THE SECRETARY OF TRANSPORTATION WASHINGTON DC 20590

April 29, 2011



The Honorable Frank R. Lautenberg United States Senate

Washington, DC 20510

Dear Senator Lautenberg:

Thank you for your letter of February 15, cosigned by your congressional colleagues, regarding the repayment of Federal funding expended in the planning, design, and construction of the Access to the Region's Core (ARC) project. As you know, the ARC project was terminated unilaterally by Governor Christie this past October.

The Governor's unfortunate decision will affect the commuters of New Jersey and the entire Northeast region for generations. Not only did it eliminate the opportunity for thousands of crucial jobs, but it also halts the much-needed effort to modernize the rail system's tunnel infrastructure in this region, which is more than a century old. The mobility improvements promised by the ARC project would have improved the daily commute for people who drive and take the train, as well as provided greater opportunities for economic growth in the region. The planning, design, and environmental approval processes- for the ARC project spanned decades. Any substitute project, should one emerge, will take a great many years to develop and deploy.

Following an exhaustive review of the State of New Jersey's response to the Federal Transit Administration's (FTA) Demand for Repayment of November 2010, the Agency's Chief Financial Officer has determined that the State is obligated to repay $271 million to the Federal taxpayer-the full amount covered by the Early Systems Work Agreement (ESWA) between New Jersey Transit (NJT) and FT A. An ESWA, like the Full Funding Grant Agreements that NJT has benefited from in the past, constitutes a contract between the American taxpayers and NJT.

The taxpayers, acting through FTA, committed more than a billion to NJT in exchange for which NJT was committed to build a defined transit improvement for the benefit of the American people. In this case, after the initial contract was entered into and later expanded at Governor Christie's request, the State of New Jersey broke the terms of the contract.

The law is clear on this matter. In very specific and clear language, the statute requires FTA to collect the taxpayers' funds if the project sponsor-in this case, NJT -disavows its responsibilities under the contract and fails to complete the project. Moreover, Governor Christie and the leadership ofNJT were fully aware of these consequences and the requirements under the law when the Governor made his decision to terminate the project.

In February 2010, Governor Christie sat in my office and expressed his full commitment to the completion of the ARC project. In March of2010, when several news stories called Governor Christie's commitment to the completion of the ARC project into question, I asked the Governor to restate that commitment in writing. He did so in a letter to me dated April 6, 2010. In that same letter, he even asked me to expedite the expansion of the ESWA, which I did.

···,·a

Page 2

When the Governor sgddenly announced 5 months later that he was putting the project on hold, I began a series of conversations with the Governor that culminated in my making two separate trips to New Jersey to meet with him personally. As part of those meetings, I presented several different possible scenarios regarding the financing and scope of the ARC project, all with the goal of keeping the project alive. The purpose of my efforts was to avoid the very circumstance in which we now find ourselves: no jobs, no congestion relief, and an enduring debt whereby New Jersey must return $271 million to the Nation's taxpayers.

Governor Christie has explained that an important rationale in his canceling the ARC project pertained to new information indicating that the project was at risk of substantial cost growth. The FTA routinely establishes cost ranges for large projects of this kind at all stages of their development. Indeed, the possibility that this project's cost could run between $8.4 billion and $12 billion was first shared with NJT as far back as August 2008. As is customary, there were dozens of meetings between FTA and NJT staff, including the NJT Executive Director, during which refinements were. made to these cost ranges. Any notion that the potential for cost growth constituted new and emergent information when the Governor made his decision is simply not accurate.

The U.S. Department of Transportation and the U.S. Department of Treasury have many tools under the Debt Collection Act to recoup the lost Federal taxpayer funds, including withholding future State funding from a wide variety of sources. However, in consideration of the current economic challenges burdening New Jersey and all other States, I am not pursuing these collection methods at this time in the hope that we and the State of New Jersey can develop a workable payment schedule that will result in the least harm to New Jersey residents.

In your letter, you address the issue of fairness in the treatment of New Jersey. Indeed, not only is my decision fair to the taxpayers of New Jersey, it is the only one that is fair to all taxpayers across the United States who made the financial investment in what was to be the largest public works project in the Nation. My decision considers their needs, including those of citizens from Montana and Wyoming who wrote to me asking that I do all in my power to protect their jobs, which depend on contracts related to the ARC project.

I have enclosed a copy ofFTA's decision. The NJT should contact FTA to make arrangements to pay the amount due. In the interim, should you ve any questions, please feel free to call

me.

Enclosure

BEFORE THE

UNITED STATES DEPARTMENT OF TRANSPORTATION FEDERAL TRANSIT ADMINISTRATION

FINAL DECISION OF THE FEDERAL TRANSIT ADMINISTRATION DEBT COLLECTION ACTION

NEW JERSEY TRANSIT CORPORATION

ACCESS TO THE REGION'S CORE PROJECT

TABLE OF CONTENTS

Final Decision of the Federal Transit Administration

I. OVERVIEW ,~ 1 ~

II. SUMMARY OF KEY FINDINGS 2

III. BACKGROUND 4

A. FTA's New Starts Process and the Use of an ESWA 5

B. The 2008 Risk Assessment for the ARC Project 7

C. New Jersey Requests an Early System Work Agreement 9

D. NJT Seeks an Expanded ESWA 13

E. New Jersey's Termination of the ARC Project.. 17

F. FTA's Debt Collection Action 21

IV. LEGAL FRAMEWORK 25

v. ANALYSIS 28

A. The State of New Jersey's Decision to Terminate the ARC Project Was a

Discretionary Decision Within Its Control. 29

1. NJT's fears of escalating cost estimates and New Jersey's own financial difficulties do not constitute reasons for the State to terminate the Project that are

outside of its control. 30

2. NJT controlled the actual costs incurred on the ARC Project and its assertion that

the increasing cost estimate was beyond its control is without merit.. 34

B. The Early System Work Agreement Included New Starts Funds, CMAQ Funds, and

ARRA Funds-All of Which Must Now be Repaid 36

1. An ESW A may include more than New Starts funds 37

2. NJT and FTA expressly included ARRA, CMAQ, and previously expended funds in the ESW A, and FTA's payment of these funds to NJT constituted payments

under the ESW A 38

3. The Repayment Provision requires the repayment of all Federal payments made

under the ESW A, not just New Starts funds 43

4. Formula Program funds administered under 49 U.S.C. § 5307 are subject to

repayment 45

C. The Master Agreements Independently Authorize FTA to Seek Repayment of All the

Federal Funds Expended on the Project.. 47

D. Principles of Equity and Fairness Favor Enforcing the Statute and Master Agreements Voluntarily Entered Into by NJT and Requiring New Jersey to Repay the Debt That it

Owes to the United States Government 48

VI. FINAL DECISION 52

1

Final Decision of the Federal Transit Administration

I. OVERVIEW

The New Jersey Transit Corporation ("NJT") has requested an administrative review of

the Federal Transit Administration's ("FTA") determination that NJT owes a debt to the United

States Government in the amount of $271,101,291. Pursuant to the Federal Claims Collection

Act of 1966, as amended, and FTA's Debt Collection Order, I hereby issue this Final Decision in

my capacity as FT A's Chief Financial Officer.

FTA's claim against NJT arose out of the State of New Jersey's voluntary and willful

termination of the Access to the Region's Core Project (hereinafter "ARC Project" or "Project")

that received Federal funds from FTA under an Early System Work Agreement ("ESWA") and

FTA's Master Agreements.' Under the statute authorizing the use of an ESWA, a recipient must

repay all Government payments made under the ESW A if the recipient fails to carry out the

project for reasons within its control. In addition to this statutory repayment provision, under the

Master Agreements governing FTA-funded projects, including the ARC project, FTA has the

right to require a recipient to refund all Federal funds expended on the project if the recipient

willfully fails to make adequate progress on the project. FTA is entitled to repayment from NJT

under both the repayment provision and the applicable Master Agreements.

After New Jersey terminated the Project, FTA demanded that NJT repay the

$271,101,291 in Federal payments made under the ESWA. FTA advised NJT that it had the

right to request a review of the validity or amount of FT A's claim. On January 25, 2011, NJT

submitted an opposition to FTA's claim and included supporting documents and declarations.

New Jersey contended that it should not have to repay the Federal funds it expended on the ARC

1 FTA's Master Agreement contains the standard terms and conditions governing the administration of a project supported with Federal assistance awarded by FTA through a grant agreement. The Master Agreement is incorporated by reference into every grant agreement FTA executes, and is updated annually.

2

Final Decision of the Federal Transit Administration

Project under the ESWA because it terminated the Project for reasons outside its control and the

statutory repayment provision did not apply to the funds it received.

After carefully considering NJT's submission and the administrative record as a whole, I

have concluded that the State of New Jersey is indebted to the United States in the amount of

$271,101,291.

H. SUMMARY OF KEY FINDINGS

1. NJT, an instrumentality of the State of New Jersey.t expended a sum total of

$271,101,291 in Federal funds under the ESWA and the Master Agreements for the ARC

Project. The sum total of $271,101,291 was comprised of $51,589,932 in Federal funds

provided under FTA's New Starts program; $91,501,954 in Federal funds provided under the

American Recovery and Reinvestment Act ("ARRA"); and $128,009,405 in Federal funds

provided under the Department of Transportation's ("DOT") Congestion Mitigation and Air

Quality ("CMAQ") program? At the time that the ARC Project entered Final Design," NJT and

FTA negotiated a figure of $8.7 billion as the baseline cost estimate-or the total estimated cost

of the Project-based on the results of a 2008 Risk Assessment that preliminarily estimated the

cost of the Project to range from $8.4 billion to $12 billion. The baseline cost estimate of $8.7

billion was still in place at the time the ESWA was executed on August 20,2009, and it always

was subject to further negotiations between NJT and FT A. Moreover, consistent with long

2 See New Jersey Public Transportation Act of 1979, codified as amended at N.J. STAT. ANN. § 27:25-4(a) (2010) ("There is hereby established in the Executive Branch of the State Government the New Jersey Transit Corporation."). The New Jersey Governor appoints each of the eight members of NJT's Board of Directors. N.J. STAT. ANN. § 27:25-4(b) (2010). For purposes of this debt collection action, PTA will treat the State of New Jersey and NJT as one and the same.

3 NJT has not disputed that $271,101,291 of Federal funds were expended for the ARC Project under Grant Numbers NJ-03-0169-00; NJ-03-0169-01; NJ-03-0138-02; NJ-95-X002-00; NJ-90-X086-00; NJ-95-X003-00; NJ- 95-X008-00; and NJ-96-X002-0 1. See NJT Opposition to Demand (Jan. 25, 201 1); Agency Doc. 19, NJT Quarterly Report (Sept. 30, 2010); Agency Doc. 7, ARC Expenditures as of 9/30110.

4 "Final Design" is the last phase of project development for a "New Starts" project funded by FT A. This phase is intended to provide a smooth transition between project development and project implementation. The project development phases are further explained below.

3

Final Decision of the Federal Transit Administration

established FTA policy, FTA informed NJT-and NJT understood at all times-that NJT was responsible for any and all actual costs incurred on the Project that exceeded the baseline cost estimate.

2. On January 8,2010, NJT requested an amendment to the ESWA to capture

additional Federal funding, expand the scope of work, and further accelerate construction of the ARC Project. By letter dated April 6, 2010, New Jersey Governor Chris Christie requested that FTA agree to "an expeditious award" of an ESW A amendment, and, at the request of Transportation Secretary Ray LaHood, Governor Christie explicitly reaffirmed the State's commitment to the Project. On April 14, 2010, NJT and FTA amended the ESW A. Based on the upper range of the estimates provided by FT A and agreed to by NJT, NJT and the Governor were aware that the costs of the ARC Project might run in excess of $12 billion when (1) NJT and the Governor requested the ESWA amendment, (2) the Governor reaffirmed the State's commitment to the Project, and (3) NJT and FTA subsequently executed the amendment.

3. In October 2010, on NJT's behalf, Governor Christie terminated the ARC Project

on the recommendation of the NJT ARC Executive Steering Committee. The administrative record shows the ARC Project was unilaterally terminated by the "applicant"-NJT-for "reasons within the control of the applicant," within the meaning of 49 U.S.C.

§ 5309(g)(3)(B)(iv).

4. NJT insisted that funds expended for engineering and design for the ARC

Project-including New Starts, CMAQ and ARRA funds-be included in an ESW A, which requires FTA to recover all Government payments made under the ESW A if a recipient terminates a project for reasons within its control. Importantly, NJT chose to request an ESW A, chose to include the grants at issue in the ESW A, and chose to abide by all conditions associated

4

Final Decision of the Federal Transit Administration

with the ESW A in exchange for the funding and the unique and significant benefits that an ESW A provides to a grantee. As a consequence of NJT' s voluntary choices, the Federal payments made under the ESW A must now be repaid in accordance with 49 U.S.C.

§ 5309(g)(3)(B)(iv) and the Master Agreements.

5. The financial challenges facing the State of New Jersey do not excuse NJT's non-

compliance with the terms of the ESW A and the Master Agreements, nor do they negate FTA's statutory obligation under 49 U.S.C. § 5309(g)(3)(B)(iv) to obtain repayment of the $271,101,291 in Federal funds expended under the ESW A, as mandated by the Federal Claims Collection Act, as amended and codified at 31 U.S.C. Chapter 37, and the Federal Claims Collection Standards codified at 31 C.F.R. Chapter IX.

HI. BACKGROUND

The ARC Project was the largest planned public works project in the United States. NJT and the Port Authority of New York and New Jersey ("Port Authority") developed the ARC Project-a nine-mile commuter rail line between Secaucus, New Jersey and midtown Manhattan-to alleviate the crippling congestion and daily delays experienced by more than 135,000 daily passengers along a segment of the Northeast Corridor that is currently serviced by a limited capacity, 100-year old tunnel. The ARC Project would have increased capacity on this segment of the Northeast Corridor to more than 250,000 daily passengers, thereby supporting sustained economic growth in the New York-New Jersey region.

