Guidance Asphalt Paving Operations April 2011
Guidance Asphalt Paving Operations April 2011
Guidance Asphalt Paving Operations April 2011
for Asphalt
Paving Operations
Paver
Finished
surface
course
10–15 cm
GUIDELINES
Guidance for Asphalt Paving Operations
1 Preparation of sub-base .......................................................2
Granular base course ....................................................................2
Bound base course ........................................................................2
2 Orders and release orders for asphalt-mix ....................6
Ordering the asphalt-mix ..............................................................6
Release orders for paving operations..............................................7
3 Mix Transport ..........................................................................8
4 Mix inspection prior to paving operations..........................10
Measuring the mix temperature ..................................................10
Visual inspection of the mix ........................................................11
Flawless mix ..............................................................................11
Excessive cooling of mix ............................................................12
Overheated mix ........................................................................12
How to proceed with mixes that failed the visual inspection ........13
Excessive cooling of mix ............................................................13
Overheated mix ........................................................................13
5 Paving ......................................................................................14
Getting started ............................................................................14
Guidance for paving operations ..................................................16
Tests during paving operations ....................................................17
Manual placement ......................................................................18
Cold weather paving....................................................................19
Paving during wet weather ..........................................................19
6 Compaction of the mix ........................................................20
Guidance for compaction ............................................................20
Getting the rollers ready ..............................................................22
Roller passes ................................................................................23
Guidance for asphalt mix compaction ..........................................23
Compaction mistakes ..................................................................26
7 Skid Resistance.......................................................................28
Paving and compaction process ....................................................28
Guidance ....................................................................................28
8 Design specific guidance ..........................................................29
Compact Asphalt ......................................................................29
Planning the job ........................................................................29
Planning paving operations........................................................29
During paving operations ..........................................................30
8 Design specific guidance…
Porous Asphalt ..........................................................................30
Planning the job ........................................................................30
Planning paving operations........................................................31
During paving operations ..........................................................31
Warm mix asphalt ....................................................................32
Planning the job ........................................................................32
Planning paving operations........................................................32
During paving operations ..........................................................32
Light-colored surface courses ..................................................33
Railway track beds ....................................................................33
Hydraulic applications and landfill construction ....................33
Anti-icing surfaces ....................................................................34
Colored pavements ..................................................................34
9 Joints ........................................................................................35
Guidance ....................................................................................35
Longitudinal joints ......................................................................35
“Hot to hot” technique ............................................................35
“Hot to cold” technique............................................................36
Transverse joints ..........................................................................38
Material finishing/shaping ............................................................40
10 Gap joints ................................................................................41
Guidance ....................................................................................41
Joint faces....................................................................................41
Filling the sealant reservoir ..........................................................41
Application of sealant ................................................................42
Sealing strips ............................................................................42
Application of sealing strips ......................................................43
11 Road Edges..............................................................................44
12 Taking samples to verify quality features..............................46
Sampling......................................................................................46
Documentation ............................................................................47
Guidance ....................................................................................47
Annex
Additional information about the German Asphalt Pavement
Association (DAV) and further DAV-Guidelines ............................48
Publisher
Author
Bau-Ing. Roland Milster, Regensburg
in cperation with:
Dipl.-Ing. (FH) Walter Emperhoff,
Regensburg;
Dipl.-Ing. Klaus Graf, Leipheim;
Dipl.-Ing. Carsten Lips, Bad Hersfeld;
Dipl.-Ing. Richard Mansfeld, Rodewisch.
Design
Elke Schlüter Werbeagentur, Alfter
Tel. +49 228 64 79 89
1
Guidance for Asphalt paving operations
1 1
Preparation Preparation
of sub-base of sub-base
Granular base course The paving foreman must com-
(anti-freeze/ municate any obvious failures
crushed stone base) to the site manager, who will
promptly inform the client.
Producing a smooth, durable,
and adequately compacted base
course to specifications is vital Bound base course
for evenly solid asphalt pave- (Pre-existing bases or
ments.
bases that have been
Acceptance and hand over of laid formerly within the
the sub-base should always be project)
completed in due time before
starting paving operations. Existing bound bases must be
tested for suitability and relea-
Placement can only start if there
sed for use in due time prior to
are no defects in:
the commencement of paving
■ Bearing capacity operations.
