ORIYX Scheulde

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Oriyx GTL Project, Raslaffan IMCO DUKHAN 19-Apr-11 14:46

Activity ID Activity Name Original Planned Start Planned FinishM M M M A A A A M M M M M J J J J J J J J J A A A A S S S S O O O O O N N NN


Duration

Oriyx GTL Project, Raslaffan 1800 13-Mar-11 30-Nov-11

Engineering 344 13-Mar-11 28-Apr-11 28-Apr-11, Engineering


A1000 Site Survey 56 13-Mar-11 21-Mar-11 Site Survey
A1010 Designing 56 22-Mar-11 30-Mar-11 Designing
A1020 AFC Drawing 168 31-Mar-11 28-Apr-11 AFC Drawing
Procurement 512 01-May-11 13-Jul-11 13-Jul-11, Procurement
A1030 MAT Submittal for Approval 168 01-May-11 29-May-11 MAT Submittal for Approval
A1040 PO Place 24 30-May-11 01-Jun-11 PO Place
A1050 Material Received 240 02-Jun-11 13-Jul-11 Material Received
Fabrication 184 14-Jul-11 09-Aug-11 09-Aug-11, Fabrication
A1060 Fitting & Welding 56 14-Jul-11 24-Jul-11 Fitting & Welding
A1070 Support fabrication 32 14-Jul-11 19-Jul-11 Support fabrication
A1090 NDT & PWHT 64 25-Jul-11 03-Aug-11 NDT & PWHT
A1110 Hydrotesting 8 04-Aug-11 04-Aug-11 Hydrotesting
A1120 Painting 24 07-Aug-11 09-Aug-11 Painting
Installation 160 10-Aug-11 04-Sep-11 04-Sep-11, Installation
A1130 Scafolding Erection 56 10-Aug-11 18-Aug-11 Scafolding Erection
A1140 Pipe Installation 8 21-Aug-11 21-Aug-11 Pipe Installation
A1150 Support Installation 8 22-Aug-11 22-Aug-11 Support Installation
A1160 Pipe Insulation 56 23-Aug-11 31-Aug-11 Pipe Insulation
A1170 Punch list 16 01-Sep-11 04-Sep-11 Punch list
Commisioning 24 05-Sep-11 07-Sep-11 07-Sep-11, Commisioning
A1180 Final Walk through & Plant Startup 16 05-Sep-11 06-Sep-11 Final Walk through & Plant Startup
A1190 Punch List 8 07-Sep-11 07-Sep-11 Punch List
Documents Work 568 08-Sep-11 30-Nov-11
A1200 Submission of Project Dossier 480 08-Sep-11 30-Nov-11

Actual Work Critical Remaining Work Summary Page 1 of 1 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.