Thu 9/27/07 0%
45 Cold Cutting of pipes 24 hrs Thu 9/27/07 Fri 9/28/07 0%
46 Dismantling of old pipe 12 hrs Fri 9/28/07 Fri 9/28/07 0%
47 Erection of new pipe 24 hrs Fri 9/28/07 Sat 9/29/07 0%
48 Welding of new pipe 72 hrs Sat 9/29/07 Tue 10/2/07 0%
49 NDT 24 hrs Tue 10/2/07 Wed 10/3/07 0%
50 Hydrotest 24 hrs Wed 10/3/07 Thu 10/4/07 0%
51 Draining of water 24 hrs Thu 10/4/07 Fri 10/5/07 0%
52 Deblinding 12 hrs Fri 10/5/07 Sat 10/6/07 0%
53 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
54 3.13.1:FUEL GAS LINES(2",80M) 13.83 days Mon 9/24/07 Mon 10/8/07 0%
55 Blinding / Deblinding 36 hrs Mon 9/24/07 Tue 9/25/07 0%
56 Steam & Water Washing 24 hrs Tue 9/25/07 Wed 9/26/07 0%
57 Final Blinding 8 hrs Wed 9/26/07 Thu 9/27/07 0%
58 Cold Cutting of pipes 24 hrs Thu 9/27/07 Fri 9/28/07 0%
59 Dismantling of old pipe 8 hrs Fri 9/28/07 Fri 9/28/07 0%
60 Erection of new pipe 16 hrs Fri 9/28/07 Sat 9/29/07 0%
61 Welding of new pipe 48 hrs Sat 9/29/07 Mon 10/1/07 0%
62 NDT 12 hrs Mon 10/1/07 Mon 10/1/07 0%
63 Hydrotest 24 hrs Mon 10/1/07 Tue 10/2/07 0%
64 Draining of water 16 hrs Tue 10/2/07 Wed 10/3/07 0%
Page 2
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
S M T W T F S S M T W T F S S M T W
65 Deblinding 12 hrs Wed 10/3/07 Wed 10/3/07 0%
66 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
67 3.13.2:FUEL GAS LINES(4",30m) 13.83 days Mon 9/24/07 Mon 10/8/07 0%
68 Blinding / Deblinding 36 hrs Mon 9/24/07 Tue 9/25/07 0%
69 Steam & Water Washing 24 hrs Tue 9/25/07 Wed 9/26/07 0%
70 Final Blinding 8 hrs Wed 9/26/07 Thu 9/27/07 0%
71 Cold Cutting of pipes 24 hrs Thu 9/27/07 Fri 9/28/07 0%
72 Dismantling of old pipe 8 hrs Fri 9/28/07 Fri 9/28/07 0%
73 Erection of new pipe 16 hrs Fri 9/28/07 Sat 9/29/07 0%
74 Welding of new pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
75 NDT 12 hrs Sun 9/30/07 Sun 9/30/07 0%
76 Hydrotest 24 hrs Sun 9/30/07 Mon 10/1/07 0%
77 Draining of water 12 hrs Mon 10/1/07 Tue 10/2/07 0%
78 Deblinding 12 hrs Tue 10/2/07 Tue 10/2/07 0%
79 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
80 3.13.3:FUEL GAS LINES(6",40 M) 13.83 days Mon 9/24/07 Mon 10/8/07 0%
81 Blinding / Deblinding 36 hrs Mon 9/24/07 Tue 9/25/07 0%
82 Steam & Water Washing 24 hrs Tue 9/25/07 Wed 9/26/07 0%
83 Final Blinding 12 hrs Wed 9/26/07 Thu 9/27/07 0%
84 Cold Cutting of pipes 24 hrs Thu 9/27/07 Fri 9/28/07 0%
85 Dismantling of old pipe 12 hrs Fri 9/28/07 Fri 9/28/07 0%
86 Erection of new pipe 24 hrs Fri 9/28/07 Sat 9/29/07 0%
87 Welding of new pipe 48 hrs Sat 9/29/07 Mon 10/1/07 0%
88 NDT 24 hrs Mon 10/1/07 Tue 10/2/07 0%
89 Hydrotest 24 hrs Tue 10/2/07 Wed 10/3/07 0%
90 Draining of water 24 hrs Wed 10/3/07 Thu 10/4/07 0%
91 Deblinding 12 hrs Thu 10/4/07 Thu 10/4/07 0%
92 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
93 3.13.4:FUEL GAS LINES(8",60M) 13.83 days Mon 9/24/07 Mon 10/8/07 0%
94 Blinding / Deblinding 36 hrs Mon 9/24/07 Tue 9/25/07 0%
95 Steam & Water Washing 24 hrs Tue 9/25/07 Wed 9/26/07 0%
96 Final Blinding 12 hrs Wed 9/26/07 Thu 9/27/07 0%
Page 3
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
S M T W T F S S M T W T F S S M T W
97 Cold Cutting of pipes 48 hrs Thu 9/27/07 Sat 9/29/07 0%
98 Dismantling of old pipe 24 hrs Fri 9/28/07 Sat 9/29/07 0%
99 Erection of new pipe 48 hrs Sat 9/29/07 Mon 10/1/07 0%
100 Welding of new pipe 72 hrs Sun 9/30/07 Wed 10/3/07 0%
101 NDT 24 hrs Wed 10/3/07 Thu 10/4/07 0%
102 Hydrotest 24 hrs Thu 10/4/07 Fri 10/5/07 0%
103 Draining of water 24 hrs Fri 10/5/07 Sat 10/6/07 0%
104 Deblinding 12 hrs Sat 10/6/07 Sat 10/6/07 0%
105 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
106 3.2.1:H2 LINES(2",60M) 13.83 days Mon 9/24/07 Mon 10/8/07 0%
107 Blinding / Deblinding 36 hrs Mon 9/24/07 Tue 9/25/07 0%
108 Steam & Water Washing 24 hrs Tue 9/25/07 Wed 9/26/07 0%
109 Final Blinding 8 hrs Wed 9/26/07 Thu 9/27/07 0%
110 Cold Cutting of pipes 24 hrs Thu 9/27/07 Fri 9/28/07 0%
111 Dismantling of old pipe 8 hrs Fri 9/28/07 Fri 9/28/07 0%
112 Erection of new pipe 16 hrs Fri 9/28/07 Sat 9/29/07 0%
113 Welding of new pipe 48 hrs Sat 9/29/07 Mon 10/1/07 0%
114 NDT 12 hrs Mon 10/1/07 Mon 10/1/07 0%
115 Hydrotest 24 hrs Mon 10/1/07 Tue 10/2/07 0%
116 Draining of water 16 hrs Tue 10/2/07 Wed 10/3/07 0%
117 Deblinding 12 hrs Wed 10/3/07 Wed 10/3/07 0%
118 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
119 3.2.2: H2 LINES(3",84M) 13.83 days Mon 9/24/07 Mon 10/8/07 0%
120 Blinding / Deblinding 36 hrs Mon 9/24/07 Tue 9/25/07 0%
121 Steam & Water Washing 24 hrs Tue 9/25/07 Wed 9/26/07 0%
122 Final Blinding 8 hrs Wed 9/26/07 Thu 9/27/07 0%
123 Cold Cutting of pipes 16 hrs Thu 9/27/07 Thu 9/27/07 0%
124 Dismantling of old pipe 8 hrs Thu 9/27/07 Fri 9/28/07 0%