As set forth below, the Governor and NJT terminated the ARC Project in October 2010, while work was ongoing under an ESW A. At that time, the Project was the largest in the history of the Federal transit program, with an expected Federal New Starts commitment of $3 billion. In addition to the New Starts funds committed to the Project, the Port Authority committed $3

Final Decision of the Federal Transit Administration

billion and the State of New Jersey committed $2.7 billion, which included $1.25 billion from

the New Jersey Turnpike Authority and $1.35 billion in Federal Highway Administration

"flexed" CMAQ funds. NJT intended to contribute $100 million to the Project from the New

Jersey Transportation Trust Fund. In the history of the New Starts program, no grantee has ever

terminated a project while an ESW A was in effect.

5

A. FTA's New Starts Process and the Use of an ESWA

The ARC Project was part ofFTA's discretionary "New Starts" program, the Federal

Government's primary financial resource for supporting locally planned, implemented, and

operated public transit fixed-guideway capital mvestments.' Through this program, FTA

identifies and recommends new fixed-guideway transit projects-including heavy, light, and

commuter rail; ferry; and certain bus projects-for Federal funding. As the United States

Government Accountability Office ("GAO") has noted, FTA's New Starts program is considered

"a model for other transportation programs" because of its use of a rigorous and systematic

evaluation process to make decisions about moving projects forward and forecasting their costs."

Transportation projects seeking New Starts funding typically proceed through three

phases of planning and development: (1) Alternatives Analysis, in which a locally preferred

alternative is selected; (2) Preliminary Engineering; and (3) Final Design. At the successful

culmination of this planning and development process, FTA may advance a project into

construction by entering into a Full Funding Grant Agreement ("FFGA") with its grantee. An

FFGA is a multi-year contractual agreement between FTA and the project sponsor that formally

defines the project scope, cost and schedule. An FFGA establishes the maximum level of

5 The primary statutory guidance for PTA's New Starts process is located at 49 U.S.C. § 5309 (2006). 6 UNITED STATES GOVERNMENT ACCOUNTABILITY OFFICE, GAO-OS-S44, PUBLIC TRANSPORTATION:

IMPROVEMENTS ARE NEEDED TO MORE FULLY ASSESS PREDICTED IMPACTS OF NEW STARTS PROJECTS at 2 (July 200S).

6

Final Decision of the Federal Transit Administration

Federal financial assistance and outlines the terms and conditions of Federal financial

participation.

In some cases, as with the ARC project, a project sponsor in Final Design may be ready

to begin construction or otherwise start carrying out a project before a full commitment of

Federal funds can be made through an FFGA. If certain requirements are met, FTA may provide

Federal funds for a New Starts project through an ESW A. An ESW A defines a specific scope of

work for a New Starts project and dedicates Federal funds to enable a grantee to carry out that

work.' Relying on this initial award of Federal funds, a grantee may enter into construction

contracts, acquire real estate, or finance other activities that will make efficient, long-term

project management easier. An ESWA promotes the completion of a project more rapidly and at

less cost by making a substantial amount of Federal funds available to the grantee, through the

execution of fund-obligating grants included in the ESW A prior to the execution of an FFGA.

Throughout the development of an ESW A, FT A and the grantee negotiate the scope of work and

the funding sources, and the parties mutually agree to these terms when they execute the ESWA.

When executed, the ESW A becomes a binding agreement between the parties.

The ESW A statute provides that an ESW A "obligates an amount of available budget

authority specified in law."g By its very terms then, the funds provided by an ESWA are not

limited to New Starts funds and thus may include funds from a variety of Federal funding

sources so long as they are derived from available budget authority. Such available budget

authority could include FTA's New Starts program at 49 U.S.C. § 5309, FTA's Urbanized Area

Formula Program at 49 U.S.C. § 5307, DOT's CMAQ program, or other Federal funding

sources, such as ARRA. In this case, FTA and NJT agreed to the use of several Federal funding

7 A grantee is also required to match the Federal funding in an ESW A with local funds. See 49 U.S.C. § 5309(h). As such, the ESW A includes funds from Federal and local funding sources.

849 U.S.C. § 5309(g)(3)(B)(i).

7

Final Decision of the Federal Transit Administration

sources for the ARC project, including ARRA, CMAQ and New Starts, and they further agreed, at NJT's request, to incorporate grants from these various Federal funding sources into the

ESW A. After the incorporation of these grants into the ESW A, the monies that had been or were to be expended under the grants became subject to the repayment provisions of section 5309 that require repayment of "all Government payments made under the work agreement." Each of the ARRA, CMAQ and New Starts grants from which expenditures were made as part of the $271,101,291 in "Government payments" in dispute here are likewise identified in the ESWA as providing funding for the ARC Project under the ESW A.

B. The 2008 Risk Assessment for the ARC Proiect

As is typical in a New Starts project, before the ARC Project was approved into Final Design, NJT and FTA undertook a joint, collaborative effort to assess the risks of the Project and negotiate a baseline cost estimate for the Project. The baseline cost estimate is significant because it: (1) is used in applying the New Starts criteria for project justification under the requirements of 49 U.S.C. § 5309; (2) provides all parties involved with a reasonable forecast of the financial commitment necessary to complete the project; and (3) helps establish the maximum Federal New Starts contribution. As a project moves through each stage of development, FTA and its grantee-in this case, NJT-constantly and collaboratively update the risk assessment and negotiated baseline cost estimate. Since the maximum Federal share generally is established when a project enters Final Design, the grantee is well aware that, if the grantee requests and subsequently executes an ESW A, the grantee is responsible for all costs exceeding the baseline cost estimate.

On August 7,2008, with input from NJT, FTA prepared a draft preliminary cost estimate for the Project with a range of $9.5 billion to $12.4 billion, and shared this draft with NJT for its

8

Final Decision of the Federal Transit Administration

review and comment. 9 In response, NJT provided FTA with two sets of comments and

additional input on the draft.i" Through these responses, NJT attempted to demonstrate that it

could deliver the Project within an estimated cost range of $7.495 to $7.520 billion.!! Upon

consideration of NJT' s comments and input, FTA substantially revised the Risk Assessment and

produced a revised cost estimate range of $8.4 billion to $12 billion, to which NJT agreed.f

From this Risk Assessment, NJT and FTA negotiated and ultimately agreed that the estimated

cost of the Project was $9.1 billion; FTA subsequently approved the Project into Final Design. 13

This $9.1 billion figure included an agreed upon $1.8 billion contingency from which NJT could

drawdown funds if it experienced cost overruns and realized risks identified in the Risk

Assessment. 14

Although NJT and FTA agreed that the estimated cost of the Project would be $9.1

billion, the parties further agreed to use a lower figure-$8.7 billion-as the actual baseline cost

estimate on the basis of the depreciated value of railcars that NJT was to procure for the

Project.l" Additionally, FTA relied upon and counted on NJT's assurances that NJT would

deliver the Project at this cost and aggressively mitigate risk and potential cost overruns when

9 See Declaration of Brigid Hynes-Cherin at <J[ 17; PTA Hynes-Cherin Ex. 2, PTA's Draft 2008 Risk Assessment at 6 (Aug. 7, 2008).

10 See Hynes-Cherin Decl. at <J[ 18; PTA Hynes-Cherin Ex. 3, Grantee Response to PTA Letter (Aug. 11,2008); PTA Hynes-Cherin Ex. 4, Grantee Response to PTA Letter at 9 (Aug. 14,2008).

IIId.

12 See Hynes-Cherin Decl. at <J[ 19; PTA Hynes-Cherin Ex. 5, 2008 Risk Assessment at 7 (Aug. 26, 2008). See also NIT Silber Ex. 19,2008 Risk Assessment at 7 (Aug. 26, 2008).

13 See Hynes-Cherin Decl. at <J[ 37; PTA Hynes-Cherin Ex. 8, PTA Letter to NIT Approving Entry into Final Design (Ian. 27, 2009).

14 See Hynes-Cherin Decl. at <J[ 37.

15 See Hynes-Cherin Decl. at <J[ <J[ 26-29; PTA Hynes-Cherin Ex. 8, PTA Letter to NIT Approving Entry into Final Design (Ian. 27, 2009). NIT intended to purchase the railcars early with its own funds and use them in its existing service until the ARC Project was ready for revenue operations. Id. at <J[ 27. NIT subsequently planned to "sell" the railcars to the Project for their depreciated value. Id at <J[ 28; PTA Hynes-Cherin Ex. 8, PTA Letter to NIT Approving the ARC Project Into Final Design at 1 (Ian. 27,2009). See also NIT Silber Ex. 19,2008 Risk Assessment at 7 (Aug. 26, 2008).

9

Final Decision of the Federal Transit Administration

FTA agreed to use the $8.7 billion figure as the baseline cost estimate. 16 Under an FFGA, NJT

would be responsible for any costs exceeding the final baseline cost estimate of the Projt;:ct.17 As

the Project proceeded to construction and the parties neared the execution of an FFGA, NJT and

FT A were to engage in further negotiations which would narrow the scope of the cost range for

the Project and identify a more accurate baseline cost estimate, no different from a typical New

Starts project. NJT and FT A knew that the parties would need to negotiate a new baseline cost

estimate prior to the execution of an FFGA, because FT A had to ensure that NJT continued to

have the financial capacity to carry out and complete the Project. 18 As with all New Starts

projects, prior to committing additional Federal funds through an FFGA, FTA, in collaboration

with its grantee, NJT, would need to conduct an updated risk assessment and negotiate a revised

baseline cost estimate.

c. New Jersey Requests an Early System Work Agreement

After NJT and FTA agreed to a baseline cost estimate and FTA approved the ARC

Project for entry into Final Design in January 2009, NJT turned its attention to obtaining

additional Federal funds through an ESW A. 19 NJT intended to award several large contracts for

real estate, construction, and professional services by early 2010.20 To facilitate the execution of

such contracts, NJT wanted to demonstrate a significant commitment of Federal funds to the

Project.21 Anecdotally, contractors are often more willing to bid on contracts when the project

sponsor can demonstrate a substantial commitment of funds to the project, especially Federal

16 See Hynes-Cherin Dec!. at'lI'lI 24, 25, 33.

17 See FTA 2006 Guidance on New Starts Policies and Procedures at 9, available at http://www . fta.dot. gov /planning/news tarts/p lanning_ en vironment_5 203 .html (May 16, 2006).

18 Pursuant to 49 U.S.C. § 5309(d), before FTA decides whether to execute an FFGA for a project, Congress requires FT A to apply a series of evaluation criteria to a project to determine whether the grantee has the financial capacity to carry out and deliver the project.

19 See Hynes-Cherin Dec!. at <J[ 44.

20 [d. at <J[ 51 (citing NJT Letter to FTA Requesting an ESWA (June 24,2009)). 21 [d.

10

Final Decision of the Federal Transit Administration

commitment when the Federal Govemment is a funding partner. This increases competition and

drives down overall project cost. But NJT recognized that an FFGA would not be executed for

the ARC Project until late 2010,22 which would cause delays unacceptable to NJT. As a result,

NJT sought to obtain the necessary funds through an ESW A, negotiating its terms with FT A

starting in early 2009 and making an official request by letter dated June 24,2009.23

NJT explained in its request that an ESW A was "critical" to allow NJT to maintain the

Project's schedule and budget, and to "demonstrate a federal funding commitment to the project

in support of local funding commitments already in place.,,24 NJT proposed a scope of workfor

the ESw' A that included (1) the Manhattan Tunnel Contract; (2) the Tonnelle Avenue Underpass

Contract; (3) Early Property Acquisition; (4) Professional Services; and (5) Contingency.f NJT

insisted that the ESW A include New Starts funds, ARRA funds, and CMAQ funds-some of

which had previously been obligated-and included such funds in its ESWA proposal.f By

letter dated August 14, 2009, FT A approved the scope of work and total ESW A amount

proposed by NJT.27

On August 20,2009, NJT and FTA executed the ESWA, as reflected in Grant NJ-03-

0169-00.28 An ESWA is processed through FTA's grants management system-the

Transportation Electronic Award Management System ("TEAM"). TEAM is an electronic

database accessible to both FT A and applicants via the Intemet, whereby applicants apply for

22 [d.

23 [d. at <JI<JI 44-60; Agency Doc. 27, NJT Letter to PTA Requesting an ESWA at 1 (June 24, 2009). 24 Agency Doc. 27, NJT Letter to PTA Requesting an ESWA at 1 (June 24, 2009).

25 ta.. Agency Doc. 2, ESWA, Grant Number NJ-03-0169-00 at Part 2 (Aug. 20, 2009) 26 Hynes-Cherin Decl. at <JI<JI 46-61.

27 [d. at <JI 61; Agency Doc. 1, PTA Letter to NJT Approving the ESWA at 2 (Aug. 14,2009). In this letter, PTA reiterated the total baseline cost estimate for the Project of $8.7 billion, which both parties agreed to when the Project entered Final Design.

28 Agency Doc. 2, ESW A, Grant Number NJ-03-0 169-00 at Parts 2, 3 (Aug. 20, 2009). The terms of the ESW A, including the scope of work and sources of funds, are further defined in the June 24, 2009 letter from NJT to PTA and the August 14, 2009 letter from PTA to NJT.

11

Final Decision of the Federal Transit Administration

and FTA approves grants and other agreements. Applicants enter important project information

into TEAM, including the project description, scope, budget, and milestones.i" FTA reviews this.

information, and if necessary, FTA provides the applicant with comments regarding the extent to

which the application is satisfactory.f" Once FTA is satisfied with the application, it approves

the document in TEAM by executing an electronic agreement. 31

Federal funds provided to a project under an ESWA are obligated to the grantee under

grant agreements, also executed through TEAM, that are included in, and support the scope of

work outlined in, the ESW A. Funds from different appropriation sources cannot be joined in a

single grant due to the inability ofFTA's financial management systems to process different

program funds within a single grant application. As a result, separate grant documents are

necessary to obligate funds from different sources provided under the ESW A.

