I/O Summary For BMS

The document provides a point schedule for a BMS system controlling various building equipment. It lists 6 control panels that will monitor a total of 79 input/output points. Panel 1 will monitor 18 points for chillers and pumps. Panel 2 will monitor 16 points for two air handling units. Similarly, Panels 3 and 4 will monitor points for additional air handling units, while Panels 5 and 6 will monitor package units. The document outlines the specific points that each panel will monitor, such as start/stop commands, temperature sensors, and alarm statuses.

Uploaded by

safwan10
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
100% found this document useful (7 votes)
11K views2 pages

I/O Summary For BMS

The document provides a point schedule for a BMS system controlling various building equipment. It lists 6 control panels that will monitor a total of 79 input/output points. Panel 1 will monitor 18 points for chillers and pumps. Panel 2 will monitor 16 points for two air handling units. Similarly, Panels 3 and 4 will monitor points for additional air handling units, while Panels 5 and 6 will monitor package units. The document outlines the specific points that each panel will monitor, such as start/stop commands, temperature sensors, and alarm statuses.

Uploaded by

safwan10
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 2

Point Schedule 12/08/2021

Point Schedule for BMS

Input/Output Points Total I/O Points


Equipment Qty Description Controllers QTY
DI DO AI AO DI DO AI AO REMARKS
3 Chiller Start/Stop Command 1 0 3 0 0 1
3 Command for Butterfly Valve 1 0 3 0 0 1
3 Chiller Trip Alarm 1 3 0 0 0
3 Water Flow Status 1 3 0 0 0
Chillers & Chilled
3 Supply Chilled Water Temperature 1 0 0 3 0
Water Pumps
Panel - 1 3 Return Chilled Water Temperature 1 0 0 3 0
3 Pump Star/Stop Command 1 0 3 0 0
3 Pump Run Status 1 3 0 0 0
3 Pump Trip Alarm 1 3 0 0 0

Total Points for this panel 12 9 6 0 18X9

2 Supply Fan Start/Stop Command 1 0 2 0 0 1


2 Supply Fan Trip Alarm 1 2 0 0 0 1
2 Supply Fan DPS 1 2 0 0 0
2 Pre-Filter Status 1 2 0 0 0
2 Final Filter Status 1 2 0 0 0
Air Handling Unit No. 1 2 Return Air Humidity + Temperature 2 0 0 4 0
&2 Panel - 2 Cooling Valve Control 1 0 0 0 2
2 2 Return Air Smoke Detector 1 2 0 0 0
2 Supply Air Smoke Detector 1 0 2 0 0
2 Fresh Air Damper Control 1 0 2 0 0
2 Return Air Damper Control 1 0 2 0 0
2 Humidity Control 1 0 0 2 0
2 Electric Heater Stages 3 0 6 0 0
Total Points for this panel 10 14 6 2 16X16

1 Supply Fan Start/Stop Command 1 0 1 0 0 1


1 Supply Fan Trip Alarm 1 1 0 0 0
1 Supply Fan DPS 1 1 0 0 0
1 Pre-Filter Status 1 1 0 0 0
1 Final Filter Status 1 1 0 0 0
1 Return Air Humidity + Temperature 2 0 0 2 0
Air Handling Unit No. 3 1 Cooling Valve Control 1 0 0 0 1
Panel - 3 1 Return Air Smoke Detector 1 1 0 0 0
1 Supply Air Smoke Detector 1 0 1 0 0
1 Fresh Air Damper Control 1 0 1 0 0
1 Return Air Damper Control 1 0 1 0 0
1 Humidity Control 1 0 0 1 0
1 Electric Heater Stages 3 0 3 0 0

Total Points for this panel 5 7 3 1 8X8

1 file:///conversion/tmp/scratch/55804640.xls
Point Schedule 12/08/2021
1 Supply Fan Start/Stop Command 1 0 1 0 0 1
1 Supply Fan Trip Alarm 1 1 0 0 0
1 Supply Fan DPS 1 1 0 0 0
1 Pre-Filter Status 1 1 0 0 0
1 Final Filter Status 1 1 0 0 0
1 Return Air Humidity + Temperature 2 0 0 2 0
Air Handling Unit No. 4 1 Cooling Valve Control 1 0 0 0 1
Panel - 4 1 Return Air Smoke Detector 1 1 0 0 0
1 Supply Air Smoke Detector 1 0 1 0 0
1 Fresh Air Damper Control 1 0 1 0 0
1 Return Air Damper Control 1 0 1 0 0
1 Humidity Control 1 0 0 1 0
1 Electric Heater Stages 1 0 1 0 0

Total Points for this panel 5 5 3 1 8x8

1 Supply Fan Start/Stop Command 1 0 1 0 0 1


1 Supply Fan Trip Alarm 1 1 0 0 0
1 Supply Fan DPS 1 1 0 0 0
Package Unit No. 1 1 Pre-Filter Status 1 1 0 0 0
Panel - 5 1 Cooling Stage 2 0 2 0 0
1 Heating Stage 2 0 2 0 0
1 Return Air Temperature Sensor 1 0 0 1 0

Total Points for this panel 3 5 1 0 4x5

1 Supply Fan Start/Stop Command 1 0 1 0 0 1


1 Supply Fan Trip Alarm 1 1 0 0 0
1 Supply Fan DPS 1 1 0 0 0
Package Unit No. 2 1 Pre-Filter Status 1 1 0 0 0
Panel - 6 1 Cooling Stage 2 0 2 0 0
1 Heating Stage 2 0 2 0 0
1 Return Air Temperature Sensor 1 0 0 1 0

Total Points for this panel 3 5 1 0 4x5

10 Exhaust Fan Start/Stop Command 1 0 10 0 0 2


10 Exhaust Fan Run Status 1 10 0 0 0
Exhaust Fans
Panel - 7 10 Exhaust Fan Trip Alam 1 10 0 0 0
10 Exhaust Fan Flow Status (DPS) 1 10 0 0 0

Total Points for this panel 30 10 0 0 30x10


1 Software
Total points for this project 68 55 20 4 1 Key
1 RS485/USB
4 16x12 Controller
4 8x8 Controller
2 4x4 Controller