N ATION AL HIGHW AY AUT HORITY

MINISTRY OF COMMUNICATIONS
GOVERNMENT OF PAKISTAN
ISLAMABAD

COMPOSITE SCHEDULE OF RATES

JANUARY 2009

(NWFP)

Shabir Associates
Quantity Surveying & Construction Cost Consultants
FOREWARD

Following the increases in prices of materials and labour in the year 2008, the
revision / updation of CSR has been carried out. In the year 2008 we have seen the
prices of steel / diesel / bitumen go up considerably and towards the end of year
have come down. Analysts are still uncertain with the prices in the year 2009. For the
year 2009, we have carried out a general revision of all prices upto January 2009 in
consultation with leading manufacturer’s, supplier, and specialist contractors.

In the absence of standard fix formula the best engineering knowledge and rate
analysis practices are used to develop these rates. The variation in the proposed
rates is anticipated in certain cases, which may be due to varying degrees / levels of
productivity and price differences of various inputs at the regional level.

The rates, prices and outputs included in the resources and unit cost calculations,
including allowances for wastage, normal productivity and efficiency are based for
roadwork and bridge projects being carried out by NHA. The unit rates are average
unit rates for a particular district and not project specific. The market can change
very rapidly, which would obviously have an impact on the unit rates.

It must be understood that main objective of the CSR is to provide a realistic


reference base for preparing Cost Estimates / PC-I and Evaluation of Bids, for NHA
projects.

My gratitude to The Chairman NHA, Member (Finance), Member (Operations),


Member (Construction), Member (Motorway) and Member (Planning) without whose
guidance and support it would have been difficult to develop this Document.

In the end, my appreciation to my team for all the possible technical and professional
efforts to produce Revised Composite Schedule of Rates 2009.

It is hoped that the CSR 2009, would serve as a Basic Engineer’s Estimate
Reference Document for National Highway Authority, various Government
Departments and the construction industry in general.

Whilst all efforts are made to ensure the accuracy of the data and information used
in updating the CSR , neither NHA or M/s Shabir Associates can in any way accept
liability for loss of any kind resulting from the use of CSR made by any person,
institution, company, department etc.

Muhammad Shabir
Q.S & Estimation Specialist
Shabir Associates

i
CONTENTS

1. General
2. Manpower List
3. Material List
4. Plants & Equipment Owning and Operating Cost
5. Quarry Sites
6. Conversion Factors & Technical Data
7. List of Districts
8. CSR January 2009 Item Rates

ii
National Highway Authority Shabir Associates
Islamabad Quantity Surveying & Construction Cost Consultants

1. General

For many years National Highway Authority has been compiling / updating the
Composite Schedule of Rates for use in the Civil Engineering Industry. The
Civil Engineering Industry uses this Schedule of Rates for pricing work by the
application of unit rates to the quantities measured from the designer’s
drawings. The main objective of the CSR is to provide a realistic reference
base for cost estimates. One has to understand no two projects are the same,
there are variables which effect the price of the project i.e., the volume of work
below ground, embankment height, cut & fill, increased exposure to weather,
and the tremendous variety of the projects, in terms of type, complexity and
scale makes the straight forward use of unit rates less reliable. This
uncertainty is compounded by the lower number of bill items generated in Civil
Engineering Projects as compared to Building Works so that the precise
nature of work is less apparent from bill descriptions and the statistical effect
of ‘swings and roundabout’ has less scope to average out extremes of pricing.

To prepare a price for a Civil Engineering project, then, it is necessary to have


regard to the method to be adopted in executing the work, draw up a detailed
programme and then cost out the resources necessary to prosecute the
chosen method. The first part of this process is the province of construction
planner, there has been a tendency to postpone detailed estimating until the
tendering stage itself, with the employer relying upto that point upon an
estimate prepared on a ‘broad brush’ basis.

There is increasing growing pressure on the part of project sponsors for an


improvement to budgetary advice, so that a decision to commit expenditure to
a particular project is taken on firmer grounds. The absence of detailed price
method during the pre-contract phase also inhibits the accurate costing of
alternative designs and regular cost checking to ensure that the design is
being developed within the employer’s budget. The CSR gives unit rates for
use when quantities can be taken from available drawings. To take some note
of the range of unit rates that might apply to an item, the rates themselves are
in some cases related to working method – for example by identifying the
different types of plant that would suit varying circumstances. Nonetheless, it
would be folly to propose that all types of Civil Engineering work could be
covered by the use of CSR. While developing these unit rates, we had in mind
the type and scale of work to be commissioned by NHA.

The CSR does embrace the great majority of work undertaken by NHA.
Although almost all projects will have individual features that require careful
attention in pricing, there will be some projects that are so specialist that they
will not confirm to standard pricing information at all. But for most projects,
within the range of work covered, this CSR should provide a firm foundation
for:

Preparing Project Cost Estimate and PC-1

Evaluating Tender / Bids

iii
National Highway Authority Shabir Associates
Islamabad Quantity Surveying & Construction Cost Consultants

Evaluating Claims and Variation Order

Arbitration Matters

In order to prepare an authentic Composite Schedule of Rates and to keep it


effective, the basic requirements are as under:

 Collection of first hand, prudent and legitimate information for inputs


(Manpower, Material & Equipment) in the rate analysis

 Merging the above information in proper proportion according to Design


Specifications and Constructional requirements to create the rate of a work
item

 Updating the data inputs every year or from time to time, to revalidate the
item rates

2. GENERAL METHODOLOGY:

a. Composite Schedule of Rates was originally published in the year 1991 and
subsequent revisions were carried out in 1995, 2000, 2005, 2006 and 2008.
There are total of 91 Districts considered and are given numbers in
Alphabetical order and their Province wise breakdown as under:

Province No of Districts
Punjab 34
Sind 16
NWFP 21
Balochistan 20

Specifications and Methodology for Construction items have been adopted as


given in General Specification of National Highway Authority (1998). Items of
work for construction have been given the same numbers as appearing in the
General Specifications of National Highway Authority.

b. These rates are based on the existing formulae and efficiency levels used in
the preparation of CSR 2005, 2006 and 2008 with some modifications.

c. The rates analysis of individual items of CSR 2009 consists of four basic
inputs, which have been assigned the same code numbers as in the previous
Composite Schedule of Rates.

i. Manpower code starting from 1001 onwards

ii. Material code starting from 2001 onwards

iii. Equipment code starting from 3001 onwards

iv. Overheads, Profits & Preliminaries

iv
National Highway Authority Shabir Associates
Islamabad Quantity Surveying & Construction Cost Consultants

d. For the preparation of rates following documents have been referred:

i. General Specifications 1998

ii. NHA Composite Schedule of Rates 2005, 2006 & 2008 and its basic data

iii. Statistical Bulletins by Federal Bureau of Statistics

iv. Current Market rates study

Code list of Manpower, Material and Equipment appear at the end of the
chapter for the convenience of the users.

2.1 MANPOWER:

a. Allocation of Code Numbers:

Costs of manpower engaged on Plant & Equipment have been included in


rental charges of Plant & Equipment and only site supervisory staff have been
considered under the heading of Manpower. Code numbers are allocated
accordingly to such manpower that is directly charged to the items of work.
Manpower cost for top supervision, administration and other non-productive
works of support services have been considered under overhead charges.

b. Formulation of Rates:

Manpower basic rates collected from districts have been first scrutinized, to
eliminate irrational information and following overheads are applied to include
fringe benefits and other charges:

i. Social Security Payment

ii. E.O.B.I. Payment

iii. Education Cess Payment

iv. Yearly Leave Salary (Earned, casual and sick)

v. Bonus (Compulsory)

vi. Provident Fund (Contribution of Employer) or Gratuity

vii. Mess Expenses (Site Staff)

viii. Entertainment Allowance (Provisional)

ix. Group Life Insurance

x. Site Staff Accommodation

After including above overheads, manpower rates for each of the 91 district
have been calculated and separate records developed for use by the
Computer Program.

v
National Highway Authority Shabir Associates
Islamabad Quantity Surveying & Construction Cost Consultants

2.2 CONSTRUCTION MATERIAL:

a. Allocation of Code Numbers to Materials:

List of materials required for road construction has been first prepared from
the construction items appearing in the General Specifications of National
Highway Authority. After arranging the construction material list in order, code
numbers have been allocated.

b. Formulation of Rates:

Considering the location of each district, Engineers decided the most


appropriate source of construction materials for all the code numbers. The
cost of material at source has been established from field data and
transportation rates calculated, to arrive at the landed cost of material at the
district headquarters.

c. Cost of Material

In order to arrive at a “Material at sources” rate, following considerations have


been made.

i. Material royalty at quarry (actual or estimated)

ii. Cost of Preparation of material

iii. Unauthorized local charges in the province of Balochistan and Sind

iv. Loading of material in truck / trailer etc

d. Cost of Transportation

Transportation charges have been taken as actual, where local transporters


are available. However, in some districts where local transporters rates are
not quoted, transportation charges graphs have been used.

In case of quarry materials, the source of materials for embankment, Sub-


Base or Base Course can be more than one; however, the most appropriate
source from the point of view of quality and economy has been used for
preparing the Composite Schedule of Rates – 2009.

2.3 PLANT AND EQUIPMENT

a. Allocation of Code Numbers

The list of plant and equipment includes major equipment whereas small
equipment, tools and attachments are ignored, as these have been charged
under the item of overhead. After arranging the list in order, code numbers
have been allocated starting from 3001 (onwards).

vi
National Highway Authority Shabir Associates
Islamabad Quantity Surveying & Construction Cost Consultants

b. Power, Performance and Maintenance of Plant & Equipment

To arrive at the decision for choosing the right horse power, appropriate
performance level and reasonable maintenance charges, the
recommendation of well known suppliers have been considered. In order to
decide the price level of any equipment, average cost has been used, which
includes C&F price, plus duties and taxes etc.

c. Formulation of Rates of Plant and Equipment

The owning and operating costs are similar for all the districts, unlike
manpower and materials where rates may differ for each district.

The owning and operating costs are developed by using a standard format.
The duties and taxes have been calculated as per the latest Excise and Land
Customs Tariff for calculating total cost of equipment.

Fuel consumption, working efficiency and maintenance costs have been fixed
after consulting the recommendation of the manufacturers. Equipment
economical life and tire life have been fixed after consulting several
organizations using heavy and light equipment in the present indigenous
conditions.

The owning and operating costs for 80 types of equipment is provided at the
end of this chapter.

2.4 FORMULAE FOR CONSTRUCTION ITEMS

All the basic inputs have been updated in the individual rates analysis. These
formulae have been created by appropriate quantitative inputs of the following
items.

Manpower Hour and Number


Material Weight, Volume, Length and Unit
Plant Equipment Hour and Number
Overheads, profit and 25 percent
preliminaries
2.5 OVERHEADS, PROFIT & PRELIMINARIES

a. Profit

The level of profit is governed by the degree of competition applicable to the


job which is in turn a function of the industry’s current work load. The
appropriate addition is highly variable.

b. Head Office Overheads

An addition to the estimate needs to be made to the net estimate to cover all
costs incurred in operating the central services provided by head office. Apart

vii
National Highway Authority Shabir Associates
Islamabad Quantity Surveying & Construction Cost Consultants

from general management and accountancy, this will normally include the
departments dealing with:

Tendering / Estimating
Planning & design
Wages and bonus
Finance Cost:- Some companies would include finance costs with head office
overheads, but this will vary from contractor to contractor.

The appropriate addition varies with the extent of services provided centrally
and company to company, rather than on site, and with size of organization.

c. Preliminaries

Preliminaries cost in Civil Engineering works or indirectly related to the actual


quantity of work being carried out. It comprises a definition of method related
charges, a checklist of items to be accounted for on typical Civil Engineering
Contract.

Generally contract document give detailed requirements for the facilities and
equipment to be provided for the employer and the Engineer’s Representative
given in the Bill of Quantities. Thus General Items given in the BOQ are
excluded from the check list of preliminaries.

The following checklist is representative but not exhaustive which is not


covered in the BOQ or General items section. The list describes the major
preliminaries which are included, implicitly or explicitly, in a typically Civil
Engineering Contract.
 Contractor’s site on costs
 Temporary works (other then those included in unit cost)
 General purpose plant (other than those included in unit cost)
 Other services, charges and fees
 Site Staff Salaries

All non-productive supervisory staff on site i.e., agents, clerks,


computer operators, security guards, store men, drivers for staff
vehicles, cleaners, general labour for general clearance etc.

 Plant Maintenance

Fitters, electricians and assistants engaged on general plant


maintenance on site (excludes drivers who are provided in the unit
costs)

 Site Transport for Staff and General Use

Vehicles / buses provided for use of staff and others including running
costs etc.

viii
National Highway Authority Shabir Associates
Islamabad Quantity Surveying & Construction Cost Consultants

 Contractors offices rental / construction / site huts and associated running


costs.
 Canteen, welfare / medical
 General office expenditure
 Provision of postage, stationary and other consumables for general office use
 Mobilization and demobilisation of resources.
 Telecommunications
 Furniture and equipment
 Small tools
 Traffic Control, traffic diversion and sign
 Fencing
 Protective clothing
 Health and safety
 Road lighting
 Cleaning roads etc
 Progress photographs
 Water Supply
 Electric connection
 Notice boards and signs
 Insurances / bonds / bank guarantees / Employees liabilities insurance etc.

There will be many other items of preliminaries which may have to be


considered, which probably will be project and site specific.

Preliminaries % percentage can vary from project to project.

d. Tax

Tax has been included as per Government rules.

In the CSR, 25% is added on the estimated unit cost of the items which
includes over heads, taxes, preliminaries and profit, however this will vary
from project to project and contractor to contractor.

2.6 VARIABLES EFFECTING THE RATE ANALYSIS

Rate analysis in CSR have been prepared based on policy explained here
above. However, there are certain factors required to be considered while
deciding about more realistic rates in special situations.

ix
National Highway Authority Shabir Associates
Islamabad Quantity Surveying & Construction Cost Consultants

a. Price Escalation

General and Special escalation has been considered as published by


Government Agencies. However, care is to be exercised to consider
Government Legislation, which may create condition of Special Escalation.

b. Double Taxation

In International tenders, a factor is to be considered which may handicap the


contractors from such countries, whose governments have no agreement with
the Government of Pakistan to avoid double taxation. Effect of this item will be
equal to the limit of tax level in such a country.

c. Service Roads

No provision has been made in this rate analysis for road diversion cost or
service road, which the contractor has to construct or maintain as a non-BOQ
item.

d. Extra Overhead for Expatriate Staff

International tenders will require a factor to employ expatriate staff on the


project. Effect of this will be equal to the actual expenses on such item.

e. Other Factors

Some of the items mentioned in above text included as overhead Cost in


Estimates of CSR, may appear as a B.O.Q item in a tender, the cost of such
items are to be adjusted from the total estimate of the project.

x
National Highway Authority Shabir Associates
Islamabad Quantity Surveying & Construction Cost Consultants

LIST OF MANPOWER
Man power Code Description
1001 SITE ENGINEER
1002 ASPHALT PLANT ENGINEER
1003 CONCRETE PLANT ENGINEER
1011 FOREMAN ASPHALT
1012 FOREMAN EARTHWORK
1013 FOREMAN CONCRETE
1014 GENERAL FOREMAN
1021 SUPERVISOR
1022 SURVEYOR
1023 ASSISTANT SURVEYOR
1031 MASON
1032 CARPENTER
1033 PAINTER
1034 STEEL BINDER/CUTTER
1040 HIGHLY SKILLED LABOUR
1041 HELPER
1042 WELDER
1051 LABOUR

Note:

Cost of following Manpower has been included elsewhere as under:

1. Top Management, Senior Engineers and above included in overhead


and preliminaries.

2. All indirect Manpower such as Clerk, Typist, Accountant, Lab staff,


Workshop staff, Store staff, Security staff etc. is included under overhead
and preliminaries.

3. All operators of Light and Heavy Duty Equipment and Plant Included in
the hourly rate of the equipment

xi
National Highway Authority Shabir Associates
Islamabad Quantity Surveying & Construction Cost Consultants

LIST OF MATERIAL

Material Code Description Unit

2001 ROCK CM
2002 SOIL CLASS-A1 CM
2004 SOIL CLASS-A2 CM
2008 SOIL CLASS-A3 CM
2009 SOIL CLASS-A4 CM
2010 SOIL CLASS-A5 CM
2014 CRUSHED AGGREGATE BASE A CM
2015 CRUSHED AGGREGATE BASE B CM
2016 CRUSHED AGGREGATE BASE B1 CM
2017 GRANULAR SUB-BASE A CM
2018 GRANULAR SUB-BASE B CM
2019 SAND CLASS C CM
2021 COARSE SAND CM
2022 FINE SAND CM
2023 AGGREGATE 2"-1.1/2" CM
2024 AGGREGATE 1.1/2"-3/4" CM
2025 AGGREGATE 3/4"-3/8" CM
2026 AGGREGATE 3/8"-EACH 4 CM
2027 AGGREGATE EACH4-EACH200 CM
2028 FILLER MATERIAL CM
2029 BRICK CLASS A EACH
2030 STONE RANDOM CLASS-A CM
2031 STONE RANDOM CLASS-B CM
2032 STONE RANDOM CLASS-C CM
2033 STONE RANDOM CLASS-D CM
2034 STONE DRESSED CM
2035 HAND BROKEN STONE 2.1/2"-1/2" CM
2041 ASPHALT GRADE 60/70 TON
2042 ASPHALT GRADE 80/100 TON
2043 ASPHALT M.C. 70 TON
2044 ASPHALT M.C. 250 TON
2045 ASPHALT M.C. 800 TON
2046 ASPHALT R.C. 70 TON
2047 ASPHALT R.C. 250 TON
2048 ASPHALT R.C. 800 TON
2049 ASPHALT S.S. 1 TON
2050 ASPHALT S.S. 1H TON
2051 ASPHALT R.S. 1 TON
2052 ASPHALT R.S. 2 TON
2053 CEMENT TYPE-I (OPC) BAG
2054 CEMENT TYPE-II (LOW S.R) BAG
2057 CEMENT TYPE-V (HIGH S.R) BAG
2058 ACCELERATOR LIT
2059 RETARDER LIT
2060 CURING COMPOUND LIT
2061 STEEL GRADE. 40 TON
2062 STEEL GRADE. 60 TON

xii
National Highway Authority Shabir Associates
Islamabad Quantity Surveying & Construction Cost Consultants

LIST OF MATERIAL

Material Code Description Unit


2063 PRE-STRESSING STRAND, 3/8", 1/2" TON
2064 STEEL WIRE MESH, 4" x 4" KG
2065 WATER 1000 LIT
2067 STEEL WIRE FABRIC AASHTO M-55 TON
2068 STEEL EXPANSION JOINT KG
2070 COLD STEEL WIRE AASHTO M-32 TON
2072 STRUCTURES SHAPES ASTM A-36 TON
2073 ELASTOMERIC BEARING PAD M-183 c.cm
2077 RCC PIPE CLASS-II 310 MM (AASHTO M-170) M
2078 RCC PIPE CLASS-II 380 MM (AASHTO M-170) M
2079 RCC PIPE CLASS-II 460 MM (AASHTO M-170) M
2080 RCC PIPE CLASS-II 610 MM (AASHTO M-170) M
2081 RCC PIPE CLASS-II 760 MM (AASHTO M-170) M
2082 RCC PIPE CLASS-II 910 MM (AASHTO M-170) M
2083 RCC PIPE CLASS-II 1070 MM (AASHTO M-170) M
2084 RCC PIPE CLASS-II 1220 MM (AASHTO M-170) M
2085 RCC PIPE CLASS-II 1520 MM (AASHTO M-170) M
2091 CAT EYE SINGLE (RAISED PROFILE) EACH
2092 CAT EYE DOUBLE (RAISED PROFILE) EACH
2093 STEEL/METAL BEARING DEVICES KG
2095 BITUMEN IMPREGNATED FIBRE BOARD SM
2096 NEOPRENE RUBBER JOINT FELT SM
2097 ASPHALT FELT (3-PLY) SM
2098 PVC/NEOPRENE WATER STOPS (6") M
2099 BENTONITE POWDER KG
2100 JOINT SEALANT FILLER KG
2101 TRAFFIC SIGN CAT 1 EACH
2102 TRAFFIC SIGN CAT 2 EACH
2103 TRAFFIC SIGN CAT 3 (A, B, C) SM
2104 PAVEMENT MARKING NON-REFLECTING (CR) LIT
2105 PAVEMENT MARKING REFLECTING (CR) LIT
2108 TUNGSTEN CARBIDE BITS SET
2109 RED OXIDE PAINT LIT
2110 QUICK LIME KG
2111 DIESEL LIT
2112 SUPER LIT
2113 REGULAR LIT
2114 OILS (ALL TYPES) LIT
2115 LUBRICANTS (GREASE) KG
2116 FURNACE OIL LIT
2117 BLASTING MATERIAL KG
2118 ELECTRIC CHARGES COMMERCIAL KWH
2119 MASTIC WATER PROOF PAINT KG
2120 SYNTHETIC ENAMEL PAINT LIT
2121 SHUTTERING (401) A LS
2122 SHUTTERING (401) B LS
2123 SHUTTERING (401) C LS
2124 SHUTTERING (401) D LS

xiii
National Highway Authority Shabir Associates
Islamabad Quantity Surveying & Construction Cost Consultants

LIST OF MATERIAL
Material
Material Code Material Code
Code
2125 SHUTTERING (401) E LS
2126 SHUTTERING (401) F LS
2127 SHUTTERING (401) G LS
2128 SHUTTERING (401) H LS
2129 SHUTTERING (410) LS
2131 G.M.S BARBED WIRE KG
2133 ANGLE IRONS DIFFERENT SIZES KG
2134 STEEL CHANNELS KG
2135 SHEATHS (3/8", 1/2") M
2136 LIVE ANCHORAGES (3/8" - 1/2") EACH
2137 G.I. PIPE 3" DIA M
2140 G.M.S SCREW, NUTS, BOLTS AND WASHERS KG
2142 PLANTATION TREES EACH
2143 MOBILIZATION OF PILING EQUIPMENT LS
2144 RCC PIPE CLS-IV 310 MM (AASHTO M-170) M
2145 RCC PIPE CLS-IV 380 MM (AASHTO M-170) M
2146 RCC PIPE CLS-IV 460 MM (AASHTO M-170) M
2147 RCC PIPE CLS-IV 610 MM (AASHTO M-170) M
2148 RCC PIPE CLS-IV 760 MM (AASHTO M-170) M
2149 RCC PIPE CLS-IV 910 MM (AASHTO M-170) M
2150 RCC PIPE CLS-IV 1070 MM (AASHTO M-170) M
2151 RCC PIPE CLS-IV 1220 MM (AASHTO M-170) M
2152 RCC PIPE CLS-IV 1520 MM (AASHTO M-170) M
2153 PAVEMENT MARKING NON REFLECTING (TP) KG
2154 PAVEMENT MARKING REFLECTING (TP) KG
2155 GALVANIZED FLAT STEEL FASTENERS & WASHERS KG
2156 GALVANIZED U-BOLT CLAMP WITH 2 NUTS & TIE BOLTS KG
GALVANIZED SUPPORTING HOOKS CAST IN PRECAST
2157 EACH
POSTS
2158 GALVANIZED CHAIN LINK WIRE MESH FABRIC SM
2159 GALVANIZED WIRE 3.76MM Ø TENSION, 3MM Ø STIRRUP KG
2160 PRE-CAST CONCRETE TUFF KERB STONE(K-5) EACH
2161 LIFTING DEVICE ANCHORS EACH
2162 MS SHEET KG
2163 FABRICATION KG
2164 GALVANIZATION KG

xiv
National Highway Authority Shabir Associates
Islamabad Quantity Surveying & Construction Cost Consultants

PLANT AND EQUIPMENT OWNING OPERATING COST SUMMARY


(CSR- Jan-2009)

T – Owning T- Operating T – Hourly


Equipment
Description Cost Cost O.W. &
Code
Operating Cost
3001 Bull-Dozer. 200 H.P 1,503.78 2,064.93 3,568.71
3002 Bull-Dozer. 120 H.P 973.02 1,011.88 1,984.90
3003 Bull-Dozer. 90 H.P 796.11 672.49 1,468.60
3004 Front End Loader. 3.00 Cu.M 1,457.39 1,558.64 3,016.03
3005 Front End Loader. 2.50 Cu.M 942.30 1,267.74 2,210.04
3006 Front End Loader. 1.50 Cu.M 854.12 1,044.74 1,898.86
3007 Grader. 165 H.P 1,210.40 1,411.34 2,621.74
3008 Grader. 140 H.P 857.12 1,117.67 1,974.79
3011 Tandem Vibratory Roller. 10-12 Ton 751.89 876.19 1,628.08
3012 Tandem Vibratory Roller. 8 Ton 692.91 766.50 1,459.41
3013 Tandem Vibratory Roller. 6 Ton 339.09 524.82 863.91
3014 Tandem Vibratory Roller. 1.5 Ton 240.30 281.56 521.86
3015 Combination Roller. 18 T 844.61 1,201.71 2,046.32
3016 Combination Roller 10 - 12 T 669.88 1,079.05 1,748.93
3017 Combination Roller 8 T 479.07 691.31 1,170.38
3018 P.T.R (9 - Wheeler) 21 T 405.57 941.13 1,346.70
3019 P.T.R (9 - Wheeler) 18 T 369.27 781.57 1,150.84
3020 Static Tandem Roller 12 T 140.07 488.28 628.35
3021 Static Tandem Roller 8T 117.93 486.84 604.77
3022 Tractor 80 H. P 62.95 591.82 654.77
3023 Tractor 50 H. P 37.56 376.62 414.18
3024 Water Tank Bowser Type 12000 Litre 240.49 618.21 858.70
3025 Water Tank Tow Type 4000 Litre 52.16 382.07 434.23
3031 Motor Scraper 400 H. P 1,449.78 5,135.17 6,584.95
3032 Dumper 18 T 288.03 1,084.37 1,372.40
3033 Dumper 10 T 230.44 693.31 923.75
3034 Flat Body Truck 8 T 177.69 513.95 691.64
3047 Excavator, (Track Type ) 100 H. P 825.60 727.34 1,552.94
3048 Power Broom 92.93 527.46 620.39
3051 Bitumen Distributor Tow Type 2000 Litre 155.67 414.85 570.52
3052 Bitumen Sprayer (Manual) 250 Litre 11.93 51.99 63.92
3053 Aggregate Spreader 4 M Wide 729.78 510.65 1,240.43
3054 Asphalt Plant 120 T 7,983.72 8,759.34 16,743.06
3055 Asphalt Plant 80 T 5,655.13 7,446.96 13,102.09
3056 Asphalt Plant. 40 Ton 4,657.19 4,114.85 8,772.04

xv
National Highway Authority Shabir Associates
Islamabad Quantity Surveying & Construction Cost Consultants

PLANT AND EQUIPMENT OWNING OPERATING COST SUMMARY


(CSR – Jan-2009)

T – Owning T- Operating T – Hourly


Equipment
Description Cost Cost O.W. &
Code
Operating Cost
3057 Asphalt Plant. 20 Ton 3,326.57 3,151.87 6,478.44
3058 Paver 4 M Wide 729.78 1,109.56 1,839.34
3059 Paver 2.5 M Wide 501.27 990.82 1,492.09
3061 Compressor. 300 CFM 168.72 907.25 1,075.97
3062 Rock Driller 204.48 79.81 284.29
3071 Concrete Batching Plant. 30 CUM/H 554.97 2,499.29 3,054.26
3072 Concrete Static Mixer 1 Cu.Y 110.76 331.90 442.66
3073 Concrete Static Mixer 1/4 Cu.Y 25.56 221.24 246.80
3074 Concrete Transit Mixer 6 Cu.M 807.29 1,043.38 1,850.67
3075 Concrete Transit Mixer 4 Cu.M 754.19 752.33 1,506.52
3081 Trailer Low Bed 30 T. 506.66 1,000.71 1,507.37
3082 Crane. 45 T. 651.30 1,039.13 1,690.43
3083 Crane. 20 T. 564.69 849.55 1,414.24
3084 Cold Milling Machine. 1 M Width 1,765.58 1,265.48 3,031.06
3085 Road Marking Machine. 135.32 346.26 481.58
3086 Pump 4 " Delivery (Diesel) 43.50 262.48 305.98
3087 Pug mill 40 Tons per Hour. 746.27 2,381.43 3,127.70
3088 Chipping Spreader 3 Meter Wide 70.03 379.76 449.79
3089 Sand Blasting Machine 73.71 1,651.67 1,725.38
3120 Stressing Equipment 112.01 1,627.88 1,739.89
3121 Asphalt Cutter 47.14 321.07 368.21
3122 Concrete Cutter 47.14 321.07 368.21
3123 Electric Saw 21.30 810.84 832.14
3195 Truck (3-Axle) 248.42 668.52 916.94
3196 Tractor Trolley 94.15 445.65 539.80
3197 Trailer (30 Ton) 445.63 1,000.71 1,446.34
3198 Welding Plant 55.99 815.06 871.05
3199 Generator (Diesel) 150 KVA 214.62 1,365.49 1,580.11
3200 Generator (Diesel) 250 KVA 355.54 2,154.76 2,510.30
3202 Rock Crushing & Screening (200 T/H) 1,233.96 8,294.10 9,528.06
3205 Secondary Crusher 59.64 2,990.77 3,050.41
3206 Diesel Tanker 215.24 516.80 732.04
3208 Jack Hammer 33.60 304.09 337.69
3209 Pilling Rig (upto 1.5 m dia) 417.40 667.99 1,085.39

xvi
National Highway Authority Shabir Associates
Islamabad Quantity Surveying & Construction Cost Consultants

PLANT AND EQUIPMENT OWNING OPERATING COST SUMMARY


(CSR – Jan-2009)

T – Owning T- Operating T – Hourly


Equipment
Description Cost Cost O.W. &
Code
Operating Cost
3209a Pilling Rig (above 1.5 m dia) 571.50 1,235.49 1,806.99
3210 Vibrator (Poker 1.5 ") 17.40 302.76 320.16
3211 Percussion Boring Rig 119.28 267.80 387.08
3212 Forgoing / Shape Machine 67.20 1,561.84 1,629.04
3214 Concrete Pump 621.60 1,170.56 1,792.16
3215 Plate Compactor 43.50 305.76 349.26
3217 Girder Launcher 1,464.46 1,034.77 2,499.23
3218 Tripod & Chain Pulley (20 Ton) 11.21 128.54 139.75
3219 Electric Generator 50 KVA 81.79 4,531.51 4,613.30
3220 Asphalt Recycling Machine 7,154.11 3,961.17 11,115.28
3221 Road Marking Machine (TP) 196.02 416.54 612.56

xvii
National Highway Authority Shabir Associates
Islamabad Quantity Surveying & Construction Cost Consultants

QUARRY SITES (NWFP)


Dist Code District Sites

AGGREGATES
35 Kohistan dasu Buttgram/ Mansehra area
7-B Buttgram Buttgram/ Mansehra area
43 Mansehra Margalla, Hawalian
73 Muzafarabad Margalla, Hawalian
1 Abbottabad Margallah, Dur Nala
20-B Haripur Hazara Margallah, Dur Nala
10 Chitral Chitral Area, Swat Area
15 Dir Swat Area, Quarry Available no crusher
66 Swat Saidu Sharif Chakdara, Swat Area
66-B Kalam Chakdara, Swat Area
7-A Buneer Swat Area
42 Malakand chakdara, Swat area
10-A Charsaddah Charsad Area, Mardan, Dara Adam Khel
44 Mardan Katlung, Charsada
66-A Swabi Margallah, Katlung
49-C Nowshera Katlung (Nowshera), Margallah
52 Peshawar Charsada, charat, Khyber pass, Adam Khel
34 Kohat Kohat Area, Dara Adam Khel
27 Karak Kohat Area
6 Bannu Kohat, Eisa Khel
41-B Lucky Murwat Kohat, Eisa Khel
70-A Tank Daraban Crushers
12 Dera Ismail Khan Daraban Crushers, Chund quarry
CRUSHED AGGREGATE BASE
35 Kohistan dasu Chillas, Jalkot, Buttgram/ Mansehra area
7-B Buttgram Buttgram/ Mansehra area
43 Mansehra Margalla, Hawalian
73 Muzafarabad Margalla, Hawalian
1 Abbottabad Abbotabad Area, Dor Nala
20-B Haripur Hazara Margallah, Dur Nala
10 Chitral Shishi Bridge, Chitral Area
15 Dir Swat Area, Quarry Available no crusher
66 Swat Saidu Sharif Chakdara, Swat Area
66-B Kalam Chakdara, Swat Area
7-A Buneer Swat Area

xviii
National Highway Authority Shabir Associates
Islamabad Quantity Surveying & Construction Cost Consultants

QUARRY SITES (NWFP)


Dist Code District Sites

42 Malakand chakdara, Swat area


10-A Charsaddah Charsad Area, Mardan, Dara Adam Khel
44 Mardan Katlung, Charsada
66-A Swabi Margallah, Katlung
49-C Nowshera Nowshera area, Mardan Area
52 Peshawar Charsada, charat, Khyber pass, Adam Khel
34 Kohat Dara Adam Khel, Darsamand
27 Karak Kohat
6 Bannu Kurram, Bannu area
41-B Lucky Murwat Bannu area
70-A Tank Eisa Khel, Zam Nala, Pezu, Daraban
12 Dera Ismail Khan Daraban
GRANULAR SUB-BASE
35 Kohistan dasu Pattan, Chillas, Jalkot, Buttgram
7-B Buttgram Dor Nallah, Patan
43 Mansehra Dor Nullah, Katha Nullah, Icher Nala
73 Muzafarabad Dor Nullah, Katha Nullah, Icher Nala
1 Abbottabad Dor nullah
20-B Haripur Hazara Dor Nullah
10 Chitral Shishi Bridge, Chitral Area
15 Dir Maiar Nala, Punjkot River
66 Swat Saidu Sharif Swat river
66-B Kalam Swat river
7-A Buneer Swat Area
42 Malakand Wartir Nala, Heru Shah Quary
10-A Charsaddah Charsad Area, Mardan, Dara Adam Khel
44 Mardan Katlung, Charsada
66-A Swabi Margallah
49-C Nowshera Nowshera, Mardan Area
52 Peshawar Balu Nala, GandiahNala Dheri Kati Khel Nala
34 Kohat Kohat area
27 Karak Pezu, Chokara, Tri Nala, Tironky nala
6 Bannu Kurram River, Pizu
41-B Lucky Murwat Pezu area
70-A Tank DI Khan Area
12 Dera Ismail Khan Daraban, Zam, Pirkuch Nala, Chund Quarry

xix
National Highway Authority Shabir Associates
Islamabad Quantity Surveying & Construction Cost Consultants

QUARRY SITES (NWFP)


Dist Code District Sites

FILLER MATERIAL
35 Kohistan dasu Buttgram/ Mansehra area
7-B Buttgram Buttgram/ Mansehra area
43 Mansehra Margalla, Hawalian
73 Muzafarabad Margalla, Hawalian
1 Abbottabad Dur Nala
20-B Haripur Hazara Margallah, Dur Nala
10 Chitral Chitral Area, Swat Area
15 Dir Swat Area, Quarry Available no crusher
66 Swat Saidu Sharif Chakdara, Swat Area
66-B Kalam Chakdara, Swat Area
7-A Buneer Swat Area
42 Malakand chakdara, Swat area
10-A Charsaddah Charsad Area, Mardan, Dara Adam Khel
44 Mardan Katlung, Charsada
66-A Swabi Margallah, Katlung
49-C Nowshera Katlung (Nowshera), Margallah
52 Peshawar Charsada, charat, Khyber pass, Adam Khel
34 Kohat Kohat Area, Dara Adam Khel
27 Karak Kohat Area
6 Bannu Kohat, Eisa Khel
41-B Lucky Murwat Kohat, Eisa Khel
70-A Tank Daraban Crushers
12 Dera Ismail Khan Daraban Crushers, Chund quarry

xx
National Highway Authority Shabir Associates
Islamabad Quantity Surveying & Construction Cost Consultants

Quantities of Material for Bituminous Surface Treatments

Surface Treatment Aggregate Bituminous Material

Type Application Size Quantity Quantity Type


No. Kg/ Sq.M Litres/ Sq.M
1.19 (a)
Single Single 2 12.5
1.63 (b)
1.9 (a)
First 1 24
2.14 (b)
Double
1.19 (a)
Second 3 12.5
1.63 (b)
1.9 (a)
First 1 24
2.14 (b)
Triple 1.19 (a)
Second 2 12.5
1.63 (b)
Third 3 6.5 0.68 (c)
Seal Coat / Pad
Coat with 4 4 0.5 (c)
Aggregate
Over Sub grade, Sub base , WBM or
0.65 ~ 1.75 (b)
Aggregate base
Prime Coat
Over Bridge, wearing surface. Concrete
0.15 ~ 0.4 (b)
pavement
Over Previously laid asphaltic layer 0.2 ~ 0.4 Cut-back
Tack Coat
Emulsified
Over Previously laid asphaltic layer 0.3 ~ 0.6
asphalt
Over prime or tack As per NHA / Grade 40/50,
Asphaltic Base 3% (Min.)
coated surface Project Spec's 60/70, 80/100
Asphaltic Over tack coated As per NHA / Grade 40/50,
3.5% (Min.)
Wearing Coarse surface Project Spec's 60/70, 80/100

Note:
(i) Bituminous material types are (a) asphalt cement, (b) cut-back or
emulsified and (c) asphalt cement, cut-back and emulsified

xxi
National Highway Authority Shabir Associates
Islamabad Quantity Surveying & Construction Cost Consultants

Portland Cement Concrete Requirements

Class of Min. Cement Max. Size 28 Days Compressive Consistency Maximum


Concrete Kg/ Cubic of Coarse Strength (Min) (Cylinder) (Range in Slump) Permissible
Meter Aggregate Water - Cement
(mm) (Kg/Sq. (Psi) Vibrated Ratio
Cm) (mm)
A1 300 20 210 3000 25 - 75 0.58
A2 350 25 245 3500 100 - 150 0.58
A3 400 38 280 4000 100 - 150 0.58
B 250 51 170 2450 25 - 75 0.65
C 275 38 210 3000 25 - 75 0.58
D1 450 25 350 5000 50 - 100 0.40
D2 500 25 425 6000 50 - 100 0.40
D3 550 25 500 7100 50 - 100 0.40
Y 400 13 210 3000 25 - 75 0.58
Lean
175 51 100 1420 – –
Concrete

Cement Bags per Unit Quantity

Qty of Cement
Sr. No Description Unit in Bag of 50
Kg

1 Burnt brickwork in Cement Mortar (1:6) CM 2.10


2 Burnt brickwork in Cement Mortar (1:3) CM 2.79
3 Pointing brickwork (flush) in Cement Mortar (1:3) SM 0.018
4 Pointing brickwork (flush) in Cement Mortar (1:4) SM 0.013
5 Pointing brickwork (flush) in Cement Mortar (1:6) SM 0.009
7 Random rubble masonry in Cement Mortar (1:4) CM 1.960
8 Pointing in Cement Mortar (1:3) flush to stone masonry SM 0.063
9 Pointing in Cement Mortar (1:4) flush to stone masonry SM 0.050
10 13 mm thick cement plaster (1:4) SM 0.14
11 13 mm thick cement plaster (1:3) SM 0.20
12 19 mm thick cement plaster (1:6) SM 0.13
13 19 mm thick cement plaster (1:4) SM 0.20

xxii
National Highway Authority Shabir Associates
Islamabad Quantity Surveying & Construction Cost Consultants

CONVERSION FACTORS
To Convert Into Multiply By
Length
Inch Millimetre 25.4
Millimetre Inch 0.03937
Foot Metre 0.30480
Metre Foot 3.28084
Yard Metre 0.91440
Metre Yard 1.09361
Mile Kilometre 1.60934
Kilometre Mile 0.62137
Mass. Weight
Pound Kilogram 0.45359237
Kilogram Pound 2.20462
Ounce Gram 28.3495
Gram Ounce 0.03527
Quintal Kilogram 100
Grain Milligram 64.7989
Hundred Weight Kilogram 50.8023
Tonne Hundred Weight 19.6841
Tonne Kilogram 1000
Ton Kilogram 1016.0469
Ton Pound 2240
Ton Tonne 1.0160469
Tonne Ton 0.9842065
Seer Kilogram 0.9331
Maund Kilogram 37.324
Tola Gram 11.664
Capacity Volume
Pint (UK) Litre 0.568261
Gallon (Imperial) Litre 4.54609
Cubic foot Litre 28.3168
Cubic metre Litre 1000
Litre Cubic foot 0.0353147
Fluid ounce Millilitre 28.413
Litre Gallon (Imperial) 0.219969
Cubic inch Cubic millimetre 16387.1
Cubic foot Cubic metre 0.0283168
Cubic metre Cubic foot 35.3147
Cubic yard Cubic metre 0.764555
Cubic metre Cubic yard 1.30795
Acre foot Hectare metre 0.12334
Weights & Standard Sizes of Sheets
Birmingham Gauge Thickness in mm Kg Per Sqm

28 0.40 3.15
26 0.50 3.90
24 0.63 4.95
22 0.80 6.30
20 1.00 7.85
18 1.25 9.80
16 1.60 12.75
14 2.00 15.70
12 2.50 19.60
10 3.15 24.75
8 4.00 31.40

xxiii
National Highway Authority Shabir Associates
Islamabad Quantity Surveying & Construction Cost Consultants

To Convert Into Multiply

Area

Square inch Square millimetre 645.16


Square millimetre Square inch 0.00155
Square foot Square metre 0.0929
Square metre Square foot 10.7639
Square yard Square metre 0.836127
Square metre Square yard 1.19599
Acre Square metre 4046.8564
Acre Hectare 0.40468564
Hectare Acre 2.47105
Hectare Square metre 10000
Square mile Square kilometre 2.58999
Square kilometre Square mile 0.386102
Square mile Hectare 258.999
Hectare Square mile 0.00386102

Mass Per Unit Area

Ton per square mile Kilogram per square kilometre 392.298


Pound per square foot Kilogram per square metre 4.88243
Kilogram per square metre Pound per square foot 0.204816

Mass Per Unit Volume

Ton per cubic foot Kilogram per cubic metre 16.0185


Pound per cubic foot Grams per litre 16.0185
Kilogram per cubic metre Pound per cubic foot 0.062428
Grams per litre Pound per cubic foot 0.062428

The weight of Mild Steel and Ribbed Tor Steel bars

Sectional area in Square Weight in Kilogram


Dia in Millimetre
Centimetre Per Metre
6 0.283 0.222
8 0.502 0.395
10 0.785 0.617
12 1.131 0.888
16 2.011 1.578
18 2.545 2.000
22 3.801 2.980
25 4.909 3.854
28 6.157 4.830
32 8.042 6.313
35 10.179 7.990
40 12.566 9.864
50 19.635 15.410

xxiv
NATIONAL HIGHWAY AUTHORITY

COMPOSITE SCHEDULE OF RATES


January - 2009

N.W.F.P.

Shabir Associates
Quantity Surveying & Construction Cost Consultants

Page 1
.

Page 2
CSR - January 2009
National Highway Authority Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

LIST OF DISTRICTS (NWFP)


Sr. No. Name of District Code Page
1 Abbottabad 01 5
2 Bannu 06 15
3 Buneer 07-A 25
4 Buttgram 07-B 35
5 Chitral 10 45
6 Charsaddah 10-A 55
7 Dera Ismail Khan 12 65
8 Dir 15 75
9 Haripur Hazara 20-B 85
10 Karak 27 95
11 Kohat 34 105
12 Kohistan Dasu 35 115
13 Lucky Murwat 41-B 125
14 Malakand 42 135
15 Mansehra 43 145
16 Mardan 44 155
17 Nowshera 49-C 165
18 Peshawar 52 175
19 Swat Saidu Sharif 66 185
20 Swabi 66-A 195
21 Tank 70-A 205
.

Page 4
NATIONAL HIGHWAY AUTHORITY

COMPOSITE SCHEDULE OF RATES


January - 2009

ABBOTTABAD
(01)

Shabir Associates
Quantity Surveying & Construction Cost Consultants

Page 5
.

Page 6
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Abbottabad
Abbottabad District Code: 01

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

101 CLEARING AND GRUBBING SM 0.73 10.10 - 2.71 13.54

102a REMOVAL OF TREES 150 - 300 mm GIRTH EACH 7.72 173.32 1.17 45.55 227.76

102b REMOVAL OF TREES 301 - 600 mm GIRTH EACH 21.50 456.54 2.63 120.17 600.84

102c REMOVAL OF TREES 601 mm OR OVER GIRTH EACH 86.01 1,826.16 10.51 480.67 2,403.35

103 STRIPPING CM 2.75 93.22 - 23.99 119.96

104 COMPACTION OF NATURAL GROUND SM 0.40 9.91 0.76 2.77 13.84

106a EXCAVATE UNSUITABLE COMMON MATERIAL CM 5.65 135.76 - 35.35 176.76

106bi EXCAVATE UNSUITABLE HARD ROCK MATERIAL CM 141.76 316.30 50.82 127.22 636.10

106bii EXCAVATE UNSUITABLE MEDIUM ROCK MATERIAL CM 18.27 337.99 - 89.07 445.33

106biii EXCAVATE UNSUITABLE SOFT ROCK MATERIAL CM 12.03 262.40 - 68.61 343.03

106c EXCAVATE SURPLUS COMMON MATERIAL CM 4.62 120.27 - 31.22 156.11

106di EXCAVATE SURPLUS HARD ROCK MATERIAL CM 141.76 316.30 50.82 127.22 636.10

106dii EXCAVATE SURPLUS MEDIUM ROCK MATERIAL CM 22.64 316.03 - 84.67 423.34

106diii EXCAVATE SURPLUS SOFT ROCK MATERIAL CM 9.25 263.92 - 68.29 341.47

107a STRUCTURAL EXCAVATION IN COMMON MATERIAL CM 8.58 137.60 0.38 36.64 183.20

107b STRUCTURAL EXCAVATION IN COMMON MATERIAL BELOW CM 66.41 287.11 70.80 106.08 530.42
WATER LEVEL

107ci STRUCTURAL EXCAVATION IN HARD ROCK MATERIAL CM 125.77 427.01 33.88 146.67 733.33

107cii STRUCTURAL EXCAVATION IN MEDIUM ROCK MATERIAL CM 105.22 292.53 - 99.44 497.20

107ciii STRUCTURAL EXCAVATION IN SOFT ROCK MATERIAL CM 64.68 238.86 - 75.89 379.43

107d GRANULAR BACK FILL CM 37.04 137.14 415.39 147.39 736.96

107e COMMON BACK FILL CM 25.46 62.84 5.09 23.35 116.74

108a FORMATION OF EMBANKMENT FROM ROADWAY CM 7.56 174.71 5.09 46.84 234.20
EXCAVATION IN COMMON MATERIAL

108bi FORMATION OF EMBANKMENT FROM ROADWAY CM 21.72 482.48 54.04 139.56 697.80
EXCAVATION IN HARD ROCK MATERIAL

108bii FORMATION OF EMBANKMENT FROM ROADWAY CM 16.29 416.71 2.42 108.85 544.27
EXCAVATION IN MEDIUM ROCK MATERIAL

108biii FORMATION OF EMBANKMENT FROM ROADWAY CM 14.48 369.34 - 95.96 479.78


EXCAVATION IN SOFT ROCK MATERIAL

108c FORMATION OF EMBANKMENT FROM BORROW CM 8.48 177.46 7.94 48.47 242.35
EXCAVATION IN COMMON MATERIAL

108d FORMATION OF EMBANKMENT FROM STRUCTURAL CM 6.77 76.32 5.09 22.04 110.22
EXCAVATION IN COMMON MATERIAL

108e FORMATION OF EMBANKMENT FROM STRUCTURAL CM 15.36 110.29 3.03 32.17 160.84
EXCAVATION IN ANY TYPE OF ROCK MATERIAL

109a SUB GRADE PREPARATION IN EARTH CUT SM 1.54 27.34 1.46 7.58 37.91

Page 7
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Abbottabad
Abbottabad District Code: 01

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

109bi SUB GRADE PREPARATION IN EXISTING ROAD WITHOUT SM 1.13 18.21 0.77 5.03 25.14
ANY FILL

110 IMPROVED SUB-GRADE CM 10.80 120.02 52.42 45.81 229.05

114a DRESSING OF BERM WITHOUT EXTRA MATERIAL SM 0.92 15.26 0.79 4.24 21.22

114b DRESSING OF BERM WITH EXTRA BORROW MATERIAL SM 1.34 15.57 0.90 4.45 22.26

201 GRANULAR SUB-BASE CM 8.66 255.06 496.38 190.02 950.12

202 AGGREGATE BASE CM 10.54 326.54 728.09 266.29 1,331.46

203a ASPHALTIC BASE COURSE PLANT MIX (CLASS "A") CM 72.70 1,510.17 5,779.15 1,840.50 9,202.52

203b ASPHALTIC BASE COURSE PLANT MIX (CLASS "B") CM 75.56 1,510.17 6,199.49 1,946.30 9,731.52

203c ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "A") CM 80.83 1,577.28 5,769.58 1,856.92 9,284.62

203d ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "B") CM 80.83 1,571.31 6,342.09 1,998.56 9,992.79

204b CEMENT STABILIZED BASE CM 31.56 569.10 956.14 389.20 1,946.00

204d LIQUID ASPHALT FOR CURING SEAL, TYPE MC-250 TON 269.62 915.38 50,538.21 12,930.80 64,654.01

204e EMULSIFIED ASPHALT FOR CURING SEAL, TYPE SS-1 TON 269.62 915.38 48,960.08 12,536.27 62,681.35

205a GRADED CRUSHED AGGREGATE CRACK-RELIEF LAYER CM 91.61 112.80 966.30 292.68 1,463.38

205b ASPHALTIC OPEN-GRADED PLANT MIX CRACK-RELIEF CM 152.82 2,437.94 5,563.63 2,038.60 10,192.99
LAYER

206b WATER BOUND MACADAM BASE WITH COARSE CM 100.25 126.27 777.24 250.94 1,254.71
AGGREGATE CLASS B

207a DEEP PATCHING (0-15 cm) SM 1.90 45.04 1.26 12.05 60.24

207b DEEP PATCHING (16-30 cm) SM 1.90 39.67 1.26 10.71 53.53

208 REINSTATEMENT OF ROAD SURFACE SM 2.09 57.10 0.56 14.94 74.69

209a BREAKING OF EXISTING ROAD PAVEMENT STRUCTURE CM 2.50 110.61 0.68 28.45 142.23

209b SCARIFICATION OF EXISTING ROAD PAVEMENT SM 0.50 22.12 0.14 5.69 28.45

302a CUT-BACK ASPHALT FOR BITUMINOUS PRIME COAT SM 0.33 1.57 35.87 9.44 47.22

302b EMULSIFIED ASPHALT FOR BITUMINOUS PRIME COAT SM 0.32 1.57 40.04 10.48 52.42

303a CUT-BACK ASPHALT FOR BITUMINOUS TACK COAT SM 0.13 0.58 15.01 3.93 19.66

303b EMULSIFIED ASPHALT FOR BITUMINOUS TACK COAT SM 0.13 0.58 17.51 4.56 22.78

304a SINGLE SURFACE TREATMENT SM 0.88 7.57 71.25 19.92 99.62

304b DOUBLE SURFACE TREATMENT SM 1.27 14.15 138.38 38.45 192.24

304c TRIPLE SURFACE TREATMENT SM 2.14 19.94 157.82 44.97 224.87

304d SEAL COAT SM 0.82 4.12 50.15 13.77 68.87

Page 8
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Abbottabad
Abbottabad District Code: 01

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

305a ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 69.52 1,489.33 6,772.24 2,082.77 10,413.86
"A")

305b ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 69.52 1,438.23 7,296.26 2,201.00 11,005.01
"B")

307a DENSE GRADED HOT BIT-MAC CM 167.81 379.77 5,555.86 1,525.86 7,629.31

307b OPEN GRADED HOT BIT-MAC CM 167.81 379.77 5,441.58 1,497.29 7,486.45

308a RECYCLING OF ASPHALT CONCRETE (0 - 60 mm THICK) CM 29.24 590.65 2,021.86 660.44 3,302.18

308b BITUMEN BINDER GRADE (40 - 50, 60 - 70, 80 - 100) TON 29.19 650.70 42,543.28 10,805.79 54,028.96

309a COLD MILLING, 0 - 30 mm SM 1.07 24.99 8.68 8.69 43.43

309b COLD MILLING, 0 - 50 mm SM 1.79 41.65 14.46 14.48 72.38

309c COLD MILLING, 0 - 70 mm SM 2.68 62.48 21.69 21.71 108.56

401a1i CONCRETE CLASS "A1" (Underground) CM 544.84 1,059.94 3,946.83 1,387.90 6,939.52

401a1ii CONCRETE CLASS "A1" (On ground) CM 544.84 1,059.94 4,224.31 1,457.27 7,286.36

401a1iii CONCRETE CLASS "A1" (Elevated) CM 544.84 1,059.94 4,779.25 1,596.01 7,980.04

401a2i CONCRETE CLASS "A2" (Underground) CM 544.84 1,059.94 4,324.83 1,482.40 7,412.02

401a2ii CONCRETE CLASS "A2" (On ground) CM 544.84 1,059.94 4,602.31 1,551.77 7,758.86

401a2iii CONCRETE CLASS "A2" (Elevated) CM 544.84 1,059.94 5,157.25 1,690.51 8,452.54

401a3i CONCRETE CLASS "A3" (Underground) CM 544.84 1,059.94 4,702.83 1,576.90 7,884.52

401a3ii CONCRETE CLASS "A3" (On ground) CM 544.84 1,059.94 4,980.31 1,646.27 8,231.36

401a3iii CONCRETE CLASS "A3" (Elevated) CM 544.84 1,059.94 5,535.25 1,785.01 8,925.04

401b CONCRETE CLASS "B" CM 719.81 805.93 3,249.38 1,193.78 5,968.90

401ci CONCRETE CLASS "C" (Underground) CM 531.99 500.55 3,544.96 1,144.37 5,721.87

401cii CONCRETE CLASS "C" (On ground) CM 531.99 500.55 3,663.30 1,173.96 5,869.80

401ciii CONCRETE CLASS "C" (Elevated) CM 531.99 500.55 3,899.98 1,233.13 6,165.66

401d CONCRETE CLASS "D1" CM 830.79 1,265.57 5,295.34 1,847.93 9,239.63

401e CONCRETE CLASS "Y" CM 1,144.74 500.55 4,712.45 1,589.44 7,947.18

401f LEAN CONCRETE CM 446.13 507.52 2,520.49 868.53 4,342.66

401gi(1) PRECAST CONCRETE CLASS "A-1" CM 1,788.08 947.15 4,942.49 1,919.43 9,597.14

401gi(3) PRECAST CONCRETE CLASS "A-3" CM 1,788.08 947.15 5,698.49 2,108.43 10,542.14

401gii PRECAST CONCRETE CLASS "B" CM 1,788.08 947.15 4,778.84 1,878.52 9,392.59

401giii(1) PRECAST CONCRETE CLASS "D1" CM 1,788.08 947.15 6,076.49 2,202.93 11,014.64

Page 9
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Abbottabad
Abbottabad District Code: 01

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

401giii(2) PRECAST CONCRETE CLASS "D2" CM 1,788.08 947.15 6,454.49 2,297.43 11,487.14

401giii(3) PRECAST CONCRETE CLASS "D3" CM 1,788.08 947.15 6,832.49 2,391.93 11,959.64

404a REINFORCEMENT AS PER AASHTO M. 31 GRADE 40 TON 1,649.89 781.47 59,888.00 15,579.84 77,899.20

404b REINFORCEMENT AS PER AASHTO M. 31 GRADE 60 TON 1,649.89 781.47 67,238.00 17,417.34 87,086.70

404h REINFORCEMENT (STRUCTURAL SHAPES) AS PER ASTM-A- TON 1,311.27 5,393.81 56,007.02 15,678.02 78,390.12
36

405a PRE-STRESSING WIRE STRAND 3/8" - 1/2" DIA COMPLETE IN TON 2,816.57 15,659.05 133,860.36 38,083.99 190,419.97
ALL RESPECT

405b LAUNCHING OF GIRDER TON 65.06 532.52 - 149.40 746.98

406a PREMOULDED JOINT FILLER 12 mm THICK WITH SM 115.67 - 301.01 104.17 520.85
BITUMASTIC JOINT SEAL

406b NEOPRENE RUBBER JOINT FILLER 12 mm THICK WITH SM 115.67 - 307.07 105.68 528.42
BITUMASTIC JOINT SEAL

406c STEEL EXPANSION JOINTS KG 9.48 26.40 90.86 31.68 158.42

406d WATER STOPS 6" SIZE M 98.99 - 472.28 142.82 714.08

406e ELASTOMERIC BEARING PADS (ACCORDING TO SIZE AND ccm 0.02 - 2.12 0.53 2.67
THICKNESS)

406f ASPHALT FELT (3 PLY) SM 45.65 - 2,960.09 751.43 3,757.17

406g STEEL OR METAL BEARING DEVICES KG 20.82 69.68 117.77 52.07 260.34

407d1 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 355.84 1,654.04 899.75 727.41 3,637.04
(BORING ONLY) IN NORMAL SOIL

407d2 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 533.76 2,481.06 1,349.62 1,091.11 5,455.56
(BORING ONLY) IN GRAVEL STRATA

407d3 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 533.76 2,481.06 997.52 1,003.09 5,015.44
ONLY) IN NORMAL SOIL

407d4 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 889.61 4,135.11 1,174.50 1,549.80 7,749.02
ONLY) IN GRAVEL STRATA

407d5 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 762.52 4,884.94 1,354.70 1,750.54 8,752.70
ONLY) IN NORMAL SOIL

407d6 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 1,334.41 6,909.78 1,487.23 2,432.86 12,164.28
ONLY) IN GRAVEL SOIL

407h PILE LOAD TEST UP TO 120 TON EACH 22,545.15 45,769.30 100,542.38 42,214.21 211,071.05

407i PILE LOAD TEST UP TO 240 TON EACH 41,156.52 45,769.30 201,084.76 72,002.65 360,013.23

407j PILE LOAD TEST UP TO 360 TON EACH 59,767.89 50,188.38 301,627.14 102,895.85 514,479.27

407k CONFIRMATORY BORING (NX SIZE) M 194.25 1,582.02 6.37 445.66 2,228.30

410 BRICK WORK CM 356.73 282.72 3,076.60 929.01 4,645.06

411a STONE MASONRY RANDOM DRY CM 299.85 107.96 562.16 242.49 1,212.46

411b STONE MASONRY RANDOM WITH MORTAR CM 324.74 166.68 1,635.48 531.73 2,658.64

411c STONE MASONRY DRESSED UNCOURSED DRY CM 391.00 107.96 625.28 281.06 1,405.29

411d STONE MASONRY DRESSED UNCOURSED WITH MORTAR CM 461.46 166.68 1,697.90 581.51 2,907.55

Page 10
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Abbottabad
Abbottabad District Code: 01

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

411g ROLL POINTING SM 76.19 11.74 44.53 33.12 165.59

412a STONE MASONRY DRESSED COURSED WITH MORTAR CM 618.85 264.08 1,603.09 621.51 3,107.53

501a R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 310 mm M 229.85 437.48 644.86 328.05 1,640.25

501b R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 380 mm M 221.88 577.19 835.93 408.75 2,043.75

501c R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 460 mm M 221.73 935.96 1,071.91 557.40 2,787.00

501d R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 610 mm M 229.77 1,146.39 1,600.63 744.20 3,720.99

501e R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 760 mm M 264.84 1,078.41 2,300.27 910.88 4,554.41

501f R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 910 mm M 330.10 1,331.30 3,618.01 1,319.85 6,599.26

501g R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1070 mm M 427.18 1,481.41 4,683.95 1,648.14 8,240.68

501h R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1220 mm M 500.94 1,798.85 5,968.88 2,067.17 10,335.84

501i R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1520 mm M 596.65 2,098.66 9,218.85 2,978.54 14,892.70

501j R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 310 mm M 229.85 507.33 725.04 365.56 1,827.78

501k R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 380 mm M 221.88 577.19 854.75 413.46 2,067.28

501l R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 460 mm M 216.61 935.96 1,046.49 549.77 2,748.83

501m R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 610 mm M 229.77 1,146.39 1,745.56 780.43 3,902.15

501n R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 760 mm M 264.84 1,078.41 3,318.70 1,165.49 5,827.45

501o R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 910 mm M 330.10 1,331.30 4,875.32 1,634.18 8,170.90

501p R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1070 mm M 427.18 1,481.41 6,812.38 2,180.24 10,901.22

501q R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1220 mm M 500.94 1,798.85 9,239.15 2,884.74 14,423.68

501r R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1520 mm M 596.65 2,098.66 12,997.71 3,923.26 19,616.28

502a GRANULAR MATERIAL IN BED TO CONCRETE PIPE CM 93.70 118.93 428.06 160.17 800.85
CULVERT

502b CONCRETE CLASS "B" IN BEDDING AND ENCASEMENT OF CM 800.63 612.95 3,599.38 1,253.24 6,266.20
CONCRETE PIPE CULVERT

507a STEEL WIRE MESH FOR GABIONS KG 5.67 - 109.50 28.79 143.96

507b ROCK FILL IN GABIONS CM 96.86 - 388.21 121.27 606.34

508a BRICK PAVING (SINGLE COURSE) SM 115.45 32.70 246.96 98.78 493.88

508b BRICK PAVING (DOUBLE COURSE) SM 206.59 32.70 490.14 182.36 911.78

509a RIP RAP CLASS "A" CM 506.56 - 467.35 243.48 1,217.38

509b RIP RAP CLASS "B" CM 486.43 - 463.61 237.51 1,187.55

509c RIP RAP CLASS "C" CM 489.61 - 467.35 239.24 1,196.20

Page 11
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Abbottabad
Abbottabad District Code: 01

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

509d GROUTED RIP RAP CLASS "A" CM 616.99 102.14 1,889.70 652.21 3,261.04

509e GROUTED RIP RAP CLASS "B" CM 594.69 81.72 1,738.21 603.65 3,018.27

509f GROUTED RIP RAP CLASS "C" CM 586.72 68.10 1,784.62 609.86 3,049.29

509g REINFORCED CONCRETE SLOPE PROTECTION (WITHOUT CM 816.75 353.02 4,161.87 1,332.91 6,664.55
REINFORCEMENT)

509h FILTER LAYER OF GRANULAR MATERIAL CM 47.66 191.97 415.94 163.90 819.48

510 DISMANTLING OF STRUCTURE AND OBSTRUCTIONS CM 107.69 390.69 - 124.60 622.98

511a1 DRY STONE PITCHING (15-20 cm Thick) SM 159.31 67.48 75.94 75.68 378.41

511a2 DRY STONE PITCHING (21-25 cm Thick) SM 203.92 86.37 97.21 96.87 484.37

511b1 GROUTED STONE PITCHING (15-20 cm Thick) SM 260.29 180.32 374.87 203.87 1,019.34

511b2 GROUTED STONE PITCHING (21-25 cm Thick) SM 325.36 225.40 468.58 254.84 1,274.18

601ai CONCRETE KERB IN PLACE NEW JERSY BARRIER FOR M 288.84 572.25 2,210.98 768.02 3,840.08
MEDIAN (DOUBLE FACE)

601di PRECAST REINFORCED CONCRETE KERB NEW JERSY M 982.88 670.54 4,055.33 1,427.18 7,135.92
BARRIER FOR MEDIAN (DOUBLE FACE)

601dii PRECAST KERB IN CONCRETE CLASS A-1 OF SIZE 450 X 150 MM M 143.14 90.27 430.28 165.92 829.61
INCLUDING CONCRETE BEDDING & HAUNCHING

603 BRICK EDGING M 9.22 - 38.88 12.03 60.13

604a METAL GUARD RAIL M 19.85 70.84 1,579.36 417.51 2,087.56

604b METAL GUARD RAIL END PIECES EACH 25.20 - 1,197.58 305.69 1,528.47

604d STEEL POST OF METAL GUARD RAIL EACH 95.54 976.73 3,776.31 1,212.14 6,060.72

605a CONCRETE BEAM GUARD RAIL M 74.55 30.82 590.23 173.90 869.50

605c CONCRETE POST FOR GUARD RAIL M 91.53 27.36 590.14 177.26 886.29

607a TRAFFIC ROAD SIGN CATEGORY 1 EACH 240.49 255.15 6,856.68 1,838.08 9,190.40

607b TRAFFIC ROAD SIGN CATEGORY 2 EACH 70.70 382.72 9,258.32 2,427.94 12,139.68

607c TRAFFIC ROAD SIGN CATEGORY 3 (a) EACH 240.49 541.89 11,887.89 3,167.57 15,837.83

607d TRAFFIC ROAD SIGN CATEGORY 3 (b) EACH 754.41 598.64 20,957.75 5,577.70 27,888.50

607e TRAFFIC ROAD SIGN CATEGORY 3 (c) SM 150.88 119.73 9,209.53 2,370.04 11,850.18

607f ADDITIONAL PANEL SIZE 60 X 30 cm EACH 316.33 - 1,303.23 404.89 2,024.46

607g ADDITIONAL PANEL SIZE 90 X 30 cm EACH 316.33 - 1,954.85 567.80 2,838.98

608b1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.83 5.86 16.16 6.21 31.07
LINES OF 15 cm WIDTH

608b2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.94 4.03 39.66 11.16 55.79
LINES OF 15 cm WIDTH

608c1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.83 5.86 21.57 7.56 37.82
LINES OF 20 cm WIDTH

Page 12
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Abbottabad
Abbottabad District Code: 01

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

608c2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.94 4.03 52.89 14.47 72.33
LINES OF 20 cm WIDTH

608d1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 76.53 5.22 156.16 59.48 297.39
4.0 M ARROWS

608d2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR 4.0 EACH 76.53 9.98 499.74 146.56 732.82
M ARROWS

608h1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.54 8.59 22.48 8.65 43.26
OF 15 cm WIDTH

608h2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.54 9.63 67.50 20.17 100.85
OF 15 cm WIDTH

608i1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.54 6.95 29.97 10.12 50.58
OF 20 cm WIDTH

608i2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.54 9.63 90.01 25.79 128.97
OF 20 cm WIDTH

608j1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR 4.0 M EACH 76.53 3.73 217.02 74.32 371.60
ARROWS

608j2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR 4.0 M EACH 76.53 7.90 851.20 233.91 1,169.53
ARROWS

608n1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 63.89 3.73 104.11 42.93 214.66
STOP

608n2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR EACH 63.89 7.90 333.67 101.36 506.82
STOP

608n3 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR STOP EACH 63.89 3.73 144.68 53.07 265.37

608n4 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR STOP EACH 63.89 7.90 568.32 160.03 800.14

609c REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 9.41 81.62 193.86 71.22 356.11
SINGLE)

609d REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 9.41 81.62 233.86 81.22 406.10
DOUBLE)

610b RIGHT OF WAY MARKER EACH 102.51 121.33 299.32 130.79 653.95

610c KILOMETRE POST (0.610 X 0.114 X 1.5 M) EACH 640.99 976.31 2,009.70 906.75 4,533.75

610d TEN KILOMETRE POST EACH 1,224.53 1,952.61 4,414.31 1,897.86 9,489.32

611a CHAIN LINK WIRE FABRIC FENCING 1500 MM HEIGHT M 135.53 91.00 952.71 294.81 1,474.05
WITH PRECAST PRESTRESSED R.C.C. POST

Page 13
.