125 Erection of new pipe 16 hrs Fri 9/28/07 Fri 9/28/07 0%
126 Welding of new pipe 24 hrs Fri 9/28/07 Sat 9/29/07 0%
127 NDT 12 hrs Sat 9/29/07 Sun 9/30/07 0%
128 Hydrotest 24 hrs Sun 9/30/07 Mon 10/1/07 0%
Page 4
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
S M T W T F S S M T W T F S S M T W
129 Draining of water 16 hrs Mon 10/1/07 Tue 10/2/07 0%
130 Deblinding 12 hrs Tue 10/2/07 Tue 10/2/07 0%
131 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
132 3.2.3:H2 LINES(4",36 M) 13.83 days Mon 9/24/07 Mon 10/8/07 0%
133 Blinding / Deblinding 36 hrs Mon 9/24/07 Tue 9/25/07 0%
134 Steam & Water Washing 24 hrs Tue 9/25/07 Wed 9/26/07 0%
135 Final Blinding 8 hrs Wed 9/26/07 Thu 9/27/07 0%
136 Cold Cutting of pipes 24 hrs Thu 9/27/07 Fri 9/28/07 0%
137 Dismantling of old pipe 8 hrs Fri 9/28/07 Fri 9/28/07 0%
138 Erection of new pipe 16 hrs Fri 9/28/07 Sat 9/29/07 0%
139 Welding of new pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
140 NDT 12 hrs Sun 9/30/07 Sun 9/30/07 0%
141 Hydrotest 24 hrs Sun 9/30/07 Mon 10/1/07 0%
142 Draining of water 12 hrs Mon 10/1/07 Tue 10/2/07 0%
143 Deblinding 12 hrs Tue 10/2/07 Tue 10/2/07 0%
144 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
145 3.4.1:ATF LINES(4",60 M) 12.83 days Tue 9/25/07 Mon 10/8/07 0%
146 Blinding / Deblinding 36 hrs Tue 9/25/07 Wed 9/26/07 0%
147 Steam & Water Washing 24 hrs Wed 9/26/07 Thu 9/27/07 0%
148 Final Blinding 12 hrs Thu 9/27/07 Fri 9/28/07 0%
149 Cold Cutting of pipes 24 hrs Fri 9/28/07 Sat 9/29/07 0%
150 Dismantling of old pipe 12 hrs Sat 9/29/07 Sat 9/29/07 0%
151 Erection of new pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
152 Welding of new pipe 48 hrs Sun 9/30/07 Tue 10/2/07 0%
153 NDT 24 hrs Tue 10/2/07 Wed 10/3/07 0%
154 Hydrotest 24 hrs Wed 10/3/07 Thu 10/4/07 0%
155 Draining of water 24 hrs Thu 10/4/07 Fri 10/5/07 0%
156 Deblinding 12 hrs Fri 10/5/07 Sat 10/6/07 0%
157 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
158 3.10.1:OFFGAS LINES(2",36M) 12.83 days Tue 9/25/07 Mon 10/8/07 0%
159 Blinding / Deblinding 36 hrs Tue 9/25/07 Wed 9/26/07 0%
160 Steam & Water Washing 24 hrs Wed 9/26/07 Thu 9/27/07 0%
Page 5
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
S M T W T F S S M T W T F S S M T W
161 Final Blinding 8 hrs Thu 9/27/07 Fri 9/28/07 0%
162 Cold Cutting of pipes 12 hrs Fri 9/28/07 Fri 9/28/07 0%
163 Dismantling of old pipe 8 hrs Fri 9/28/07 Sat 9/29/07 0%
164 Erection of new pipe 8 hrs Sat 9/29/07 Sat 9/29/07 0%
165 Welding of new pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
166 NDT 12 hrs Sun 9/30/07 Sun 9/30/07 0%
167 Hydrotest 12 hrs Sun 9/30/07 Mon 10/1/07 0%
168 Draining of water 12 hrs Mon 10/1/07 Mon 10/1/07 0%
169 Deblinding 12 hrs Mon 10/1/07 Tue 10/2/07 0%
170 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
171 3.10.2:OFFGAS LINES(3",60M) 12.83 days Tue 9/25/07 Mon 10/8/07 0%
172 Blinding / Deblinding 36 hrs Tue 9/25/07 Wed 9/26/07 0%
173 Steam & Water Washing 24 hrs Wed 9/26/07 Thu 9/27/07 0%
174 Final Blinding 8 hrs Thu 9/27/07 Fri 9/28/07 0%
175 Cold Cutting of pipes 16 hrs Fri 9/28/07 Fri 9/28/07 0%
176 Dismantling of old pipe 8 hrs Fri 9/28/07 Sat 9/29/07 0%
177 Erection of new pipe 16 hrs Sat 9/29/07 Sat 9/29/07 0%
178 Welding of new pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
179 NDT 12 hrs Sun 9/30/07 Mon 10/1/07 0%
180 Hydrotest 24 hrs Mon 10/1/07 Tue 10/2/07 0%
181 Draining of water 16 hrs Tue 10/2/07 Wed 10/3/07 0%
182 Deblinding 12 hrs Wed 10/3/07 Wed 10/3/07 0%
183 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
184 3.10.3:OFFGAS LINES(4",60M) 12.83 days Tue 9/25/07 Mon 10/8/07 0%
185 Blinding / Deblinding 36 hrs Tue 9/25/07 Wed 9/26/07 0%
186 Steam & Water Washing 24 hrs Wed 9/26/07 Thu 9/27/07 0%
187 Final Blinding 12 hrs Thu 9/27/07 Fri 9/28/07 0%
188 Cold Cutting of pipes 24 hrs Fri 9/28/07 Sat 9/29/07 0%
189 Dismantling of old pipe 12 hrs Sat 9/29/07 Sat 9/29/07 0%
190 Erection of new pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
191 Welding of new pipe 48 hrs Sun 9/30/07 Tue 10/2/07 0%
192 NDT 24 hrs Tue 10/2/07 Wed 10/3/07 0%
Page 6
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
S M T W T F S S M T W T F S S M T W
193 Hydrotest 24 hrs Wed 10/3/07 Thu 10/4/07 0%
194 Draining of water 24 hrs Thu 10/4/07 Fri 10/5/07 0%
195 Deblinding 12 hrs Fri 10/5/07 Sat 10/6/07 0%
196 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
197 3.11.1:SOURGAS LINES(6",60M) 12.83 days Tue 9/25/07 Mon 10/8/07 0%
198 Blinding / Deblinding 36 hrs Tue 9/25/07 Wed 9/26/07 0%
199 Steam & Water Washing 24 hrs Wed 9/26/07 Thu 9/27/07 0%
200 Final Blinding 12 hrs Thu 9/27/07 Fri 9/28/07 0%