■ Evenness The paving foreman must com-
■ Grade and cross-slope municate any obvious failures
■ Contamination to the site manager, who will
■ Required level promptly inform the client.
2
Preliminary works:
■ Thoroughly clean the base
surface of all dust, dirt and
other debris.
■ Ensure that manhole covers,
fire hydrants and utility
covers are at the right level
or adjusted to the required Appropriate mixes
level if required. for leveling courses:
■ Leveling courses or milling: Asphalt- Layer
usually a paver is used to base course thickness
pave the leveling course.
0/32 8,0 to 14,0 cm
Minor areas can be prepared
manually. 0/22 8,0 to 10,0 cm
0/16 3,0 to 8,0 cm
■ The mix should be applied in 0/11 < 6,0 cm
a separate work phase at all
times.
Tack coat:
■ Make sure that the leveling
A tack coat should be applied
course is densely compacted.
to the existing surface in com-
■ Slight irregularities do not pliance with table 1 and 2 of
need a leveling course and the M SNAR* guideline to en-
should be leveled out when sure a bond between the exis-
placing the next layer. ting surface and the new asphalt
overlay, see next page.
3
Preparation of sub-base
Overlay to be applied
Base Binder SMA
PmOB Type C U 60 K PmOB Type C U 60 K x
f
150 to 250 250 to 350
Base
f – x PmOB Type C U 60 K
150 to 250
Binder
4
Table 2: …for the categories IV to VI (g/m2)
Overlay to be applied
Base Binder AC SMA
U 60 K U 60 K U 60 K HK x
f
Type and quality of existing surface
U 60 K U 60 K U 60 K x
o/d 300 – 400 300 – 500 250 – 350
– HK HK x
d 200 – 300 200 – 300
x x U 60 K HK U 60 K HK
f
150 – 250 150 – 250 50 – 250 150 – 250
x U 60 K U 60 K HK U 60 K HK
m
Binder
250 – 350 250 – 350 200 – 300 150 – 250 150 – 250
x x U 60 K U 60 K
o/d 300 – 400 250 – 350
x x HK HK
d 200 – 300 200 – 300
5
Preparation of sub-base
2
Ordering and release
orders for asphalt-mix
Guidance for tack coat Ordering the asphalt-mix
application:
■ Apply the tack coat on the Every order should be made in
previous day, if possible. writing and as early as possible.
Allow enough time for set- Orders must comply with the
ting. Cover kerb restraints specifications set forth in the
and ironworks etc. construction contract. The dav
guidelines „How to organise
■ Apply a thin and even layer; quality“ include a form for
avoid fat spots, especially asphalt mixture release orders
when using hand-held de- attached as annex 4. It is re-
vices (avoid slip planes in commended that this order
wet condition). form be used.
■ Use truck mounted spray
bar, whenever possible.
The quality
of the entire overlay
hinges on the base!
6
The order should include Release orders for
the following items: paving operations:
■ Contractor
■ Ensure effective commu-
■ Construction job nication between paving
(cost center, if required) foreman and mix plant
7
3
Mix Transport
■ Haul distance and haul time ■ The truck bed of the haul
truck is to be thoroughly
■ Traffic holdups, e. g.
cleaned. Only use release
■ other construction sites, agents that are suited for
asphalt when spraying the
■ Traffic jams occurring
truck bed or bitumen im-
every day at certain times
pregnated crushed aggre-
(e. g. rush hour traffic),
gate/sand mixtures.
■ Detours that are required Make sure that there is no
due to weight limits for puddling when using liquid
bridges and certain road release agents.
sections.
■ Heavy and/or unpredic- ■ The use of oils, e.g. diesel oil,
table traffic (congestions can cause severe damage to
and detours) the asphalt layer and is thus
strictly prohibited.
■ Rest periods for drivers
8
■ The mix should not be
hauled to the paving site A continuous
if defects are detected visu- mix supply
ally already during loading for the paver
(e. g. segregation, wrong is vital
temperature, fatting-up or to the evenness
dry mixes). and regularity
of the applied
■ All vehicles must be equip- asphalt layer!
ped with windproof
tarpaulins; the load has
to remain covered during
transport and while the
truck is stationary.
