Programme Evaluatio N and Review Technique
Programme Evaluatio N and Review Technique
Programme Evaluatio N and Review Technique
The special project office of the US Navy, concerned with performance trends on
large military development programmes introduces PERT on its Polaris Weapon
System in 1958, after the technique was developed with the aid of a consulting
firm in the US. Since that time, PERT has spread rapidly throughout the defence
forces in all countries as well as to large industrial projects. In our country, large
public scale organizations like Fertilizers Corporation Of India, Indian Oil
Corporation, Oil and Gas Commission, National Thermal Power Corporation,
Engineers India Limited, Engineering Projects Corporation, Bharat Heavy
Electricals Limited, as well as private companies like Larson and Turbo, Reliance
Industries, TISCO, etc. Claim to use PERT successfully for new projects,
diversification, replacement, and even for maintenance.
REQUISITIES OF PERT:
- The project goal needs to be clearly and unambiguously identified; all the
individual tasks in a given programme need to be visualised in a logical
manner, creating a work- break structure. These are put in a network flow
diagram, which is comprised of events and activities; the duration of an
activity, except in a time scale network, is not represented by the length of
the line. An activity succeeding an event cannot occur until all activities
leading to it are accomplished.
- All activity paths need to be completed by appropriate events, and a
description of each activity needs to be written above the arrow linking the
events. Emphasis is laid on defining events and activities with precision so
that there is no difficulty in monitoring actual accomplishments.
- Events and activities need to be sequenced in the network under a logical set
of ground rules which allow the determination of the critical paths, and all
constraints and interdependencies need to be clearly shown in the diagram.
The numbering of the events can be forward or backward, depending upon
whether the network diagram begins from the starting point or the end point
(the goal)
The expected time for each activity can be approximated using the following
weighted average:
These times are calculated using the expected time for the relevant
activities. The Es and EF of each activity are determined by working
forward through the network and determining the earliest time at which
an activity can start and finish considering its predecessor activities.
The latest start and finish times are the latest times that an activity can
start and finish without delaying the project. LS and LF are found by
working backward through the network. The difference in the latest and
earliest finish of each activity is that activity’s slack. The critical path
then is the path through the network in which none of the activities have
slack.
ADVANTAGES OF PERT:
- PERT gives management the ability to plan the best possible use of
resources to achieve a given goal within the overall time and cost
limitations. It enables the project executives to mange variety of
programmes, as opposed to repetitive production situations; it helps the
project manager to handle the uncertainties involved in programming where
no standard time data are available; it utilises the time network analysis as a
base of method of approach to determine manpower, material, machinery
and capital requirements. The use of PERT needs a clear definition of goals
for proper communication at all levels; the feedback and review of the
different stages of project helps the management to take corrective measures
and formulate strategies for allocating the limited resources in case of
emergencies.
- PERT is an effective mechanism for planning, scheduling, and co-ordinating
the different activities in project buying. The tenders for many public sector
projects insist on PERT network charts to be submitted along with the
quotations.
- PERT is useful for balance- sheet preparation, annual shutdown and
overhauls to identify the critical activities; it is particularly useful in
construction and R&D projects because it makes room for uncertainties
associated with futuristic decisions on project planning. It not only helps the
management in deciding when to initiate the follow-up and provide the
materials, but also gives an estimate of the consequences of not meeting
such demands. Thus, it helps avoid last minute delays, and panic buying
resulting in cost over runs. Because of the logical inter- relationships
between the planned elements, the project team can think of alternative
vendors.
- PERT enables the optimum utilisation of the resources by their transfer from
the slack to busy segments in the network in order to accomplish the
stipulated goal. It is useful for pre-crises planning and buying when the
‘force majeur’ clauses are operative because the responsibilities to project
executives are allocated well in advance to tackle such emergencies. The
summation manpower data in PERT often reveals a manpower or funding
restrictions in project planning, and forces a re- planning cycle if no
alternatives are evaluated.
-