4 Feb 2011

The document assigns various work tasks to an employee over several dates in February and March 2011. It includes preparing reports on repair and maintenance of 16 inch transmission distribution lines and 8 inch pipelines, verifying completed work, scheduling projects to revamp storage tanks C1, C4 and C5, and planning and executing remaining pipeline work. It also requests the submission of academic certificates and registration of a professional engineering card.

Uploaded by

Willium Smith
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
28 views2 pages

4 Feb 2011

The document assigns various work tasks to an employee over several dates in February and March 2011. It includes preparing reports on repair and maintenance of 16 inch transmission distribution lines and 8 inch pipelines, verifying completed work, scheduling projects to revamp storage tanks C1, C4 and C5, and planning and executing remaining pipeline work. It also requests the submission of academic certificates and registration of a professional engineering card.

Uploaded by

Willium Smith
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

4-Feb-2011

Work Assigned.

 Reports of TDL 16 Inch Dia Repair and Maintenance.


 Prepare report of 16 inch TDL repair work that has been completed in w/shop &
field.
 Prepare report of 16 inch TDL repair work (Total)
 Working on scheduling and planning.
 Verification of the work performed of TDL 8” Project form Jetty to DP.

14-Feb-2011

Work Assigned.
 Remaining Work of TDL 8” Project from Jetty to DP (Verify).
 Work on realistic scheduling and planning.
 Scheduling of the Projects Revamping of Tank C1, C4 and C5 and Laying of Pipeline &
Pumps from Blending Tower to Gantry at LOBP.

15-Feb-2011

 Completed scheduling work of Project Revamping of Tank C4

17-Feb-11
Work Assigned.
 Again Verification of the work performed of TDL 8” Project form Jetty to DP (till
Saturday) Repeated…
 CV and Academic Certificates to be submitted in Office
• PEC Card Registration
 Bank Account

22-Feb-11
Work Assigned.
 Presentation of the project: Revamping of Tank C4” till Friday.
 Implement Schedule and Planning phase
• Remaining work of TDL 8” to be performed.
1-Mar-11

Work Assigned.
 Prepare Progress Report of Storage Tank C1, C4 and C5 with revision of
scheduling

7-March-2011
Work Assigned.

• .Auto Cad drawing and TDL 8” planning for remaining work.

8-March-2011

Work Assigned

• Plan the remaining work of LOBP C4 Tank to execution phase


• Plan and execute cold work of TDL Ø 16” Rep and Maintenance with
clearance of area.