For the ARC Project, the ESWA was executed, in accordance with NJT's request, in the

amount of $1,352,000,000, which included both Federal and local funding.32 With regard to

Federal funds, the ESW A committed $395,020,000 in New Starts funds and authorized the use

of $130,000,000 in ARRA funds and $125,000,000 in CMAQ funds, making the total Federal

share $650,020,000.33 Funds provided under the ESWA were obligated either

29 The grant applicant also enters information regarding its organization, such as its address, its contact information, union information, an urbanized area identification number, congressional district information, and its Data Universal Numbering System number. In addition, the applicant enters project information which identifies whether the application is for a new grant, a grant amendment, or a budget revision, and the project's start date and end date. See FTA Circular 9300.1B, Capital Investment Program Guidance and Application Instructions, Appendix A at 1-2 (Nov. 1, 2008).

30Id. at 4.

31Id.

32 Agency Doc. 2, ESW A, Grant Number NJ-03-0l69-00 at Parts 2, 3 (Aug. 20, 2009) (a purpose of the grant was "to outline the components of the ESW A for $1,352,000,000").

33 Id. at Part 2.

12

Final Decision of the Federal Transit Administration

contemporaneously with the ESW A or through separate grant agreements that were incorporated

into the ESW A and supported its scope of work. 34 In particular:

® A portion of the New Starts funds committed by the ESWA ($14,700,000) was

obligated contemporaneously with the ESWA, in the same grant agreement that

executed the ESW A.35

® Two days before the ESW A was executed, NJT and FTA entered into a grant

agreement obligating the $130,000,000 in ARRA funds included in the ESW A.36

The ESWA specifically incorporated this ARRA grant." Moreover, the ESWA's

scope of work included the specific work covered by the grant, i. e., construction of

the Tonnelle Avenue Underpass and final design services.i"

® A few weeks after the ESW A was executed, NJT and FTA entered into a grant

agreement obligating $50,000,000 of the CMAQ funds included in the ESW A. 39

These funds were budgeted for professional services, property acquisition, and the

Manhattan Tunnel construction, all of which were included in the ESW A's scope of

work.40 The ESWA specifically incorporated this CMAQ grant."

® The ESW A also incorporated CMAQ funds previously obligated for preliminary

engineering work through three separate grant agreements. The ESWA specifically

34 Note, however, a substantial portion of the funds provided under the ESW A were still unobligated at the time NJT terminated the ARC Project.

35 See Agency Doc. 2, ESWA, Grant Number NJ-03-0169-00 at Parts 3, 9.

36 See Agency Doc. 38, NJ-96-X002-00 (Aug. 18,2009) (obligating $130 million in ARRA funds for the Tonnelle A venue Underpass and professional services for final design). This grant agreement was amended on March 4, 2010. See Agency Doc. 14, NJ-96-X002-01 (Mar. 4, 2010).

37 See Agency Doc. 2, ESWA, Grant Number NJ-03-0169-00 at Part 2 ("A grant application of $130,000,000 of ARRA funds is pending.").

38 [d.

39 See Agency Doc. 13, Grant Number NJ-95-X008-00, at Part 2 (September 4,2009) ("The $50 M of CMAQ funding in this grant is part of a total of $125 M of CMAQ funds that is authorized as part of an Early Systems Work Agreement (ESWA) outlined under pending FTA grant NJ-03-169.").

40 See id. at Part 3; Agency Doc. 2, ESWA, Grant Number NJ-03-0169-00 at Part 2.

41 See Agency Doc. 2, ESWA, Grant Number NJ-03-0169-00 at Part 2 ("A grant application of $50,000,000 of CMAQ funds is also pending.").

13

Final Decision of the Federal Transit Administration

referenced the grant numbers and amounts of those grants.42 Preliminary

engineering was included in the ESWA's scope of work.43

In total, Federal funds provided to the ARC Project under the August 20,2009 ESWA

were obligated through six grant agreements that were incorporated into the ESW A and

supported its defined scope of work.

D. NJT Seeks an Expanded ESW A

Shortly after the parties executed the ESW A, NJT requested an amendment to increase

the ESWA's scope of work and provide additional funds for the Project. On October 23,2009

NJT submitted an amended ESW A in TEAM.44 On January 8, 2010, NJT sent FT A a letter

officially requesting an ESW A amendment covering $2.117 billion in project costs-"a $765

million increase over the original $1.352 billion original ESW A"-and additional project

elements, including the Palisades Tunnels, Amtrak Towers, and Kearny Yard Earthwork.45 NJT

contended that the amendment was "critical not only to maintain schedule and budget, but also to

demonstrate a federal funding commitment to the project to match the local funding

commitments that have been in place.,,46 According to NJT, an ESWA amendment would

"continue to unleash more than $5.7 billion in funding allocated by local sources.r'"

Before approving NJT's request, FTA wanted assurance that newly-elected New Jersey

Governor Chris Christie would continue to support the ARC Project." In February 2010,

Secretary LaHood met with Governor Christie to discuss the ARC Project. In that meeting, the

42 See Agency Doc. 2, ESWA, Grant Number NJ-03-0169-00 at Part 2 ("Previous federal CMAQ funds awarded for ARC Preliminary Engineering include NJ-90-X086 ($766,000); NJ-95-X002 ($34,756,000); and NJ-95-X003

($94,680,000). Budget Revision to NJ-95-X003 will reduce ARC funding in the grant ").

43Id. ("The ESW A covers professional services expenses for preliminary engineering ").

44 Agency Doc. 29, NJT Letter to FfA Requesting an Amendment to the ESWA at 1 (Jan. 8, 2010). 45Id.

46Id. at 3.

47Id.

48 See Hynes-Cherin Decl. at ] 69.

14

Final Decision of the Federal Transit Administration

Governor expressed the State's continued support for the Project." By letter following the

meeting, Secretary LaHood advised the Governor that the Federal New Starts commitment to the.

Project would be capped at $3 billion under a future FFGA, and, as is typical with New Starts

projects, "any costs exceeding this amount will be the responsibility of the State and its non-

Federal funding partners.t'" Secretary LaHood sought the Governor's assurance of a continued

commitment to a project implementation plan that would keep the Project on schedule and on

budget to mitigate the potential impact of delays and cost overruns on the State of New Jersey."

In his response letter to Secretary LaHood dated April 6, 2010, Governor Christie stated

that he recognized that the Project was "critical for the transit riders of New Jersey and the

region," and he therefore wrote to, "restate [his] commitment" to the Project, including the funds

controlled by the State.52 In the letter, Governor Christie did not condition the State's

commitment to the Project on the Project remaining within any particular estimated cost range.

The Governor stated that he looked forward to "an expeditious award of the second Early

Systems Work Agreement," and directed NJT's Executive Director James Weinstein to work

with FTA to finalize an FFGA that would commit $3 billion of Federal New Starts funds for the

project "as soon as possible.Y'

On April 14, 2010, a week after receiving this written commitment from the Governor,

FTA and NJT amended the ESW A, providing additional Federal funds for the ARC Project

through additional grants and expanding the scope of work in accordance with NJT's request."

49 Agency Doc. 3, Secretary Ray LaHood Letter to Governor Chris Christie at 1 (Mar. 26, 2010). 50Id.

5! Id.

52 Agency Doc. 4, Governor Chris Christie Letter to Secretary Ray LaHood at 1 (Apr. 6,2010). 53Id. at 1-2.

54 Agency Doc. 6, Amendment to the ESW A, Grant NJ-03-0 169-0 1 at Part 9 (Apr. 14, 2010). The terms of the Amended ESWA, including the scope of work and the sources of funds, are further defined in the January 8, 2010 letter from NIT to FfA, and the April 14, 2010 letter from FfA to NJT. See Agency Doc. 29, NJT Letter to FfA

15

Final Decision of the Federal Transit Administration

Under the amended ESWA, FTA and NJT committed $2,117,050,000 for the ARC Project.55

FTA's commitment included an additional $206,069,932 in New Starts Funds and an additional

$179,050,000 in CMAQ funds, bringing the total Federal share to $1,035,139,932.56 A portion

of the newly available funds provided under the ESW A were obligated through grant agreements

executed either contemporaneously with the amended ESWA or incorporated into the ESWA. In

particular:

• A portion of the New Starts funds committed by the amended ESWA ($47,520,000)

was obligated contemporaneously with the amended ESW A, through a grant

agreement contained in the same TEAM document as the amended ESW A.57

€I The amended ESWA incorporated $6,069,932 in New Starts funds that had been

previously obligated in a separate grant agreement for preliminary engineering,

which fell under the ESW A's scope of work. 58

€I The amendment further referenced the ARRA grant and four CMAQ grants that had

been incorporated into the initial ESW A.59

The amended ESW A also contained detailed budget descriptions for each activity

included within the amended ESWA's scope of work (e.g., Manhattan Tunnel, Tonnelle Avenue,

Requesting an Amendment to the ESWA (Jan. 8,2010); Agency Doc. 5, PTA Letter to NIT Approving an Amendment to the ESWA at 1 (Apr. 14,2010).

55 Agency Doc. 6, Amendment to the ESWA, Grant NJ-03-0l69-0l at Part 2 (Apr. 14,2010). 56 Id. The balance of the funds came from local sources.

57 See Agency Doc. 6, ESWA, Amendment to the ESWA, Grant NJ-03-0169-01 at Parts 2, 3, 9 (Apr. 14,2010).

58 See Agency Doc. 6, Amendment to the ESWA, Grant NJ-03-0l69-0l at Part 2 (Apr. 14,2010) ("This includes ... $6,069,932 of prior New Starts funding used for Preliminary Engineering from a grant that has since closed."). See also Agency Doc. 9, New Starts Grant NJ-03-0l38-02 (Mar. 8,2007) (obligating New Starts funding to support Preliminary Engineering for the ARC Project).

59 See Agency Doc. 6, ESW A, Amendment to the ESW A, Grant NJ-03-0 169-0 1 at Part 2 (Apr. 14, 2010) ("In addition to this grant, $304,050,000 of Federal Highway Administration flex funds have been or will be used to fund this project. The following is the breakdown of the $304,050,000: Prior CMAQ funding awarded for PE consists of FY 2007 funds in the amount of $34,756,000 from NJ-95-X002, $766,000 from NJ-90-X086, and $64,478,000 from NJ-95-X003 (A budged revision is pending to reduce NJ-95-X003 to $64,478,000 from $77,680,000). In addition, FY 2009 CMAQ funds (non-PE) were awarded in the amount of $50,000,000 (NJ-95-X008) .... An additional $130,000,000 of ARRA funds have been awarded under NJ-96-X002.").

16

Final Decision of the Federal Transit Administration

Property Acquisition, etc.).60 Each description contained a breakdown of the funding sources

supporting that particular activity. These descriptions make clear that the activities under the

scope of work were funded by various combinations of local, CMAQ, ARRA, and New Starts

funds, all of which were provided under the ESW A. For instance, after itemizing the sources of

New Starts and local funding eligible for costs incurred for work on the Manhattan Tunnel, the

amended ESW A itemized the CMAQ grants that supported those costs. It then added the local,

New Starts, and CMAQ funds together to reach the total amount of funding provided under the

ESWA:

'Total Eligible Cost' of [the Manhattan Tunnel] line item is $471,474,550. Current New Starts funding funds $15,700,000. Future New Starts grant amendments to this grant will fund $90,132,373. Port Authority funding funds $362,941,000. TTF funding funds $2,701,177. In addition to funding provided through this grant, as amended, there are other grants that also support

costs associated with [the Manhattan Tunnel] line item. Specifically, the FY09 CMAQ grant (NJ-95-X008) funds $30,000,000. Funding in the amount of $30,000,000 will be included in the FYlO CMAQ grant. Funding in the amount of $40,000,000 will be funded by CMAQ grants in FYll and beyond. The total amount offunding provided through the ESWA, as amended, for Manhattan Tunnel direct costl s] is $571,474,550.61

The descriptions provided for the other activities under the amended ESW A's scope of work-

including Tonnelle Avenue, Property Acquisition, Professional Services, Palisades Tunnels,

Amtrak Tower Relocation, and Kearny Yard Earthwork-similarly make clear that the Federal

funding supporting those activities was "provided through the ESWA.,,62 In other words, the

amended ESW A demonstrates that all of the Federal funds-New Starts, ARRA, and CMAQ-

supporting the activities within its scope of work are "provided through the ESW A."

6oId. at Part 3.

61/d. (emphasis added). 62Id.

17

Final Decision of the Federal Transit Administration

In sum, the ESW A and amended ESW A provided certain Federal funds to support a

defined scope of work for the ARC Project. A portion of those funds was obligated to NJT through eight different grants-three New Starts,63 one ARRA,64 and four CMAQ65 grants-that

were either contained in the same document as the ESW A, as amended, or in separate grant

agreements that were incorporated by reference into the ESW A, as amended. Each of these eight

agreements support the specific scope of work set forth by the ESW A, as amended. According

to FT A and NJT records, and discussed below, NJT expended $271,101,291 under the ESW A

through these eight grants-a figure not challenged by NJT.66

E. New Jersey's Termination of the ARC Project

At the time the ESW A amendment was executed, FT A again expressed numerous

concerns with NJT's ability to mitigate major risks associated with the Project." FTA warned

NJT, specifically, that "[t]he scheduled completion date for the project is extremely optimistic

and has the potential to slip, with possible delays ranging from nine to 22 months.,,68 Prior to

any execution of an FFGA, FTA requested further assurances from NJT that NJT would

vigorously mitigate and control project costs.