Page 14
NATIONAL HIGHWAY AUTHORITY

COMPOSITE SCHEDULE OF RATES


January - 2009

BANNU
(06)

Shabir Associates
Quantity Surveying & Construction Cost Consultants

Page 15
.

Page 16
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Bannu
Bannu District Code: 06

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

101 CLEARING AND GRUBBING SM 0.61 10.10 - 2.68 13.39

102a REMOVAL OF TREES 150 - 300 mm GIRTH EACH 6.47 173.32 1.17 45.24 226.20

102b REMOVAL OF TREES 301 - 600 mm GIRTH EACH 17.93 456.54 2.63 119.27 596.37

102c REMOVAL OF TREES 601 mm OR OVER GIRTH EACH 71.71 1,826.16 10.51 477.10 2,385.48

103 STRIPPING CM 2.37 93.22 - 23.90 119.49

104 COMPACTION OF NATURAL GROUND SM 0.34 9.91 0.76 2.75 13.77

106a EXCAVATE UNSUITABLE COMMON MATERIAL CM 4.73 135.76 - 35.12 175.61

106bi EXCAVATE UNSUITABLE HARD ROCK MATERIAL CM 119.86 316.30 50.82 121.74 608.72

106bii EXCAVATE UNSUITABLE MEDIUM ROCK MATERIAL CM 15.88 337.99 - 88.47 442.34

106biii EXCAVATE UNSUITABLE SOFT ROCK MATERIAL CM 10.44 262.40 - 68.21 341.05

106c EXCAVATE SURPLUS COMMON MATERIAL CM 3.87 120.27 - 31.04 155.18

106di EXCAVATE SURPLUS HARD ROCK MATERIAL CM 119.86 316.30 50.82 121.74 608.72

106dii EXCAVATE SURPLUS MEDIUM ROCK MATERIAL CM 19.06 316.03 - 83.77 418.86

106diii EXCAVATE SURPLUS SOFT ROCK MATERIAL CM 8.10 263.92 - 68.01 340.03

107a STRUCTURAL EXCAVATION IN COMMON MATERIAL CM 7.50 137.60 0.38 36.37 181.85

107b STRUCTURAL EXCAVATION IN COMMON MATERIAL BELOW CM 56.09 287.11 70.80 103.50 517.52
WATER LEVEL

107ci STRUCTURAL EXCAVATION IN HARD ROCK MATERIAL CM 105.87 427.01 33.88 141.69 708.46

107cii STRUCTURAL EXCAVATION IN MEDIUM ROCK MATERIAL CM 88.71 292.53 - 95.31 476.56

107ciii STRUCTURAL EXCAVATION IN SOFT ROCK MATERIAL CM 54.45 238.86 - 73.33 366.64

107d GRANULAR BACK FILL CM 30.39 137.14 340.81 127.08 635.42

107e COMMON BACK FILL CM 20.82 62.84 5.09 22.19 110.93

108a FORMATION OF EMBANKMENT FROM ROADWAY CM 6.60 174.71 5.09 46.60 233.01
EXCAVATION IN COMMON MATERIAL

108bi FORMATION OF EMBANKMENT FROM ROADWAY CM 18.71 482.48 54.04 138.81 694.04
EXCAVATION IN HARD ROCK MATERIAL

108bii FORMATION OF EMBANKMENT FROM ROADWAY CM 14.03 416.71 2.42 108.29 541.45
EXCAVATION IN MEDIUM ROCK MATERIAL

108biii FORMATION OF EMBANKMENT FROM ROADWAY CM 12.47 369.34 - 95.45 477.27


EXCAVATION IN SOFT ROCK MATERIAL

108c FORMATION OF EMBANKMENT FROM BORROW CM 7.35 177.46 7.94 48.19 240.94
EXCAVATION IN COMMON MATERIAL

108d FORMATION OF EMBANKMENT FROM STRUCTURAL CM 5.95 76.32 5.09 21.84 109.20
EXCAVATION IN COMMON MATERIAL

108e FORMATION OF EMBANKMENT FROM STRUCTURAL CM 13.31 110.29 3.03 31.66 158.28
EXCAVATION IN ANY TYPE OF ROCK MATERIAL

109a SUB GRADE PREPARATION IN EARTH CUT SM 1.32 27.34 1.46 7.53 37.65

Page 17
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Bannu
Bannu District Code: 06

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

109bi SUB GRADE PREPARATION IN EXISTING ROAD WITHOUT SM 0.99 18.21 0.77 4.99 24.96
ANY FILL

110 IMPROVED SUB-GRADE CM 9.43 120.02 55.47 46.23 231.15

114a DRESSING OF BERM WITHOUT EXTRA MATERIAL SM 0.81 15.26 0.79 4.21 21.07

114b DRESSING OF BERM WITH EXTRA BORROW MATERIAL SM 1.20 15.57 0.90 4.42 22.08

201 GRANULAR SUB-BASE CM 7.48 255.06 456.69 179.81 899.03

202 AGGREGATE BASE CM 9.04 326.54 701.45 259.26 1,296.29

203a ASPHALTIC BASE COURSE PLANT MIX (CLASS "A") CM 60.93 1,510.17 6,175.96 1,936.76 9,683.82

203b ASPHALTIC BASE COURSE PLANT MIX (CLASS "B") CM 63.29 1,510.17 6,637.76 2,052.80 10,264.01

203c ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "A") CM 67.89 1,577.28 6,165.88 1,952.76 9,763.81

203d ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "B") CM 67.89 1,571.31 6,787.17 2,106.59 10,532.96

204b CEMENT STABILIZED BASE CM 26.94 569.10 1,007.07 400.78 2,003.89

204d LIQUID ASPHALT FOR CURING SEAL, TYPE MC-250 TON 225.34 915.38 54,580.23 13,930.24 69,651.19

204e EMULSIFIED ASPHALT FOR CURING SEAL, TYPE SS-1 TON 225.34 915.38 53,002.10 13,535.71 67,678.53

205a GRADED CRUSHED AGGREGATE CRACK-RELIEF LAYER CM 76.02 112.80 1,020.83 302.41 1,512.06

205b ASPHALTIC OPEN-GRADED PLANT MIX CRACK-RELIEF CM 130.07 2,437.94 5,897.02 2,116.26 10,581.30
LAYER

206b WATER BOUND MACADAM BASE WITH COARSE CM 82.54 126.27 819.51 257.08 1,285.41
AGGREGATE CLASS B

207a DEEP PATCHING (0-15 cm) SM 1.68 45.04 1.26 11.99 59.96

207b DEEP PATCHING (16-30 cm) SM 1.68 39.67 1.26 10.65 53.26

208 REINSTATEMENT OF ROAD SURFACE SM 1.80 57.10 0.56 14.87 74.33

209a BREAKING OF EXISTING ROAD PAVEMENT STRUCTURE CM 2.20 110.61 0.68 28.37 141.87

209b SCARIFICATION OF EXISTING ROAD PAVEMENT SM 0.44 22.12 0.14 5.67 28.37

302a CUT-BACK ASPHALT FOR BITUMINOUS PRIME COAT SM 0.28 1.57 38.74 10.15 50.74

302b EMULSIFIED ASPHALT FOR BITUMINOUS PRIME COAT SM 0.27 1.57 43.24 11.27 56.36

303a CUT-BACK ASPHALT FOR BITUMINOUS TACK COAT SM 0.11 0.58 16.21 4.23 21.13

303b EMULSIFIED ASPHALT FOR BITUMINOUS TACK COAT SM 0.11 0.58 18.91 4.90 24.51

304a SINGLE SURFACE TREATMENT SM 0.73 7.57 77.52 21.46 107.28

304b DOUBLE SURFACE TREATMENT SM 1.06 14.15 150.81 41.51 207.53

304c TRIPLE SURFACE TREATMENT SM 1.81 19.94 172.05 48.45 242.24

304d SEAL COAT SM 0.68 4.12 54.25 14.76 73.81

Page 18
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Bannu
Bannu District Code: 06

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

305a ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 58.58 1,489.33 7,271.71 2,204.91 11,024.53
"A")

305b ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 58.58 1,438.23 7,847.43 2,336.06 11,680.30
"B")

307a DENSE GRADED HOT BIT-MAC CM 143.88 379.77 6,033.35 1,639.25 8,196.25

307b OPEN GRADED HOT BIT-MAC CM 143.88 379.77 5,901.23 1,606.22 8,031.11

308a RECYCLING OF ASPHALT CONCRETE (0 - 60 mm THICK) CM 26.26 590.65 2,127.90 686.20 3,431.01

308b BITUMEN BINDER GRADE (40 - 50, 60 - 70, 80 - 100) TON 23.97 650.70 46,705.36 11,845.01 59,225.03

309a COLD MILLING, 0 - 30 mm SM 0.91 24.99 8.68 8.65 43.23

309b COLD MILLING, 0 - 50 mm SM 1.52 41.65 14.46 14.41 72.05

309c COLD MILLING, 0 - 70 mm SM 2.28 62.48 21.69 21.61 108.07

401a1i CONCRETE CLASS "A1" (Underground) CM 478.21 1,059.94 4,023.06 1,390.30 6,951.52

401a1ii CONCRETE CLASS "A1" (On ground) CM 478.21 1,059.94 4,300.54 1,459.67 7,298.36

401a1iii CONCRETE CLASS "A1" (Elevated) CM 478.21 1,059.94 4,855.48 1,598.41 7,992.04

401a2i CONCRETE CLASS "A2" (Underground) CM 478.21 1,059.94 4,401.06 1,484.80 7,424.02

401a2ii CONCRETE CLASS "A2" (On ground) CM 478.21 1,059.94 4,678.54 1,554.17 7,770.86

401a2iii CONCRETE CLASS "A2" (Elevated) CM 478.21 1,059.94 5,233.48 1,692.91 8,464.54

401a3i CONCRETE CLASS "A3" (Underground) CM 478.21 1,059.94 4,779.06 1,579.30 7,896.52

401a3ii CONCRETE CLASS "A3" (On ground) CM 478.21 1,059.94 5,056.54 1,648.67 8,243.36

401a3iii CONCRETE CLASS "A3" (Elevated) CM 478.21 1,059.94 5,611.48 1,787.41 8,937.04

401b CONCRETE CLASS "B" CM 628.71 805.93 3,339.12 1,193.44 5,967.20

401ci CONCRETE CLASS "C" (Underground) CM 468.51 500.55 3,636.33 1,151.35 5,756.74

401cii CONCRETE CLASS "C" (On ground) CM 468.51 500.55 3,754.67 1,180.93 5,904.67

401ciii CONCRETE CLASS "C" (Elevated) CM 468.51 500.55 3,991.36 1,240.10 6,200.52

401d CONCRETE CLASS "D1" CM 719.69 1,265.57 5,366.12 1,837.85 9,189.23

401e CONCRETE CLASS "Y" CM 968.35 500.55 4,779.57 1,562.12 7,810.59

401f LEAN CONCRETE CM 386.26 507.52 2,610.45 876.06 4,380.28

401gi(1) PRECAST CONCRETE CLASS "A-1" CM 1,544.99 947.15 5,024.80 1,879.24 9,396.18

401gi(3) PRECAST CONCRETE CLASS "A-3" CM 1,544.99 947.15 5,780.80 2,068.24 10,341.18

401gii PRECAST CONCRETE CLASS "B" CM 1,544.99 947.15 4,872.67 1,841.20 9,206.02

401giii(1) PRECAST CONCRETE CLASS "D1" CM 1,544.99 947.15 6,158.80 2,162.74 10,813.68

Page 19
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Bannu
Bannu District Code: 06

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

401giii(2) PRECAST CONCRETE CLASS "D2" CM 1,544.99 947.15 6,536.80 2,257.24 11,286.18

401giii(3) PRECAST CONCRETE CLASS "D3" CM 1,544.99 947.15 6,914.80 2,351.74 11,758.68

404a REINFORCEMENT AS PER AASHTO M. 31 GRADE 40 TON 1,404.37 781.47 61,478.00 15,915.96 79,579.80

404b REINFORCEMENT AS PER AASHTO M. 31 GRADE 60 TON 1,404.37 781.47 68,828.00 17,753.46 88,767.30

404h REINFORCEMENT (STRUCTURAL SHAPES) AS PER ASTM-A- TON 1,116.38 5,393.81 56,979.33 15,872.38 79,361.90
36

405a PRE-STRESSING WIRE STRAND 3/8" - 1/2" DIA COMPLETE IN TON 2,680.32 15,659.05 133,860.48 38,049.96 190,249.81
ALL RESPECT

405b LAUNCHING OF GIRDER TON 63.07 532.52 - 148.90 744.49

406a PREMOULDED JOINT FILLER 12 mm THICK WITH SM 97.59 - 305.06 100.66 503.31
BITUMASTIC JOINT SEAL

406b NEOPRENE RUBBER JOINT FILLER 12 mm THICK WITH SM 97.59 - 304.27 100.47 502.33
BITUMASTIC JOINT SEAL

406c STEEL EXPANSION JOINTS KG 7.81 26.40 91.98 31.55 157.73

406d WATER STOPS 6" SIZE M 90.10 - 469.93 140.01 700.04

406e ELASTOMERIC BEARING PADS (ACCORDING TO SIZE AND ccm 0.02 - 2.12 0.53 2.67
THICKNESS)

406f ASPHALT FELT (3 PLY) SM 40.00 - 3,061.21 775.30 3,876.51

406g STEEL OR METAL BEARING DEVICES KG 16.68 69.68 119.64 51.50 257.50

407d1 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 347.81 1,654.04 900.65 725.62 3,628.12
(BORING ONLY) IN NORMAL SOIL

407d2 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 521.71 2,481.06 1,350.97 1,088.44 5,442.19
(BORING ONLY) IN GRAVEL STRATA

407d3 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 521.71 2,481.06 999.02 1,000.45 5,002.25
ONLY) IN NORMAL SOIL

407d4 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 869.52 4,135.11 1,177.00 1,545.41 7,727.04
ONLY) IN GRAVEL STRATA

407d5 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 745.31 4,884.94 1,357.91 1,747.04 8,735.20
ONLY) IN NORMAL SOIL

407d6 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 1,304.29 6,909.78 1,490.98 2,426.26 12,131.31
ONLY) IN GRAVEL SOIL

407h PILE LOAD TEST UP TO 120 TON EACH 18,410.39 45,769.30 92,271.26 39,112.74 195,563.69

407i PILE LOAD TEST UP TO 240 TON EACH 33,575.21 45,769.30 184,542.52 65,971.76 329,858.79

407j PILE LOAD TEST UP TO 360 TON EACH 48,740.03 50,188.38 276,813.78 93,935.55 469,677.74

407k CONFIRMATORY BORING (NX SIZE) M 179.28 1,582.02 6.37 441.92 2,209.59

410 BRICK WORK CM 314.26 282.72 3,081.68 919.66 4,598.32

411a STONE MASONRY RANDOM DRY CM 266.98 107.96 488.09 215.76 1,078.79

411b STONE MASONRY RANDOM WITH MORTAR CM 289.95 166.68 1,599.02 513.91 2,569.56

411c STONE MASONRY DRESSED UNCOURSED DRY CM 346.63 107.96 544.22 249.70 1,248.51

411d STONE MASONRY DRESSED UNCOURSED WITH MORTAR CM 409.43 166.68 1,645.04 555.29 2,776.44

Page 20
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Bannu
Bannu District Code: 06

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

411g ROLL POINTING SM 67.49 11.74 45.16 31.10 155.50

412a STONE MASONRY DRESSED COURSED WITH MORTAR CM 545.76 264.08 1,550.23 590.02 2,950.10

501a R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 310 mm M 192.60 437.48 646.04 319.03 1,595.15

501b R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 380 mm M 186.03 577.19 837.34 400.14 2,000.69

501c R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 460 mm M 188.33 935.96 1,073.55 549.46 2,747.30

501d R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 610 mm M 194.19 1,146.39 1,602.55 735.78 3,678.91

501e R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 760 mm M 222.93 1,078.41 2,302.19 900.88 4,504.42

501f R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 910 mm M 277.58 1,331.30 3,620.79 1,307.42 6,537.09

501g R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1070 mm M 359.23 1,481.41 4,686.72 1,631.84 8,159.19

501h R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1220 mm M 419.79 1,798.85 5,972.23 2,047.72 10,238.59

501i R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1520 mm M 499.25 2,098.66 9,222.77 2,955.17 14,775.85

501j R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 310 mm M 192.60 507.33 727.39 356.83 1,784.15

501k R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 380 mm M 186.03 577.19 856.16 404.84 2,024.22

501l R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 460 mm M 182.54 935.96 1,048.13 541.66 2,708.29

501m R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 610 mm M 194.19 1,146.39 1,747.05 771.91 3,859.53

501n R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 760 mm M 222.93 1,078.41 3,320.84 1,155.55 5,777.73

501o R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 910 mm M 277.58 1,331.30 4,878.10 1,621.75 8,108.73

501p R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1070 mm M 359.23 1,481.41 6,815.15 2,163.94 10,819.72

501q R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1220 mm M 419.79 1,798.85 9,242.51 2,865.29 14,326.44

501r R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1520 mm M 499.25 2,098.66 13,001.63 3,899.89 19,499.43

502a GRANULAR MATERIAL IN BED TO CONCRETE PIPE CM 78.15 118.93 315.27 128.09 640.43
CULVERT

502b CONCRETE CLASS "B" IN BEDDING AND ENCASEMENT OF CM 704.80 612.95 3,689.12 1,251.72 6,258.59
CONCRETE PIPE CULVERT

507a STEEL WIRE MESH FOR GABIONS KG 4.48 - 109.44 28.48 142.41

507b ROCK FILL IN GABIONS CM 80.62 - 317.63 99.56 497.80

508a BRICK PAVING (SINGLE COURSE) SM 100.44 32.70 239.43 93.14 465.72

508b BRICK PAVING (DOUBLE COURSE) SM 180.10 32.70 476.03 172.21 861.03

509a RIP RAP CLASS "A" CM 442.33 - 393.29 208.90 1,044.52

509b RIP RAP CLASS "B" CM 424.32 - 390.14 203.62 1,018.08

509c RIP RAP CLASS "C" CM 427.64 - 393.29 205.23 1,026.16

Page 21
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Bannu
Bannu District Code: 06

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

509d GROUTED RIP RAP CLASS "A" CM 537.79 102.14 1,839.13 619.77 3,098.83

509e GROUTED RIP RAP CLASS "B" CM 519.08 81.72 1,685.80 571.65 2,858.23

509f GROUTED RIP RAP CLASS "C" CM 512.22 68.10 1,732.48 578.20 2,891.00

509g REINFORCED CONCRETE SLOPE PROTECTION (WITHOUT CM 730.30 353.02 4,247.16 1,332.62 6,663.10
REINFORCEMENT)

509h FILTER LAYER OF GRANULAR MATERIAL CM 40.28 191.97 341.03 143.32 716.61

510 DISMANTLING OF STRUCTURE AND OBSTRUCTIONS CM 98.99 390.69 - 122.42 612.10

511a1 DRY STONE PITCHING (15-20 cm Thick) SM 139.51 67.48 63.91 67.72 338.62

511a2 DRY STONE PITCHING (21-25 cm Thick) SM 178.58 86.37 81.80 86.69 433.44

511b1 GROUTED STONE PITCHING (15-20 cm Thick) SM 228.82 180.32 374.93 196.02 980.10

511b2 GROUTED STONE PITCHING (21-25 cm Thick) SM 286.03 225.40 468.67 245.02 1,225.12

601ai CONCRETE KERB IN PLACE NEW JERSY BARRIER FOR M 253.36 572.25 2,250.81 769.10 3,845.52
MEDIAN (DOUBLE FACE)

601di PRECAST REINFORCED CONCRETE KERB NEW JERSY M 849.29 670.54 4,131.20 1,412.76 7,063.79
BARRIER FOR MEDIAN (DOUBLE FACE)

601dii PRECAST KERB IN CONCRETE CLASS A-1 OF SIZE 450 X 150 MM M 123.93 90.27 438.18 163.09 815.47
INCLUDING CONCRETE BEDDING & HAUNCHING

603 BRICK EDGING M 8.02 - 38.40 11.61 58.03

604a METAL GUARD RAIL M 18.07 70.84 1,579.36 417.07 2,085.34

604b METAL GUARD RAIL END PIECES EACH 24.03 - 1,197.58 305.40 1,527.00

604d STEEL POST OF METAL GUARD RAIL EACH 85.29 976.73 3,776.31 1,209.58 6,047.91

605a CONCRETE BEAM GUARD RAIL M 62.31 30.82 600.21 173.33 866.67

605c CONCRETE POST FOR GUARD RAIL M 76.51 27.36 601.41 176.32 881.60

607a TRAFFIC ROAD SIGN CATEGORY 1 EACH 200.61 255.15 6,867.38 1,830.79 9,153.93

607b TRAFFIC ROAD SIGN CATEGORY 2 EACH 67.97 382.72 9,280.50 2,432.80 12,163.99

607c TRAFFIC ROAD SIGN CATEGORY 3 (a) EACH 200.61 541.89 11,926.37 3,167.22 15,836.08

607d TRAFFIC ROAD SIGN CATEGORY 3 (b) EACH 618.00 598.64 21,016.48 5,558.28 27,791.41

607e TRAFFIC ROAD SIGN CATEGORY 3 (c) SM 123.60 119.73 9,225.18 2,367.13 11,835.64

607f ADDITIONAL PANEL SIZE 60 X 30 cm EACH 250.16 - 1,303.98 388.53 1,942.67

607g ADDITIONAL PANEL SIZE 90 X 30 cm EACH 250.16 - 1,955.96 551.53 2,757.65

608b1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.54 5.86 16.17 6.14 30.71
LINES OF 15 cm WIDTH

608b2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.85 4.03 39.77 11.16 55.81
LINES OF 15 cm WIDTH

608c1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.54 5.86 21.58 7.49 37.47
LINES OF 20 cm WIDTH

Page 22
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Bannu
Bannu District Code: 06

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

608c2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.85 4.03 53.05 14.48 72.40
LINES OF 20 cm WIDTH

608d1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 59.69 5.22 156.28 55.30 276.48
4.0 M ARROWS

608d2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR 4.0 EACH 59.69 9.98 501.20 142.72 713.60
M ARROWS

608h1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.17 8.59 22.49 8.56 42.81
OF 15 cm WIDTH

608h2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.17 9.63 67.50 20.08 100.39
OF 15 cm WIDTH

608i1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.17 6.95 29.99 10.03 50.14
OF 20 cm WIDTH

608i2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.17 9.63 90.01 25.70 128.51
OF 20 cm WIDTH

608j1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR 4.0 M EACH 59.69 3.73 217.14 70.14 350.69
ARROWS

608j2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR 4.0 M EACH 59.69 7.90 851.20 229.70 1,148.49
ARROWS

608n1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 50.50 3.73 104.19 39.60 198.02
STOP

608n2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR EACH 50.50 7.90 334.64 98.26 491.30
STOP

608n3 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR STOP EACH 50.50 3.73 144.76 49.75 248.73

608n4 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR STOP EACH 50.50 7.90 568.32 156.68 783.40

609c REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 9.51 81.62 193.91 71.26 356.30
SINGLE)

609d REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 9.51 81.62 233.91 81.26 406.29
DOUBLE)

610b RIGHT OF WAY MARKER EACH 86.18 121.33 304.13 127.91 639.55

610c KILOMETRE POST (0.610 X 0.114 X 1.5 M) EACH 525.23 976.31 2,056.66 889.55 4,447.75

610d TEN KILOMETRE POST EACH 989.20 1,952.61 4,506.63 1,862.11 9,310.54

611a CHAIN LINK WIRE FABRIC FENCING 1500 MM HEIGHT M 122.66 91.00 957.79 292.86 1,464.32
WITH PRECAST PRESTRESSED R.C.C. POST

Page 23
.

Page 24
NATIONAL HIGHWAY AUTHORITY

COMPOSITE SCHEDULE OF RATES


January - 2009

BUNEER
(07-A)

Shabir Associates
Quantity Surveying & Construction Cost Consultants

Page 25
.

Page 26
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Buneer
Buneer District Code: 7-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

101 CLEARING AND GRUBBING SM 0.64 11.11 - 2.94 14.69

102a REMOVAL OF TREES 150 - 300 mm GIRTH EACH 6.87 190.65 1.28 49.70 248.50

102b REMOVAL OF TREES 301 - 600 mm GIRTH EACH 18.92 502.19 2.89 131.00 655.00

102c REMOVAL OF TREES 601 mm OR OVER GIRTH EACH 75.67 2,008.78 11.56 524.00 2,620.01

103 STRIPPING CM 2.54 102.54 - 26.27 131.35

104 COMPACTION OF NATURAL GROUND SM 0.37 10.90 0.84 3.03 15.13

106a EXCAVATE UNSUITABLE COMMON MATERIAL CM 5.18 149.33 - 38.63 193.15

106bi EXCAVATE UNSUITABLE HARD ROCK MATERIAL CM 129.72 347.93 55.90 133.39 666.94

106bii EXCAVATE UNSUITABLE MEDIUM ROCK MATERIAL CM 17.06 371.79 - 97.21 486.07

106biii EXCAVATE UNSUITABLE SOFT ROCK MATERIAL CM 11.25 288.63 - 74.97 374.86

106c EXCAVATE SURPLUS COMMON MATERIAL CM 4.24 132.30 - 34.13 170.67

106di EXCAVATE SURPLUS HARD ROCK MATERIAL CM 129.72 347.93 55.90 133.39 666.94

106dii EXCAVATE SURPLUS MEDIUM ROCK MATERIAL CM 20.64 347.63 - 92.07 460.34

106diii EXCAVATE SURPLUS SOFT ROCK MATERIAL CM 8.71 290.32 - 74.76 373.78

107a STRUCTURAL EXCAVATION IN COMMON MATERIAL CM 8.16 151.36 0.42 39.99 199.93

107b STRUCTURAL EXCAVATION IN COMMON MATERIAL BELOW CM 63.16 315.83 77.89 114.22 571.09
WATER LEVEL

107ci STRUCTURAL EXCAVATION IN HARD ROCK MATERIAL CM 114.67 469.72 37.27 155.41 777.06

107cii STRUCTURAL EXCAVATION IN MEDIUM ROCK MATERIAL CM 95.97 321.79 - 104.44 522.20

107ciii STRUCTURAL EXCAVATION IN SOFT ROCK MATERIAL CM 58.97 262.75 - 80.43 402.15

107d GRANULAR BACK FILL CM 32.46 150.85 374.89 139.55 697.76

107e COMMON BACK FILL CM 21.83 69.12 5.60 24.14 120.69

108a FORMATION OF EMBANKMENT FROM ROADWAY CM 7.14 192.18 5.60 51.23 256.15
EXCAVATION IN COMMON MATERIAL

108bi FORMATION OF EMBANKMENT FROM ROADWAY CM 20.09 530.73 59.45 152.57 762.83
EXCAVATION IN HARD ROCK MATERIAL

108bii FORMATION OF EMBANKMENT FROM ROADWAY CM 15.07 458.38 2.66 119.03 595.14
EXCAVATION IN MEDIUM ROCK MATERIAL

108biii FORMATION OF EMBANKMENT FROM ROADWAY CM 13.39 406.28 - 104.92 524.59


EXCAVATION IN SOFT ROCK MATERIAL

108c FORMATION OF EMBANKMENT FROM BORROW CM 7.91 195.20 8.73 52.96 264.81
EXCAVATION IN COMMON MATERIAL

108d FORMATION OF EMBANKMENT FROM STRUCTURAL CM 6.42 83.95 5.60 23.99 119.96
EXCAVATION IN COMMON MATERIAL

108e FORMATION OF EMBANKMENT FROM STRUCTURAL CM 14.25 121.32 3.33 34.72 173.62
EXCAVATION IN ANY TYPE OF ROCK MATERIAL

109a SUB GRADE PREPARATION IN EARTH CUT SM 1.43 30.07 1.60 8.27 41.37

Page 27
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Buneer
Buneer District Code: 7-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

109bi SUB GRADE PREPARATION IN EXISTING ROAD WITHOUT SM 1.06 20.03 0.85 5.49 27.43
ANY FILL

110 IMPROVED SUB-GRADE CM 10.12 132.02 61.15 50.82 254.12

114a DRESSING OF BERM WITHOUT EXTRA MATERIAL SM 0.86 16.79 0.87 4.63 23.15

114b DRESSING OF BERM WITH EXTRA BORROW MATERIAL SM 1.29 17.13 0.99 4.85 24.25

201 GRANULAR SUB-BASE CM 7.84 272.91 488.65 192.35 961.76

202 AGGREGATE BASE CM 9.52 349.40 738.27 274.30 1,371.48

203a ASPHALTIC BASE COURSE PLANT MIX (CLASS "A") CM 62.56 1,615.88 6,223.24 1,975.42 9,877.10

203b ASPHALTIC BASE COURSE PLANT MIX (CLASS "B") CM 65.08 1,615.88 6,685.49 2,091.61 10,458.07

203c ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "A") CM 69.89 1,687.69 6,212.77 1,992.59 9,962.95

203d ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "B") CM 69.89 1,681.30 6,840.53 2,147.93 10,739.65

204b CEMENT STABILIZED BASE CM 28.22 608.94 954.96 398.03 1,990.14

204d LIQUID ASPHALT FOR CURING SEAL, TYPE MC-250 TON 237.22 979.45 55,307.88 14,131.14 70,655.69

204e EMULSIFIED ASPHALT FOR CURING SEAL, TYPE SS-1 TON 237.22 979.45 53,619.29 13,708.99 68,544.95

205a GRADED CRUSHED AGGREGATE CRACK-RELIEF LAYER CM 77.06 120.69 963.10 290.21 1,451.06

205b ASPHALTIC OPEN-GRADED PLANT MIX CRACK-RELIEF CM 134.71 2,608.60 5,956.16 2,174.87 10,874.33
LAYER

206b WATER BOUND MACADAM BASE WITH COARSE CM 83.51 135.11 788.03 251.66 1,258.31
AGGREGATE CLASS B

207a DEEP PATCHING (0-15 cm) SM 1.76 48.19 1.34 12.82 64.11

207b DEEP PATCHING (16-30 cm) SM 1.76 42.45 1.34 11.39 56.94

208 REINSTATEMENT OF ROAD SURFACE SM 1.89 61.10 0.60 15.90 79.49

209a BREAKING OF EXISTING ROAD PAVEMENT STRUCTURE CM 2.33 118.35 0.73 30.35 151.77

209b SCARIFICATION OF EXISTING ROAD PAVEMENT SM 0.47 23.67 0.15 6.07 30.35

302a CUT-BACK ASPHALT FOR BITUMINOUS PRIME COAT SM 0.29 1.68 39.25 10.31 51.54

302b EMULSIFIED ASPHALT FOR BITUMINOUS PRIME COAT SM 0.28 1.68 43.82 11.45 57.23

303a CUT-BACK ASPHALT FOR BITUMINOUS TACK COAT SM 0.12 0.62 16.43 4.29 21.46

303b EMULSIFIED ASPHALT FOR BITUMINOUS TACK COAT SM 0.12 0.62 19.17 4.98 24.88

304a SINGLE SURFACE TREATMENT SM 0.77 8.10 77.73 21.65 108.25

304b DOUBLE SURFACE TREATMENT SM 1.12 15.14 150.57 41.71 208.55

304c TRIPLE SURFACE TREATMENT SM 1.91 21.33 171.70 48.74 243.68

304d SEAL COAT SM 0.71 4.41 54.77 14.97 74.87

Page 28
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Buneer
Buneer District Code: 7-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

305a ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 60.48 1,593.58 7,318.59 2,243.16 11,215.81
"A")

305b ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 60.48 1,538.91 7,892.89 2,373.07 11,865.34
"B")

307a DENSE GRADED HOT BIT-MAC CM 147.67 406.36 6,023.18 1,644.30 8,221.51

307b OPEN GRADED HOT BIT-MAC CM 147.67 406.36 5,886.71 1,610.18 8,050.92

308a RECYCLING OF ASPHALT CONCRETE (0 - 60 mm THICK) CM 27.01 631.99 2,179.20 709.55 3,547.75

308b BITUMEN BINDER GRADE (40 - 50, 60 - 70, 80 - 100) TON 24.99 696.25 46,789.90 11,877.79 59,388.93

309a COLD MILLING, 0 - 30 mm SM 0.96 26.74 9.28 9.25 46.23

309b COLD MILLING, 0 - 50 mm SM 1.60 44.57 15.47 15.41 77.05

309c COLD MILLING, 0 - 70 mm SM 2.40 66.86 23.21 23.11 115.57

401a1i CONCRETE CLASS "A1" (Underground) CM 519.72 1,112.93 4,079.84 1,428.12 7,140.61

401a1ii CONCRETE CLASS "A1" (On ground) CM 519.72 1,112.93 4,371.18 1,500.96 7,504.79

401a1iii CONCRETE CLASS "A1" (Elevated) CM 519.72 1,112.93 4,953.87 1,646.63 8,233.16

401a2i CONCRETE CLASS "A2" (Underground) CM 519.72 1,112.93 4,476.74 1,527.35 7,636.73

401a2ii CONCRETE CLASS "A2" (On ground) CM 519.72 1,112.93 4,768.08 1,600.18 8,000.92

401a2iii CONCRETE CLASS "A2" (Elevated) CM 519.72 1,112.93 5,350.77 1,745.86 8,729.28

401a3i CONCRETE CLASS "A3" (Underground) CM 519.72 1,112.93 4,873.64 1,626.57 8,132.86

401a3ii CONCRETE CLASS "A3" (On ground) CM 519.72 1,112.93 5,164.98 1,699.41 8,497.04

401a3iii CONCRETE CLASS "A3" (Elevated) CM 519.72 1,112.93 5,747.67 1,845.08 9,225.41

401b CONCRETE CLASS "B" CM 654.91 846.23 3,331.64 1,208.19 6,040.97

401ci CONCRETE CLASS "C" (Underground) CM 498.50 525.57 3,638.41 1,165.62 5,828.11

401cii CONCRETE CLASS "C" (On ground) CM 498.50 525.57 3,762.67 1,196.69 5,983.43

401ciii CONCRETE CLASS "C" (Elevated) CM 498.50 525.57 4,011.19 1,258.82 6,294.08

401d CONCRETE CLASS "D1" CM 806.92 1,328.84 5,500.04 1,908.95 9,544.75

401e CONCRETE CLASS "Y" CM 1,091.81 525.57 4,891.71 1,627.27 8,136.37

401f LEAN CONCRETE CM 393.74 532.89 2,565.36 873.00 4,364.99

401gi(1) PRECAST CONCRETE CLASS "A-1" CM 1,626.16 994.51 5,120.44 1,935.28 9,676.38

401gi(3) PRECAST CONCRETE CLASS "A-3" CM 1,626.16 994.51 5,914.24 2,133.73 10,668.63

401gii PRECAST CONCRETE CLASS "B" CM 1,626.16 994.51 4,933.12 1,888.45 9,442.24

401giii(1) PRECAST CONCRETE CLASS "D1" CM 1,626.16 994.51 6,311.14 2,232.95 11,164.75

Page 29
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Buneer
Buneer District Code: 7-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

401giii(2) PRECAST CONCRETE CLASS "D2" CM 1,626.16 994.51 6,708.04 2,332.18 11,660.88

401giii(3) PRECAST CONCRETE CLASS "D3" CM 1,626.16 994.51 7,104.94 2,431.40 12,157.00

404a REINFORCEMENT AS PER AASHTO M. 31 GRADE 40 TON 1,603.90 820.55 63,772.80 16,549.31 82,746.56

404b REINFORCEMENT AS PER AASHTO M. 31 GRADE 60 TON 1,603.90 820.55 71,490.30 18,478.69 92,393.44

404h REINFORCEMENT (STRUCTURAL SHAPES) AS PER ASTM-A- TON 1,275.65 5,663.50 59,328.57 16,566.93 82,834.66
36

405a PRE-STRESSING WIRE STRAND 3/8" - 1/2" DIA COMPLETE IN TON 2,724.95 16,442.00 140,581.54 39,937.12 199,685.61
ALL RESPECT

405b LAUNCHING OF GIRDER TON 63.87 559.15 - 155.75 778.77

406a PREMOULDED JOINT FILLER 12 mm THICK WITH SM 108.38 - 319.92 107.08 535.38
BITUMASTIC JOINT SEAL

406b NEOPRENE RUBBER JOINT FILLER 12 mm THICK WITH SM 108.38 - 318.85 106.81 534.04
BITUMASTIC JOINT SEAL

406c STEEL EXPANSION JOINTS KG 8.91 27.72 95.96 33.15 165.74

406d WATER STOPS 6" SIZE M 99.50 - 496.64 149.03 745.17

406e ELASTOMERIC BEARING PADS (ACCORDING TO SIZE AND ccm 0.02 - 2.23 0.56 2.80
THICKNESS)

406f ASPHALT FELT (3 PLY) SM 39.41 - 3,189.00 807.10 4,035.52

406g STEEL OR METAL BEARING DEVICES KG 17.86 73.17 124.08 53.78 268.88

407d1 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 352.77 1,736.74 945.27 758.70 3,793.48
(BORING ONLY) IN NORMAL SOIL

407d2 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 529.16 2,605.12 1,417.90 1,138.05 5,690.23
(BORING ONLY) IN GRAVEL STRATA

407d3 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 529.16 2,605.12 1,048.29 1,045.64 5,228.21
ONLY) IN NORMAL SOIL

407d4 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 881.93 4,341.86 1,234.71 1,614.63 8,073.13
ONLY) IN GRAVEL STRATA

407d5 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 755.94 5,129.19 1,424.35 1,827.37 9,136.85
ONLY) IN NORMAL SOIL

407d6 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 1,322.90 7,255.27 1,563.82 2,535.50 12,677.49
ONLY) IN GRAVEL SOIL

407h PILE LOAD TEST UP TO 120 TON EACH 18,298.32 48,057.77 96,884.82 40,810.23 204,051.14

407i PILE LOAD TEST UP TO 240 TON EACH 33,188.79 48,057.77 193,769.65 68,754.05 343,770.26

407j PILE LOAD TEST UP TO 360 TON EACH 48,079.27 52,697.80 290,654.47 97,857.89 489,289.43

407k CONFIRMATORY BORING (NX SIZE) M 178.98 1,661.12 6.68 461.70 2,308.48

410 BRICK WORK CM 306.69 296.86 3,529.64 1,033.30 5,166.48

411a STONE MASONRY RANDOM DRY CM 262.96 113.36 437.90 203.55 1,017.77

411b STONE MASONRY RANDOM WITH MORTAR CM 285.07 175.02 1,545.15 501.31 2,506.55

411c STONE MASONRY DRESSED UNCOURSED DRY CM 340.28 113.36 497.04 237.67 1,188.35

411d STONE MASONRY DRESSED UNCOURSED WITH MORTAR CM 401.06 175.02 1,608.49 546.14 2,730.70

Page 30
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Buneer
Buneer District Code: 7-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

411g ROLL POINTING SM 65.46 12.33 46.43 31.06 155.28

412a STONE MASONRY DRESSED COURSED WITH MORTAR CM 533.58 277.29 1,508.95 579.95 2,899.77

501a R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 310 mm M 196.68 472.48 695.82 341.25 1,706.23

501b R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 380 mm M 189.59 623.36 902.05 428.75 2,143.74

501c R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 460 mm M 193.44 1,010.84 1,156.77 590.26 2,951.30

501d R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 610 mm M 199.06 1,238.10 1,727.64 791.20 3,956.00

501e R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 760 mm M 229.02 1,164.69 2,483.25 969.24 4,846.21

501f R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 910 mm M 285.50 1,437.80 3,905.96 1,407.32 7,036.58

501g R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1070 mm M 369.48 1,599.92 5,057.17 1,756.64 8,783.22

501h R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1220 mm M 432.40 1,942.76 6,444.57 2,204.93 11,024.67

501i R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1520 mm M 513.68 2,266.55 9,954.24 3,183.62 15,918.09

501j R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 310 mm M 196.68 547.92 781.77 381.59 1,907.97

501k R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 380 mm M 189.59 623.36 922.37 433.83 2,169.15

501l R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 460 mm M 187.59 1,010.84 1,129.32 581.94 2,909.68

501m R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 610 mm M 199.06 1,238.10 1,884.39 830.39 4,151.94

501n R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 760 mm M 229.02 1,164.69 3,583.05 1,244.19 6,220.95

501o R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 910 mm M 285.50 1,437.80 5,263.85 1,746.79 8,733.95

501p R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1070 mm M 369.48 1,599.92 7,355.88 2,331.32 11,656.60

501q R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1220 mm M 432.40 1,942.76 9,976.47 3,087.91 15,439.54

501r R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1520 mm M 513.68 2,266.55 14,035.41 4,203.91 21,019.56

502a GRANULAR MATERIAL IN BED TO CONCRETE PIPE CM 80.98 128.44 340.49 137.48 687.39
CULVERT

502b CONCRETE CLASS "B" IN BEDDING AND ENCASEMENT OF CM 773.04 661.98 3,804.83 1,309.96 6,549.82
CONCRETE PIPE CULVERT

507a STEEL WIRE MESH FOR GABIONS KG 5.10 - 120.81 31.48 157.38

507b ROCK FILL IN GABIONS CM 82.86 - 398.48 120.33 601.67

508a BRICK PAVING (SINGLE COURSE) SM 101.23 35.32 298.25 108.70 543.50

508b BRICK PAVING (DOUBLE COURSE) SM 180.76 35.32 593.44 202.38 1,011.89

509a RIP RAP CLASS "A" CM 444.83 - 348.02 198.21 991.06

509b RIP RAP CLASS "B" CM 426.29 - 345.23 192.88 964.41

509c RIP RAP CLASS "C" CM 429.10 - 348.02 194.28 971.40

Page 31
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Buneer
Buneer District Code: 7-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

509d GROUTED RIP RAP CLASS "A" CM 540.84 110.32 1,871.46 630.65 3,153.27

509e GROUTED RIP RAP CLASS "B" CM 521.30 88.25 1,710.43 580.00 2,899.99

509f GROUTED RIP RAP CLASS "C" CM 513.95 73.54 1,758.82 586.58 2,932.89

509g REINFORCED CONCRETE SLOPE PROTECTION (WITHOUT CM 750.93 381.27 4,416.66 1,387.21 6,936.07
REINFORCEMENT)

509h FILTER LAYER OF GRANULAR MATERIAL CM 41.47 207.33 368.32 154.28 771.40

510 DISMANTLING OF STRUCTURE AND OBSTRUCTIONS CM 101.82 421.95 - 130.94 654.71

511a1 DRY STONE PITCHING (15-20 cm Thick) SM 141.31 72.87 56.55 67.68 338.42

511a2 DRY STONE PITCHING (21-25 cm Thick) SM 180.88 93.28 72.39 86.64 433.18

511b1 GROUTED STONE PITCHING (15-20 cm Thick) SM 230.89 194.75 377.32 200.74 1,003.70

511b2 GROUTED STONE PITCHING (21-25 cm Thick) SM 288.61 243.44 471.66 250.93 1,254.63

601ai CONCRETE KERB IN PLACE NEW JERSY BARRIER FOR M 280.93 613.92 2,333.98 807.21 4,036.03
MEDIAN (DOUBLE FACE)

601di PRECAST REINFORCED CONCRETE KERB NEW JERSY M 912.38 711.97 4,321.15 1,486.37 7,431.87
BARRIER FOR MEDIAN (DOUBLE FACE)

601dii PRECAST KERB IN CONCRETE CLASS A-1 OF SIZE 450 X 150 MM M 132.05 97.09 452.55 170.42 852.11
INCLUDING CONCRETE BEDDING & HAUNCHING

603 BRICK EDGING M 7.72 - 45.53 13.31 66.57

604a METAL GUARD RAIL M 17.83 72.26 1,610.95 425.26 2,126.29

604b METAL GUARD RAIL END PIECES EACH 23.35 - 1,221.53 311.22 1,556.10

604d STEEL POST OF METAL GUARD RAIL EACH 84.69 996.27 3,851.83 1,233.20 6,165.99

605a CONCRETE BEAM GUARD RAIL M 62.15 31.44 603.55 174.29 871.43

605c CONCRETE POST FOR GUARD RAIL M 76.31 27.91 603.31 176.88 884.41

607a TRAFFIC ROAD SIGN CATEGORY 1 EACH 200.77 260.25 6,990.19 1,862.80 9,314.02

607b TRAFFIC ROAD SIGN CATEGORY 2 EACH 65.01 390.38 9,432.97 2,472.09 12,360.45

607c TRAFFIC ROAD SIGN CATEGORY 3 (a) EACH 200.77 552.72 12,108.52 3,215.50 16,077.52

607d TRAFFIC ROAD SIGN CATEGORY 3 (b) EACH 613.45 610.62 21,352.47 5,644.13 28,220.67

607e TRAFFIC ROAD SIGN CATEGORY 3 (c) SM 122.69 122.12 9,391.72 2,409.13 12,045.67

607f ADDITIONAL PANEL SIZE 60 X 30 cm EACH 271.91 - 1,329.94 400.46 2,002.31

607g ADDITIONAL PANEL SIZE 90 X 30 cm EACH 271.91 - 1,994.91 566.71 2,833.53

608b1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.50 5.98 16.49 6.24 31.20
LINES OF 15 cm WIDTH

608b2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.83 4.11 40.51 11.36 56.81
LINES OF 15 cm WIDTH

608c1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.50 5.98 22.00 7.62 38.10
LINES OF 20 cm WIDTH

Page 32
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Buneer
Buneer District Code: 7-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

608c2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.83 4.11 54.03 14.74 73.71
LINES OF 20 cm WIDTH

608d1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 70.14 5.32 159.35 58.70 293.50
4.0 M ARROWS

608d2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR 4.0 EACH 70.14 10.18 510.48 147.70 738.50
M ARROWS

608h1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.12 8.76 22.93 8.70 43.52
OF 15 cm WIDTH

608h2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.12 9.82 68.85 20.45 102.25
OF 15 cm WIDTH

608i1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.12 7.09 30.58 10.20 50.98
OF 20 cm WIDTH

608i2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.12 9.82 91.81 26.19 130.94
OF 20 cm WIDTH

608j1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR 4.0 M EACH 70.14 3.80 221.42 73.84 369.20
ARROWS

608j2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR 4.0 M EACH 70.14 8.06 868.22 236.60 1,183.02
ARROWS

608n1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 58.42 3.80 106.23 42.11 210.56
STOP

608n2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR EACH 58.42 8.06 340.84 101.83 509.14
STOP

608n3 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR STOP EACH 58.42 3.80 147.61 52.46 262.29

608n4 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR STOP EACH 58.42 8.06 579.69 161.54 807.71

609c REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 9.17 83.25 197.71 72.53 362.66
SINGLE)

609d REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 9.17 83.25 238.51 82.73 413.67
DOUBLE)

610b RIGHT OF WAY MARKER EACH 84.33 123.75 303.75 127.96 639.79

610c KILOMETRE POST (0.610 X 0.114 X 1.5 M) EACH 537.79 995.83 2,040.17 893.45 4,467.24

610d TEN KILOMETRE POST EACH 1,028.70 1,991.66 4,484.05 1,876.10 9,380.52

611a CHAIN LINK WIRE FABRIC FENCING 1500 MM HEIGHT M 123.92 95.67 983.15 300.68 1,503.42
WITH PRECAST PRESTRESSED R.C.C. POST

Page 33
.

Page 34
NATIONAL HIGHWAY AUTHORITY

COMPOSITE SCHEDULE OF RATES


January - 2009

BUTTGRAM
(07-B)

Shabir Associates
Quantity Surveying & Construction Cost Consultants

Page 35
.

