This document contains Jeffrey Panen's weekly time log over 6 weeks. It tracks the number of hours he spent on various projects each day, including tasks like HVAC calculations and equipment schedules. It shows his total regular hours, overtime hours, and miscellaneous overhead hours each week. The time log is reviewed and approved by his lead engineer and other managers.

Uploaded by

Jeffrey Panen
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
104 views

Weekly Time Log: This Form To Be Submitted To Time Keeper Every Sat by 9:OO Am

This document contains Jeffrey Panen's weekly time log over 6 weeks. It tracks the number of hours he spent on various projects each day, including tasks like HVAC calculations and equipment schedules. It shows his total regular hours, overtime hours, and miscellaneous overhead hours each week. The time log is reviewed and approved by his lead engineer and other managers.

Uploaded by

Jeffrey Panen
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 6

WEEKLY TIME LOG

WEEK NO. : 21 FROM P.O. / P.P. / SASEC CODE # : 21-May-11 TO : 27-May-11 BRIEF WORK DESCRIPTION / SASEC CODE DESCRIPTION

EMPLOYEE NAME : EMP. NO. DISCIPLINE : :

JUAN DELA CRUZ 37917 Sr. Engineer CLASSIFICATION : DEPARTMENT TOTAL : MECHANICAL

21
SAT

22
SUN

23
MON

24
TUE

25
WED

26
THU

27
FRI

Accepted By : LEAD ENGINEER

PO - 103 PACKAGE 1 TO 3 COMPLETED ISO EA-XXXXX (DE) ONGOING ISOS EA-XXXXX (DE), EA-XXXX PO - 103-4 (L A C ) PREPARE PIPING LAYOUT EA-XXXX (BE) DRAWING SEARCH PREPARE DATA SHEET PUMP EA-XXXX(BE) PREPARE SOW, EA-XXXXX (BE) PO - 128 (RAH WASH WATER SYS) SITE VISIT / DRAWING SEARCH STARTED PIPING PLAN EA-XXXXX (BE) STARTED ISO EA-XXXXX (DE) M/O PRINTING DOCUMENTS / MADE FORM BACKDRAFTING - EAXXXXX

0.0 13.0

10.0

3.0 3.0 4.0 4.0 2.0 2.0 6.0 4.0 4.0 2.0 3.0 5.0

8.0 4.0 4.0 2.0 2.0 6.0 4.0 4.0 5.0 0.0 0.0 0.0

TOTAL STRAIGHT TIME :

48

TOTAL OT:

TOTAL M/O:

10.0

10.0

10.0

10.0

8.0

4.0

0.0

52.0 APPROVED BY:

* This form to be submitted to Time keeper every Sat by 9:OO am

N O T E D B Y:
ENGINEERING DIRECTOR : NAME : : : V.P. & OPERATION DIRECTOR NAME SIGNATURE DATE : : : NAME SIGNATURE DATE

PRESIDENT & GENERAL MANAGER : : :

SIGNATURE OF EMPLOYEE DATE :

SIGNATURE DATE

MO - Miscellaneous Overhead BE - Base Design DE - Defailed Engineering

Timekeeper shall input hours to Project Weekly Expended Manhour Report

WEEKLY TIME LOG


WEEK NO. : FROM P.O. / P.P. / SASEC CODE # P.O. 3-PACK.4 P.O. 3-PACK.2 P.O. 128 : WEEK 22 28-May-11 TO : 3-Jun-11 BRIEF WORK DESCRIPTION / SASEC CODE DESCRIPTION HVAC (CALCULATION; EQUIPMENT SCHEDULE) SERVICE TEST PROCEDURE (STEAM, SEAL AND ASPIRATING LINE) BOILER WASH WATER

EMPLOYEE NAME : EMP. NO. DISCIPLINE : :