9
Mix Transport
For Warm Mix Asphalts, the bottom limit of the regular mix temperature
should be used as reference value based on the additive applied, the process
technology, and the boundary conditions.
The lower limits are applicable to the unloaded mix during paving operations;
the upper limits are applicable to the mix when discharged from the mixing
plant or silo.
4
Mix inspection prior
to paving operations
BS CA PA TOH
– 130 to 180 130 to 180 130 to 180
120 to 180 120 to 180 130 to 180 130 to 180
120 to 180 120 to 180 130 to 180 130 to 180
– 130 to 180 –
– 130 to 180 130 to 180 130 to 180
– 120 to 180 130 to 180 130 to 180
Visual inspection
of the mix
Visual inspection
of the mix
Defective material
may not
be paved!
12
How to proceed with
mixes that failed
the visual inspection
13
5 5
Paving Paving
14
Different kinds of pre-compaction
with paver screeds
(Voegele equipment as example)
Tamper Tamper
Pressure bar
Tamper
2 pressure bars
15
Paving
16
Tests during
paving operations
Manual placement
The asphalt mix should be pla- Make sure you have enough
ced by hand only in exceptio- hot mix available when star-
nal cases. Use an extendable ting manual work. As there is
screed to accommodate chan- no screed affording initial com-
ging paving widths. Pave span- paction, the tolerance range
drels manually, while continu- has to be increased. Do not
ing laydown operations with throw the material through the
the paver. Manual work may be air. Instead, deposit the material
required in the following cases: from the shovel on to a small
pile. Verify surface evenness with
■ Very small areas a straight edger before starting
(repairs, excavations) compaction.
■ Cable trenches
Start with compaction immedi-
■ Driveways ately. Lightweight rollers and
■ Spandrels vibratory plate compactors are
ideal for base and binder cour-
It is vital that manual work only
ses when working on excava-
be performed after you have tions and small repair areas. A
completed preliminary work e.g. vibro-tamper or hand tamper
■ Cleaning should be on hand for corners
and side areas.
■ Applying tack coat
adhesive or emulsion Fast and uninterrupted work is
■ Fitting sealing strips or of the essence when surfacing
applying joint sealants by hand.
18
Surface course +5 o C As a general
Binder course 0 oC rule, the lower
Base course –3 o C layer should
Surface tem- not be frozen or wet,
perature of the and should be free
lower layer from snow and ice!
Ambient conditions
and the mix type
have a strong impact
on paving operations
19
6
Compaction
of the mix
20
Various types and weights of Static tandem rollers
rollers can be used for the follo-
wing purposes: ■ For breakdown rolling of
asphalt layers,
Static three wheel rollers ■ For compacting asphalt layers
(10–22 t) up to 8 cm in thickness,
■ Used for compacting ■ For compacting edges of the
asphalt layers, edges of lane as well as transverse and
the lane, transverse and longitudinal joints,
longitudinal joints, and ■ For smoothing the layer after
to smooth the layer after the roller passes have been
all roller passes have been completed;
completed.
Tandem vibratory rollers
■ Used for compacting asphalt
layers up to 16 cm in thickness,
■ Never to be used for breakdown
rolling, on engineering structures,
or on thin overlays or porous
asphalt surface courses.
21
Compaction of the mix
22
Roller passes
23
Guidance for asphalt mix compaction
■ Typically, at least 2 rollers should switch off the engine and allow
be on site during placement. the roller to coast down; then
■ Follow the paver as closely as restart the engine right away,
possible during the first roller thus avoiding a surge.
pass (breakdown). ■ When using vibratory rollers
■ Turn the roller slightly when turn off the vibration with
stopping in front of the paver. enough lead time before chan-
ging directions, to avoid vibra-
■ Angle the drive wheel (of single
tory roller marks on the layer
drum rollers) towards the paver
that are unable to be ironed
to avoid bow humps and crak-
out by subsequent rolling.
king (exception: paving opera-
tions on steep sections). ■ Vibratory compaction has to
be consistent with the mix
■ Begin the compaction process
temperature.
on the low side of the pave-
ment lane and proceed up- ■ Moisten the drums regularly
wards towards the centre or with only enough water (e.g. in-
the high side, using the drum termittent water spray system).
width as reference. ■ Assign the longitudinal joint to
■ When compacting curves with a specific roller when paving two
crossfall begin compaction on layers „hot on hot“.
the low side of the road's edge. ■ In no circumstance should the
The lane first paved serves as roller be stopped on the hot lay-
an abutment for the next roller er. After having completed the
passes. required roller passes, remove
■ Always stop rollers on comple- the roller from the cooling
ted asphalt layers and never on asphalt layer and park it out-
a hot layer that is still plastic. side the cold surface.
