Feasibility Study Example

Download as pdf or txt
Download as pdf or txt
You are on page 1of 17

Sample Feasibility Study

XYZ Company
Widget Part Design

Prepared For:
XYZ Company
1234 Anywhere Street
Any Town, State 12345-6789

Prepared By:
Some Engineer
Plastics Technology Center
Penn State Erie, The Behrend College
Erie, PA 16511-1088
Table of Contents

Section Page Number

Objective ...................................................................................................... 2

Executive Summary ........................................................................................ 2

Table 1.1: Part Information .......................................................................... 2


Table 1.2: Tooling and Purchased Part Cost Estimates ........................................ 3
Chart 1.1: Part Cost vs. Production Volume ...................................................... 3

Tooling and Part Cost Estimations ....................................................................... 4

Design and Manufacturing Recommendations ........................................................ 5

APPENDIX

Section Page Number

I. Part Cost Estimate Information

Part Cost Estimates: Mold Type I..................................................... I.II


Part Cost Estimates: Mold Type II.................................................... I.III
Part Cost Estimates: Mold Type III................................................... I.IV
Part Cost vs. Production Volume...................................................... I.V

II. Processing Information

Sure Shot Results ........................................................................ II.II

1
OBJECTIVE

The objective of this project was to determine the feasibility of manufacturing a plastic
widget. All required information to conduct the study was supplied by XYZ Company. This
information included the following:

• Part drawings or sketches


• Description of part application and requirements
• Production information
• Miscellaneous information as requested

EXECUTIVE SUMMARY

Given the part design and requirements, the manufacturing materials and process were
selected (see Table 1.1). The parts were determined to be injection molded from a general-
purpose polypropylene material. After selecting the process and material, there were then
several types of molds selected to manufacture the parts. The mold types are as follows:

1. Single Cavity, Center Sprue gate, (SC, CSG)


2. Single Cavity, Hot Runner Edge gated, Fan or Multiple Tab gates (SC, HREG)
3. Two Cavity, Hot Runner Edge gated, Fan or Multiple Tab gates (TC, HREG)

Table 1.1: Part Information


Annual Volume: 10, 25, 50, 75, and 100,000

Part Geometry: Per print

Estimated Part Volume: 579.9 cm3

Manufacturing Process: Injection Molding

Suggested Material: General Purpose Polypropylene

Part Requirements: Flatness

Target Tool Costs: $50,000 - $75,000

Target Part Costs: $5.00

2
After determining the molding process and material estimates, tooling and parts costs could
then be calculated. The cost estimates for the various tools and production volumes
mentioned previously can be found in the following table.

Table 1.2: Tooling and Purchased Cost Estimates


Part Costs

Type of Tool Est. Tool Cost 10,000 25,000 50,000 75,000 100,000

SC, CSG $49,000 $4.74 $3.80 $3.49 $3.38 $3.33

SC, HREG $68,000 $4.22 $2.97 $2.56 $2.42 $2.35

TC, HREG $65,000 $5.34 $4.04 $3.61 $3.46 $3.39

To provide additional information showing the influence of production volume on part cost,
refer to Chart 1.1: Part Cost versus Production Volume.

Chart 1.1: Part Cost Versus Production Volume

$5.50
$5.50

$5.00
$5.00
Part Cost ($/part)

$4.50
Part Cost ($/part)

$4.50

$4.00
$4.00

$3.50
$3.50

$3.00
$3.00

$2.50
$2.50

$2.00
$2.00
10,000 25,000 50,000 75,000 100,000
10,000 25,000 50,000 75,000 100,000

Production Volume (parts / year)


Production Volume (parts / year)

3
From Table 1.2 and Chart 1.1 it can be seen that the two-cavity tool produces the lowest
cost parts with a medium range part cost. However, all part cost estimates except the SC,
HREG at 10,000 parts per year fall within the targeted part cost range. These estimates
appear to be in the targeted range for both tool and part costs. The decision on which tool
to select can not be made at this time; we recommend a 3D mold filling analysis be
performed to determine the best gating location given the part geometry.

Based upon these estimates, the PTC recommends that this is a feasible plastic part design,
providing any additional costs such as packaging, decorating, assembly, etc. do not cause
the part cost to exceed the $5.00 target cost. For this study, the aforementioned costs were
not estimated per XYZ Company’s request. Copies of the spreadsheets showing the part
cost estimates can be found in the Appendix.