JEFFREY PANEN 37920 MECHANICAL CLASSIFICATION : DEPARTMENT TOTAL : MECHANICAL

28
SAT

29
SUN

30
MON

31
TUE

1
WED

2
THU

3
FRI

Accepted By : LEAD ENGINEER

1.5

3.0 4.5

5.0 7.0

4.0 6.0 2.0

7.0

6.0

26.5 17.5 2.0 0.0 0.0 0.0

SASEC-001

MEDICAL CHECK UP ELITE INSTALLATION (HVAC APPLICATION) WEEKLY TIME LOG PREPARATION PROGRESS MEETING

8.0

2.0

1.0 1.5

11.0 1.5 1.0 0.5 0.0 0.0 0.0 0.0

0.5 0.5

0.5

TOTAL STRAIGHT TIME :

48

TOTAL OT:

12

TOTAL M/O:

14

10.0

10.0

12.0

12.0

8.0

8.0

0.0

60.0 APPROVED BY:

* This form to be submitted to Time keeper every Sat by 9:OO am

N O T E D B Y:
ENGINEERING DIRECTOR : NAME : : : V.P. & OPERATION DIRECTOR NAME SIGNATURE DATE : : : NAME SIGNATURE DATE

PRESIDENT & GENERAL MANAGER : : :

SIGNATURE OF EMPLOYEE DATE :

SIGNATURE DATE

MO - Miscellaneous Overhead BE - Base Design DE - Defailed Engineering

Timekeeper shall input hours to Project Weekly Expended Manhour Report

WEEKLY TIME LOG


WEEK NO. : FROM P.O. / P.P. / SASEC CODE # P.O. 3-PACK.4 : WEEK 23 4-Jun-11 TO : 10-Jun-11 BRIEF WORK DESCRIPTION / SASEC CODE DESCRIPTION HVAC (CALCULATION; EQUIPMENT SCHEDULE; LAY-OUT)

EMPLOYEE NAME : EMP. NO. DISCIPLINE : :

JEFFREY PANEN 37920 MECHANICAL CLASSIFICATION : DEPARTMENT TOTAL : MECHANICAL

4
SAT

5
SUN

6
MON

7
TUE

8
WED

9
THU

10
FRI

Accepted By : LEAD ENGINEER

11.5

10.0

10.0

10.0

8.0

8.0

8.0

65.5 0.0 0.0 0.0 0.0 0.0

SASEC-001

WEEKLY TIME LOG PREPARATION

0.5

0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0

TOTAL STRAIGHT TIME :

48

TOTAL OT:

18

TOTAL M/O:

0.5

12.0

10.0

10.0

10.0

8.0

8.0

8.0

66.0 APPROVED BY:

* This form to be submitted to Time keeper every Sat by 9:OO am

N O T E D B Y:
ENGINEERING DIRECTOR : NAME : : : V.P. & OPERATION DIRECTOR NAME SIGNATURE DATE : : : NAME SIGNATURE DATE

PRESIDENT & GENERAL MANAGER : : :

SIGNATURE OF EMPLOYEE DATE :

SIGNATURE DATE

MO - Miscellaneous Overhead BE - Base Design DE - Defailed Engineering

Timekeeper shall input hours to Project Weekly Expended Manhour Report

WEEKLY TIME LOG


WEEK NO. : FROM P.O. / P.P. / SASEC CODE # P.O. 3-PACK.4 : WEEK 24 11-Jun-11 TO : 17-Jun-11 BRIEF WORK DESCRIPTION / SASEC CODE DESCRIPTION HVAC (CALCULATION; EQUIPMENT SCHEDULE; LAY-OUT)

EMPLOYEE NAME : EMP. NO. DISCIPLINE : :

JEFFREY PANEN 37920 MECHANICAL CLASSIFICATION : DEPARTMENT TOTAL : MECHANICAL

11
SAT

12
SUN

13
MON

14
TUE

15
WED

16
THU

17
FRI

Accepted By : LEAD ENGINEER

9.5

10.0

13.0

12.0

9.5

8.0

8.0

70.0 0.0 0.0 0.0 0.0 0.0

SASEC-001 SASEC-008 SASEC-001

WEEKLY TIME LOG PREPARATION DRIVER LICENSE APPLICATION PROGRESS MEETING

0.5 1.0 0.5

0.5 1.0 0.5 0.0 0.0 0.0 0.0 0.0

TOTAL STRAIGHT TIME :

48

TOTAL OT:

24.0

TOTAL M/O:

10.0

10.0

13.0

13.0

10.0

8.0

8.0

72.0 APPROVED BY:

* This form to be submitted to Time keeper every Sat by 9:OO am

N O T E D B Y:
ENGINEERING DIRECTOR : NAME : : : V.P. & OPERATION DIRECTOR NAME SIGNATURE DATE : : : NAME SIGNATURE DATE

PRESIDENT & GENERAL MANAGER : : :

SIGNATURE OF EMPLOYEE DATE :

SIGNATURE DATE

MO - Miscellaneous Overhead BE - Base Design DE - Defailed Engineering

Timekeeper shall input hours to Project Weekly Expended Manhour Report

WEEKLY TIME LOG


WEEK NO. : FROM P.O. / P.P. / SASEC CODE # P.O. 3-PACK.4 SASEC-001 : WEEK 25 18-Jun-11 TO : 24-Jun-11 BRIEF WORK DESCRIPTION / SASEC CODE DESCRIPTION HVAC (CALCULATION; EQUIPMENT SCHEDULE; LAY-OUT) ORIENTATION FOR SITE/FIELD ASSIGNMENT

EMPLOYEE NAME : EMP. NO. DISCIPLINE : :

JEFFREY PANEN 37920 MECHANICAL CLASSIFICATION : DEPARTMENT TOTAL : MECHANICAL

18
SAT

19
SUN

20
MON

21
TUE

22
WED

23
THU

24
FRI

Accepted By : LEAD ENGINEER

7.0

2.0 8.0

2.0 8.0 9.0 8.0

11.0 33.0 0.0 0.0 0.0 0.0

SASEC-001 SASEC-001 SASEC-001

Pipe Support Limited (Seminar/product Orientation) WEEKLY TIME LOG PREPARATION Driving Test

1.0 0.5 1.5

1.0 0.5 1.5 0.0 0.0 0.0 0.0 0.0

TOTAL STRAIGHT TIME :

48

TOTAL OT:

0.0

TOTAL M/O:

36

9.0

10.0

10.0

10.0

8.0

0.0

0.0

47.0 APPROVED BY:

* This form to be submitted to Time keeper every Sat by 9:OO am

N O T E D B Y:
ENGINEERING DIRECTOR : NAME : : : V.P. & OPERATION DIRECTOR NAME SIGNATURE DATE : : : NAME SIGNATURE DATE

PRESIDENT & GENERAL MANAGER : : :

SIGNATURE OF EMPLOYEE DATE :

SIGNATURE DATE

WEEKLY TIME LOG


WEEK NO. : FROM P.O. / P.P. / SASEC CODE # P.O. 3-PACK.4 : WEEK 26 25-Jun-11 TO : 1-Jul-11 BRIEF WORK DESCRIPTION / SASEC CODE DESCRIPTION ORIENTATION FOR SITE/FIELD ASSIGNMENT

EMPLOYEE NAME : EMP. NO. DISCIPLINE : :

JEFFREY PANEN 37920 MECHANICAL CLASSIFICATION : DEPARTMENT TOTAL : MECHANICAL

25
SAT

26
SUN

27
MON

28
TUE

29
WED

30
THU

1
FRI

Accepted By : LEAD ENGINEER

9.5

9.5 0.0 0.0 0.0 0.0 0.0

SASEC-001

WEEKLY TIME LOG PREPARATION

0.5

0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0

TOTAL STRAIGHT TIME :

48

TOTAL OT:

0.0

TOTAL M/O:

1.5

10.0

0.0

0.0

0.0

0.0

0.0

0.0

10.0 APPROVED BY:

* This form to be submitted to Time keeper every Sat by 9:OO am

N O T E D B Y:
ENGINEERING DIRECTOR : NAME : : : V.P. & OPERATION DIRECTOR NAME SIGNATURE DATE : : : NAME SIGNATURE DATE

PRESIDENT & GENERAL MANAGER : : :

SIGNATURE OF EMPLOYEE DATE :

SIGNATURE DATE

MO - Miscellaneous Overhead BE - Base Design DE - Defailed Engineering

Timekeeper shall input hours to Project Weekly Expended Manhour Report

You might also like