Page 36
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Buttgram
Buttgram District Code: 7-B

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

101 CLEARING AND GRUBBING SM 0.79 11.11 - 2.98 14.88

102a REMOVAL OF TREES 150 - 300 mm GIRTH EACH 8.32 190.65 1.28 50.06 250.32

102b REMOVAL OF TREES 301 - 600 mm GIRTH EACH 23.27 502.19 2.89 132.09 660.44

102c REMOVAL OF TREES 601 mm OR OVER GIRTH EACH 93.09 2,008.78 11.56 528.36 2,641.78

103 STRIPPING CM 2.85 102.54 - 26.35 131.74

104 COMPACTION OF NATURAL GROUND SM 0.42 10.90 0.84 3.04 15.19

106a EXCAVATE UNSUITABLE COMMON MATERIAL CM 6.01 149.33 - 38.84 194.18

106bi EXCAVATE UNSUITABLE HARD ROCK MATERIAL CM 161.10 347.93 55.90 141.23 706.16

106bii EXCAVATE UNSUITABLE MEDIUM ROCK MATERIAL CM 21.39 371.79 - 98.30 491.48

106biii EXCAVATE UNSUITABLE SOFT ROCK MATERIAL CM 14.09 288.63 - 75.68 378.40

106c EXCAVATE SURPLUS COMMON MATERIAL CM 4.92 132.30 - 34.30 171.52

106di EXCAVATE SURPLUS HARD ROCK MATERIAL CM 161.10 347.93 55.90 141.23 706.16

106dii EXCAVATE SURPLUS MEDIUM ROCK MATERIAL CM 25.82 347.63 - 93.36 466.82

106diii EXCAVATE SURPLUS SOFT ROCK MATERIAL CM 10.82 290.32 - 75.28 376.42

107a STRUCTURAL EXCAVATION IN COMMON MATERIAL CM 9.12 151.36 0.42 40.23 201.13

107b STRUCTURAL EXCAVATION IN COMMON MATERIAL BELOW CM 71.46 315.83 77.89 116.29 581.46
WATER LEVEL

107ci STRUCTURAL EXCAVATION IN HARD ROCK MATERIAL CM 143.47 469.72 37.27 162.61 813.07

107cii STRUCTURAL EXCAVATION IN MEDIUM ROCK MATERIAL CM 121.06 321.79 - 110.71 553.56

107ciii STRUCTURAL EXCAVATION IN SOFT ROCK MATERIAL CM 73.78 262.75 - 84.13 420.67

107d GRANULAR BACK FILL CM 40.90 150.85 497.93 172.42 862.10

107e COMMON BACK FILL CM 27.39 69.12 5.60 25.53 127.63

108a FORMATION OF EMBANKMENT FROM ROADWAY CM 8.59 192.18 5.60 51.59 257.97
EXCAVATION IN COMMON MATERIAL

108bi FORMATION OF EMBANKMENT FROM ROADWAY CM 24.45 530.73 59.45 153.66 768.28
EXCAVATION IN HARD ROCK MATERIAL

108bii FORMATION OF EMBANKMENT FROM ROADWAY CM 18.34 458.38 2.66 119.85 599.23
EXCAVATION IN MEDIUM ROCK MATERIAL

108biii FORMATION OF EMBANKMENT FROM ROADWAY CM 16.30 406.28 - 105.64 528.22


EXCAVATION IN SOFT ROCK MATERIAL

108c FORMATION OF EMBANKMENT FROM BORROW CM 9.61 195.20 8.73 53.39 266.93
EXCAVATION IN COMMON MATERIAL

108d FORMATION OF EMBANKMENT FROM STRUCTURAL CM 7.59 83.95 5.60 24.28 121.42
EXCAVATION IN COMMON MATERIAL

108e FORMATION OF EMBANKMENT FROM STRUCTURAL CM 16.98 121.32 3.33 35.41 177.03
EXCAVATION IN ANY TYPE OF ROCK MATERIAL

109a SUB GRADE PREPARATION IN EARTH CUT SM 1.71 30.07 1.60 8.35 41.73

Page 37
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Buttgram
Buttgram District Code: 7-B

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

109bi SUB GRADE PREPARATION IN EXISTING ROAD WITHOUT SM 1.22 20.03 0.85 5.52 27.62
ANY FILL

110 IMPROVED SUB-GRADE CM 12.08 132.02 61.26 51.34 256.71

114a DRESSING OF BERM WITHOUT EXTRA MATERIAL SM 0.98 16.79 0.87 4.66 23.30

114b DRESSING OF BERM WITH EXTRA BORROW MATERIAL SM 1.46 17.13 0.99 4.89 24.46

201 GRANULAR SUB-BASE CM 9.63 272.91 573.09 213.91 1,069.54

202 AGGREGATE BASE CM 12.03 349.40 860.09 305.38 1,526.91

203a ASPHALTIC BASE COURSE PLANT MIX (CLASS "A") CM 80.37 1,615.88 6,459.09 2,038.83 10,194.17

203b ASPHALTIC BASE COURSE PLANT MIX (CLASS "B") CM 83.88 1,615.88 6,897.41 2,149.29 10,746.46

203c ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "A") CM 89.49 1,687.69 6,448.52 2,056.43 10,282.13

203d ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "B") CM 89.49 1,681.30 7,053.73 2,206.13 11,030.65

204b CEMENT STABILIZED BASE CM 35.80 608.94 1,146.64 447.84 2,239.22

204d LIQUID ASPHALT FOR CURING SEAL, TYPE MC-250 TON 286.50 979.45 56,312.93 14,394.72 71,973.60

204e EMULSIFIED ASPHALT FOR CURING SEAL, TYPE SS-1 TON 286.50 979.45 54,624.34 13,972.57 69,862.86

205a GRADED CRUSHED AGGREGATE CRACK-RELIEF LAYER CM 97.62 120.69 1,004.34 305.66 1,528.32

205b ASPHALTIC OPEN-GRADED PLANT MIX CRACK-RELIEF CM 169.85 2,608.60 6,106.46 2,221.23 11,106.14
LAYER

206b WATER BOUND MACADAM BASE WITH COARSE CM 108.02 135.11 834.88 269.50 1,347.52
AGGREGATE CLASS B

207a DEEP PATCHING (0-15 cm) SM 2.03 48.19 1.34 12.89 64.45

207b DEEP PATCHING (16-30 cm) SM 2.03 42.45 1.34 11.46 57.28

208 REINSTATEMENT OF ROAD SURFACE SM 2.32 61.10 0.60 16.01 80.03

209a BREAKING OF EXISTING ROAD PAVEMENT STRUCTURE CM 2.45 118.35 0.73 30.38 151.92

209b SCARIFICATION OF EXISTING ROAD PAVEMENT SM 0.49 23.67 0.15 6.08 30.38

302a CUT-BACK ASPHALT FOR BITUMINOUS PRIME COAT SM 0.36 1.68 39.97 10.50 52.52

302b EMULSIFIED ASPHALT FOR BITUMINOUS PRIME COAT SM 0.35 1.68 44.61 11.66 58.31

303a CUT-BACK ASPHALT FOR BITUMINOUS TACK COAT SM 0.15 0.62 16.73 4.37 21.87

303b EMULSIFIED ASPHALT FOR BITUMINOUS TACK COAT SM 0.15 0.62 19.51 5.07 25.35

304a SINGLE SURFACE TREATMENT SM 0.97 8.10 79.65 22.18 110.91

304b DOUBLE SURFACE TREATMENT SM 1.41 15.14 154.30 42.71 213.57

304c TRIPLE SURFACE TREATMENT SM 2.38 21.33 176.07 49.95 249.73

304d SEAL COAT SM 0.92 4.41 56.39 15.43 77.15

Page 38
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Buttgram
Buttgram District Code: 7-B

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

305a ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 77.57 1,593.58 7,567.55 2,309.68 11,548.38
"A")

305b ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 77.57 1,538.91 8,169.44 2,446.48 12,232.39
"B")

307a DENSE GRADED HOT BIT-MAC CM 187.95 406.36 6,283.20 1,719.38 8,596.88

307b OPEN GRADED HOT BIT-MAC CM 187.95 406.36 6,094.61 1,672.23 8,361.15

308a RECYCLING OF ASPHALT CONCRETE (0 - 60 mm THICK) CM 32.28 631.99 2,210.92 718.80 3,593.99

308b BITUMEN BINDER GRADE (40 - 50, 60 - 70, 80 - 100) TON 29.72 696.25 47,824.81 12,137.69 60,688.47

309a COLD MILLING, 0 - 30 mm SM 1.18 26.74 9.28 9.30 46.51

309b COLD MILLING, 0 - 50 mm SM 1.97 44.57 15.47 15.50 77.51

309c COLD MILLING, 0 - 70 mm SM 2.95 66.86 23.21 23.25 116.27

401a1i CONCRETE CLASS "A1" (Underground) CM 555.90 1,112.93 4,287.33 1,489.04 7,445.20

401a1ii CONCRETE CLASS "A1" (On ground) CM 555.90 1,112.93 4,578.67 1,561.88 7,809.38

401a1iii CONCRETE CLASS "A1" (Elevated) CM 555.90 1,112.93 5,161.36 1,707.55 8,537.74

401a2i CONCRETE CLASS "A2" (Underground) CM 555.90 1,112.93 4,684.23 1,588.26 7,941.32

401a2ii CONCRETE CLASS "A2" (On ground) CM 555.90 1,112.93 4,975.57 1,661.10 8,305.50

401a2iii CONCRETE CLASS "A2" (Elevated) CM 555.90 1,112.93 5,558.26 1,806.77 9,033.87

401a3i CONCRETE CLASS "A3" (Underground) CM 555.90 1,112.93 5,081.13 1,687.49 8,437.45

401a3ii CONCRETE CLASS "A3" (On ground) CM 555.90 1,112.93 5,372.47 1,760.33 8,801.63

401a3iii CONCRETE CLASS "A3" (Elevated) CM 555.90 1,112.93 5,955.16 1,906.00 9,529.99

401b CONCRETE CLASS "B" CM 744.54 846.23 3,462.82 1,263.40 6,316.98

401ci CONCRETE CLASS "C" (Underground) CM 534.61 525.57 3,815.35 1,218.89 6,094.43

401cii CONCRETE CLASS "C" (On ground) CM 534.61 525.57 3,939.61 1,249.95 6,249.75

401ciii CONCRETE CLASS "C" (Elevated) CM 534.61 525.57 4,188.13 1,312.08 6,560.40

401d CONCRETE CLASS "D1" CM 830.09 1,328.84 5,678.18 1,959.28 9,796.38

401e CONCRETE CLASS "Y" CM 1,134.98 525.57 5,109.73 1,692.57 8,462.85

401f LEAN CONCRETE CM 452.32 532.89 2,696.93 920.54 4,602.68

401gi(1) PRECAST CONCRETE CLASS "A-1" CM 1,798.96 994.51 5,354.15 2,036.90 10,184.52

401gi(3) PRECAST CONCRETE CLASS "A-3" CM 1,798.96 994.51 6,147.95 2,235.35 11,176.77

401gii PRECAST CONCRETE CLASS "B" CM 1,798.96 994.51 5,067.11 1,965.14 9,825.72

401giii(1) PRECAST CONCRETE CLASS "D1" CM 1,798.96 994.51 6,544.85 2,334.58 11,672.89

Page 39
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Buttgram
Buttgram District Code: 7-B

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

401giii(2) PRECAST CONCRETE CLASS "D2" CM 1,798.96 994.51 6,941.75 2,433.80 12,169.02

401giii(3) PRECAST CONCRETE CLASS "D3" CM 1,798.96 994.51 7,338.65 2,533.03 12,665.14

404a REINFORCEMENT AS PER AASHTO M. 31 GRADE 40 TON 1,629.09 820.55 64,412.78 16,715.60 83,578.01

404b REINFORCEMENT AS PER AASHTO M. 31 GRADE 60 TON 1,629.09 820.55 72,130.28 18,644.98 93,224.89

404h REINFORCEMENT (STRUCTURAL SHAPES) AS PER ASTM-A- TON 1,342.11 5,663.50 59,879.17 16,721.20 83,605.98
36

405a PRE-STRESSING WIRE STRAND 3/8" - 1/2" DIA COMPLETE IN TON 3,217.96 16,442.00 140,626.65 40,071.65 200,358.27
ALL RESPECT

405b LAUNCHING OF GIRDER TON 73.74 559.15 - 158.22 791.11

406a PREMOULDED JOINT FILLER 12 mm THICK WITH SM 119.30 - 321.05 110.09 550.44
BITUMASTIC JOINT SEAL

406b NEOPRENE RUBBER JOINT FILLER 12 mm THICK WITH SM 119.30 - 319.98 109.82 549.10
BITUMASTIC JOINT SEAL

406c STEEL EXPANSION JOINTS KG 9.69 27.72 96.51 33.48 167.39

406d WATER STOPS 6" SIZE M 95.44 - 497.51 148.24 741.19

406e ELASTOMERIC BEARING PADS (ACCORDING TO SIZE AND ccm 0.02 - 2.23 0.56 2.81
THICKNESS)

406f ASPHALT FELT (3 PLY) SM 47.11 - 3,159.40 801.63 4,008.14

406g STEEL OR METAL BEARING DEVICES KG 22.84 73.17 124.01 55.00 275.02

407d1 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 386.35 1,736.74 1,042.27 791.34 3,956.71
(BORING ONLY) IN NORMAL SOIL

407d2 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 579.53 2,605.12 1,563.40 1,187.01 5,935.06
(BORING ONLY) IN GRAVEL STRATA

407d3 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 579.53 2,605.12 1,145.90 1,082.64 5,413.18
ONLY) IN NORMAL SOIL

407d4 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 965.88 4,341.86 1,333.34 1,660.27 8,301.34
ONLY) IN GRAVEL STRATA

407d5 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 827.90 5,129.19 1,523.70 1,870.19 9,350.97
ONLY) IN NORMAL SOIL

407d6 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 1,448.82 7,255.27 1,675.73 2,594.95 12,974.76
ONLY) IN GRAVEL SOIL

407h PILE LOAD TEST UP TO 120 TON EACH 23,946.10 48,057.77 108,824.75 45,207.15 226,035.77

407i PILE LOAD TEST UP TO 240 TON EACH 43,488.04 48,057.77 217,649.50 77,298.83 386,494.13

407j PILE LOAD TEST UP TO 360 TON EACH 63,029.97 52,697.80 326,474.25 110,550.51 552,752.54

407k CONFIRMATORY BORING (NX SIZE) M 212.17 1,661.12 6.68 470.00 2,349.98

410 BRICK WORK CM 352.02 296.86 3,094.05 935.73 4,678.66

411a STONE MASONRY RANDOM DRY CM 296.27 113.36 612.69 255.58 1,277.91

411b STONE MASONRY RANDOM WITH MORTAR CM 319.95 175.02 1,798.90 573.47 2,867.33

411c STONE MASONRY DRESSED UNCOURSED DRY CM 387.05 113.36 679.66 295.02 1,475.08

411d STONE MASONRY DRESSED UNCOURSED WITH MORTAR CM 456.11 175.02 1,850.32 620.36 3,101.81

Page 40
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Buttgram
Buttgram District Code: 7-B

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

411g ROLL POINTING SM 74.95 12.33 47.75 33.76 168.79

412a STONE MASONRY DRESSED COURSED WITH MORTAR CM 613.99 277.29 1,750.77 660.51 3,302.57

501a R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 310 mm M 241.34 472.48 698.36 353.05 1,765.23

501b R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 380 mm M 233.43 623.36 905.09 440.47 2,202.35

501c R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 460 mm M 235.72 1,010.84 1,160.32 601.72 3,008.59

501d R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 610 mm M 244.74 1,238.10 1,731.79 803.66 4,018.30

501e R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 760 mm M 285.25 1,164.69 2,487.41 984.34 4,921.68

501f R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 910 mm M 358.75 1,437.80 3,911.95 1,427.13 7,135.63

501g R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1070 mm M 464.26 1,599.92 5,063.15 1,781.83 8,909.16

501h R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1220 mm M 546.35 1,942.76 6,451.82 2,235.23 11,176.17

501i R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1520 mm M 649.33 2,266.55 9,962.70 3,219.65 16,098.23

501j R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 310 mm M 241.34 547.92 786.84 394.03 1,970.14

501k R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 380 mm M 233.43 623.36 925.42 445.55 2,227.76

501l R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 460 mm M 230.69 1,010.84 1,132.87 593.60 2,967.99

501m R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 610 mm M 244.74 1,238.10 1,887.62 842.62 4,213.08

501n R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 760 mm M 285.25 1,164.69 3,587.66 1,259.40 6,297.00

501o R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 910 mm M 358.75 1,437.80 5,269.85 1,766.60 8,833.00

501p R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1070 mm M 464.26 1,599.92 7,361.85 2,356.51 11,782.54

501q R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1220 mm M 546.35 1,942.76 9,983.72 3,118.21 15,591.04

501r R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1520 mm M 649.33 2,266.55 14,043.87 4,239.94 21,199.69

502a GRANULAR MATERIAL IN BED TO CONCRETE PIPE CM 97.83 128.44 473.70 174.99 874.96
CULVERT

502b CONCRETE CLASS "B" IN BEDDING AND ENCASEMENT OF CM 838.70 661.98 3,939.75 1,360.11 6,800.55
CONCRETE PIPE CULVERT

507a STEEL WIRE MESH FOR GABIONS KG 5.99 - 118.20 31.05 155.23

507b ROCK FILL IN GABIONS CM 102.16 - 571.73 168.47 842.36

508a BRICK PAVING (SINGLE COURSE) SM 119.28 35.32 247.26 100.46 502.32

508b BRICK PAVING (DOUBLE COURSE) SM 212.65 35.32 490.06 184.51 922.53

509a RIP RAP CLASS "A" CM 519.54 - 527.81 261.84 1,309.19

509b RIP RAP CLASS "B" CM 499.27 - 523.59 255.71 1,278.57

509c RIP RAP CLASS "C" CM 501.98 - 527.81 257.45 1,287.24

Page 41
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Buttgram
Buttgram District Code: 7-B

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

509d GROUTED RIP RAP CLASS "A" CM 635.20 110.32 2,102.01 711.88 3,559.40

509e GROUTED RIP RAP CLASS "B" CM 611.27 88.25 1,934.26 658.45 3,292.23

509f GROUTED RIP RAP CLASS "C" CM 602.76 73.54 1,985.98 665.57 3,327.86

509g REINFORCED CONCRETE SLOPE PROTECTION (WITHOUT CM 846.94 381.27 4,544.21 1,443.10 7,215.52
REINFORCEMENT)

509h FILTER LAYER OF GRANULAR MATERIAL CM 51.38 207.33 489.54 187.06 935.32

510 DISMANTLING OF STRUCTURE AND OBSTRUCTIONS CM 113.55 421.95 - 133.87 669.37

511a1 DRY STONE PITCHING (15-20 cm Thick) SM 162.85 72.87 85.77 80.37 401.87

511a2 DRY STONE PITCHING (21-25 cm Thick) SM 208.45 93.28 109.78 102.88 514.39

511b1 GROUTED STONE PITCHING (15-20 cm Thick) SM 265.28 194.75 424.50 221.13 1,105.67

511b2 GROUTED STONE PITCHING (21-25 cm Thick) SM 331.60 243.44 530.63 276.42 1,382.08

601ai CONCRETE KERB IN PLACE NEW JERSY BARRIER FOR M 300.75 613.92 2,444.21 839.72 4,198.59
MEDIAN (DOUBLE FACE)

601di PRECAST REINFORCED CONCRETE KERB NEW JERSY M 1,006.80 711.97 4,458.68 1,544.36 7,721.82
BARRIER FOR MEDIAN (DOUBLE FACE)

601dii PRECAST KERB IN CONCRETE CLASS A-1 OF SIZE 450 X 150 MM M 146.78 97.09 473.13 179.25 896.25
INCLUDING CONCRETE BEDDING & HAUNCHING

603 BRICK EDGING M 8.95 - 36.23 11.30 56.48

604a METAL GUARD RAIL M 20.67 72.26 1,610.95 425.97 2,129.85

604b METAL GUARD RAIL END PIECES EACH 25.05 - 1,221.53 311.64 1,558.22

604d STEEL POST OF METAL GUARD RAIL EACH 97.45 996.27 3,851.83 1,236.39 6,181.93

605a CONCRETE BEAM GUARD RAIL M 73.31 31.44 614.71 179.86 899.32

605c CONCRETE POST FOR GUARD RAIL M 90.01 27.91 616.63 183.64 918.18

607a TRAFFIC ROAD SIGN CATEGORY 1 EACH 247.33 260.25 7,005.46 1,878.26 9,391.30

607b TRAFFIC ROAD SIGN CATEGORY 2 EACH 67.04 390.38 9,470.67 2,482.02 12,410.10

607c TRAFFIC ROAD SIGN CATEGORY 3 (a) EACH 247.33 552.72 12,172.27 3,243.08 16,215.41

607d TRAFFIC ROAD SIGN CATEGORY 3 (b) EACH 769.36 610.62 21,458.42 5,709.60 28,548.00

607e TRAFFIC ROAD SIGN CATEGORY 3 (c) SM 153.87 122.12 9,426.66 2,425.67 12,128.33

607f ADDITIONAL PANEL SIZE 60 X 30 cm EACH 301.69 - 1,333.85 408.89 2,044.43

607g ADDITIONAL PANEL SIZE 90 X 30 cm EACH 301.69 - 2,000.78 575.62 2,878.09

608b1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.74 5.98 16.51 6.31 31.53
LINES OF 15 cm WIDTH

608b2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.91 4.11 40.65 11.42 57.10
LINES OF 15 cm WIDTH

608c1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.74 5.98 22.02 7.68 38.42
LINES OF 20 cm WIDTH

Page 42
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Buttgram
Buttgram District Code: 7-B

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

608c2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.91 4.11 54.22 14.81 74.06
LINES OF 20 cm WIDTH

608d1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 72.75 5.32 159.49 59.39 296.95
4.0 M ARROWS

608d2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR 4.0 EACH 72.75 10.18 512.30 148.81 744.05
M ARROWS

608h1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.42 8.76 22.95 8.78 43.91
OF 15 cm WIDTH

608h2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.42 9.82 68.85 20.53 102.63
OF 15 cm WIDTH

608i1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.42 7.09 30.60 10.28 51.39
OF 20 cm WIDTH

608i2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.42 9.82 91.81 26.26 131.32
OF 20 cm WIDTH

608j1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR 4.0 M EACH 72.75 3.80 221.56 74.53 372.64
ARROWS

608j2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR 4.0 M EACH 72.75 8.06 868.22 237.26 1,186.29
ARROWS

608n1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 60.82 3.80 106.32 42.74 213.68
STOP

608n2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR EACH 60.82 8.06 342.05 102.73 513.66
STOP

608n3 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR STOP EACH 60.82 3.80 147.71 53.08 265.41

608n4 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR STOP EACH 60.82 8.06 579.69 162.14 810.70

609c REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 8.74 83.25 197.81 72.45 362.25
SINGLE)

609d REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 8.74 83.25 238.61 82.65 413.25
DOUBLE)

610b RIGHT OF WAY MARKER EACH 101.67 123.75 313.42 134.71 673.55

610c KILOMETRE POST (0.610 X 0.114 X 1.5 M) EACH 626.15 995.83 2,123.30 936.32 4,681.60

610d TEN KILOMETRE POST EACH 1,200.07 1,991.66 4,647.61 1,959.84 9,799.18

611a CHAIN LINK WIRE FABRIC FENCING 1500 MM HEIGHT M 135.90 95.67 992.09 305.92 1,529.59
WITH PRECAST PRESTRESSED R.C.C. POST

Page 43
.

Page 44
NATIONAL HIGHWAY AUTHORITY

COMPOSITE SCHEDULE OF RATES


January - 2009

CHITRAL
(10)

Shabir Associates
Quantity Surveying & Construction Cost Consultants

Page 45
.

Page 46
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Chitral
Chitral District Code: 10

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

101 CLEARING AND GRUBBING SM 0.70 11.31 - 3.00 15.02

102a REMOVAL OF TREES 150 - 300 mm GIRTH EACH 7.36 194.12 1.31 50.70 253.49

102b REMOVAL OF TREES 301 - 600 mm GIRTH EACH 20.54 511.33 2.94 133.70 668.51

102c REMOVAL OF TREES 601 mm OR OVER GIRTH EACH 82.16 2,045.30 11.77 534.81 2,674.04

103 STRIPPING CM 2.68 104.40 - 26.77 133.86

104 COMPACTION OF NATURAL GROUND SM 0.39 11.10 0.86 3.08 15.42

106a EXCAVATE UNSUITABLE COMMON MATERIAL CM 5.30 152.05 - 39.34 196.69

106bi EXCAVATE UNSUITABLE HARD ROCK MATERIAL CM 142.37 354.26 56.92 138.39 691.93

106bii EXCAVATE UNSUITABLE MEDIUM ROCK MATERIAL CM 19.30 378.55 - 99.46 497.32

106biii EXCAVATE UNSUITABLE SOFT ROCK MATERIAL CM 12.83 293.88 - 76.68 383.38

106c EXCAVATE SURPLUS COMMON MATERIAL CM 4.34 134.70 - 34.76 173.80

106di EXCAVATE SURPLUS HARD ROCK MATERIAL CM 142.37 354.26 56.92 138.39 691.93

106dii EXCAVATE SURPLUS MEDIUM ROCK MATERIAL CM 22.68 353.95 - 94.16 470.79

106diii EXCAVATE SURPLUS SOFT ROCK MATERIAL CM 9.84 295.59 - 76.36 381.79

107a STRUCTURAL EXCAVATION IN COMMON MATERIAL CM 8.55 154.11 0.43 40.77 203.86

107b STRUCTURAL EXCAVATION IN COMMON MATERIAL BELOW CM 68.93 321.57 79.30 117.45 587.25
WATER LEVEL

107ci STRUCTURAL EXCAVATION IN HARD ROCK MATERIAL CM 126.00 478.26 37.95 160.55 802.75

107cii STRUCTURAL EXCAVATION IN MEDIUM ROCK MATERIAL CM 106.22 327.64 - 108.46 542.32

107ciii STRUCTURAL EXCAVATION IN SOFT ROCK MATERIAL CM 64.80 267.53 - 83.08 415.41

107d GRANULAR BACK FILL CM 35.48 153.60 415.34 151.10 755.52

107e COMMON BACK FILL CM 24.03 70.38 5.70 25.03 125.14

108a FORMATION OF EMBANKMENT FROM ROADWAY CM 7.87 195.67 5.70 52.31 261.56
EXCAVATION IN COMMON MATERIAL

108bi FORMATION OF EMBANKMENT FROM ROADWAY CM 22.18 540.38 60.53 155.77 778.85
EXCAVATION IN HARD ROCK MATERIAL

108bii FORMATION OF EMBANKMENT FROM ROADWAY CM 16.63 466.72 2.71 121.51 607.57
EXCAVATION IN MEDIUM ROCK MATERIAL

108biii FORMATION OF EMBANKMENT FROM ROADWAY CM 14.78 413.66 - 107.11 535.56


EXCAVATION IN SOFT ROCK MATERIAL

108c FORMATION OF EMBANKMENT FROM BORROW CM 8.75 198.75 8.89 54.10 270.49
EXCAVATION IN COMMON MATERIAL

108d FORMATION OF EMBANKMENT FROM STRUCTURAL CM 7.04 85.47 5.70 24.55 122.77
EXCAVATION IN COMMON MATERIAL

108e FORMATION OF EMBANKMENT FROM STRUCTURAL CM 15.62 123.52 3.39 35.63 178.17
EXCAVATION IN ANY TYPE OF ROCK MATERIAL

109a SUB GRADE PREPARATION IN EARTH CUT SM 1.56 30.62 1.63 8.45 42.26

Page 47
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Chitral
Chitral District Code: 10

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

109bi SUB GRADE PREPARATION IN EXISTING ROAD WITHOUT SM 1.14 20.39 0.87 5.60 28.00
ANY FILL

110 IMPROVED SUB-GRADE CM 10.98 134.42 59.28 51.17 255.85

114a DRESSING OF BERM WITHOUT EXTRA MATERIAL SM 0.92 17.09 0.89 4.73 23.63

114b DRESSING OF BERM WITH EXTRA BORROW MATERIAL SM 1.40 17.44 1.00 4.96 24.80

201 GRANULAR SUB-BASE CM 8.71 278.02 541.05 206.94 1,034.71

202 AGGREGATE BASE CM 10.41 355.93 793.62 289.99 1,449.95

203a ASPHALTIC BASE COURSE PLANT MIX (CLASS "A") CM 70.53 1,646.08 6,879.12 2,148.93 10,744.66

203b ASPHALTIC BASE COURSE PLANT MIX (CLASS "B") CM 73.44 1,646.08 7,369.31 2,272.21 11,361.03

203c ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "A") CM 79.10 1,719.24 6,867.81 2,166.54 10,832.68

203d ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "B") CM 79.10 1,712.72 7,534.06 2,331.47 11,657.36

204b CEMENT STABILIZED BASE CM 31.01 620.32 1,174.29 456.41 2,282.04

204d LIQUID ASPHALT FOR CURING SEAL, TYPE MC-250 TON 261.51 997.76 60,681.42 15,485.17 77,425.87

204e EMULSIFIED ASPHALT FOR CURING SEAL, TYPE SS-1 TON 261.51 997.76 58,961.26 15,055.13 75,275.67

205a GRADED CRUSHED AGGREGATE CRACK-RELIEF LAYER CM 86.75 122.95 1,075.60 321.32 1,606.62

205b ASPHALTIC OPEN-GRADED PLANT MIX CRACK-RELIEF CM 150.85 2,657.36 6,494.39 2,325.65 11,628.25
LAYER

206b WATER BOUND MACADAM BASE WITH COARSE CM 94.85 137.64 834.25 266.69 1,333.43
AGGREGATE CLASS B

207a DEEP PATCHING (0-15 cm) SM 1.90 49.09 1.37 13.09 65.45

207b DEEP PATCHING (16-30 cm) SM 1.90 43.25 1.37 11.63 58.15

208 REINSTATEMENT OF ROAD SURFACE SM 2.04 62.24 0.61 16.22 81.11

209a BREAKING OF EXISTING ROAD PAVEMENT STRUCTURE CM 2.43 120.57 0.74 30.94 154.68

209b SCARIFICATION OF EXISTING ROAD PAVEMENT SM 0.49 24.11 0.15 6.19 30.94

302a CUT-BACK ASPHALT FOR BITUMINOUS PRIME COAT SM 0.32 1.72 43.07 11.28 56.38

302b EMULSIFIED ASPHALT FOR BITUMINOUS PRIME COAT SM 0.31 1.72 48.07 12.53 62.63

303a CUT-BACK ASPHALT FOR BITUMINOUS TACK COAT SM 0.13 0.63 18.02 4.70 23.48

303b EMULSIFIED ASPHALT FOR BITUMINOUS TACK COAT SM 0.13 0.63 21.03 5.45 27.24

304a SINGLE SURFACE TREATMENT SM 0.85 8.26 86.26 23.84 119.21

304b DOUBLE SURFACE TREATMENT SM 1.24 15.43 167.45 46.03 230.15

304c TRIPLE SURFACE TREATMENT SM 2.10 21.73 191.09 53.73 268.65

304d SEAL COAT SM 0.79 4.49 60.66 16.48 82.42

Page 48
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Chitral
Chitral District Code: 10

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

305a ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 68.06 1,623.37 8,092.64 2,446.02 12,230.08
"A")

305b ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 68.06 1,567.67 8,743.32 2,594.76 12,973.81
"B")

307a DENSE GRADED HOT BIT-MAC CM 164.59 413.95 6,758.19 1,834.18 9,170.91

307b OPEN GRADED HOT BIT-MAC CM 164.59 413.95 6,568.69 1,786.81 8,934.03

308a RECYCLING OF ASPHALT CONCRETE (0 - 60 mm THICK) CM 29.03 643.80 2,341.02 753.46 3,767.31

308b BITUMEN BINDER GRADE (40 - 50, 60 - 70, 80 - 100) TON 26.27 709.26 52,133.13 13,217.16 66,085.82

309a COLD MILLING, 0 - 30 mm SM 1.03 27.24 9.46 9.43 47.16

309b COLD MILLING, 0 - 50 mm SM 1.72 45.40 15.76 15.72 78.61

309c COLD MILLING, 0 - 70 mm SM 2.58 68.10 23.64 23.58 117.91

401a1i CONCRETE CLASS "A1" (Underground) CM 569.68 1,165.93 4,423.58 1,539.80 7,698.99

401a1ii CONCRETE CLASS "A1" (On ground) CM 569.68 1,165.93 4,728.80 1,616.10 8,080.51

401a1iii CONCRETE CLASS "A1" (Elevated) CM 569.68 1,165.93 5,339.24 1,768.71 8,843.56

401a2i CONCRETE CLASS "A2" (Underground) CM 569.68 1,165.93 4,839.38 1,643.75 8,218.74

401a2ii CONCRETE CLASS "A2" (On ground) CM 569.68 1,165.93 5,144.60 1,720.05 8,600.26

401a2iii CONCRETE CLASS "A2" (Elevated) CM 569.68 1,165.93 5,755.04 1,872.66 9,363.31

401a3i CONCRETE CLASS "A3" (Underground) CM 569.68 1,165.93 5,255.18 1,747.70 8,738.49

401a3ii CONCRETE CLASS "A3" (On ground) CM 569.68 1,165.93 5,560.40 1,824.00 9,120.01

401a3iii CONCRETE CLASS "A3" (Elevated) CM 569.68 1,165.93 6,170.84 1,976.61 9,883.06

401b CONCRETE CLASS "B" CM 724.73 886.52 3,591.86 1,300.78 6,503.89

401ci CONCRETE CLASS "C" (Underground) CM 546.01 550.60 3,954.63 1,262.81 6,314.05

401cii CONCRETE CLASS "C" (On ground) CM 546.01 550.60 4,084.80 1,295.35 6,476.77

401ciii CONCRETE CLASS "C" (Elevated) CM 546.01 550.60 4,345.16 1,360.44 6,802.21

401d CONCRETE CLASS "D1" CM 877.22 1,392.12 5,891.76 2,040.28 10,201.38

401e CONCRETE CLASS "Y" CM 1,199.03 550.60 5,280.72 1,757.59 8,787.95

401f LEAN CONCRETE CM 438.15 558.27 2,790.85 946.82 4,734.08

401gi(1) PRECAST CONCRETE CLASS "A-1" CM 1,801.80 1,041.87 5,531.38 2,093.76 10,468.81

401gi(3) PRECAST CONCRETE CLASS "A-3" CM 1,801.80 1,041.87 6,362.98 2,301.66 11,508.31

401gii PRECAST CONCRETE CLASS "B" CM 1,801.80 1,041.87 5,275.03 2,029.67 10,148.37

401giii(1) PRECAST CONCRETE CLASS "D1" CM 1,801.80 1,041.87 6,778.78 2,405.61 12,028.06

Page 49
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Chitral
Chitral District Code: 10

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

401giii(2) PRECAST CONCRETE CLASS "D2" CM 1,801.80 1,041.87 7,194.58 2,509.56 12,547.81

401giii(3) PRECAST CONCRETE CLASS "D3" CM 1,801.80 1,041.87 7,610.38 2,613.51 13,067.56

404a REINFORCEMENT AS PER AASHTO M. 31 GRADE 40 TON 1,716.12 859.62 67,625.80 17,550.39 87,751.93

404b REINFORCEMENT AS PER AASHTO M. 31 GRADE 60 TON 1,716.12 859.62 75,710.80 19,571.64 97,858.18

404h REINFORCEMENT (STRUCTURAL SHAPES) AS PER ASTM-A- TON 1,393.08 5,933.20 62,696.24 17,505.63 87,528.14
36

405a PRE-STRESSING WIRE STRAND 3/8" - 1/2" DIA COMPLETE IN TON 2,891.00 17,224.95 147,314.08 41,857.51 209,287.54
ALL RESPECT

405b LAUNCHING OF GIRDER TON 66.77 585.78 - 163.14 815.68

406a PREMOULDED JOINT FILLER 12 mm THICK WITH SM 120.09 - 337.83 114.48 572.39
BITUMASTIC JOINT SEAL

406b NEOPRENE RUBBER JOINT FILLER 12 mm THICK WITH SM 120.09 - 336.90 114.25 571.23
BITUMASTIC JOINT SEAL

406c STEEL EXPANSION JOINTS KG 9.91 29.03 101.15 35.02 175.12

406d WATER STOPS 6" SIZE M 102.94 - 520.94 155.97 779.85

406e ELASTOMERIC BEARING PADS (ACCORDING TO SIZE AND ccm 0.02 - 2.33 0.59 2.94
THICKNESS)

406f ASPHALT FELT (3 PLY) SM 45.48 - 3,377.00 855.62 4,278.10

406g STEEL OR METAL BEARING DEVICES KG 20.92 76.65 129.94 56.88 284.39

407d1 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 358.17 1,819.45 1,192.20 842.45 4,212.27
(BORING ONLY) IN NORMAL SOIL

407d2 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 537.25 2,729.17 1,788.30 1,263.68 6,318.40
(BORING ONLY) IN GRAVEL STRATA

407d3 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 537.25 2,729.17 1,300.52 1,141.74 5,708.68
ONLY) IN NORMAL SOIL

407d4 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 895.42 4,548.62 1,496.48 1,735.13 8,675.64
ONLY) IN GRAVEL STRATA

407d5 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 767.50 5,373.43 1,695.62 1,959.14 9,795.69
ONLY) IN NORMAL SOIL

407d6 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 1,343.13 7,600.76 1,867.25 2,702.78 13,513.92
ONLY) IN GRAVEL SOIL

407h PILE LOAD TEST UP TO 120 TON EACH 21,389.84 50,346.23 103,772.22 43,877.07 219,385.36

407i PILE LOAD TEST UP TO 240 TON EACH 38,940.59 50,346.23 207,544.44 74,207.81 371,039.07

407j PILE LOAD TEST UP TO 360 TON EACH 56,491.34 55,207.22 311,316.65 105,753.80 528,769.02

407k CONFIRMATORY BORING (NX SIZE) M 192.86 1,740.22 7.00 485.02 2,425.11

410 BRICK WORK CM 349.06 311.00 4,236.76 1,224.20 6,121.02

411a STONE MASONRY RANDOM DRY CM 297.37 118.76 473.31 222.36 1,111.80

411b STONE MASONRY RANDOM WITH MORTAR CM 322.39 183.35 1,653.97 539.93 2,699.64

411c STONE MASONRY DRESSED UNCOURSED DRY CM 386.42 118.76 529.98 258.79 1,293.94

411d STONE MASONRY DRESSED UNCOURSED WITH MORTAR CM 455.96 183.35 1,709.86 587.29 2,936.47

Page 50
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Chitral
Chitral District Code: 10

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

411g ROLL POINTING SM 74.86 12.92 48.99 34.19 170.95

412a STONE MASONRY DRESSED COURSED WITH MORTAR CM 609.03 290.49 1,605.57 626.27 3,131.37

501a R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 310 mm M 218.18 481.23 709.35 352.19 1,760.95

501b R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 380 mm M 211.13 634.90 919.53 441.39 2,206.95

501c R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 460 mm M 214.93 1,029.55 1,179.10 605.89 3,029.47

501d R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 610 mm M 221.98 1,261.03 1,760.69 810.93 4,054.63

501e R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 760 mm M 256.43 1,186.26 2,530.30 993.25 4,966.23

501f R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 910 mm M 320.85 1,464.43 3,979.82 1,441.27 7,206.37

501g R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1070 mm M 415.22 1,629.55 5,152.35 1,799.28 8,996.39

501h R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1220 mm M 486.32 1,978.74 6,565.76 2,257.71 11,288.53

501i R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1520 mm M 579.20 2,308.53 10,140.73 3,257.12 16,285.58

501j R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 310 mm M 218.18 558.07 797.54 393.45 1,967.23

501k R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 380 mm M 211.13 634.90 940.23 446.56 2,232.82

501l R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 460 mm M 209.51 1,029.55 1,151.14 597.55 2,987.75

501m R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 610 mm M 221.98 1,261.03 1,920.11 850.78 4,253.90

501n R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 760 mm M 256.43 1,186.26 3,650.57 1,273.31 6,366.57

501o R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 910 mm M 320.85 1,464.43 5,362.86 1,787.03 8,935.17

501p R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1070 mm M 415.22 1,629.55 7,493.62 2,384.60 11,922.99

501q R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1220 mm M 486.32 1,978.74 10,163.07 3,157.03 15,785.16

501r R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1520 mm M 579.20 2,308.53 14,297.48 4,296.30 21,481.51

502a GRANULAR MATERIAL IN BED TO CONCRETE PIPE CM 87.97 130.82 377.80 149.15 745.74
CULVERT

502b CONCRETE CLASS "B" IN BEDDING AND ENCASEMENT OF CM 818.35 674.24 3,976.86 1,367.36 6,836.81
CONCRETE PIPE CULVERT

507a STEEL WIRE MESH FOR GABIONS KG 5.58 - 119.56 31.28 156.42

507b ROCK FILL IN GABIONS CM 91.57 - 465.85 139.35 696.77

508a BRICK PAVING (SINGLE COURSE) SM 112.77 35.97 364.11 128.21 641.06

508b BRICK PAVING (DOUBLE COURSE) SM 201.82 35.97 724.84 240.66 1,203.28

509a RIP RAP CLASS "A" CM 494.27 - 369.02 215.82 1,079.12

509b RIP RAP CLASS "B" CM 474.46 - 366.07 210.13 1,050.66

509c RIP RAP CLASS "C" CM 477.93 - 369.02 211.74 1,058.68

Page 51
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Chitral
Chitral District Code: 10

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

509d GROUTED RIP RAP CLASS "A" CM 602.27 112.36 1,933.60 662.06 3,310.29

509e GROUTED RIP RAP CLASS "B" CM 580.87 89.89 1,768.13 609.72 3,048.61

509f GROUTED RIP RAP CLASS "C" CM 573.10 74.91 1,818.02 616.51 3,082.53

509g REINFORCED CONCRETE SLOPE PROTECTION (WITHOUT CM 813.36 388.33 4,594.72 1,449.10 7,245.50
REINFORCEMENT)

509h FILTER LAYER OF GRANULAR MATERIAL CM 46.45 211.17 408.19 166.45 832.26

510 DISMANTLING OF STRUCTURE AND OBSTRUCTIONS CM 102.52 429.76 - 133.07 665.35

511a1 DRY STONE PITCHING (15-20 cm Thick) SM 155.67 74.22 59.97 72.47 362.33

511a2 DRY STONE PITCHING (21-25 cm Thick) SM 199.26 95.01 76.76 92.76 463.78

511b1 GROUTED STONE PITCHING (15-20 cm Thick) SM 254.90 198.35 401.16 213.60 1,068.01

511b2 GROUTED STONE PITCHING (21-25 cm Thick) SM 318.62 247.94 501.45 267.00 1,335.02

601ai CONCRETE KERB IN PLACE NEW JERSY BARRIER FOR M 310.99 648.78 2,549.31 877.27 4,386.35
MEDIAN (DOUBLE FACE)

601di PRECAST REINFORCED CONCRETE KERB NEW JERSY M 1,019.28 745.57 4,674.05 1,609.73 8,048.63
BARRIER FOR MEDIAN (DOUBLE FACE)

601dii PRECAST KERB IN CONCRETE CLASS A-1 OF SIZE 450 X 150 MM M 147.67 102.44 492.96 185.77 928.83
INCLUDING CONCRETE BEDDING & HAUNCHING

603 BRICK EDGING M 8.41 - 55.37 15.94 79.72

604a METAL GUARD RAIL M 18.12 72.97 1,626.74 429.46 2,147.28

604b METAL GUARD RAIL END PIECES EACH 22.64 - 1,233.50 314.04 1,570.18

604d STEEL POST OF METAL GUARD RAIL EACH 85.54 1,006.03 3,889.60 1,245.29 6,226.46

605a CONCRETE BEAM GUARD RAIL M 67.92 31.75 618.76 179.61 898.03

605c CONCRETE POST FOR GUARD RAIL M 83.40 28.18 620.14 182.93 914.65

607a TRAFFIC ROAD SIGN CATEGORY 1 EACH 225.02 262.80 7,073.94 1,890.44 9,452.21

607b TRAFFIC ROAD SIGN CATEGORY 2 EACH 69.06 394.21 9,551.21 2,503.62 12,518.10

607c TRAFFIC ROAD SIGN CATEGORY 3 (a) EACH 225.02 558.14 12,270.23 3,263.35 16,316.74

607d TRAFFIC ROAD SIGN CATEGORY 3 (b) EACH 690.55 616.60 21,630.70 5,734.46 28,672.31

607e TRAFFIC ROAD SIGN CATEGORY 3 (c) SM 138.11 123.32 9,504.22 2,441.41 12,207.06

607f ADDITIONAL PANEL SIZE 60 X 30 cm EACH 284.23 - 1,344.76 407.25 2,036.23

607g ADDITIONAL PANEL SIZE 90 X 30 cm EACH 284.23 - 2,017.13 575.34 2,876.70

608b1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.66 6.03 16.66 6.34 31.70
LINES OF 15 cm WIDTH

608b2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.89 4.15 41.00 11.51 57.55
LINES OF 15 cm WIDTH

608c1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.66 6.03 22.23 7.73 38.66
LINES OF 20 cm WIDTH

Page 52
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Chitral
Chitral District Code: 10

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

608c2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.89 4.15 54.69 14.93 74.66
LINES OF 20 cm WIDTH

608d1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 75.22 5.37 161.01 60.40 301.99
4.0 M ARROWS

608d2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR 4.0 EACH 75.22 10.28 516.71 150.55 752.77
M ARROWS

608h1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.33 8.85 23.17 8.84 44.18
OF 15 cm WIDTH

608h2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.33 9.92 69.53 20.69 103.47
OF 15 cm WIDTH

608i1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.33 7.16 30.89 10.34 51.72
OF 20 cm WIDTH

608i2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.33 9.92 92.71 26.49 132.44
OF 20 cm WIDTH

608j1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR 4.0 M EACH 75.22 3.84 223.69 75.69 378.43
ARROWS

608j2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR 4.0 M EACH 75.22 8.13 876.74 240.02 1,200.11
ARROWS

608n1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 62.44 3.84 107.34 43.40 217.02
STOP

608n2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR EACH 62.44 8.13 345.00 103.89 519.46
STOP

608n3 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR STOP EACH 62.44 3.84 149.13 53.85 269.25

608n4 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR STOP EACH 62.44 8.13 585.37 163.99 819.93

609c REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 9.64 84.07 199.68 73.35 366.73
SINGLE)

609d REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 9.64 84.06 240.87 83.65 418.23
DOUBLE)

610b RIGHT OF WAY MARKER EACH 92.32 124.97 313.83 132.78 663.89

610c KILOMETRE POST (0.610 X 0.114 X 1.5 M) EACH 591.34 1,005.59 2,121.89 929.71 4,648.53

610d TEN KILOMETRE POST EACH 1,131.56 2,011.19 4,651.41 1,948.54 9,742.70

611a CHAIN LINK WIRE FABRIC FENCING 1500 MM HEIGHT M 132.91 99.10 1,014.27 311.57 1,557.85
WITH PRECAST PRESTRESSED R.C.C. POST

Page 53
.

Page 54
NATIONAL HIGHWAY AUTHORITY

COMPOSITE SCHEDULE OF RATES


January - 2009

CHARSADDAH
(10-A)

Shabir Associates
Quantity Surveying & Construction Cost Consultants

Page 55
.

Page 56
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Charsaddah
Charsaddah District Code: 10-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

101 CLEARING AND GRUBBING SM 0.56 10.10 - 2.67 13.33

102a REMOVAL OF TREES 150 - 300 mm GIRTH EACH 5.84 173.32 1.17 45.08 225.41

102b REMOVAL OF TREES 301 - 600 mm GIRTH EACH 16.35 456.54 2.63 118.88 594.39

102c REMOVAL OF TREES 601 mm OR OVER GIRTH EACH 65.38 1,826.16 10.51 475.51 2,377.57

103 STRIPPING CM 2.09 93.22 - 23.83 119.13

104 COMPACTION OF NATURAL GROUND SM 0.30 9.91 0.84 2.76 13.81

106a EXCAVATE UNSUITABLE COMMON MATERIAL CM 4.07 135.76 - 34.96 174.79

106bi EXCAVATE UNSUITABLE HARD ROCK MATERIAL CM 106.99 316.30 50.82 118.53 592.64

106bii EXCAVATE UNSUITABLE MEDIUM ROCK MATERIAL CM 14.34 337.99 - 88.08 440.42

106biii EXCAVATE UNSUITABLE SOFT ROCK MATERIAL CM 9.41 262.40 - 67.95 339.76

106c EXCAVATE SURPLUS COMMON MATERIAL CM 3.33 120.27 - 30.90 154.50

106di EXCAVATE SURPLUS HARD ROCK MATERIAL CM 106.99 316.30 50.82 118.53 592.64

106dii EXCAVATE SURPLUS MEDIUM ROCK MATERIAL CM 17.03 316.03 - 83.27 416.33

106diii EXCAVATE SURPLUS SOFT ROCK MATERIAL CM 7.29 263.92 - 67.80 339.02

107a STRUCTURAL EXCAVATION IN COMMON MATERIAL CM 6.46 137.60 0.42 36.12 180.60

107b STRUCTURAL EXCAVATION IN COMMON MATERIAL BELOW CM 53.51 287.11 70.80 102.86 514.29
WATER LEVEL

107ci STRUCTURAL EXCAVATION IN HARD ROCK MATERIAL CM 94.63 427.01 33.88 138.88 694.40

107cii STRUCTURAL EXCAVATION IN MEDIUM ROCK MATERIAL CM 79.59 292.53 - 93.03 465.16

107ciii STRUCTURAL EXCAVATION IN SOFT ROCK MATERIAL CM 48.67 238.86 - 71.88 359.41

107d GRANULAR BACK FILL CM 27.57 137.14 382.09 136.70 683.49

107e COMMON BACK FILL CM 19.22 62.84 5.59 21.91 109.56

108a FORMATION OF EMBANKMENT FROM ROADWAY CM 5.86 174.71 5.59 46.54 232.70
EXCAVATION IN COMMON MATERIAL

108bi FORMATION OF EMBANKMENT FROM ROADWAY CM 16.75 482.48 54.36 138.40 691.99
EXCAVATION IN HARD ROCK MATERIAL

108bii FORMATION OF EMBANKMENT FROM ROADWAY CM 12.56 416.71 2.66 107.98 539.91
EXCAVATION IN MEDIUM ROCK MATERIAL

108biii FORMATION OF EMBANKMENT FROM ROADWAY CM 11.17 369.34 - 95.13 475.64


EXCAVATION IN SOFT ROCK MATERIAL

108c FORMATION OF EMBANKMENT FROM BORROW CM 6.57 177.46 8.44 48.12 240.59
EXCAVATION IN COMMON MATERIAL

108d FORMATION OF EMBANKMENT FROM STRUCTURAL CM 5.26 76.32 5.59 21.79 108.97
EXCAVATION IN COMMON MATERIAL

108e FORMATION OF EMBANKMENT FROM STRUCTURAL CM 11.89 110.29 3.32 31.38 156.88
EXCAVATION IN ANY TYPE OF ROCK MATERIAL

109a SUB GRADE PREPARATION IN EARTH CUT SM 1.17 27.34 1.60 7.53 37.64

Page 57
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Charsaddah
Charsaddah District Code: 10-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

109bi SUB GRADE PREPARATION IN EXISTING ROAD WITHOUT SM 0.86 18.21 0.85 4.98 24.90
ANY FILL

110 IMPROVED SUB-GRADE CM 8.40 120.02 55.91 46.08 230.42

114a DRESSING OF BERM WITHOUT EXTRA MATERIAL SM 0.71 15.26 0.87 4.21 21.05

114b DRESSING OF BERM WITH EXTRA BORROW MATERIAL SM 1.06 15.57 0.97 4.40 22.00

201 GRANULAR SUB-BASE CM 6.69 255.06 437.55 174.83 874.13

202 AGGREGATE BASE CM 8.09 326.54 709.15 260.95 1,304.73

203a ASPHALTIC BASE COURSE PLANT MIX (CLASS "A") CM 56.28 1,510.17 5,991.72 1,889.54 9,447.70

203b ASPHALTIC BASE COURSE PLANT MIX (CLASS "B") CM 58.42 1,510.17 6,404.20 1,993.20 9,965.99

203c ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "A") CM 62.55 1,577.28 5,981.81 1,905.41 9,527.06

203d ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "B") CM 62.55 1,571.31 6,550.19 2,046.01 10,230.06

204b CEMENT STABILIZED BASE CM 24.26 569.10 1,035.28 407.16 2,035.81

204d LIQUID ASPHALT FOR CURING SEAL, TYPE MC-250 TON 200.32 915.38 52,507.71 13,405.85 67,029.26

204e EMULSIFIED ASPHALT FOR CURING SEAL, TYPE SS-1 TON 200.32 915.38 50,929.58 13,011.32 65,056.59

205a GRADED CRUSHED AGGREGATE CRACK-RELIEF LAYER CM 70.86 112.80 916.96 275.15 1,375.76

205b ASPHALTIC OPEN-GRADED PLANT MIX CRACK-RELIEF CM 118.58 2,437.94 5,669.56 2,056.52 10,282.60
LAYER

206b WATER BOUND MACADAM BASE WITH COARSE CM 77.49 126.27 816.11 254.97 1,274.84
AGGREGATE CLASS B

207a DEEP PATCHING (0-15 cm) SM 1.47 45.04 1.38 11.97 59.86

207b DEEP PATCHING (16-30 cm) SM 1.47 39.67 1.38 10.63 53.16

208 REINSTATEMENT OF ROAD SURFACE SM 1.60 57.10 0.62 14.83 74.15

209a BREAKING OF EXISTING ROAD PAVEMENT STRUCTURE CM 1.87 110.61 0.75 28.31 141.54

209b SCARIFICATION OF EXISTING ROAD PAVEMENT SM 0.37 22.12 0.15 5.66 28.31

302a CUT-BACK ASPHALT FOR BITUMINOUS PRIME COAT SM 0.25 1.57 37.27 9.77 48.86

302b EMULSIFIED ASPHALT FOR BITUMINOUS PRIME COAT SM 0.24 1.57 41.60 10.85 54.27

303a CUT-BACK ASPHALT FOR BITUMINOUS TACK COAT SM 0.10 0.58 15.60 4.07 20.35

303b EMULSIFIED ASPHALT FOR BITUMINOUS TACK COAT SM 0.10 0.58 18.20 4.72 23.59

304a SINGLE SURFACE TREATMENT SM 0.66 7.57 74.12 20.59 102.94

304b DOUBLE SURFACE TREATMENT SM 0.95 14.15 143.51 39.65 198.26

304c TRIPLE SURFACE TREATMENT SM 1.61 19.94 163.73 46.32 231.60

304d SEAL COAT SM 0.61 4.12 52.48 14.30 71.51

Page 58
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Charsaddah
Charsaddah District Code: 10-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

305a ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 53.81 1,489.33 7,025.82 2,142.24 10,711.19
"A")

305b ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 53.81 1,438.23 7,584.47 2,269.13 11,345.64
"B")

307a DENSE GRADED HOT BIT-MAC CM 132.34 379.77 5,826.50 1,584.65 7,923.26

307b OPEN GRADED HOT BIT-MAC CM 132.34 379.77 5,655.06 1,541.79 7,708.96

308a RECYCLING OF ASPHALT CONCRETE (0 - 60 mm THICK) CM 23.64 590.65 2,059.20 668.37 3,341.86

308b BITUMEN BINDER GRADE (40 - 50, 60 - 70, 80 - 100) TON 21.30 650.70 44,571.28 11,310.82 56,554.10

309a COLD MILLING, 0 - 30 mm SM 0.82 24.99 8.68 8.62 43.11

309b COLD MILLING, 0 - 50 mm SM 1.36 41.65 14.47 14.37 71.85

309c COLD MILLING, 0 - 70 mm SM 2.04 62.48 21.70 21.56 107.78

401a1i CONCRETE CLASS "A1" (Underground) CM 468.85 1,059.94 4,014.71 1,385.87 6,929.37

401a1ii CONCRETE CLASS "A1" (On ground) CM 468.85 1,059.94 4,292.18 1,455.24 7,276.21

401a1iii CONCRETE CLASS "A1" (Elevated) CM 468.85 1,059.94 4,847.13 1,593.98 7,969.89

401a2i CONCRETE CLASS "A2" (Underground) CM 468.85 1,059.94 4,392.71 1,480.37 7,401.87

401a2ii CONCRETE CLASS "A2" (On ground) CM 468.85 1,059.94 4,670.18 1,549.74 7,748.71

401a2iii CONCRETE CLASS "A2" (Elevated) CM 468.85 1,059.94 5,225.13 1,688.48 8,442.39

401a3i CONCRETE CLASS "A3" (Underground) CM 468.85 1,059.94 4,770.71 1,574.87 7,874.37

401a3ii CONCRETE CLASS "A3" (On ground) CM 468.85 1,059.94 5,048.18 1,644.24 8,221.21

401a3iii CONCRETE CLASS "A3" (Elevated) CM 468.85 1,059.94 5,603.13 1,782.98 8,914.89

401b CONCRETE CLASS "B" CM 586.23 805.93 3,212.17 1,151.08 5,755.42

401ci CONCRETE CLASS "C" (Underground) CM 454.48 500.55 3,547.05 1,125.52 5,627.60

401cii CONCRETE CLASS "C" (On ground) CM 454.48 500.55 3,665.40 1,155.11 5,775.53

401ciii CONCRETE CLASS "C" (Elevated) CM 454.48 500.55 3,902.08 1,214.28 6,071.38

401d CONCRETE CLASS "D1" CM 734.94 1,265.57 5,352.43 1,838.24 9,191.18

401e CONCRETE CLASS "Y" CM 1,007.25 500.55 4,785.79 1,573.40 7,866.98

401f LEAN CONCRETE CM 361.09 507.52 2,473.39 835.50 4,177.49

401gi(1) PRECAST CONCRETE CLASS "A-1" CM 1,506.02 947.15 5,016.28 1,867.36 9,336.81

401gi(3) PRECAST CONCRETE CLASS "A-3" CM 1,506.02 947.15 5,772.28 2,056.36 10,281.81

401gii PRECAST CONCRETE CLASS "B" CM 1,506.02 947.15 4,751.22 1,801.10 9,005.49

401giii(1) PRECAST CONCRETE CLASS "D1" CM 1,506.02 947.15 6,150.28 2,150.86 10,754.31

Page 59
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Charsaddah
Charsaddah District Code: 10-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

401giii(2) PRECAST CONCRETE CLASS "D2" CM 1,506.02 947.15 6,528.28 2,245.36 11,226.81

401giii(3) PRECAST CONCRETE CLASS "D3" CM 1,506.02 947.15 6,906.28 2,339.86 11,699.31

404a REINFORCEMENT AS PER AASHTO M. 31 GRADE 40 TON 1,445.71 781.47 60,206.00 15,608.29 78,041.47

404b REINFORCEMENT AS PER AASHTO M. 31 GRADE 60 TON 1,445.71 781.47 67,556.00 17,445.79 87,228.97

404h REINFORCEMENT (STRUCTURAL SHAPES) AS PER ASTM-A- TON 1,160.29 5,393.81 56,000.99 15,638.77 78,193.86
36

405a PRE-STRESSING WIRE STRAND 3/8" - 1/2" DIA COMPLETE IN TON 2,470.45 15,659.05 133,860.62 37,997.53 189,987.65
ALL RESPECT

405b LAUNCHING OF GIRDER TON 58.23 532.52 - 147.69 738.44

406a PREMOULDED JOINT FILLER 12 mm THICK WITH SM 99.62 - 302.98 100.65 503.25
BITUMASTIC JOINT SEAL

406b NEOPRENE RUBBER JOINT FILLER 12 mm THICK WITH SM 99.62 - 302.17 100.45 502.24
BITUMASTIC JOINT SEAL

406c STEEL EXPANSION JOINTS KG 8.24 26.40 90.85 31.37 156.86

406d WATER STOPS 6" SIZE M 88.85 - 472.37 140.30 701.52

406e ELASTOMERIC BEARING PADS (ACCORDING TO SIZE AND ccm 0.01 - 2.12 0.53 2.67
THICKNESS)

406f ASPHALT FELT (3 PLY) SM 36.90 - 3,004.11 760.25 3,801.26

406g STEEL OR METAL BEARING DEVICES KG 16.50 69.68 117.83 51.00 255.01

407d1 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 319.83 1,654.04 719.98 673.46 3,367.32
(BORING ONLY) IN NORMAL SOIL

407d2 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 479.75 2,481.06 1,079.97 1,010.20 5,050.98
(BORING ONLY) IN GRAVEL STRATA

407d3 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 479.75 2,481.06 819.36 945.04 4,725.21
ONLY) IN NORMAL SOIL

407d4 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 799.58 4,135.11 999.57 1,483.56 7,417.82
ONLY) IN GRAVEL STRATA

407d5 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 685.35 4,884.94 1,182.08 1,688.09 8,440.47
ONLY) IN NORMAL SOIL

407d6 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 1,199.37 6,909.78 1,293.47 2,350.65 11,753.27
ONLY) IN GRAVEL SOIL

407h PILE LOAD TEST UP TO 120 TON EACH 17,317.36 45,769.30 99,000.62 40,521.82 202,609.10

407i PILE LOAD TEST UP TO 240 TON EACH 31,756.11 45,769.30 198,001.24 68,881.66 344,408.31

407j PILE LOAD TEST UP TO 360 TON EACH 46,194.85 50,188.38 297,001.86 98,346.27 491,731.37

407k CONFIRMATORY BORING (NX SIZE) M 167.58 1,582.02 6.99 439.15 2,195.74

410 BRICK WORK CM 289.69 282.72 2,998.75 892.79 4,463.95

411a STONE MASONRY RANDOM DRY CM 243.26 107.96 573.28 231.13 1,155.63

411b STONE MASONRY RANDOM WITH MORTAR CM 264.33 166.68 1,641.05 518.01 2,590.07

411c STONE MASONRY DRESSED UNCOURSED DRY CM 317.48 107.96 639.90 266.33 1,331.66

411d STONE MASONRY DRESSED UNCOURSED WITH MORTAR CM 375.64 166.68 1,709.41 562.93 2,814.67

Page 60
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Charsaddah
Charsaddah District Code: 10-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

411g ROLL POINTING SM 62.49 11.74 44.49 29.68 148.40

412a STONE MASONRY DRESSED COURSED WITH MORTAR CM 503.00 264.08 1,614.60 595.42 2,977.11

501a R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 310 mm M 178.12 437.48 645.37 315.24 1,576.22

501b R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 380 mm M 172.55 577.19 836.46 396.55 1,982.75

501c R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 460 mm M 172.97 935.96 1,072.53 545.36 2,726.82

501d R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 610 mm M 179.12 1,146.39 1,601.53 731.76 3,658.79

501e R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 760 mm M 205.91 1,078.41 2,301.17 896.37 4,481.86

501f R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 910 mm M 256.66 1,331.30 3,619.29 1,301.81 6,509.06

501g R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1070 mm M 332.15 1,481.41 4,685.73 1,624.82 8,124.11

501h R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1220 mm M 388.28 1,798.85 5,971.03 2,039.54 10,197.71

501i R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1520 mm M 462.34 2,098.66 9,221.37 2,945.59 14,727.96

501j R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 310 mm M 178.12 507.33 725.36 352.70 1,763.52

501k R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 380 mm M 172.55 577.19 855.28 401.25 2,006.27

501l R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 460 mm M 168.04 935.96 1,047.11 537.78 2,688.89

501m R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 610 mm M 179.12 1,146.39 1,746.12 767.91 3,839.54

501n R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 760 mm M 205.91 1,078.41 3,319.79 1,151.03 5,755.14

501o R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 910 mm M 256.66 1,331.30 4,876.60 1,616.14 8,080.70

501p R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1070 mm M 332.15 1,481.41 6,814.16 2,156.93 10,784.65

501q R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1220 mm M 388.28 1,798.85 9,241.31 2,857.11 14,285.56

501r R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1520 mm M 462.34 2,098.66 13,000.23 3,890.31 19,451.54

502a GRANULAR MATERIAL IN BED TO CONCRETE PIPE CM 70.99 118.93 407.53 149.36 746.81
CULVERT

502b CONCRETE CLASS "B" IN BEDDING AND ENCASEMENT OF CM 672.70 612.95 3,562.17 1,211.95 6,059.77
CONCRETE PIPE CULVERT

507a STEEL WIRE MESH FOR GABIONS KG 4.52 - 109.50 28.50 142.52

507b ROCK FILL IN GABIONS CM 74.25 - 423.50 124.44 622.19

508a BRICK PAVING (SINGLE COURSE) SM 92.92 32.70 237.66 90.82 454.10

508b BRICK PAVING (DOUBLE COURSE) SM 167.13 32.70 471.68 167.88 839.39

509a RIP RAP CLASS "A" CM 408.93 - 478.48 221.85 1,109.25

509b RIP RAP CLASS "B" CM 392.93 - 474.65 216.89 1,084.47

509c RIP RAP CLASS "C" CM 396.30 - 478.48 218.69 1,093.47

Page 61
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Charsaddah
Charsaddah District Code: 10-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

509d GROUTED RIP RAP CLASS "A" CM 497.87 102.14 1,897.44 624.36 3,121.82

509e GROUTED RIP RAP CLASS "B" CM 480.93 81.72 1,746.29 577.24 2,886.18

509f GROUTED RIP RAP CLASS "C" CM 474.99 68.10 1,792.68 583.94 2,919.71

509g REINFORCED CONCRETE SLOPE PROTECTION (WITHOUT CM 676.71 353.02 4,126.08 1,288.95 6,444.77
REINFORCEMENT)

509h FILTER LAYER OF GRANULAR MATERIAL CM 37.12 191.97 382.69 152.95 764.74

510 DISMANTLING OF STRUCTURE AND OBSTRUCTIONS CM 90.85 390.69 - 120.39 601.93

511a1 DRY STONE PITCHING (15-20 cm Thick) SM 127.80 67.48 77.75 68.26 341.29

511a2 DRY STONE PITCHING (21-25 cm Thick) SM 163.59 86.37 99.52 87.37 436.85

511b1 GROUTED STONE PITCHING (15-20 cm Thick) SM 210.12 180.32 379.74 192.55 962.73

511b2 GROUTED STONE PITCHING (21-25 cm Thick) SM 262.65 225.40 474.67 240.68 1,203.41

601ai CONCRETE KERB IN PLACE NEW JERSY BARRIER FOR M 248.44 572.25 2,246.49 766.80 3,833.98
MEDIAN (DOUBLE FACE)

601di PRECAST REINFORCED CONCRETE KERB NEW JERSY M 828.62 670.54 4,100.42 1,399.89 6,999.46
BARRIER FOR MEDIAN (DOUBLE FACE)

601dii PRECAST KERB IN CONCRETE CLASS A-1 OF SIZE 450 X 150 MM M 119.93 90.27 433.90 161.02 805.12
INCLUDING CONCRETE BEDDING & HAUNCHING

603 BRICK EDGING M 7.32 - 37.44 11.19 55.94

604a METAL GUARD RAIL M 16.45 70.84 1,579.36 416.66 2,083.32

604b METAL GUARD RAIL END PIECES EACH 21.98 - 1,197.58 304.89 1,524.45

604d STEEL POST OF METAL GUARD RAIL EACH 76.62 976.73 3,776.31 1,207.42 6,037.08

605a CONCRETE BEAM GUARD RAIL M 60.29 30.82 594.68 171.45 857.25

605c CONCRETE POST FOR GUARD RAIL M 74.03 27.36 595.43 174.21 871.03

607a TRAFFIC ROAD SIGN CATEGORY 1 EACH 192.65 255.15 6,846.80 1,823.65 9,118.26

607b TRAFFIC ROAD SIGN CATEGORY 2 EACH 60.66 382.72 9,242.62 2,421.50 12,107.51

607c TRAFFIC ROAD SIGN CATEGORY 3 (a) EACH 192.65 541.89 11,862.24 3,149.19 15,745.97

607d TRAFFIC ROAD SIGN CATEGORY 3 (b) EACH 600.00 598.64 20,913.67 5,528.08 27,640.39

607e TRAFFIC ROAD SIGN CATEGORY 3 (c) SM 120.00 119.73 9,193.99 2,358.43 11,792.15

607f ADDITIONAL PANEL SIZE 60 X 30 cm EACH 247.37 - 1,301.21 387.15 1,935.73

607g ADDITIONAL PANEL SIZE 90 X 30 cm EACH 247.37 - 1,951.82 549.80 2,748.99

608b1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.25 5.86 16.16 6.07 30.33
LINES OF 15 cm WIDTH

608b2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.75 4.03 39.61 11.10 55.48
LINES OF 15 cm WIDTH

608c1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.25 5.86 21.56 7.42 37.08
LINES OF 20 cm WIDTH

Page 62
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Charsaddah
Charsaddah District Code: 10-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

608c2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.75 4.03 52.83 14.40 72.01
LINES OF 20 cm WIDTH

608d1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 67.36 5.22 156.12 57.17 285.87
4.0 M ARROWS

608d2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR 4.0 EACH 67.36 9.98 499.15 144.12 720.61
M ARROWS

608h1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 2.81 8.59 22.47 8.47 42.34
OF 15 cm WIDTH

608h2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 2.81 9.63 67.50 19.99 99.93
OF 15 cm WIDTH

608i1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 2.81 6.95 29.96 9.93 49.65
OF 20 cm WIDTH

608i2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 2.81 9.63 90.01 25.61 128.06
OF 20 cm WIDTH

608j1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR 4.0 M EACH 67.36 3.73 216.98 72.02 360.08
ARROWS

608j2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR 4.0 M EACH 67.36 7.90 851.20 231.61 1,158.07
ARROWS

608n1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 55.87 3.73 104.08 40.92 204.59
STOP

608n2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR EACH 55.87 7.90 333.27 99.26 496.29
STOP

608n3 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR STOP EACH 55.87 3.73 144.65 51.06 255.31

608n4 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR STOP EACH 55.87 7.90 568.32 158.02 790.11

609c REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 8.29 81.62 193.85 70.94 354.70
SINGLE)

609d REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 8.29 81.62 233.85 80.94 404.70
DOUBLE)

610b RIGHT OF WAY MARKER EACH 81.54 121.33 302.80 126.42 632.08

610c KILOMETRE POST (0.610 X 0.114 X 1.5 M) EACH 521.25 976.31 2,036.05 883.40 4,417.02

610d TEN KILOMETRE POST EACH 996.55 1,952.61 4,467.86 1,854.26 9,271.28

611a CHAIN LINK WIRE FABRIC FENCING 1500 MM HEIGHT M 113.81 91.00 953.30 289.53 1,447.65
WITH PRECAST PRESTRESSED R.C.C. POST

Page 63
.