201 Cold Cutting of pipes 24 hrs Fri 9/28/07 Sat 9/29/07 0%
202 Dismantling of old pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
203 Erection of new pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
204 Welding of new pipe 72 hrs Sun 9/30/07 Wed 10/3/07 0%
205 NDT 16 hrs Wed 10/3/07 Thu 10/4/07 0%
206 Hydrotest 24 hrs Thu 10/4/07 Fri 10/5/07 0%
207 Draining of water 24 hrs Fri 10/5/07 Sat 10/6/07 0%
208 Deblinding 12 hrs Sat 10/6/07 Sat 10/6/07 0%
209 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
210 3.18.1:AMINE LINES(2",120 M) 12.83 days Tue 9/25/07 Mon 10/8/07 0%
211 Blinding / Deblinding 36 hrs Tue 9/25/07 Wed 9/26/07 0%
212 Steam & Water Washing 24 hrs Wed 9/26/07 Thu 9/27/07 0%
213 Final Blinding 8 hrs Thu 9/27/07 Fri 9/28/07 0%
214 Cold Cutting of pipes 36 hrs Fri 9/28/07 Sat 9/29/07 0%
215 Dismantling of old pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
216 Erection of new pipe 48 hrs Sat 9/29/07 Mon 10/1/07 0%
217 Welding of new pipe 72 hrs Sun 9/30/07 Wed 10/3/07 0%
218 NDT 16 hrs Wed 10/3/07 Thu 10/4/07 0%
219 Hydrotest 24 hrs Thu 10/4/07 Fri 10/5/07 0%
220 Draining of water 16 hrs Fri 10/5/07 Fri 10/5/07 0%
221 Deblinding 12 hrs Fri 10/5/07 Sat 10/6/07 0%
222 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
223 3.18.2:AMINE LINES(3",60M) 12.83 days Tue 9/25/07 Mon 10/8/07 0%
224 Blinding / Deblinding 36 hrs Tue 9/25/07 Wed 9/26/07 0%
Page 7
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
S M T W T F S S M T W T F S S M T W
225 Steam & Water Washing 24 hrs Wed 9/26/07 Thu 9/27/07 0%
226 Final Blinding 8 hrs Thu 9/27/07 Fri 9/28/07 0%
227 Cold Cutting of pipes 16 hrs Fri 9/28/07 Fri 9/28/07 0%
228 Dismantling of old pipe 8 hrs Fri 9/28/07 Sat 9/29/07 0%
229 Erection of new pipe 16 hrs Sat 9/29/07 Sat 9/29/07 0%
230 Welding of new pipe 40 hrs Sat 9/29/07 Mon 10/1/07 0%
231 NDT 12 hrs Mon 10/1/07 Tue 10/2/07 0%
232 Hydrotest 24 hrs Tue 10/2/07 Wed 10/3/07 0%
233 Draining of water 16 hrs Wed 10/3/07 Wed 10/3/07 0%
234 Deblinding 12 hrs Wed 10/3/07 Thu 10/4/07 0%
235 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
236 3.19.1:IFO LINES(11/2",60M) 12.83 days Tue 9/25/07 Mon 10/8/07 0%
237 Blinding / Deblinding 36 hrs Tue 9/25/07 Wed 9/26/07 0%
238 Steam & Water Washing 24 hrs Wed 9/26/07 Thu 9/27/07 0%
239 Final Blinding 8 hrs Thu 9/27/07 Fri 9/28/07 0%
240 Cold Cutting of pipes 16 hrs Fri 9/28/07 Fri 9/28/07 0%
241 Dismantling of old pipe 8 hrs Fri 9/28/07 Sat 9/29/07 0%
242 Erection of new pipe 16 hrs Sat 9/29/07 Sat 9/29/07 0%
243 Welding of new pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
244 NDT 12 hrs Sun 9/30/07 Mon 10/1/07 0%
245 Hydrotest 24 hrs Mon 10/1/07 Tue 10/2/07 0%
246 Draining of water 16 hrs Tue 10/2/07 Wed 10/3/07 0%
247 Deblinding 12 hrs Wed 10/3/07 Wed 10/3/07 0%
248 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
249 3.19.2: IFO LINES(2",120 M) 12.83 days Tue 9/25/07 Mon 10/8/07 0%
250 Blinding / Deblinding 36 hrs Tue 9/25/07 Wed 9/26/07 0%
251 Steam & Water Washing 24 hrs Wed 9/26/07 Thu 9/27/07 0%
252 Final Blinding 8 hrs Thu 9/27/07 Fri 9/28/07 0%
253 Cold Cutting of pipes 32 hrs Fri 9/28/07 Sat 9/29/07 0%
254 Dismantling of old pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
255 Erection of new pipe 40 hrs Sat 9/29/07 Mon 10/1/07 0%
256 Welding of new pipe 72 hrs Sun 9/30/07 Wed 10/3/07 0%
Page 8
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
S M T W T F S S M T W T F S S M T W
257 NDT 12 hrs Wed 10/3/07 Wed 10/3/07 0%
258 Hydrotest 24 hrs Wed 10/3/07 Thu 10/4/07 0%
259 Draining of water 16 hrs Thu 10/4/07 Fri 10/5/07 0%
260 Deblinding 12 hrs Fri 10/5/07 Sat 10/6/07 0%
261 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
262 3.19.3: IFO LINES(3",200M) 12.83 days Tue 9/25/07 Mon 10/8/07 0%
263 Blinding / Deblinding 36 hrs Tue 9/25/07 Wed 9/26/07 0%
264 Steam & Water Washing 24 hrs Wed 9/26/07 Thu 9/27/07 0%
265 Final Blinding 12 hrs Thu 9/27/07 Fri 9/28/07 0%
266 Cold Cutting of pipes 48 hrs Fri 9/28/07 Sun 9/30/07 0%
267 Dismantling of old pipe 48 hrs Fri 9/28/07 Sun 9/30/07 0%
268 Erection of new pipe 48 hrs Sat 9/29/07 Mon 10/1/07 0%
269 Welding of new pipe 72 hrs Sun 9/30/07 Wed 10/3/07 0%
270 NDT 24 hrs Wed 10/3/07 Thu 10/4/07 0%
271 Hydrotest 24 hrs Thu 10/4/07 Fri 10/5/07 0%
272 Draining of water 24 hrs Fri 10/5/07 Sat 10/6/07 0%
273 Deblinding 12 hrs Sat 10/6/07 Sat 10/6/07 0%
274 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
275 3.5.1:RTF LINES(6",120 M) 11.83 days Wed 9/26/07 Mon 10/8/07 0%
276 Blinding / Deblinding 36 hrs Wed 9/26/07 Thu 9/27/07 0%
277 Steam & Water Washing 24 hrs Thu 9/27/07 Fri 9/28/07 0%
278 Final Blinding 12 hrs Fri 9/28/07 Sat 9/29/07 0%