■ Change directions smoothly; ■ Do not use the vibratory mode
when reversing directions for cold layers!
24
Compaction of the mix
smaller 6 tons • • + • + ++ • •
larger 6 tons + ++ ++ ++ ++ ++ ++ ++
vibratory mode
normal ++ ++ + • to + ++ – – • to +
Oscillation ++ ++ ++ • to + ++ – • • to ++
Combi roller + • • – ++ – – –
++ = especially suited
+ = suited
• = suited under certain circumstances
– = not very well suited
Finishe
Paver 1 d
surface Paver
course
Paver 2
Mini- 10–15 cm
mum:
15 cm 25
Compaction
of the mix
An excessive,
initial mix temperature
causes...
26
…transverse cracks behind …mix sticking to the roller
the roller drum, drum despite wetting the
roller,
Better
a roller too much
than a roller short
27
7
Skid Resistance
29
Design specific
guidance
30
Planning paving operations During paving operations
■ If the mix is placed on an ■ The tolerance range is
existing surface, ensure considerably lower than
that it is sufficiently sealed. for standard asphalt layers.
■ Special care should be given ■ Also, make sure to use
to preheating the plate on smooth drum rollers only
the bottom of the screed. when compacting the mat.
■ Operate the roller in
■ When paving half of the
static mode.
road width, ensure that
water drainage within the ■ Base courses laid under block
layer is not stopped by a pavements and permeable
sealing strip, etc. The same sports surfaces can also be
applies when repairing compacted under vibratory
road damages. mode.
■ Be especially careful when
the roller moves across the
lane to the next rolling lane.
■ Porous asphalt overlays are
not gritted because the
aggregates would clog the
voids of the porous asphalt
surface course.
31
Design specific guidance
32
Light-colored surface courses
The asphalt base courses for the Asphalt layers serve as water-
solid track bed are laid with the proof sealing for hydraulic and
same technique as in road de- landfill constructions. In such
sign. There is, however, a signi- construction projects the base
ficant difference in the surface and also the embankments
course which is compacted sole- should be rendered waterproof.
ly by the screed without using Asphalts used in these appli-
any rollers. Only when using this cations must have sufficient sta-
technique can the course be laid bility to be laid without sliding
to the specified level. The course down the slope. Specific paving
is laid using the approved equip-
and compaction equipment is
ment and in compliance with
required in addition to a special
the specifications pertaining to
mix design. The applicable con-
the building of solid track beds.
tract specifications should be
The track bed should be placed observed. The construction of
while taking on-site conditions joints and seams requires ad-
adequately into consideration vanced techniques and special
and using equipment modified care.
specifically for this purpose.
33
Design specific guidance
Special designs
require
special instructions
and information!
34
9
Joints
36
Centerline of the pavement
Longitudinal joint
Remove any
dirt and loose particles!
37
Joints
splashguard, if required
bituminous material
roller pass
if completed layer roller
is not passable
39
Joints
Material finishing/shaping
40
10
Gap joint
Guidance Gap joint configurations
41
Gap joints
43
11
Road Edges
Faulty sealing
damages
the asphalt!
44
≥ 2,5%
Not required if the layers
are placed immediately
Asphalt surface course
one after another
≥10 cm
Asphalt binder course
≥10 cm
2nd layer
Asphalt base course
≥10 cm
1st layer
45
12
Taking Samples to
verify quality features
Sampling
46
Documentation
47
Annex
Notes
49
Notes
73494 Rosenberg
Germany
Fon +49 7967 152 297 • Fax +49 7967 152 500 151
[email protected] • www.jrs.de
www.sma-viatop.com