Page 64
NATIONAL HIGHWAY AUTHORITY

COMPOSITE SCHEDULE OF RATES


January - 2009

DERA ISMAIL KHAN


(12)

Shabir Associates
Quantity Surveying & Construction Cost Consultants

Page 65
.

Page 66
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Dera
Dera Ismail
Ismail Khan
Khan District Code: 12

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

101 CLEARING AND GRUBBING SM 0.66 10.10 - 2.69 13.45

102a REMOVAL OF TREES 150 - 300 mm GIRTH EACH 6.89 173.32 1.17 45.34 226.72

102b REMOVAL OF TREES 301 - 600 mm GIRTH EACH 19.32 456.54 2.63 119.62 598.11

102c REMOVAL OF TREES 601 mm OR OVER GIRTH EACH 77.29 1,826.16 10.51 478.49 2,392.46

103 STRIPPING CM 2.42 93.22 - 23.91 119.55

104 COMPACTION OF NATURAL GROUND SM 0.35 9.91 0.76 2.76 13.78

106a EXCAVATE UNSUITABLE COMMON MATERIAL CM 4.73 135.76 - 35.12 175.61

106bi EXCAVATE UNSUITABLE HARD ROCK MATERIAL CM 121.49 316.30 50.82 122.15 610.77

106bii EXCAVATE UNSUITABLE MEDIUM ROCK MATERIAL CM 16.01 337.99 - 88.50 442.50

106biii EXCAVATE UNSUITABLE SOFT ROCK MATERIAL CM 10.41 262.40 - 68.20 341.01

106c EXCAVATE SURPLUS COMMON MATERIAL CM 3.87 120.27 - 31.04 155.18

106di EXCAVATE SURPLUS HARD ROCK MATERIAL CM 121.49 316.30 50.82 122.15 610.77

106dii EXCAVATE SURPLUS MEDIUM ROCK MATERIAL CM 19.35 316.03 - 83.85 419.23

106diii EXCAVATE SURPLUS SOFT ROCK MATERIAL CM 8.11 263.92 - 68.01 340.04

107a STRUCTURAL EXCAVATION IN COMMON MATERIAL CM 7.33 137.60 0.38 36.33 181.64

107b STRUCTURAL EXCAVATION IN COMMON MATERIAL BELOW CM 60.23 287.11 70.80 104.54 522.69
WATER LEVEL

107ci STRUCTURAL EXCAVATION IN HARD ROCK MATERIAL CM 107.51 427.01 33.88 142.10 710.51

107cii STRUCTURAL EXCAVATION IN MEDIUM ROCK MATERIAL CM 90.19 292.53 - 95.68 478.40

107ciii STRUCTURAL EXCAVATION IN SOFT ROCK MATERIAL CM 55.29 238.86 - 73.54 367.69

107d GRANULAR BACK FILL CM 32.22 137.14 410.89 145.06 725.32

107e COMMON BACK FILL CM 22.86 62.84 5.09 22.70 113.49

108a FORMATION OF EMBANKMENT FROM ROADWAY CM 6.56 174.71 5.09 46.59 232.95
EXCAVATION IN COMMON MATERIAL

108bi FORMATION OF EMBANKMENT FROM ROADWAY CM 18.99 482.48 54.04 138.88 694.39
EXCAVATION IN HARD ROCK MATERIAL

108bii FORMATION OF EMBANKMENT FROM ROADWAY CM 14.24 416.71 2.42 108.34 541.71
EXCAVATION IN MEDIUM ROCK MATERIAL

108biii FORMATION OF EMBANKMENT FROM ROADWAY CM 12.66 369.34 - 95.50 477.50


EXCAVATION IN SOFT ROCK MATERIAL

108c FORMATION OF EMBANKMENT FROM BORROW CM 7.41 177.46 7.94 48.20 241.01
EXCAVATION IN COMMON MATERIAL

108d FORMATION OF EMBANKMENT FROM STRUCTURAL CM 5.90 76.32 5.09 21.83 109.14
EXCAVATION IN COMMON MATERIAL

108e FORMATION OF EMBANKMENT FROM STRUCTURAL CM 13.54 110.29 3.03 31.71 158.57
EXCAVATION IN ANY TYPE OF ROCK MATERIAL

109a SUB GRADE PREPARATION IN EARTH CUT SM 1.33 27.34 1.46 7.53 37.66

Page 67
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Dera
Dera Ismail
Ismail Khan
Khan District Code: 12

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

109bi SUB GRADE PREPARATION IN EXISTING ROAD WITHOUT SM 0.98 18.21 0.77 4.99 24.95
ANY FILL

110 IMPROVED SUB-GRADE CM 9.58 120.02 53.53 45.78 228.91

114a DRESSING OF BERM WITHOUT EXTRA MATERIAL SM 0.81 15.26 0.79 4.22 21.08

114b DRESSING OF BERM WITH EXTRA BORROW MATERIAL SM 1.19 15.57 0.90 4.41 22.07

201 GRANULAR SUB-BASE CM 7.53 255.06 516.15 194.68 973.42

202 AGGREGATE BASE CM 9.19 326.54 720.28 264.00 1,320.01

203a ASPHALTIC BASE COURSE PLANT MIX (CLASS "A") CM 65.24 1,510.17 6,104.67 1,920.02 9,600.10

203b ASPHALTIC BASE COURSE PLANT MIX (CLASS "B") CM 67.59 1,510.17 6,580.96 2,039.68 10,198.40

203c ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "A") CM 72.03 1,577.28 6,093.84 1,935.79 9,678.94

203d ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "B") CM 72.03 1,571.31 6,733.42 2,094.19 10,470.95

204b CEMENT STABILIZED BASE CM 27.70 569.10 812.99 352.45 1,762.24

204d LIQUID ASPHALT FOR CURING SEAL, TYPE MC-250 TON 226.93 915.38 56,046.75 14,297.26 71,486.32

204e EMULSIFIED ASPHALT FOR CURING SEAL, TYPE SS-1 TON 226.93 915.38 54,468.62 13,902.73 69,513.66

205a GRADED CRUSHED AGGREGATE CRACK-RELIEF LAYER CM 83.54 112.80 817.47 253.45 1,267.25

205b ASPHALTIC OPEN-GRADED PLANT MIX CRACK-RELIEF CM 135.72 2,437.94 5,767.82 2,085.37 10,426.85
LAYER

206b WATER BOUND MACADAM BASE WITH COARSE CM 91.47 126.27 761.36 244.77 1,223.87
AGGREGATE CLASS B

207a DEEP PATCHING (0-15 cm) SM 1.66 45.04 1.26 11.99 59.94

207b DEEP PATCHING (16-30 cm) SM 1.66 39.67 1.26 10.65 53.24

208 REINSTATEMENT OF ROAD SURFACE SM 1.84 57.10 0.56 14.88 74.38

209a BREAKING OF EXISTING ROAD PAVEMENT STRUCTURE CM 2.11 110.61 0.68 28.35 141.75

209b SCARIFICATION OF EXISTING ROAD PAVEMENT SM 0.42 22.12 0.14 5.67 28.35

302a CUT-BACK ASPHALT FOR BITUMINOUS PRIME COAT SM 0.29 1.57 39.78 10.41 52.05

302b EMULSIFIED ASPHALT FOR BITUMINOUS PRIME COAT SM 0.28 1.57 44.40 11.56 57.81

303a CUT-BACK ASPHALT FOR BITUMINOUS TACK COAT SM 0.11 0.58 16.65 4.34 21.68

303b EMULSIFIED ASPHALT FOR BITUMINOUS TACK COAT SM 0.11 0.58 19.42 5.03 25.15

304a SINGLE SURFACE TREATMENT SM 0.75 7.57 78.73 21.76 108.81

304b DOUBLE SURFACE TREATMENT SM 1.08 14.15 152.06 41.82 209.12

304c TRIPLE SURFACE TREATMENT SM 1.83 19.94 173.40 48.79 243.96

304d SEAL COAT SM 0.69 4.12 55.38 15.05 75.25

Page 68
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Dera
Dera Ismail
Ismail Khan
Khan District Code: 12

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

305a ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 61.94 1,489.33 7,232.51 2,195.94 10,979.72
"A")

305b ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 61.94 1,438.23 7,819.16 2,329.83 11,649.15
"B")

307a DENSE GRADED HOT BIT-MAC CM 153.42 379.77 6,016.53 1,637.43 8,187.15

307b OPEN GRADED HOT BIT-MAC CM 153.42 379.77 5,860.62 1,598.45 7,992.26

308a RECYCLING OF ASPHALT CONCRETE (0 - 60 mm THICK) CM 27.40 590.65 2,124.46 685.63 3,428.14

308b BITUMEN BINDER GRADE (40 - 50, 60 - 70, 80 - 100) TON 25.24 650.70 48,215.44 12,222.85 61,114.23

309a COLD MILLING, 0 - 30 mm SM 0.94 24.99 8.68 8.65 43.26

309b COLD MILLING, 0 - 50 mm SM 1.56 41.65 14.46 14.42 72.10

309c COLD MILLING, 0 - 70 mm SM 2.35 62.48 21.69 21.63 108.15

401a1i CONCRETE CLASS "A1" (Underground) CM 522.66 1,059.94 3,802.32 1,346.23 6,731.15

401a1ii CONCRETE CLASS "A1" (On ground) CM 522.66 1,059.94 4,079.79 1,415.60 7,077.99

401a1iii CONCRETE CLASS "A1" (Elevated) CM 522.66 1,059.94 4,634.74 1,554.33 7,771.67

401a2i CONCRETE CLASS "A2" (Underground) CM 522.66 1,059.94 4,180.32 1,440.73 7,203.65

401a2ii CONCRETE CLASS "A2" (On ground) CM 522.66 1,059.94 4,457.79 1,510.10 7,550.49

401a2iii CONCRETE CLASS "A2" (Elevated) CM 522.66 1,059.94 5,012.74 1,648.83 8,244.17

401a3i CONCRETE CLASS "A3" (Underground) CM 522.66 1,059.94 4,558.32 1,535.23 7,676.15

401a3ii CONCRETE CLASS "A3" (On ground) CM 522.66 1,059.94 4,835.79 1,604.60 8,022.99

401a3iii CONCRETE CLASS "A3" (Elevated) CM 522.66 1,059.94 5,390.74 1,743.33 8,716.67

401b CONCRETE CLASS "B" CM 659.59 805.93 3,070.65 1,134.04 5,670.21

401ci CONCRETE CLASS "C" (Underground) CM 508.01 500.55 3,358.60 1,091.79 5,458.95

401cii CONCRETE CLASS "C" (On ground) CM 508.01 500.55 3,476.94 1,121.38 5,606.88

401ciii CONCRETE CLASS "C" (Elevated) CM 508.01 500.55 3,713.63 1,180.55 5,902.74

401d CONCRETE CLASS "D1" CM 821.14 1,265.57 5,160.79 1,811.87 9,059.37

401e CONCRETE CLASS "Y" CM 1,125.25 500.55 4,585.74 1,552.88 7,764.42

401f LEAN CONCRETE CM 414.30 507.52 2,340.82 815.66 4,078.30

401gi(1) PRECAST CONCRETE CLASS "A-1" CM 1,690.12 947.15 4,785.87 1,855.79 9,278.93

401gi(3) PRECAST CONCRETE CLASS "A-3" CM 1,690.12 947.15 5,541.87 2,044.79 10,223.93

401gii PRECAST CONCRETE CLASS "B" CM 1,690.12 947.15 4,589.10 1,806.59 9,032.97

401giii(1) PRECAST CONCRETE CLASS "D1" CM 1,690.12 947.15 5,919.87 2,139.29 10,696.43

Page 69
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Dera
Dera Ismail
Ismail Khan
Khan District Code: 12

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

401giii(2) PRECAST CONCRETE CLASS "D2" CM 1,690.12 947.15 6,297.87 2,233.79 11,168.93

401giii(3) PRECAST CONCRETE CLASS "D3" CM 1,690.12 947.15 6,675.87 2,328.29 11,641.43

404a REINFORCEMENT AS PER AASHTO M. 31 GRADE 40 TON 1,633.53 781.47 60,206.00 15,655.25 78,276.25

404b REINFORCEMENT AS PER AASHTO M. 31 GRADE 60 TON 1,633.53 781.47 67,556.00 17,492.75 87,463.75

404h REINFORCEMENT (STRUCTURAL SHAPES) AS PER ASTM-A- TON 1,299.70 5,393.81 56,161.26 15,713.69 78,568.47
36

405a PRE-STRESSING WIRE STRAND 3/8" - 1/2" DIA COMPLETE IN TON 2,832.66 15,659.05 133,811.69 38,075.85 190,379.24
ALL RESPECT

405b LAUNCHING OF GIRDER TON 67.08 532.52 - 149.90 749.51

406a PREMOULDED JOINT FILLER 12 mm THICK WITH SM 112.88 - 310.41 105.82 529.11
BITUMASTIC JOINT SEAL

406b NEOPRENE RUBBER JOINT FILLER 12 mm THICK WITH SM 112.88 - 309.31 105.55 527.73
BITUMASTIC JOINT SEAL

406c STEEL EXPANSION JOINTS KG 9.28 26.40 90.58 31.56 157.81

406d WATER STOPS 6" SIZE M 101.91 - 407.95 127.46 637.32

406e ELASTOMERIC BEARING PADS (ACCORDING TO SIZE AND ccm 0.02 - 2.12 0.53 2.67
THICKNESS)

406f ASPHALT FELT (3 PLY) SM 39.04 - 3,088.17 781.80 3,909.02

406g STEEL OR METAL BEARING DEVICES KG 18.71 69.68 116.93 51.33 256.65

407d1 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 372.35 1,654.04 1,189.34 803.93 4,019.66
(BORING ONLY) IN NORMAL SOIL

407d2 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 558.52 2,481.06 1,784.01 1,205.90 6,029.49
(BORING ONLY) IN GRAVEL STRATA

407d3 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 558.52 2,481.06 1,480.77 1,130.09 5,650.44
ONLY) IN NORMAL SOIL

407d4 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 930.86 4,135.11 1,979.92 1,761.47 8,807.36
ONLY) IN GRAVEL STRATA

407d5 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 797.88 4,884.94 2,386.41 2,017.31 10,086.55
ONLY) IN NORMAL SOIL

407d6 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 1,396.30 6,909.78 2,695.36 2,750.36 13,751.79
ONLY) IN GRAVEL SOIL

407h PILE LOAD TEST UP TO 120 TON EACH 20,478.32 45,769.30 100,985.02 41,808.16 209,040.80

407i PILE LOAD TEST UP TO 240 TON EACH 37,711.07 45,769.30 201,970.04 71,362.60 356,813.01

407j PILE LOAD TEST UP TO 360 TON EACH 54,943.82 50,188.38 302,955.06 102,021.82 510,109.08

407k CONFIRMATORY BORING (NX SIZE) M 196.36 1,582.02 6.37 446.19 2,230.94

410 BRICK WORK CM 310.55 282.72 2,914.01 876.82 4,384.10

411a STONE MASONRY RANDOM DRY CM 264.65 107.96 426.76 199.84 999.21

411b STONE MASONRY RANDOM WITH MORTAR CM 285.52 166.68 1,453.09 476.32 2,381.62

411c STONE MASONRY DRESSED UNCOURSED DRY CM 344.69 107.96 459.93 228.14 1,140.72

411d STONE MASONRY DRESSED UNCOURSED WITH MORTAR CM 405.59 166.68 1,497.31 517.39 2,586.97

Page 70
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Dera
Dera Ismail
Ismail Khan
Khan District Code: 12

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

411g ROLL POINTING SM 66.04 11.74 43.75 30.38 151.91

412a STONE MASONRY DRESSED COURSED WITH MORTAR CM 544.80 264.08 1,402.50 552.84 2,764.22

501a R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 310 mm M 206.90 437.48 643.39 321.95 1,609.73

501b R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 380 mm M 200.33 577.19 834.17 402.92 2,014.61

501c R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 460 mm M 198.36 935.96 1,069.85 551.04 2,755.22

501d R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 610 mm M 206.44 1,146.39 1,598.23 737.76 3,688.82

501e R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 760 mm M 237.27 1,078.41 2,297.87 903.39 4,516.94

501f R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 910 mm M 294.10 1,331.30 3,614.54 1,309.99 6,549.93

501g R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1070 mm M 380.61 1,481.41 4,680.50 1,635.63 8,178.14

501h R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1220 mm M 447.26 1,798.85 5,964.68 2,052.70 10,263.48

501i R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1520 mm M 529.40 2,098.66 9,213.95 2,960.50 14,802.52

501j R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 310 mm M 206.90 507.33 722.10 359.08 1,795.42

501k R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 380 mm M 200.33 577.19 852.99 407.63 2,038.14

501l R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 460 mm M 192.49 935.96 1,044.43 543.22 2,716.10

501m R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 610 mm M 206.44 1,146.39 1,743.69 774.13 3,870.65

501n R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 760 mm M 237.27 1,078.41 3,316.03 1,157.93 5,789.65

501o R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 910 mm M 294.10 1,331.30 4,871.85 1,624.31 8,121.57

501p R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1070 mm M 380.61 1,481.41 6,808.93 2,167.74 10,838.68

501q R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1220 mm M 447.26 1,798.85 9,234.95 2,870.27 14,351.33

501r R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1520 mm M 529.40 2,098.66 12,992.82 3,905.22 19,526.09

502a GRANULAR MATERIAL IN BED TO CONCRETE PIPE CM 83.73 118.93 380.62 145.82 729.09
CULVERT

502b CONCRETE CLASS "B" IN BEDDING AND ENCASEMENT OF CM 760.04 612.95 3,420.65 1,198.41 5,992.04
CONCRETE PIPE CULVERT

507a STEEL WIRE MESH FOR GABIONS KG 5.15 - 109.50 28.66 143.32

507b ROCK FILL IN GABIONS CM 87.73 - 388.21 118.98 594.92

508a BRICK PAVING (SINGLE COURSE) SM 101.65 32.70 233.08 91.86 459.29

508b BRICK PAVING (DOUBLE COURSE) SM 181.69 32.70 462.34 169.18 845.92

509a RIP RAP CLASS "A" CM 443.44 - 331.95 193.85 969.24

509b RIP RAP CLASS "B" CM 426.45 - 329.29 188.94 944.68

509c RIP RAP CLASS "C" CM 429.03 - 331.95 190.25 951.23

Page 71
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Dera
Dera Ismail
Ismail Khan
Khan District Code: 12

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

509d GROUTED RIP RAP CLASS "A" CM 540.44 102.14 1,724.93 591.88 2,959.39

509e GROUTED RIP RAP CLASS "B" CM 520.74 81.72 1,577.58 545.01 2,725.05

509f GROUTED RIP RAP CLASS "C" CM 514.00 68.10 1,621.80 550.97 2,754.87

509g REINFORCED CONCRETE SLOPE PROTECTION (WITHOUT CM 753.62 353.02 3,992.64 1,274.82 6,374.10
REINFORCEMENT)

509h FILTER LAYER OF GRANULAR MATERIAL CM 43.27 191.97 411.50 161.69 808.43

510 DISMANTLING OF STRUCTURE AND OBSTRUCTIONS CM 108.10 390.69 - 124.70 623.49

511a1 DRY STONE PITCHING (15-20 cm Thick) SM 140.41 67.48 53.94 65.46 327.28

511a2 DRY STONE PITCHING (21-25 cm Thick) SM 179.72 86.37 69.05 83.78 418.92

511b1 GROUTED STONE PITCHING (15-20 cm Thick) SM 228.43 180.32 361.65 192.60 963.01

511b2 GROUTED STONE PITCHING (21-25 cm Thick) SM 285.54 225.40 452.06 240.75 1,203.76

601ai CONCRETE KERB IN PLACE NEW JERSY BARRIER FOR M 277.04 572.25 2,136.06 746.34 3,731.68
MEDIAN (DOUBLE FACE)

601di PRECAST REINFORCED CONCRETE KERB NEW JERSY M 929.05 670.54 3,980.50 1,395.02 6,975.12
BARRIER FOR MEDIAN (DOUBLE FACE)

601dii PRECAST KERB IN CONCRETE CLASS A-1 OF SIZE 450 X 150 MM M 134.43 90.27 414.37 159.77 798.83
INCLUDING CONCRETE BEDDING & HAUNCHING

603 BRICK EDGING M 8.19 - 36.48 11.17 55.83

604a METAL GUARD RAIL M 19.19 70.84 1,579.36 417.35 2,086.74

604b METAL GUARD RAIL END PIECES EACH 26.15 - 1,197.58 305.93 1,529.66

604d STEEL POST OF METAL GUARD RAIL EACH 89.55 976.73 3,776.31 1,210.65 6,053.23

605a CONCRETE BEAM GUARD RAIL M 69.11 30.82 586.17 171.53 857.64

605c CONCRETE POST FOR GUARD RAIL M 84.86 27.36 585.03 174.31 871.56

607a TRAFFIC ROAD SIGN CATEGORY 1 EACH 216.37 255.15 6,437.77 1,727.32 8,636.61

607b TRAFFIC ROAD SIGN CATEGORY 2 EACH 66.12 382.72 9,235.23 2,421.02 12,105.09

607c TRAFFIC ROAD SIGN CATEGORY 3 (a) EACH 216.37 541.89 11,848.47 3,151.68 15,758.41

607d TRAFFIC ROAD SIGN CATEGORY 3 (b) EACH 691.81 598.64 20,906.45 5,549.23 27,746.13

607e TRAFFIC ROAD SIGN CATEGORY 3 (c) SM 138.36 119.73 9,208.66 2,366.69 11,833.44

607f ADDITIONAL PANEL SIZE 60 X 30 cm EACH 283.68 - 1,306.05 397.43 1,987.16

607g ADDITIONAL PANEL SIZE 90 X 30 cm EACH 283.68 - 1,959.07 560.69 2,803.44

608b1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.57 5.86 16.18 6.15 30.77
LINES OF 15 cm WIDTH

608b2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.86 4.03 39.87 11.19 55.95
LINES OF 15 cm WIDTH

608c1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.57 5.86 21.59 7.51 37.53
LINES OF 20 cm WIDTH

Page 72
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Dera
Dera Ismail
Ismail Khan
Khan District Code: 12

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

608c2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.86 4.03 53.18 14.52 72.58
LINES OF 20 cm WIDTH

608d1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 74.98 5.22 156.37 59.14 295.71
4.0 M ARROWS

608d2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR 4.0 EACH 74.98 9.98 502.46 146.85 734.27
M ARROWS

608h1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.21 8.59 22.50 8.58 42.88
OF 15 cm WIDTH

608h2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.21 9.63 67.50 20.09 100.44
OF 15 cm WIDTH

608i1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.21 6.95 30.00 10.04 50.20
OF 20 cm WIDTH

608i2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.21 9.63 90.01 25.71 128.56
OF 20 cm WIDTH

608j1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR 4.0 M EACH 74.98 3.73 217.23 73.98 369.92
ARROWS

608j2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR 4.0 M EACH 74.98 7.90 851.20 233.52 1,167.59
ARROWS

608n1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 62.45 3.73 104.25 42.61 213.03
STOP

608n2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR EACH 62.45 7.90 335.48 101.46 507.29
STOP

608n3 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR STOP EACH 62.45 3.73 144.82 52.75 263.75

608n4 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR STOP EACH 62.45 7.90 568.32 159.67 798.34

609c REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 8.86 81.62 193.80 71.07 355.35
SINGLE)

609d REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 8.86 81.62 233.80 81.07 405.34
DOUBLE)

610b RIGHT OF WAY MARKER EACH 94.95 121.33 293.84 127.53 637.65

610c KILOMETRE POST (0.610 X 0.114 X 1.5 M) EACH 588.53 976.31 1,965.01 882.46 4,412.30

610d TEN KILOMETRE POST EACH 1,135.30 1,952.61 4,327.27 1,853.80 9,268.98

611a CHAIN LINK WIRE FABRIC FENCING 1500 MM HEIGHT M 129.01 91.00 944.66 291.17 1,455.84
WITH PRECAST PRESTRESSED R.C.C. POST

Page 73
.

Page 74
NATIONAL HIGHWAY AUTHORITY

COMPOSITE SCHEDULE OF RATES


January - 2009

DIR
(15)

Shabir Associates
Quantity Surveying & Construction Cost Consultants

Page 75
.

Page 76
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Dir
Dir District Code: 15

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

101 CLEARING AND GRUBBING SM 0.78 11.11 - 2.97 14.87

102a REMOVAL OF TREES 150 - 300 mm GIRTH EACH 7.89 190.65 1.28 49.96 249.79

102b REMOVAL OF TREES 301 - 600 mm GIRTH EACH 22.57 502.19 2.89 131.91 659.57

102c REMOVAL OF TREES 601 mm OR OVER GIRTH EACH 90.30 2,008.78 11.56 527.66 2,638.29

103 STRIPPING CM 2.76 102.54 - 26.32 131.62

104 COMPACTION OF NATURAL GROUND SM 0.39 10.90 0.84 3.03 15.17

106a EXCAVATE UNSUITABLE COMMON MATERIAL CM 4.93 149.33 - 38.57 192.83

106bi EXCAVATE UNSUITABLE HARD ROCK MATERIAL CM 136.18 347.93 55.90 135.00 675.01

106bii EXCAVATE UNSUITABLE MEDIUM ROCK MATERIAL CM 18.53 371.79 - 97.58 487.90

106biii EXCAVATE UNSUITABLE SOFT ROCK MATERIAL CM 12.13 288.63 - 75.19 375.95

106c EXCAVATE SURPLUS COMMON MATERIAL CM 4.03 132.30 - 34.08 170.41

106di EXCAVATE SURPLUS HARD ROCK MATERIAL CM 136.18 347.93 55.90 135.00 675.01

106dii EXCAVATE SURPLUS MEDIUM ROCK MATERIAL CM 21.66 347.63 - 92.32 461.62

106diii EXCAVATE SURPLUS SOFT ROCK MATERIAL CM 9.36 290.32 - 74.92 374.59

107a STRUCTURAL EXCAVATION IN COMMON MATERIAL CM 7.93 151.36 0.42 39.93 199.64

107b STRUCTURAL EXCAVATION IN COMMON MATERIAL BELOW CM 70.05 315.83 77.89 115.94 579.70
WATER LEVEL

107ci STRUCTURAL EXCAVATION IN HARD ROCK MATERIAL CM 120.34 469.72 37.27 156.83 784.15

107cii STRUCTURAL EXCAVATION IN MEDIUM ROCK MATERIAL CM 101.56 321.79 - 105.84 529.18

107ciii STRUCTURAL EXCAVATION IN SOFT ROCK MATERIAL CM 61.89 262.75 - 81.16 405.80

107d GRANULAR BACK FILL CM 37.08 150.85 441.87 157.45 787.25

107e COMMON BACK FILL CM 27.39 69.12 5.60 25.53 127.64

108a FORMATION OF EMBANKMENT FROM ROADWAY CM 7.40 192.18 5.60 51.30 256.48
EXCAVATION IN COMMON MATERIAL

108bi FORMATION OF EMBANKMENT FROM ROADWAY CM 21.75 530.73 59.45 152.98 764.91
EXCAVATION IN HARD ROCK MATERIAL

108bii FORMATION OF EMBANKMENT FROM ROADWAY CM 16.31 458.38 2.66 119.34 596.69
EXCAVATION IN MEDIUM ROCK MATERIAL

108biii FORMATION OF EMBANKMENT FROM ROADWAY CM 14.50 406.28 - 105.19 525.97


EXCAVATION IN SOFT ROCK MATERIAL

108c FORMATION OF EMBANKMENT FROM BORROW CM 8.47 195.20 8.73 53.10 265.51
EXCAVATION IN COMMON MATERIAL

108d FORMATION OF EMBANKMENT FROM STRUCTURAL CM 6.68 83.95 5.60 24.06 120.29
EXCAVATION IN COMMON MATERIAL

108e FORMATION OF EMBANKMENT FROM STRUCTURAL CM 15.59 121.32 3.33 35.06 175.30
EXCAVATION IN ANY TYPE OF ROCK MATERIAL

109a SUB GRADE PREPARATION IN EARTH CUT SM 1.50 30.07 1.60 8.29 41.47

Page 77
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Dir
Dir District Code: 15

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

109bi SUB GRADE PREPARATION IN EXISTING ROAD WITHOUT SM 1.09 20.03 0.85 5.49 27.47
ANY FILL

110 IMPROVED SUB-GRADE CM 10.77 132.02 62.52 51.33 256.64

114a DRESSING OF BERM WITHOUT EXTRA MATERIAL SM 0.92 16.79 0.87 4.65 23.23

114b DRESSING OF BERM WITH EXTRA BORROW MATERIAL SM 1.36 17.13 0.99 4.87 24.34

201 GRANULAR SUB-BASE CM 8.35 272.91 488.73 192.50 962.49

202 AGGREGATE BASE CM 9.78 349.40 799.18 289.59 1,447.96

203a ASPHALTIC BASE COURSE PLANT MIX (CLASS "A") CM 75.50 1,615.88 6,628.48 2,079.96 10,399.82

203b ASPHALTIC BASE COURSE PLANT MIX (CLASS "B") CM 78.02 1,615.88 7,091.14 2,196.26 10,981.29

203c ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "A") CM 83.51 1,687.69 6,617.69 2,097.22 10,486.12

203d ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "B") CM 83.51 1,681.30 7,250.21 2,253.75 11,268.77

204b CEMENT STABILIZED BASE CM 29.94 608.94 1,164.25 450.78 2,253.92

204d LIQUID ASPHALT FOR CURING SEAL, TYPE MC-250 TON 254.73 979.45 57,998.83 14,808.25 74,041.26

204e EMULSIFIED ASPHALT FOR CURING SEAL, TYPE SS-1 TON 254.73 979.45 56,310.23 14,386.10 71,930.52

205a GRADED CRUSHED AGGREGATE CRACK-RELIEF LAYER CM 99.46 120.69 1,055.84 319.00 1,594.99

205b ASPHALTIC OPEN-GRADED PLANT MIX CRACK-RELIEF CM 154.09 2,608.60 6,271.64 2,258.58 11,292.91
LAYER

206b WATER BOUND MACADAM BASE WITH COARSE CM 109.53 135.11 813.69 264.58 1,322.91
AGGREGATE CLASS B

207a DEEP PATCHING (0-15 cm) SM 1.83 48.19 1.34 12.84 64.20

207b DEEP PATCHING (16-30 cm) SM 1.83 42.45 1.34 11.41 57.03

208 REINSTATEMENT OF ROAD SURFACE SM 1.95 61.10 0.60 15.91 79.56

209a BREAKING OF EXISTING ROAD PAVEMENT STRUCTURE CM 2.26 118.35 0.73 30.34 151.68

209b SCARIFICATION OF EXISTING ROAD PAVEMENT SM 0.45 23.67 0.15 6.07 30.34

302a CUT-BACK ASPHALT FOR BITUMINOUS PRIME COAT SM 0.31 1.68 41.16 10.79 53.95

302b EMULSIFIED ASPHALT FOR BITUMINOUS PRIME COAT SM 0.30 1.68 45.95 11.98 59.92

303a CUT-BACK ASPHALT FOR BITUMINOUS TACK COAT SM 0.12 0.62 17.23 4.49 22.47

303b EMULSIFIED ASPHALT FOR BITUMINOUS TACK COAT SM 0.12 0.62 20.10 5.21 26.05

304a SINGLE SURFACE TREATMENT SM 0.81 8.10 82.36 22.82 114.09

304b DOUBLE SURFACE TREATMENT SM 1.18 15.14 159.87 44.05 220.24

304c TRIPLE SURFACE TREATMENT SM 1.98 21.33 182.44 51.44 257.20

304d SEAL COAT SM 0.75 4.41 58.03 15.80 78.99

Page 78
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Dir
Dir District Code: 15

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

305a ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 70.81 1,593.58 7,780.91 2,361.33 11,806.63
"A")

305b ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 70.81 1,538.91 8,401.79 2,502.88 12,514.38
"B")

307a DENSE GRADED HOT BIT-MAC CM 173.89 406.36 6,478.55 1,764.70 8,823.50

307b OPEN GRADED HOT BIT-MAC CM 173.89 406.36 6,296.47 1,719.18 8,595.90

308a RECYCLING OF ASPHALT CONCRETE (0 - 60 mm THICK) CM 29.84 631.99 2,260.77 730.65 3,653.25

308b BITUMEN BINDER GRADE (40 - 50, 60 - 70, 80 - 100) TON 27.59 696.25 49,560.77 12,571.15 62,855.77

309a COLD MILLING, 0 - 30 mm SM 1.00 26.74 9.28 9.26 46.29

309b COLD MILLING, 0 - 50 mm SM 1.67 44.57 15.47 15.43 77.15

309c COLD MILLING, 0 - 70 mm SM 2.51 66.86 23.21 23.14 115.72

401a1i CONCRETE CLASS "A1" (Underground) CM 571.24 1,112.93 4,231.39 1,478.89 7,394.46

401a1ii CONCRETE CLASS "A1" (On ground) CM 571.24 1,112.93 4,522.74 1,551.73 7,758.64

401a1iii CONCRETE CLASS "A1" (Elevated) CM 571.24 1,112.93 5,105.43 1,697.40 8,487.01

401a2i CONCRETE CLASS "A2" (Underground) CM 571.24 1,112.93 4,628.29 1,578.12 7,890.58

401a2ii CONCRETE CLASS "A2" (On ground) CM 571.24 1,112.93 4,919.64 1,650.95 8,254.77

401a2iii CONCRETE CLASS "A2" (Elevated) CM 571.24 1,112.93 5,502.33 1,796.63 8,983.13

401a3i CONCRETE CLASS "A3" (Underground) CM 571.24 1,112.93 5,025.19 1,677.34 8,386.71

401a3ii CONCRETE CLASS "A3" (On ground) CM 571.24 1,112.93 5,316.54 1,750.18 8,750.89

401a3iii CONCRETE CLASS "A3" (Elevated) CM 571.24 1,112.93 5,899.23 1,895.85 9,479.26

401b CONCRETE CLASS "B" CM 725.53 846.23 3,429.15 1,250.22 6,251.12

401ci CONCRETE CLASS "C" (Underground) CM 565.44 525.57 3,779.22 1,217.56 6,087.80

401cii CONCRETE CLASS "C" (On ground) CM 565.44 525.57 3,903.48 1,248.62 6,243.12

401ciii CONCRETE CLASS "C" (Elevated) CM 565.44 525.57 4,152.00 1,310.75 6,553.77

401d CONCRETE CLASS "D1" CM 898.65 1,328.84 5,631.64 1,964.78 9,823.91

401e CONCRETE CLASS "Y" CM 1,257.67 525.57 5,049.93 1,708.29 8,541.47

401f LEAN CONCRETE CM 469.75 532.89 2,663.99 916.66 4,583.29

401gi(1) PRECAST CONCRETE CLASS "A-1" CM 1,920.24 994.51 5,289.53 2,051.07 10,255.34

401gi(3) PRECAST CONCRETE CLASS "A-3" CM 1,920.24 994.51 6,083.33 2,249.52 11,247.59

401gii PRECAST CONCRETE CLASS "B" CM 1,920.24 994.51 5,036.60 1,987.84 9,939.18

401giii(1) PRECAST CONCRETE CLASS "D1" CM 1,920.24 994.51 6,480.23 2,348.74 11,743.72

Page 79
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Dir
Dir District Code: 15

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

401giii(2) PRECAST CONCRETE CLASS "D2" CM 1,920.24 994.51 6,877.13 2,447.97 12,239.84

401giii(3) PRECAST CONCRETE CLASS "D3" CM 1,920.24 994.51 7,274.03 2,547.19 12,735.97

404a REINFORCEMENT AS PER AASHTO M. 31 GRADE 40 TON 1,943.00 820.55 64,551.90 16,828.86 84,144.31

404b REINFORCEMENT AS PER AASHTO M. 31 GRADE 60 TON 1,943.00 820.55 72,269.40 18,758.24 93,791.18

404h REINFORCEMENT (STRUCTURAL SHAPES) AS PER ASTM-A- TON 1,558.72 5,663.50 59,801.63 16,755.96 83,779.82
36

405a PRE-STRESSING WIRE STRAND 3/8" - 1/2" DIA COMPLETE IN TON 2,724.93 16,442.00 140,608.98 39,943.98 199,719.89
ALL RESPECT

405b LAUNCHING OF GIRDER TON 63.87 559.15 - 155.75 778.77

406a PREMOULDED JOINT FILLER 12 mm THICK WITH SM 124.47 - 320.40 111.22 556.08
BITUMASTIC JOINT SEAL

406b NEOPRENE RUBBER JOINT FILLER 12 mm THICK WITH SM 124.47 - 319.53 111.00 555.00
BITUMASTIC JOINT SEAL

406c STEEL EXPANSION JOINTS KG 11.41 27.72 96.62 33.94 169.68

406d WATER STOPS 6" SIZE M 106.62 - 496.76 150.85 754.23

406e ELASTOMERIC BEARING PADS (ACCORDING TO SIZE AND ccm 0.02 - 2.23 0.56 2.81
THICKNESS)

406f ASPHALT FELT (3 PLY) SM 47.05 - 3,195.61 810.67 4,053.33

406g STEEL OR METAL BEARING DEVICES KG 22.20 73.17 124.35 54.93 274.65

407d1 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 352.65 1,736.74 946.99 759.09 3,795.47
(BORING ONLY) IN NORMAL SOIL

407d2 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 528.97 2,605.12 1,420.48 1,138.64 5,693.21
(BORING ONLY) IN GRAVEL STRATA

407d3 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 528.97 2,605.12 1,050.89 1,046.24 5,231.22
ONLY) IN NORMAL SOIL

407d4 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 881.62 4,341.86 1,239.04 1,615.63 8,078.15
ONLY) IN GRAVEL STRATA

407d5 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 755.67 5,129.19 1,431.62 1,829.12 9,145.60
ONLY) IN NORMAL SOIL

407d6 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 1,322.43 7,255.27 1,570.32 2,537.00 12,685.02
ONLY) IN GRAVEL SOIL

407h PILE LOAD TEST UP TO 120 TON EACH 24,005.50 48,057.77 105,786.64 44,462.48 222,312.39

407i PILE LOAD TEST UP TO 240 TON EACH 44,686.18 48,057.77 211,573.28 76,079.31 380,396.53

407j PILE LOAD TEST UP TO 360 TON EACH 65,366.86 52,697.80 317,359.92 108,856.14 544,280.72

407k CONFIRMATORY BORING (NX SIZE) M 203.10 1,661.12 6.68 467.73 2,338.64

410 BRICK WORK CM 379.42 296.86 3,309.18 996.37 4,981.83

411a STONE MASONRY RANDOM DRY CM 316.53 113.36 484.88 228.69 1,143.47

411b STONE MASONRY RANDOM WITH MORTAR CM 343.07 175.02 1,611.88 532.49 2,662.45

411c STONE MASONRY DRESSED UNCOURSED DRY CM 415.56 113.36 541.62 267.64 1,338.18

411d STONE MASONRY DRESSED UNCOURSED WITH MORTAR CM 491.62 175.02 1,667.88 583.63 2,918.14

Page 80
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Dir
Dir District Code: 15

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

411g ROLL POINTING SM 81.94 12.33 46.76 35.26 176.29

412a STONE MASONRY DRESSED COURSED WITH MORTAR CM 663.15 277.29 1,568.33 627.19 3,135.96

501a R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 310 mm M 248.78 472.48 696.45 354.43 1,772.15

501b R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 380 mm M 242.16 623.36 902.81 442.08 2,210.41

501c R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 460 mm M 236.38 1,010.84 1,157.66 601.22 3,006.09

501d R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 610 mm M 247.12 1,238.10 1,728.68 803.47 4,017.37

501e R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 760 mm M 283.10 1,164.69 2,484.29 983.02 4,915.10

501f R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 910 mm M 350.67 1,437.80 3,907.46 1,423.98 7,119.91

501g R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1070 mm M 453.81 1,599.92 5,058.67 1,778.10 8,890.50

501h R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1220 mm M 531.56 1,942.76 6,446.39 2,230.18 11,150.88

501i R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1520 mm M 633.15 2,266.55 9,956.36 3,214.02 16,070.08

501j R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 310 mm M 248.78 547.92 783.04 394.94 1,974.68

501k R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 380 mm M 242.16 623.36 923.13 447.16 2,235.82

501l R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 460 mm M 230.53 1,010.84 1,130.21 592.89 2,964.46

501m R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 610 mm M 247.12 1,238.10 1,885.20 842.60 4,213.02

501n R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 760 mm M 283.10 1,164.69 3,584.20 1,258.00 6,289.98

501o R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 910 mm M 350.67 1,437.80 5,265.35 1,763.46 8,817.28

501p R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1070 mm M 453.81 1,599.92 7,357.37 2,352.78 11,763.88

501q R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1220 mm M 531.56 1,942.76 9,978.28 3,113.15 15,565.75

501r R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1520 mm M 633.15 2,266.55 14,037.53 4,234.31 21,171.54

502a GRANULAR MATERIAL IN BED TO CONCRETE PIPE CM 96.93 128.44 436.56 165.48 827.41
CULVERT

502b CONCRETE CLASS "B" IN BEDDING AND ENCASEMENT OF CM 847.98 661.98 3,905.12 1,353.77 6,768.85
CONCRETE PIPE CULVERT

507a STEEL WIRE MESH FOR GABIONS KG 6.35 - 119.56 31.48 157.39

507b ROCK FILL IN GABIONS CM 103.85 - 419.27 130.78 653.89

508a BRICK PAVING (SINGLE COURSE) SM 126.61 35.32 275.99 109.48 547.40

508b BRICK PAVING (DOUBLE COURSE) SM 228.47 35.32 547.88 202.92 1,014.59

509a RIP RAP CLASS "A" CM 554.89 - 396.35 237.81 1,189.05

509b RIP RAP CLASS "B" CM 534.86 - 393.18 232.01 1,160.04

509c RIP RAP CLASS "C" CM 539.70 - 396.35 234.01 1,170.06

Page 81
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Dir
Dir District Code: 15

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

509d GROUTED RIP RAP CLASS "A" CM 676.55 110.32 1,932.48 679.84 3,399.18

509e GROUTED RIP RAP CLASS "B" CM 654.02 88.25 1,769.75 628.00 3,140.02

509f GROUTED RIP RAP CLASS "C" CM 646.88 73.54 1,818.99 634.85 3,174.27

509g REINFORCED CONCRETE SLOPE PROTECTION (WITHOUT CM 896.07 381.27 4,511.67 1,447.25 7,236.26
REINFORCEMENT)

509h FILTER LAYER OF GRANULAR MATERIAL CM 51.39 207.33 434.53 173.31 866.56

510 DISMANTLING OF STRUCTURE AND OBSTRUCTIONS CM 113.16 421.95 - 133.78 668.89

511a1 DRY STONE PITCHING (15-20 cm Thick) SM 172.54 72.87 64.41 77.46 387.28

511a2 DRY STONE PITCHING (21-25 cm Thick) SM 220.85 93.28 82.44 99.14 495.71

511b1 GROUTED STONE PITCHING (15-20 cm Thick) SM 283.44 194.75 398.78 219.24 1,096.20

511b2 GROUTED STONE PITCHING (21-25 cm Thick) SM 354.30 243.44 498.47 274.05 1,370.25

601ai CONCRETE KERB IN PLACE NEW JERSY BARRIER FOR M 308.92 613.92 2,414.48 834.33 4,171.65
MEDIAN (DOUBLE FACE)

601di PRECAST REINFORCED CONCRETE KERB NEW JERSY M 1,079.33 711.97 4,427.36 1,554.66 7,773.32
BARRIER FOR MEDIAN (DOUBLE FACE)

601dii PRECAST KERB IN CONCRETE CLASS A-1 OF SIZE 450 X 150 MM M 155.77 97.09 467.55 180.10 900.51
INCLUDING CONCRETE BEDDING & HAUNCHING

603 BRICK EDGING M 9.34 - 41.13 12.62 63.09

604a METAL GUARD RAIL M 18.56 72.26 1,610.95 425.44 2,127.21

604b METAL GUARD RAIL END PIECES EACH 24.86 - 1,221.53 311.60 1,557.98

604d STEEL POST OF METAL GUARD RAIL EACH 86.36 996.27 3,851.83 1,233.61 6,168.07

605a CONCRETE BEAM GUARD RAIL M 78.93 31.44 613.11 180.87 904.36

605c CONCRETE POST FOR GUARD RAIL M 96.92 27.91 614.57 184.85 924.25

607a TRAFFIC ROAD SIGN CATEGORY 1 EACH 245.41 260.25 7,001.87 1,876.88 9,384.41

607b TRAFFIC ROAD SIGN CATEGORY 2 EACH 74.54 390.38 9,453.66 2,479.64 12,398.22

607c TRAFFIC ROAD SIGN CATEGORY 3 (a) EACH 245.41 552.72 12,144.23 3,235.59 16,177.95

607d TRAFFIC ROAD SIGN CATEGORY 3 (b) EACH 794.46 610.62 21,406.96 5,703.01 28,515.04

607e TRAFFIC ROAD SIGN CATEGORY 3 (c) SM 158.89 122.12 9,405.08 2,421.52 12,107.62

607f ADDITIONAL PANEL SIZE 60 X 30 cm EACH 321.54 - 1,330.46 413.00 2,065.01

607g ADDITIONAL PANEL SIZE 90 X 30 cm EACH 321.54 - 1,995.70 579.31 2,896.55

608b1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.79 5.98 16.49 6.31 31.57
LINES OF 15 cm WIDTH

608b2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.93 4.11 40.53 11.39 56.96
LINES OF 15 cm WIDTH

608c1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.79 5.98 22.01 7.69 38.47
LINES OF 20 cm WIDTH

Page 82
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Dir
Dir District Code: 15

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

608c2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.93 4.11 54.06 14.77 73.87
LINES OF 20 cm WIDTH

608d1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 82.49 5.32 159.36 61.79 308.97
4.0 M ARROWS

608d2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR 4.0 EACH 82.49 10.18 510.75 150.86 754.28
M ARROWS

608h1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.49 8.76 22.93 8.80 43.98
OF 15 cm WIDTH

608h2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.49 9.82 68.85 20.54 102.71
OF 15 cm WIDTH

608i1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.49 7.09 30.58 10.29 51.45
OF 20 cm WIDTH

608i2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.49 9.82 91.81 26.28 131.40
OF 20 cm WIDTH

608j1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR 4.0 M EACH 82.49 3.80 221.44 76.93 384.66
ARROWS

608j2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR 4.0 M EACH 82.49 8.06 868.22 239.69 1,198.46
ARROWS

608n1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 68.43 3.80 106.24 44.62 223.09
STOP

608n2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR EACH 68.43 8.06 341.02 104.37 521.87
STOP

608n3 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR STOP EACH 68.43 3.80 147.63 54.96 274.82

608n4 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR STOP EACH 68.43 8.06 579.69 164.04 820.22

609c REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 9.84 83.25 197.74 72.71 363.54
SINGLE)

609d REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 9.85 83.25 238.54 82.91 414.54
DOUBLE)

610b RIGHT OF WAY MARKER EACH 107.35 123.75 311.17 135.57 677.83

610c KILOMETRE POST (0.610 X 0.114 X 1.5 M) EACH 673.03 995.83 2,104.23 943.27 4,716.36

610d TEN KILOMETRE POST EACH 1,289.81 1,991.66 4,612.08 1,973.39 9,866.95

611a CHAIN LINK WIRE FABRIC FENCING 1500 MM HEIGHT M 141.09 95.67 989.87 306.66 1,533.30
WITH PRECAST PRESTRESSED R.C.C. POST

Page 83
.

Page 84
NATIONAL HIGHWAY AUTHORITY

COMPOSITE SCHEDULE OF RATES


January - 2009

HARIPUR HAZARA
(20-B)

Shabir Associates
Quantity Surveying & Construction Cost Consultants

Page 85
.

Page 86
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Haripur
Haripur Hazara
Hazara District Code: 20-B

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

101 CLEARING AND GRUBBING SM 0.73 10.10 - 2.71 13.54

102a REMOVAL OF TREES 150 - 300 mm GIRTH EACH 7.68 173.32 1.17 45.54 227.71

102b REMOVAL OF TREES 301 - 600 mm GIRTH EACH 21.41 456.54 2.63 120.14 600.72

102c REMOVAL OF TREES 601 mm OR OVER GIRTH EACH 85.64 1,826.16 10.51 480.58 2,402.89

103 STRIPPING CM 2.72 93.22 - 23.98 119.92

104 COMPACTION OF NATURAL GROUND SM 0.40 9.91 0.76 2.77 13.84

106a EXCAVATE UNSUITABLE COMMON MATERIAL CM 5.63 135.76 - 35.35 176.73

106bi EXCAVATE UNSUITABLE HARD ROCK MATERIAL CM 141.07 316.30 50.82 127.05 635.23

106bii EXCAVATE UNSUITABLE MEDIUM ROCK MATERIAL CM 18.09 337.99 - 89.02 445.10

106biii EXCAVATE UNSUITABLE SOFT ROCK MATERIAL CM 11.92 262.40 - 68.58 342.89

106c EXCAVATE SURPLUS COMMON MATERIAL CM 4.61 120.27 - 31.22 156.09

106di EXCAVATE SURPLUS HARD ROCK MATERIAL CM 141.07 316.30 50.82 127.05 635.23

106dii EXCAVATE SURPLUS MEDIUM ROCK MATERIAL CM 22.55 316.03 - 84.64 423.22

106diii EXCAVATE SURPLUS SOFT ROCK MATERIAL CM 9.15 263.92 - 68.27 341.34

107a STRUCTURAL EXCAVATION IN COMMON MATERIAL CM 8.48 137.60 0.38 36.62 183.08

107b STRUCTURAL EXCAVATION IN COMMON MATERIAL BELOW CM 66.07 287.11 70.80 106.00 529.98
WATER LEVEL

107ci STRUCTURAL EXCAVATION IN HARD ROCK MATERIAL CM 125.25 427.01 33.88 146.54 732.69

107cii STRUCTURAL EXCAVATION IN MEDIUM ROCK MATERIAL CM 104.76 292.53 - 99.32 496.62

107ciii STRUCTURAL EXCAVATION IN SOFT ROCK MATERIAL CM 64.42 238.86 - 75.82 379.10

107d GRANULAR BACK FILL CM 37.04 137.14 407.71 145.47 727.35

107e COMMON BACK FILL CM 25.46 62.84 5.09 23.35 116.74

108a FORMATION OF EMBANKMENT FROM ROADWAY CM 7.48 174.71 5.09 46.82 234.10
EXCAVATION IN COMMON MATERIAL

108bi FORMATION OF EMBANKMENT FROM ROADWAY CM 21.53 482.48 54.04 139.51 697.57
EXCAVATION IN HARD ROCK MATERIAL

108bii FORMATION OF EMBANKMENT FROM ROADWAY CM 16.15 416.71 2.42 108.82 544.10
EXCAVATION IN MEDIUM ROCK MATERIAL

108biii FORMATION OF EMBANKMENT FROM ROADWAY CM 14.36 369.34 - 95.92 479.62


EXCAVATION IN SOFT ROCK MATERIAL

108c FORMATION OF EMBANKMENT FROM BORROW CM 8.40 177.46 7.94 48.45 242.24
EXCAVATION IN COMMON MATERIAL

108d FORMATION OF EMBANKMENT FROM STRUCTURAL CM 6.68 76.32 5.09 22.02 110.12
EXCAVATION IN COMMON MATERIAL

108e FORMATION OF EMBANKMENT FROM STRUCTURAL CM 15.21 110.29 3.03 32.13 160.65
EXCAVATION IN ANY TYPE OF ROCK MATERIAL

109a SUB GRADE PREPARATION IN EARTH CUT SM 1.52 27.34 1.46 7.58 37.90

Page 87
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Haripur
Haripur Hazara
Hazara District Code: 20-B

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

109bi SUB GRADE PREPARATION IN EXISTING ROAD WITHOUT SM 1.11 18.21 0.77 5.02 25.12
ANY FILL

110 IMPROVED SUB-GRADE CM 10.66 120.02 55.62 46.57 232.87

114a DRESSING OF BERM WITHOUT EXTRA MATERIAL SM 0.91 15.26 0.79 4.24 21.21

114b DRESSING OF BERM WITH EXTRA BORROW MATERIAL SM 1.32 15.57 0.90 4.45 22.24

201 GRANULAR SUB-BASE CM 8.58 255.06 393.91 164.39 821.94

202 AGGREGATE BASE CM 10.43 326.54 708.80 261.44 1,307.22

203a ASPHALTIC BASE COURSE PLANT MIX (CLASS "A") CM 72.36 1,510.17 5,637.85 1,805.09 9,025.47

203b ASPHALTIC BASE COURSE PLANT MIX (CLASS "B") CM 75.21 1,510.17 6,055.75 1,910.28 9,551.41

203c ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "A") CM 80.47 1,577.28 5,628.18 1,821.48 9,107.42

203d ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "B") CM 80.47 1,571.31 6,198.57 1,962.59 9,812.93

204b CEMENT STABILIZED BASE CM 31.27 569.10 828.47 357.21 1,786.07

204d LIQUID ASPHALT FOR CURING SEAL, TYPE MC-250 TON 269.62 915.38 50,344.29 12,882.32 64,411.61

204e EMULSIFIED ASPHALT FOR CURING SEAL, TYPE SS-1 TON 269.62 915.38 48,766.16 12,487.79 62,438.95

205a GRADED CRUSHED AGGREGATE CRACK-RELIEF LAYER CM 91.35 112.80 833.93 259.52 1,297.60

205b ASPHALTIC OPEN-GRADED PLANT MIX CRACK-RELIEF CM 151.71 2,437.94 5,399.57 1,997.30 9,986.52
LAYER

206b WATER BOUND MACADAM BASE WITH COARSE CM 100.10 126.27 737.36 240.93 1,204.67
AGGREGATE CLASS B

207a DEEP PATCHING (0-15 cm) SM 1.87 45.04 1.26 12.04 60.21

207b DEEP PATCHING (16-30 cm) SM 1.87 39.67 1.26 10.70 53.50

208 REINSTATEMENT OF ROAD SURFACE SM 2.06 57.10 0.56 14.93 74.66

209a BREAKING OF EXISTING ROAD PAVEMENT STRUCTURE CM 2.47 110.61 0.68 28.44 142.20

209b SCARIFICATION OF EXISTING ROAD PAVEMENT SM 0.49 22.12 0.14 5.69 28.44

302a CUT-BACK ASPHALT FOR BITUMINOUS PRIME COAT SM 0.33 1.57 35.73 9.41 47.04

302b EMULSIFIED ASPHALT FOR BITUMINOUS PRIME COAT SM 0.32 1.57 39.89 10.45 52.23

303a CUT-BACK ASPHALT FOR BITUMINOUS TACK COAT SM 0.13 0.58 14.95 3.92 19.58

303b EMULSIFIED ASPHALT FOR BITUMINOUS TACK COAT SM 0.13 0.58 17.45 4.54 22.70

304a SINGLE SURFACE TREATMENT SM 0.87 7.57 70.32 19.69 98.46

304b DOUBLE SURFACE TREATMENT SM 1.26 14.15 135.86 37.82 189.10

304c TRIPLE SURFACE TREATMENT SM 2.13 19.94 154.89 44.24 221.20

304d SEAL COAT SM 0.82 4.12 49.75 13.67 68.36

Page 88
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Haripur
Haripur Hazara
Hazara District Code: 20-B

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

305a ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 69.13 1,489.33 6,628.07 2,046.63 10,233.15
"A")

305b ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 69.13 1,438.23 7,146.65 2,163.50 10,817.51
"B")

307a DENSE GRADED HOT BIT-MAC CM 165.96 379.77 5,431.97 1,494.43 7,472.13

307b OPEN GRADED HOT BIT-MAC CM 165.96 379.77 5,305.64 1,462.84 7,314.22

308a RECYCLING OF ASPHALT CONCRETE (0 - 60 mm THICK) CM 28.58 590.65 1,992.08 652.83 3,264.14

308b BITUMEN BINDER GRADE (40 - 50, 60 - 70, 80 - 100) TON 29.19 650.70 42,343.60 10,755.87 53,779.36

309a COLD MILLING, 0 - 30 mm SM 1.06 24.99 8.68 8.68 43.41

309b COLD MILLING, 0 - 50 mm SM 1.77 41.65 14.46 14.47 72.36

309c COLD MILLING, 0 - 70 mm SM 2.66 62.48 21.69 21.71 108.53

401a1i CONCRETE CLASS "A1" (Underground) CM 536.49 1,059.94 3,830.96 1,356.85 6,784.23

401a1ii CONCRETE CLASS "A1" (On ground) CM 536.49 1,059.94 4,108.43 1,426.21 7,131.07

401a1iii CONCRETE CLASS "A1" (Elevated) CM 536.49 1,059.94 4,663.37 1,564.95 7,824.75

401a2i CONCRETE CLASS "A2" (Underground) CM 536.49 1,059.94 4,208.96 1,451.35 7,256.73

401a2ii CONCRETE CLASS "A2" (On ground) CM 536.49 1,059.94 4,486.43 1,520.71 7,603.57

401a2iii CONCRETE CLASS "A2" (Elevated) CM 536.49 1,059.94 5,041.37 1,659.45 8,297.25

401a3i CONCRETE CLASS "A3" (Underground) CM 536.49 1,059.94 4,586.96 1,545.85 7,729.23

401a3ii CONCRETE CLASS "A3" (On ground) CM 536.49 1,059.94 4,864.43 1,615.21 8,076.07

401a3iii CONCRETE CLASS "A3" (Elevated) CM 536.49 1,059.94 5,419.37 1,753.95 8,769.75

401b CONCRETE CLASS "B" CM 711.09 805.93 3,104.98 1,155.50 5,777.50

401ci CONCRETE CLASS "C" (Underground) CM 524.18 500.55 3,393.06 1,104.45 5,522.23

401cii CONCRETE CLASS "C" (On ground) CM 524.18 500.55 3,511.41 1,134.03 5,670.16

401ciii CONCRETE CLASS "C" (Elevated) CM 524.18 500.55 3,748.09 1,193.20 5,966.02