279 Cold Cutting of pipes 48 hrs Sat 9/29/07 Mon 10/1/07 0%
280 Dismantling of old pipe 48 hrs Sat 9/29/07 Mon 10/1/07 0%
281 Erection of new pipe 48 hrs Sun 9/30/07 Tue 10/2/07 0%
282 Welding of new pipe 88 hrs Sun 9/30/07 Thu 10/4/07 0%
283 NDT 24 hrs Wed 10/3/07 Thu 10/4/07 0%
284 Hydrotest 24 hrs Thu 10/4/07 Fri 10/5/07 0%
285 Draining of water 24 hrs Fri 10/5/07 Sat 10/6/07 0%
286 Deblinding 12 hrs Sat 10/6/07 Sun 10/7/07 0%
287 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
288 3.7.2:SKO LINES(3",84M) 11.83 days Wed 9/26/07 Mon 10/8/07 0%
Page 9
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
S M T W T F S S M T W T F S S M T W
289 Blinding / Deblinding 36 hrs Wed 9/26/07 Thu 9/27/07 0%
290 Steam & Water Washing 24 hrs Thu 9/27/07 Fri 9/28/07 0%
291 Final Blinding 8 hrs Fri 9/28/07 Sat 9/29/07 0%
292 Cold Cutting of pipes 16 hrs Sat 9/29/07 Sat 9/29/07 0%
293 Dismantling of old pipe 8 hrs Sat 9/29/07 Sun 9/30/07 0%
294 Erection of new pipe 16 hrs Sun 9/30/07 Sun 9/30/07 0%
295 Welding of new pipe 24 hrs Sun 9/30/07 Mon 10/1/07 0%
296 NDT 12 hrs Mon 10/1/07 Tue 10/2/07 0%
297 Hydrotest 24 hrs Tue 10/2/07 Wed 10/3/07 0%
298 Draining of water 16 hrs Wed 10/3/07 Thu 10/4/07 0%
299 Deblinding 12 hrs Thu 10/4/07 Thu 10/4/07 0%
300 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
301 3.7.3:SKO LINES(6",60M) 11.83 days Wed 9/26/07 Mon 10/8/07 0%
302 Blinding / Deblinding 36 hrs Wed 9/26/07 Thu 9/27/07 0%
303 Steam & Water Washing 24 hrs Thu 9/27/07 Fri 9/28/07 0%
304 Final Blinding 12 hrs Fri 9/28/07 Sat 9/29/07 0%
305 Cold Cutting of pipes 24 hrs Sat 9/29/07 Sun 9/30/07 0%
306 Dismantling of old pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
307 Erection of new pipe 24 hrs Sun 9/30/07 Mon 10/1/07 0%
308 Welding of new pipe 72 hrs Sun 9/30/07 Wed 10/3/07 0%
309 NDT 24 hrs Wed 10/3/07 Thu 10/4/07 0%
310 Hydrotest 24 hrs Thu 10/4/07 Fri 10/5/07 0%
311 Draining of water 24 hrs Fri 10/5/07 Sat 10/6/07 0%
312 Deblinding 12 hrs Sat 10/6/07 Sun 10/7/07 0%
313 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
314 3.8.1:HSD LINES(6",120 M) 11.83 days Wed 9/26/07 Mon 10/8/07 0%
315 Blinding / Deblinding 36 hrs Wed 9/26/07 Thu 9/27/07 0%
316 Steam & Water Washing 24 hrs Thu 9/27/07 Fri 9/28/07 0%
317 Final Blinding 12 hrs Fri 9/28/07 Sat 9/29/07 0%
318 Cold Cutting of pipes 48 hrs Sat 9/29/07 Mon 10/1/07 0%
319 Dismantling of old pipe 48 hrs Sat 9/29/07 Mon 10/1/07 0%
320 Erection of new pipe 48 hrs Sun 9/30/07 Tue 10/2/07 0%
Page 10
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
S M T W T F S S M T W T F S S M T W
321 Welding of new pipe 88 hrs Sun 9/30/07 Thu 10/4/07 0%
322 NDT 24 hrs Wed 10/3/07 Thu 10/4/07 0%
323 Hydrotest 24 hrs Thu 10/4/07 Fri 10/5/07 0%
324 Draining of water 24 hrs Fri 10/5/07 Sat 10/6/07 0%
325 Deblinding 12 hrs Sat 10/6/07 Sun 10/7/07 0%
326 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
Page 11
Activity Bar Chart of Refractory Application during Shutdown at P.G.Boiler at IOCL - HALDIA
Sr.No. Activity
No. of Days
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A R.G.Boiler
1 Dismantling & debris cleaning
2 Surface cleaning & anchor welding
3 End Tube Sheet Casting
4 First layer casting using form work
5 Second layer casting
6 Form work removal & natural curing
7 Dry out up to 250 deg C
8 Final Inspection & Boxing up
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
S M T W T F S S M T W T F S S M T W
1 OFFSITE PIPING 13.83 days Mon 9/24/07 Mon 10/8/07 0%
2 3.1.3: LPG LINES(3", 80M) 13.83 days Mon 9/24/07 Mon 10/8/07 0%
3 Blinding / Deblinding 36 hrs Mon 9/24/07 Tue 9/25/07 0%
4 Steam & Water Washing 24 hrs Tue 9/25/07 Wed 9/26/07 0%
5 Final Blinding 8 hrs Wed 9/26/07 Thu 9/27/07 0%
6 Cold Cutting of pipes 24 hrs Thu 9/27/07 Fri 9/28/07 0%
7 Dismantling of old pipe 16 hrs Fri 9/28/07 Fri 9/28/07 0%
8 Erection of new pipe 24 hrs Fri 9/28/07 Sat 9/29/07 0%
9 Welding of new pipe 72 hrs Sat 9/29/07 Tue 10/2/07 0%
10 NDT 16 hrs Tue 10/2/07 Wed 10/3/07 0%
11 Hydrotest 24 hrs Wed 10/3/07 Thu 10/4/07 0%
12 Draining of water 16 hrs Thu 10/4/07 Fri 10/5/07 0%
13 Deblinding 12 hrs Fri 10/5/07 Fri 10/5/07 0%
14 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
15 3.3.1:NAPTHA LINES(2",24 M) 13.83 days Mon 9/24/07 Mon 10/8/07 0%
16 Blinding / Deblinding 36 hrs Mon 9/24/07 Tue 9/25/07 0%
17 Steam & Water Washing 24 hrs Tue 9/25/07 Wed 9/26/07 0%
18 Final Blinding 8 hrs Wed 9/26/07 Thu 9/27/07 0%
19 Cold Cutting of pipes 12 hrs Thu 9/27/07 Thu 9/27/07 0%
20 Dismantling of old pipe 8 hrs Thu 9/27/07 Fri 9/28/07 0%
21 Erection of new pipe 8 hrs Fri 9/28/07 Fri 9/28/07 0%
22 Welding of new pipe 24 hrs Fri 9/28/07 Sat 9/29/07 0%