Following the execution of the ESW A amendment in April 2010, FTA and NJT worked

towards entering into the next phase of the ARC Project and sought to execute by September

63 See Agency Doc. 9, New Starts Grant NJ-03-0138-02 (Mar. 8,2007); Agency Doc. 2, ESWA, Grant Number NJ- 03-0169-00 (Aug. 20, 2009); Agency Doc. 6, Amendment to the ESWA, Grant NJ-03-0169-01 at Part 2 (Apr. 14, 2010). While for ease of reference, PTA describes Grant NJ-03-0169-00 and Grant NJ-03-0169-01 as separate grants, Grant NJ-03-0169-01 is an amendment to Grant NJ-03-0169-00 and they are technically the same grant.

64 See Agency Doc. 14, ARRA Grant NJ-96-X002-01 (Mar. 4, 2010) (original grant at Agency Doc. 38, ARRA Grant NJ-96-X002-00 (Aug. 18,2009)).

65 See Agency Doc. 10, CMAQ Grant NJ-95-X002-00 (Aug. 23,2007); Agency Doc. 11, CMAQ Grant NJ-90- X086-00 (Ju!. 30, 2008); Agency Doc. 12, CMAQ Grant NJ-95-X003-00 (Sept. 10,2008); Agency Doc. 13, CMAQ Grant NJ-95-X008-00 (Sept. 4, 2009).

66 See Agency Doc. 8, PTA Demand Letter to NJT at 1 (Nov. 24, 2010); Agency Doc. 19, NJT Quarterly Report (Sept. 30, 2010); Agency Doc. 7, ARC Expenditures as of 9/30/10.

67 Agency Doc. 5, PTA Letter to NJT Approving an Amendment to the ESWA at 3-4. 68 [d. at 3.

18

Final Decision of the Federal Transit Administration

2010 an FFGA committing a total of $3 billion in Federal New Starts funds. To this end, FTA

initiated the process of updating the risk assessment, consistent with FT A policy and pursuant to

49 U.S.C. § 5309, to ensure that NJT continued to have the financial capacity to carry out the

Project. In addition, FT A and NJT needed to establish a revised baseline cost estimate for the

Project which would take into account NJT's ongoing efforts to mitigate and control the

Project's costs. Accordingly, FTA met with NJT staff on numerous occasions between May and

August of 2010 to discuss different aspects of the cost estimate. FT A used information provided

by NJT during those discussions to prepare a draft risk assessment, including an estimated risk

range, for presentation to NJT.69

On August 16, 2010, representatives from FTA and NJT gathered for a meeting to

discuss the initial working draft of the updated risk assessment with the understanding that FT A

needed to review its assumptions and information with NJT in detail and engage in further

discussion before it could reach a final risk assessment with a revised cost estimate for FFGA

negotiations.i" After FTA's Regional Administrator presented a summary of FTA' s draft risk

assessment, but before any discussion of those results, NJT representatives asked for and took a

five minute recess." When they returned, NJT Executive Director Weinstein informed the FTA

representatives that NJT would not review in detail the draft results of FT A's updated risk

assessment because NJT's representatives believed that none of their input over the last several

months had been incorporated.f The NJT representatives then walked out of the room after

indicating that they would provide their own risk assessment in a few days.73 Notwithstanding

69 Hynes-Cherin Decl., at Ij[ 78. 70 Id. at Ij[ 79.

71 Id. at Ij[ 80.

71 Id. at Ij[ 81.

73 Id. at Ij[ 82.

19

Final Decision of the Federal Transit Administration

NJT's walkout, FTA provided NJT with a copy of its draft 2010 Risk Assessment and the

Regional Administrator's talking points.i"

In the draft 2010 Risk Assessment, FTA preliminarily calculated that the Project's

estimated cost range could be between $10.9 billion and $13.7 billion.i'' These figures increased

from FTA's 2008 cost estimate of $8.4 billion to $12 billion due, in part, to NJT's failure to

aggressively mitigate risks and control project costs. 76 NJT failed to do so despite FTA's

repeated cautionary guidance on this point during: (1) the negotiation and execution of the

original ESW A; (2) the negotiation and execution of the ESWA amendment; and (3) the entirety

of the Final Design process. Indeed, NJT already had expended $775 million of its $1.8 billion

contingency before it even began major construction on the Project." Following the August 16,

2010 meeting, NJT provided FTA with its own projected cost range of $8.7 billion to $10 billion

for the Project.i'' At this point, both NJT and FTA had increased their respective cost estimates

from the original 2008 Risk Assessment. NJT and FTA met again in late September and early

October and continued their discussions regarding the revised risk assessment." Upon

consideration of NJT's estimate, as well as additional information and input provided by NJT,

FTA subsequently reduced its estimated cost range by $1.1 billion on the low end and $1.3

billion on the high end, to a range of $9.8 billion to $12.4 billion.8o

On October 7,2010, while FTA continued to evaluate the Project's progress and its risks

in an effort to further reduce the estimated cost range based on NJT' s input, and more than two

74Id. at'lI 83. See also NJT Silber Ex. 4, FTA ARC Risk Assessment Meeting Notes (Aug. 16,2010).

75 Hynes-Cherin Decl. at'lI 84. See also NJT Weinstein Ex. 2, ARC Steering Committee Memorandum at 5 (Oct. 26, 2010).

76 Hynes-Cherin Decl. at'lI 85. See also NJT Silber Ex. 4, FTA ARC Risk Assessment Meeting Notes (Aug. 16, 2010).

77 Hynes-Cherin Dec!. at'lI 86.

78 Hynes-Cherin Dec!. at'lI 87. See also Agency Doc. 31, NJT ARC Executive Steering Committee Memorandum Recommending ARC Project Termination at 2 (Oct. 7, 2010).

79 Hynes-Cherin Dec!. at'lI'lI 91-93.

80 Hynes-Cherin Dec!. at'lI 94.

20

Final Decision of the Federal Transit Administration

years after FTA notified NIT that it estimated ARC costs could run as high as $12 billion, NJT's

ARC Executive Steering Committee unanimously recommended to the Governor that "the ARC

Project be terminated and that staff immediately begin an expeditious and orderly shutdown of

the project" because the State of New Jersey could not afford to continue it.8l The very next day,

a contingent of DOT and FTA representatives traveled to New Jersey and met with Governor

Christie in an effort to save the Project. DOT provided the Governor with the updated risk range

of $9.8 billion to $12.4 billion, and proposed that FTA and NJT use the lower end $9.8 billion

figure as the baseline cost estimate for an FFGA in light of NJT' s estimated cost range.82

Moreover, DOT pledged additional Federal New Starts funds in the amount of $358 million if

the Port Authority and the State would help fund the difference between the $9.8 billion cost

estimate and the Project's original $8.7 billion baseline cost estimate. 83

In addition to DOT's extra grant support, DOT proposed four options that NJT and the

State of New Jersey might utilize to fund the remaining project costs." First, DOT offered to

provide the State of New Jersey with a low interest Federal Railroad Rehabilitation and

Improvement Financing ("RRIF") loan through the Federal Railroad Administration, which

would have had a repayment period of up to thirty-five years with repayment obligations not to

begin until six years after the first drawdown of the loan. Notably, DOT offered this loan as a

"safety net" that NJT would use only if the actual project costs exceeded the original baseline

cost estimate plus the additional pledge offunds provided by FTA and the Port Authority. If NJT

had mitigated costs as it asserted it would, then NJT never would have had to use the line of

81Agency Doc. 31, NIT ARC Executive Steering Committee Memorandum to Governor Chris Christie Recommending ARC Project Termination at 1, 3 (Oct. 26, 2010).

82 Fl' A normally would require NIT to identify a source of funding to meet the projected mid-range cost estimate, but in this case, Ff A was prepared to allow NIT to use the lower end of the range because NIT continued to assert that it could complete the Project for a lower cost.

83 See DOT's "Options Charts" that DOT provided to Governor Christie on October 8, 2010, Agency Doc. 36, Options to Cover ARC Project Costs (Oct. 8,2010); Agency Doc. 37, The Funding Challenge (Oct. 8, 2010). 84 [d.

21

Final Decision of the Federal Transit Administration

credit provided through the loan. Second, DOT suggested that NIT might avail itself of a RRIF

loan and, additionally, reduce the project scope to reduce costs. Third, DOT suggested that NfT

might enter into a public-private partnership to secure additional funding from private sources

for the Project. Finally, DOT suggested a hybrid approach whereby DOT offered a RRIF loan

for the Portal Bridge,85 and suggested that NIT enter into a public-private partnership to secure

additional funding for the ARC Project.

Despite the numerous options presented by DOT that would have enabled the Project to

continue, on October 26, 2010, NIT Executive Director Weinstein recommended to Governor

Christie that he proceed with the Project's termination." The next day, the Governor terminated

the ARC Project.V After publicly dismissing each of DOT's four suggested options for funding

the additional estimated project costs, and emphasizing his unwillingness to fund those costs

from other sources, Governor Christie stated: "I have instructed Mr. Weinstein to continue the

orderly wind down and closing of this project. This decision is final. There is no opportunity for

reconsideration of this decision on my part. 1 am done. We are moving on.,,88

F. FTA's Debt Collection Action

At the time NIT terminated the ARC Project, FTA had obligated more than $350 million

in Federal funds through grant agreements under the ESW A, and NIT had received

$271,101,291 in Federal payments under it; the balance of the obligated funds had not yet been

85 Although NJT deemed the absence of funding for the Portal Bridge to be "critical," Agency Doc. 31, NJT ARC Executive Steering Committee Memorandum Recommending ARC Project Termination at 2 (Oct. 7, 2010), the Portal Bridge was never a part of the Project and is irrelevant to this debt collection action.

86 Agency Doc. 31, NJT ARC Executive Steering Committee Memorandum Recommending ARC Project Termination at 2 (Oct. 7, 2010).

87 Agency Doc. 34, Transcript of Governor Chris Christie's Public Comments Terminating the ARC Project at 4 (Oct. 27,2010).

88Id.

22

Final Decision of the Federal Transit Administration

expended/" Specifically, NJT drew down a total of $271,101,291 against the eight grant

agreements that obligated funds provided under the ESW A. A November 5, 2010 chart that NJT

submitted to FTA provides a grant-by-grant breakdown of ARC expenditures and calculates

$271,101,291 to be the total amount of Federal funds expended.t" These grants-listed by grant

number-are the same eight grants incorporated into the ESW A, as amended, and used to

obligate the funds under it.91

On November 8, 2010, FTA's Regional Administrator for Region 2 sent NJT a letter and

notified NJT that, based on the Governor's termination of the ARC Project, FT A intended to de-

obligate all unexpended funds and collect all Federal funds expended on the Project.92 A few

weeks later, on November 24,2010, FTA sent NJT a formal "Demand Letter" pursuant to the

Federal Claims Collection Act of 1966, as amended, and initiated an administrative debt

collection action.93 In that Demand Letter, FTA notified NJT that, due to the Governor's

termination of the ARC Project, NJT owed a debt to the United States in the amount of

$271,101,291, the total amount of Federal funds expended on the Project under the ESW A. 94

FT A informed NJT that, within thirty calendar days from the date of receipt of the Demand

Letter, NJT had the following rights: (1) to pay the amount in full; (2) to request FTA to review

the validity or the amount ofFTA's debt claim, stating the legal basis for the dispute; and (3) to

inspect and copy FTA records related to the debt.95 In its Demand letter, FTA notified NJT that

89 Hynes-Cherin Decl. at U 97-98.

90 Agency Doc. 7, ARC Expenditures as of9/30/l0.

91 [d. The chart lists seven grants, instead of eight, because it treats the ESWA (NJ-03-0169-00) and ESWA amendment (NJ-03-0169-01) as one grant.

92 Agency Doc. 35, PTA Letter to NJT Regarding Repayment of Federal Funding (Nov. 8,2010).

93 Agency Doc. 8, PTA Demand Letter to NJT at 1 (Nov. 24, 2010). See 31 U.S.C. Chapter 37 (2006).

94 Agency Doc. 8, PTA Demand Letter to NJT at 1 (Nov. 24, 2010). See Agency Doc. 19, NJT Quarterly Report (Sept. 30,2010); Agency Doc. 7, ARC Expenditures as of 9/30/10.

95 Agency Doc. 8, PTA Demand Letter at 2.

23

Final Decision of the Federal Transit Administration

if NJT did not exercise its right to repay the debt that it owes to the United States, then FTA

would exercise its rights to collect the debt, including administrative offset. 96

By letter of December 10, 2010, representatives of Patton Boggs LLP notified FTA that

they had been engaged as counsel to represent NJT in FTA's debt collection action." On

December 13, 2010, and December 14, 2010, NJT had telephone conversations with FTA's

Deputy Chief Counsel and requested "a standstill of the administrative process," or alternatively,

a thirty day extension of time to respond to FTA's Demand Letter pursuant to FTA's Debt

Collection Order.98 By letter of December 15, 2010, NJT followed up with a written request for

a thirty day extension of nme." By letter of December 20, 2010, FTA granted NJT its first

extension of time to respond to FT A's Demand Letter and set a deadline of January 10, 2011. 100

By letter of December 23, 2010, NJT asked FT A to grant it an additional extension of

time to respond to FTA's Demand Letter. 101 After several subsequent discussions, FTA granted

NJT a second extension of time to respond to FTA's Demand Letter and set a deadline of

January 18, 2011.102

On January 11, 2011, representatives from FTA and NJT met to discuss FTA's debt

collection action. In that meeting, NJT requested a third extension oftime to respond to FTA's

Demand Letter, which FTA granted, allowing NJT to respond on or before January 25,2011.103

In sum, pursuant to FTA's Debt Collection Order, FT A granted NJT the maximum amount of

96 [d.

97 NIT Letter to FTA (Dec. 10,2010).

98 See Federal Transit Administration (FT A) Order 2060. lA, Internal Procedures for Debt Collection (July 2, 2008). 99 NJT Letter to FTA at 1-3 (Dec. 15,2010).