401d CONCRETE CLASS "D1" CM 818.77 1,265.57 5,186.95 1,817.82 9,089.11

401e CONCRETE CLASS "Y" CM 1,134.72 500.55 4,612.31 1,561.89 7,809.47

401f LEAN CONCRETE CM 441.38 507.52 2,376.86 831.44 4,157.20

401gi(1) PRECAST CONCRETE CLASS "A-1" CM 1,770.55 947.15 4,816.33 1,883.51 9,417.54

401gi(3) PRECAST CONCRETE CLASS "A-3" CM 1,770.55 947.15 5,572.33 2,072.51 10,362.54

401gii PRECAST CONCRETE CLASS "B" CM 1,770.55 947.15 4,622.32 1,835.01 9,175.03

401giii(1) PRECAST CONCRETE CLASS "D1" CM 1,770.55 947.15 5,950.33 2,167.01 10,835.04

Page 89
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Haripur
Haripur Hazara
Hazara District Code: 20-B

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

401giii(2) PRECAST CONCRETE CLASS "D2" CM 1,770.55 947.15 6,328.33 2,261.51 11,307.54

401giii(3) PRECAST CONCRETE CLASS "D3" CM 1,770.55 947.15 6,706.33 2,356.01 11,780.04

404a REINFORCEMENT AS PER AASHTO M. 31 GRADE 40 TON 1,629.06 781.47 59,358.00 15,442.13 77,210.66

404b REINFORCEMENT AS PER AASHTO M. 31 GRADE 60 TON 1,629.06 781.47 66,708.00 17,279.63 86,398.16

404h REINFORCEMENT (STRUCTURAL SHAPES) AS PER ASTM-A- TON 1,280.39 5,393.81 55,550.69 15,556.22 77,781.12
36

405a PRE-STRESSING WIRE STRAND 3/8" - 1/2" DIA COMPLETE IN TON 2,816.57 15,659.05 133,836.01 38,077.91 190,389.53
ALL RESPECT

405b LAUNCHING OF GIRDER TON 65.06 532.52 - 149.40 746.98

406a PREMOULDED JOINT FILLER 12 mm THICK WITH SM 114.51 - 299.99 103.62 518.12
BITUMASTIC JOINT SEAL

406b NEOPRENE RUBBER JOINT FILLER 12 mm THICK WITH SM 114.51 - 299.23 103.44 517.18
BITUMASTIC JOINT SEAL

406c STEEL EXPANSION JOINTS KG 9.30 26.40 90.23 31.48 157.40

406d WATER STOPS 6" SIZE M 96.10 - 472.04 142.03 710.17

406e ELASTOMERIC BEARING PADS (ACCORDING TO SIZE AND ccm 0.02 - 2.12 0.53 2.67
THICKNESS)

406f ASPHALT FELT (3 PLY) SM 45.58 - 2,954.30 749.97 3,749.85

406g STEEL OR METAL BEARING DEVICES KG 20.54 69.68 117.26 51.87 259.36

407d1 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 354.77 1,654.04 898.09 726.73 3,633.63
(BORING ONLY) IN NORMAL SOIL

407d2 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 532.15 2,481.06 1,347.14 1,090.09 5,450.45
(BORING ONLY) IN GRAVEL STRATA

407d3 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 532.15 2,481.06 995.00 1,002.05 5,010.27
ONLY) IN NORMAL SOIL

407d4 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 886.92 4,135.11 1,170.29 1,548.08 7,740.40
ONLY) IN GRAVEL STRATA

407d5 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 760.22 4,884.94 1,347.81 1,748.24 8,741.21
ONLY) IN NORMAL SOIL

407d6 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 1,330.38 6,909.78 1,480.92 2,430.27 12,151.35
ONLY) IN GRAVEL SOIL

407h PILE LOAD TEST UP TO 120 TON EACH 22,545.15 45,769.30 100,541.50 42,213.99 211,069.95

407i PILE LOAD TEST UP TO 240 TON EACH 41,156.52 45,769.30 201,083.00 72,002.21 360,011.03

407j PILE LOAD TEST UP TO 360 TON EACH 59,767.89 50,188.38 301,624.50 102,895.19 514,475.97

407k CONFIRMATORY BORING (NX SIZE) M 194.25 1,582.02 6.37 445.66 2,228.30

410 BRICK WORK CM 355.79 282.72 3,029.04 916.89 4,584.44

411a STONE MASONRY RANDOM DRY CM 297.65 107.96 492.04 224.41 1,122.06

411b STONE MASONRY RANDOM WITH MORTAR CM 322.47 166.68 1,537.17 506.58 2,532.90

411c STONE MASONRY DRESSED UNCOURSED DRY CM 388.65 107.96 548.49 261.27 1,306.37

411d STONE MASONRY DRESSED UNCOURSED WITH MORTAR CM 458.97 166.68 1,599.96 556.40 2,782.01

Page 90
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Haripur
Haripur Hazara
Hazara District Code: 20-B

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

411g ROLL POINTING SM 76.05 11.74 44.06 32.96 164.82

412a STONE MASONRY DRESSED COURSED WITH MORTAR CM 616.14 264.08 1,505.16 596.35 2,981.73

501a R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 310 mm M 229.32 437.48 643.98 327.70 1,638.48

501b R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 380 mm M 221.35 577.19 834.87 408.35 2,041.76

501c R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 460 mm M 220.74 935.96 1,070.67 556.84 2,784.21

501d R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 610 mm M 228.87 1,146.39 1,599.19 743.61 3,718.06

501e R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 760 mm M 263.94 1,078.41 2,298.83 910.30 4,551.48

501f R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 910 mm M 329.16 1,331.30 3,615.93 1,319.10 6,595.49

501g R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1070 mm M 425.97 1,481.41 4,681.88 1,647.31 8,236.57

501h R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1220 mm M 499.52 1,798.85 5,966.36 2,066.18 10,330.91

501i R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1520 mm M 595.70 2,098.66 9,215.91 2,977.57 14,887.84

501j R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 310 mm M 229.32 507.33 723.27 364.98 1,824.91

501k R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 380 mm M 221.35 577.19 853.69 413.06 2,065.29

501l R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 460 mm M 216.08 935.96 1,045.25 549.32 2,746.62

501m R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 610 mm M 228.87 1,146.39 1,744.43 779.92 3,899.62

501n R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 760 mm M 263.94 1,078.41 3,317.10 1,164.86 5,824.32

501o R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 910 mm M 329.16 1,331.30 4,873.24 1,633.42 8,167.12

501p R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1070 mm M 425.97 1,481.41 6,810.31 2,179.42 10,897.11

501q R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1220 mm M 499.52 1,798.85 9,236.63 2,883.75 14,418.76

501r R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1520 mm M 595.70 2,098.66 12,994.77 3,922.28 19,611.42

502a GRANULAR MATERIAL IN BED TO CONCRETE PIPE CM 93.39 118.93 440.73 163.26 816.32
CULVERT

502b CONCRETE CLASS "B" IN BEDDING AND ENCASEMENT OF CM 787.63 612.95 3,454.98 1,213.89 6,069.44
CONCRETE PIPE CULVERT

507a STEEL WIRE MESH FOR GABIONS KG 5.70 - 109.41 28.78 143.89

507b ROCK FILL IN GABIONS CM 96.56 - 423.50 130.01 650.07

508a BRICK PAVING (SINGLE COURSE) SM 115.12 32.70 244.13 97.99 489.94

508b BRICK PAVING (DOUBLE COURSE) SM 206.12 32.70 484.49 180.83 904.13

509a RIP RAP CLASS "A" CM 505.38 - 397.24 225.65 1,128.27

509b RIP RAP CLASS "B" CM 485.38 - 394.06 219.86 1,099.29

509c RIP RAP CLASS "C" CM 488.59 - 397.24 221.46 1,107.28

Page 91
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Haripur
Haripur Hazara
Hazara District Code: 20-B

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

509d GROUTED RIP RAP CLASS "A" CM 615.67 102.14 1,801.96 629.94 3,149.72

509e GROUTED RIP RAP CLASS "B" CM 593.46 81.72 1,652.87 582.01 2,910.06

509f GROUTED RIP RAP CLASS "C" CM 585.55 68.10 1,698.06 587.93 2,939.63

509g REINFORCED CONCRETE SLOPE PROTECTION (WITHOUT CM 805.63 353.02 4,025.81 1,296.12 6,480.59
REINFORCEMENT)

509h FILTER LAYER OF GRANULAR MATERIAL CM 47.38 191.97 408.30 161.91 809.57

510 DISMANTLING OF STRUCTURE AND OBSTRUCTIONS CM 107.69 390.69 - 124.60 622.98

511a1 DRY STONE PITCHING (15-20 cm Thick) SM 158.55 67.48 64.55 72.64 363.22

511a2 DRY STONE PITCHING (21-25 cm Thick) SM 202.95 86.37 82.63 92.99 464.93

511b1 GROUTED STONE PITCHING (15-20 cm Thick) SM 259.20 180.32 360.08 199.90 999.51

511b2 GROUTED STONE PITCHING (21-25 cm Thick) SM 324.00 225.40 450.10 249.88 1,249.38

601ai CONCRETE KERB IN PLACE NEW JERSY BARRIER FOR M 284.44 572.25 2,150.61 751.82 3,759.12
MEDIAN (DOUBLE FACE)

601di PRECAST REINFORCED CONCRETE KERB NEW JERSY M 973.28 670.54 3,978.70 1,405.63 7,028.15
BARRIER FOR MEDIAN (DOUBLE FACE)

601dii PRECAST KERB IN CONCRETE CLASS A-1 OF SIZE 450 X 150 MM M 141.76 90.27 417.47 162.37 811.87
INCLUDING CONCRETE BEDDING & HAUNCHING

603 BRICK EDGING M 9.17 - 38.40 11.89 59.46

604a METAL GUARD RAIL M 19.85 70.84 1,579.36 417.51 2,087.56

604b METAL GUARD RAIL END PIECES EACH 25.20 - 1,197.58 305.69 1,528.47

604d STEEL POST OF METAL GUARD RAIL EACH 95.54 976.73 3,776.31 1,212.14 6,060.72

605a CONCRETE BEAM GUARD RAIL M 74.35 30.82 583.43 172.15 860.75

605c CONCRETE POST FOR GUARD RAIL M 91.29 27.36 582.15 175.20 876.00

607a TRAFFIC ROAD SIGN CATEGORY 1 EACH 240.32 255.15 6,841.57 1,834.26 9,171.30

607b TRAFFIC ROAD SIGN CATEGORY 2 EACH 68.78 382.72 9,230.52 2,420.51 12,102.53

607c TRAFFIC ROAD SIGN CATEGORY 3 (a) EACH 240.32 541.89 11,841.08 3,155.82 15,779.10

607d TRAFFIC ROAD SIGN CATEGORY 3 (b) EACH 754.96 598.64 20,888.29 5,560.47 27,802.37

607e TRAFFIC ROAD SIGN CATEGORY 3 (c) SM 150.99 119.73 9,195.20 2,366.48 11,832.40

607f ADDITIONAL PANEL SIZE 60 X 30 cm EACH 318.35 - 1,303.32 405.42 2,027.08

607g ADDITIONAL PANEL SIZE 90 X 30 cm EACH 318.35 - 1,954.97 568.33 2,841.66

608b1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.79 5.86 16.16 6.20 31.00
LINES OF 15 cm WIDTH

608b2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.93 4.03 39.59 11.14 55.68
LINES OF 15 cm WIDTH

608c1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.79 5.86 21.56 7.55 37.75
LINES OF 20 cm WIDTH

Page 92
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Haripur
Haripur Hazara
Hazara District Code: 20-B

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

608c2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.93 4.03 52.80 14.44 72.20
LINES OF 20 cm WIDTH

608d1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 77.02 5.22 156.10 59.59 297.93
4.0 M ARROWS

608d2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR 4.0 EACH 77.02 9.98 498.88 146.47 732.36
M ARROWS

608h1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.48 8.59 22.47 8.64 43.18
OF 15 cm WIDTH

608h2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.48 9.63 67.50 20.16 100.78
OF 15 cm WIDTH

608i1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.48 6.95 29.96 10.10 50.50
OF 20 cm WIDTH

608i2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.48 9.63 90.01 25.78 128.90
OF 20 cm WIDTH

608j1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR 4.0 M EACH 77.02 3.73 216.96 74.43 372.14
ARROWS

608j2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR 4.0 M EACH 77.02 7.90 851.20 234.03 1,170.15
ARROWS

608n1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 64.14 3.73 104.07 42.98 214.92
STOP

608n2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR EACH 64.14 7.90 333.09 101.28 506.42
STOP

608n3 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR STOP EACH 64.14 3.73 144.64 53.13 265.64

608n4 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR STOP EACH 64.14 7.90 568.32 160.09 800.46

609c REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 9.05 81.62 193.82 71.12 355.61
SINGLE)

609d REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 9.05 81.62 233.82 81.12 405.61
DOUBLE)

610b RIGHT OF WAY MARKER EACH 102.01 121.33 294.06 129.35 646.74

610c KILOMETRE POST (0.610 X 0.114 X 1.5 M) EACH 642.60 976.31 1,964.08 895.75 4,478.73

610d TEN KILOMETRE POST EACH 1,228.85 1,952.61 4,324.10 1,876.39 9,381.95

611a CHAIN LINK WIRE FABRIC FENCING 1500 MM HEIGHT M 134.15 91.00 945.78 292.73 1,463.66
WITH PRECAST PRESTRESSED R.C.C. POST

Page 93
.

Page 94
NATIONAL HIGHWAY AUTHORITY

COMPOSITE SCHEDULE OF RATES


January - 2009

KARAK
(27)

Shabir Associates
Quantity Surveying & Construction Cost Consultants

Page 95
.

Page 96
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Karak
Karak District Code: 27

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

101 CLEARING AND GRUBBING SM 0.78 10.10 - 2.72 13.60

102a REMOVAL OF TREES 150 - 300 mm GIRTH EACH 8.13 173.32 1.17 45.65 228.27

102b REMOVAL OF TREES 301 - 600 mm GIRTH EACH 22.72 456.54 2.63 120.47 602.36

102c REMOVAL OF TREES 601 mm OR OVER GIRTH EACH 90.87 1,826.16 10.51 481.89 2,409.43

103 STRIPPING CM 2.85 93.22 - 24.02 120.09

104 COMPACTION OF NATURAL GROUND SM 0.42 9.91 0.76 2.77 13.86

106a EXCAVATE UNSUITABLE COMMON MATERIAL CM 5.81 135.76 - 35.39 176.96

106bi EXCAVATE UNSUITABLE HARD ROCK MATERIAL CM 151.45 316.30 50.82 129.64 648.21

106bii EXCAVATE UNSUITABLE MEDIUM ROCK MATERIAL CM 20.00 337.99 - 89.50 447.49

106biii EXCAVATE UNSUITABLE SOFT ROCK MATERIAL CM 13.12 262.40 - 68.88 344.40

106c EXCAVATE SURPLUS COMMON MATERIAL CM 4.75 120.27 - 31.26 156.28

106di EXCAVATE SURPLUS HARD ROCK MATERIAL CM 151.45 316.30 50.82 129.64 648.21

106dii EXCAVATE SURPLUS MEDIUM ROCK MATERIAL CM 24.20 316.03 - 85.06 425.28

106diii EXCAVATE SURPLUS SOFT ROCK MATERIAL CM 10.13 263.92 - 68.51 342.57

107a STRUCTURAL EXCAVATION IN COMMON MATERIAL CM 8.93 137.60 0.38 36.73 183.64

107b STRUCTURAL EXCAVATION IN COMMON MATERIAL BELOW CM 69.76 287.11 70.80 106.92 534.60
WATER LEVEL

107ci STRUCTURAL EXCAVATION IN HARD ROCK MATERIAL CM 134.42 427.01 33.88 148.83 744.14

107cii STRUCTURAL EXCAVATION IN MEDIUM ROCK MATERIAL CM 113.02 292.53 - 101.39 506.95

107ciii STRUCTURAL EXCAVATION IN SOFT ROCK MATERIAL CM 69.13 238.86 - 77.00 384.99

107d GRANULAR BACK FILL CM 39.04 137.14 333.46 127.41 637.04

107e COMMON BACK FILL CM 26.75 62.84 5.09 23.67 118.34

108a FORMATION OF EMBANKMENT FROM ROADWAY CM 8.15 174.71 5.09 46.99 234.93
EXCAVATION IN COMMON MATERIAL

108bi FORMATION OF EMBANKMENT FROM ROADWAY CM 23.30 482.48 54.04 139.95 699.77
EXCAVATION IN HARD ROCK MATERIAL

108bii FORMATION OF EMBANKMENT FROM ROADWAY CM 17.47 416.71 2.42 109.15 545.75
EXCAVATION IN MEDIUM ROCK MATERIAL

108biii FORMATION OF EMBANKMENT FROM ROADWAY CM 15.53 369.34 - 96.22 481.09


EXCAVATION IN SOFT ROCK MATERIAL

108c FORMATION OF EMBANKMENT FROM BORROW CM 9.13 177.46 7.94 48.63 243.16
EXCAVATION IN COMMON MATERIAL

108d FORMATION OF EMBANKMENT FROM STRUCTURAL CM 7.26 76.32 5.09 22.17 110.84
EXCAVATION IN COMMON MATERIAL

108e FORMATION OF EMBANKMENT FROM STRUCTURAL CM 16.39 110.29 3.03 32.43 162.13
EXCAVATION IN ANY TYPE OF ROCK MATERIAL

109a SUB GRADE PREPARATION IN EARTH CUT SM 1.64 27.34 1.46 7.61 38.04

Page 97
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Karak
Karak District Code: 27

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

109bi SUB GRADE PREPARATION IN EXISTING ROAD WITHOUT SM 1.19 18.21 0.77 5.04 25.21
ANY FILL

110 IMPROVED SUB-GRADE CM 11.62 120.02 50.09 45.43 227.17

114a DRESSING OF BERM WITHOUT EXTRA MATERIAL SM 0.97 15.26 0.79 4.26 21.28

114b DRESSING OF BERM WITH EXTRA BORROW MATERIAL SM 1.43 15.57 0.90 4.47 22.37

201 GRANULAR SUB-BASE CM 9.35 255.06 416.14 170.14 850.69

202 AGGREGATE BASE CM 11.51 326.54 784.55 280.65 1,403.24

203a ASPHALTIC BASE COURSE PLANT MIX (CLASS "A") CM 78.57 1,510.17 5,942.49 1,882.81 9,414.04

203b ASPHALTIC BASE COURSE PLANT MIX (CLASS "B") CM 81.74 1,510.17 6,397.70 1,997.40 9,987.02

203c ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "A") CM 87.29 1,577.28 5,932.13 1,899.17 9,495.87

203d ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "B") CM 87.29 1,571.31 6,546.67 2,051.32 10,256.58

204b CEMENT STABILIZED BASE CM 34.39 569.10 825.35 357.21 1,786.06

204d LIQUID ASPHALT FOR CURING SEAL, TYPE MC-250 TON 281.09 915.38 53,974.23 13,792.67 68,963.37

204e EMULSIFIED ASPHALT FOR CURING SEAL, TYPE SS-1 TON 281.09 915.38 52,396.10 13,398.14 66,990.71

205a GRADED CRUSHED AGGREGATE CRACK-RELIEF LAYER CM 97.69 112.80 830.30 260.20 1,300.98

205b ASPHALTIC OPEN-GRADED PLANT MIX CRACK-RELIEF CM 165.47 2,437.94 5,642.02 2,061.36 10,306.79
LAYER

206b WATER BOUND MACADAM BASE WITH COARSE CM 107.33 126.27 744.05 244.41 1,222.07
AGGREGATE CLASS B

207a DEEP PATCHING (0-15 cm) SM 2.02 45.04 1.26 12.08 60.39

207b DEEP PATCHING (16-30 cm) SM 2.02 39.67 1.26 10.74 53.69

208 REINSTATEMENT OF ROAD SURFACE SM 2.26 57.10 0.56 14.98 74.90

209a BREAKING OF EXISTING ROAD PAVEMENT STRUCTURE CM 2.54 110.61 0.68 28.46 142.29

209b SCARIFICATION OF EXISTING ROAD PAVEMENT SM 0.51 22.12 0.14 5.69 28.46

302a CUT-BACK ASPHALT FOR BITUMINOUS PRIME COAT SM 0.35 1.57 38.31 10.06 50.29

302b EMULSIFIED ASPHALT FOR BITUMINOUS PRIME COAT SM 0.34 1.57 42.76 11.17 55.85

303a CUT-BACK ASPHALT FOR BITUMINOUS TACK COAT SM 0.14 0.58 16.03 4.19 20.94

303b EMULSIFIED ASPHALT FOR BITUMINOUS TACK COAT SM 0.14 0.58 18.70 4.86 24.28

304a SINGLE SURFACE TREATMENT SM 0.93 7.57 75.71 21.05 105.27

304b DOUBLE SURFACE TREATMENT SM 1.36 14.15 146.28 40.45 202.23

304c TRIPLE SURFACE TREATMENT SM 2.29 19.94 166.79 47.26 236.28

304d SEAL COAT SM 0.88 4.12 53.35 14.59 72.93

Page 98
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Karak
Karak District Code: 27

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

305a ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 75.36 1,489.33 7,021.16 2,146.46 10,732.32
"A")

305b ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 75.36 1,438.23 7,583.42 2,274.25 11,371.26
"B")

307a DENSE GRADED HOT BIT-MAC CM 183.99 379.77 5,811.58 1,593.84 7,969.18

307b OPEN GRADED HOT BIT-MAC CM 183.99 379.77 5,666.56 1,557.58 7,787.90

308a RECYCLING OF ASPHALT CONCRETE (0 - 60 mm THICK) CM 32.29 590.65 2,077.65 675.15 3,375.73

308b BITUMEN BINDER GRADE (40 - 50, 60 - 70, 80 - 100) TON 29.98 650.70 46,081.36 11,690.51 58,452.55

309a COLD MILLING, 0 - 30 mm SM 1.15 24.99 8.68 8.70 43.52

309b COLD MILLING, 0 - 50 mm SM 1.92 41.65 14.46 14.51 72.54

309c COLD MILLING, 0 - 70 mm SM 2.88 62.48 21.69 21.76 108.81

401a1i CONCRETE CLASS "A1" (Underground) CM 571.52 1,059.94 3,809.45 1,360.23 6,801.14

401a1ii CONCRETE CLASS "A1" (On ground) CM 571.52 1,059.94 4,086.93 1,429.60 7,147.98

401a1iii CONCRETE CLASS "A1" (Elevated) CM 571.52 1,059.94 4,641.87 1,568.33 7,841.66

401a2i CONCRETE CLASS "A2" (Underground) CM 571.52 1,059.94 4,187.45 1,454.73 7,273.64

401a2ii CONCRETE CLASS "A2" (On ground) CM 571.52 1,059.94 4,464.93 1,524.10 7,620.48

401a2iii CONCRETE CLASS "A2" (Elevated) CM 571.52 1,059.94 5,019.87 1,662.83 8,314.16

401a3i CONCRETE CLASS "A3" (Underground) CM 571.52 1,059.94 4,565.45 1,549.23 7,746.14

401a3ii CONCRETE CLASS "A3" (On ground) CM 571.52 1,059.94 4,842.93 1,618.60 8,092.98

401a3iii CONCRETE CLASS "A3" (Elevated) CM 571.52 1,059.94 5,397.87 1,757.33 8,786.66

401b CONCRETE CLASS "B" CM 752.65 805.93 3,080.89 1,159.87 5,799.34

401ci CONCRETE CLASS "C" (Underground) CM 550.17 500.55 3,369.77 1,105.12 5,525.61

401cii CONCRETE CLASS "C" (On ground) CM 550.17 500.55 3,488.12 1,134.71 5,673.54

401ciii CONCRETE CLASS "C" (Elevated) CM 550.17 500.55 3,724.80 1,193.88 5,969.39

401d CONCRETE CLASS "D1" CM 869.93 1,265.57 5,167.32 1,825.70 9,128.52

401e CONCRETE CLASS "Y" CM 1,186.05 500.55 4,592.37 1,569.74 7,848.70

401f LEAN CONCRETE CM 464.76 507.52 2,351.24 830.88 4,154.40

401gi(1) PRECAST CONCRETE CLASS "A-1" CM 1,831.87 947.15 4,794.10 1,893.28 9,466.40

401gi(3) PRECAST CONCRETE CLASS "A-3" CM 1,831.87 947.15 5,550.10 2,082.28 10,411.40

401gii PRECAST CONCRETE CLASS "B" CM 1,831.87 947.15 4,600.16 1,844.80 9,223.98

401giii(1) PRECAST CONCRETE CLASS "D1" CM 1,831.87 947.15 5,928.10 2,176.78 10,883.90

Page 99
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Karak
Karak District Code: 27

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

401giii(2) PRECAST CONCRETE CLASS "D2" CM 1,831.87 947.15 6,306.10 2,271.28 11,356.40

401giii(3) PRECAST CONCRETE CLASS "D3" CM 1,831.87 947.15 6,684.10 2,365.78 11,828.90

404a REINFORCEMENT AS PER AASHTO M. 31 GRADE 40 TON 1,730.40 781.47 60,842.00 15,838.47 79,192.34

404b REINFORCEMENT AS PER AASHTO M. 31 GRADE 60 TON 1,730.40 781.47 68,192.00 17,675.97 88,379.84

404h REINFORCEMENT (STRUCTURAL SHAPES) AS PER ASTM-A- TON 1,397.38 5,393.81 56,521.96 15,828.29 79,141.45
36

405a PRE-STRESSING WIRE STRAND 3/8" - 1/2" DIA COMPLETE IN TON 3,317.26 15,659.05 133,842.72 38,204.76 191,023.79
ALL RESPECT

405b LAUNCHING OF GIRDER TON 77.25 532.52 - 152.44 762.21

406a PREMOULDED JOINT FILLER 12 mm THICK WITH SM 123.44 - 305.24 107.17 535.85
BITUMASTIC JOINT SEAL

406b NEOPRENE RUBBER JOINT FILLER 12 mm THICK WITH SM 123.44 - 304.39 106.96 534.79
BITUMASTIC JOINT SEAL

406c STEEL EXPANSION JOINTS KG 10.01 26.40 91.38 31.95 159.74

406d WATER STOPS 6" SIZE M 105.48 - 470.21 143.92 719.61

406e ELASTOMERIC BEARING PADS (ACCORDING TO SIZE AND ccm 0.02 - 2.12 0.53 2.67
THICKNESS)

406f ASPHALT FELT (3 PLY) SM 43.69 - 3,036.57 770.06 3,850.32

406g STEEL OR METAL BEARING DEVICES KG 22.31 69.68 117.85 52.46 262.31

407d1 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 416.93 1,654.04 889.13 740.03 3,700.13
(BORING ONLY) IN NORMAL SOIL

407d2 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 625.39 2,481.06 1,333.70 1,110.04 5,550.19
(BORING ONLY) IN GRAVEL STRATA

407d3 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 625.39 2,481.06 981.72 1,022.04 5,110.22
ONLY) IN NORMAL SOIL

407d4 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 1,042.32 4,135.11 1,148.17 1,581.40 7,907.00
ONLY) IN GRAVEL STRATA

407d5 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 893.42 4,884.94 1,308.66 1,771.76 8,858.78
ONLY) IN NORMAL SOIL

407d6 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 1,563.49 6,909.78 1,447.73 2,480.25 12,401.25
ONLY) IN GRAVEL SOIL

407h PILE LOAD TEST UP TO 120 TON EACH 24,126.58 45,769.30 90,203.26 40,024.79 200,123.93

407i PILE LOAD TEST UP TO 240 TON EACH 44,046.27 45,769.30 180,406.52 67,555.52 337,777.62

407j PILE LOAD TEST UP TO 360 TON EACH 63,965.96 50,188.38 270,609.78 96,191.03 480,955.16

407k CONFIRMATORY BORING (NX SIZE) M 223.15 1,582.02 6.37 452.88 2,264.42

410 BRICK WORK CM 335.42 282.72 3,199.01 954.29 4,771.44

411a STONE MASONRY RANDOM DRY CM 291.16 107.96 429.91 207.26 1,036.29

411b STONE MASONRY RANDOM WITH MORTAR CM 312.23 166.68 1,456.24 483.79 2,418.94

411c STONE MASONRY DRESSED UNCOURSED DRY CM 377.55 107.96 481.39 241.73 1,208.63

411d STONE MASONRY DRESSED UNCOURSED WITH MORTAR CM 441.81 166.68 1,518.77 531.82 2,659.08

Page 100
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Karak
Karak District Code: 27

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

411g ROLL POINTING SM 70.27 11.74 43.75 31.44 157.21

412a STONE MASONRY DRESSED COURSED WITH MORTAR CM 593.53 264.08 1,423.96 570.39 2,851.97

501a R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 310 mm M 237.69 437.48 643.39 329.64 1,648.20

501b R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 380 mm M 229.73 577.19 834.17 410.27 2,051.36

501c R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 460 mm M 230.49 935.96 1,069.85 559.08 2,795.38

501d R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 610 mm M 239.72 1,146.39 1,598.23 746.08 3,730.42

501e R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 760 mm M 277.90 1,078.41 2,297.87 913.55 4,567.73

501f R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 910 mm M 346.22 1,331.30 3,614.54 1,323.02 6,615.08

501g R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1070 mm M 448.05 1,481.41 4,680.50 1,652.49 8,262.45

501h R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1220 mm M 529.02 1,798.85 5,964.68 2,073.14 10,365.69

501i R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1520 mm M 624.86 2,098.66 9,213.95 2,984.37 14,921.85

501j R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 310 mm M 237.69 507.33 722.10 366.78 1,833.90

501k R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 380 mm M 229.73 577.19 852.99 414.98 2,074.88

501l R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 460 mm M 224.56 935.96 1,044.43 551.24 2,756.19

501m R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 610 mm M 239.72 1,146.39 1,743.69 782.45 3,912.25

501n R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 760 mm M 277.90 1,078.41 3,316.03 1,168.09 5,840.43

501o R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 910 mm M 346.22 1,331.30 4,871.85 1,637.34 8,186.72

501p R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1070 mm M 448.05 1,481.41 6,808.93 2,184.60 10,922.99

501q R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1220 mm M 529.02 1,798.85 9,234.95 2,890.71 14,453.54

501r R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1520 mm M 624.86 2,098.66 12,992.82 3,929.08 19,645.42

502a GRANULAR MATERIAL IN BED TO CONCRETE PIPE CM 98.08 118.93 287.07 126.02 630.09
CULVERT

502b CONCRETE CLASS "B" IN BEDDING AND ENCASEMENT OF CM 844.07 612.95 3,430.89 1,221.98 6,109.89
CONCRETE PIPE CULVERT

507a STEEL WIRE MESH FOR GABIONS KG 5.88 - 110.38 29.06 145.32

507b ROCK FILL IN GABIONS CM 102.22 - 423.50 131.43 657.15

508a BRICK PAVING (SINGLE COURSE) SM 112.13 32.70 259.16 101.00 504.99

508b BRICK PAVING (DOUBLE COURSE) SM 198.52 32.70 515.72 186.74 933.68

509a RIP RAP CLASS "A" CM 484.55 - 335.10 204.91 1,024.56

509b RIP RAP CLASS "B" CM 465.60 - 332.42 199.51 997.53

509c RIP RAP CLASS "C" CM 467.01 - 335.10 200.53 1,002.64

Page 101
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Karak
Karak District Code: 27

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

509d GROUTED RIP RAP CLASS "A" CM 591.93 102.14 1,728.08 605.54 3,027.69

509e GROUTED RIP RAP CLASS "B" CM 568.36 81.72 1,580.71 557.70 2,788.48

509f GROUTED RIP RAP CLASS "C" CM 560.02 68.10 1,624.95 563.27 2,816.34

509g REINFORCED CONCRETE SLOPE PROTECTION (WITHOUT CM 825.33 353.02 4,002.36 1,295.18 6,475.90
REINFORCEMENT)

509h FILTER LAYER OF GRANULAR MATERIAL CM 50.95 191.97 333.54 144.11 720.57

510 DISMANTLING OF STRUCTURE AND OBSTRUCTIONS CM 120.01 390.69 - 127.68 638.38

511a1 DRY STONE PITCHING (15-20 cm Thick) SM 155.26 67.48 54.45 69.30 346.49

511a2 DRY STONE PITCHING (21-25 cm Thick) SM 198.74 86.37 69.70 88.70 443.51

511b1 GROUTED STONE PITCHING (15-20 cm Thick) SM 250.14 180.32 351.30 195.44 977.20

511b2 GROUTED STONE PITCHING (21-25 cm Thick) SM 312.68 225.40 439.12 244.30 1,221.50

601ai CONCRETE KERB IN PLACE NEW JERSY BARRIER FOR M 303.07 572.25 2,139.59 753.73 3,768.64
MEDIAN (DOUBLE FACE)

601di PRECAST REINFORCED CONCRETE KERB NEW JERSY M 1,005.85 670.54 3,998.01 1,418.60 7,092.99
BARRIER FOR MEDIAN (DOUBLE FACE)

601dii PRECAST KERB IN CONCRETE CLASS A-1 OF SIZE 450 X 150 MM M 146.31 90.27 414.78 162.84 814.21
INCLUDING CONCRETE BEDDING & HAUNCHING

603 BRICK EDGING M 9.21 - 41.95 12.79 63.95

604a METAL GUARD RAIL M 22.24 70.84 1,579.36 418.11 2,090.56

604b METAL GUARD RAIL END PIECES EACH 28.60 - 1,197.58 306.54 1,532.72

604d STEEL POST OF METAL GUARD RAIL EACH 104.64 976.73 3,776.31 1,214.42 6,072.10

605a CONCRETE BEAM GUARD RAIL M 76.63 30.82 589.31 174.19 870.96

605c CONCRETE POST FOR GUARD RAIL M 94.09 27.36 588.49 177.49 887.43

607a TRAFFIC ROAD SIGN CATEGORY 1 EACH 250.32 255.15 6,843.99 1,837.37 9,186.83

607b TRAFFIC ROAD SIGN CATEGORY 2 EACH 71.20 382.72 9,228.48 2,420.60 12,103.01

607c TRAFFIC ROAD SIGN CATEGORY 3 (a) EACH 250.32 541.89 11,838.59 3,157.70 15,788.50

607d TRAFFIC ROAD SIGN CATEGORY 3 (b) EACH 793.86 598.64 20,882.85 5,568.84 27,844.20

607e TRAFFIC ROAD SIGN CATEGORY 3 (c) SM 158.77 119.73 9,194.76 2,368.32 11,841.58

607f ADDITIONAL PANEL SIZE 60 X 30 cm EACH 319.78 - 1,303.08 405.71 2,028.57

607g ADDITIONAL PANEL SIZE 90 X 30 cm EACH 319.78 - 1,954.62 568.60 2,843.00

608b1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.99 5.86 16.17 6.25 31.27
LINES OF 15 cm WIDTH

608b2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 1.00 4.03 39.75 11.19 55.96
LINES OF 15 cm WIDTH

608c1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.99 5.86 21.58 7.61 38.03
LINES OF 20 cm WIDTH

Page 102
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Karak
Karak District Code: 27

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

608c2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 1.00 4.03 53.01 14.51 72.55
LINES OF 20 cm WIDTH

608d1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 78.08 5.22 156.25 59.89 299.43
4.0 M ARROWS

608d2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR 4.0 EACH 78.08 9.98 500.87 147.23 736.16
M ARROWS

608h1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.73 8.59 22.49 8.70 43.51
OF 15 cm WIDTH

608h2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.73 9.63 67.50 20.22 101.09
OF 15 cm WIDTH

608i1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.73 6.95 29.98 10.17 50.83
OF 20 cm WIDTH

608i2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.73 9.63 90.01 25.84 129.21
OF 20 cm WIDTH

608j1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR 4.0 M EACH 78.08 3.73 217.11 74.73 373.64
ARROWS

608j2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR 4.0 M EACH 78.08 7.90 851.20 234.29 1,171.47
ARROWS

608n1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 65.44 3.73 104.17 43.33 216.67
STOP

608n2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR EACH 65.44 7.90 334.42 101.94 509.69
STOP

608n3 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR STOP EACH 65.44 3.73 144.74 53.48 267.38

608n4 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR STOP EACH 65.44 7.90 568.32 160.42 802.08

609c REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 9.54 81.62 193.80 71.24 356.20
SINGLE)

609d REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 9.54 81.62 233.80 81.24 406.19
DOUBLE)

610b RIGHT OF WAY MARKER EACH 107.15 121.33 294.85 130.83 654.16

610c KILOMETRE POST (0.610 X 0.114 X 1.5 M) EACH 649.01 976.31 1,975.98 900.32 4,501.61

610d TEN KILOMETRE POST EACH 1,255.89 1,952.61 4,349.06 1,889.39 9,446.95

611a CHAIN LINK WIRE FABRIC FENCING 1500 MM HEIGHT M 142.80 91.00 945.48 294.82 1,474.11
WITH PRECAST PRESTRESSED R.C.C. POST

Page 103
.

Page 104
NATIONAL HIGHWAY AUTHORITY

COMPOSITE SCHEDULE OF RATES


January - 2009

KOHAT
(34)

Shabir Associates
Quantity Surveying & Construction Cost Consultants

Page 105
.

Page 106
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Kohat
Kohat District Code: 34

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

101 CLEARING AND GRUBBING SM 0.67 10.10 - 2.69 13.47

102a REMOVAL OF TREES 150 - 300 mm GIRTH EACH 7.14 173.32 1.17 45.41 227.03

102b REMOVAL OF TREES 301 - 600 mm GIRTH EACH 19.84 456.54 2.63 119.75 598.76

102c REMOVAL OF TREES 601 mm OR OVER GIRTH EACH 79.37 1,826.16 10.51 479.01 2,395.05

103 STRIPPING CM 2.60 93.22 - 23.95 119.77

104 COMPACTION OF NATURAL GROUND SM 0.38 9.91 0.76 2.76 13.81

106a EXCAVATE UNSUITABLE COMMON MATERIAL CM 5.20 135.76 - 35.24 176.20

106bi EXCAVATE UNSUITABLE HARD ROCK MATERIAL CM 126.24 316.30 50.82 123.34 616.70

106bii EXCAVATE UNSUITABLE MEDIUM ROCK MATERIAL CM 16.12 337.99 - 88.53 442.65

106biii EXCAVATE UNSUITABLE SOFT ROCK MATERIAL CM 10.56 262.40 - 68.24 341.20

106c EXCAVATE SURPLUS COMMON MATERIAL CM 4.26 120.27 - 31.13 155.66

106di EXCAVATE SURPLUS HARD ROCK MATERIAL CM 126.24 316.30 50.82 123.34 616.70

106dii EXCAVATE SURPLUS MEDIUM ROCK MATERIAL CM 20.09 316.03 - 84.03 420.15

106diii EXCAVATE SURPLUS SOFT ROCK MATERIAL CM 8.19 263.92 - 68.03 340.14

107a STRUCTURAL EXCAVATION IN COMMON MATERIAL CM 7.98 137.60 0.38 36.49 182.45

107b STRUCTURAL EXCAVATION IN COMMON MATERIAL BELOW CM 61.45 287.11 70.80 104.84 524.21
WATER LEVEL

107ci STRUCTURAL EXCAVATION IN HARD ROCK MATERIAL CM 111.59 427.01 33.88 143.12 715.61

107cii STRUCTURAL EXCAVATION IN MEDIUM ROCK MATERIAL CM 92.95 292.53 - 96.37 481.86

107ciii STRUCTURAL EXCAVATION IN SOFT ROCK MATERIAL CM 57.39 238.86 - 74.06 370.32

107d GRANULAR BACK FILL CM 33.43 137.14 400.54 142.78 713.89

107e COMMON BACK FILL CM 23.44 62.84 5.09 22.84 114.21

108a FORMATION OF EMBANKMENT FROM ROADWAY CM 6.79 174.71 5.09 46.65 233.24
EXCAVATION IN COMMON MATERIAL

108bi FORMATION OF EMBANKMENT FROM ROADWAY CM 19.59 482.48 54.04 139.03 695.13
EXCAVATION IN HARD ROCK MATERIAL

108bii FORMATION OF EMBANKMENT FROM ROADWAY CM 14.69 416.71 2.42 108.45 542.27
EXCAVATION IN MEDIUM ROCK MATERIAL

108biii FORMATION OF EMBANKMENT FROM ROADWAY CM 13.06 369.34 - 95.60 478.00


EXCAVATION IN SOFT ROCK MATERIAL

108c FORMATION OF EMBANKMENT FROM BORROW CM 7.63 177.46 7.94 48.26 241.28
EXCAVATION IN COMMON MATERIAL

108d FORMATION OF EMBANKMENT FROM STRUCTURAL CM 6.14 76.32 5.09 21.89 109.43
EXCAVATION IN COMMON MATERIAL

108e FORMATION OF EMBANKMENT FROM STRUCTURAL CM 14.03 110.29 3.03 31.84 159.19
EXCAVATION IN ANY TYPE OF ROCK MATERIAL

109a SUB GRADE PREPARATION IN EARTH CUT SM 1.39 27.34 1.46 7.55 37.73

Page 107
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Kohat
Kohat District Code: 34

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

109bi SUB GRADE PREPARATION IN EXISTING ROAD WITHOUT SM 1.04 18.21 0.77 5.01 25.03
ANY FILL

110 IMPROVED SUB-GRADE CM 9.85 120.02 52.15 45.50 227.52

114a DRESSING OF BERM WITHOUT EXTRA MATERIAL SM 0.86 15.26 0.79 4.23 21.14

114b DRESSING OF BERM WITH EXTRA BORROW MATERIAL SM 1.25 15.57 0.90 4.43 22.15

201 GRANULAR SUB-BASE CM 7.73 255.06 543.95 201.69 1,008.43

202 AGGREGATE BASE CM 9.30 326.54 705.13 260.24 1,301.22

203a ASPHALTIC BASE COURSE PLANT MIX (CLASS "A") CM 65.21 1,510.17 6,167.01 1,935.60 9,677.99

203b ASPHALTIC BASE COURSE PLANT MIX (CLASS "B") CM 67.55 1,510.17 6,600.97 2,044.67 10,223.36

203c ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "A") CM 72.29 1,577.28 6,156.63 1,951.55 9,757.76

203d ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "B") CM 72.29 1,571.31 6,750.75 2,098.59 10,492.94

204b CEMENT STABILIZED BASE CM 27.95 569.10 1,019.57 404.16 2,020.78

204d LIQUID ASPHALT FOR CURING SEAL, TYPE MC-250 TON 243.07 915.38 54,737.79 13,974.06 69,870.30

204e EMULSIFIED ASPHALT FOR CURING SEAL, TYPE SS-1 TON 243.07 915.38 53,159.66 13,579.53 67,897.64

205a GRADED CRUSHED AGGREGATE CRACK-RELIEF LAYER CM 83.92 112.80 897.88 273.65 1,368.26

205b ASPHALTIC OPEN-GRADED PLANT MIX CRACK-RELIEF CM 136.80 2,437.94 5,802.67 2,094.35 10,471.77
LAYER

206b WATER BOUND MACADAM BASE WITH COARSE CM 91.14 126.27 722.78 235.05 1,175.24
AGGREGATE CLASS B

207a DEEP PATCHING (0-15 cm) SM 1.75 45.04 1.26 12.01 60.05

207b DEEP PATCHING (16-30 cm) SM 1.75 39.67 1.26 10.67 53.35

208 REINSTATEMENT OF ROAD SURFACE SM 1.88 57.10 0.56 14.89 74.43

209a BREAKING OF EXISTING ROAD PAVEMENT STRUCTURE CM 2.37 110.61 0.68 28.42 142.08

209b SCARIFICATION OF EXISTING ROAD PAVEMENT SM 0.47 22.12 0.14 5.68 28.42

302a CUT-BACK ASPHALT FOR BITUMINOUS PRIME COAT SM 0.30 1.57 38.85 10.18 50.90

302b EMULSIFIED ASPHALT FOR BITUMINOUS PRIME COAT SM 0.29 1.57 43.37 11.31 56.53

303a CUT-BACK ASPHALT FOR BITUMINOUS TACK COAT SM 0.12 0.58 16.26 4.24 21.20

303b EMULSIFIED ASPHALT FOR BITUMINOUS TACK COAT SM 0.12 0.58 18.97 4.92 24.58

304a SINGLE SURFACE TREATMENT SM 0.77 7.57 77.37 21.43 107.15

304b DOUBLE SURFACE TREATMENT SM 1.12 14.15 149.70 41.24 206.21

304c TRIPLE SURFACE TREATMENT SM 1.90 19.94 170.80 48.16 240.80

304d SEAL COAT SM 0.72 4.12 54.68 14.88 74.40

Page 108
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Kohat
Kohat District Code: 34

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

305a ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 62.01 1,489.33 7,253.98 2,201.33 11,006.65
"A")

305b ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 62.01 1,438.23 7,838.95 2,334.80 11,673.99
"B")

307a DENSE GRADED HOT BIT-MAC CM 151.13 379.77 6,048.94 1,644.96 8,224.81

307b OPEN GRADED HOT BIT-MAC CM 151.13 379.77 5,863.98 1,598.72 7,993.61

308a RECYCLING OF ASPHALT CONCRETE (0 - 60 mm THICK) CM 27.07 590.65 2,109.07 681.70 3,408.48

308b BITUMEN BINDER GRADE (40 - 50, 60 - 70, 80 - 100) TON 27.12 650.70 46,867.60 11,886.35 59,431.77

309a COLD MILLING, 0 - 30 mm SM 0.97 24.99 8.68 8.66 43.29

309b COLD MILLING, 0 - 50 mm SM 1.61 41.65 14.46 14.43 72.15

309c COLD MILLING, 0 - 70 mm SM 2.41 62.48 21.69 21.65 108.23

401a1i CONCRETE CLASS "A1" (Underground) CM 517.14 1,059.94 3,973.64 1,387.68 6,938.40

401a1ii CONCRETE CLASS "A1" (On ground) CM 517.14 1,059.94 4,251.11 1,457.05 7,285.24

401a1iii CONCRETE CLASS "A1" (Elevated) CM 517.14 1,059.94 4,806.06 1,595.78 7,978.92

401a2i CONCRETE CLASS "A2" (Underground) CM 517.14 1,059.94 4,351.64 1,482.18 7,410.90

401a2ii CONCRETE CLASS "A2" (On ground) CM 517.14 1,059.94 4,629.11 1,551.55 7,757.74

401a2iii CONCRETE CLASS "A2" (Elevated) CM 517.14 1,059.94 5,184.06 1,690.28 8,451.42

401a3i CONCRETE CLASS "A3" (Underground) CM 517.14 1,059.94 4,729.64 1,576.68 7,883.40

401a3ii CONCRETE CLASS "A3" (On ground) CM 517.14 1,059.94 5,007.11 1,646.05 8,230.24

401a3iii CONCRETE CLASS "A3" (Elevated) CM 517.14 1,059.94 5,562.06 1,784.78 8,923.92

401b CONCRETE CLASS "B" CM 670.17 805.93 3,184.04 1,165.03 5,825.17

401ci CONCRETE CLASS "C" (Underground) CM 507.28 500.55 3,516.30 1,131.03 5,655.16

401cii CONCRETE CLASS "C" (On ground) CM 507.28 500.55 3,634.64 1,160.62 5,803.08

401ciii CONCRETE CLASS "C" (Elevated) CM 507.28 500.55 3,871.32 1,219.79 6,098.94

401d CONCRETE CLASS "D1" CM 799.90 1,265.57 5,308.19 1,843.41 9,217.07

401e CONCRETE CLASS "Y" CM 1,096.46 500.55 4,765.78 1,590.70 7,953.48

401f LEAN CONCRETE CM 420.11 507.52 2,454.69 845.58 4,227.90

401gi(1) PRECAST CONCRETE CLASS "A-1" CM 1,690.71 947.15 4,979.69 1,904.39 9,521.93

401gi(3) PRECAST CONCRETE CLASS "A-3" CM 1,690.71 947.15 5,735.69 2,093.39 10,466.93

401gii PRECAST CONCRETE CLASS "B" CM 1,690.71 947.15 4,708.59 1,836.61 9,183.07

401giii(1) PRECAST CONCRETE CLASS "D1" CM 1,690.71 947.15 6,113.69 2,187.89 10,939.43

Page 109
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Kohat
Kohat District Code: 34

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

401giii(2) PRECAST CONCRETE CLASS "D2" CM 1,690.71 947.15 6,491.69 2,282.39 11,411.93

401giii(3) PRECAST CONCRETE CLASS "D3" CM 1,690.71 947.15 6,869.69 2,376.89 11,884.43

404a REINFORCEMENT AS PER AASHTO M. 31 GRADE 40 TON 1,595.78 781.47 60,206.00 15,645.81 78,229.06

404b REINFORCEMENT AS PER AASHTO M. 31 GRADE 60 TON 1,595.78 781.47 67,556.00 17,483.31 87,416.56

404h REINFORCEMENT (STRUCTURAL SHAPES) AS PER ASTM-A- TON 1,245.21 5,393.81 56,041.90 15,670.23 78,351.16
36

405a PRE-STRESSING WIRE STRAND 3/8" - 1/2" DIA COMPLETE IN TON 2,804.43 15,659.05 133,831.75 38,073.81 190,369.04
ALL RESPECT

405b LAUNCHING OF GIRDER TON 66.38 532.52 - 149.73 748.64

406a PREMOULDED JOINT FILLER 12 mm THICK WITH SM 108.80 - 307.11 103.98 519.89
BITUMASTIC JOINT SEAL

406b NEOPRENE RUBBER JOINT FILLER 12 mm THICK WITH SM 108.80 - 306.17 103.74 518.71
BITUMASTIC JOINT SEAL

406c STEEL EXPANSION JOINTS KG 8.91 26.40 90.79 31.52 157.62

406d WATER STOPS 6" SIZE M 99.51 - 470.59 142.52 712.62

406e ELASTOMERIC BEARING PADS (ACCORDING TO SIZE AND ccm 0.02 - 2.12 0.53 2.67
THICKNESS)

406f ASPHALT FELT (3 PLY) SM 41.24 - 3,060.35 775.40 3,876.99

406g STEEL OR METAL BEARING DEVICES KG 18.32 69.68 117.68 51.42 257.11

407d1 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 374.18 1,654.04 899.35 731.89 3,659.47
(BORING ONLY) IN NORMAL SOIL

407d2 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 561.27 2,481.06 1,349.02 1,097.84 5,489.20
(BORING ONLY) IN GRAVEL STRATA

407d3 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 561.27 2,481.06 996.97 1,009.83 5,049.14
ONLY) IN NORMAL SOIL

407d4 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 935.46 4,135.11 1,173.58 1,561.04 7,805.18
ONLY) IN GRAVEL STRATA

407d5 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 801.82 4,884.94 1,352.77 1,759.88 8,799.42
ONLY) IN NORMAL SOIL

407d6 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 1,403.19 6,909.78 1,485.86 2,449.71 12,248.53
ONLY) IN GRAVEL SOIL

407h PILE LOAD TEST UP TO 120 TON EACH 20,395.24 45,769.30 98,474.38 41,159.73 205,798.66

407i PILE LOAD TEST UP TO 240 TON EACH 37,393.75 45,769.30 196,948.76 70,027.95 350,139.77

407j PILE LOAD TEST UP TO 360 TON EACH 54,392.26 50,188.38 295,423.14 100,000.95 500,004.73

407k CONFIRMATORY BORING (NX SIZE) M 194.02 1,582.02 6.37 445.60 2,228.01

410 BRICK WORK CM 331.41 282.72 3,119.08 933.30 4,666.51

411a STONE MASONRY RANDOM DRY CM 281.11 107.96 426.43 203.87 1,019.37

411b STONE MASONRY RANDOM WITH MORTAR CM 304.36 166.68 1,490.36 490.35 2,451.75

411c STONE MASONRY DRESSED UNCOURSED DRY CM 365.39 107.96 477.63 237.74 1,188.72

411d STONE MASONRY DRESSED UNCOURSED WITH MORTAR CM 430.79 166.68 1,543.20 535.17 2,675.84

Page 110
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Kohat
Kohat District Code: 34

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

411g ROLL POINTING SM 70.67 11.74 44.38 31.70 158.49

412a STONE MASONRY DRESSED COURSED WITH MORTAR CM 576.11 264.08 1,448.39 572.15 2,860.73

501a R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 310 mm M 212.44 437.48 644.57 323.62 1,618.11

501b R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 380 mm M 204.95 577.19 835.58 404.43 2,022.15

501c R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 460 mm M 203.82 935.96 1,071.50 552.82 2,764.10

501d R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 610 mm M 211.05 1,146.39 1,600.15 739.40 3,696.98

501e R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 760 mm M 241.56 1,078.41 2,299.79 904.94 4,524.70

501f R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 910 mm M 298.99 1,331.30 3,617.32 1,311.90 6,559.51

501g R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1070 mm M 386.93 1,481.41 4,683.26 1,637.90 8,189.49

501h R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1220 mm M 453.23 1,798.85 5,968.04 2,055.03 10,275.14

501i R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1520 mm M 538.73 2,098.66 9,217.87 2,963.82 14,819.08

501j R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 310 mm M 212.44 507.33 724.45 361.05 1,805.27

501k R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 380 mm M 204.95 577.19 854.40 409.14 2,045.68

501l R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 460 mm M 198.17 935.96 1,046.08 545.05 2,725.26

501m R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 610 mm M 211.05 1,146.39 1,745.18 775.66 3,878.28

501n R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 760 mm M 241.56 1,078.41 3,318.17 1,159.54 5,797.68

501o R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 910 mm M 298.99 1,331.30 4,874.63 1,626.23 8,131.15

501p R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1070 mm M 386.93 1,481.41 6,811.69 2,170.01 10,850.03

501q R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1220 mm M 453.23 1,798.85 9,238.31 2,872.60 14,362.99

501r R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1520 mm M 538.73 2,098.66 12,996.73 3,908.53 19,542.65

502a GRANULAR MATERIAL IN BED TO CONCRETE PIPE CM 87.04 118.93 399.86 151.46 757.28
CULVERT

502b CONCRETE CLASS "B" IN BEDDING AND ENCASEMENT OF CM 760.14 612.95 3,534.04 1,226.78 6,133.91
CONCRETE PIPE CULVERT

507a STEEL WIRE MESH FOR GABIONS KG 5.18 - 109.50 28.67 143.35

507b ROCK FILL IN GABIONS CM 89.65 - 388.21 119.47 597.33

508a BRICK PAVING (SINGLE COURSE) SM 106.70 32.70 251.43 97.71 488.54

508b BRICK PAVING (DOUBLE COURSE) SM 190.98 32.70 499.32 180.75 903.76

509a RIP RAP CLASS "A" CM 468.81 - 331.63 200.11 1,000.55

509b RIP RAP CLASS "B" CM 450.04 - 328.97 194.75 973.76

509c RIP RAP CLASS "C" CM 453.02 - 331.63 196.16 980.81

Page 111
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Kohat
Kohat District Code: 34

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

509d GROUTED RIP RAP CLASS "A" CM 569.88 102.14 1,748.10 605.03 3,025.15

509e GROUTED RIP RAP CLASS "B" CM 549.49 81.72 1,598.31 557.38 2,786.90

509f GROUTED RIP RAP CLASS "C" CM 542.20 68.10 1,643.41 563.43 2,817.13

509g REINFORCED CONCRETE SLOPE PROTECTION (WITHOUT CM 771.05 353.02 4,099.51 1,305.90 6,529.48
REINFORCEMENT)

509h FILTER LAYER OF GRANULAR MATERIAL CM 43.73 191.97 400.99 159.17 795.86

510 DISMANTLING OF STRUCTURE AND OBSTRUCTIONS CM 110.63 390.69 - 125.33 626.65

511a1 DRY STONE PITCHING (15-20 cm Thick) SM 148.51 67.48 53.89 67.47 337.35

511a2 DRY STONE PITCHING (21-25 cm Thick) SM 190.10 86.37 68.98 86.36 431.80

511b1 GROUTED STONE PITCHING (15-20 cm Thick) SM 242.42 180.32 362.76 196.38 981.88

511b2 GROUTED STONE PITCHING (21-25 cm Thick) SM 303.02 225.40 453.45 245.47 1,227.35

601ai CONCRETE KERB IN PLACE NEW JERSY BARRIER FOR M 274.07 572.25 2,225.15 767.86 3,839.32
MEDIAN (DOUBLE FACE)

601di PRECAST REINFORCED CONCRETE KERB NEW JERSY M 929.75 670.54 4,081.29 1,420.39 7,101.96
BARRIER FOR MEDIAN (DOUBLE FACE)

601dii PRECAST KERB IN CONCRETE CLASS A-1 OF SIZE 450 X 150 MM M 135.10 90.27 430.75 164.03 820.14
INCLUDING CONCRETE BEDDING & HAUNCHING

603 BRICK EDGING M 8.61 - 39.84 12.11 60.56

604a METAL GUARD RAIL M 19.62 70.84 1,579.36 417.46 2,087.28

604b METAL GUARD RAIL END PIECES EACH 26.80 - 1,197.58 306.09 1,530.47

604d STEEL POST OF METAL GUARD RAIL EACH 93.46 976.73 3,776.31 1,211.62 6,058.12

605a CONCRETE BEAM GUARD RAIL M 69.51 30.82 593.39 173.43 867.15

605c CONCRETE POST FOR GUARD RAIL M 85.34 27.36 593.85 176.64 883.20

607a TRAFFIC ROAD SIGN CATEGORY 1 EACH 217.01 255.15 6,848.29 1,830.11 9,150.57

607b TRAFFIC ROAD SIGN CATEGORY 2 EACH 68.95 382.72 9,243.83 2,423.88 12,119.38

607c TRAFFIC ROAD SIGN CATEGORY 3 (a) EACH 217.01 541.89 11,864.05 3,155.74 15,778.69

607d TRAFFIC ROAD SIGN CATEGORY 3 (b) EACH 685.96 598.64 20,920.35 5,551.24 27,756.18

607e TRAFFIC ROAD SIGN CATEGORY 3 (c) SM 137.19 119.73 9,200.07 2,364.25 11,821.24

607f ADDITIONAL PANEL SIZE 60 X 30 cm EACH 295.24 - 1,302.64 399.47 1,997.35

607g ADDITIONAL PANEL SIZE 90 X 30 cm EACH 295.24 - 1,953.96 562.30 2,811.50

608b1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.70 5.86 16.16 6.18 30.91
LINES OF 15 cm WIDTH

608b2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.90 4.03 39.68 11.15 55.76
LINES OF 15 cm WIDTH

608c1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.70 5.86 21.57 7.53 37.67
LINES OF 20 cm WIDTH

Page 112
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Kohat
Kohat District Code: 34

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

608c2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.90 4.03 52.92 14.46 72.31
LINES OF 20 cm WIDTH

608d1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 72.37 5.22 156.19 58.44 292.22
4.0 M ARROWS

608d2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR 4.0 EACH 72.37 9.98 500.01 145.59 727.95
M ARROWS

608h1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.38 8.59 22.48 8.61 43.06
OF 15 cm WIDTH

608h2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.38 9.63 67.50 20.13 100.65
OF 15 cm WIDTH

608i1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.38 6.95 29.97 10.08 50.38
OF 20 cm WIDTH

608i2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.38 9.63 90.01 25.75 128.77
OF 20 cm WIDTH

608j1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR 4.0 M EACH 72.37 3.73 217.05 73.29 366.43
ARROWS

608j2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR 4.0 M EACH 72.37 7.90 851.20 232.87 1,164.33
ARROWS

608n1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 60.56 3.73 104.13 42.10 210.52
STOP

608n2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR EACH 60.56 7.90 333.84 100.58 502.88
STOP

608n3 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR STOP EACH 60.56 3.73 144.70 52.25 261.23

608n4 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR STOP EACH 60.56 7.90 568.32 159.20 795.98

609c REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 9.38 81.62 193.85 71.21 356.06
SINGLE)

609d REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 9.38 81.62 233.85 81.21 406.05
DOUBLE)

610b RIGHT OF WAY MARKER EACH 95.52 121.33 301.54 129.60 647.98

610c KILOMETRE POST (0.610 X 0.114 X 1.5 M) EACH 594.15 976.31 2,028.46 899.73 4,498.65

610d TEN KILOMETRE POST EACH 1,134.63 1,952.61 4,452.94 1,885.05 9,425.23

611a CHAIN LINK WIRE FABRIC FENCING 1500 MM HEIGHT M 132.06 91.00 951.76 293.71 1,468.53
WITH PRECAST PRESTRESSED R.C.C. POST

Page 113
.

Page 114
NATIONAL HIGHWAY AUTHORITY

COMPOSITE SCHEDULE OF RATES


January - 2009

KOHISTAN DASU
(35)

Shabir Associates
Quantity Surveying & Construction Cost Consultants

Page 115
.