23 NDT 12 hrs Sat 9/29/07 Sat 9/29/07 0%
24 Hydrotest 12 hrs Sat 9/29/07 Sun 9/30/07 0%
25 Draining of water 12 hrs Sun 9/30/07 Sun 9/30/07 0%
26 Deblinding 12 hrs Sun 9/30/07 Mon 10/1/07 0%
27 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
28 3.3.2:NAPTHA LINE(3",200 M) 13.83 days Mon 9/24/07 Mon 10/8/07 0%
29 Blinding / Deblinding 36 hrs Mon 9/24/07 Tue 9/25/07 0%
30 Steam & Water Washing 24 hrs Tue 9/25/07 Wed 9/26/07 0%
31 Final Blinding 12 hrs Wed 9/26/07 Thu 9/27/07 0%
32 Cold Cutting of pipes 48 hrs Thu 9/27/07 Sat 9/29/07 0%
Page 1
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
S M T W T F S S M T W T F S S M T W
33 Dismantling of old pipe 32 hrs Fri 9/28/07 Sat 9/29/07 0%
34 Erection of new pipe 48 hrs Sat 9/29/07 Mon 10/1/07 0%
35 Welding of new pipe 96 hrs Sat 9/29/07 Wed 10/3/07 0%
36 NDT 24 hrs Wed 10/3/07 Thu 10/4/07 0%
37 Hydrotest 24 hrs Thu 10/4/07 Fri 10/5/07 0%
38 Draining of water 24 hrs Fri 10/5/07 Sat 10/6/07 0%
39 Deblinding 12 hrs Sat 10/6/07 Sun 10/7/07 0%
40 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
41 3.3.3:NAPTHA LINES(4",60 M) 13.83 days Mon 9/24/07 Mon 10/8/07 0%
42 Blinding / Deblinding 36 hrs Mon 9/24/07 Tue 9/25/07 0%
43 Steam & Water Washing 24 hrs Tue 9/25/07 Wed 9/26/07 0%
44 Final Blinding 12 hrs Wed 9/26/07 Thu 9/27/07 0%
45 Cold Cutting of pipes 24 hrs Thu 9/27/07 Fri 9/28/07 0%
46 Dismantling of old pipe 12 hrs Fri 9/28/07 Fri 9/28/07 0%
47 Erection of new pipe 24 hrs Fri 9/28/07 Sat 9/29/07 0%
48 Welding of new pipe 72 hrs Sat 9/29/07 Tue 10/2/07 0%
49 NDT 24 hrs Tue 10/2/07 Wed 10/3/07 0%
50 Hydrotest 24 hrs Wed 10/3/07 Thu 10/4/07 0%
51 Draining of water 24 hrs Thu 10/4/07 Fri 10/5/07 0%
52 Deblinding 12 hrs Fri 10/5/07 Sat 10/6/07 0%
53 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
54 3.13.1:FUEL GAS LINES(2",80M) 13.83 days Mon 9/24/07 Mon 10/8/07 0%
55 Blinding / Deblinding 36 hrs Mon 9/24/07 Tue 9/25/07 0%
56 Steam & Water Washing 24 hrs Tue 9/25/07 Wed 9/26/07 0%
57 Final Blinding 8 hrs Wed 9/26/07 Thu 9/27/07 0%
58 Cold Cutting of pipes 24 hrs Thu 9/27/07 Fri 9/28/07 0%
59 Dismantling of old pipe 8 hrs Fri 9/28/07 Fri 9/28/07 0%
60 Erection of new pipe 16 hrs Fri 9/28/07 Sat 9/29/07 0%
61 Welding of new pipe 48 hrs Sat 9/29/07 Mon 10/1/07 0%
62 NDT 12 hrs Mon 10/1/07 Mon 10/1/07 0%
63 Hydrotest 24 hrs Mon 10/1/07 Tue 10/2/07 0%
64 Draining of water 16 hrs Tue 10/2/07 Wed 10/3/07 0%
Page 2
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
S M T W T F S S M T W T F S S M T W
65 Deblinding 12 hrs Wed 10/3/07 Wed 10/3/07 0%
66 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
67 3.13.2:FUEL GAS LINES(4",30m) 13.83 days Mon 9/24/07 Mon 10/8/07 0%
68 Blinding / Deblinding 36 hrs Mon 9/24/07 Tue 9/25/07 0%
69 Steam & Water Washing 24 hrs Tue 9/25/07 Wed 9/26/07 0%
70 Final Blinding 8 hrs Wed 9/26/07 Thu 9/27/07 0%
71 Cold Cutting of pipes 24 hrs Thu 9/27/07 Fri 9/28/07 0%
72 Dismantling of old pipe 8 hrs Fri 9/28/07 Fri 9/28/07 0%
73 Erection of new pipe 16 hrs Fri 9/28/07 Sat 9/29/07 0%
74 Welding of new pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
75 NDT 12 hrs Sun 9/30/07 Sun 9/30/07 0%
76 Hydrotest 24 hrs Sun 9/30/07 Mon 10/1/07 0%
77 Draining of water 12 hrs Mon 10/1/07 Tue 10/2/07 0%
78 Deblinding 12 hrs Tue 10/2/07 Tue 10/2/07 0%
79 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
80 3.13.3:FUEL GAS LINES(6",40 M) 13.83 days Mon 9/24/07 Mon 10/8/07 0%
81 Blinding / Deblinding 36 hrs Mon 9/24/07 Tue 9/25/07 0%
82 Steam & Water Washing 24 hrs Tue 9/25/07 Wed 9/26/07 0%
83 Final Blinding 12 hrs Wed 9/26/07 Thu 9/27/07 0%
84 Cold Cutting of pipes 24 hrs Thu 9/27/07 Fri 9/28/07 0%
85 Dismantling of old pipe 12 hrs Fri 9/28/07 Fri 9/28/07 0%
86 Erection of new pipe 24 hrs Fri 9/28/07 Sat 9/29/07 0%
87 Welding of new pipe 48 hrs Sat 9/29/07 Mon 10/1/07 0%
88 NDT 24 hrs Mon 10/1/07 Tue 10/2/07 0%
89 Hydrotest 24 hrs Tue 10/2/07 Wed 10/3/07 0%
90 Draining of water 24 hrs Wed 10/3/07 Thu 10/4/07 0%
91 Deblinding 12 hrs Thu 10/4/07 Thu 10/4/07 0%
92 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
93 3.13.4:FUEL GAS LINES(8",60M) 13.83 days Mon 9/24/07 Mon 10/8/07 0%
94 Blinding / Deblinding 36 hrs Mon 9/24/07 Tue 9/25/07 0%
95 Steam & Water Washing 24 hrs Tue 9/25/07 Wed 9/26/07 0%
96 Final Blinding 12 hrs Wed 9/26/07 Thu 9/27/07 0%
Page 3
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
S M T W T F S S M T W T F S S M T W
97 Cold Cutting of pipes 48 hrs Thu 9/27/07 Sat 9/29/07 0%
98 Dismantling of old pipe 24 hrs Fri 9/28/07 Sat 9/29/07 0%
99 Erection of new pipe 48 hrs Sat 9/29/07 Mon 10/1/07 0%
100 Welding of new pipe 72 hrs Sun 9/30/07 Wed 10/3/07 0%