100 FTA Letter to NJT at 1 (Dec. 20, 2010).

101 NJT Letter to FTA at 2 (Dec. 23, 2010).

102 FTA Letter to NJT (Jan. 7,2011).

103 FTA Letter to NJT (Jan. 14,2011); FTA Letter to NJT (Jan. 13,2011).

24

Final Decision of the Federal Transit Administration

time allowable-sixty calendar days from the date of receipt ofFTA's Demand Letter-to

submit a formal response. 104

Although the Federal Claims Collection Act of 1966, as amended, and the joint United

States Department of Justice ("DOJ") and United States Department of Treasury ("Treasury")

Debt Collection Regulations instruct Federal agencies to provide debtors with the opportunity to

inspect and copy agency records related to the debtor's debt, NJT submitted to FT A several

broad and sweeping requests throughout this administrative debt collection process for the

opportunity to inspect and copy thousands of unrelated agency records corresponding to the

P . 1'05

roject.

In response to NJT's requests, on December 15, 2010, and January 11, 2011, FTA

provided NJT with substantial volumes of documents related to NJT's debt, including relevant

grant agreements, FTA Master Agreements, NJT Quarterly Progress Reports, internal FTA

memoranda, and various correspondence between NJT and FT A.

On January 25,2011, citing these and other documents, NJT sent to FTA by electronic

mail NJT's response to FTA's Demand Letter (hereinafter "NJT's Response" or "NJT's

Opposition to Demand"), which included over 3,000 pages of documents that NJT asserts are

related to the debt. On January 27,2011, NJT sent to FTA a hard copy of NJT's response.i'"

This Final Decision of the FTA follows.l'"

104 FTA Letter to NJT (Jan. 14,2011).

105 NJT Letter to FTA at 5-8 (Dec. 15,2010); NJT Letter to FTA at 1 (Dec. 23, 2010). FTA notes that NJT submitted two letters to FTA on December 23, 2010, requesting the opportunity to inspect and copy all agency records related to the Project.

106 For consistency, throughout this Final Decision, FTA will cite to the hard copy version of NJT's Response, which is an amended version of the electronic Response that NJT submitted to FTA on January 25, 2011. PTA notes that NJT submitted its hard copy Response two days after the deadline.

107 FT A attaches and cites to three additional documents and the Declaration of Ms. Brigid Hynes-Cherin in support of this Final Decision. The Declaration includes twenty-seven Exhibits; ten of which FT A is adding to the record of this debt collection proceeding. Although FT A did not provide these documents to NJT throughout the course of the administrative debt collection proceeding because they are related to the Project and not related to the debt, the

25

Final Decision of the Federal Transit Administration

IV. LEGAL FRAMEWORK

FTA has authority to collect all Federal funds expended on the ARC Project. FTA's legal.

authority to collect all Federal New Starts, CMAQ, and ARRA funds expended on the Project

under the ESWA is derived from: (1) the ESWA provisions of FTA's authorizing statute; (2) the

ARC Project's Master Agreements; (3) the "Common Grant Rule"; (4) the Federal Claims

Collection Act of 1966, as amended; 108 (5) the joint DOJ and Treasury Debt Collection

Regulations; (6) DOT's Debt Collection Regulations; and (7) FTA's Debt Collection Order.

Under 49 U.S.C. § 5309(g)(3)(B)(iv) (the "Repayment Provision"), "If an [ESWA]

applicant does not carry out the project for reasons within the control of the applicant, the

applicant shall repay all Government payments made under the work agreement plus reasonable

interest and penalty charges the Secretary establishes in the agreement.r''l"

As discussed in more detail below, Governor Christie and NJT terminated the ARC

Project for reasons within their control, and therefore, New Jersey must repay all Federal

payments made under the ESWA.

Moreover, pursuant to each of the Master Agreements that NJT voluntarily entered into

with FTA to receive Federal funds for the ARC Project, NJT was subject to the following terms

and conditions:

If ... the Federal Government determines that the Recipient has willfully misused Federal assistance by failing to make adequate progress, by failing to make reasonable and appropriate use of Project property, or by failing to comply with the terms of the Grant Agreement or Cooperative Agreement for the Project

transmittal of the documents with this Final Decision has not prejudiced NJT's ability to respond to PTA's claim because each of the documents was in NJT's possession prior to the initiation of this debt collection proceeding. Moreover, PTA includes these documents with its Final Decision because they are necessary to respond to NJT's arguments.

108 The Federal Claims Collection Act of 1966 is codified at 31 U.S.c. Chapter 37, and it has been amended by the Debt Collection Improvement Act of 1982, the Debt Collection Amendments of 1986, and the Debt Collection Improvement Act of 1996.

10949 U.S.C. § 5309(g)(3)(B)(iv) (emphasis added).

Final Decision of the Federal Transit Administration

including this Master Agreement, the Federal Government reserves the right to require the Recipient to refund the entire amount of Federal assistance provided for the Project or any lesser amount as the Federal Government may determine. I 10

Additionally, the Master Agreements provide: "Unless prohibited by Federal law or regulation,

the Federal Government may recover any Federal assistance as necessary to satisfy any

outstanding monetary claims that the Federal Government may have against the Recipient." III

By terminating the ARC Project, the State of New Jersey willfully failed to make any

further progress on the Project. As such, in addition to the above-referenced mandatory statutory

repayment obligation, FT A has authority under the Master Agreements corresponding to each of

the ARC Project's New Starts, CMAQ, and ARRA grants to collect all of the Federal funds

expended under those agreements.

FT A has additional authority under the plain terms of the Common Grant Rule at 49

C.F.R. Part 18 to collect Federal funds that it expends on a project if a grantee fails to carry out a

project. Pursuant to the Common Grant Rule:

If a grantee or subgrantee materially fails to comply with any term of an award, whether stated in a Federal statute or regulation, an assurance, in a State plan or application, a notice of award, or elsewhere, the awarding agency may ... take ... remedies that may be legally available.112

Again, in the instant case, Governor Christie and NJT terminated the ARC Project and failed to

carry it out under the terms and conditions of each of the Master Agreements corresponding to

lID .

Agency Doc. 24, PTA Master Agreement for Fiscal Year 2011 at § 11 (Oct. 1,2010). See Agency Doc. 23, PTA

Master Agreement for Fiscal Year 2010 at § 11 (Oct. 1,2009); Agency Doc. 22, PTA Master Agreement for Fiscal Year 2009 at § 11 (Oct. 1,2008); Agency Doc. 21, PTA Master Agreement for Fiscal Year 2008 at § 11 (Oct. 1, 2007); Agency Doc. 20, PTA Master Agreement for Fiscal Year 2007 at § 11 (Oct. 1,2006). See also 49 U.S.C. § 5309(c)(3) ("The Secretary shall require that any grant awarded under this section to a recipient be subject to all terms, conditions, requirements, and provisions that the Secretary determines to be necessary or appropriate for the purposes of this section.").

III Agency Doc. 24, PTA Master Agreement for Fiscal Year 2011 at § 9(e)(2) (Oct. 1,2010). See Agency Doc. 23, PTA Master Agreement for Fiscal Year 2010 at § 9(e)(2) (Oct. 1,2009); Agency Doc. 22, PTA Master Agreement for Fiscal Year 2009 at § 9(e)(2) (Oct. 1, 2008); Agency Doc. 21 , PTA Master Agreement for Fiscal Year 2008 at § 9(e)(2) (Oct. 1,2007); Agency Doc. 20, PTA Master Agreement for Fiscal Year 2007 at § 9(e)(2) (Oct. 1,2006). 11249 C.F.R. § 18.43(a)(5) (2010).

26

27

Final Decision of the Federal Transit Administration

the New Starts, CMAQ, and ARRA grants for the Project. Therefore, the Common Grant Rule

authorizes FTA to take any remedy that may be legally available, including collection of all

Federal funds expended on the Project.

FTA also has authority under the Federal Claims Collection Act of 1966 and its

amendments-most significantly, the Debt Collection Improvement Act of 1996-to collect

funds owed to the Federal Government arising out of FTA activities. Pursuant to those statutes,

"The head of an executive, judicial, or legislative agency ... shall try to collect a claim of the

United States Government for money or property arising out of the activities of, or referred to,

th ~ 113

e agency."

As used in the statutes, the terms "claim" and "debt" are synonymous and

interchangeable, and mean "any amount of funds or property that has been determined by an

appropriate official of the Federal Government to be owed to the United States by a person,

organization, or entity other than another Federal agency.v'!" The expansively defined term

"claim" includes, without limitation, "any amount the United States is authorized by statute to

collect for the benefit of any person," "the unpaid share of any non-Federal partner in a program

involving a Federal payment and a matching, or cost-sharing, payment by the non-Federal

partner," and "other amounts of money owed to the Government." I 15

DO] and Treasury jointly promulgated regulations that implement these statutory

provisions. Pursuant to the joint DO] and Treasury Debt Collection Regulations, "Federal

11331 U.S.C. § 37 11 (a)(1). 114 31 U.S.c. § 3701 (b)(1). lIS Id.

28

Final Decision of the Federal Transit Administration

agencies shall aggressively collect all debts arising out of activities of, or referred or transferred

for collection services to, that agency." I 16

DOT promulgated its own Debt Collection Regulations at 49 C.F.R. Part 89 and FTA

promulgated its own guidance-FTA's Debt Collection Order-that implement the Federal

Claims Collection Act of 1966, as amended.l '" The regulations and FT A's internal order require

FTA to aggressively collect debt.

In sum, under the ESW A statutory provision, the terms and conditions of the Master

Agreements, the Common Grant Rule, and all of the applicable debt collection statutory,

regulatory, and administrative provisions, FTA has a mandate to collect all New Starts, CMAQ,

and ARRA funds expended on the ARC Project under the ESW A.

v. ANALYSIS

In support of its opposition to FTA's request for repayment, NJT makes a series of

arguments. First, NJT contends that the ARC Project failed to proceed for reasons outside of

NJT's control-specifically, where a cost estimate of the Project indicated that the cost likely

would increase and where a fiscal crisis was impacting the State of New Jersey-and therefore,

NJT has no obligation to repay $271,101,291 to the United States. Second, NJT argues that the

ESWA included funds only from FTA's New Starts program, and therefore, FTA cannot recover

CMAQ and ARRA payments made to NJT. Third, according to NJT, equitable and policy

considerations mandate that no repayment obligation should be imposed on NJT. After careful

consideration, based on the facts in the record and applicable legal authority, FTA finds these

11631 C.F.R. § 901.1(a). Similar to the statutory definitions, DO] and Treasury define the terms "debt" and "claim" synonymously and interchangeably. They refer to "an amount of money, funds, or property that has been determined by an agency official to be due the United States from any person, organization, or entity, except another Federal agency." 31 c.F.R. § 900.2(a).

117 See 49 C.F.R. Part 89; PTA Order 2060. l A, Internal Procedures for Debt Collection (July 2, 2008).

29

Final Decision of the Federal Transit Administration

arguments to be without merit and that NJT is required to repay the funds in question under the

Repayment Provision and Master Agreements.

A. The State of New .Jersey's Decision to Terminate the ARC Project Was a Discretionary Decision Within Its Control.

Pursuant to the statutory Repayment Provision, "If an applicant does not carry out the

projectfor reasons within the control of the applicant, the applicant shall repay all Government

payments made under the work agreement plus reasonable interest and penalty charges the

Secretary establishes in the agreement.,,118 In this case, FTA provided NJT with $271,101,291 in

Federal funds under the ESW A for the ARC Project and NJT and Governor Christie

subsequently terminated the Project for reasons manifestly within their control. Their

termination of the Project also constituted a willful failure to make adequate progress on the

Project. Accordingly, pursuant to the Repayment Provision, and the terms and conditions of the

Master Agreements, NJT has an affirmative obligation to pay back $271,101,291 to the Federal

Government.

In its Response to FTA's Demand Letter, NJT argues that the ARC Project failed to

proceed for reasons outside ofNJT's control, and therefore, NJT has no obligation to repay any

Federal funds expended on the proj ect. 119 NJT identifies these reasons as the allegedly drastic

and unexpected increases in FTA's cost estimates for the Project and NJT's alleged lack of

control over FTA's cost estimate methodology. For the reasons discussed below, FTA finds that

these arguments are unsupported by the administrative record and are otherwise without merit; to

the contrary, the record shows that the cost estimate increases were neither drastic nor

ll8 49 V.S.c. § 5309(g)(3)(B)(iv) (emphasis added).

ll9 NJT Opposition to Demand at 17-44 (Jan. 25, 2011).

30

Final Decision of the Federal Transit Administration

unforeseeable and that NJT had significant input into and control over FTA's cost estimate

calculations. Thus, NJT terminated the Project for reasons manifestly within its control,

1. NJT's fears of escalating cost estimates and New Jersey's own financial difficulties do not constitute reasons for the State to terminate the Project that are outside of its control.

In its Response, NJT contends that FTA unilaterally, "drastically," and "unexpectedly"

increased the cost estimate for the ARC Project in June 2010 to an amount greater than $S.7

billion.12o The administrative record contradicts NJT's contention. As early as August 200S, in

collaboration with NJT, FTA estimated the cost of the Project to range from $S.4 billion to $12

billion, and FT A provided this estimate to NJT as part of the collaborative process of

determining the Project's estimated cost. When the Project neared the potential execution of an

FFGA, FTA initiated the process of updating a Risk Assessment, and in August 2010, based on

risk assumptions that were the subject of ongoing negotiations between FTA and NJT, FTA

preliminarily estimated the updated cost of the Project to range from $10.9 billion to $13.7

billion. After receiving input from NJT and reassessing certain assumptions regarding costs, in

October 2010, FTA provided NJT with a lower revised cost estimate with $9.S billion as the low

end estimate, $10.9 billion as the mid range estimate, and $12.4 billion as the high end estimate.