Page 116
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Kohistan
Kohistan dasu
dasu District Code: 35

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

101 CLEARING AND GRUBBING SM 1.07 11.31 - 3.10 15.48

102a REMOVAL OF TREES 150 - 300 mm GIRTH EACH 11.09 194.12 1.31 51.63 258.14

102b REMOVAL OF TREES 301 - 600 mm GIRTH EACH 31.25 511.33 2.94 136.38 681.90

102c REMOVAL OF TREES 601 mm OR OVER GIRTH EACH 125.02 2,045.30 11.77 545.52 2,727.61

103 STRIPPING CM 3.99 104.40 - 27.10 135.50

104 COMPACTION OF NATURAL GROUND SM 0.57 11.10 0.86 3.13 15.66

106a EXCAVATE UNSUITABLE COMMON MATERIAL CM 7.45 152.05 - 39.88 199.38

106bi EXCAVATE UNSUITABLE HARD ROCK MATERIAL CM 192.10 354.26 56.92 150.82 754.09

106bii EXCAVATE UNSUITABLE MEDIUM ROCK MATERIAL CM 25.67 378.55 - 101.06 505.28

106biii EXCAVATE UNSUITABLE SOFT ROCK MATERIAL CM 16.91 293.88 - 77.70 388.49

106c EXCAVATE SURPLUS COMMON MATERIAL CM 6.10 134.70 - 35.20 176.00

106di EXCAVATE SURPLUS HARD ROCK MATERIAL CM 192.10 354.26 56.92 150.82 754.09

106dii EXCAVATE SURPLUS MEDIUM ROCK MATERIAL CM 30.51 353.95 - 96.12 480.58

106diii EXCAVATE SURPLUS SOFT ROCK MATERIAL CM 13.04 295.59 - 77.16 385.79

107a STRUCTURAL EXCAVATION IN COMMON MATERIAL CM 11.98 154.11 0.43 41.63 208.14

107b STRUCTURAL EXCAVATION IN COMMON MATERIAL BELOW CM 94.34 321.57 79.30 123.80 619.01
WATER LEVEL

107ci STRUCTURAL EXCAVATION IN HARD ROCK MATERIAL CM 169.52 478.26 37.95 171.43 857.15

107cii STRUCTURAL EXCAVATION IN MEDIUM ROCK MATERIAL CM 142.21 327.64 - 117.46 587.31

107ciii STRUCTURAL EXCAVATION IN SOFT ROCK MATERIAL CM 87.18 267.53 - 88.68 443.38

107d GRANULAR BACK FILL CM 51.53 153.60 540.34 186.37 931.83

107e COMMON BACK FILL CM 37.24 70.38 5.70 28.33 141.65

108a FORMATION OF EMBANKMENT FROM ROADWAY CM 10.62 195.67 5.70 53.00 265.00
EXCAVATION IN COMMON MATERIAL

108bi FORMATION OF EMBANKMENT FROM ROADWAY CM 30.68 540.38 60.53 157.90 789.48
EXCAVATION IN HARD ROCK MATERIAL

108bii FORMATION OF EMBANKMENT FROM ROADWAY CM 23.01 466.72 2.71 123.11 615.55
EXCAVATION IN MEDIUM ROCK MATERIAL

108biii FORMATION OF EMBANKMENT FROM ROADWAY CM 20.45 413.66 - 108.53 542.65


EXCAVATION IN SOFT ROCK MATERIAL

108c FORMATION OF EMBANKMENT FROM BORROW CM 12.03 198.75 8.89 54.92 274.59
EXCAVATION IN COMMON MATERIAL

108d FORMATION OF EMBANKMENT FROM STRUCTURAL CM 9.59 85.47 5.70 25.19 125.96
EXCAVATION IN COMMON MATERIAL

108e FORMATION OF EMBANKMENT FROM STRUCTURAL CM 22.13 123.52 3.39 37.26 186.31
EXCAVATION IN ANY TYPE OF ROCK MATERIAL

109a SUB GRADE PREPARATION IN EARTH CUT SM 2.15 30.62 1.63 8.60 43.00

Page 117
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Kohistan
Kohistan dasu
dasu District Code: 35

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

109bi SUB GRADE PREPARATION IN EXISTING ROAD WITHOUT SM 1.60 20.39 0.87 5.71 28.57
ANY FILL

110 IMPROVED SUB-GRADE CM 15.43 134.42 58.41 52.07 260.33

114a DRESSING OF BERM WITHOUT EXTRA MATERIAL SM 1.33 17.09 0.89 4.83 24.14

114b DRESSING OF BERM WITH EXTRA BORROW MATERIAL SM 1.97 17.44 1.00 5.10 25.52

201 GRANULAR SUB-BASE CM 11.87 278.02 636.90 231.70 1,158.48

202 AGGREGATE BASE CM 13.97 355.93 855.16 306.26 1,531.32

203a ASPHALTIC BASE COURSE PLANT MIX (CLASS "A") CM 103.44 1,646.08 6,875.71 2,156.31 10,781.54

203b ASPHALTIC BASE COURSE PLANT MIX (CLASS "B") CM 107.05 1,646.08 7,338.58 2,272.93 11,364.64

203c ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "A") CM 114.83 1,719.24 6,864.90 2,174.74 10,873.71

203d ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "B") CM 114.83 1,712.72 7,500.48 2,332.01 11,660.05

204b CEMENT STABILIZED BASE CM 42.34 620.32 1,310.15 493.20 2,466.01

204d LIQUID ASPHALT FOR CURING SEAL, TYPE MC-250 TON 366.50 997.76 59,188.60 15,138.22 75,691.08

204e EMULSIFIED ASPHALT FOR CURING SEAL, TYPE SS-1 TON 366.50 997.76 57,468.44 14,708.18 73,540.88

205a GRADED CRUSHED AGGREGATE CRACK-RELIEF LAYER CM 133.65 122.95 1,160.29 354.22 1,771.10

205b ASPHALTIC OPEN-GRADED PLANT MIX CRACK-RELIEF CM 215.35 2,657.36 6,504.77 2,344.37 11,721.84
LAYER

206b WATER BOUND MACADAM BASE WITH COARSE CM 145.86 137.64 810.40 273.47 1,367.37
AGGREGATE CLASS B

207a DEEP PATCHING (0-15 cm) SM 2.63 49.09 1.37 13.27 66.36

207b DEEP PATCHING (16-30 cm) SM 2.63 43.25 1.37 11.81 59.06

208 REINSTATEMENT OF ROAD SURFACE SM 2.79 62.24 0.61 16.41 82.05

209a BREAKING OF EXISTING ROAD PAVEMENT STRUCTURE CM 3.46 120.57 0.74 31.19 155.95

209b SCARIFICATION OF EXISTING ROAD PAVEMENT SM 0.69 24.11 0.15 6.24 31.19

302a CUT-BACK ASPHALT FOR BITUMINOUS PRIME COAT SM 0.45 1.72 42.01 11.04 55.21

302b EMULSIFIED ASPHALT FOR BITUMINOUS PRIME COAT SM 0.43 1.72 46.89 12.26 61.30

303a CUT-BACK ASPHALT FOR BITUMINOUS TACK COAT SM 0.18 0.63 17.58 4.60 22.99

303b EMULSIFIED ASPHALT FOR BITUMINOUS TACK COAT SM 0.18 0.63 20.51 5.33 26.65

304a SINGLE SURFACE TREATMENT SM 1.16 8.26 84.54 23.49 117.45

304b DOUBLE SURFACE TREATMENT SM 1.69 15.43 164.52 45.41 227.05

304c TRIPLE SURFACE TREATMENT SM 2.87 21.73 187.80 53.10 265.50

304d SEAL COAT SM 1.08 4.49 59.51 16.27 81.34

Page 118
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Kohistan
Kohistan dasu
dasu District Code: 35

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

305a ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 97.95 1,623.37 8,049.70 2,442.75 12,213.77
"A")

305b ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 97.95 1,567.67 8,689.51 2,588.78 12,943.92
"B")

307a DENSE GRADED HOT BIT-MAC CM 240.34 413.95 6,715.99 1,842.57 9,212.85

307b OPEN GRADED HOT BIT-MAC CM 240.34 413.95 6,523.78 1,794.52 8,972.59

308a RECYCLING OF ASPHALT CONCRETE (0 - 60 mm THICK) CM 42.53 643.80 2,322.17 752.13 3,760.63

308b BITUMEN BINDER GRADE (40 - 50, 60 - 70, 80 - 100) TON 39.44 709.26 50,595.97 12,836.17 64,180.84

309a COLD MILLING, 0 - 30 mm SM 1.45 27.24 9.46 9.54 47.69

309b COLD MILLING, 0 - 50 mm SM 2.42 45.40 15.76 15.90 79.48

309c COLD MILLING, 0 - 70 mm SM 3.63 68.10 23.64 23.84 119.22

401a1i CONCRETE CLASS "A1" (Underground) CM 761.72 1,165.93 4,606.28 1,633.48 8,167.42

401a1ii CONCRETE CLASS "A1" (On ground) CM 761.72 1,165.93 4,911.50 1,709.79 8,548.94

401a1iii CONCRETE CLASS "A1" (Elevated) CM 761.72 1,165.93 5,521.94 1,862.40 9,311.99

401a2i CONCRETE CLASS "A2" (Underground) CM 761.72 1,165.93 5,022.08 1,737.43 8,687.17

401a2ii CONCRETE CLASS "A2" (On ground) CM 761.72 1,165.93 5,327.30 1,813.74 9,068.69

401a2iii CONCRETE CLASS "A2" (Elevated) CM 761.72 1,165.93 5,937.74 1,966.35 9,831.74

401a3i CONCRETE CLASS "A3" (Underground) CM 761.72 1,165.93 5,437.88 1,841.38 9,206.92

401a3ii CONCRETE CLASS "A3" (On ground) CM 761.72 1,165.93 5,743.10 1,917.69 9,588.44

401a3iii CONCRETE CLASS "A3" (Elevated) CM 761.72 1,165.93 6,353.54 2,070.30 10,351.49

401b CONCRETE CLASS "B" CM 1,010.98 886.52 3,766.84 1,416.09 7,080.43

401ci CONCRETE CLASS "C" (Underground) CM 756.12 550.60 4,146.95 1,363.42 6,817.09

401cii CONCRETE CLASS "C" (On ground) CM 756.12 550.60 4,277.13 1,395.96 6,979.81

401ciii CONCRETE CLASS "C" (Elevated) CM 756.12 550.60 4,537.48 1,461.05 7,305.25

401d CONCRETE CLASS "D1" CM 1,159.37 1,392.12 6,055.70 2,151.80 10,758.99

401e CONCRETE CLASS "Y" CM 1,591.92 550.60 5,453.68 1,899.05 9,495.25

401f LEAN CONCRETE CM 647.02 558.27 2,965.69 1,042.75 5,213.73

401gi(1) PRECAST CONCRETE CLASS "A-1" CM 2,528.19 1,041.87 5,732.19 2,325.56 11,627.81

401gi(3) PRECAST CONCRETE CLASS "A-3" CM 2,528.19 1,041.87 6,563.79 2,533.46 12,667.31

401gii PRECAST CONCRETE CLASS "B" CM 2,528.19 1,041.87 5,457.45 2,256.87 11,284.37

401giii(1) PRECAST CONCRETE CLASS "D1" CM 2,528.19 1,041.87 6,979.59 2,637.41 13,187.06

Page 119
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Kohistan
Kohistan dasu
dasu District Code: 35

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

401giii(2) PRECAST CONCRETE CLASS "D2" CM 2,528.19 1,041.87 7,395.39 2,741.36 13,706.81

401giii(3) PRECAST CONCRETE CLASS "D3" CM 2,528.19 1,041.87 7,811.19 2,845.31 14,226.56

404a REINFORCEMENT AS PER AASHTO M. 31 GRADE 40 TON 2,269.93 859.62 67,625.80 17,688.84 88,444.19

404b REINFORCEMENT AS PER AASHTO M. 31 GRADE 60 TON 2,269.93 859.62 75,710.80 19,710.09 98,550.44

404h REINFORCEMENT (STRUCTURAL SHAPES) AS PER ASTM-A- TON 1,791.78 5,933.20 62,730.55 17,613.88 88,069.41
36

405a PRE-STRESSING WIRE STRAND 3/8" - 1/2" DIA COMPLETE IN TON 3,585.21 17,224.95 147,324.91 42,033.77 210,168.84
ALL RESPECT

405b LAUNCHING OF GIRDER TON 83.27 585.78 - 167.26 836.31

406a PREMOULDED JOINT FILLER 12 mm THICK WITH SM 160.01 - 338.37 124.60 622.98
BITUMASTIC JOINT SEAL

406b NEOPRENE RUBBER JOINT FILLER 12 mm THICK WITH SM 160.01 - 337.24 124.31 621.57
BITUMASTIC JOINT SEAL

406c STEEL EXPANSION JOINTS KG 12.88 29.03 101.10 35.75 178.77

406d WATER STOPS 6" SIZE M 144.57 - 521.24 166.45 832.26

406e ELASTOMERIC BEARING PADS (ACCORDING TO SIZE AND ccm 0.03 - 2.33 0.59 2.95
THICKNESS)

406f ASPHALT FELT (3 PLY) SM 61.75 - 3,345.12 851.72 4,258.58

406g STEEL OR METAL BEARING DEVICES KG 27.56 76.65 129.89 58.53 292.63

407d1 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 461.25 1,819.45 1,094.63 843.83 4,219.16
(BORING ONLY) IN NORMAL SOIL

407d2 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 691.88 2,729.17 1,641.95 1,265.75 6,328.75
(BORING ONLY) IN GRAVEL STRATA

407d3 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 691.88 2,729.17 1,204.56 1,156.40 5,782.01
ONLY) IN NORMAL SOIL

407d4 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 1,153.13 4,548.62 1,403.66 1,776.35 8,881.76
ONLY) IN GRAVEL STRATA

407d5 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 988.40 5,373.43 1,607.96 1,992.45 9,962.24
ONLY) IN NORMAL SOIL

407d6 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 1,729.70 7,600.76 1,765.77 2,774.06 13,870.28
ONLY) IN GRAVEL SOIL

407h PILE LOAD TEST UP TO 120 TON EACH 32,702.74 50,346.23 117,420.05 50,117.26 250,586.28

407i PILE LOAD TEST UP TO 240 TON EACH 60,581.96 50,346.23 234,840.10 86,442.07 432,210.37

407j PILE LOAD TEST UP TO 360 TON EACH 88,461.19 55,207.22 352,260.15 123,982.14 619,910.70

407k CONFIRMATORY BORING (NX SIZE) M 264.58 1,740.22 7.00 502.95 2,514.75

410 BRICK WORK CM 502.21 311.00 3,670.43 1,120.91 5,604.53

411a STONE MASONRY RANDOM DRY CM 432.02 118.76 622.73 293.38 1,466.89

411b STONE MASONRY RANDOM WITH MORTAR CM 465.81 183.35 1,886.10 633.81 3,169.07

411c STONE MASONRY DRESSED UNCOURSED DRY CM 561.55 118.76 690.06 342.59 1,712.96

411d STONE MASONRY DRESSED UNCOURSED WITH MORTAR CM 660.10 183.35 1,931.97 693.86 3,469.28

Page 120
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Kohistan
Kohistan dasu
dasu District Code: 35

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

411g ROLL POINTING SM 106.78 12.92 50.37 42.52 212.59

412a STONE MASONRY DRESSED COURSED WITH MORTAR CM 885.37 290.49 1,827.69 750.89 3,754.44

501a R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 310 mm M 333.83 481.23 711.93 381.75 1,908.75

501b R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 380 mm M 323.67 634.90 922.63 470.30 2,351.50

501c R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 460 mm M 319.03 1,029.55 1,182.72 632.82 3,164.12

501d R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 610 mm M 332.27 1,261.03 1,764.92 839.55 4,197.77

501e R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 760 mm M 381.20 1,186.26 2,534.53 1,025.49 5,127.47

501f R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 910 mm M 470.90 1,464.43 3,985.92 1,480.31 7,401.57

501g R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1070 mm M 609.40 1,629.55 5,158.43 1,849.34 9,246.72

501h R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1220 mm M 715.85 1,978.74 6,573.15 2,316.93 11,584.67

501i R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1520 mm M 848.26 2,308.53 10,149.35 3,326.53 16,632.67

501j R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 310 mm M 333.83 558.07 803.28 423.80 2,118.98

501k R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 380 mm M 323.67 634.90 943.33 475.47 2,377.37

501l R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 460 mm M 309.99 1,029.55 1,154.75 623.58 3,117.88

501m R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 610 mm M 332.27 1,261.03 1,923.40 879.17 4,395.87

501n R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 760 mm M 381.20 1,186.26 3,655.27 1,305.68 6,528.41

501o R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 910 mm M 470.90 1,464.43 5,368.97 1,826.07 9,130.37

501p R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1070 mm M 609.40 1,629.55 7,499.70 2,434.66 12,173.31

501q R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1220 mm M 715.85 1,978.74 10,170.45 3,216.26 16,081.30

501r R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1520 mm M 848.26 2,308.53 14,306.10 4,365.72 21,828.60

502a GRANULAR MATERIAL IN BED TO CONCRETE PIPE CM 134.53 130.82 563.91 207.31 1,036.57
CULVERT

502b CONCRETE CLASS "B" IN BEDDING AND ENCASEMENT OF CM 1,133.63 674.24 4,151.84 1,489.93 7,449.64
CONCRETE PIPE CULVERT

507a STEEL WIRE MESH FOR GABIONS KG 7.55 - 122.35 32.47 162.37

507b ROCK FILL IN GABIONS CM 141.62 - 465.85 151.87 759.34

508a BRICK PAVING (SINGLE COURSE) SM 164.47 35.97 300.39 125.21 626.04

508b BRICK PAVING (DOUBLE COURSE) SM 294.00 35.97 595.85 231.46 1,157.28

509a RIP RAP CLASS "A" CM 716.62 - 518.44 308.77 1,543.83

509b RIP RAP CLASS "B" CM 689.31 - 514.30 300.90 1,504.51

509c RIP RAP CLASS "C" CM 693.63 - 518.44 303.02 1,515.09

Page 121
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Kohistan
Kohistan dasu
dasu District Code: 35

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

509d GROUTED RIP RAP CLASS "A" CM 873.06 112.36 2,134.72 780.03 3,900.17

509e GROUTED RIP RAP CLASS "B" CM 841.49 89.89 1,962.67 723.51 3,617.57

509f GROUTED RIP RAP CLASS "C" CM 830.77 74.91 2,015.68 730.34 3,651.70

509g REINFORCED CONCRETE SLOPE PROTECTION (WITHOUT CM 1,187.18 388.33 4,759.55 1,583.76 7,918.82
REINFORCEMENT)

509h FILTER LAYER OF GRANULAR MATERIAL CM 70.25 211.17 531.50 203.23 1,016.15

510 DISMANTLING OF STRUCTURE AND OBSTRUCTIONS CM 148.52 429.76 - 144.57 722.85

511a1 DRY STONE PITCHING (15-20 cm Thick) SM 227.79 74.22 84.25 96.57 482.83

511a2 DRY STONE PITCHING (21-25 cm Thick) SM 291.58 95.01 107.84 123.60 618.02

511b1 GROUTED STONE PITCHING (15-20 cm Thick) SM 370.42 198.35 438.94 251.93 1,259.65

511b2 GROUTED STONE PITCHING (21-25 cm Thick) SM 463.02 247.94 548.68 314.91 1,574.56

601ai CONCRETE KERB IN PLACE NEW JERSY BARRIER FOR M 415.87 648.78 2,647.31 927.99 4,639.94
MEDIAN (DOUBLE FACE)

601di PRECAST REINFORCED CONCRETE KERB NEW JERSY M 1,427.45 745.57 4,781.61 1,738.66 8,693.28
BARRIER FOR MEDIAN (DOUBLE FACE)

601dii PRECAST KERB IN CONCRETE CLASS A-1 OF SIZE 450 X 150 MM M 207.86 102.44 512.83 205.78 1,028.92
INCLUDING CONCRETE BEDDING & HAUNCHING

603 BRICK EDGING M 12.45 - 44.00 14.11 70.56

604a METAL GUARD RAIL M 24.72 72.97 1,626.74 431.11 2,155.53

604b METAL GUARD RAIL END PIECES EACH 32.01 - 1,233.50 316.38 1,581.90

604d STEEL POST OF METAL GUARD RAIL EACH 117.97 1,006.03 3,889.60 1,253.40 6,267.00

605a CONCRETE BEAM GUARD RAIL M 100.22 31.75 625.42 189.35 946.74

605c CONCRETE POST FOR GUARD RAIL M 123.05 28.18 628.29 194.88 974.41

607a TRAFFIC ROAD SIGN CATEGORY 1 EACH 312.67 262.80 7,087.58 1,915.76 9,578.82

607b TRAFFIC ROAD SIGN CATEGORY 2 EACH 101.93 394.21 9,587.80 2,520.98 12,604.92

607c TRAFFIC ROAD SIGN CATEGORY 3 (a) EACH 312.67 558.14 12,331.71 3,300.63 16,503.16

607d TRAFFIC ROAD SIGN CATEGORY 3 (b) EACH 1,010.74 616.60 21,728.96 5,839.08 29,195.39

607e TRAFFIC ROAD SIGN CATEGORY 3 (c) SM 202.15 123.32 9,531.12 2,464.15 12,320.73

607f ADDITIONAL PANEL SIZE 60 X 30 cm EACH 384.52 - 1,346.93 432.86 2,164.31

607g ADDITIONAL PANEL SIZE 90 X 30 cm EACH 384.52 - 2,020.39 601.23 3,006.14

608b1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 3.98 6.03 16.67 6.67 33.36
LINES OF 15 cm WIDTH

608b2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 1.33 4.15 41.05 11.63 58.16
LINES OF 15 cm WIDTH

608c1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 3.98 6.03 22.24 8.06 40.32
LINES OF 20 cm WIDTH

Page 122
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Kohistan
Kohistan dasu
dasu District Code: 35

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

608c2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 1.33 4.15 54.75 15.06 75.29
LINES OF 20 cm WIDTH

608d1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 94.07 5.37 161.05 65.12 325.62
4.0 M ARROWS

608d2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR 4.0 EACH 94.07 10.28 517.33 155.42 777.10
M ARROWS

608h1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 4.98 8.85 23.17 9.25 46.25
OF 15 cm WIDTH

608h2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 4.98 9.92 69.53 21.11 105.54
OF 15 cm WIDTH

608i1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 4.98 7.16 30.90 10.76 53.79
OF 20 cm WIDTH

608i2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 4.98 9.92 92.71 26.90 134.51
OF 20 cm WIDTH

608j1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR 4.0 M EACH 94.07 3.84 223.73 80.41 402.06
ARROWS

608j2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR 4.0 M EACH 94.07 8.13 876.74 244.74 1,223.68
ARROWS

608n1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 79.48 3.84 107.37 47.67 238.36
STOP

608n2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR EACH 79.48 8.13 345.41 108.26 541.28
STOP

608n3 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR STOP EACH 79.48 3.84 149.16 58.12 290.59

608n4 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR STOP EACH 79.48 8.13 585.37 168.25 841.24

609c REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 13.98 84.07 199.77 74.45 372.27
SINGLE)

609d REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 13.97 84.06 240.97 84.75 423.76
DOUBLE)

610b RIGHT OF WAY MARKER EACH 140.54 124.97 320.97 146.62 733.09

610c KILOMETRE POST (0.610 X 0.114 X 1.5 M) EACH 839.65 1,005.59 2,181.85 1,006.78 5,033.88

610d TEN KILOMETRE POST EACH 1,601.40 2,011.19 4,767.99 2,095.14 10,475.72

611a CHAIN LINK WIRE FABRIC FENCING 1500 MM HEIGHT M 189.55 99.10 1,023.53 328.04 1,640.22
WITH PRECAST PRESTRESSED R.C.C. POST

Page 123
.

Page 124
NATIONAL HIGHWAY AUTHORITY

COMPOSITE SCHEDULE OF RATES


January - 2009

LUCKY MURWAT
(41-B)

Shabir Associates
Quantity Surveying & Construction Cost Consultants

Page 125
.

Page 126
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Lucky
Lucky Murwat
Murwat District Code: 41-B

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

101 CLEARING AND GRUBBING SM 0.82 10.10 - 2.73 13.65

102a REMOVAL OF TREES 150 - 300 mm GIRTH EACH 8.04 173.32 1.17 45.63 228.16

102b REMOVAL OF TREES 301 - 600 mm GIRTH EACH 23.36 456.54 2.63 120.63 603.16

102c REMOVAL OF TREES 601 mm OR OVER GIRTH EACH 93.44 1,826.16 10.51 482.53 2,412.64

103 STRIPPING CM 2.76 93.22 - 23.99 119.97

104 COMPACTION OF NATURAL GROUND SM 0.39 9.91 0.76 2.77 13.83

106a EXCAVATE UNSUITABLE COMMON MATERIAL CM 4.54 135.76 - 35.07 175.37

106bi EXCAVATE UNSUITABLE HARD ROCK MATERIAL CM 132.61 316.30 50.82 124.93 624.67

106bii EXCAVATE UNSUITABLE MEDIUM ROCK MATERIAL CM 18.39 337.99 - 89.10 445.48

106biii EXCAVATE UNSUITABLE SOFT ROCK MATERIAL CM 11.98 262.40 - 68.59 342.97

106c EXCAVATE SURPLUS COMMON MATERIAL CM 3.72 120.27 - 31.00 154.98

106di EXCAVATE SURPLUS HARD ROCK MATERIAL CM 132.61 316.30 50.82 124.93 624.67

106dii EXCAVATE SURPLUS MEDIUM ROCK MATERIAL CM 21.06 316.03 - 84.27 421.36

106diii EXCAVATE SURPLUS SOFT ROCK MATERIAL CM 9.25 263.92 - 68.29 341.47

107a STRUCTURAL EXCAVATION IN COMMON MATERIAL CM 7.48 137.60 0.38 36.37 181.83

107b STRUCTURAL EXCAVATION IN COMMON MATERIAL BELOW CM 69.85 287.11 70.80 106.94 534.71
WATER LEVEL

107ci STRUCTURAL EXCAVATION IN HARD ROCK MATERIAL CM 117.00 427.01 33.88 144.47 722.37

107cii STRUCTURAL EXCAVATION IN MEDIUM ROCK MATERIAL CM 99.12 292.53 - 97.91 489.56

107ciii STRUCTURAL EXCAVATION IN SOFT ROCK MATERIAL CM 60.17 238.86 - 74.76 373.80

107d GRANULAR BACK FILL CM 37.50 137.14 341.14 128.94 644.72

107e COMMON BACK FILL CM 28.92 62.84 5.09 24.21 121.06

108a FORMATION OF EMBANKMENT FROM ROADWAY CM 7.19 174.71 5.09 46.75 233.74
EXCAVATION IN COMMON MATERIAL

108bi FORMATION OF EMBANKMENT FROM ROADWAY CM 21.58 482.48 54.04 139.53 697.63
EXCAVATION IN HARD ROCK MATERIAL

108bii FORMATION OF EMBANKMENT FROM ROADWAY CM 16.19 416.71 2.42 108.83 544.15
EXCAVATION IN MEDIUM ROCK MATERIAL

108biii FORMATION OF EMBANKMENT FROM ROADWAY CM 14.39 369.34 - 95.93 479.67


EXCAVATION IN SOFT ROCK MATERIAL

108c FORMATION OF EMBANKMENT FROM BORROW CM 8.36 177.46 7.94 48.44 242.20
EXCAVATION IN COMMON MATERIAL

108d FORMATION OF EMBANKMENT FROM STRUCTURAL CM 6.53 76.32 5.09 21.98 109.92
EXCAVATION IN COMMON MATERIAL

108e FORMATION OF EMBANKMENT FROM STRUCTURAL CM 15.59 110.29 3.03 32.23 161.13
EXCAVATION IN ANY TYPE OF ROCK MATERIAL

109a SUB GRADE PREPARATION IN EARTH CUT SM 1.47 27.34 1.46 7.57 37.83

Page 127
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Lucky
Lucky Murwat
Murwat District Code: 41-B

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

109bi SUB GRADE PREPARATION IN EXISTING ROAD WITHOUT SM 1.06 18.21 0.77 5.01 25.06
ANY FILL

110 IMPROVED SUB-GRADE CM 10.60 120.02 78.38 52.25 261.25

114a DRESSING OF BERM WITHOUT EXTRA MATERIAL SM 0.92 15.26 0.79 4.24 21.22

114b DRESSING OF BERM WITH EXTRA BORROW MATERIAL SM 1.34 15.57 0.90 4.45 22.25

201 GRANULAR SUB-BASE CM 8.43 255.06 542.53 201.50 1,007.52

202 AGGREGATE BASE CM 9.62 326.54 739.55 268.93 1,344.64

203a ASPHALTIC BASE COURSE PLANT MIX (CLASS "A") CM 80.25 1,510.17 6,200.76 1,947.80 9,738.98

203b ASPHALTIC BASE COURSE PLANT MIX (CLASS "B") CM 82.63 1,510.17 6,645.99 2,059.70 10,298.49

203c ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "A") CM 88.43 1,577.28 6,190.35 1,964.01 9,820.07

203d ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "B") CM 88.43 1,571.31 6,796.47 2,114.05 10,570.25

204b CEMENT STABILIZED BASE CM 29.94 569.10 1,009.72 402.19 2,010.96

204d LIQUID ASPHALT FOR CURING SEAL, TYPE MC-250 TON 258.08 915.38 55,149.87 14,080.83 70,404.16

204e EMULSIFIED ASPHALT FOR CURING SEAL, TYPE SS-1 TON 258.08 915.38 53,571.74 13,686.30 68,431.50

205a GRADED CRUSHED AGGREGATE CRACK-RELIEF LAYER CM 109.21 112.80 920.29 285.58 1,427.88

205b ASPHALTIC OPEN-GRADED PLANT MIX CRACK-RELIEF CM 160.09 2,437.94 5,848.76 2,111.70 10,558.50
LAYER

206b WATER BOUND MACADAM BASE WITH COARSE CM 120.75 126.27 719.09 241.53 1,207.65
AGGREGATE CLASS B

207a DEEP PATCHING (0-15 cm) SM 1.84 45.04 1.26 12.03 60.17

207b DEEP PATCHING (16-30 cm) SM 1.84 39.67 1.26 10.69 53.47

208 REINSTATEMENT OF ROAD SURFACE SM 1.93 57.10 0.56 14.90 74.49

209a BREAKING OF EXISTING ROAD PAVEMENT STRUCTURE CM 2.22 110.61 0.68 28.38 141.89

209b SCARIFICATION OF EXISTING ROAD PAVEMENT SM 0.44 22.12 0.14 5.68 28.38

302a CUT-BACK ASPHALT FOR BITUMINOUS PRIME COAT SM 0.31 1.57 39.14 10.26 51.28

302b EMULSIFIED ASPHALT FOR BITUMINOUS PRIME COAT SM 0.30 1.57 43.69 11.39 56.96

303a CUT-BACK ASPHALT FOR BITUMINOUS TACK COAT SM 0.12 0.58 16.38 4.27 21.36

303b EMULSIFIED ASPHALT FOR BITUMINOUS TACK COAT SM 0.12 0.58 19.11 4.95 24.77

304a SINGLE SURFACE TREATMENT SM 0.80 7.57 78.05 21.61 108.03

304b DOUBLE SURFACE TREATMENT SM 1.16 14.15 151.17 41.62 208.11

304c TRIPLE SURFACE TREATMENT SM 1.96 19.94 172.48 48.59 242.97

304d SEAL COAT SM 0.74 4.12 55.01 14.97 74.84

Page 128
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Lucky
Lucky Murwat
Murwat District Code: 41-B

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

305a ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 74.21 1,489.33 7,300.44 2,216.00 11,079.98
"A")

305b ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 74.21 1,438.23 7,888.15 2,350.15 11,750.74
"B")

307a DENSE GRADED HOT BIT-MAC CM 182.91 379.77 6,086.42 1,662.27 8,311.37

307b OPEN GRADED HOT BIT-MAC CM 182.91 379.77 5,911.72 1,618.60 8,093.00

308a RECYCLING OF ASPHALT CONCRETE (0 - 60 mm THICK) CM 30.69 590.65 2,123.13 686.12 3,430.59

308b BITUMEN BINDER GRADE (40 - 50, 60 - 70, 80 - 100) TON 28.39 650.70 47,291.92 11,992.75 59,963.76

309a COLD MILLING, 0 - 30 mm SM 1.00 24.99 8.68 8.67 43.33

309b COLD MILLING, 0 - 50 mm SM 1.67 41.65 14.46 14.44 72.22

309c COLD MILLING, 0 - 70 mm SM 2.50 62.48 21.69 21.67 108.34

401a1i CONCRETE CLASS "A1" (Underground) CM 585.32 1,059.94 3,924.75 1,392.50 6,962.51

401a1ii CONCRETE CLASS "A1" (On ground) CM 585.32 1,059.94 4,202.22 1,461.87 7,309.35

401a1iii CONCRETE CLASS "A1" (Elevated) CM 585.32 1,059.94 4,757.17 1,600.61 8,003.03

401a2i CONCRETE CLASS "A2" (Underground) CM 585.32 1,059.94 4,302.75 1,487.00 7,435.01

401a2ii CONCRETE CLASS "A2" (On ground) CM 585.32 1,059.94 4,580.22 1,556.37 7,781.85

401a2iii CONCRETE CLASS "A2" (Elevated) CM 585.32 1,059.94 5,135.17 1,695.11 8,475.53

401a3i CONCRETE CLASS "A3" (Underground) CM 585.32 1,059.94 4,680.75 1,581.50 7,907.51

401a3ii CONCRETE CLASS "A3" (On ground) CM 585.32 1,059.94 4,958.22 1,650.87 8,254.35

401a3iii CONCRETE CLASS "A3" (Elevated) CM 585.32 1,059.94 5,513.17 1,789.61 8,948.03

401b CONCRETE CLASS "B" CM 747.73 805.93 3,155.19 1,177.21 5,886.06

401ci CONCRETE CLASS "C" (Underground) CM 586.28 500.55 3,481.48 1,142.08 5,710.39

401cii CONCRETE CLASS "C" (On ground) CM 586.28 500.55 3,599.82 1,171.66 5,858.32

401ciii CONCRETE CLASS "C" (Elevated) CM 586.28 500.55 3,836.51 1,230.83 6,154.17

401d CONCRETE CLASS "D1" CM 928.64 1,265.57 5,266.77 1,865.24 9,326.21

401e CONCRETE CLASS "Y" CM 1,316.75 500.55 4,714.16 1,632.86 8,164.32

401f LEAN CONCRETE CM 503.54 507.52 2,425.97 859.26 4,296.29

401gi(1) PRECAST CONCRETE CLASS "A-1" CM 2,017.87 947.15 4,924.54 1,972.39 9,861.95

401gi(3) PRECAST CONCRETE CLASS "A-3" CM 2,017.87 947.15 5,680.54 2,161.39 10,806.95

401gii PRECAST CONCRETE CLASS "B" CM 2,017.87 947.15 4,681.42 1,911.61 9,558.05

401giii(1) PRECAST CONCRETE CLASS "D1" CM 2,017.87 947.15 6,058.54 2,255.89 11,279.45

Page 129
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Lucky
Lucky Murwat
Murwat District Code: 41-B

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

401giii(2) PRECAST CONCRETE CLASS "D2" CM 2,017.87 947.15 6,436.54 2,350.39 11,751.95

401giii(3) PRECAST CONCRETE CLASS "D3" CM 2,017.87 947.15 6,814.54 2,444.89 12,224.45

404a REINFORCEMENT AS PER AASHTO M. 31 GRADE 40 TON 1,802.64 781.47 60,842.00 15,856.53 79,282.64

404b REINFORCEMENT AS PER AASHTO M. 31 GRADE 60 TON 1,802.64 781.47 68,192.00 17,694.03 88,470.14

404h REINFORCEMENT (STRUCTURAL SHAPES) AS PER ASTM-A- TON 1,448.99 5,393.81 56,542.49 15,846.32 79,231.62
36

405a PRE-STRESSING WIRE STRAND 3/8" - 1/2" DIA COMPLETE IN TON 2,873.81 15,659.05 133,838.87 38,092.93 190,464.67
ALL RESPECT

405b LAUNCHING OF GIRDER TON 68.00 532.52 - 150.13 750.65

406a PREMOULDED JOINT FILLER 12 mm THICK WITH SM 131.45 - 305.68 109.28 546.41
BITUMASTIC JOINT SEAL

406b NEOPRENE RUBBER JOINT FILLER 12 mm THICK WITH SM 131.45 - 304.89 109.08 545.42
BITUMASTIC JOINT SEAL

406c STEEL EXPANSION JOINTS KG 10.88 26.40 91.31 32.15 160.73

406d WATER STOPS 6" SIZE M 110.37 - 469.93 145.07 725.37

406e ELASTOMERIC BEARING PADS (ACCORDING TO SIZE AND ccm 0.02 - 2.12 0.53 2.67
THICKNESS)

406f ASPHALT FELT (3 PLY) SM 47.29 - 3,065.71 778.25 3,891.26

406g STEEL OR METAL BEARING DEVICES KG 22.67 69.68 119.04 52.85 264.24

407d1 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 375.34 1,654.04 903.13 733.13 3,665.64
(BORING ONLY) IN NORMAL SOIL

407d2 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 563.00 2,481.06 1,354.70 1,099.69 5,498.45
(BORING ONLY) IN GRAVEL STRATA

407d3 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 563.00 2,481.06 1,002.75 1,011.70 5,058.52
ONLY) IN NORMAL SOIL

407d4 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 938.34 4,135.11 1,183.21 1,564.16 7,820.82
ONLY) IN GRAVEL STRATA

407d5 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 804.29 4,884.94 1,368.56 1,764.45 8,822.24
ONLY) IN NORMAL SOIL

407d6 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 1,407.51 6,909.78 1,500.29 2,454.40 12,271.98
ONLY) IN GRAVEL SOIL

407h PILE LOAD TEST UP TO 120 TON EACH 26,948.44 45,769.30 90,203.26 40,730.25 203,651.26

407i PILE LOAD TEST UP TO 240 TON EACH 50,661.04 45,769.30 180,406.52 69,209.22 346,046.08

407j PILE LOAD TEST UP TO 360 TON EACH 74,373.63 50,188.38 270,609.78 98,792.95 493,964.74

407k CONFIRMATORY BORING (NX SIZE) M 225.35 1,582.02 6.37 453.43 2,267.17

410 BRICK WORK CM 389.20 282.72 3,119.01 947.73 4,738.67

411a STONE MASONRY RANDOM DRY CM 328.42 107.96 551.78 247.04 1,235.20

411b STONE MASONRY RANDOM WITH MORTAR CM 353.70 166.68 1,578.12 524.62 2,623.12

411c STONE MASONRY DRESSED UNCOURSED DRY CM 431.67 107.96 613.00 288.16 1,440.79

411d STONE MASONRY DRESSED UNCOURSED WITH MORTAR CM 508.57 166.68 1,650.38 581.41 2,907.04

Page 130
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Lucky
Lucky Murwat
Murwat District Code: 41-B

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

411g ROLL POINTING SM 83.41 11.74 43.75 34.72 173.62

412a STONE MASONRY DRESSED COURSED WITH MORTAR CM 689.78 264.08 1,555.58 627.36 3,136.80

501a R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 310 mm M 265.21 437.48 643.39 336.52 1,682.61

501b R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 380 mm M 259.02 577.19 834.17 417.59 2,087.97

501c R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 460 mm M 248.57 935.96 1,069.85 563.60 2,817.98

501d R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 610 mm M 261.90 1,146.39 1,598.23 751.63 3,758.15

501e R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 760 mm M 299.40 1,078.41 2,297.87 918.92 4,594.60

501f R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 910 mm M 368.40 1,331.30 3,614.54 1,328.56 6,642.80

501g R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1070 mm M 476.75 1,481.41 4,680.50 1,659.66 8,298.32

501h R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1220 mm M 560.86 1,798.85 5,964.68 2,081.10 10,405.49

501i R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1520 mm M 665.51 2,098.66 9,213.95 2,994.53 14,972.66

501j R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 310 mm M 265.21 507.33 722.10 373.66 1,868.31

501k R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 380 mm M 259.02 577.19 852.99 422.30 2,111.50

501l R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 460 mm M 242.64 935.96 1,044.43 555.76 2,778.79

501m R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 610 mm M 261.90 1,146.39 1,743.69 788.00 3,939.98

501n R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 760 mm M 299.40 1,078.41 3,316.03 1,173.46 5,867.31

501o R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 910 mm M 368.40 1,331.30 4,871.85 1,642.89 8,214.44

501p R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1070 mm M 476.75 1,481.41 6,808.93 2,191.77 10,958.86

501q R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1220 mm M 560.86 1,798.85 9,234.95 2,898.67 14,493.33

501r R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1520 mm M 665.51 2,098.66 12,992.82 3,939.25 19,696.24

502a GRANULAR MATERIAL IN BED TO CONCRETE PIPE CM 102.61 118.93 287.07 127.15 635.75
CULVERT

502b CONCRETE CLASS "B" IN BEDDING AND ENCASEMENT OF CM 851.42 612.95 3,505.19 1,242.39 6,211.95
CONCRETE PIPE CULVERT

507a STEEL WIRE MESH FOR GABIONS KG 6.08 - 110.38 29.11 145.57

507b ROCK FILL IN GABIONS CM 111.92 - 352.92 116.21 581.04

508a BRICK PAVING (SINGLE COURSE) SM 128.91 32.70 250.12 102.93 514.66

508b BRICK PAVING (DOUBLE COURSE) SM 232.15 32.70 497.64 190.62 953.12

509a RIP RAP CLASS "A" CM 559.82 - 456.98 254.20 1,271.00

509b RIP RAP CLASS "B" CM 540.99 - 453.32 248.58 1,242.89

509c RIP RAP CLASS "C" CM 545.29 - 456.98 250.57 1,252.83

Page 131
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Lucky
Lucky Murwat
Murwat District Code: 41-B

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

509d GROUTED RIP RAP CLASS "A" CM 683.69 102.14 1,849.95 658.95 3,294.73

509e GROUTED RIP RAP CLASS "B" CM 660.31 81.72 1,701.61 610.91 3,054.54

509f GROUTED RIP RAP CLASS "C" CM 653.50 68.10 1,746.83 617.11 3,085.54

509g REINFORCED CONCRETE SLOPE PROTECTION (WITHOUT CM 911.79 353.02 4,072.29 1,334.28 6,671.38
REINFORCEMENT)

509h FILTER LAYER OF GRANULAR MATERIAL CM 55.09 191.97 341.18 147.06 735.30

510 DISMANTLING OF STRUCTURE AND OBSTRUCTIONS CM 121.36 390.69 - 128.01 640.07

511a1 DRY STONE PITCHING (15-20 cm Thick) SM 175.23 67.48 74.26 79.24 396.21

511a2 DRY STONE PITCHING (21-25 cm Thick) SM 224.30 86.37 95.05 101.43 507.14

511b1 GROUTED STONE PITCHING (15-20 cm Thick) SM 285.81 180.32 371.64 209.44 1,047.22

511b2 GROUTED STONE PITCHING (21-25 cm Thick) SM 357.27 225.40 464.55 261.81 1,309.03

601ai CONCRETE KERB IN PLACE NEW JERSY BARRIER FOR M 310.41 572.25 2,199.64 770.57 3,852.87
MEDIAN (DOUBLE FACE)

601di PRECAST REINFORCED CONCRETE KERB NEW JERSY M 1,107.10 670.54 4,065.84 1,460.87 7,304.35
BARRIER FOR MEDIAN (DOUBLE FACE)

601dii PRECAST KERB IN CONCRETE CLASS A-1 OF SIZE 450 X 150 MM M 160.54 90.27 425.82 169.16 845.78
INCLUDING CONCRETE BEDDING & HAUNCHING

603 BRICK EDGING M 10.17 - 40.42 12.65 63.24

604a METAL GUARD RAIL M 20.23 70.84 1,579.36 417.61 2,088.04

604b METAL GUARD RAIL END PIECES EACH 28.15 - 1,197.58 306.43 1,532.15

604d STEEL POST OF METAL GUARD RAIL EACH 92.54 976.73 3,776.31 1,211.39 6,056.97

605a CONCRETE BEAM GUARD RAIL M 87.77 30.82 594.26 178.21 891.06

605c CONCRETE POST FOR GUARD RAIL M 107.77 27.36 594.53 182.42 912.08

607a TRAFFIC ROAD SIGN CATEGORY 1 EACH 270.26 255.15 6,855.57 1,845.24 9,226.22

607b TRAFFIC ROAD SIGN CATEGORY 2 EACH 79.67 382.72 9,245.65 2,427.01 12,135.05

607c TRAFFIC ROAD SIGN CATEGORY 3 (a) EACH 270.26 541.89 11,866.42 3,169.64 15,848.21

607d TRAFFIC ROAD SIGN CATEGORY 3 (b) EACH 903.84 598.64 20,927.09 5,607.39 28,036.97

607e TRAFFIC ROAD SIGN CATEGORY 3 (c) SM 180.77 119.73 9,206.60 2,376.77 11,883.87

607f ADDITIONAL PANEL SIZE 60 X 30 cm EACH 316.02 - 1,303.98 405.00 2,024.99

607g ADDITIONAL PANEL SIZE 90 X 30 cm EACH 316.02 - 1,955.96 567.99 2,839.97

608b1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 3.08 5.86 16.17 6.28 31.38
LINES OF 15 cm WIDTH

608b2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 1.03 4.03 39.77 11.21 56.03
LINES OF 15 cm WIDTH

608c1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 3.08 5.86 21.58 7.63 38.14
LINES OF 20 cm WIDTH

Page 132
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Lucky
Lucky Murwat
Murwat District Code: 41-B

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

608c2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 1.03 4.03 53.05 14.53 72.63
LINES OF 20 cm WIDTH

608d1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 89.41 5.22 156.28 62.73 313.63
4.0 M ARROWS

608d2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR 4.0 EACH 89.41 9.98 501.20 150.15 750.75
M ARROWS

608h1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.84 8.59 22.49 8.73 43.65
OF 15 cm WIDTH

608h2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.84 9.63 67.50 20.24 101.22
OF 15 cm WIDTH

608i1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.84 6.95 29.99 10.20 50.98
OF 20 cm WIDTH

608i2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.84 9.63 90.01 25.87 129.35
OF 20 cm WIDTH

608j1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR 4.0 M EACH 89.41 3.73 217.14 77.57 387.84
ARROWS

608j2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR 4.0 M EACH 89.41 7.90 851.20 237.13 1,185.64
ARROWS

608n1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 74.25 3.73 104.19 45.54 227.70
STOP

608n2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR EACH 74.25 7.90 334.64 104.20 520.98
STOP

608n3 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR STOP EACH 74.25 3.73 144.76 55.68 278.41

608n4 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR STOP EACH 74.25 7.90 568.32 162.62 813.09

609c REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 10.34 81.62 193.80 71.44 357.20
SINGLE)

609d REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 10.34 81.62 233.80 81.44 407.19
DOUBLE)

610b RIGHT OF WAY MARKER EACH 121.74 121.33 300.09 135.79 678.95

610c KILOMETRE POST (0.610 X 0.114 X 1.5 M) EACH 745.53 976.31 2,018.48 935.08 4,675.39

610d TEN KILOMETRE POST EACH 1,440.50 1,952.61 4,434.84 1,956.99 9,784.95

611a CHAIN LINK WIRE FABRIC FENCING 1500 MM HEIGHT M 151.04 91.00 950.20 298.06 1,490.31
WITH PRECAST PRESTRESSED R.C.C. POST

Page 133
.

Page 134
NATIONAL HIGHWAY AUTHORITY

COMPOSITE SCHEDULE OF RATES


January - 2009

MALAKAND
(42)

Shabir Associates
Quantity Surveying & Construction Cost Consultants

Page 135
.

Page 136
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Malakand
Malakand District Code: 42

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

101 CLEARING AND GRUBBING SM 0.59 10.10 - 2.67 13.37

102a REMOVAL OF TREES 150 - 300 mm GIRTH EACH 6.10 173.32 1.17 45.15 225.74

102b REMOVAL OF TREES 301 - 600 mm GIRTH EACH 17.23 456.54 2.63 119.10 595.50

102c REMOVAL OF TREES 601 mm OR OVER GIRTH EACH 68.93 1,826.16 10.51 476.40 2,382.00

103 STRIPPING CM 2.22 93.22 - 23.86 119.30

104 COMPACTION OF NATURAL GROUND SM 0.32 9.91 0.76 2.75 13.74

106a EXCAVATE UNSUITABLE COMMON MATERIAL CM 4.09 135.76 - 34.96 174.81

106bi EXCAVATE UNSUITABLE HARD ROCK MATERIAL CM 108.10 316.30 50.82 118.81 594.03

106bii EXCAVATE UNSUITABLE MEDIUM ROCK MATERIAL CM 14.48 337.99 - 88.12 440.60

106biii EXCAVATE UNSUITABLE SOFT ROCK MATERIAL CM 9.55 262.40 - 67.99 339.93

106c EXCAVATE SURPLUS COMMON MATERIAL CM 3.34 120.27 - 30.90 154.52

106di EXCAVATE SURPLUS HARD ROCK MATERIAL CM 108.10 316.30 50.82 118.81 594.03

106dii EXCAVATE SURPLUS MEDIUM ROCK MATERIAL CM 17.16 316.03 - 83.30 416.49

106diii EXCAVATE SURPLUS SOFT ROCK MATERIAL CM 7.35 263.92 - 67.82 339.10

107a STRUCTURAL EXCAVATION IN COMMON MATERIAL CM 6.61 137.60 0.38 36.15 180.74

107b STRUCTURAL EXCAVATION IN COMMON MATERIAL BELOW CM 55.47 287.11 70.80 103.35 516.73
WATER LEVEL

107ci STRUCTURAL EXCAVATION IN HARD ROCK MATERIAL CM 95.34 427.01 33.88 139.06 695.29

107cii STRUCTURAL EXCAVATION IN MEDIUM ROCK MATERIAL CM 80.06 292.53 - 93.15 465.74

107ciii STRUCTURAL EXCAVATION IN SOFT ROCK MATERIAL CM 49.03 238.86 - 71.97 359.87

107d GRANULAR BACK FILL CM 28.65 137.14 395.98 140.44 702.21

107e COMMON BACK FILL CM 20.69 62.84 5.09 22.15 110.77

108a FORMATION OF EMBANKMENT FROM ROADWAY CM 5.92 174.71 5.09 46.43 232.15
EXCAVATION IN COMMON MATERIAL

108bi FORMATION OF EMBANKMENT FROM ROADWAY CM 17.17 482.48 54.04 138.42 692.11
EXCAVATION IN HARD ROCK MATERIAL

108bii FORMATION OF EMBANKMENT FROM ROADWAY CM 12.88 416.71 2.42 108.00 540.01
EXCAVATION IN MEDIUM ROCK MATERIAL

108biii FORMATION OF EMBANKMENT FROM ROADWAY CM 11.44 369.34 - 95.20 475.99


EXCAVATION IN SOFT ROCK MATERIAL

108c FORMATION OF EMBANKMENT FROM BORROW CM 6.70 177.46 7.94 48.02 240.12
EXCAVATION IN COMMON MATERIAL

108d FORMATION OF EMBANKMENT FROM STRUCTURAL CM 5.37 76.32 5.09 21.69 108.47
EXCAVATION IN COMMON MATERIAL

108e FORMATION OF EMBANKMENT FROM STRUCTURAL CM 12.33 110.29 3.03 31.41 157.05
EXCAVATION IN ANY TYPE OF ROCK MATERIAL

109a SUB GRADE PREPARATION IN EARTH CUT SM 1.20 27.34 1.46 7.50 37.49

Page 137
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Malakand
Malakand District Code: 42

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

109bi SUB GRADE PREPARATION IN EXISTING ROAD WITHOUT SM 0.89 18.21 0.77 4.97 24.84
ANY FILL

110 IMPROVED SUB-GRADE CM 8.50 120.02 77.43 51.49 257.44

114a DRESSING OF BERM WITHOUT EXTRA MATERIAL SM 0.75 15.26 0.79 4.20 21.00

114b DRESSING OF BERM WITH EXTRA BORROW MATERIAL SM 1.10 15.57 0.90 4.39 21.95

201 GRANULAR SUB-BASE CM 6.77 255.06 528.84 197.67 988.34

202 AGGREGATE BASE CM 7.84 326.54 716.61 262.75 1,313.74

203a ASPHALTIC BASE COURSE PLANT MIX (CLASS "A") CM 58.31 1,510.17 6,021.56 1,897.51 9,487.54

203b ASPHALTIC BASE COURSE PLANT MIX (CLASS "B") CM 60.29 1,510.17 6,435.32 2,001.44 10,007.22

203c ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "A") CM 64.88 1,577.28 6,011.52 1,913.42 9,567.11

203d ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "B") CM 64.88 1,571.31 6,582.07 2,054.56 10,272.82

204b CEMENT STABILIZED BASE CM 23.80 569.10 1,028.28 405.30 2,026.49

204d LIQUID ASPHALT FOR CURING SEAL, TYPE MC-250 TON 210.59 915.38 52,944.03 13,517.50 67,587.50

204e EMULSIFIED ASPHALT FOR CURING SEAL, TYPE SS-1 TON 210.59 915.38 51,365.90 13,122.97 65,614.84

205a GRADED CRUSHED AGGREGATE CRACK-RELIEF LAYER CM 76.35 112.80 897.86 271.75 1,358.76

205b ASPHALTIC OPEN-GRADED PLANT MIX CRACK-RELIEF CM 121.06 2,437.94 5,683.23 2,060.56 10,302.80
LAYER

206b WATER BOUND MACADAM BASE WITH COARSE CM 83.33 126.27 756.53 241.53 1,207.66
AGGREGATE CLASS B

207a DEEP PATCHING (0-15 cm) SM 1.52 45.04 1.26 11.95 59.77

207b DEEP PATCHING (16-30 cm) SM 1.52 39.67 1.26 10.61 53.07

208 REINSTATEMENT OF ROAD SURFACE SM 1.57 57.10 0.56 14.81 74.05

209a BREAKING OF EXISTING ROAD PAVEMENT STRUCTURE CM 2.00 110.61 0.68 28.32 141.61

209b SCARIFICATION OF EXISTING ROAD PAVEMENT SM 0.40 22.12 0.14 5.66 28.32

302a CUT-BACK ASPHALT FOR BITUMINOUS PRIME COAT SM 0.25 1.57 37.58 9.85 49.25

302b EMULSIFIED ASPHALT FOR BITUMINOUS PRIME COAT SM 0.24 1.57 41.94 10.94 54.70

303a CUT-BACK ASPHALT FOR BITUMINOUS TACK COAT SM 0.10 0.58 15.73 4.10 20.51

303b EMULSIFIED ASPHALT FOR BITUMINOUS TACK COAT SM 0.10 0.58 18.35 4.76 23.79

304a SINGLE SURFACE TREATMENT SM 0.65 7.57 74.71 20.73 103.67

304b DOUBLE SURFACE TREATMENT SM 0.95 14.15 144.54 39.91 199.55

304c TRIPLE SURFACE TREATMENT SM 1.61 19.94 164.91 46.61 233.07

304d SEAL COAT SM 0.60 4.12 52.93 14.41 72.07

Page 138
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Malakand
Malakand District Code: 42

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

305a ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 55.04 1,489.33 7,064.48 2,152.21 10,761.06
"A")

305b ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 55.04 1,438.23 7,628.62 2,280.47 11,402.36
"B")

307a DENSE GRADED HOT BIT-MAC CM 133.73 379.77 5,867.54 1,595.26 7,976.30

307b OPEN GRADED HOT BIT-MAC CM 133.73 379.77 5,688.56 1,550.52 7,752.58

308a RECYCLING OF ASPHALT CONCRETE (0 - 60 mm THICK) CM 23.37 590.65 2,066.44 670.11 3,350.57

308b BITUMEN BINDER GRADE (40 - 50, 60 - 70, 80 - 100) TON 22.51 650.70 45,020.56 11,423.44 57,117.21

309a COLD MILLING, 0 - 30 mm SM 0.81 24.99 8.68 8.62 43.09

309b COLD MILLING, 0 - 50 mm SM 1.35 41.65 14.46 14.36 71.82

309c COLD MILLING, 0 - 70 mm SM 2.02 62.48 21.69 21.55 107.74

401a1i CONCRETE CLASS "A1" (Underground) CM 470.65 1,059.94 3,957.32 1,371.98 6,859.88

401a1ii CONCRETE CLASS "A1" (On ground) CM 470.65 1,059.94 4,234.80 1,441.34 7,206.72

401a1iii CONCRETE CLASS "A1" (Elevated) CM 470.65 1,059.94 4,789.74 1,580.08 7,900.40

401a2i CONCRETE CLASS "A2" (Underground) CM 470.65 1,059.94 4,335.32 1,466.48 7,332.38

401a2ii CONCRETE CLASS "A2" (On ground) CM 470.65 1,059.94 4,612.80 1,535.84 7,679.22

401a2iii CONCRETE CLASS "A2" (Elevated) CM 470.65 1,059.94 5,167.74 1,674.58 8,372.90

401a3i CONCRETE CLASS "A3" (Underground) CM 470.65 1,059.94 4,713.32 1,560.98 7,804.88

401a3ii CONCRETE CLASS "A3" (On ground) CM 470.65 1,059.94 4,990.80 1,630.34 8,151.72

401a3iii CONCRETE CLASS "A3" (Elevated) CM 470.65 1,059.94 5,545.74 1,769.08 8,845.40

401b CONCRETE CLASS "B" CM 597.07 805.93 3,160.51 1,140.88 5,704.39

401ci CONCRETE CLASS "C" (Underground) CM 464.47 500.55 3,496.88 1,115.47 5,577.37

401cii CONCRETE CLASS "C" (On ground) CM 464.47 500.55 3,615.22 1,145.06 5,725.30

401ciii CONCRETE CLASS "C" (Elevated) CM 464.47 500.55 3,851.91 1,204.23 6,021.15

401d CONCRETE CLASS "D1" CM 738.77 1,265.57 5,292.74 1,824.27 9,121.35

401e CONCRETE CLASS "Y" CM 1,028.48 500.55 4,752.87 1,570.47 7,852.37

401f LEAN CONCRETE CM 379.67 507.52 2,431.20 829.60 4,147.98

401gi(1) PRECAST CONCRETE CLASS "A-1" CM 1,560.36 947.15 4,962.45 1,867.49 9,337.46

401gi(3) PRECAST CONCRETE CLASS "A-3" CM 1,560.36 947.15 5,718.45 2,056.49 10,282.46

401gii PRECAST CONCRETE CLASS "B" CM 1,560.36 947.15 4,685.02 1,798.13 8,990.67

401giii(1) PRECAST CONCRETE CLASS "D1" CM 1,560.36 947.15 6,096.45 2,150.99 10,754.96

Page 139
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Malakand
Malakand District Code: 42

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

401giii(2) PRECAST CONCRETE CLASS "D2" CM 1,560.36 947.15 6,474.45 2,245.49 11,227.46

401giii(3) PRECAST CONCRETE CLASS "D3" CM 1,560.36 947.15 6,852.45 2,339.99 11,699.96

404a REINFORCEMENT AS PER AASHTO M. 31 GRADE 40 TON 1,445.94 781.47 60,736.00 15,740.85 78,704.26

404b REINFORCEMENT AS PER AASHTO M. 31 GRADE 60 TON 1,445.94 781.47 68,086.00 17,578.35 87,891.76

404h REINFORCEMENT (STRUCTURAL SHAPES) AS PER ASTM-A- TON 1,147.38 5,393.81 56,467.29 15,752.12 78,760.60
36

405a PRE-STRESSING WIRE STRAND 3/8" - 1/2" DIA COMPLETE IN TON 2,333.44 15,659.05 133,885.80 37,969.57 189,847.87
ALL RESPECT

405b LAUNCHING OF GIRDER TON 55.05 532.52 - 146.89 734.46

406a PREMOULDED JOINT FILLER 12 mm THICK WITH SM 100.44 - 304.79 101.31 506.54
BITUMASTIC JOINT SEAL

406b NEOPRENE RUBBER JOINT FILLER 12 mm THICK WITH SM 100.44 - 303.87 101.08 505.38
BITUMASTIC JOINT SEAL

406c STEEL EXPANSION JOINTS KG 8.34 26.40 91.44 31.54 157.71

406d WATER STOPS 6" SIZE M 88.41 - 472.65 140.27 701.33

406e ELASTOMERIC BEARING PADS (ACCORDING TO SIZE AND ccm 0.01 - 2.12 0.53 2.67
THICKNESS)

406f ASPHALT FELT (3 PLY) SM 38.88 - 2,992.67 757.89 3,789.44

406g STEEL OR METAL BEARING DEVICES KG 16.84 69.68 118.30 51.21 256.03

407d1 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 306.83 1,654.04 910.36 717.81 3,589.04
(BORING ONLY) IN NORMAL SOIL

407d2 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 460.24 2,481.06 1,365.55 1,076.71 5,383.56
(BORING ONLY) IN GRAVEL STRATA

407d3 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 460.24 2,481.06 1,013.47 988.69 4,943.46
ONLY) IN NORMAL SOIL

407d4 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 767.06 4,135.11 1,201.08 1,525.81 7,629.07
ONLY) IN GRAVEL STRATA

407d5 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 657.48 4,884.94 1,400.09 1,735.63 8,678.15
ONLY) IN NORMAL SOIL

407d6 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 1,150.59 6,909.78 1,527.11 2,396.87 11,984.35
ONLY) IN GRAVEL SOIL