101 NDT 24 hrs Wed 10/3/07 Thu 10/4/07 0%
102 Hydrotest 24 hrs Thu 10/4/07 Fri 10/5/07 0%
103 Draining of water 24 hrs Fri 10/5/07 Sat 10/6/07 0%
104 Deblinding 12 hrs Sat 10/6/07 Sat 10/6/07 0%
105 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
106 3.2.1:H2 LINES(2",60M) 13.83 days Mon 9/24/07 Mon 10/8/07 0%
107 Blinding / Deblinding 36 hrs Mon 9/24/07 Tue 9/25/07 0%
108 Steam & Water Washing 24 hrs Tue 9/25/07 Wed 9/26/07 0%
109 Final Blinding 8 hrs Wed 9/26/07 Thu 9/27/07 0%
110 Cold Cutting of pipes 24 hrs Thu 9/27/07 Fri 9/28/07 0%
111 Dismantling of old pipe 8 hrs Fri 9/28/07 Fri 9/28/07 0%
112 Erection of new pipe 16 hrs Fri 9/28/07 Sat 9/29/07 0%
113 Welding of new pipe 48 hrs Sat 9/29/07 Mon 10/1/07 0%
114 NDT 12 hrs Mon 10/1/07 Mon 10/1/07 0%
115 Hydrotest 24 hrs Mon 10/1/07 Tue 10/2/07 0%
116 Draining of water 16 hrs Tue 10/2/07 Wed 10/3/07 0%
117 Deblinding 12 hrs Wed 10/3/07 Wed 10/3/07 0%
118 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
119 3.2.2: H2 LINES(3",84M) 13.83 days Mon 9/24/07 Mon 10/8/07 0%
120 Blinding / Deblinding 36 hrs Mon 9/24/07 Tue 9/25/07 0%
121 Steam & Water Washing 24 hrs Tue 9/25/07 Wed 9/26/07 0%
122 Final Blinding 8 hrs Wed 9/26/07 Thu 9/27/07 0%
123 Cold Cutting of pipes 16 hrs Thu 9/27/07 Thu 9/27/07 0%
124 Dismantling of old pipe 8 hrs Thu 9/27/07 Fri 9/28/07 0%
125 Erection of new pipe 16 hrs Fri 9/28/07 Fri 9/28/07 0%
126 Welding of new pipe 24 hrs Fri 9/28/07 Sat 9/29/07 0%
127 NDT 12 hrs Sat 9/29/07 Sun 9/30/07 0%
128 Hydrotest 24 hrs Sun 9/30/07 Mon 10/1/07 0%
Page 4
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
S M T W T F S S M T W T F S S M T W
129 Draining of water 16 hrs Mon 10/1/07 Tue 10/2/07 0%
130 Deblinding 12 hrs Tue 10/2/07 Tue 10/2/07 0%
131 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
132 3.2.3:H2 LINES(4",36 M) 13.83 days Mon 9/24/07 Mon 10/8/07 0%
133 Blinding / Deblinding 36 hrs Mon 9/24/07 Tue 9/25/07 0%
134 Steam & Water Washing 24 hrs Tue 9/25/07 Wed 9/26/07 0%
135 Final Blinding 8 hrs Wed 9/26/07 Thu 9/27/07 0%
136 Cold Cutting of pipes 24 hrs Thu 9/27/07 Fri 9/28/07 0%
137 Dismantling of old pipe 8 hrs Fri 9/28/07 Fri 9/28/07 0%
138 Erection of new pipe 16 hrs Fri 9/28/07 Sat 9/29/07 0%
139 Welding of new pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
140 NDT 12 hrs Sun 9/30/07 Sun 9/30/07 0%
141 Hydrotest 24 hrs Sun 9/30/07 Mon 10/1/07 0%
142 Draining of water 12 hrs Mon 10/1/07 Tue 10/2/07 0%
143 Deblinding 12 hrs Tue 10/2/07 Tue 10/2/07 0%
144 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
145 3.4.1:ATF LINES(4",60 M) 12.83 days Tue 9/25/07 Mon 10/8/07 0%
146 Blinding / Deblinding 36 hrs Tue 9/25/07 Wed 9/26/07 0%
147 Steam & Water Washing 24 hrs Wed 9/26/07 Thu 9/27/07 0%
148 Final Blinding 12 hrs Thu 9/27/07 Fri 9/28/07 0%
149 Cold Cutting of pipes 24 hrs Fri 9/28/07 Sat 9/29/07 0%
150 Dismantling of old pipe 12 hrs Sat 9/29/07 Sat 9/29/07 0%
151 Erection of new pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
152 Welding of new pipe 48 hrs Sun 9/30/07 Tue 10/2/07 0%
153 NDT 24 hrs Tue 10/2/07 Wed 10/3/07 0%
154 Hydrotest 24 hrs Wed 10/3/07 Thu 10/4/07 0%
155 Draining of water 24 hrs Thu 10/4/07 Fri 10/5/07 0%
156 Deblinding 12 hrs Fri 10/5/07 Sat 10/6/07 0%
157 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
158 3.10.1:OFFGAS LINES(2",36M) 12.83 days Tue 9/25/07 Mon 10/8/07 0%
159 Blinding / Deblinding 36 hrs Tue 9/25/07 Wed 9/26/07 0%
160 Steam & Water Washing 24 hrs Wed 9/26/07 Thu 9/27/07 0%
Page 5
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
S M T W T F S S M T W T F S S M T W
161 Final Blinding 8 hrs Thu 9/27/07 Fri 9/28/07 0%
162 Cold Cutting of pipes 12 hrs Fri 9/28/07 Fri 9/28/07 0%
163 Dismantling of old pipe 8 hrs Fri 9/28/07 Sat 9/29/07 0%
164 Erection of new pipe 8 hrs Sat 9/29/07 Sat 9/29/07 0%
165 Welding of new pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
166 NDT 12 hrs Sun 9/30/07 Sun 9/30/07 0%
167 Hydrotest 12 hrs Sun 9/30/07 Mon 10/1/07 0%
168 Draining of water 12 hrs Mon 10/1/07 Mon 10/1/07 0%
169 Deblinding 12 hrs Mon 10/1/07 Tue 10/2/07 0%
170 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
171 3.10.2:OFFGAS LINES(3",60M) 12.83 days Tue 9/25/07 Mon 10/8/07 0%
172 Blinding / Deblinding 36 hrs Tue 9/25/07 Wed 9/26/07 0%
173 Steam & Water Washing 24 hrs Wed 9/26/07 Thu 9/27/07 0%
174 Final Blinding 8 hrs Thu 9/27/07 Fri 9/28/07 0%
175 Cold Cutting of pipes 16 hrs Fri 9/28/07 Fri 9/28/07 0%
176 Dismantling of old pipe 8 hrs Fri 9/28/07 Sat 9/29/07 0%
177 Erection of new pipe 16 hrs Sat 9/29/07 Sat 9/29/07 0%
178 Welding of new pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
179 NDT 12 hrs Sun 9/30/07 Mon 10/1/07 0%
