Priority Rules of Techniques
Priority Rules of Techniques
operation
arrival due date due date process time
LCFS EDD
avg job at work centr 2.875 avg job at work centr 2.4375
SPT
7.2
job
sequencin
a 2 7 g start job time finish due date
b 8 16 a 0 2 2 7
c 4 4 b 2 8 10 16
d 10 17 c 10 4 14 4
e 5 15 d 14 10 24 17
f 12 18 e 24 5 29 15
f 29 12 41 18
flow time 120
mean flow time 20
makespan 41
avg lateness 9
Avg. job at work centre 2.926829
tre, use fcfs,spt,edd,cr
LCFS
job
sequencin
lateness g start job time finish due date lateness
0 F 0 12 12 18 0
0 E 12 5 17 15 2
10 D 17 10 27 17 10
7 C 27 4 31 4 27
14 B 31 8 39 16 23
23 A 39 2 41 7 34
54 167 96
27.83333 16
Avg. job at work centre 4.073171
Critical ratio at day 0,4
Jobs Processing time Due date Critical Ratio
A 2 7
B 8 16
C 4 4
D 10 17
E 5 15
F 12 18