The record thus demonstrates that, contrary to NJT's characterization, the increase in the range

was neither "drastic" nor "unexpected," but was in fact well within NJT's contemplation,

particularly given its ability to influence the risk assessments and control its own cost mitigation

measures. Moreover, the increase in the cost estimate range was not unusual for a New Starts

project. 121

120 Id. at 17-18.

121 Hynes-Cherin Decl. at <J[ 85.

31

Final Decision of the Federal Transit Administration

NJT's objection to these cost estimates derives from the requirement that a grantee bear

all additional costs on a project after FTA approves a project into Final Design. 122 NJT .argues

that, in light of the revised cost estimates in 2010, NJT could not commit additional funds to the

Project because a fiscal and economic crisis was impacting the State of New Jersey. 123

According to NJT, "To continue performance of the ARC Project, given FTA's dramatic cost

increases, would have been fiscally and financially irresponsible for the State and NJT.,,124

With respect to DOT's alternative proposals to save the Project, NJT asserts that the

Governor had no choice but to reject DOT's offer to provide NJT with a loan because the loan

would place the State of New Jersey into deeper debt.125 In addressing DOT's suggestion that

NJT enter into a public-private partnership as an option to secure funding for NJT's additional

share, NJT argues, based partly on remarks made in the press by the former governor of a

different state who had no involvement in the ARC Project, that it might have had to spend a

significant amount of time entering into a partnership with no guarantee that the partnership

would be at an acceptable price or on terms acceptable to the State of New Jersey. 126

In sum, NJT argues, based on (1) FTA's 2010 cost estimates, (2) the requirement that

NJT bear any costs exceeding the original baseline cost estimate, and (3) the fiscal and economic

crisis impacting the State of New Jersey, that the Governor and NJT had no choice but to

terminate the Project for reasons beyond their control. 127 NJT's fears of escalating cost estimates

and the State of New Jersey's own financial difficulties do not, however, excuse NJT's non-

122 Pursuant to FTA's 2006 Guidance on New Starts Policies and Procedures, "Once [a] project is approved into final design, any increase in project costs will be borne by the sponsoring agency and its non-section 5309 New Starts funding partners." FTA 2006 Guidance on New Starts Policies and Procedures at 9, available at http://www.fta.dot.gov/planning/newstarts/planning_environment_5203.html (May 16,2006).

123 NJT Opposition to Demand at 18-33.

124 [d. at 27.

125 [d. at 30-31. 126 [d. at 31.

127 NJT Opposition to Demand at 17-44.

32

Final Decision of the Federal Transit Administration

compliance with the ESW A and the Repayment Provision or its obligation under the Master Agreements.

First, even assuming the accuracy of NJT' s claims regarding its difficulties of funding the Project in light of its budget issues, the State of New Jersey's own budget issues are, by definition, circumstances within the State of New Jersey's control. Indeed, NJT's Response repeatedly acknowledges the State of New Jersey's control over its own budget. For instance, NJT recognized in its Response that (1) New Jersey "defer[red] its $3 billion pension contributions and ... reduce[d] school aid by $1.7 billion, municipal aid by $334 million, and higher education assistance by $178 million" to meet a balanced budget; (2) New Jersey can assess taxes to raise additional revenue; and (3) New Jersey has control over disbursements from the New Jersey Transportation Trust Fund. 128

As NJT concedes in its Response, the State of New Jersey has a $30 billion annual budget, and in managing that budget, the Governor makes discretionary decisions on a regular basis regarding the programs and projects that the State should fund, the programs and projects that the State should not fund, and whether the State should raise additional revenue to increase its operating budget. From the inception of the Project, the State decided to allocate resources from its budget to fund the Project, until it decided in October 2010 to allocate those resources elsewhere. Once NJT requested and entered into an ESW A-and subsequently amended the ESWA after Governor Christie took office and affirmed the State's support for the Project-it knowingly accepted a Federal financial commitment with clearly stated statutory and contractual repayment obligations should New Jersey fail to comply with the requirements of that commitment. Governor Christie's wholly discretionary budget decisions with respect to its revenue pool and the allocation of its operating budget do not obviate or supersede those

128 [d. at 25, 29.

33

Final Decision of the Federal Transit Administration

statutory and contractual obligations.i'" If they did, then any ESW A recipient would simply be

able to walk away from a project anytime it decided that it would be in its best interest to direct

its resources elsewhere, rendering the Repayment Provision meaningless.

Second, the fact that NJT rebuffed DOT's final efforts to save the Project demonstrates

that it was NJT-not FTA-that controlled the termination of the Project. As acknowledged in

NJT's Response, NJT and Governor Christie rejected four different proposals offered by DOT to

save the Project, including (1) a RRIF loan through the Federal Railroad Administration, (2) a

RRIF loan combined with a reduction in the Project's scope, (3) a public-private partnership

which would have infused financing from outside sources, and (4) a RRIF loan to fund the Portal

Bridge, combined with a public-private partnership. And while NJT dismissed the loan

proposals by arguing that New Jersey could not increase its debt load, the Governor subsequently

made a discretionary decision to fund future transportation projects by taking on additional and

substantial debt.13o Governor Christie's unilateral termination of the project, and his rejection of

feasible alternatives presented by DOT, demonstrates that the termination of the Project was

willful and based on reasons squarely within New Jersey's control.

129 Indeed, if a grantee's own budgetary pressures provide a legally recognized carve-out from the repayment obligations of an ESWA, then it would create an enormous exception that swallows the rule. Any grantee debtor always could point to budgetary pressures as a reason to terminate a project and escape the ESWA's repayment obligations.

130 Patrick McGeehan, Christie Outlines a Plan to Pay jor Transit Work, N.Y. TIMES, available at http://www.nytimes.coml2011101l07 Inyregion/07christie.html? _r=l , Jan. 6, 2011 ("Gov. Christie of New Jersey laid out a plan on Thursday to pay for five years of work on the state's roads, rails and bridges by borrowing $4.4 billion."); NORTHJERSEY.COM, The Record: Another Band-Aid, available at http://www.northjersey.comlnews/opinions!113186934_Another_Band-Aid.htm1. Jan. 10,2011 ("Governor Christie unveiled his grand plan for the [Transportation Trust Fund] on Thursday: Borrow more money.").

34

Final Decision of the Federal Transit Administration

2. NJT controlled the actual costs incurred on the ARC Project and its assertion that the increasing cost estimate was beyond its control is without merit.

NJT argues that the processes, methods, and assumptions that FT A used when conducting

its 2010 Risk Assessment were beyond NJT's control, and therefore, justified the Project's

termination. 131 This argument is similarly without merit. Setting aside the fact that NJT had

ample input into the Risk Assessment and the baseline cost estimate, NJT's argument based on

an increasing estimate is misplaced given that NJT had, at all times, firm control over the actual

costs incurred on the Project, which drive the estimates on an ongoing and continuous basis.

Because NJT had undisputed control over the costs incurred on the Project, FTA finds that any

change in the cost estimate does not constitute a reason to terminate the Project that was beyond

NJT's control.

Specifically, NJT alleges that FTA conducted its 2010 Risk Assessment without any

input from NJTY2 NJT states it strongly disagreed with FTA's re-estimate, and during the

summer of 2010, NJT asserts that it attempted to demonstrate that it could deliver the Project at

or near $8.7 billion. 133 NJT attempted to demonstrate how it had mitigated several major risk

areas.134 In an effort to account for FTA's concerns, NJT even presented its own revised cost

estimate with $9.5 billion as the most likely cost of the Project. 135

NJT further argues that FT A considered improper factors when revising the risk

assessment, even though there were no material changes in the Project itself. 136 However, the

arrival at various estimates involved a collaborative effort between NJT and FT A. The initial

131 NJT Opposition to Demand at 32-40. 132 [d. at 38.

133 [d. at 40.

134 [d. at 40.

135 [d. at 38. Notably, with NJT presenting $9.5 billion as the most likely cost, and PTA's low end estimate of $9.775 billion, the parties were less than $300 million apart at the time the Project was terminated.

136 [d. at 41-44.

35

Final Decision of the Federal Transit Administration

August 2008 baseline cost estimate was reached only after rounds of discussions between NJT and FT A regarding the Project's scope and its various inputs. As detailed above, NJT understood at all times that the estimates were subject to ongoing negotiations between NJT and FTA and further subject to actual Project progress and cost mitigation by NJT. In arriving at the revised October 2010 baseline cost estimate, FTA first presented a draft risk assessment to NJT, and then subsequently revised and adjusted the risk assessment after reviewing and considering multiple submissions from NJT, including NJT's own draft cost estimate. In other words, a baseline cost estimate could only be reached after receiving data and other informational input from NJT, including the actual costs incurred by NJT to date.

To be clear, there is a distinction between the act of estimating costs and the act of controlling costs. Both parties-FTA and NJT-had the ability to estimate costs, but only NJT had the ability to control costs. FTA's role with respect to costs throughout the Project, as with all New Starts projects, was to re-estimate costs in collaboration with NJT at each decision point before it committed additional Federal investments, taking into account NJT's actual costs to date. NJT's role was to manage the Project and to enter into contracts to deliver the Project, and at all times, NJT had the ability to control the actual costs of these contracts. FTA was never a party to these contracts and had no ability to intervene and control the actual Project's costs. NJT's efforts, notwithstanding any FTA estimate to the contrary, demonstrate that NJT controlled and believed that it controlled the ability to complete the Project at or near the originally projected cost of $8.7 billion. It is apparent in NJT's argument that NJT was in firm control of the actual costs expended on the Project, the management of the Project, and the use of Federal funds for the Project under the ESW A. Again, even assuming for the sake of argument that NJT had limited control over the Project's cost estimate, NJT cannot cite to a rising cost

36

Final Decision of the Federal Transit Administration

estimate as a reason justifying the termination of the Project when it had firm control of the

actual costs expended.

In short, NJT's argument fails because it is based on an estimate-the mere potential that

NJT would have to pay actual excess costs beyond an estimated figure. As the party negotiating

the underlying construction contracts and managing the Project, NJT always was in control of

the actual costs that it incurred on the Project. FTA awarded substantial amounts of Federal

funds for the ARC Project due to NJT's commitment and responsibility under the ESW A and the

Master Agreements to manage and deliver the Project within the agreed upon $8.7 billion

budget. FT A obligated funds under the ESW A to reimburse NJT as NJT-not FT A-incurred

costs for the Project. Consequently, because NJT's ability to support the Project was based on its

ability to pay actual costs, not estimated costs, its argument based on the cost estimate fails.

In summary, the increase in the cost estimate range was not drastic and was well within a

foreseeable range for the ARC Project. New Jersey's fiscal difficulties do not change these facts.

FTA and NJT jointly and collaboratively calculated the cost estimates, which were based on

actual costs that were, at all times, within NJT's control. Accordingly, FTA finds that the

Governor and NJT terminated the Project for reasons entirely within their control.

B. The Early System Work Agreement Included New Starts Funds, CMAQ Funds, and ARRA Funds-All of Which Must Now be Repaid.

In its Response to FTA's Demand Letter, NJT argues that the ESWA included only New

Starts funds.!37 In particular, NJT argues that as a matter of law, only New Starts funds may be

included in an ESW A and are subject to the Repayment Provision. Furthermore, NJT contends

that as a matter of fact, the ESWA, as amended, only obligated New Starts funds. As addressed

137 Id. at 4-16.

37

Final Decision of the Federal Transit Administration

in more detail below, FT A disagrees with NJT's interpretation of the law and facts, and finds that

the ESWA can, and did, include New Starts and non-New Starts funds.

1. An ESWA may include more than New Starts funds.

In its Response, NJT argues that "the ESWA statute applies only to New Starts funds.,,138

NJT's assertion is incorrect as 49 U.S.C. § 5309 does not limit the scope of an ESWA to New

Starts funds. There is no language in title 49 of the United States Code that provides such a

limitation. To the contrary, pursuant to 49 U.S.C. § 5309(g)(3)(B)(i), an ESWA "obligates an

amount of available budget authority specified in law.,,139

GAO defines budget authority as "[a]uthority provided by federal law to enter into

financial obligations that will result in immediate or future outlays involving federal government

funds.,,140 Thus, "available budget authority" includes not only New Starts funds but all Federal

financial assistance provided to the ARC Project under the ESW A. The plain meaning of 49

U.S.C. § 5309(g)(3)(B)(i) does not limit the scope of an ESWA to New Starts funds; rather, the

plain meaning allows an ESW A to include within its scope any source or type of Federal

funding.

NJT also cites 49 U.S.C. § 5309(g)(4) in support of its argument that ESWAs may

include only New Starts funds, but this reliance is misplaced. This paragraph describes

contingent commitment authority, which applies to "future obligations of the Government and

contingent commitments to incur obligations.v"" This paragraph, by its terms, does not apply to

138 NIT Opposition to Demand at 5. 13949 U.S.c. § 5309(g)(3)(B)(i).

140 UNITED STATES GOVERNMENT ACCOUNTABILITY OFFICE, GLOSSARY OF TERMS USED IN THE FEDERAL BUDGET PROCESS at 20 (2005).

14149 U.S.c. § 5309(g)(4)(A).

38

Final Decision of the Federal Transit Administration

current year or previously obligated funds at issue in this debt collection action, and does not

alter the plain meaning of 49 V.S.c. § 5309(g)(3)(B)(i).

2. NJT and FTA expressly included ARRA, CMAQ, and previously expended funds in the ESW A, and FTA's payment of these funds to NJT constituted payments under the ESW A.

