METALCRAFT INC
CASE STUDY CGN SUPPLY CHAIN MANAGEMENT
TARAB SYED AHMED DIVYA CHADHA SHUBHANGA PRASAD SAMIRA VEMPARALA TARUN VIR SINGH BANGA KUNAL SINGH AESHA MARU 2010A36 2010A60 2010B19 2010B32 2010B41 2010C43 2010C60
ABOUT THE COMPANY
Tier 1 supplier of automotive parts to large automakers 84 plants, 1 million incoming components per plant per day Financials 2001 - Revenue : USD 12.8 Billion Net Income : USD 30 million
Automakers
OEM After market
Tier 2 - Phillips
Convert raw materials into basic automotive components
Tier 1 - Metalcraft
Assemble component into modules
Tier 3 supply
raw materials
INDUSTRY & METALCRAFT
Sector - Market cap USD 39.2 billion Metalcraft Market cap USD 2.8 billion Major Industry Problem - Cost of defects Warranty costs total per vehicle > Average profit per vehicle Metalcrafts cost quality problems, delay in parts delivery, warranty costs Metalcraft Quality control - Scorecard
CASE SITUATION
Autoparts Inc
Electroparts Inc
Mark Mueller Commodity Purchasing Agent
Caltek Inc
Ellie Smith Quality Supervisor
Mark Letcher Corporate Supplier Development Manager Darell Bonds Product Engineer
Who - Rubber Vent Hose Vendor?
METALCRAFTS SOURCING PROCESS
What is right Considers Basic Cost, Weight and Performance targets of the product Prototype development capabilities Evaluation of Quotes based on: Cost Analysis Tooling Analysis Capacity Requirements Program Timing Constraints What more? Financial Health Transparency of finances Expertise Investments in R&D Operational Effectiveness in terms of: Responsiveness Inclusion of TQC, 6, JIT Customer Service Index
QUALITY CONTROL PROCESS
1 2 3 4 5 Determination of Physical & Performance Characteristics Determination of method to evaluate these characteristics Preparation of Control Plan Review & Approve Control Plan Quality Checks & Recording Results on Control Chart
QUALITY RATING SYSTEM
PPM Performance
QR Performance
Significant Quality Event
Quality System Status
QOS/BOS Status
PPAP Level
PPAP Slippage
METALCRAFTS SUPPLIER SCORECARD
WHY
To be successful Tier 1 automotive components supplier Zero Defect Rate Single, worldwide reference point on Supplier performance OPERATIONS OF SUPPLIER SCORECARD
INPUTS
Electronic Orders from EDI system Contact Information Quality System Information
HOW
Rating suppliers on three dimensions Quality Timing Delivery Continuous evaluation of supplier performance Not based on single audits
PROCESS
Calculates PPM and Trendline Calculates Supplier Quality Ratings Calculates PSW Slippage
OUTPUTS
Consolidated Contact Information Quality and Delivery Results by Individual Plants Sourcing Recommendation
SUPPLIER SCORECARD
Quality
Overall Quality Rating
F (different aspects of quality & performance)
Timing
Meeting Timelines
For certification of new components
Delivery
Delay in Deliveries induces
Rescheduling Costs Overtime Production Costs Expidited delivery costs
Launch Quality Rejects
Problems reported in the production startup phase Separated launch problems from normal production
PPAP
Important to ensure Low volume and High volume products meet requirements
New parts meeting all specifications
Delivery Performance Rating
Supplier Communication system Up to Schedule Shipping Problem resolution and prevention Overshipment Record Maintenance Other Performance
Defect Rates
Measured in PPM Classified fit or function rejects
PSW
Components can be used on vehicles for sale
USE OF SCORECARD
Buyers Supplier selection responsibility Cost and quality implications Limited information sourcing Scorecard Objective metrics, constricted supplier base Plant Quality Engineers Ensures high quality and defect free parts Indentify recurring defects from historical data Address QRs across all plants Identify and directly contact problem suppliers SD engineers Technical assistance to suppliers Helped evaluate and identify attention areas Learnt about problems after significant Suppliers Helped guide internal movement Monitor health of relationship with Metalcraft Strengthen competitive position
PROBLEM: WHICH SUPPLIER TO SELECT?
Solution
[A] Standardize Scorecard:
1. Correct Metrics 2. Metrics accurately reflecting information [B] Use of Scorecard by all stakeholders (Product engineer)
PROPOSALS
1 2
Scorecard should have detailed data & query functions Data by product line Updation of performance rating should be done statistically Negotiation should have no role
Reduce incentive for buyer to buy at lowest cost Define minimum level of quality and increase incentive for same
Which supplier is better ? (Outlier)
4 Standardize strategy for one time spike Exclude one-time event (but capture in notes)
Variation in PPM
5
Exhibit 5: Huge variation in PPM Keep standards constants for reasonable time
Metalcraft Supplier Scorecard - Summary
CALTEK INC
Dec 2000 Total PPM Parts Received (000) 640 Jan 2001 5165 Feb 2001 409 Mar 2001 1 Apr 2001 696 May 2001 3 Jun 2001 1100 Jul 2001 208 Aug 2001 77 Sep 2001 1 Oct 2001 1328 Nov 2001 355
42628 55092 61751 67496 62243 66158 45859 46704 66487 41958 56535 56021
QRS Points
6
Continuous Basis for QRS Points
Quality Performance Data PPM Performance 0 1 to 60 61 to 200 201 to 500 > 500
Points 25 20 to 15 15 to 10 10 to 0 0
Restructuring Scorecard
Cost Analysis Tooling Analysis Capacity Requirements Program Timing Constraints Quality Performance Delivery Performance Lowest Landed Cost Currency Impact Productivity History Long Term Agreement Hard Tooling cost Soft Tooling Cost
Buyer Sourcing Team Product Engineer
Supplier Development Engineer
Manufacturing Plant Representative
DECISION
CALTEK WHY?
Risk Associated For Mark with the decision
Less Critical Component Only Visual Quality Check Price offered is low Not much impact on his incentives
Scorecard - not fully reliable
Huge fluctuation in PPM values Plant rated red even though it has 0 defects in the last 11 months Once identified, Company is improving the metrics
Design Capability
Industry shifting to High end Products Future Partnership Prospects
Supplier Relationship Management Stages
Vendors as partners Check the Quality and try to improve the vendors
Contractual Relationship
THANK YOU
TARAB SYED AHMED 2010A36
DIVYA CHADHA
SHUBHANGA PRASAD SAMIRA VEMPARALA TARUN VIR SINGH BANGA KUNAL SINGH AESHA MARU
2010A60