407h PILE LOAD TEST UP TO 120 TON EACH 18,577.21 45,769.30 98,475.26 40,705.44 203,527.21

407i PILE LOAD TEST UP TO 240 TON EACH 34,351.60 45,769.30 196,950.52 69,267.86 346,339.28

407j PILE LOAD TEST UP TO 360 TON EACH 50,125.99 50,188.38 295,425.78 98,935.04 494,675.20

407k CONFIRMATORY BORING (NX SIZE) M 167.77 1,582.02 6.37 439.04 2,195.20

410 BRICK WORK CM 313.25 282.72 3,084.04 920.00 4,600.02

411a STONE MASONRY RANDOM DRY CM 262.81 107.96 534.02 226.20 1,130.99

411b STONE MASONRY RANDOM WITH MORTAR CM 285.56 166.68 1,579.15 507.85 2,539.24

411c STONE MASONRY DRESSED UNCOURSED DRY CM 343.37 107.96 593.83 261.29 1,306.45

411d STONE MASONRY DRESSED UNCOURSED WITH MORTAR CM 406.40 166.68 1,645.31 554.60 2,772.98

Page 140
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Malakand
Malakand District Code: 42

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

411g ROLL POINTING SM 67.68 11.74 44.06 30.87 154.36

412a STONE MASONRY DRESSED COURSED WITH MORTAR CM 544.76 264.08 1,550.50 589.84 2,949.18

501a R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 310 mm M 192.55 437.48 643.98 318.50 1,592.52

501b R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 380 mm M 186.80 577.19 834.87 399.72 1,998.58

501c R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 460 mm M 184.85 935.96 1,070.67 547.87 2,739.36

501d R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 610 mm M 191.95 1,146.39 1,599.19 734.38 3,671.91

501e R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 760 mm M 219.17 1,078.41 2,298.83 899.10 4,495.52

501f R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 910 mm M 271.40 1,331.30 3,615.93 1,304.66 6,523.28

501g R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1070 mm M 351.22 1,481.41 4,681.88 1,628.63 8,143.13

501h R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1220 mm M 410.23 1,798.85 5,966.36 2,043.86 10,219.30

501i R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1520 mm M 489.73 2,098.66 9,215.91 2,951.08 14,755.38

501j R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 310 mm M 192.55 507.33 723.27 355.79 1,778.94

501k R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 380 mm M 186.80 577.19 853.69 404.42 2,022.10

501l R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 460 mm M 180.16 935.96 1,045.25 540.34 2,701.71

501m R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 610 mm M 191.95 1,146.39 1,744.43 770.69 3,853.47

501n R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 760 mm M 219.17 1,078.41 3,317.10 1,153.67 5,768.36

501o R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 910 mm M 271.40 1,331.30 4,873.24 1,618.98 8,094.92

501p R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1070 mm M 351.22 1,481.41 6,810.31 2,160.73 10,803.67

501q R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1220 mm M 410.23 1,798.85 9,236.63 2,861.43 14,307.14

501r R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1520 mm M 489.73 2,098.66 12,994.77 3,895.79 19,478.96

502a GRANULAR MATERIAL IN BED TO CONCRETE PIPE CM 76.13 118.93 399.87 148.73 743.66
CULVERT

502b CONCRETE CLASS "B" IN BEDDING AND ENCASEMENT OF CM 679.54 612.95 3,510.51 1,200.75 6,003.75
CONCRETE PIPE CULVERT

507a STEEL WIRE MESH FOR GABIONS KG 4.67 - 109.86 28.63 143.16

507b ROCK FILL IN GABIONS CM 80.15 - 352.92 108.27 541.34

508a BRICK PAVING (SINGLE COURSE) SM 100.24 32.70 249.17 95.53 477.65

508b BRICK PAVING (DOUBLE COURSE) SM 180.80 32.70 494.80 177.08 885.38

509a RIP RAP CLASS "A" CM 441.59 - 439.21 220.20 1,101.00

509b RIP RAP CLASS "B" CM 424.73 - 435.70 215.11 1,075.53

509c RIP RAP CLASS "C" CM 428.65 - 439.21 216.97 1,084.83

Page 141
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Malakand
Malakand District Code: 42

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

509d GROUTED RIP RAP CLASS "A" CM 537.11 102.14 1,843.94 620.80 3,103.99

509e GROUTED RIP RAP CLASS "B" CM 519.35 81.72 1,694.51 573.89 2,869.47

509f GROUTED RIP RAP CLASS "C" CM 513.35 68.10 1,740.03 580.37 2,901.84

509g REINFORCED CONCRETE SLOPE PROTECTION (WITHOUT CM 709.53 353.02 4,077.28 1,284.96 6,424.80
REINFORCEMENT)

509h FILTER LAYER OF GRANULAR MATERIAL CM 39.62 191.97 396.45 157.01 785.06

510 DISMANTLING OF STRUCTURE AND OBSTRUCTIONS CM 92.82 390.69 - 120.88 604.39

511a1 DRY STONE PITCHING (15-20 cm Thick) SM 138.03 67.48 71.37 69.22 346.09

511a2 DRY STONE PITCHING (21-25 cm Thick) SM 176.67 86.37 91.36 88.60 443.00

511b1 GROUTED STONE PITCHING (15-20 cm Thick) SM 227.10 180.32 371.17 194.65 973.24

511b2 GROUTED STONE PITCHING (21-25 cm Thick) SM 283.87 225.40 463.97 243.31 1,216.55

601ai CONCRETE KERB IN PLACE NEW JERSY BARRIER FOR M 249.42 572.25 2,216.57 759.56 3,797.80
MEDIAN (DOUBLE FACE)

601di PRECAST REINFORCED CONCRETE KERB NEW JERSY M 858.11 670.54 4,083.35 1,403.00 7,015.00
BARRIER FOR MEDIAN (DOUBLE FACE)

601dii PRECAST KERB IN CONCRETE CLASS A-1 OF SIZE 450 X 150 MM M 124.48 90.27 428.88 160.91 804.54
INCLUDING CONCRETE BEDDING & HAUNCHING

603 BRICK EDGING M 7.89 - 39.46 11.84 59.18

604a METAL GUARD RAIL M 16.22 70.84 1,579.36 416.60 2,083.02

604b METAL GUARD RAIL END PIECES EACH 22.09 - 1,197.58 304.92 1,524.58

604d STEEL POST OF METAL GUARD RAIL EACH 76.16 976.73 3,776.31 1,207.30 6,036.50

605a CONCRETE BEAM GUARD RAIL M 64.28 30.82 595.22 172.58 862.90

605c CONCRETE POST FOR GUARD RAIL M 78.92 27.36 595.78 175.52 877.58

607a TRAFFIC ROAD SIGN CATEGORY 1 EACH 202.15 255.15 6,850.96 1,827.07 9,135.33

607b TRAFFIC ROAD SIGN CATEGORY 2 EACH 64.50 382.72 9,242.90 2,422.53 12,112.66

607c TRAFFIC ROAD SIGN CATEGORY 3 (a) EACH 202.15 541.89 11,862.60 3,151.66 15,758.30

607d TRAFFIC ROAD SIGN CATEGORY 3 (b) EACH 640.54 598.64 20,918.75 5,539.48 27,697.42

607e TRAFFIC ROAD SIGN CATEGORY 3 (c) SM 128.11 119.73 9,201.80 2,362.41 11,812.04

607f ADDITIONAL PANEL SIZE 60 X 30 cm EACH 257.14 - 1,303.04 390.04 1,950.22

607g ADDITIONAL PANEL SIZE 90 X 30 cm EACH 257.14 - 1,954.55 552.92 2,764.61

608b1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.41 5.86 16.16 6.11 30.54
LINES OF 15 cm WIDTH

608b2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.80 4.03 39.65 11.12 55.61
LINES OF 15 cm WIDTH

608c1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.41 5.86 21.56 7.46 37.29
LINES OF 20 cm WIDTH

Page 142
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Malakand
Malakand District Code: 42

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

608c2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.80 4.03 52.89 14.43 72.15
LINES OF 20 cm WIDTH

608d1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 69.38 5.22 156.16 57.69 288.44
4.0 M ARROWS

608d2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR 4.0 EACH 69.38 9.98 499.68 144.76 723.80
M ARROWS

608h1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.01 8.59 22.48 8.52 42.60
OF 15 cm WIDTH

608h2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.01 9.63 67.50 20.04 100.19
OF 15 cm WIDTH

608i1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.01 6.95 29.97 9.98 49.92
OF 20 cm WIDTH

608i2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.01 9.63 90.01 25.66 128.32
OF 20 cm WIDTH

608j1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR 4.0 M EACH 69.38 3.73 217.02 72.53 362.65
ARROWS

608j2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR 4.0 M EACH 69.38 7.90 851.20 232.12 1,160.60
ARROWS

608n1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 57.58 3.73 104.11 41.35 206.76
STOP

608n2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR EACH 57.58 7.90 333.62 99.77 498.87
STOP

608n3 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR STOP EACH 57.58 3.73 144.68 51.49 257.47

608n4 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR STOP EACH 57.58 7.90 568.32 158.45 792.25

609c REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 8.82 81.62 193.82 71.07 355.33
SINGLE)

609d REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 8.82 81.62 233.82 81.07 405.33
DOUBLE)

610b RIGHT OF WAY MARKER EACH 87.31 121.33 301.53 127.54 637.70

610c KILOMETRE POST (0.610 X 0.114 X 1.5 M) EACH 556.83 976.31 2,030.11 890.81 4,454.06

610d TEN KILOMETRE POST EACH 1,062.01 1,952.61 4,457.19 1,867.95 9,339.76

611a CHAIN LINK WIRE FABRIC FENCING 1500 MM HEIGHT M 118.43 91.00 951.06 290.13 1,450.63
WITH PRECAST PRESTRESSED R.C.C. POST

Page 143
.

Page 144
NATIONAL HIGHWAY AUTHORITY

COMPOSITE SCHEDULE OF RATES


January - 2009

MANSEHRA
(43)

Shabir Associates
Quantity Surveying & Construction Cost Consultants

Page 145
.

Page 146
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Mansehra
Mansehra District Code: 43

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

101 CLEARING AND GRUBBING SM 0.64 10.10 - 2.69 13.43

102a REMOVAL OF TREES 150 - 300 mm GIRTH EACH 6.87 173.32 1.17 45.34 226.69

102b REMOVAL OF TREES 301 - 600 mm GIRTH EACH 18.96 456.54 2.63 119.53 597.66

102c REMOVAL OF TREES 601 mm OR OVER GIRTH EACH 75.83 1,826.16 10.51 478.12 2,390.62

103 STRIPPING CM 2.44 93.22 - 23.92 119.58

104 COMPACTION OF NATURAL GROUND SM 0.36 9.91 0.76 2.76 13.79

106a EXCAVATE UNSUITABLE COMMON MATERIAL CM 5.25 135.76 - 35.25 176.26

106bi EXCAVATE UNSUITABLE HARD ROCK MATERIAL CM 134.43 316.30 50.82 125.39 626.93

106bii EXCAVATE UNSUITABLE MEDIUM ROCK MATERIAL CM 17.55 337.99 - 88.89 444.43

106biii EXCAVATE UNSUITABLE SOFT ROCK MATERIAL CM 11.57 262.40 - 68.49 342.46

106c EXCAVATE SURPLUS COMMON MATERIAL CM 4.30 120.27 - 31.14 155.71

106di EXCAVATE SURPLUS HARD ROCK MATERIAL CM 134.43 316.30 50.82 125.39 626.93

106dii EXCAVATE SURPLUS MEDIUM ROCK MATERIAL CM 21.50 316.03 - 84.38 421.92

106diii EXCAVATE SURPLUS SOFT ROCK MATERIAL CM 8.91 263.92 - 68.21 341.05

107a STRUCTURAL EXCAVATION IN COMMON MATERIAL CM 7.98 137.60 0.38 36.49 182.45

107b STRUCTURAL EXCAVATION IN COMMON MATERIAL BELOW CM 61.11 287.11 70.80 104.76 523.79
WATER LEVEL

107ci STRUCTURAL EXCAVATION IN HARD ROCK MATERIAL CM 119.46 427.01 33.88 145.09 725.45

107cii STRUCTURAL EXCAVATION IN MEDIUM ROCK MATERIAL CM 100.28 292.53 - 98.20 491.02

107ciii STRUCTURAL EXCAVATION IN SOFT ROCK MATERIAL CM 61.44 238.86 - 75.08 375.38

107d GRANULAR BACK FILL CM 33.49 137.14 469.73 160.09 800.45

107e COMMON BACK FILL CM 22.01 62.84 5.09 22.48 112.42

108a FORMATION OF EMBANKMENT FROM ROADWAY CM 7.20 174.71 5.09 46.75 233.75
EXCAVATION IN COMMON MATERIAL

108bi FORMATION OF EMBANKMENT FROM ROADWAY CM 20.32 482.48 54.04 139.21 696.05
EXCAVATION IN HARD ROCK MATERIAL

108bii FORMATION OF EMBANKMENT FROM ROADWAY CM 15.24 416.71 2.42 108.59 542.96
EXCAVATION IN MEDIUM ROCK MATERIAL

108biii FORMATION OF EMBANKMENT FROM ROADWAY CM 13.55 369.34 - 95.72 478.61


EXCAVATION IN SOFT ROCK MATERIAL

108c FORMATION OF EMBANKMENT FROM BORROW CM 7.98 177.46 7.94 48.34 241.72
EXCAVATION IN COMMON MATERIAL

108d FORMATION OF EMBANKMENT FROM STRUCTURAL CM 6.40 76.32 5.09 21.95 109.76
EXCAVATION IN COMMON MATERIAL

108e FORMATION OF EMBANKMENT FROM STRUCTURAL CM 14.16 110.29 3.03 31.87 159.34
EXCAVATION IN ANY TYPE OF ROCK MATERIAL

109a SUB GRADE PREPARATION IN EARTH CUT SM 1.44 27.34 1.46 7.56 37.79

Page 147
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Mansehra
Mansehra District Code: 43

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

109bi SUB GRADE PREPARATION IN EXISTING ROAD WITHOUT SM 1.05 18.21 0.77 5.01 25.03
ANY FILL

110 IMPROVED SUB-GRADE CM 10.10 120.02 56.20 46.58 232.89

114a DRESSING OF BERM WITHOUT EXTRA MATERIAL SM 0.84 15.26 0.79 4.22 21.12

114b DRESSING OF BERM WITH EXTRA BORROW MATERIAL SM 1.24 15.57 0.90 4.43 22.14

201 GRANULAR SUB-BASE CM 8.20 255.06 616.97 220.06 1,100.28

202 AGGREGATE BASE CM 10.20 326.54 780.88 279.41 1,397.03

203a ASPHALTIC BASE COURSE PLANT MIX (CLASS "A") CM 65.74 1,510.17 5,984.60 1,890.13 9,450.63

203b ASPHALTIC BASE COURSE PLANT MIX (CLASS "B") CM 68.62 1,510.17 6,393.95 1,993.18 9,965.92

203c ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "A") CM 73.41 1,577.28 5,974.66 1,906.34 9,531.69

203d ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "B") CM 73.41 1,571.31 6,539.97 2,046.17 10,230.85

204b CEMENT STABILIZED BASE CM 30.16 569.10 1,028.25 406.88 2,034.40

204d LIQUID ASPHALT FOR CURING SEAL, TYPE MC-250 TON 246.88 915.38 52,507.71 13,417.49 67,087.46

204e EMULSIFIED ASPHALT FOR CURING SEAL, TYPE SS-1 TON 246.88 915.38 50,929.58 13,022.96 65,114.80

205a GRADED CRUSHED AGGREGATE CRACK-RELIEF LAYER CM 79.47 112.80 897.90 272.54 1,362.72

205b ASPHALTIC OPEN-GRADED PLANT MIX CRACK-RELIEF CM 140.98 2,437.94 5,653.69 2,058.15 10,290.76
LAYER

206b WATER BOUND MACADAM BASE WITH COARSE CM 87.07 126.27 788.83 250.54 1,252.72
AGGREGATE CLASS B

207a DEEP PATCHING (0-15 cm) SM 1.78 45.04 1.26 12.02 60.08

207b DEEP PATCHING (16-30 cm) SM 1.78 39.67 1.26 10.68 53.38

208 REINSTATEMENT OF ROAD SURFACE SM 2.00 57.10 0.56 14.91 74.57

209a BREAKING OF EXISTING ROAD PAVEMENT STRUCTURE CM 2.27 110.61 0.68 28.39 141.95

209b SCARIFICATION OF EXISTING ROAD PAVEMENT SM 0.45 22.12 0.14 5.68 28.39

302a CUT-BACK ASPHALT FOR BITUMINOUS PRIME COAT SM 0.31 1.57 37.27 9.79 48.94

302b EMULSIFIED ASPHALT FOR BITUMINOUS PRIME COAT SM 0.30 1.57 41.60 10.87 54.34

303a CUT-BACK ASPHALT FOR BITUMINOUS TACK COAT SM 0.12 0.58 15.60 4.08 20.38

303b EMULSIFIED ASPHALT FOR BITUMINOUS TACK COAT SM 0.12 0.58 18.20 4.72 23.62

304a SINGLE SURFACE TREATMENT SM 0.83 7.57 74.06 20.62 103.08

304b DOUBLE SURFACE TREATMENT SM 1.20 14.15 143.28 39.66 198.29

304c TRIPLE SURFACE TREATMENT SM 2.03 19.94 163.47 46.36 231.80

304d SEAL COAT SM 0.78 4.12 52.49 14.35 71.74

Page 148
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Mansehra
Mansehra District Code: 43

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

305a ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 63.78 1,489.33 7,016.99 2,142.53 10,712.63
"A")

305b ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 63.78 1,438.23 7,575.87 2,269.47 11,347.36
"B")

307a DENSE GRADED HOT BIT-MAC CM 154.10 379.77 5,821.73 1,588.90 7,944.50

307b OPEN GRADED HOT BIT-MAC CM 154.10 379.77 5,644.92 1,544.70 7,723.50

308a RECYCLING OF ASPHALT CONCRETE (0 - 60 mm THICK) CM 27.21 590.65 2,056.08 668.48 3,342.42

308b BITUMEN BINDER GRADE (40 - 50, 60 - 70, 80 - 100) TON 25.81 650.70 44,571.28 11,311.95 56,559.74

309a COLD MILLING, 0 - 30 mm SM 1.01 24.99 8.68 8.67 43.34

309b COLD MILLING, 0 - 50 mm SM 1.68 41.65 14.46 14.45 72.24

309c COLD MILLING, 0 - 70 mm SM 2.52 62.48 21.69 21.67 108.36

401a1i CONCRETE CLASS "A1" (Underground) CM 511.44 1,059.94 3,936.44 1,376.95 6,884.77

401a1ii CONCRETE CLASS "A1" (On ground) CM 511.44 1,059.94 4,213.91 1,446.32 7,231.61

401a1iii CONCRETE CLASS "A1" (Elevated) CM 511.44 1,059.94 4,768.86 1,585.06 7,925.29

401a2i CONCRETE CLASS "A2" (Underground) CM 511.44 1,059.94 4,314.44 1,471.45 7,357.27

401a2ii CONCRETE CLASS "A2" (On ground) CM 511.44 1,059.94 4,591.91 1,540.82 7,704.11

401a2iii CONCRETE CLASS "A2" (Elevated) CM 511.44 1,059.94 5,146.86 1,679.56 8,397.79

401a3i CONCRETE CLASS "A3" (Underground) CM 511.44 1,059.94 4,692.44 1,565.95 7,829.77

401a3ii CONCRETE CLASS "A3" (On ground) CM 511.44 1,059.94 4,969.91 1,635.32 8,176.61

401a3iii CONCRETE CLASS "A3" (Elevated) CM 511.44 1,059.94 5,524.86 1,774.06 8,870.29

401b CONCRETE CLASS "B" CM 666.77 805.93 3,137.40 1,152.53 5,762.63

401ci CONCRETE CLASS "C" (Underground) CM 489.90 500.55 3,475.15 1,116.40 5,582.01

401cii CONCRETE CLASS "C" (On ground) CM 489.90 500.55 3,593.50 1,145.99 5,729.93

401ciii CONCRETE CLASS "C" (Elevated) CM 489.90 500.55 3,830.18 1,205.16 6,025.79

401d CONCRETE CLASS "D1" CM 776.43 1,265.57 5,273.89 1,828.97 9,144.86

401e CONCRETE CLASS "Y" CM 1,055.91 500.55 4,733.63 1,572.52 7,862.61

401f LEAN CONCRETE CM 397.68 507.52 2,407.72 828.23 4,141.15

401gi(1) PRECAST CONCRETE CLASS "A-1" CM 1,624.82 947.15 4,939.82 1,877.95 9,389.74

401gi(3) PRECAST CONCRETE CLASS "A-3" CM 1,624.82 947.15 5,695.82 2,066.95 10,334.74

401gii PRECAST CONCRETE CLASS "B" CM 1,624.82 947.15 4,662.43 1,808.60 9,042.99

401giii(1) PRECAST CONCRETE CLASS "D1" CM 1,624.82 947.15 6,073.82 2,161.45 10,807.24

Page 149
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Mansehra
Mansehra District Code: 43

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

401giii(2) PRECAST CONCRETE CLASS "D2" CM 1,624.82 947.15 6,451.82 2,255.95 11,279.74

401giii(3) PRECAST CONCRETE CLASS "D3" CM 1,624.82 947.15 6,829.82 2,350.45 11,752.24

404a REINFORCEMENT AS PER AASHTO M. 31 GRADE 40 TON 1,538.63 781.47 60,126.50 15,611.65 78,058.26

404b REINFORCEMENT AS PER AASHTO M. 31 GRADE 60 TON 1,538.63 781.47 67,476.50 17,449.15 87,245.76

404h REINFORCEMENT (STRUCTURAL SHAPES) AS PER ASTM-A- TON 1,246.10 5,393.81 56,040.58 15,670.12 78,350.62
36

405a PRE-STRESSING WIRE STRAND 3/8" - 1/2" DIA COMPLETE IN TON 2,860.52 15,659.05 133,865.31 38,096.22 190,481.10
ALL RESPECT

405b LAUNCHING OF GIRDER TON 66.02 532.52 - 149.63 748.17

406a PREMOULDED JOINT FILLER 12 mm THICK WITH SM 107.88 - 304.56 103.11 515.56
BITUMASTIC JOINT SEAL

406b NEOPRENE RUBBER JOINT FILLER 12 mm THICK WITH SM 107.88 - 303.62 102.88 514.38
BITUMASTIC JOINT SEAL

406c STEEL EXPANSION JOINTS KG 8.85 26.40 90.77 31.50 157.51

406d WATER STOPS 6" SIZE M 91.39 - 472.55 140.98 704.92

406e ELASTOMERIC BEARING PADS (ACCORDING TO SIZE AND ccm 0.02 - 2.12 0.53 2.67
THICKNESS)

406f ASPHALT FELT (3 PLY) SM 42.23 - 2,979.50 755.43 3,777.16

406g STEEL OR METAL BEARING DEVICES KG 19.52 69.68 117.64 51.71 258.55

407d1 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 353.91 1,654.04 910.51 729.62 3,648.08
(BORING ONLY) IN NORMAL SOIL

407d2 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 530.87 2,481.06 1,365.77 1,094.43 5,472.13
(BORING ONLY) IN GRAVEL STRATA

407d3 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 530.87 2,481.06 1,013.72 1,006.41 5,032.06
ONLY) IN NORMAL SOIL

407d4 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 884.78 4,135.11 1,201.50 1,555.35 7,776.73
ONLY) IN GRAVEL STRATA

407d5 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 758.38 4,884.94 1,400.63 1,760.99 8,804.94
ONLY) IN NORMAL SOIL

407d6 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 1,327.17 6,909.78 1,527.73 2,441.17 12,205.85
ONLY) IN GRAVEL SOIL

407h PILE LOAD TEST UP TO 120 TON EACH 19,648.26 45,769.30 100,542.38 41,489.99 207,449.94

407i PILE LOAD TEST UP TO 240 TON EACH 35,422.66 45,769.30 201,084.76 70,569.18 352,845.90

407j PILE LOAD TEST UP TO 360 TON EACH 51,197.05 50,188.38 301,627.14 100,753.14 503,765.72

407k CONFIRMATORY BORING (NX SIZE) M 184.51 1,582.02 6.37 443.23 2,216.13

410 BRICK WORK CM 317.65 282.72 2,999.01 899.84 4,499.22

411a STONE MASONRY RANDOM DRY CM 266.97 107.96 613.48 247.10 1,235.52

411b STONE MASONRY RANDOM WITH MORTAR CM 289.72 166.68 1,639.82 524.06 2,620.28

411c STONE MASONRY DRESSED UNCOURSED DRY CM 347.53 107.96 679.65 283.79 1,418.93

411d STONE MASONRY DRESSED UNCOURSED WITH MORTAR CM 410.56 166.68 1,717.03 573.57 2,867.84

Page 150
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Mansehra
Mansehra District Code: 43

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

411g ROLL POINTING SM 67.98 11.74 43.75 30.87 154.34

412a STONE MASONRY DRESSED COURSED WITH MORTAR CM 548.92 264.08 1,622.22 608.81 3,044.04

501a R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 310 mm M 199.53 437.48 643.39 320.10 1,600.51

501b R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 380 mm M 192.30 577.19 834.17 400.91 2,004.57

501c R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 460 mm M 196.60 935.96 1,069.85 550.60 2,753.02

501d R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 610 mm M 202.63 1,146.39 1,598.23 736.81 3,684.06

501e R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 760 mm M 234.98 1,078.41 2,297.87 902.82 4,514.08

501f R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 910 mm M 295.38 1,331.30 3,614.54 1,310.31 6,551.53

501g R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1070 mm M 382.26 1,481.41 4,680.50 1,636.04 8,180.20

501h R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1220 mm M 447.92 1,798.85 5,964.68 2,052.86 10,264.32

501i R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1520 mm M 533.71 2,098.66 9,213.95 2,961.58 14,807.90

501j R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 310 mm M 199.53 507.33 722.10 357.24 1,786.21

501k R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 380 mm M 192.30 577.19 852.99 405.62 2,028.09

501l R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 460 mm M 191.91 935.96 1,044.43 543.07 2,715.37

501m R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 610 mm M 202.63 1,146.39 1,743.69 773.18 3,865.88

501n R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 760 mm M 234.98 1,078.41 3,316.03 1,157.36 5,786.79

501o R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 910 mm M 295.38 1,331.30 4,871.85 1,624.63 8,123.17

501p R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1070 mm M 382.26 1,481.41 6,808.93 2,168.15 10,840.74

501q R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1220 mm M 447.92 1,798.85 9,234.95 2,870.43 14,352.16

501r R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1520 mm M 533.71 2,098.66 12,992.82 3,906.30 19,531.48

502a GRANULAR MATERIAL IN BED TO CONCRETE PIPE CM 81.78 118.93 428.06 157.19 785.95
CULVERT

502b CONCRETE CLASS "B" IN BEDDING AND ENCASEMENT OF CM 743.29 612.95 3,487.40 1,210.91 6,054.55
CONCRETE PIPE CULVERT

507a STEEL WIRE MESH FOR GABIONS KG 5.17 - 109.00 28.54 142.71

507b ROCK FILL IN GABIONS CM 83.82 - 423.50 126.83 634.15

508a BRICK PAVING (SINGLE COURSE) SM 102.38 32.70 242.44 94.38 471.90

508b BRICK PAVING (DOUBLE COURSE) SM 182.94 32.70 481.10 174.18 870.92

509a RIP RAP CLASS "A" CM 449.91 - 518.68 242.15 1,210.73

509b RIP RAP CLASS "B" CM 431.38 - 514.53 236.48 1,182.38

509c RIP RAP CLASS "C" CM 434.20 - 518.68 238.22 1,191.09

Page 151
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Mansehra
Mansehra District Code: 43

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

509d GROUTED RIP RAP CLASS "A" CM 548.26 102.14 1,911.65 640.51 3,202.56

509e GROUTED RIP RAP CLASS "B" CM 528.26 81.72 1,762.81 593.20 2,965.99

509f GROUTED RIP RAP CLASS "C" CM 520.78 68.10 1,808.53 599.35 2,996.75

509g REINFORCED CONCRETE SLOPE PROTECTION (WITHOUT CM 734.97 353.02 4,055.43 1,285.86 6,429.28
REINFORCEMENT)

509h FILTER LAYER OF GRANULAR MATERIAL CM 41.96 191.97 469.98 175.98 879.90

510 DISMANTLING OF STRUCTURE AND OBSTRUCTIONS CM 98.76 390.69 - 122.36 611.82

511a1 DRY STONE PITCHING (15-20 cm Thick) SM 141.19 67.48 84.28 73.24 366.18

511a2 DRY STONE PITCHING (21-25 cm Thick) SM 180.72 86.37 107.88 93.74 468.71

511b1 GROUTED STONE PITCHING (15-20 cm Thick) SM 231.14 180.32 379.89 197.84 989.19

511b2 GROUTED STONE PITCHING (21-25 cm Thick) SM 288.93 225.40 474.86 247.30 1,236.49

601ai CONCRETE KERB IN PLACE NEW JERSY BARRIER FOR M 271.10 572.25 2,205.69 762.26 3,811.30
MEDIAN (DOUBLE FACE)

601di PRECAST REINFORCED CONCRETE KERB NEW JERSY M 893.74 670.54 4,058.90 1,405.79 7,028.97
BARRIER FOR MEDIAN (DOUBLE FACE)

601dii PRECAST KERB IN CONCRETE CLASS A-1 OF SIZE 450 X 150 MM M 129.98 90.27 426.74 161.75 808.74
INCLUDING CONCRETE BEDDING & HAUNCHING

603 BRICK EDGING M 8.14 - 38.11 11.56 57.82

604a METAL GUARD RAIL M 18.95 70.84 1,579.36 417.29 2,086.44

604b METAL GUARD RAIL END PIECES EACH 23.58 - 1,197.58 305.29 1,526.44

604d STEEL POST OF METAL GUARD RAIL EACH 90.29 976.73 3,776.31 1,210.83 6,054.16

605a CONCRETE BEAM GUARD RAIL M 65.50 30.82 591.73 172.01 860.06

605c CONCRETE POST FOR GUARD RAIL M 80.43 27.36 591.86 174.91 874.56

607a TRAFFIC ROAD SIGN CATEGORY 1 EACH 219.42 255.15 6,853.75 1,832.08 9,160.40

607b TRAFFIC ROAD SIGN CATEGORY 2 EACH 63.61 382.72 9,243.69 2,422.51 12,112.53

607c TRAFFIC ROAD SIGN CATEGORY 3 (a) EACH 219.42 541.89 11,862.38 3,155.92 15,779.60

607d TRAFFIC ROAD SIGN CATEGORY 3 (b) EACH 666.44 598.64 20,924.05 5,547.28 27,736.41

607e TRAFFIC ROAD SIGN CATEGORY 3 (c) SM 133.29 119.73 9,208.26 2,365.32 11,826.60

607f ADDITIONAL PANEL SIZE 60 X 30 cm EACH 286.86 - 1,304.87 397.93 1,989.66

607g ADDITIONAL PANEL SIZE 90 X 30 cm EACH 286.86 - 1,957.31 561.04 2,805.21

608b1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.52 5.86 16.16 6.13 30.67
LINES OF 15 cm WIDTH

608b2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.84 4.03 39.67 11.14 55.68
LINES OF 15 cm WIDTH

608c1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.52 5.86 21.57 7.49 37.43
LINES OF 20 cm WIDTH

Page 152
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Mansehra
Mansehra District Code: 43

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

608c2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.84 4.03 52.91 14.45 72.23
LINES OF 20 cm WIDTH

608d1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 70.48 5.22 156.18 57.97 289.85
4.0 M ARROWS

608d2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR 4.0 EACH 70.48 9.98 499.94 145.10 725.51
M ARROWS

608h1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.14 8.59 22.48 8.55 42.77
OF 15 cm WIDTH

608h2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.14 9.63 67.50 20.07 100.35
OF 15 cm WIDTH

608i1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.14 6.95 29.97 10.02 50.09
OF 20 cm WIDTH

608i2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.14 9.63 90.01 25.70 128.48
OF 20 cm WIDTH

608j1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR 4.0 M EACH 70.48 3.73 217.04 72.81 364.06
ARROWS

608j2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR 4.0 M EACH 70.48 7.90 851.20 232.39 1,161.97
ARROWS

608n1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 58.68 3.73 104.12 41.63 208.16
STOP

608n2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR EACH 58.68 7.90 333.80 100.09 500.47
STOP

608n3 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR STOP EACH 58.68 3.73 144.69 51.77 258.87

608n4 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR STOP EACH 58.68 7.90 568.32 158.72 793.62

609c REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 8.60 81.62 193.80 71.01 355.03
SINGLE)

609d REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 8.60 81.62 233.80 81.00 405.02
DOUBLE)

610b RIGHT OF WAY MARKER EACH 89.22 121.33 300.02 127.64 638.21

610c KILOMETRE POST (0.610 X 0.114 X 1.5 M) EACH 567.83 976.31 2,014.67 889.70 4,448.51

610d TEN KILOMETRE POST EACH 1,084.00 1,952.61 4,427.28 1,865.97 9,329.87

611a CHAIN LINK WIRE FABRIC FENCING 1500 MM HEIGHT M 123.61 91.00 949.61 291.05 1,455.27
WITH PRECAST PRESTRESSED R.C.C. POST

Page 153
.

Page 154
NATIONAL HIGHWAY AUTHORITY

COMPOSITE SCHEDULE OF RATES


January - 2009

MARDAN
(44)

Shabir Associates
Quantity Surveying & Construction Cost Consultants

Page 155
.

Page 156
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Mardan
Mardan District Code: 44

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

101 CLEARING AND GRUBBING SM 0.62 10.10 - 2.68 13.40

102a REMOVAL OF TREES 150 - 300 mm GIRTH EACH 6.31 173.32 1.17 45.20 226.00

102b REMOVAL OF TREES 301 - 600 mm GIRTH EACH 17.91 456.54 2.63 119.27 596.35

102c REMOVAL OF TREES 601 mm OR OVER GIRTH EACH 71.64 1,826.16 10.51 477.08 2,385.39

103 STRIPPING CM 2.23 93.22 - 23.86 119.32

104 COMPACTION OF NATURAL GROUND SM 0.32 9.91 0.76 2.75 13.74

106a EXCAVATE UNSUITABLE COMMON MATERIAL CM 4.11 135.76 - 34.97 174.83

106bi EXCAVATE UNSUITABLE HARD ROCK MATERIAL CM 112.43 316.30 50.82 119.89 599.44

106bii EXCAVATE UNSUITABLE MEDIUM ROCK MATERIAL CM 15.27 337.99 - 88.32 441.58

106biii EXCAVATE UNSUITABLE SOFT ROCK MATERIAL CM 10.01 262.40 - 68.10 340.51

106c EXCAVATE SURPLUS COMMON MATERIAL CM 3.36 120.27 - 30.91 154.54

106di EXCAVATE SURPLUS HARD ROCK MATERIAL CM 112.43 316.30 50.82 119.89 599.44

106dii EXCAVATE SURPLUS MEDIUM ROCK MATERIAL CM 17.88 316.03 - 83.48 417.39

106diii EXCAVATE SURPLUS SOFT ROCK MATERIAL CM 7.74 263.92 - 67.91 339.57

107a STRUCTURAL EXCAVATION IN COMMON MATERIAL CM 6.62 137.60 0.38 36.15 180.75

107b STRUCTURAL EXCAVATION IN COMMON MATERIAL BELOW CM 56.23 287.11 70.80 103.54 517.69
WATER LEVEL

107ci STRUCTURAL EXCAVATION IN HARD ROCK MATERIAL CM 99.35 427.01 33.88 140.06 700.30

107cii STRUCTURAL EXCAVATION IN MEDIUM ROCK MATERIAL CM 83.79 292.53 - 94.08 470.40

107ciii STRUCTURAL EXCAVATION IN SOFT ROCK MATERIAL CM 51.09 238.86 - 72.49 362.45

107d GRANULAR BACK FILL CM 29.76 137.14 468.55 158.86 794.32

107e COMMON BACK FILL CM 21.49 62.84 5.09 22.35 111.77

108a FORMATION OF EMBANKMENT FROM ROADWAY CM 6.13 174.71 5.09 46.48 232.42
EXCAVATION IN COMMON MATERIAL

108bi FORMATION OF EMBANKMENT FROM ROADWAY CM 17.81 482.48 54.04 138.58 692.92
EXCAVATION IN HARD ROCK MATERIAL

108bii FORMATION OF EMBANKMENT FROM ROADWAY CM 13.36 416.71 2.42 108.12 540.61
EXCAVATION IN MEDIUM ROCK MATERIAL

108biii FORMATION OF EMBANKMENT FROM ROADWAY CM 11.88 369.34 - 95.30 476.52


EXCAVATION IN SOFT ROCK MATERIAL

108c FORMATION OF EMBANKMENT FROM BORROW CM 6.96 177.46 7.94 48.09 240.45
EXCAVATION IN COMMON MATERIAL

108d FORMATION OF EMBANKMENT FROM STRUCTURAL CM 5.53 76.32 5.09 21.74 108.68
EXCAVATION IN COMMON MATERIAL

108e FORMATION OF EMBANKMENT FROM STRUCTURAL CM 12.71 110.29 3.03 31.51 157.53
EXCAVATION IN ANY TYPE OF ROCK MATERIAL

109a SUB GRADE PREPARATION IN EARTH CUT SM 1.24 27.34 1.46 7.51 37.54

Page 157
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Mardan
Mardan District Code: 44

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

109bi SUB GRADE PREPARATION IN EXISTING ROAD WITHOUT SM 0.90 18.21 0.77 4.97 24.86
ANY FILL

110 IMPROVED SUB-GRADE CM 8.84 120.02 54.78 45.91 229.54

114a DRESSING OF BERM WITHOUT EXTRA MATERIAL SM 0.76 15.26 0.79 4.20 21.01

114b DRESSING OF BERM WITH EXTRA BORROW MATERIAL SM 1.12 15.57 0.90 4.40 21.98

201 GRANULAR SUB-BASE CM 7.06 255.06 583.69 211.45 1,057.27

202 AGGREGATE BASE CM 8.34 326.54 746.90 270.44 1,352.22

203a ASPHALTIC BASE COURSE PLANT MIX (CLASS "A") CM 61.68 1,510.17 5,777.65 1,837.37 9,186.87

203b ASPHALTIC BASE COURSE PLANT MIX (CLASS "B") CM 63.84 1,510.17 6,173.08 1,936.77 9,683.85

203c ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "A") CM 68.42 1,577.28 5,768.09 1,853.45 9,267.23

203d ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "B") CM 68.42 1,571.31 6,315.89 1,988.90 9,944.52

204b CEMENT STABILIZED BASE CM 25.30 569.10 981.15 393.89 1,969.44

204d LIQUID ASPHALT FOR CURING SEAL, TYPE MC-250 TON 213.30 915.38 50,523.06 12,912.93 64,564.67

204e EMULSIFIED ASPHALT FOR CURING SEAL, TYPE SS-1 TON 213.30 915.38 48,944.93 12,518.40 62,592.01

205a GRADED CRUSHED AGGREGATE CRACK-RELIEF LAYER CM 80.01 112.80 877.89 267.67 1,338.36

205b ASPHALTIC OPEN-GRADED PLANT MIX CRACK-RELIEF CM 127.52 2,437.94 5,490.02 2,013.87 10,069.36
LAYER

206b WATER BOUND MACADAM BASE WITH COARSE CM 87.86 126.27 706.61 230.19 1,150.94
AGGREGATE CLASS B

207a DEEP PATCHING (0-15 cm) SM 1.55 45.04 1.26 11.96 59.81

207b DEEP PATCHING (16-30 cm) SM 1.55 39.67 1.26 10.62 53.11

208 REINSTATEMENT OF ROAD SURFACE SM 1.66 57.10 0.56 14.83 74.15

209a BREAKING OF EXISTING ROAD PAVEMENT STRUCTURE CM 1.94 110.61 0.68 28.31 141.54

209b SCARIFICATION OF EXISTING ROAD PAVEMENT SM 0.39 22.12 0.14 5.66 28.31

302a CUT-BACK ASPHALT FOR BITUMINOUS PRIME COAT SM 0.26 1.57 35.86 9.42 47.12

302b EMULSIFIED ASPHALT FOR BITUMINOUS PRIME COAT SM 0.25 1.57 40.03 10.46 52.32

303a CUT-BACK ASPHALT FOR BITUMINOUS TACK COAT SM 0.10 0.58 15.01 3.92 19.61

303b EMULSIFIED ASPHALT FOR BITUMINOUS TACK COAT SM 0.10 0.58 17.51 4.55 22.74

304a SINGLE SURFACE TREATMENT SM 0.68 7.57 70.97 19.81 99.03

304b DOUBLE SURFACE TREATMENT SM 0.99 14.15 137.22 38.09 190.46

304c TRIPLE SURFACE TREATMENT SM 1.67 19.94 156.53 44.53 222.67

304d SEAL COAT SM 0.63 4.12 50.39 13.79 68.93

Page 158
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Mardan
Mardan District Code: 44

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

305a ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 58.27 1,489.33 6,764.70 2,078.07 10,390.37
"A")

305b ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 58.27 1,438.23 7,296.61 2,198.28 10,991.39
"B")

307a DENSE GRADED HOT BIT-MAC CM 142.97 379.77 5,576.28 1,524.76 7,623.78

307b OPEN GRADED HOT BIT-MAC CM 142.97 379.77 5,416.47 1,484.80 7,424.02

308a RECYCLING OF ASPHALT CONCRETE (0 - 60 mm THICK) CM 24.90 590.65 2,005.10 655.16 3,275.81

308b BITUMEN BINDER GRADE (40 - 50, 60 - 70, 80 - 100) TON 22.81 650.70 42,527.68 10,800.30 54,001.48

309a COLD MILLING, 0 - 30 mm SM 0.85 24.99 8.68 8.63 43.14

309b COLD MILLING, 0 - 50 mm SM 1.41 41.65 14.46 14.38 71.91

309c COLD MILLING, 0 - 70 mm SM 2.12 62.48 21.69 21.57 107.86

401a1i CONCRETE CLASS "A1" (Underground) CM 478.37 1,059.94 3,893.71 1,358.00 6,790.02

401a1ii CONCRETE CLASS "A1" (On ground) CM 478.37 1,059.94 4,171.18 1,427.37 7,136.86

401a1iii CONCRETE CLASS "A1" (Elevated) CM 478.37 1,059.94 4,726.13 1,566.11 7,830.54

401a2i CONCRETE CLASS "A2" (Underground) CM 478.37 1,059.94 4,271.71 1,452.50 7,262.52

401a2ii CONCRETE CLASS "A2" (On ground) CM 478.37 1,059.94 4,549.18 1,521.87 7,609.36

401a2iii CONCRETE CLASS "A2" (Elevated) CM 478.37 1,059.94 5,104.13 1,660.61 8,303.04

401a3i CONCRETE CLASS "A3" (Underground) CM 478.37 1,059.94 4,649.71 1,547.00 7,735.02

401a3ii CONCRETE CLASS "A3" (On ground) CM 478.37 1,059.94 4,927.18 1,616.37 8,081.86

401a3iii CONCRETE CLASS "A3" (Elevated) CM 478.37 1,059.94 5,482.13 1,755.11 8,775.54

401b CONCRETE CLASS "B" CM 610.15 805.93 3,107.82 1,130.97 5,654.87

401ci CONCRETE CLASS "C" (Underground) CM 469.86 500.55 3,435.35 1,101.44 5,507.20

401cii CONCRETE CLASS "C" (On ground) CM 469.86 500.55 3,553.70 1,131.02 5,655.12

401ciii CONCRETE CLASS "C" (Elevated) CM 469.86 500.55 3,790.38 1,190.20 5,950.98

401d CONCRETE CLASS "D1" CM 746.86 1,265.57 5,236.77 1,812.30 9,061.50

401e CONCRETE CLASS "Y" CM 1,035.27 500.55 4,690.32 1,556.53 7,782.67

401f LEAN CONCRETE CM 388.73 507.52 2,379.66 818.98 4,094.88

401gi(1) PRECAST CONCRETE CLASS "A-1" CM 1,580.65 947.15 4,890.66 1,854.62 9,273.08

401gi(3) PRECAST CONCRETE CLASS "A-3" CM 1,580.65 947.15 5,646.66 2,043.62 10,218.08

401gii PRECAST CONCRETE CLASS "B" CM 1,580.65 947.15 4,629.05 1,789.21 8,946.07

401giii(1) PRECAST CONCRETE CLASS "D1" CM 1,580.65 947.15 6,024.66 2,138.12 10,690.58

Page 159
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Mardan
Mardan District Code: 44

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

401giii(2) PRECAST CONCRETE CLASS "D2" CM 1,580.65 947.15 6,402.66 2,232.62 11,163.08

401giii(3) PRECAST CONCRETE CLASS "D3" CM 1,580.65 947.15 6,780.66 2,327.12 11,635.58

404a REINFORCEMENT AS PER AASHTO M. 31 GRADE 40 TON 1,458.73 781.47 59,888.00 15,532.05 77,660.25

404b REINFORCEMENT AS PER AASHTO M. 31 GRADE 60 TON 1,458.73 781.47 67,238.00 17,369.55 86,847.75

404h REINFORCEMENT (STRUCTURAL SHAPES) AS PER ASTM-A- TON 1,173.23 5,393.81 55,999.50 15,641.63 78,208.17
36

405a PRE-STRESSING WIRE STRAND 3/8" - 1/2" DIA COMPLETE IN TON 2,507.06 15,659.05 133,859.15 38,006.31 190,031.56
ALL RESPECT

405b LAUNCHING OF GIRDER TON 59.04 532.52 - 147.89 739.45

406a PREMOULDED JOINT FILLER 12 mm THICK WITH SM 103.49 - 300.83 101.08 505.39
BITUMASTIC JOINT SEAL

406b NEOPRENE RUBBER JOINT FILLER 12 mm THICK WITH SM 103.49 - 300.00 100.87 504.37
BITUMASTIC JOINT SEAL

406c STEEL EXPANSION JOINTS KG 8.52 26.40 90.76 31.42 157.09

406d WATER STOPS 6" SIZE M 89.65 - 472.34 140.50 702.49

406e ELASTOMERIC BEARING PADS (ACCORDING TO SIZE AND ccm 0.02 - 2.12 0.53 2.67
THICKNESS)

406f ASPHALT FELT (3 PLY) SM 38.56 - 2,965.42 750.99 3,754.97

406g STEEL OR METAL BEARING DEVICES KG 17.71 69.68 119.24 51.66 258.30

407d1 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 323.80 1,654.04 806.65 696.12 3,480.62
(BORING ONLY) IN NORMAL SOIL

407d2 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 485.70 2,481.06 1,209.98 1,044.19 5,220.93
(BORING ONLY) IN GRAVEL STRATA

407d3 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 485.70 2,481.06 903.50 967.57 4,837.83
ONLY) IN NORMAL SOIL

407d4 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 809.51 4,135.11 1,078.79 1,505.85 7,529.25
ONLY) IN GRAVEL STRATA

407d5 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 693.86 4,884.94 1,256.91 1,708.93 8,544.65
ONLY) IN NORMAL SOIL

407d6 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 1,214.26 6,909.78 1,377.98 2,375.50 11,877.52
ONLY) IN GRAVEL SOIL

407h PILE LOAD TEST UP TO 120 TON EACH 19,634.37 45,769.30 96,405.50 40,452.29 202,261.46

407i PILE LOAD TEST UP TO 240 TON EACH 36,326.85 45,769.30 192,811.00 68,726.79 343,633.94

407j PILE LOAD TEST UP TO 360 TON EACH 53,019.33 50,188.38 289,216.50 98,106.05 490,530.26

407k CONFIRMATORY BORING (NX SIZE) M 178.73 1,582.02 6.37 441.78 2,208.90

410 BRICK WORK CM 306.85 282.72 2,906.48 874.01 4,370.07

411a STONE MASONRY RANDOM DRY CM 259.24 107.96 479.37 211.64 1,058.21

411b STONE MASONRY RANDOM WITH MORTAR CM 280.49 166.68 1,496.30 485.87 2,429.34

411c STONE MASONRY DRESSED UNCOURSED DRY CM 338.84 107.96 538.34 246.28 1,231.42

411d STONE MASONRY DRESSED UNCOURSED WITH MORTAR CM 399.89 166.68 1,568.66 533.81 2,669.04

Page 160
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Mardan
Mardan District Code: 44

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

411g ROLL POINTING SM 65.89 11.74 43.59 30.30 151.52

412a STONE MASONRY DRESSED COURSED WITH MORTAR CM 537.84 264.08 1,473.85 568.94 2,844.72

501a R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 310 mm M 197.92 437.48 643.10 319.63 1,598.13

501b R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 380 mm M 192.30 577.19 833.82 400.82 2,004.12

501c R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 460 mm M 189.99 935.96 1,069.44 548.85 2,744.23

501d R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 610 mm M 198.01 1,146.39 1,597.75 735.54 3,677.68

501e R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 760 mm M 227.18 1,078.41 2,297.39 900.75 4,503.73

501f R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 910 mm M 281.75 1,331.30 3,613.85 1,306.73 6,533.63

501g R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1070 mm M 364.62 1,481.41 4,679.80 1,631.46 8,157.29

501h R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1220 mm M 427.58 1,798.85 5,963.84 2,047.57 10,237.83

501i R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1520 mm M 508.27 2,098.66 9,212.97 2,954.98 14,774.88

501j R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 310 mm M 197.92 507.33 721.51 356.69 1,783.46

501k R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 380 mm M 192.30 577.19 852.64 405.53 2,027.65

501l R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 460 mm M 185.02 935.96 1,044.02 541.25 2,706.25

501m R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 610 mm M 198.01 1,146.39 1,743.31 771.93 3,859.64

501n R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 760 mm M 227.18 1,078.41 3,315.50 1,155.27 5,776.37

501o R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 910 mm M 281.75 1,331.30 4,871.16 1,621.05 8,105.26

501p R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1070 mm M 364.62 1,481.41 6,808.23 2,163.57 10,817.83

501q R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1220 mm M 427.58 1,798.85 9,234.11 2,865.14 14,325.68

501r R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1520 mm M 508.27 2,098.66 12,991.84 3,899.69 19,498.46

502a GRANULAR MATERIAL IN BED TO CONCRETE PIPE CM 78.25 118.93 371.64 142.21 711.03
CULVERT

502b CONCRETE CLASS "B" IN BEDDING AND ENCASEMENT OF CM 693.45 612.95 3,457.82 1,191.06 5,955.28
CONCRETE PIPE CULVERT

507a STEEL WIRE MESH FOR GABIONS KG 4.76 - 109.50 28.56 142.82

507b ROCK FILL IN GABIONS CM 83.12 - 388.21 117.83 589.16

508a BRICK PAVING (SINGLE COURSE) SM 99.86 32.70 230.48 90.76 453.80

508b BRICK PAVING (DOUBLE COURSE) SM 179.45 32.70 457.66 167.45 837.26

509a RIP RAP CLASS "A" CM 436.71 - 384.56 205.32 1,026.58

509b RIP RAP CLASS "B" CM 420.46 - 381.49 200.49 1,002.43

509c RIP RAP CLASS "C" CM 423.80 - 384.56 202.09 1,010.45

Page 161
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Mardan
Mardan District Code: 44

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

509d GROUTED RIP RAP CLASS "A" CM 532.35 102.14 1,771.66 601.54 3,007.69

509e GROUTED RIP RAP CLASS "B" CM 513.98 81.72 1,624.51 555.05 2,775.25

509f GROUTED RIP RAP CLASS "C" CM 507.91 68.10 1,668.93 561.24 2,806.18

509g REINFORCED CONCRETE SLOPE PROTECTION (WITHOUT CM 717.03 353.02 4,027.56 1,274.40 6,372.02
REINFORCEMENT)

509h FILTER LAYER OF GRANULAR MATERIAL CM 41.33 191.97 468.44 175.44 877.19

510 DISMANTLING OF STRUCTURE AND OBSTRUCTIONS CM 96.40 390.69 - 121.77 608.86

511a1 DRY STONE PITCHING (15-20 cm Thick) SM 136.95 67.48 62.49 66.73 333.65

511a2 DRY STONE PITCHING (21-25 cm Thick) SM 175.30 86.37 79.99 85.41 427.07

511b1 GROUTED STONE PITCHING (15-20 cm Thick) SM 224.14 180.32 352.19 189.16 945.81

511b2 GROUTED STONE PITCHING (21-25 cm Thick) SM 280.17 225.40 440.24 236.45 1,182.27

601ai CONCRETE KERB IN PLACE NEW JERSY BARRIER FOR M 253.58 572.25 2,183.31 752.28 3,761.42
MEDIAN (DOUBLE FACE)

601di PRECAST REINFORCED CONCRETE KERB NEW JERSY M 868.46 670.54 4,028.38 1,391.84 6,959.22
BARRIER FOR MEDIAN (DOUBLE FACE)

601dii PRECAST KERB IN CONCRETE CLASS A-1 OF SIZE 450 X 150 MM M 126.00 90.27 422.40 159.67 798.33
INCLUDING CONCRETE BEDDING & HAUNCHING

603 BRICK EDGING M 7.90 - 36.48 11.10 55.48

604a METAL GUARD RAIL M 16.99 70.84 1,579.36 416.80 2,083.99

604b METAL GUARD RAIL END PIECES EACH 22.92 - 1,197.58 305.12 1,525.62

604d STEEL POST OF METAL GUARD RAIL EACH 78.80 976.73 3,776.31 1,207.96 6,039.79

605a CONCRETE BEAM GUARD RAIL M 65.70 30.82 588.84 171.34 856.71

605c CONCRETE POST FOR GUARD RAIL M 80.67 27.36 588.47 174.13 870.63

607a TRAFFIC ROAD SIGN CATEGORY 1 EACH 208.46 255.15 6,845.59 1,827.30 9,136.51

607b TRAFFIC ROAD SIGN CATEGORY 2 EACH 63.97 382.72 9,229.86 2,419.14 12,095.69

607c TRAFFIC ROAD SIGN CATEGORY 3 (a) EACH 208.46 541.89 11,839.98 3,147.58 15,737.92

607d TRAFFIC ROAD SIGN CATEGORY 3 (b) EACH 666.64 598.64 20,883.54 5,537.20 27,686.02

607e TRAFFIC ROAD SIGN CATEGORY 3 (c) SM 133.33 119.73 9,191.86 2,361.23 11,806.15

607f ADDITIONAL PANEL SIZE 60 X 30 cm EACH 255.50 - 1,302.38 389.47 1,947.35

607g ADDITIONAL PANEL SIZE 90 X 30 cm EACH 255.50 - 1,953.58 552.27 2,761.34

608b1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.43 5.86 16.16 6.11 30.56
LINES OF 15 cm WIDTH

608b2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.81 4.03 39.60 11.11 55.56
LINES OF 15 cm WIDTH

608c1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.43 5.86 21.56 7.46 37.31
LINES OF 20 cm WIDTH

Page 162
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Mardan
Mardan District Code: 44

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

608c2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.81 4.03 52.82 14.42 72.08
LINES OF 20 cm WIDTH

608d1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 69.01 5.22 156.11 57.58 287.92
4.0 M ARROWS

608d2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR 4.0 EACH 69.01 9.98 499.08 144.52 722.59
M ARROWS

608h1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.04 8.59 22.47 8.53 42.63
OF 15 cm WIDTH

608h2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.04 9.63 67.50 20.04 100.22
OF 15 cm WIDTH

608i1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.04 6.95 29.96 9.99 49.94
OF 20 cm WIDTH

608i2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.04 9.63 90.01 25.67 128.35
OF 20 cm WIDTH

608j1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR 4.0 M EACH 69.01 3.73 216.97 72.43 362.13
ARROWS

608j2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR 4.0 M EACH 69.01 7.90 851.20 232.03 1,160.13
ARROWS

608n1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 57.42 3.73 104.08 41.30 206.52
STOP

608n2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR EACH 57.42 7.90 333.22 99.63 498.17
STOP

608n3 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR STOP EACH 57.42 3.73 144.65 51.45 257.24

608n4 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR STOP EACH 57.42 7.90 568.32 158.41 792.05

609c REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 8.62 81.62 193.79 71.01 355.04
SINGLE)

609d REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 8.62 81.62 233.79 81.00 405.02
DOUBLE)

610b RIGHT OF WAY MARKER EACH 90.22 121.33 297.85 127.35 636.74

610c KILOMETRE POST (0.610 X 0.114 X 1.5 M) EACH 562.34 976.31 1,996.14 883.70 4,418.48

610d TEN KILOMETRE POST EACH 1,078.31 1,952.61 4,390.39 1,855.33 9,276.63

611a CHAIN LINK WIRE FABRIC FENCING 1500 MM HEIGHT M 120.23 91.00 947.65 289.72 1,448.60
WITH PRECAST PRESTRESSED R.C.C. POST

Page 163
.

Page 164
NATIONAL HIGHWAY AUTHORITY

COMPOSITE SCHEDULE OF RATES


January - 2009

NOWSHERA
(49-C)

Shabir Associates
Quantity Surveying & Construction Cost Consultants

Page 165
.