NJT argues that the ESW A, as amended, obligates only certain New Starts funds and expressly excludes all CMAQ, ARRA, and previously awarded New Starts funds.142 In

particular, NJT argues that the only payments made under the ESWA are the New Starts funds

that were obligated in the same documents wherein the parties executed the ESW A and its

amendment. 143

NJT's argument fundamentally confuses the grant documents that obligate New Starts

funds included in the ESW A with the ESW A itself. While the ESW A and ESW A amendment

were executed in documents that also obligated certain New Starts funds, the ESW A is not

limited to those obligations. Instead, as described above, the ESW A and ESWA amendment set

forth a defined scope of work for the ARC Project and provided certain funds in support of that

work. Because of legal requirements, accounting rules, limitations ofFTA's financial

management system, and timing constraints, FT A obligated the ESW A funds in separate grant

agreements. The fact that different program funds included in the ESW A were obligated through

different grants, as FTA systems require, does not convert the funds NJT drew down from those

grants into payments outside the ESW A.

The Repayment Provision is not limited to funds that were obligated in the same

document wherein the parties executed the ESW A. Rather, it requires repayment of all Federal

142 NJT Opposition to Demand at lO.

[43 Agency Doc. 2, ESWA, Grant NJ-03-0169-00 (Aug. 14,2009) (obligating $14,700,000 in New Starts funds); Agency Doc. 6, ESWA Amendment, Grant NJ-03-0169-01 (Apr. 14,2010) (obligating $47,520,000 in New Starts funds).

39

Final Decision of the Federal Transit Administration

"payments made under the work agreement." This provision encompasses all Federal payments

made under the ESW A, whether they were obligated through the ESW A-executing document or

in a separate document and whether they are New Starts funds or from some other available

budget authority. NJT's argument that funds are not "under the work agreement" unless they

were obligated in the same document as the ESW A elevates form over substance and undermines

the statutory purpose of the ESW A, which is, to "promote ultimate completion of the project

more rapidly and at less COSt.,,144

NJT's argument that ARRA, CMAQ, and previously-obligated New Starts funds were

not included in the ESWA is undermined by the parties' clear understanding, evidenced in the

grant documents and the administrative record. For instance, the Line Item Extended Budget

Descriptions in the amended ESWA (NJ-03-0169-01) include the ARRA and CMAQ grants as

sources of funds. 145 For example, the Line Item "Professional Services" in the amended ESW A

is described as follows:

The 'Total Eligible Cost' of this line item is $250,407,968. New Starts funding in this amendment funds $44,520,000. Future New Start grant amendments to this grant will fund $87,101,077. Port Authority funding funds $43,943,000. TTF funding funds $74,843,891. In addition to funding provided through this grant, as amended, there are other grants that also support costs associated with this line item. Specifically, the FY09 ARRA 5307 grant (NJ- 96-SX002) funds $112,117,000. Prior New Starts Grant NJ-03- 138 provided $6,069,932. Prior CMAQ grants NJ-90-X086, NJ- 95-X002, and NJ-95-X003 will fund $100,000,000 of the cost.

The FY09 CMAQ grant (NJ-95-X008) funds $5,000,000. Future CMAQ grants will fund $52,000,000. The total amount offunding provided through this ESWA, as amended, for Professional Services is $525,644,000.146

14449 V.S.c. § 5309(g)(3)(A)(ii).

145 Agency Doc. 6, ESWA Amendment, Grant NJ-03-0169-01 at Part 3, Line Items 14.01.10, 14.06.60, 14.08.80, and 14.04.40 (Apr. 14, 2010).

146 Grant NJ-03-0169-01 at Part 3, Line Item 14.08.80 (emphasis added).

40

Final Decision of the Federal Transit Administration

In six other budget categories in Grant NJ-03-0169-01, NJT repeated this description of the line

item budget amount as encompassing New Starts, ARRA, and/or CMAQ funds, and indicated

that these funds are provided through the ESWA. The language in these grants clearly conveys

both parties' understanding and NJT's agreement by its signature on the grant that the ESW A

and its amendment included more than the New Starts grants and more than New Starts funds.

Moreover, NJT's correspondence to FTA regarding the proper scope of the ESWA

during its negotiation confirms that NJT specifically requested, indeed demanded, that

previously spent CMAQ and New Starts funds be included in the ESW A:

If the $6 M prior New Starts grant were removed from the ESW A, then an amount of "Non-section 5309 New Starts funding" would need to be removed from the ESW A scope consistent with the approximate two thirds/one third New Starts match. If that were done, the total ESWA scope would fall by approximately $18 million from $1.352 billion and the New Starts amount would fall by approximately $6 M from $400 M. ($12 M non-New Starts and $6 M New Starts)

Similarly, if the over $100 M of non-New Starts funds [CMAQ] expended on PE [Preliminary Engineering] were removed from the ESW A, then New Starts funds would need to be removed from the ESW A as well-consistent with the New StartINon New Start ratio of about one third to two thirds. So over $100 M of non-New Starts and $50 M of New Starts would need to be removed from the scope of the ESW A, lowering the total ESW A and the New Starts amount. Neither of these outcomes is desirable.Y"

As this correspondence demonstrates, NJT requested that the previously expended grants

be included in the ESWA to make additional Federal funds available to NJT, sourced from New

Starts and non-New Starts programs, and to demonstrate a robust Federal commitment to the

Project.148 By doing so, and obtaining the benefit of additional Federal funding in the ESWA

147 Agency Doc. 25, NJT E-mail to PTA Regarding the ESWA (June 5,2009). Ultimately, the $6,069,932 in prior New Starts funds were not included in the original ESW A, but they were included in the amended ESW A. See Agency Doc. 6, Amendment to the ESWA, Grant NJ-03-0l69-0l at Part 2 (Apr. 14,2010) ("This includes ... $6,069,932 of prior New Starts funding used for Preliminary Engineering from a grant that has since closed.").

148 See id.

41

Final Decision of the Federal Transit Administration

and its associated obligations, NJT is estopped from denying that payments under the ESW A,

including payments made prior to the execution of the ESW A and payments of non-New Starts

funds, constitute "payments made under the work agreement" under the Repayment Provision.

Inclusion of these funds allowed NJT to increase the scope of the ESW A. By insisting on, and

subsequently receiving, the direct benefits attendant to the inclusion of the other grants in the

ESW A, NJT cannot now attempt to shirk the obligations of the Repayment Provision.149

NJT argues that even if the ARRA and CMAQ funds were payments under the work

agreement, repayment is not necessary because they were "subtracted out of the ESWA cost."

NJT bases this argument on a misreading of a statement in the ESWA that describes the total

eligible cost under the New Starts grant. In particular, under the heading "Grant in Team," the

ESW A describes how the total eligible cost for the New Starts grant was calculated:

This grant outlines future New Starts funds that will be allocated to the ESW A. All future New Starts funds, including state match are shown in the column labeled Total Eligible Cost, ($1,097,000,000) . . .. The ARRA funds and the flex funds have been subtracted out of the ESWA cost ($1,352,000,000). As a result, the "Total Eligible Cost" for this grant is $1,097,000,000.150

In other words, to calculate the total eligible cost for the New Starts grant and state matching

funds, it was necessary to subtract out the remaining costs allocated to the ESW A-the ARRA

and CMAQ funds. That these ARRA and CMAQ funds were not included in the total eligible

cost calculation for that particular grant in no way demonstrates that they were not part of the

ESW A, and in fact, the language above demonstrates that these funds were included in the

ESWA.

149 See Hughes Masonry Co. v. Greater Clark County School Bldg. Corp., 659 F.2d 836, 839 (7th Cir. 1981) (holding that a party "cannot have it both ways. It cannot rely on the contract when it works to its advantage, and repudiate it when it works to its disadvantage"); Comer v. Micor, Inc., 436 F.3d 1098, 1101 (9th Cir. 2006) ("Equitable estoppel precludes a party from claiming the benefits of a contract while simultaneously attempting to avoid the burdens that contract imposes.").

150 Agency Doc. 2, ESWA, Grant NJ-03-0169-00 (Aug. 14,2009) (emphasis added).

42

Final Decision of the Federal Transit Administration

NJT further argues that it should not have to repay the ARRA and CMAQ funds because

they were not incorporated into an "umbrella" agreement that encompasses all of the grants

within the ESWA with common terms and conditions. lSI NJT's argument is misplaced. The

terms and conditions applicable to the various grants under the ESW A are clear. Each of the

grants-whether rooted in 49 U.S.C. § 5309, ARRA, or CMAQ-contain certain terms in the

grant itself and incorporate the then-applicable FT A Master Agreement. The ESW A, then,

incorporates the grants supporting the scope of work defined by and obligating the funds

provided under the ESW A The ESW A statutory obligations, including the Repayment

Provision, apply to the funds paid through grants under the ESW A

Although NJT acknowledges that the ESW A and amended ESWA obligated certain New

Starts funds-particularly, $62 million was obligated in grant agreements contained in the same

document as the ESW A and ESW A amendment-NJT argues that even those funds should not

be subject to the Repayment Provision. Specifically, NJT contends that the "underlying

purpose" of the Repayment Provision is to "recoup funds that were advanced:' under an ESW A

and the ESW A did not "advance" New Starts funds, as the New Starts funds included in the

ESW A were earmarked for the Project by Congress prior to execution of the ESW AIS2

This argument is unsupported by the law. FTA does not "advance" funds to grantees, but

rather, FTA pays funds to grantees on a reimbursement basis as grantees incur construction and

other costs throughout the development of a project. Moreover, the statute does not make any

distinction based on whether a payment under the ESW A is an "advance." The ESW A by its

terms included past, current, and future funds, and the statute provides that "all Government

payments made under the work agreement" shall be repaid.

151 Id. at 14-15.

152 NJT Opposition to Demand at 18 (emphasis in original).

43

Final Decision of the Federal Transit Administration

Lastly, NJT argues that it should be relieved from repaying the funds in question because

it would have been entitled to and received them regardless of whether the ESW A was

executed.153 This argument ignores the plain fact that NJT sought, negotiated, formally

requested, and accepted an ESW A, and that ESW A includes New Starts, ARRA, and CMAQ

funds. NJT's repayment obligation is based on the requirements of the actual funding vehicle for

the abandoned Project, not on an after-the-fact hypothetical.

As demonstrated above, the ESW A defined a particular scope of work under the ARC

Project and provided Federal funds from different sources to support that scope. These funds

were obligated to New Jersey through eight grants that were either contained in the same

document as the ESW A, as amended, or in separate grant agreements that were incorporated by

reference into the ESW A, as amended. Under these specific grants, NJT expended

$271,101,291. Those funds constitute "all Government payments made under the work

agreement" and NJT must repay these funds to the United States.

3. The Repayment Provision requires the repayment of all Federal payments made under the ESW A, not just New Starts funds.

NJT argues that the Repayment Provision does not apply to the ARRA or CMAQ funds.

NJT's argument defies the language of the statute, which provides that "all Government

payments made under the work agreement" shall be repaid in the event a project is terminated. 154

Statutory construction begins with the language of the statute. 155 Where the statutory

language is clear, the inquiry ends there.156 Here, the language of the statute is clear: the

Repayment Provision contains no limitation on the type of payments that FTA may recover, and

153 [d. at 4.

15449 U.S.c. § 5309(g)(3)(B)(iv) (emphasis added).

155 Richardson v. United States, 526 U.S. 813, 818 (1999) (stating "when interpreting a statute, we look first to the language").

156 Hughes Aircraft Co. v. Jacobson, 525 U.S. 432, 438 (1999).

44

Final Decision of the Federal Transit Administration

instead uses the all-encompassing phrase "all Government payments made under the work

agreement.t'{" "All" does not mean one type or source of Federal funds but not another. The

statute means exactly what it says: all Government payments.

The legislative history confirms that repayment is not limited to New Starts funds, but

rather, that Congress intended repayment to be based on the scope of work under the agreement

and the project, not to the precise source of funds used. Indeed, the Senate Committee Report

summarizing the bill containing the Repayment Provision as originally enacted states, in

pertinent part, "If an applicant failed to implement the project for reasons within the applicant's

control, the applicant would be required to repay all federal payments made under the early

systems work agreement plus reasonable interest and penalty charges as specified in the

agreement.t'l'" The Report notes that this requirement is to ensure that ESWAs "are used only in

projects that can reasonably be expected to proceed.,,159 Thus, the Repayment Provision requires

the grantee to consider the consequences of requesting an ESW A, availing itself of substantial

Federal funding, and subsequently abandoning a project: the grantee will be made to repay all

Federal payments under the ESW A regardless of the source. Where, as here, NJT sought and

obtained an ESW A, it must bear the consequences of terminating the Project.

Further, if Congress had intended to limit the scope of repayment to only New Starts

funds under 49 U.S.C. § 5309, then Congress could have easily done so by adding "provided

under this subsection" or "provided under this section" after the word "payments" in the

15749 U.S.C. § 5309(g)(3)(B)(iv) (emphasis added). Webster's Third New International Dictionary defines the word "all" as that which "is the whole amount, quantity, or extent of' the matter at hand.

158 S. Rep. No. 102-79 at 52 (1991) (emphasis added). The Supreme Court has observed that the "authoritative source for finding the Legislature's intent lies in the Committee Reports on the bill, which represent the considered and coIlective understanding of those members of Congress involved in drafting and studying proposed legislation." Eldred v. Ashcroft, 537 U.S. 186,210 n.16 (2003) (citations and quotation marks omitted). PTA therefore rejects NJT's reliance on language in a staff discussion draft of a proposal to be considered by the Committee prior to issuing the final Committee Report discussed herein. NJT's Opposition to Demand at 15. The language of the Repayment Provision contains no carve-out for engineering or design costs.

159 [d.

45

Final Decision of the Federal Transit Administration

Repayment Provision. It did not. Because Congress has demonstrated its ability to limit the

scope of repayment in other instances and did not do so here, its omission of any limitation

indicates that it meant no limitation.16o Here, unlike other repayment provisions, Congress did

not, in any way, limit the scope of recovery under the Repayment Provision_I61

4. Formula Program funds administered under 49 U.S.c. § 5307 are subject to repayment.

Notwithstanding the clarity of the Repayment Provision, NJT also argues that 49 U.S.C.