180 Hydrotest 24 hrs Mon 10/1/07 Tue 10/2/07 0%
181 Draining of water 16 hrs Tue 10/2/07 Wed 10/3/07 0%
182 Deblinding 12 hrs Wed 10/3/07 Wed 10/3/07 0%
183 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
184 3.10.3:OFFGAS LINES(4",60M) 12.83 days Tue 9/25/07 Mon 10/8/07 0%
185 Blinding / Deblinding 36 hrs Tue 9/25/07 Wed 9/26/07 0%
186 Steam & Water Washing 24 hrs Wed 9/26/07 Thu 9/27/07 0%
187 Final Blinding 12 hrs Thu 9/27/07 Fri 9/28/07 0%
188 Cold Cutting of pipes 24 hrs Fri 9/28/07 Sat 9/29/07 0%
189 Dismantling of old pipe 12 hrs Sat 9/29/07 Sat 9/29/07 0%
190 Erection of new pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
191 Welding of new pipe 48 hrs Sun 9/30/07 Tue 10/2/07 0%
192 NDT 24 hrs Tue 10/2/07 Wed 10/3/07 0%
Page 6
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
S M T W T F S S M T W T F S S M T W
193 Hydrotest 24 hrs Wed 10/3/07 Thu 10/4/07 0%
194 Draining of water 24 hrs Thu 10/4/07 Fri 10/5/07 0%
195 Deblinding 12 hrs Fri 10/5/07 Sat 10/6/07 0%
196 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
197 3.11.1:SOURGAS LINES(6",60M) 12.83 days Tue 9/25/07 Mon 10/8/07 0%
198 Blinding / Deblinding 36 hrs Tue 9/25/07 Wed 9/26/07 0%
199 Steam & Water Washing 24 hrs Wed 9/26/07 Thu 9/27/07 0%
200 Final Blinding 12 hrs Thu 9/27/07 Fri 9/28/07 0%
201 Cold Cutting of pipes 24 hrs Fri 9/28/07 Sat 9/29/07 0%
202 Dismantling of old pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
203 Erection of new pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
204 Welding of new pipe 72 hrs Sun 9/30/07 Wed 10/3/07 0%
205 NDT 16 hrs Wed 10/3/07 Thu 10/4/07 0%
206 Hydrotest 24 hrs Thu 10/4/07 Fri 10/5/07 0%
207 Draining of water 24 hrs Fri 10/5/07 Sat 10/6/07 0%
208 Deblinding 12 hrs Sat 10/6/07 Sat 10/6/07 0%
209 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
210 3.18.1:AMINE LINES(2",120 M) 12.83 days Tue 9/25/07 Mon 10/8/07 0%
211 Blinding / Deblinding 36 hrs Tue 9/25/07 Wed 9/26/07 0%
212 Steam & Water Washing 24 hrs Wed 9/26/07 Thu 9/27/07 0%
213 Final Blinding 8 hrs Thu 9/27/07 Fri 9/28/07 0%
214 Cold Cutting of pipes 36 hrs Fri 9/28/07 Sat 9/29/07 0%
215 Dismantling of old pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
216 Erection of new pipe 48 hrs Sat 9/29/07 Mon 10/1/07 0%
217 Welding of new pipe 72 hrs Sun 9/30/07 Wed 10/3/07 0%
218 NDT 16 hrs Wed 10/3/07 Thu 10/4/07 0%
219 Hydrotest 24 hrs Thu 10/4/07 Fri 10/5/07 0%
220 Draining of water 16 hrs Fri 10/5/07 Fri 10/5/07 0%
221 Deblinding 12 hrs Fri 10/5/07 Sat 10/6/07 0%
222 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
223 3.18.2:AMINE LINES(3",60M) 12.83 days Tue 9/25/07 Mon 10/8/07 0%
224 Blinding / Deblinding 36 hrs Tue 9/25/07 Wed 9/26/07 0%
Page 7
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
S M T W T F S S M T W T F S S M T W
225 Steam & Water Washing 24 hrs Wed 9/26/07 Thu 9/27/07 0%
226 Final Blinding 8 hrs Thu 9/27/07 Fri 9/28/07 0%
227 Cold Cutting of pipes 16 hrs Fri 9/28/07 Fri 9/28/07 0%
228 Dismantling of old pipe 8 hrs Fri 9/28/07 Sat 9/29/07 0%
229 Erection of new pipe 16 hrs Sat 9/29/07 Sat 9/29/07 0%
230 Welding of new pipe 40 hrs Sat 9/29/07 Mon 10/1/07 0%
231 NDT 12 hrs Mon 10/1/07 Tue 10/2/07 0%
232 Hydrotest 24 hrs Tue 10/2/07 Wed 10/3/07 0%
233 Draining of water 16 hrs Wed 10/3/07 Wed 10/3/07 0%
234 Deblinding 12 hrs Wed 10/3/07 Thu 10/4/07 0%
235 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
236 3.19.1:IFO LINES(11/2",60M) 12.83 days Tue 9/25/07 Mon 10/8/07 0%
237 Blinding / Deblinding 36 hrs Tue 9/25/07 Wed 9/26/07 0%
238 Steam & Water Washing 24 hrs Wed 9/26/07 Thu 9/27/07 0%
239 Final Blinding 8 hrs Thu 9/27/07 Fri 9/28/07 0%
240 Cold Cutting of pipes 16 hrs Fri 9/28/07 Fri 9/28/07 0%
241 Dismantling of old pipe 8 hrs Fri 9/28/07 Sat 9/29/07 0%
242 Erection of new pipe 16 hrs Sat 9/29/07 Sat 9/29/07 0%
243 Welding of new pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
244 NDT 12 hrs Sun 9/30/07 Mon 10/1/07 0%
245 Hydrotest 24 hrs Mon 10/1/07 Tue 10/2/07 0%
246 Draining of water 16 hrs Tue 10/2/07 Wed 10/3/07 0%
247 Deblinding 12 hrs Wed 10/3/07 Wed 10/3/07 0%
248 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
249 3.19.2: IFO LINES(2",120 M) 12.83 days Tue 9/25/07 Mon 10/8/07 0%
250 Blinding / Deblinding 36 hrs Tue 9/25/07 Wed 9/26/07 0%
251 Steam & Water Washing 24 hrs Wed 9/26/07 Thu 9/27/07 0%
252 Final Blinding 8 hrs Thu 9/27/07 Fri 9/28/07 0%
253 Cold Cutting of pipes 32 hrs Fri 9/28/07 Sat 9/29/07 0%
254 Dismantling of old pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
255 Erection of new pipe 40 hrs Sat 9/29/07 Mon 10/1/07 0%
256 Welding of new pipe 72 hrs Sun 9/30/07 Wed 10/3/07 0%