Tooling and Part Cost Estimations

The tooling cost estimations discussed earlier are based upon discussions between the PTC
and a local toolmaker. These ballpark figures are to be used for estimations only. The part
cost estimates have been calculated using a spreadsheet developed by the PTC. These
spreadsheets use estimations for tool costs, cycle time, material costs, and machine costs
(refer to the Appendix). When reviewing these spreadsheets, it can be seen that there are
many inputs that are used to estimate the part cost. Since most of the inputs are estimated,
the spreadsheets provide what is referred to as a “ ballpark” figure for the calculated part
cost.

The costs listed in the previous tables and graphs reflect what is referred to as the
purchased part cost. This would be an estimate of what XYZ Company could expect to pay
per part if they were to purchase the molded parts from an injection molder. The costs for
each production volume are highlighted in pink and include the cost of the tool amortized at
10% over 5 years with a 5% scrap rate. If XYZ Company were to manufacture these parts
in-house, the cost of the parts including the amortization over 5 years at 10% interest with a
5% scrap rate is shown highlighted in yellow. Once again these costs are calculated from
estimates and are “ballpark” figures only. Material and machine costs were taken as
averages from the December issues of Plastic News and Injection Molding Magazine. The
material costs found in Plastics News were for high volume production purchases and are
therefore inflated from $0.70 / lb to $1.00 / lb to reflect the lower volume of material
purchased. The machine rate is inflated to cover any hourly rates for operators which may
be required. When estimating these figures, conservative values are used to provide a slight
over-estimate to cover any unexpected costs which may arise later.

4
Design and Manufacturing Recommendations

From the blueprints and drawings it appears that there is uniform wall thickness throughout
the part. This uniform thickness is recommended to ensure a good plastic part. Due to the
ribbing on the part, there is a possibility for warpage. We recommend reducing the
thickness of the ribs to approximately half that of the nominal wall. This will prevent some
of the warpage and other cosmetic defects that could occur otherwise.

As mentioned earlier, we are recommending that these parts be injection molded from a
polypropylene material. We feel that this process and material will provide XYZ Company
with plastic widgets that meet all criteria for both cost and performance. Also, we
recommend that a 3D filling analysis be performed on this design. This is recommended
because it will assist in identifying potential problems in the molding process and allow the
PTC to vary gate location, process conditions, and/or geometry to predict problems and
determine solutions. A filling analysis will allow the PTC to make these changes before the
tool is cut and will reduce potential costs associated with reworking a tool.

Some recommendations on processing parameters can be found in Appendix II of this


report. Using some of the general part and material information, a 2D filling analysis
program, Sureshot, was used to determine the range for both melt temperature and
injection time.

5
Appendix I

Part Cost Estimate Information


PTC Part Cost Estimation
Date: July 23, 1997

PART INFORMATION: MOLD INFORMATION:


Project: XYZ Company No. of Cavities: 2
Part Name: Widget Estimated Cost: $65,000.00
Projected Area (in2): 0.00
Volume (cm3): 579.90
Mass (g): 579.90
3
Runner Volume (cm ): 0

MATERIAL INFORMATION: FINANCING INFORMATION:


Resin: PP Amortization (yrs): 5
Grade: General Purpose Int Rate (%/y r): 10
Cost ($/lb): $0.70 Man markup (%): 25
3
Spec Gravity (g/cm ): 1

PRODUCTION INFORMATION: SECONDARY OPERATIONS:


Min Press Size (tons): 0 Printing ($/prt): $0.00
Cycle Time (s): 45 Assembly ($/prt): $0.00
Machine Rate ($/hr): $125.00 Packaging ($/prt): $0.00
Scrap Rate (%): 5% Misc ($/prt): $0.00
Hourly Prod (parts/hr): 152

ANNUAL VOLUMES: PARTS/YEAR


Volume 1: 10,000 AMORTIZATION CALCULATIONS:
Volume 2: 25,000 i= 0.0083333
Volume 3: 50,000 n= 60
Volume 4: 75,000 A/P= 0.0212470
Volume 5: 100,000

COST ESTIMATION CALCULATIONS:


Material Costs: $0.89
Production Costs: $0.82
Secondary Costs: $0.00
Man Cost (without tool) $1.72
Purch Cost (without tool) $2.15

COST CALCULATIONS:
Production Volumes 10,000 25,000 50,000 75,000 100,000
Mold Cost: $1.66 $0.66 $0.33 $0.22 $0.17
Manufactured Cost: $3.37 $2.38 $2.05 $1.94 $1.88
Purchased Cost: $4.22 $2.97 $2.56 $2.42 $2.35

I-II
PTC Part Cost Estimation
Date: July 23, 1997

PART INFORMATION: MOLD INFORMATION:


Project: XYZ Company No. of Cavities: 1
Part Name: Widget Estimated Cost: $49,000.00
Projected Area (in2): 0.00
Volume (cm3): 579.90
Mass (g): 579.90
3
Runner Volume (cm ): 0

MATERIAL INFORMATION: FINANCING INFORMATION:


Resin: PP Amortization (yrs): 5
Grade: General Purpose Int Rate (%/yr): 10
Cost ($/lb): $0.70 Man markup (%): 25
3
Spec Gravity (g/cm ): 1

PRODUCTION INFORMATION: SECONDARY OPERATIONS:


Min Press Size (tons): 0 Printing ($/prt): $0.00
Cycle Time (s): 45 Assembly ($/prt): $0.00
Machine Rate ($/hr): $125.00 Packaging ($/prt): $0.00
Scrap Rate (%): 5% Misc ($/prt): $0.00
Hourly Prod (parts/hr): 76

ANNUAL VOLUMES: PARTS/YEAR


Volume 1: 10,000 AMORTIZATION CALCULATIONS:
Volume 2: 25,000 i= 0.0083333
Volume 3: 50,000 n= 60
Volume 4: 75,000 A/P= 0.0212470
Volume 5: 100,000

COST ESTIMATION CALCULATIONS:


Material Costs: $0.89
Production Costs: $1.64
Secondary Costs: $0.00
Man Cost (without tool) $2.54
Purch Cost (without tool) $3.17

COST CALCULATIONS:
Production Volumes 10,000 25,000 50,000 75,000 100,000
Mold Cost: $1.25 $0.50 $0.25 $0.17 $0.12
Manufactured Cost: $3.79 $3.04 $2.79 $2.71 $2.66
Purchased Cost: $4.74 $3.80 $3.49 $3.38 $3.33

I-III
PTC Part Cost Estimation
Date: July 23, 1997

PART INFORMATION: MOLD INFORMATION:


Project: XYZ Company No. of Cavities: 1
Part Name: Widget Estimated Cost: $68,000.00
Projected Area (in2): 0.00
Volume (cm3): 579.90
Mass (g): 579.90
3
Runner Volume (cm ): 0

MATERIAL INFORMATION: FINANCING INFORMATION:


Resin: PP Amortization (yrs): 5
Grade: General Purpose Int Rate (%/yr): 10
Cost ($/lb): $0.70 Man markup (%): 25
3
Spec Gravity (g/cm ): 1

PRODUCTION INFORMATION: SECONDARY OPERATIONS:


Min Press Size (tons): 0 Printing ($/prt): $0.00
Cycle Time (s): 45 Assembly ($/prt): $0.00
Machine Rate ($/hr): $125.00 Packaging ($/prt): $0.00
Scrap Rate (%): 5% Misc ($/prt): $0.00
Hourly Prod (parts/hr): 76

ANNUAL VOLUMES: PARTS/YEAR


Volume 1: 10,000 AMORTIZATION CALCULATIONS:
Volume 2: 25,000 i= 0.0083333
Volume 3: 50,000 n= 60
Volume 4: 75,000 A/P= 0.0212470
Volume 5: 100,000

COST ESTIMATION CALCULATIONS:


Material Costs: $0.89
Production Costs: $1.64
Secondary Costs: $0.00
Man Cost (without tool) $2.54
Purch Cost (without tool) $3.17

COST CALCULATIONS:
Production Volumes 10,000 25,000 50,000 75,000 100,000
Mold Cost: $1.73 $0.69 $0.35 $0.23 $0.17
Manufactured Cost: $4.27 $3.23 $2.89 $2.77 $2.71
Purchased Cost: $5.34 $4.04 $3.61 $3.46 $3.39

I-IV
Part Cost vs. Production Volume
Part Cost vs. Production Volume
$5.50
$5.50

$5.00
$5.00
Part Cost ($/part)

$4.50
Part Cost ($/part)

$4.50

$4.00
$4.00

$3.50
$3.50

$3.00
$3.00

$2.50
$2.50

$2.00
$2.00
10,000 25,000 50,000 75,000 100,000
10,000 25,000 50,000 75,000 100,000

Production Volume (parts / year)


Production Volume (parts / year)

I-V
Appendix II

Sure Shot Results


A Sure-Shot Moldability Assessment for:
XYZ Company – Widget Part – Center Gated

Processing Recommendations:
The area between the two injection time lines represents the acceptable set of molding
conditions for all melt temperatures shown.

• Injection pressures for the cavity are less than 10,150 psi.
• Shear stresses at the gate and end of flow are less than 36 psi.
• The melt temperature drop during filling is less than 36° F.