§ 5307(k) precludes FTA from subjecting ARRA and CMAQ formula funds to the Repayment

Provision. FTA interprets 49 U.S.c. § 5307(k) and the Repayment Provision to require

repayment of ARRA and CMAQ funds administered under 49 U.S.C. § 5307 but obligated and

paid under an ESW A for a New Starts project.

CMAQ funds are "flexed" to FTA from the Federal Highway Administration, and FTA

then administers those funds under its Urbanized Area Formula Program ("Formula Program") at

49 U.S.C. § 5307. Likewise, the ARRA funds at issue were subject to the requirements

applicable to the Formula Program. 162 Pursuant to 49 U.S.C. § 5307(k)(I), there are 17

particular sections and subsections of 49 U.S.C. Chapter 53 applicable to grants of 49

U.S.C. § 5307 funds, and under 49 U.S.C. § 5307(k)(2), all other provisions of 49 U.S.C.

Chapter 53 are, by omission, inapplicable to Formula Program grants.

As explained above, however, the language of the Repayment Provision requires

repayment of "all" funds paid under the ESWA, including, in this case, New Starts funds and

160 See Whitfield v. United States, 543 U.S. 209, 216 (2005).

161 See, e.g., 42 U.S.C. § 1395bbb(e)(4) (conditioning payments to a home health agency on its agreeing to "repay to the Federal Government payments received under this subparagraph if the corrective action is not taken") (emphasis added); 7 U.S.c. § 1446(d)(3)(A)(iv)(I1I) (requiring the producer "repay to the Secretary the entire payment received under the contract") (emphasis added).

162 See Pub. L. 111-5, 123 Stat. 115,209-10 (2009).

46

Final Decision of the Federal Transit Administration

non-New Starts funds. 163 Particularly given FTA's duty to read potentially conflicting statutory

provisions harmoniously when possible.i'" FTA finds no conflict between 49 U.S.c. § 5307(k)

and 49 U.S.C. § 5309(g)(3)(B)(iv). Section 5307(k) applies program requirements to a grant

only to the extent that a project funded with a grant under 49 U.S.C. § 5307 is being

implemented. Once the Project was terminated, 49 U.S.C. § 5307 program requirements ceased

to apply, and the Repayment Provision automatically became applicable.

In statutory construction, "the specific governs the general." 165 In this instance, the

Repayment Provision is the more specific statute as it requires repayment of all funds paid under

a precise' type of agreement-an ESW A. There are very few ESW As even in the relatively small

universe of New Starts projects. Indeed, the ARC Project is only the fifth project to enter into an

ESWA since the enactment of the ESWA statute in 1991.166 Conversely, 49 U.S.C. § 5307(k)(2)

is a "general" provision that excludes by omission the applicability of sections of the Federal

transit code to Formula Program grants. As such, 49 U.S.c. § 5307(k) applies to literally

hundreds of grantees and thousands of grants, each and every fiscal year. Here, where it is

undisputed that the ARRA and CMAQ funds were used for the ARC Project as described in the

ESWA, the more specific Repayment Provision pertaining specifically to the ESWA controls.

In short, the Repayment Provision, created simultaneously with the ESW A, imposes an

obligation on the grantee, and is an integral part of every ESW A entered into by FT A and its

163 Furthermore, pursuant to FfA guidance, "Where the urban formula funds will be used in conjunction with Capital Program new start funds (authorized by 49 U.S.c. § 5309), Capital Program requirements apply as well." Ff A Circular 9030.1 C, Urbanized Area Formula Program: Grant Application Instructions, Appendix C (Oct. 1 1998) (applicable from effective date to May 1,2010).

164 "It is a fundamental canon of statutory construction that the words of a statute must be read in their context and with a view to their place in the overall statutory scheme. A court must therefore interpret the statute as a symmetrical and coherent regulatory scheme, and fit, if possible, all parts into an harmonious whole." FDA v. Brown & Williamson Tobacco Corp., 529 U.S. 120, 133 (2000) (citations and internal quotation marks omitted).

165 See Fourco Glass Co. v. Transmirra Products Corp., 353 U.S. 222, 228 (1957) ("However inclusive may be the general language of a statute, it 'will not be held to apply to a matter specifically dealt with in another part of the same enactment. ... Specific terms prevail over the general in the same or another statute which otherwise might be controlling. "') (internal citations omitted).

166 See Hynes-Cherin Decl. at <JI 43.

47

Final Decision of the Federal Transit Administration

grantees. By including the various grants in the ESW A, including the CMAQ, ARRA, and

previously-awarded New Starts grants, NJT must accept the conditions attached to these grants

when they were made a part of the ESW A, including the Repayment Provision. 167

C. The Master Agreements Independently Authorize FT A to Seek Repayment of All the Federal Funds Expended on the Project.

Even absent the ESW A's Repayment Provision, FTA has authority to collect all of the

Federal funds expended under its New Starts, CMAQ, and ARRA grants under the terms and

conditions ofFTA's Master Agreement, which provides:

If ... the Federal Government determines that the Recipient has willfully misused Federal assistance by failing to make adequate progress, by failing to make reasonable and appropriate use of Project property, or by failing to comply with the terms of the Grant Agreement or Cooperative Agreement for the Project including this Master Agreement, the Federal Government reserves the right to require the Recipient to refund the entire amount of Federal assistance provided for the Project or any lesser amount as the Federal Government may determine. 168

FTA's Master Agreement is incorporated by reference into each of its grant agreements.

In this case, FTA's Master Agreement was incorporated into each New Starts, CMAQ, and

ARRA grant agreement, and therefore, NJT at all times was subject to the above-referenced

terms and conditions.

By terminating the ARC Project, the Governor and NJT "fail[ed] to make adequate

progress" on the Project. Clearly, the termination of the Project constituted a failure to make

167 See County Sch. Ed. v. RT, 433 F.Supp.2d 692 (E.D. Va. 2006) (noting that "it would offend every principle of equity and good morals to permit a party to a transaction to enjoy its benefits and at the same time deny its terms and qualifications" and holding that party is therefore estopped from challenging the statutory scheme under which it received federal funding).

168 Agency Doc. 24, PTA Master Agreement for Fiscal Year 2011 at § 11 (Oct. 1,2010). See Agency Doc. 23, PTA Master Agreement for Fiscal Year 2010 at § 11 (Oct. 1,2009); Agency Doc. 22, PTA Master Agreement for Fiscal Year 2009 at § 11 (Oct. 1,2008); Agency Doc. 21, PTA Master Agreement for Fiscal Year 2008 at § 11 (Oct. 1, 2007); Agency Doc. 20, PTA Master Agreement for Fiscal Year 2007 at § 11 (Oct. 1, 2006). See also 49 U.S.c. § 5309(c)(3) ("The Secretary shall require that any grant awarded under this section to a recipient be subject to all terms, conditions, requirements, and provisions that the Secretary determines to be necessary or appropriate for the purposes of this section.").

48

Final Decision of the Federal Transit Administration

"adequate progress." Moreover, as demonstrated above, the termination of the Project was

entirely within the control of the Governor and NJT. The record shows that the cost estimate

increases that NJT alleges were unexpected and beyond its control, and that NJT asserts

compelled the Project's termination, were in fact within NJT's control and were completely

foreseeable. Accordingly, the decision to terminate was a willful exercise of the Governor's and

NJT's discretion.

Thus, in addition to the above-referenced affirmative statutory obligations placed on FTA

by the Repayment Provision, FTA has independent contractual authority under the Master

Agreements corresponding to each of the ARC Project's New Starts, CMAQ, and ARRA grants

to collect all of the Federal funds expended under those agreements. Consequently, NJT is

required to repay all of the Federal funds expended under those agreements because it failed to

make adequate progress on the ARC Project.

D. Principles of Equity and Fairness Favor Enforcing the Statute and Master Agreements Voluntarily Entered Into by NJT and Requiring New Jersey to Repay the Debt That it Owes to the United States Government.

In its Response, NJT makes a political and policy argument that "principles of equity," or

"fairness," should persuade FTA to forgive the debt that it owes to the United States.

Specifically, NJT argues that it would be unfair for New Jersey to (1) repay funds expended

before the ESWA was executed, (2) repay funds expended on preliminary engineering and

design when it could have expended those funds absent the ESWA, (3) repay funds when the

ESW A did not actually provide funds, and (4) repay funds when the Project could not proceed

for reasons beyond NJT's control.169 NJT also argues that it would be unfair for FTA "to compel

NJ Transit to repay funds when NJ Transit and its local funding partners were being asked to

169 NJT Opposition to Demand at 44-45.

49

Final Decision of the Federal Transit Administration

take on virtually all of the extraordinary cost increases" for a project of regional significance. 170

Finally, NJT argues that it would be unfair for FTA to compel New Jersey to repay funds that it

owes to the United States when the work completed thus far on the ARC Project has enduring

value to other projects in the same corridor and when, to repay the debt to the United States, NJT

would have to cancel over $271 million in projects that would relieve congestion and maintain

h f d .. h 'd 171

testate 0 goo repair 111 t e corn or.

NJT's appeal to equity runs afoul of the venerable principle that "equity follows the

law."m In this case, clear statutory language of the Repayment Provision requires FTA to

collect the $271,101,291 that it expended on the ARC Project, and consequently, no appeal to

equity is available to NJT. The language of the Repayment Provision leaves no room for

consideration of equity, but instead mandates that a grantee subject to an ESW A "shall ... repay

all Government payments.,,173 NJT does not, and cannot, identify any statutory or judicial

authority for any injection of equity in the circumstances of this case. Therefore, FTA rejects

NJT's appeal to equity.

Indeed, to the extent that principles of equity and fairness apply in this case, they would

weigh in favor of requiring repayment. While it is true that it has not been the practice of FTA to

seek repayment of New Starts funds or other sources of Federal funding expended for

environmental analysis, engineering, and design of New Starts projects that did not proceed to

construction, in this case, NJT insisted the funds expended on the ARC Project-including New

Starts, CMAQ, and ARRA funds-be included in an ESW A. NJT decided to request an ESW A,

to include the grants at issue in the ESW A, and subsequently agreed to abide by all conditions

170Id. at 45.

171 Id. at 45-48.

172 Hedges v. Dixon County, 150 U.S. 182, 192 (1893).

173 Lexecon Inc. v. Milberg Weis Bershad Hynes & Lerach, 523 U.S. 26, 35 (1998) (finding that the term "shall" creates "an obligation impervious to judicial discretion").

Final Decision of the Federal Transit Administration

associated with the ESWA, in exchange for which NJT received not only the.funding, but also the unique and substantial benefits that an ESW A provides to a grantee. NJT requested and accepted the largest ESW A grant investment ever provided in the history of FTA for the ARC Project. In doing so, NJT voluntarily and knowingly bound itself to the conditions that accompanied the ESWA, including the Repayment Provision. Similarly, FTA relied on NJT completing the Project when FT A, by executing the ESW A, committed itself to the largest ESWA investment in the agency's history. Because the New Starts program is oversubscribed, FTA had to divert funding from other qualified New Starts projects to make funds available to NJT, with the understanding that NJT was committed to completing the Project. 174 To the extent funds are recovered from NJT following the termination of the Project, those funds could be made available to other worthy New Starts projects. As such, equity weighs in favor of enforcing the conditions accompanying the ESW A.

Likewise, NJT's assertion that the work completed on the ARC Project has enduring value to other projects in the same corridor is irrelevant and speculative, at best. First, neither the Repayment Provision nor any other ESW A statutory rule or regulation leaves any room for the consideration of any benefit left by an abandoned project. Second, any supposed benefit is speculative and would, in any event, ultimately inure to New Jersey's benefit. Any applicant seeking Federal funds for a project along the ARC corridor would have to fully comply with the National Environmental Policy Act and prepare a new Environmental Impact Statement after completing a new engineering and design process. And should such applicant use any data generated by the Project and follow through with a transit project, the beneficiary of any such drastically attenuated value from the Project would still be New Jersey.

174 Hynes-Cherin Dec!. at <j[ 14.

50

51

Final Decision of the Federal Transit Administration

Nor is NJT's assertion that it would have to cancel over $271 million in transit projects to

repay its debt to the United States supported by the record. The $271,101,291 debt that the State

of New Jersey owes the United States constitutes less than one percent of the State's annual

operating budget of over $30 billion. 175 Furthermore, New Jersey, of which NJT is merely one

instrumentality, may use additional sources of revenue to repay its debt to the United States.

NJT made assurances to FT A under the terms and conditions of the ESW A and the

Master Agreements that it would complete the ARC Project, and FTA provided NJT with

$271,101,291 in Federal funds under an ESWA for the Project. NJT and Governor Christie

terminated the Project for reasons manifestly within their control. Under the terms and

conditions of the ESW A and the Master Agreements, NJT has an affirmative obligation and

responsibility to pay back the $271,101,291 to the Federal Government. The law requires FTA

to recover the debt. To the extent that principles of equity and fairness apply to this case, they

favor the law and require New Jersey to repay the debt that it owes to the United States.

175 See State of New Jersey, Office of Management and Budget, Fiscal 2011 Budget in Brief at 8, available at http.z/www.state.nj.us/treasury/omb, (Mar. 16,2010). FfA notes that NJT's annual operating budget is approximately $2 billion. See National Transit Database, New Jersey Transit Corporation Profile, available at http://www.ntdprogram.gov/ntdprogram/pubs/profilesI2009/agency _profiles/2080.pdf (Sept. 14, 2010).

Final Decision of the Federal Transit Administration

VI. FINAL DECISION

After carefully considering the administrative record as a whole, and for the reasons set

forth above, the Federal Transit Administration has determined that New Jersey owes a debt to

the United States Government in the amount of $271,101,291 for Government payments made

under the ESW A for the ARC Project. NJT should contact FTA to make arrangements to pay

the amount due. This Decision is administratively final.

Associate Administrator/Chief Financial Officer Office of Budget and Policy