Page 8
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
S M T W T F S S M T W T F S S M T W
257 NDT 12 hrs Wed 10/3/07 Wed 10/3/07 0%
258 Hydrotest 24 hrs Wed 10/3/07 Thu 10/4/07 0%
259 Draining of water 16 hrs Thu 10/4/07 Fri 10/5/07 0%
260 Deblinding 12 hrs Fri 10/5/07 Sat 10/6/07 0%
261 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
262 3.19.3: IFO LINES(3",200M) 12.83 days Tue 9/25/07 Mon 10/8/07 0%
263 Blinding / Deblinding 36 hrs Tue 9/25/07 Wed 9/26/07 0%
264 Steam & Water Washing 24 hrs Wed 9/26/07 Thu 9/27/07 0%
265 Final Blinding 12 hrs Thu 9/27/07 Fri 9/28/07 0%
266 Cold Cutting of pipes 48 hrs Fri 9/28/07 Sun 9/30/07 0%
267 Dismantling of old pipe 48 hrs Fri 9/28/07 Sun 9/30/07 0%
268 Erection of new pipe 48 hrs Sat 9/29/07 Mon 10/1/07 0%
269 Welding of new pipe 72 hrs Sun 9/30/07 Wed 10/3/07 0%
270 NDT 24 hrs Wed 10/3/07 Thu 10/4/07 0%
271 Hydrotest 24 hrs Thu 10/4/07 Fri 10/5/07 0%
272 Draining of water 24 hrs Fri 10/5/07 Sat 10/6/07 0%
273 Deblinding 12 hrs Sat 10/6/07 Sat 10/6/07 0%
274 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
275 3.5.1:RTF LINES(6",120 M) 11.83 days Wed 9/26/07 Mon 10/8/07 0%
276 Blinding / Deblinding 36 hrs Wed 9/26/07 Thu 9/27/07 0%
277 Steam & Water Washing 24 hrs Thu 9/27/07 Fri 9/28/07 0%
278 Final Blinding 12 hrs Fri 9/28/07 Sat 9/29/07 0%
279 Cold Cutting of pipes 48 hrs Sat 9/29/07 Mon 10/1/07 0%
280 Dismantling of old pipe 48 hrs Sat 9/29/07 Mon 10/1/07 0%
281 Erection of new pipe 48 hrs Sun 9/30/07 Tue 10/2/07 0%
282 Welding of new pipe 88 hrs Sun 9/30/07 Thu 10/4/07 0%
283 NDT 24 hrs Wed 10/3/07 Thu 10/4/07 0%
284 Hydrotest 24 hrs Thu 10/4/07 Fri 10/5/07 0%
285 Draining of water 24 hrs Fri 10/5/07 Sat 10/6/07 0%
286 Deblinding 12 hrs Sat 10/6/07 Sun 10/7/07 0%
287 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
288 3.7.2:SKO LINES(3",84M) 11.83 days Wed 9/26/07 Mon 10/8/07 0%
Page 9
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
S M T W T F S S M T W T F S S M T W
289 Blinding / Deblinding 36 hrs Wed 9/26/07 Thu 9/27/07 0%
290 Steam & Water Washing 24 hrs Thu 9/27/07 Fri 9/28/07 0%
291 Final Blinding 8 hrs Fri 9/28/07 Sat 9/29/07 0%
292 Cold Cutting of pipes 16 hrs Sat 9/29/07 Sat 9/29/07 0%
293 Dismantling of old pipe 8 hrs Sat 9/29/07 Sun 9/30/07 0%
294 Erection of new pipe 16 hrs Sun 9/30/07 Sun 9/30/07 0%
295 Welding of new pipe 24 hrs Sun 9/30/07 Mon 10/1/07 0%
296 NDT 12 hrs Mon 10/1/07 Tue 10/2/07 0%
297 Hydrotest 24 hrs Tue 10/2/07 Wed 10/3/07 0%
298 Draining of water 16 hrs Wed 10/3/07 Thu 10/4/07 0%
299 Deblinding 12 hrs Thu 10/4/07 Thu 10/4/07 0%
300 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
301 3.7.3:SKO LINES(6",60M) 11.83 days Wed 9/26/07 Mon 10/8/07 0%
302 Blinding / Deblinding 36 hrs Wed 9/26/07 Thu 9/27/07 0%
303 Steam & Water Washing 24 hrs Thu 9/27/07 Fri 9/28/07 0%
304 Final Blinding 12 hrs Fri 9/28/07 Sat 9/29/07 0%
305 Cold Cutting of pipes 24 hrs Sat 9/29/07 Sun 9/30/07 0%
306 Dismantling of old pipe 24 hrs Sat 9/29/07 Sun 9/30/07 0%
307 Erection of new pipe 24 hrs Sun 9/30/07 Mon 10/1/07 0%
308 Welding of new pipe 72 hrs Sun 9/30/07 Wed 10/3/07 0%
309 NDT 24 hrs Wed 10/3/07 Thu 10/4/07 0%
310 Hydrotest 24 hrs Thu 10/4/07 Fri 10/5/07 0%
311 Draining of water 24 hrs Fri 10/5/07 Sat 10/6/07 0%
312 Deblinding 12 hrs Sat 10/6/07 Sun 10/7/07 0%
313 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
314 3.8.1:HSD LINES(6",120 M) 11.83 days Wed 9/26/07 Mon 10/8/07 0%
315 Blinding / Deblinding 36 hrs Wed 9/26/07 Thu 9/27/07 0%
316 Steam & Water Washing 24 hrs Thu 9/27/07 Fri 9/28/07 0%
317 Final Blinding 12 hrs Fri 9/28/07 Sat 9/29/07 0%
318 Cold Cutting of pipes 48 hrs Sat 9/29/07 Mon 10/1/07 0%
319 Dismantling of old pipe 48 hrs Sat 9/29/07 Mon 10/1/07 0%
320 Erection of new pipe 48 hrs Sun 9/30/07 Tue 10/2/07 0%
Page 10
ID Task Name Duration Start Finish Sep 23, '07 Sep 30, '07 Oct 7, '07
S M T W T F S S M T W T F S S M T W
321 Welding of new pipe 88 hrs Sun 9/30/07 Thu 10/4/07 0%
322 NDT 24 hrs Wed 10/3/07 Thu 10/4/07 0%
323 Hydrotest 24 hrs Thu 10/4/07 Fri 10/5/07 0%
324 Draining of water 24 hrs Fri 10/5/07 Sat 10/6/07 0%
325 Deblinding 12 hrs Sat 10/6/07 Sun 10/7/07 0%
326 Start Up activities 24 hrs Sun 10/7/07 Mon 10/8/07 0%
Page 11
Activity Bar Chart of Refractory Application during Shutdown at P.G.Boiler at IOCL - HALDIA
Sr.No. Activity
No. of Days
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A R.G.Boiler
1 Dismantling & debris cleaning
2 Surface cleaning & anchor welding
3 End Tube Sheet Casting
4 First layer casting using form work
5 Second layer casting
6 Form work removal & natural curing
7 Dry out up to 250 deg C
8 Final Inspection & Boxing up