Recommended Processing Conditions for XYZ Company – Widget Part – Center Gated made
with PP and a mold temperature of 68° F are:

• Melt temperature between 392° F and 500° F

At the center of the melt temperature range (rounded up), the injection time range is
between 2.15 and 4.98 seconds.

The allowable injection time range is 2.84 seconds. This should not be cause for concern.
Examine other recommendations to decide if further work is indicated.

Filling Pattern:
It is important to determine if filling will be balanced because unbalanced filling will result in
higher filling pressures, clamp pressures, and higher shear rates. Estimate if the fill pattern
is balanced by comparing distances from the gate to all extremities of the part. This
technique will work well if the wall thickness is relatively uniform along the various flow
paths.

Hesitation Concerns:
This part should fill smoothly as the pattern will not be significantly influenced by variations
in wall thickness. 3D filling analysis will not be required to avoid hesitations.

Gas Traps:
Study the product design to see if there is a possibility that plastic melt will split during fill
and re-unite somewhere that could cause venting problems. If there is a possibility, such as
a grille section, you should consider running a 3D filling analysis.

Visual Concerns:
The lack of visual requirements makes it less necessary to run filling analysis unless it is
recommended for some other reason.

II-II
Processing
ProcessingWindow
Windowfor:
for:
PP
PP Mold Temperature 68deg.
Mold Temperature 68 deg.FF

8
8
Injection Time (seconds)

7
Injection Time (seconds)

7
6
6
5
5
4
4
3
3
2
2
1
1
0
0
392 410 428 446 464 482 500
392 410 428 446 464 482 500
Melt Temperature (deg. F)
Melt Temperature (deg. F)

II-III
A Sure-Shot Moldability Assessment for:
XYZ Company – Widget Part – Edge Gated

Processing Recommendations:
The area between the two injection time lines represents the acceptable set of molding
conditions for all melt temperatures shown.

• Injection pressures for the cavity are less than 10,150 psi.
• Shear stresses at the gate and end of flow are less than 36 psi.
• The melt temperature drop during filling is less than 36° F

Recommended Processing Conditions for XYZ Company – Widget Part – Edge Gated made
with PP and a mold temperature of 68° F are:

• Melt temperature between 428° F and 500° F

At the center of the melt temperature range (rounded up), the injection time range is
between 3.72 and 6.56 seconds.

The allowable injection time range is 2.84 seconds. This should not be cause for concern.
Examine other recommendations to decide if further work is indicated.

Number of Cavities:
Every multiple cavity mold can benefit from the design of a balanced runner system. It is
highly recommended that flow balancing be used to avoid excessive material usage and to
assure that melt conditions entering the cavity are correct for the part. If the runner system
is not naturally balanced, the need for a flow balanced system is even greater.

Number of Gates:
You can use Moldability Assessments to determine the viability of a single gate. If the
assessment recommendations are not favorable, you might want to try a model representing
multiple gates.

Filling Pattern:
It is important to determine if filling will be balanced because unbalanced filling will result in
higher filling pressures, clamp pressures, and higher shear rates. Estimate if the fill pattern
is balanced by comparing distances from the gate to all extremities of the part. This
technique will work well if the wall thickness is relatively uniform along the various flow
paths.

II-IV
Filling Pattern:
A 3D filling analysis is always recommended for multiple gated parts unless you are very sure
that the gates are well balanced. You should also be sure to design a balanced runner
system. A balanced runner system provides plastic melt to the gates at the proper
temperature and pressure to fill the part as it was planned for this moldability assessment.
Balancing the runner system will also provide a check of shear rates and cooling times for
the sprue and runner system. If runners are too small, you may over shear the material.
Large runner diameters may lengthen the cycle time required for the mold.

Hesitation Concerns:
This part should fill smoothly as the pattern will not be significantly influenced by variations
in wall thickness. 3D filling analysis will not be required to avoid hesitations.

Gas Traps:
Study the product design to see if there is a possibility that plastic melt will split during fill
and re-unite somewhere that could cause venting problems. If there is a possibility, such as
a grille section, you should consider running a 3D filling analysis.

Visual Concerns:
The lack of visual requirements makes it less necessary to run filling analysis unless it is
recommended for some other reason.

II-V
Processing
ProcessingWindow
Windowfor:
for:
PP
PP Mold Temperature 68 deg.F.F.
Mold Temperature 68 deg.
15
15
13.5
13.5
Injection Time (seconds)
Injection Time (seconds)

12
12
10.5
10.5
9
9
7.5
7.5
6
6
4.5
4.5
3
3
1.5
1.5
0
0
428 446 464 482 500
428 446 464 482 500
Melt Temperature (deg. F)
Melt Temperature (deg. F)

II-VI

You might also like