Page 166
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Nowshera
Nowshera District Code: 49-C

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

101 CLEARING AND GRUBBING SM 0.65 10.10 - 2.69 13.44

102a REMOVAL OF TREES 150 - 300 mm GIRTH EACH 6.64 173.32 1.17 45.28 226.41

102b REMOVAL OF TREES 301 - 600 mm GIRTH EACH 18.79 456.54 2.63 119.49 597.45

102c REMOVAL OF TREES 601 mm OR OVER GIRTH EACH 75.17 1,826.16 10.51 477.96 2,389.80

103 STRIPPING CM 2.38 93.22 - 23.90 119.49

104 COMPACTION OF NATURAL GROUND SM 0.34 9.91 0.84 2.77 13.86

106a EXCAVATE UNSUITABLE COMMON MATERIAL CM 4.33 135.76 - 35.02 175.11

106bi EXCAVATE UNSUITABLE HARD ROCK MATERIAL CM 119.95 316.30 50.82 121.77 608.84

106bii EXCAVATE UNSUITABLE MEDIUM ROCK MATERIAL CM 16.54 337.99 - 88.63 443.17

106biii EXCAVATE UNSUITABLE SOFT ROCK MATERIAL CM 10.85 262.40 - 68.31 341.55

106c EXCAVATE SURPLUS COMMON MATERIAL CM 3.54 120.27 - 30.95 154.77

106di EXCAVATE SURPLUS HARD ROCK MATERIAL CM 119.95 316.30 50.82 121.77 608.84

106dii EXCAVATE SURPLUS MEDIUM ROCK MATERIAL CM 19.05 316.03 - 83.77 418.85

106diii EXCAVATE SURPLUS SOFT ROCK MATERIAL CM 8.41 263.92 - 68.08 340.41

107a STRUCTURAL EXCAVATION IN COMMON MATERIAL CM 7.12 137.60 0.42 36.29 181.43

107b STRUCTURAL EXCAVATION IN COMMON MATERIAL BELOW CM 59.47 287.11 70.80 104.35 521.74
WATER LEVEL

107ci STRUCTURAL EXCAVATION IN HARD ROCK MATERIAL CM 105.83 427.01 33.88 141.68 708.41

107cii STRUCTURAL EXCAVATION IN MEDIUM ROCK MATERIAL CM 89.41 292.53 - 95.48 477.42

107ciii STRUCTURAL EXCAVATION IN SOFT ROCK MATERIAL CM 54.43 238.86 - 73.32 366.61

107d GRANULAR BACK FILL CM 31.12 137.14 348.60 129.21 646.07

107e COMMON BACK FILL CM 22.31 62.84 5.59 22.69 113.43

108a FORMATION OF EMBANKMENT FROM ROADWAY CM 6.65 174.71 5.59 46.74 233.68
EXCAVATION IN COMMON MATERIAL

108bi FORMATION OF EMBANKMENT FROM ROADWAY CM 19.12 482.48 54.36 138.99 694.95
EXCAVATION IN HARD ROCK MATERIAL

108bii FORMATION OF EMBANKMENT FROM ROADWAY CM 14.34 416.71 2.66 108.43 542.14
EXCAVATION IN MEDIUM ROCK MATERIAL

108biii FORMATION OF EMBANKMENT FROM ROADWAY CM 12.75 369.34 - 95.52 477.62


EXCAVATION IN SOFT ROCK MATERIAL

108c FORMATION OF EMBANKMENT FROM BORROW CM 7.50 177.46 8.44 48.35 241.75
EXCAVATION IN COMMON MATERIAL

108d FORMATION OF EMBANKMENT FROM STRUCTURAL CM 6.00 76.32 5.59 21.98 109.89
EXCAVATION IN COMMON MATERIAL

108e FORMATION OF EMBANKMENT FROM STRUCTURAL CM 13.64 110.29 3.32 31.81 159.07
EXCAVATION IN ANY TYPE OF ROCK MATERIAL

109a SUB GRADE PREPARATION IN EARTH CUT SM 1.33 27.34 1.60 7.57 37.83

Page 167
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Nowshera
Nowshera District Code: 49-C

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

109bi SUB GRADE PREPARATION IN EXISTING ROAD WITHOUT SM 0.97 18.21 0.85 5.01 25.04
ANY FILL

110 IMPROVED SUB-GRADE CM 9.54 120.02 55.89 46.36 231.82

114a DRESSING OF BERM WITHOUT EXTRA MATERIAL SM 0.81 15.26 0.87 4.24 21.18

114b DRESSING OF BERM WITH EXTRA BORROW MATERIAL SM 1.21 15.57 0.97 4.44 22.20

201 GRANULAR SUB-BASE CM 7.61 255.06 522.71 196.34 981.72

202 AGGREGATE BASE CM 9.00 326.54 709.15 261.17 1,305.87

203a ASPHALTIC BASE COURSE PLANT MIX (CLASS "A") CM 65.29 1,510.17 5,834.90 1,852.59 9,262.95

203b ASPHALTIC BASE COURSE PLANT MIX (CLASS "B") CM 67.61 1,510.17 6,343.50 1,980.32 9,901.59

203c ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "A") CM 72.53 1,577.28 5,825.39 1,868.80 9,344.00

203d ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "B") CM 72.53 1,571.31 6,484.94 2,032.19 10,160.96

204b CEMENT STABILIZED BASE CM 27.19 569.10 1,114.16 427.61 2,138.07

204d LIQUID ASPHALT FOR CURING SEAL, TYPE MC-250 TON 225.00 915.38 50,453.37 12,898.44 64,492.18

204e EMULSIFIED ASPHALT FOR CURING SEAL, TYPE SS-1 TON 225.00 915.38 48,875.24 12,503.90 62,519.52

205a GRADED CRUSHED AGGREGATE CRACK-RELIEF LAYER CM 83.80 112.80 1,147.10 335.92 1,679.62

205b ASPHALTIC OPEN-GRADED PLANT MIX CRACK-RELIEF CM 136.21 2,437.94 5,661.44 2,058.90 10,294.50
LAYER

206b WATER BOUND MACADAM BASE WITH COARSE CM 91.82 126.27 721.47 234.89 1,174.45
AGGREGATE CLASS B

207a DEEP PATCHING (0-15 cm) SM 1.68 45.04 1.38 12.02 60.12

207b DEEP PATCHING (16-30 cm) SM 1.68 39.67 1.38 10.68 53.42

208 REINSTATEMENT OF ROAD SURFACE SM 1.79 57.10 0.62 14.88 74.38

209a BREAKING OF EXISTING ROAD PAVEMENT STRUCTURE CM 2.09 110.61 0.75 28.36 141.80

209b SCARIFICATION OF EXISTING ROAD PAVEMENT SM 0.42 22.12 0.15 5.67 28.36

302a CUT-BACK ASPHALT FOR BITUMINOUS PRIME COAT SM 0.28 1.57 35.81 9.42 47.08

302b EMULSIFIED ASPHALT FOR BITUMINOUS PRIME COAT SM 0.27 1.57 39.97 10.45 52.27

303a CUT-BACK ASPHALT FOR BITUMINOUS TACK COAT SM 0.11 0.58 14.99 3.92 19.60

303b EMULSIFIED ASPHALT FOR BITUMINOUS TACK COAT SM 0.11 0.58 17.48 4.54 22.72

304a SINGLE SURFACE TREATMENT SM 0.72 7.57 71.08 19.84 99.22

304b DOUBLE SURFACE TREATMENT SM 1.06 14.15 138.12 38.33 191.66

304c TRIPLE SURFACE TREATMENT SM 1.79 19.94 157.44 44.79 223.96

304d SEAL COAT SM 0.67 4.12 50.42 13.80 69.01

Page 168
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Nowshera
Nowshera District Code: 49-C

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

305a ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 61.96 1,489.33 6,872.70 2,106.00 10,529.99
"A")

305b ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 61.96 1,438.23 7,411.62 2,227.95 11,139.76
"B")

307a DENSE GRADED HOT BIT-MAC CM 153.19 379.77 5,639.30 1,543.07 7,715.33

307b OPEN GRADED HOT BIT-MAC CM 153.19 379.77 5,486.07 1,504.76 7,523.79

308a RECYCLING OF ASPHALT CONCRETE (0 - 60 mm THICK) CM 27.23 590.65 2,012.90 657.70 3,288.48

308b BITUMEN BINDER GRADE (40 - 50, 60 - 70, 80 - 100) TON 23.68 650.70 42,455.92 10,782.58 53,912.88

309a COLD MILLING, 0 - 30 mm SM 0.91 24.99 8.68 8.64 43.22

309b COLD MILLING, 0 - 50 mm SM 1.51 41.65 14.47 14.41 72.04

309c COLD MILLING, 0 - 70 mm SM 2.26 62.48 21.70 21.61 108.06

401a1i CONCRETE CLASS "A1" (Underground) CM 510.16 1,059.94 4,023.50 1,398.40 6,991.99

401a1ii CONCRETE CLASS "A1" (On ground) CM 510.16 1,059.94 4,300.97 1,467.77 7,338.83

401a1iii CONCRETE CLASS "A1" (Elevated) CM 510.16 1,059.94 4,855.91 1,606.50 8,032.51

401a2i CONCRETE CLASS "A2" (Underground) CM 510.16 1,059.94 4,401.50 1,492.90 7,464.49

401a2ii CONCRETE CLASS "A2" (On ground) CM 510.16 1,059.94 4,678.97 1,562.27 7,811.33

401a2iii CONCRETE CLASS "A2" (Elevated) CM 510.16 1,059.94 5,233.91 1,701.00 8,505.01

401a3i CONCRETE CLASS "A3" (Underground) CM 510.16 1,059.94 4,779.50 1,587.40 7,936.99

401a3ii CONCRETE CLASS "A3" (On ground) CM 510.16 1,059.94 5,056.97 1,656.77 8,283.83

401a3iii CONCRETE CLASS "A3" (Elevated) CM 510.16 1,059.94 5,611.91 1,795.50 8,977.51

401b CONCRETE CLASS "B" CM 648.47 805.93 3,373.09 1,206.87 6,034.35

401ci CONCRETE CLASS "C" (Underground) CM 497.42 500.55 3,632.12 1,157.52 5,787.61

401cii CONCRETE CLASS "C" (On ground) CM 497.42 500.55 3,750.46 1,187.11 5,935.54

401ciii CONCRETE CLASS "C" (Elevated) CM 497.42 500.55 3,987.14 1,246.28 6,231.39

401d CONCRETE CLASS "D1" CM 792.06 1,265.57 5,384.00 1,860.41 9,302.04

401e CONCRETE CLASS "Y" CM 1,083.81 500.55 4,796.59 1,595.24 7,976.18

401f LEAN CONCRETE CM 409.93 507.52 2,645.01 890.61 4,453.07

401gi(1) PRECAST CONCRETE CLASS "A-1" CM 1,653.45 947.15 5,026.30 1,906.73 9,533.63

401gi(3) PRECAST CONCRETE CLASS "A-3" CM 1,653.45 947.15 5,782.30 2,095.73 10,478.63

401gii PRECAST CONCRETE CLASS "B" CM 1,653.45 947.15 4,917.35 1,879.49 9,397.44

401giii(1) PRECAST CONCRETE CLASS "D1" CM 1,653.45 947.15 6,160.30 2,190.23 10,951.13

Page 169
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Nowshera
Nowshera District Code: 49-C

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

401giii(2) PRECAST CONCRETE CLASS "D2" CM 1,653.45 947.15 6,538.30 2,284.73 11,423.63

401giii(3) PRECAST CONCRETE CLASS "D3" CM 1,653.45 947.15 6,916.30 2,379.23 11,896.13

404a REINFORCEMENT AS PER AASHTO M. 31 GRADE 40 TON 1,542.00 781.47 59,358.00 15,420.37 77,101.84

404b REINFORCEMENT AS PER AASHTO M. 31 GRADE 60 TON 1,542.00 781.47 66,708.00 17,257.87 86,289.34

404h REINFORCEMENT (STRUCTURAL SHAPES) AS PER ASTM-A- TON 1,245.40 5,393.81 55,550.84 15,547.51 77,737.56
36

405a PRE-STRESSING WIRE STRAND 3/8" - 1/2" DIA COMPLETE IN TON 2,589.53 15,659.05 133,835.34 38,020.98 190,104.90
ALL RESPECT

405b LAUNCHING OF GIRDER TON 60.69 532.52 - 148.30 741.52

406a PREMOULDED JOINT FILLER 12 mm THICK WITH SM 109.40 - 299.97 102.34 511.71
BITUMASTIC JOINT SEAL

406b NEOPRENE RUBBER JOINT FILLER 12 mm THICK WITH SM 109.40 - 299.21 102.15 510.76
BITUMASTIC JOINT SEAL

406c STEEL EXPANSION JOINTS KG 8.91 26.40 90.20 31.38 156.89

406d WATER STOPS 6" SIZE M 97.26 - 472.16 142.36 711.78

406e ELASTOMERIC BEARING PADS (ACCORDING TO SIZE AND ccm 0.02 - 2.12 0.53 2.67
THICKNESS)

406f ASPHALT FELT (3 PLY) SM 39.32 - 2,960.87 750.05 3,750.24

406g STEEL OR METAL BEARING DEVICES KG 18.44 69.68 117.23 51.34 256.69

407d1 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 331.42 1,654.04 721.20 676.67 3,383.33
(BORING ONLY) IN NORMAL SOIL

407d2 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 497.13 2,481.06 1,081.80 1,015.00 5,075.00
(BORING ONLY) IN GRAVEL STRATA

407d3 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 497.13 2,481.06 821.16 949.84 4,749.20
ONLY) IN NORMAL SOIL

407d4 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 828.56 4,135.11 1,002.57 1,491.56 7,457.79
ONLY) IN GRAVEL STRATA

407d5 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 710.19 4,884.94 1,187.44 1,695.64 8,478.21
ONLY) IN NORMAL SOIL

407d6 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 1,242.83 6,909.78 1,297.97 2,362.65 11,813.23
ONLY) IN GRAVEL SOIL

407h PILE LOAD TEST UP TO 120 TON EACH 20,456.69 45,769.30 94,337.50 40,140.87 200,704.37

407i PILE LOAD TEST UP TO 240 TON EACH 37,790.54 45,769.30 188,675.00 68,058.71 340,293.55

407j PILE LOAD TEST UP TO 360 TON EACH 55,124.39 50,188.38 283,012.50 97,081.32 485,406.59

407k CONFIRMATORY BORING (NX SIZE) M 183.77 1,582.02 6.99 443.20 2,215.98

410 BRICK WORK CM 311.41 282.72 2,945.88 885.00 4,425.02

411a STONE MASONRY RANDOM DRY CM 268.29 107.96 354.71 182.74 913.69

411b STONE MASONRY RANDOM WITH MORTAR CM 289.35 166.68 1,418.88 468.73 2,343.64

411c STONE MASONRY DRESSED UNCOURSED DRY CM 348.93 107.96 400.18 214.27 1,071.34

411d STONE MASONRY DRESSED UNCOURSED WITH MORTAR CM 410.32 166.68 1,467.00 511.00 2,554.99

Page 170
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Nowshera
Nowshera District Code: 49-C

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

411g ROLL POINTING SM 66.40 11.74 44.43 30.64 153.22

412a STONE MASONRY DRESSED COURSED WITH MORTAR CM 550.54 264.08 1,372.19 546.70 2,733.52

501a R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 310 mm M 205.55 437.48 645.26 322.07 1,610.36

501b R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 380 mm M 199.71 577.19 836.33 403.31 2,016.53

501c R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 460 mm M 198.90 935.96 1,072.37 551.81 2,759.04

501d R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 610 mm M 207.09 1,146.39 1,601.34 738.70 3,693.52

501e R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 760 mm M 237.82 1,078.41 2,300.98 904.30 4,521.52

501f R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 910 mm M 294.72 1,331.30 3,619.02 1,311.26 6,556.30

501g R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1070 mm M 381.40 1,481.41 4,685.47 1,637.07 8,185.34

501h R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1220 mm M 448.08 1,798.85 5,970.71 2,054.41 10,272.06

501i R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1520 mm M 530.47 2,098.66 9,221.00 2,962.53 14,812.65

501j R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 310 mm M 205.55 507.33 725.14 359.50 1,797.52

501k R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 380 mm M 199.71 577.19 855.15 408.01 2,040.05

501l R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 460 mm M 192.99 935.96 1,046.95 543.98 2,719.88

501m R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 610 mm M 207.09 1,146.39 1,745.98 774.86 3,874.32

501n R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 760 mm M 237.82 1,078.41 3,319.59 1,158.95 5,794.77

501o R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 910 mm M 294.72 1,331.30 4,876.33 1,625.59 8,127.94

501p R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1070 mm M 381.40 1,481.41 6,813.90 2,169.18 10,845.88

501q R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1220 mm M 448.08 1,798.85 9,240.99 2,871.98 14,359.91

501r R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1520 mm M 530.47 2,098.66 12,999.86 3,907.25 19,536.23

502a GRANULAR MATERIAL IN BED TO CONCRETE PIPE CM 81.95 118.93 343.94 136.20 681.02
CULVERT

502b CONCRETE CLASS "B" IN BEDDING AND ENCASEMENT OF CM 741.53 612.95 3,723.09 1,269.39 6,346.95
CONCRETE PIPE CULVERT

507a STEEL WIRE MESH FOR GABIONS KG 4.88 - 109.41 28.57 142.86

507b ROCK FILL IN GABIONS CM 87.00 - 352.92 109.98 549.89

508a BRICK PAVING (SINGLE COURSE) SM 102.19 32.70 229.36 91.06 455.30

508b BRICK PAVING (DOUBLE COURSE) SM 182.83 32.70 455.62 167.79 838.93

509a RIP RAP CLASS "A" CM 444.69 - 259.90 176.15 880.73

509b RIP RAP CLASS "B" CM 427.97 - 257.82 171.45 857.24

509c RIP RAP CLASS "C" CM 430.87 - 259.90 172.69 863.46

Page 171
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Nowshera
Nowshera District Code: 49-C

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

509d GROUTED RIP RAP CLASS "A" CM 542.23 102.14 1,676.62 580.25 2,901.25

509e GROUTED RIP RAP CLASS "B" CM 522.86 81.72 1,527.46 533.01 2,665.04

509f GROUTED RIP RAP CLASS "C" CM 516.36 68.10 1,572.02 539.12 2,695.59

509g REINFORCED CONCRETE SLOPE PROTECTION (WITHOUT CM 753.12 353.02 4,223.93 1,332.52 6,662.60
REINFORCEMENT)

509h FILTER LAYER OF GRANULAR MATERIAL CM 43.69 191.97 348.97 146.16 730.79

510 DISMANTLING OF STRUCTURE AND OBSTRUCTIONS CM 98.37 390.69 - 122.26 611.32

511a1 DRY STONE PITCHING (15-20 cm Thick) SM 140.98 67.48 42.23 62.67 313.36

511a2 DRY STONE PITCHING (21-25 cm Thick) SM 180.46 86.37 54.06 80.22 401.11

511b1 GROUTED STONE PITCHING (15-20 cm Thick) SM 229.56 180.32 340.30 187.55 937.73

511b2 GROUTED STONE PITCHING (21-25 cm Thick) SM 286.96 225.40 425.37 234.43 1,172.16

601ai CONCRETE KERB IN PLACE NEW JERSY BARRIER FOR M 270.40 572.25 2,250.96 773.40 3,867.02
MEDIAN (DOUBLE FACE)

601di PRECAST REINFORCED CONCRETE KERB NEW JERSY M 908.20 670.54 4,087.99 1,416.68 7,083.41
BARRIER FOR MEDIAN (DOUBLE FACE)

601dii PRECAST KERB IN CONCRETE CLASS A-1 OF SIZE 450 X 150 MM M 131.78 90.27 439.39 165.36 826.80
INCLUDING CONCRETE BEDDING & HAUNCHING

603 BRICK EDGING M 8.21 - 36.48 11.17 55.86

604a METAL GUARD RAIL M 17.51 70.84 1,579.36 416.93 2,084.63

604b METAL GUARD RAIL END PIECES EACH 23.26 - 1,197.58 305.21 1,526.04

604d STEEL POST OF METAL GUARD RAIL EACH 81.31 976.73 3,776.31 1,208.59 6,042.93

605a CONCRETE BEAM GUARD RAIL M 67.96 30.82 592.48 172.82 864.08

605c CONCRETE POST FOR GUARD RAIL M 83.44 27.36 593.14 175.99 879.93

607a TRAFFIC ROAD SIGN CATEGORY 1 EACH 216.80 255.15 6,861.40 1,833.34 9,166.68

607b TRAFFIC ROAD SIGN CATEGORY 2 EACH 68.98 382.72 9,264.49 2,429.05 12,145.24

607c TRAFFIC ROAD SIGN CATEGORY 3 (a) EACH 216.80 541.89 11,901.10 3,164.94 15,824.72

607d TRAFFIC ROAD SIGN CATEGORY 3 (b) EACH 690.91 598.64 20,975.29 5,566.21 27,831.05

607e TRAFFIC ROAD SIGN CATEGORY 3 (c) SM 138.18 119.73 9,208.96 2,366.72 11,833.59

607f ADDITIONAL PANEL SIZE 60 X 30 cm EACH 260.73 - 1,302.22 390.74 1,953.69

607g ADDITIONAL PANEL SIZE 90 X 30 cm EACH 260.73 - 1,953.34 553.52 2,767.58

608b1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.63 5.86 16.16 6.16 30.81
LINES OF 15 cm WIDTH

608b2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.88 4.03 39.59 11.12 55.62
LINES OF 15 cm WIDTH

608c1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.63 5.86 21.56 7.51 37.56
LINES OF 20 cm WIDTH

Page 172
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Nowshera
Nowshera District Code: 49-C

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

608c2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.88 4.03 52.80 14.43 72.13
LINES OF 20 cm WIDTH

608d1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 70.24 5.22 156.10 57.89 289.44
4.0 M ARROWS

608d2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR 4.0 EACH 70.24 9.98 498.88 144.78 723.88
M ARROWS

608h1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.29 8.59 22.47 8.59 42.93
OF 15 cm WIDTH

608h2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.29 9.63 67.50 20.11 100.53
OF 15 cm WIDTH

608i1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.29 6.95 29.96 10.05 50.25
OF 20 cm WIDTH

608i2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.29 9.63 90.01 25.73 128.66
OF 20 cm WIDTH

608j1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR 4.0 M EACH 70.24 3.73 216.96 72.73 363.65
ARROWS

608j2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR 4.0 M EACH 70.24 7.90 851.20 232.33 1,161.67
ARROWS

608n1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 58.75 3.73 104.07 41.64 208.18
STOP

608n2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR EACH 58.75 7.90 333.09 99.93 499.67
STOP

608n3 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR STOP EACH 58.75 3.73 144.64 51.78 258.89

608n4 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR STOP EACH 58.75 7.90 568.32 158.74 793.71

609c REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 9.52 81.62 193.85 71.25 356.24
SINGLE)

609d REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 9.52 81.62 233.85 81.25 406.23
DOUBLE)

610b RIGHT OF WAY MARKER EACH 94.09 121.33 303.65 129.77 648.83

610c KILOMETRE POST (0.610 X 0.114 X 1.5 M) EACH 575.57 976.31 2,041.81 898.42 4,492.10

610d TEN KILOMETRE POST EACH 1,105.19 1,952.61 4,479.36 1,884.29 9,421.44

611a CHAIN LINK WIRE FABRIC FENCING 1500 MM HEIGHT M 126.08 91.00 957.59 293.67 1,468.35
WITH PRECAST PRESTRESSED R.C.C. POST

Page 173
.

Page 174
NATIONAL HIGHWAY AUTHORITY

COMPOSITE SCHEDULE OF RATES


January - 2009

PESHAWAR
(52)

Shabir Associates
Quantity Surveying & Construction Cost Consultants

Page 175
.

Page 176
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Peshawar
Peshawar District Code: 52

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

101 CLEARING AND GRUBBING SM 0.73 10.10 - 2.71 13.54

102a REMOVAL OF TREES 150 - 300 mm GIRTH EACH 7.25 173.32 1.17 45.43 227.17

102b REMOVAL OF TREES 301 - 600 mm GIRTH EACH 20.90 456.54 2.63 120.02 600.08

102c REMOVAL OF TREES 601 mm OR OVER GIRTH EACH 83.60 1,826.16 10.51 480.07 2,400.33

103 STRIPPING CM 2.54 93.22 - 23.94 119.70

104 COMPACTION OF NATURAL GROUND SM 0.36 9.91 0.76 2.76 13.79

106a EXCAVATE UNSUITABLE COMMON MATERIAL CM 4.16 135.76 - 34.98 174.90

106bi EXCAVATE UNSUITABLE HARD ROCK MATERIAL CM 120.09 316.30 50.82 121.80 609.01

106bii EXCAVATE UNSUITABLE MEDIUM ROCK MATERIAL CM 16.91 337.99 - 88.73 443.63

106biii EXCAVATE UNSUITABLE SOFT ROCK MATERIAL CM 10.99 262.40 - 68.35 341.73

106c EXCAVATE SURPLUS COMMON MATERIAL CM 3.40 120.27 - 30.92 154.59

106di EXCAVATE SURPLUS HARD ROCK MATERIAL CM 120.09 316.30 50.82 121.80 609.01

106dii EXCAVATE SURPLUS MEDIUM ROCK MATERIAL CM 19.01 316.03 - 83.76 418.80

106diii EXCAVATE SURPLUS SOFT ROCK MATERIAL CM 8.56 263.92 - 68.12 340.60

107a STRUCTURAL EXCAVATION IN COMMON MATERIAL CM 7.05 137.60 0.38 36.26 181.29

107b STRUCTURAL EXCAVATION IN COMMON MATERIAL BELOW CM 63.35 287.11 70.80 105.32 526.58
WATER LEVEL

107ci STRUCTURAL EXCAVATION IN HARD ROCK MATERIAL CM 105.61 427.01 33.88 141.63 708.13

107cii STRUCTURAL EXCAVATION IN MEDIUM ROCK MATERIAL CM 89.47 292.53 - 95.50 477.51

107ciii STRUCTURAL EXCAVATION IN SOFT ROCK MATERIAL CM 54.31 238.86 - 73.29 366.47

107d GRANULAR BACK FILL CM 33.11 137.14 333.46 125.93 629.64

107e COMMON BACK FILL CM 25.38 62.84 5.09 23.33 116.64

108a FORMATION OF EMBANKMENT FROM ROADWAY CM 6.69 174.71 5.09 46.62 233.12
EXCAVATION IN COMMON MATERIAL

108bi FORMATION OF EMBANKMENT FROM ROADWAY CM 19.78 482.48 54.04 139.08 695.38
EXCAVATION IN HARD ROCK MATERIAL

108bii FORMATION OF EMBANKMENT FROM ROADWAY CM 14.84 416.71 2.42 108.49 542.46
EXCAVATION IN MEDIUM ROCK MATERIAL

108biii FORMATION OF EMBANKMENT FROM ROADWAY CM 13.19 369.34 - 95.63 478.16


EXCAVATION IN SOFT ROCK MATERIAL

108c FORMATION OF EMBANKMENT FROM BORROW CM 7.71 177.46 7.94 48.28 241.39
EXCAVATION IN COMMON MATERIAL

108d FORMATION OF EMBANKMENT FROM STRUCTURAL CM 6.10 76.32 5.09 21.88 109.38
EXCAVATION IN COMMON MATERIAL

108e FORMATION OF EMBANKMENT FROM STRUCTURAL CM 14.35 110.29 3.03 31.92 159.58
EXCAVATION IN ANY TYPE OF ROCK MATERIAL

109a SUB GRADE PREPARATION IN EARTH CUT SM 1.35 27.34 1.46 7.54 37.68

Page 177
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Peshawar
Peshawar District Code: 52

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

109bi SUB GRADE PREPARATION IN EXISTING ROAD WITHOUT SM 0.99 18.21 0.77 4.99 24.97
ANY FILL

110 IMPROVED SUB-GRADE CM 9.91 120.02 52.41 45.58 227.92

114a DRESSING OF BERM WITHOUT EXTRA MATERIAL SM 0.85 15.26 0.79 4.23 21.13

114b DRESSING OF BERM WITH EXTRA BORROW MATERIAL SM 1.26 15.57 0.90 4.43 22.16

201 GRANULAR SUB-BASE CM 7.76 255.06 532.84 198.92 994.59

202 AGGREGATE BASE CM 8.94 326.54 708.80 261.07 1,305.35

203a ASPHALTIC BASE COURSE PLANT MIX (CLASS "A") CM 71.94 1,510.17 6,008.75 1,897.71 9,488.57

203b ASPHALTIC BASE COURSE PLANT MIX (CLASS "B") CM 74.08 1,510.17 6,426.94 2,002.80 10,013.99

203c ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "A") CM 79.29 1,577.28 5,998.73 1,913.83 9,569.13

203d ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "B") CM 79.29 1,571.31 6,573.83 2,056.11 10,280.54

204b CEMENT STABILIZED BASE CM 27.60 569.10 1,006.80 400.88 2,004.38

204d LIQUID ASPHALT FOR CURING SEAL, TYPE MC-250 TON 229.99 915.38 52,980.39 13,531.44 67,657.19

204e EMULSIFIED ASPHALT FOR CURING SEAL, TYPE SS-1 TON 229.99 915.38 51,402.26 13,136.91 65,684.53

205a GRADED CRUSHED AGGREGATE CRACK-RELIEF LAYER CM 96.57 112.80 894.28 275.91 1,379.56

205b ASPHALTIC OPEN-GRADED PLANT MIX CRACK-RELIEF CM 145.67 2,437.94 5,677.41 2,065.26 10,326.28
LAYER

206b WATER BOUND MACADAM BASE WITH COARSE CM 106.17 126.27 744.50 244.24 1,221.19
AGGREGATE CLASS B

207a DEEP PATCHING (0-15 cm) SM 1.72 45.04 1.26 12.00 60.02

207b DEEP PATCHING (16-30 cm) SM 1.72 39.67 1.26 10.66 53.32

208 REINSTATEMENT OF ROAD SURFACE SM 1.80 57.10 0.56 14.87 74.33

209a BREAKING OF EXISTING ROAD PAVEMENT STRUCTURE CM 2.08 110.61 0.68 28.34 141.72

209b SCARIFICATION OF EXISTING ROAD PAVEMENT SM 0.42 22.12 0.14 5.67 28.34

302a CUT-BACK ASPHALT FOR BITUMINOUS PRIME COAT SM 0.28 1.57 37.60 9.86 49.32

302b EMULSIFIED ASPHALT FOR BITUMINOUS PRIME COAT SM 0.27 1.57 41.97 10.95 54.77

303a CUT-BACK ASPHALT FOR BITUMINOUS TACK COAT SM 0.11 0.58 15.74 4.11 20.54

303b EMULSIFIED ASPHALT FOR BITUMINOUS TACK COAT SM 0.11 0.58 18.36 4.76 23.82

304a SINGLE SURFACE TREATMENT SM 0.73 7.57 74.72 20.76 103.78

304b DOUBLE SURFACE TREATMENT SM 1.06 14.15 144.56 39.94 199.72

304c TRIPLE SURFACE TREATMENT SM 1.79 19.94 164.93 46.66 233.32

304d SEAL COAT SM 0.66 4.12 52.89 14.42 72.10

Page 178
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Peshawar
Peshawar District Code: 52

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

305a ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 66.97 1,489.33 7,054.66 2,152.74 10,763.69
"A")

305b ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 66.97 1,438.23 7,617.63 2,280.71 11,403.54
"B")

307a DENSE GRADED HOT BIT-MAC CM 167.94 379.77 5,855.80 1,600.88 8,004.39

307b OPEN GRADED HOT BIT-MAC CM 167.94 379.77 5,681.91 1,557.41 7,787.03

308a RECYCLING OF ASPHALT CONCRETE (0 - 60 mm THICK) CM 29.52 590.65 2,066.62 671.70 3,358.48

308b BITUMEN BINDER GRADE (40 - 50, 60 - 70, 80 - 100) TON 25.16 650.70 45,058.00 11,433.46 57,167.32

309a COLD MILLING, 0 - 30 mm SM 0.92 24.99 8.68 8.65 43.24

309b COLD MILLING, 0 - 50 mm SM 1.54 41.65 14.46 14.41 72.07

309c COLD MILLING, 0 - 70 mm SM 2.31 62.48 21.69 21.62 108.10

401a1i CONCRETE CLASS "A1" (Underground) CM 555.13 1,059.94 3,950.88 1,391.49 6,957.44

401a1ii CONCRETE CLASS "A1" (On ground) CM 555.13 1,059.94 4,228.35 1,460.86 7,304.28

401a1iii CONCRETE CLASS "A1" (Elevated) CM 555.13 1,059.94 4,783.30 1,599.59 7,997.96

401a2i CONCRETE CLASS "A2" (Underground) CM 555.13 1,059.94 4,328.88 1,485.99 7,429.94

401a2ii CONCRETE CLASS "A2" (On ground) CM 555.13 1,059.94 4,606.35 1,555.36 7,776.78

401a2iii CONCRETE CLASS "A2" (Elevated) CM 555.13 1,059.94 5,161.30 1,694.09 8,470.46

401a3i CONCRETE CLASS "A3" (Underground) CM 555.13 1,059.94 4,706.88 1,580.49 7,902.44

401a3ii CONCRETE CLASS "A3" (On ground) CM 555.13 1,059.94 4,984.35 1,649.86 8,249.28

401a3iii CONCRETE CLASS "A3" (Elevated) CM 555.13 1,059.94 5,539.30 1,788.59 8,942.96

401b CONCRETE CLASS "B" CM 701.79 805.93 3,166.06 1,168.45 5,842.23

401ci CONCRETE CLASS "C" (Underground) CM 554.77 500.55 3,495.49 1,137.70 5,688.51

401cii CONCRETE CLASS "C" (On ground) CM 554.77 500.55 3,613.83 1,167.29 5,836.44

401ciii CONCRETE CLASS "C" (Elevated) CM 554.77 500.55 3,850.52 1,226.46 6,132.29

401d CONCRETE CLASS "D1" CM 873.14 1,265.57 5,288.11 1,856.70 9,283.51

401e CONCRETE CLASS "Y" CM 1,210.97 500.55 4,743.96 1,613.87 8,069.34

401f LEAN CONCRETE CM 464.79 507.52 2,324.42 824.18 4,120.90

401gi(1) PRECAST CONCRETE CLASS "A-1" CM 1,873.57 947.15 4,953.74 1,943.61 9,718.07

401gi(3) PRECAST CONCRETE CLASS "A-3" CM 1,873.57 947.15 5,709.74 2,132.61 10,663.07

401gii PRECAST CONCRETE CLASS "B" CM 1,873.57 947.15 4,688.65 1,877.34 9,386.71

401giii(1) PRECAST CONCRETE CLASS "D1" CM 1,873.57 947.15 6,087.74 2,227.11 11,135.57

Page 179
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Peshawar
Peshawar District Code: 52

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

401giii(2) PRECAST CONCRETE CLASS "D2" CM 1,873.57 947.15 6,465.74 2,321.61 11,608.07

401giii(3) PRECAST CONCRETE CLASS "D3" CM 1,873.57 947.15 6,843.74 2,416.11 12,080.57

404a REINFORCEMENT AS PER AASHTO M. 31 GRADE 40 TON 1,679.56 781.47 59,517.00 15,494.51 77,472.54

404b REINFORCEMENT AS PER AASHTO M. 31 GRADE 60 TON 1,679.56 781.47 66,867.00 17,332.01 86,660.04

404h REINFORCEMENT (STRUCTURAL SHAPES) AS PER ASTM-A- TON 1,347.37 5,393.81 55,564.70 15,576.47 77,882.36
36

405a PRE-STRESSING WIRE STRAND 3/8" - 1/2" DIA COMPLETE IN TON 2,533.18 15,659.05 133,834.60 38,006.71 190,033.53
ALL RESPECT

405b LAUNCHING OF GIRDER TON 59.88 532.52 - 148.10 740.50

406a PREMOULDED JOINT FILLER 12 mm THICK WITH SM 120.32 - 303.49 105.95 529.77
BITUMASTIC JOINT SEAL

406b NEOPRENE RUBBER JOINT FILLER 12 mm THICK WITH SM 120.32 - 302.69 105.75 528.76
BITUMASTIC JOINT SEAL

406c STEEL EXPANSION JOINTS KG 9.80 26.40 90.19 31.60 157.98

406d WATER STOPS 6" SIZE M 108.40 - 472.37 145.19 725.97

406e ELASTOMERIC BEARING PADS (ACCORDING TO SIZE AND ccm 0.02 - 2.12 0.54 2.68
THICKNESS)

406f ASPHALT FELT (3 PLY) SM 44.19 - 3,025.05 767.31 3,836.55

406g STEEL OR METAL BEARING DEVICES KG 19.65 69.68 117.21 51.64 258.18

407d1 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 332.38 1,654.04 689.73 669.04 3,345.20
(BORING ONLY) IN NORMAL SOIL

407d2 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 498.58 2,481.06 1,034.60 1,003.56 5,017.80
(BORING ONLY) IN GRAVEL STRATA

407d3 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 498.58 2,481.06 773.98 938.41 4,692.03
ONLY) IN NORMAL SOIL

407d4 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 830.96 4,135.11 923.94 1,472.50 7,362.51
ONLY) IN GRAVEL STRATA

407d5 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 712.25 4,884.94 1,056.02 1,663.30 8,316.51
ONLY) IN NORMAL SOIL

407d6 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 1,246.44 6,909.78 1,180.02 2,334.06 11,670.30
ONLY) IN GRAVEL SOIL

407h PILE LOAD TEST UP TO 120 TON EACH 23,557.91 45,769.30 90,203.26 39,882.62 199,413.09

407i PILE LOAD TEST UP TO 240 TON EACH 44,237.21 45,769.30 180,406.51 67,603.26 338,016.29

407j PILE LOAD TEST UP TO 360 TON EACH 64,916.51 50,188.38 270,609.77 96,428.67 482,143.33

407k CONFIRMATORY BORING (NX SIZE) M 197.07 1,582.02 6.36 446.36 2,231.82

410 BRICK WORK CM 364.29 282.72 3,085.20 933.05 4,665.26

411a STONE MASONRY RANDOM DRY CM 308.88 107.96 407.06 205.97 1,029.87

411b STONE MASONRY RANDOM WITH MORTAR CM 333.77 166.68 1,459.88 490.08 2,450.42

411c STONE MASONRY DRESSED UNCOURSED DRY CM 404.62 107.96 456.73 242.33 1,211.63

411d STONE MASONRY DRESSED UNCOURSED WITH MORTAR CM 477.38 166.68 1,513.97 539.51 2,697.54

Page 180
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Peshawar
Peshawar District Code: 52

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

411g ROLL POINTING SM 78.47 11.74 44.19 33.60 168.01

412a STONE MASONRY DRESSED COURSED WITH MORTAR CM 643.96 264.08 1,419.17 581.80 2,909.01

501a R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 310 mm M 236.91 437.48 644.22 329.65 1,648.27

501b R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 380 mm M 231.33 577.19 835.16 410.92 2,054.60

501c R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 460 mm M 224.30 935.96 1,071.01 557.82 2,789.08

501d R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 610 mm M 235.24 1,146.39 1,599.58 745.30 3,726.51

501e R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 760 mm M 268.33 1,078.41 2,299.22 911.49 4,557.46

501f R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 910 mm M 330.28 1,331.30 3,616.50 1,319.52 6,597.60

501g R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1070 mm M 427.42 1,481.41 4,682.44 1,647.82 8,239.09

501h R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1220 mm M 501.24 1,798.85 5,967.04 2,066.78 10,333.92

501i R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1520 mm M 594.03 2,098.66 9,216.71 2,977.35 14,886.76

501j R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 310 mm M 236.91 507.33 723.76 367.00 1,835.00

501k R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 380 mm M 231.33 577.19 853.98 415.63 2,078.13

501l R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 460 mm M 217.41 935.96 1,045.59 549.74 2,748.69

501m R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 610 mm M 235.24 1,146.39 1,744.74 781.59 3,907.96

501n R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 760 mm M 268.33 1,078.41 3,317.53 1,166.07 5,830.35

501o R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 910 mm M 330.28 1,331.30 4,873.81 1,633.85 8,169.24

501p R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1070 mm M 427.42 1,481.41 6,810.87 2,179.93 10,899.63

501q R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1220 mm M 501.24 1,798.85 9,237.32 2,884.35 14,421.76

501r R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1520 mm M 594.03 2,098.66 12,995.57 3,922.07 19,610.33

502a GRANULAR MATERIAL IN BED TO CONCRETE PIPE CM 91.45 118.93 287.07 124.36 621.81
CULVERT

502b CONCRETE CLASS "B" IN BEDDING AND ENCASEMENT OF CM 807.16 612.95 3,516.06 1,234.04 6,170.21
CONCRETE PIPE CULVERT

507a STEEL WIRE MESH FOR GABIONS KG 5.27 - 110.25 28.88 144.40

507b ROCK FILL IN GABIONS CM 99.33 - 388.21 121.88 609.42

508a BRICK PAVING (SINGLE COURSE) SM 119.09 32.70 243.91 98.93 494.63

508b BRICK PAVING (DOUBLE COURSE) SM 214.83 32.70 485.21 183.19 915.93

509a RIP RAP CLASS "A" CM 519.51 - 312.25 207.94 1,039.71

509b RIP RAP CLASS "B" CM 501.39 - 309.75 202.79 1,013.93

509c RIP RAP CLASS "C" CM 505.90 - 312.25 204.54 1,022.69

Page 181
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Peshawar
Peshawar District Code: 52

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

509d GROUTED RIP RAP CLASS "A" CM 633.45 102.14 1,721.73 614.33 3,071.66

509e GROUTED RIP RAP CLASS "B" CM 612.45 81.72 1,572.83 566.75 2,833.75

509f GROUTED RIP RAP CLASS "C" CM 606.12 68.10 1,617.51 572.93 2,864.66

509g REINFORCED CONCRETE SLOPE PROTECTION (WITHOUT CM 865.81 353.02 4,082.58 1,325.35 6,626.77
REINFORCEMENT)

509h FILTER LAYER OF GRANULAR MATERIAL CM 49.42 191.97 333.54 143.73 718.66

510 DISMANTLING OF STRUCTURE AND OBSTRUCTIONS CM 106.57 390.69 - 124.32 621.58

511a1 DRY STONE PITCHING (15-20 cm Thick) SM 162.73 67.48 50.74 70.24 351.19

511a2 DRY STONE PITCHING (21-25 cm Thick) SM 208.30 86.37 64.95 89.90 449.52

511b1 GROUTED STONE PITCHING (15-20 cm Thick) SM 266.51 180.32 349.62 199.11 995.56

511b2 GROUTED STONE PITCHING (21-25 cm Thick) SM 333.13 225.40 437.03 248.89 1,244.45

601ai CONCRETE KERB IN PLACE NEW JERSY BARRIER FOR M 294.22 572.25 2,213.17 769.91 3,849.54
MEDIAN (DOUBLE FACE)

601di PRECAST REINFORCED CONCRETE KERB NEW JERSY M 1,028.38 670.54 4,053.46 1,438.10 7,190.48
BARRIER FOR MEDIAN (DOUBLE FACE)

601dii PRECAST KERB IN CONCRETE CLASS A-1 OF SIZE 450 X 150 MM M 149.20 90.27 425.90 166.34 831.71
INCLUDING CONCRETE BEDDING & HAUNCHING

603 BRICK EDGING M 9.38 - 39.36 12.19 60.93

604a METAL GUARD RAIL M 17.89 70.84 1,579.41 417.04 2,085.19

604b METAL GUARD RAIL END PIECES EACH 24.73 - 1,197.61 305.59 1,527.93

604d STEEL POST OF METAL GUARD RAIL EACH 82.12 976.73 3,776.44 1,208.82 6,044.11

605a CONCRETE BEAM GUARD RAIL M 78.78 30.82 589.38 174.75 873.73

605c CONCRETE POST FOR GUARD RAIL M 96.73 27.36 589.34 178.36 891.79

607a TRAFFIC ROAD SIGN CATEGORY 1 EACH 241.22 255.15 6,843.57 1,834.99 9,174.93

607b TRAFFIC ROAD SIGN CATEGORY 2 EACH 79.52 382.72 9,234.28 2,424.13 12,120.66

607c TRAFFIC ROAD SIGN CATEGORY 3 (a) EACH 241.22 541.89 11,847.68 3,157.70 15,788.49

607d TRAFFIC ROAD SIGN CATEGORY 3 (b) EACH 794.57 598.64 20,892.36 5,571.39 27,856.97

607e TRAFFIC ROAD SIGN CATEGORY 3 (c) SM 158.91 119.73 9,189.01 2,366.91 11,834.56

607f ADDITIONAL PANEL SIZE 60 X 30 cm EACH 274.28 - 1,301.21 393.87 1,969.37

607g ADDITIONAL PANEL SIZE 90 X 30 cm EACH 274.28 - 1,951.82 556.52 2,782.62

608b1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.89 5.86 16.16 6.23 31.13
LINES OF 15 cm WIDTH

608b2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.96 4.03 39.61 11.15 55.75
LINES OF 15 cm WIDTH

608c1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.89 5.86 21.56 7.58 37.88
LINES OF 20 cm WIDTH

Page 182
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Peshawar
Peshawar District Code: 52

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

608c2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.96 4.03 52.83 14.46 72.28
LINES OF 20 cm WIDTH

608d1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 77.67 5.22 156.12 59.75 298.75
4.0 M ARROWS

608d2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR 4.0 EACH 77.67 9.98 499.17 146.70 733.52
M ARROWS

608h1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.61 8.59 22.47 8.67 43.34
OF 15 cm WIDTH

608h2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.61 9.63 67.51 20.19 100.93
OF 15 cm WIDTH

608i1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.61 6.95 29.96 10.13 50.65
OF 20 cm WIDTH

608i2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.61 9.63 90.01 25.81 129.06
OF 20 cm WIDTH

608j1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR 4.0 M EACH 77.67 3.73 216.98 74.59 372.96
ARROWS

608j2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR 4.0 M EACH 77.67 7.90 851.21 234.19 1,170.97
ARROWS

608n1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 65.03 3.73 104.08 43.21 216.04
STOP

608n2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR EACH 65.03 7.90 333.28 101.55 507.76
STOP

608n3 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR STOP EACH 65.03 3.73 144.65 53.35 266.76

608n4 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR STOP EACH 65.03 7.90 568.33 160.31 801.57

609c REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 10.74 81.62 193.83 71.55 357.74
SINGLE)

609d REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 10.74 81.62 233.83 81.55 407.73
DOUBLE)

610b RIGHT OF WAY MARKER EACH 109.35 121.33 299.80 132.62 663.10

610c KILOMETRE POST (0.610 X 0.114 X 1.5 M) EACH 659.88 976.31 2,011.42 911.90 4,559.51

610d TEN KILOMETRE POST EACH 1,262.32 1,952.61 4,419.25 1,908.55 9,542.74

611a CHAIN LINK WIRE FABRIC FENCING 1500 MM HEIGHT M 139.93 91.00 950.34 295.32 1,476.60
WITH PRECAST PRESTRESSED R.C.C. POST

Page 183
.

Page 184
NATIONAL HIGHWAY AUTHORITY

COMPOSITE SCHEDULE OF RATES


January - 2009

SWAT SAIDU SHARIF


(66)

Shabir Associates
Quantity Surveying & Construction Cost Consultants

Page 185
.

Page 186
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Swat
Swat Saidu
Saidu Sharif
Sharif District Code: 66

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

101 CLEARING AND GRUBBING SM 0.72 11.11 - 2.96 14.79

102a REMOVAL OF TREES 150 - 300 mm GIRTH EACH 7.49 190.65 1.28 49.86 249.28

102b REMOVAL OF TREES 301 - 600 mm GIRTH EACH 21.09 502.19 2.89 131.54 657.72

102c REMOVAL OF TREES 601 mm OR OVER GIRTH EACH 84.36 2,008.78 11.56 526.17 2,630.87

103 STRIPPING CM 2.73 102.54 - 26.32 131.58

104 COMPACTION OF NATURAL GROUND SM 0.39 10.90 0.84 3.03 15.16

106a EXCAVATE UNSUITABLE COMMON MATERIAL CM 5.04 149.33 - 38.59 192.97

106bi EXCAVATE UNSUITABLE HARD ROCK MATERIAL CM 136.07 347.93 55.90 134.98 674.88

106bii EXCAVATE UNSUITABLE MEDIUM ROCK MATERIAL CM 18.55 371.79 - 97.59 487.93

106biii EXCAVATE UNSUITABLE SOFT ROCK MATERIAL CM 12.21 288.63 - 75.21 376.06

106c EXCAVATE SURPLUS COMMON MATERIAL CM 4.13 132.30 - 34.11 170.53

106di EXCAVATE SURPLUS HARD ROCK MATERIAL CM 136.07 347.93 55.90 134.98 674.88

106dii EXCAVATE SURPLUS MEDIUM ROCK MATERIAL CM 21.60 347.63 - 92.31 461.54

106diii EXCAVATE SURPLUS SOFT ROCK MATERIAL CM 9.45 290.32 - 74.94 374.70

107a STRUCTURAL EXCAVATION IN COMMON MATERIAL CM 8.27 151.36 0.42 40.01 200.06

107b STRUCTURAL EXCAVATION IN COMMON MATERIAL BELOW CM 67.13 315.83 77.89 115.21 576.05
WATER LEVEL

107ci STRUCTURAL EXCAVATION IN HARD ROCK MATERIAL CM 119.99 469.72 37.27 156.74 783.72

107cii STRUCTURAL EXCAVATION IN MEDIUM ROCK MATERIAL CM 101.07 321.79 - 105.71 528.57

107ciii STRUCTURAL EXCAVATION IN SOFT ROCK MATERIAL CM 61.71 262.75 - 81.11 405.57

107d GRANULAR BACK FILL CM 35.12 150.85 360.80 136.70 683.48

107e COMMON BACK FILL CM 24.98 69.12 5.60 24.93 124.63

108a FORMATION OF EMBANKMENT FROM ROADWAY CM 7.54 192.18 5.60 51.33 256.65
EXCAVATION IN COMMON MATERIAL

108bi FORMATION OF EMBANKMENT FROM ROADWAY CM 21.63 530.73 59.45 152.95 764.75
EXCAVATION IN HARD ROCK MATERIAL

108bii FORMATION OF EMBANKMENT FROM ROADWAY CM 16.22 458.38 2.66 119.32 596.58
EXCAVATION IN MEDIUM ROCK MATERIAL

108biii FORMATION OF EMBANKMENT FROM ROADWAY CM 14.42 406.28 - 105.17 525.87


EXCAVATION IN SOFT ROCK MATERIAL

108c FORMATION OF EMBANKMENT FROM BORROW CM 8.48 195.20 8.73 53.11 265.53
EXCAVATION IN COMMON MATERIAL

108d FORMATION OF EMBANKMENT FROM STRUCTURAL CM 6.82 83.95 5.60 24.09 120.46
EXCAVATION IN COMMON MATERIAL

108e FORMATION OF EMBANKMENT FROM STRUCTURAL CM 15.45 121.32 3.33 35.02 175.12
EXCAVATION IN ANY TYPE OF ROCK MATERIAL

109a SUB GRADE PREPARATION IN EARTH CUT SM 1.51 30.07 1.60 8.30 41.48

Page 187
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Swat
Swat Saidu
Saidu Sharif
Sharif District Code: 66

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

109bi SUB GRADE PREPARATION IN EXISTING ROAD WITHOUT SM 1.12 20.03 0.85 5.50 27.50
ANY FILL

110 IMPROVED SUB-GRADE CM 10.78 132.02 76.68 54.87 274.35

114a DRESSING OF BERM WITHOUT EXTRA MATERIAL SM 0.93 16.79 0.87 4.65 23.23

114b DRESSING OF BERM WITH EXTRA BORROW MATERIAL SM 1.38 17.13 0.99 4.87 24.37

201 GRANULAR SUB-BASE CM 8.36 272.91 599.30 220.14 1,100.72

202 AGGREGATE BASE CM 9.82 349.40 758.41 279.41 1,397.04

203a ASPHALTIC BASE COURSE PLANT MIX (CLASS "A") CM 70.60 1,615.88 6,556.04 2,060.63 10,303.14

203b ASPHALTIC BASE COURSE PLANT MIX (CLASS "B") CM 73.12 1,615.88 7,027.42 2,179.10 10,895.52

203c ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "A") CM 78.62 1,687.69 6,544.95 2,077.82 10,389.08

203d ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "B") CM 78.62 1,681.30 7,187.48 2,236.85 11,184.24

204b CEMENT STABILIZED BASE CM 29.62 608.94 1,051.97 422.63 2,113.17

204d LIQUID ASPHALT FOR CURING SEAL, TYPE MC-250 TON 251.48 979.45 58,400.85 14,907.95 74,539.73

204e EMULSIFIED ASPHALT FOR CURING SEAL, TYPE SS-1 TON 251.48 979.45 56,712.25 14,485.80 72,428.98

205a GRADED CRUSHED AGGREGATE CRACK-RELIEF LAYER CM 90.56 120.69 960.73 293.00 1,464.99

205b ASPHALTIC OPEN-GRADED PLANT MIX CRACK-RELIEF CM 148.13 2,608.60 6,188.36 2,236.27 11,181.36
LAYER

206b WATER BOUND MACADAM BASE WITH COARSE CM 98.84 135.11 797.29 257.81 1,289.06
AGGREGATE CLASS B

207a DEEP PATCHING (0-15 cm) SM 1.87 48.19 1.34 12.85 64.25

207b DEEP PATCHING (16-30 cm) SM 1.87 42.45 1.34 11.42 57.08

208 REINSTATEMENT OF ROAD SURFACE SM 1.96 61.10 0.60 15.91 79.57

209a BREAKING OF EXISTING ROAD PAVEMENT STRUCTURE CM 2.39 118.35 0.73 30.37 151.84

209b SCARIFICATION OF EXISTING ROAD PAVEMENT SM 0.48 23.67 0.15 6.07 30.37

302a CUT-BACK ASPHALT FOR BITUMINOUS PRIME COAT SM 0.31 1.68 41.45 10.86 54.30

302b EMULSIFIED ASPHALT FOR BITUMINOUS PRIME COAT SM 0.30 1.68 46.27 12.06 60.31

303a CUT-BACK ASPHALT FOR BITUMINOUS TACK COAT SM 0.12 0.62 17.35 4.52 22.61

303b EMULSIFIED ASPHALT FOR BITUMINOUS TACK COAT SM 0.12 0.62 20.24 5.25 26.23

304a SINGLE SURFACE TREATMENT SM 0.80 8.10 82.48 22.84 114.22

304b DOUBLE SURFACE TREATMENT SM 1.16 15.14 159.63 43.99 219.93

304c TRIPLE SURFACE TREATMENT SM 1.97 21.33 182.11 51.36 256.78

304d SEAL COAT SM 0.73 4.41 58.20 15.84 79.18

Page 188
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Swat
Swat Saidu
Saidu Sharif
Sharif District Code: 66

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

305a ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 67.12 1,593.58 7,718.04 2,344.68 11,723.42
"A")

305b ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 67.12 1,538.91 8,338.29 2,486.08 12,430.40
"B")

307a DENSE GRADED HOT BIT-MAC CM 164.78 406.36 6,424.00 1,748.78 8,743.92

307b OPEN GRADED HOT BIT-MAC CM 164.78 406.36 6,239.88 1,702.75 8,513.77

308a RECYCLING OF ASPHALT CONCRETE (0 - 60 mm THICK) CM 29.37 631.99 2,252.70 728.52 3,642.58

308b BITUMEN BINDER GRADE (40 - 50, 60 - 70, 80 - 100) TON 26.41 696.25 49,974.74 12,674.35 63,371.74

309a COLD MILLING, 0 - 30 mm SM 0.99 26.74 9.28 9.25 46.27

309b COLD MILLING, 0 - 50 mm SM 1.66 44.57 15.47 15.42 77.12

309c COLD MILLING, 0 - 70 mm SM 2.49 66.86 23.21 23.14 115.68

401a1i CONCRETE CLASS "A1" (Underground) CM 539.58 1,112.93 4,127.95 1,445.12 7,225.58

401a1ii CONCRETE CLASS "A1" (On ground) CM 539.58 1,112.93 4,419.29 1,517.95 7,589.76

401a1iii CONCRETE CLASS "A1" (Elevated) CM 539.58 1,112.93 5,001.99 1,663.62 8,318.12

401a2i CONCRETE CLASS "A2" (Underground) CM 539.58 1,112.93 4,524.85 1,544.34 7,721.70

401a2ii CONCRETE CLASS "A2" (On ground) CM 539.58 1,112.93 4,816.19 1,617.18 8,085.88

401a2iii CONCRETE CLASS "A2" (Elevated) CM 539.58 1,112.93 5,398.89 1,762.85 8,814.25

401a3i CONCRETE CLASS "A3" (Underground) CM 539.58 1,112.93 4,921.75 1,643.57 8,217.83

401a3ii CONCRETE CLASS "A3" (On ground) CM 539.58 1,112.93 5,213.09 1,716.40 8,582.01

401a3iii CONCRETE CLASS "A3" (Elevated) CM 539.58 1,112.93 5,795.79 1,862.07 9,310.37

401b CONCRETE CLASS "B" CM 691.62 846.23 3,319.03 1,214.22 6,071.09

401ci CONCRETE CLASS "C" (Underground) CM 526.36 525.57 3,657.00 1,177.23 5,886.16

401cii CONCRETE CLASS "C" (On ground) CM 526.36 525.57 3,781.25 1,208.30 6,041.48

401ciii CONCRETE CLASS "C" (Elevated) CM 526.36 525.57 4,029.77 1,270.43 6,352.13

401d CONCRETE CLASS "D1" CM 835.44 1,328.84 5,536.75 1,925.26 9,626.30

401e CONCRETE CLASS "Y" CM 1,143.33 525.57 4,954.55 1,655.86 8,279.32

401f LEAN CONCRETE CM 435.55 532.89 2,552.76 880.30 4,401.50

401gi(1) PRECAST CONCRETE CLASS "A-1" CM 1,744.25 994.51 5,177.22 1,978.99 9,894.97

401gi(3) PRECAST CONCRETE CLASS "A-3" CM 1,744.25 994.51 5,971.02 2,177.44 10,887.22

401gii PRECAST CONCRETE CLASS "B" CM 1,744.25 994.51 4,920.45 1,914.80 9,574.01

401giii(1) PRECAST CONCRETE CLASS "D1" CM 1,744.25 994.51 6,367.92 2,276.67 11,383.35

Page 189
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Swat
Swat Saidu
Saidu Sharif
Sharif District Code: 66

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

401giii(2) PRECAST CONCRETE CLASS "D2" CM 1,744.25 994.51 6,764.82 2,375.89 11,879.47

401giii(3) PRECAST CONCRETE CLASS "D3" CM 1,744.25 994.51 7,161.72 2,475.12 12,375.60

404a REINFORCEMENT AS PER AASHTO M. 31 GRADE 40 TON 1,636.04 820.55 63,884.10 16,585.17 82,925.86

404b REINFORCEMENT AS PER AASHTO M. 31 GRADE 60 TON 1,636.04 820.55 71,601.60 18,514.55 92,572.74

404h REINFORCEMENT (STRUCTURAL SHAPES) AS PER ASTM-A- TON 1,311.76 5,663.50 59,328.59 16,575.96 82,879.82
36

405a PRE-STRESSING WIRE STRAND 3/8" - 1/2" DIA COMPLETE IN TON 2,740.86 16,442.00 140,581.54 39,941.10 199,705.50
ALL RESPECT

405b LAUNCHING OF GIRDER TON 64.18 559.15 - 155.83 779.17

406a PREMOULDED JOINT FILLER 12 mm THICK WITH SM 115.17 - 323.26 109.61 548.04
BITUMASTIC JOINT SEAL

406b NEOPRENE RUBBER JOINT FILLER 12 mm THICK WITH SM 115.17 - 322.19 109.34 546.70
BITUMASTIC JOINT SEAL

406c STEEL EXPANSION JOINTS KG 9.38 27.72 95.96 33.26 166.32

406d WATER STOPS 6" SIZE M 103.07 - 496.64 149.93 749.64

406e ELASTOMERIC BEARING PADS (ACCORDING TO SIZE AND ccm 0.02 - 2.23 0.56 2.80
THICKNESS)

406f ASPHALT FELT (3 PLY) SM 41.43 - 3,212.12 813.39 4,066.93

406g STEEL OR METAL BEARING DEVICES KG 19.47 73.17 124.08 54.18 270.90

407d1 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 352.67 1,736.74 957.83 761.81 3,809.07
(BORING ONLY) IN NORMAL SOIL

407d2 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 529.01 2,605.12 1,436.75 1,142.72 5,713.60
(BORING ONLY) IN GRAVEL STRATA

407d3 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 529.01 2,605.12 1,067.14 1,050.32 5,251.58
ONLY) IN NORMAL SOIL

407d4 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 881.68 4,341.86 1,266.13 1,622.42 8,112.09
ONLY) IN GRAVEL STRATA

407d5 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 755.73 5,129.19 1,478.20 1,840.78 9,203.89
ONLY) IN NORMAL SOIL

407d6 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 1,322.52 7,255.27 1,610.94 2,547.18 12,735.92
ONLY) IN GRAVEL SOIL

407h PILE LOAD TEST UP TO 120 TON EACH 21,597.58 48,057.77 96,884.82 41,635.04 208,175.22

407i PILE LOAD TEST UP TO 240 TON EACH 39,798.12 48,057.77 193,769.65 70,406.38 352,031.92

407j PILE LOAD TEST UP TO 360 TON EACH 57,998.66 52,697.80 290,654.47 100,337.73 501,688.67

407k CONFIRMATORY BORING (NX SIZE) M 193.65 1,661.12 6.68 465.36 2,326.82

410 BRICK WORK CM 328.90 296.86 3,338.00 990.94 4,954.70

411a STONE MASONRY RANDOM DRY CM 285.65 113.36 469.03 217.01 1,085.05

411b STONE MASONRY RANDOM WITH MORTAR CM 307.77 175.02 1,566.42 512.30 2,561.50

411c STONE MASONRY DRESSED UNCOURSED DRY CM 370.33 113.36 524.50 252.05 1,260.23

411d STONE MASONRY DRESSED UNCOURSED WITH MORTAR CM 434.78 175.02 1,628.55 559.59 2,797.93

Page 190
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Swat
Swat Saidu
Saidu Sharif
Sharif District Code: 66

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

411g ROLL POINTING SM 69.82 12.33 46.26 32.10 160.52

412a STONE MASONRY DRESSED COURSED WITH MORTAR CM 582.02 277.29 1,529.00 597.08 2,985.39

501a R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 310 mm M 224.95 472.48 695.50 348.23 1,741.16

501b R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 380 mm M 218.15 623.36 901.66 435.79 2,178.97

501c R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 460 mm M 218.10 1,010.84 1,156.33 596.32 2,981.58

501d R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 610 mm M 226.64 1,238.10 1,727.12 797.97 3,989.83

501e R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 760 mm M 260.05 1,164.69 2,482.73 976.87 4,884.34

501f R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 910 mm M 321.85 1,437.80 3,905.21 1,416.22 7,081.08

501g R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1070 mm M 416.51 1,599.92 5,056.43 1,768.22 8,841.08

501h R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1220 mm M 489.52 1,942.76 6,443.67 2,218.99 11,094.93

501i R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1520 mm M 579.42 2,266.55 9,953.19 3,199.79 15,998.95

501j R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 310 mm M 224.95 547.92 781.13 388.50 1,942.50

501k R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 380 mm M 218.15 623.36 921.99 440.88 2,204.38

501l R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 460 mm M 211.72 1,010.84 1,128.87 587.86 2,939.29

501m R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 610 mm M 226.64 1,238.10 1,883.99 837.18 4,185.91

501n R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 760 mm M 260.05 1,164.69 3,582.47 1,251.80 6,259.00

501o R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 910 mm M 321.85 1,437.80 5,263.10 1,755.69 8,778.44

501p R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1070 mm M 416.51 1,599.92 7,355.13 2,342.89 11,714.46

501q R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1220 mm M 489.52 1,942.76 9,975.56 3,101.96 15,509.80

501r R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1520 mm M 579.42 2,266.55 14,034.36 4,220.08 21,100.41

502a GRANULAR MATERIAL IN BED TO CONCRETE PIPE CM 90.79 128.44 340.49 139.93 699.66
CULVERT

502b CONCRETE CLASS "B" IN BEDDING AND ENCASEMENT OF CM 811.63 661.98 3,791.86 1,316.37 6,581.84
CONCRETE PIPE CULVERT

507a STEEL WIRE MESH FOR GABIONS KG 5.37 - 120.04 31.35 156.75

507b ROCK FILL IN GABIONS CM 95.60 - 457.38 138.25 691.23

508a BRICK PAVING (SINGLE COURSE) SM 111.01 35.32 276.89 105.80 529.02

508b BRICK PAVING (DOUBLE COURSE) SM 198.11 35.32 550.72 196.04 980.18

509a RIP RAP CLASS "A" CM 482.85 - 380.04 215.72 1,078.61

509b RIP RAP CLASS "B" CM 464.28 - 377.00 210.32 1,051.60

509c RIP RAP CLASS "C" CM 467.06 - 380.04 211.77 1,058.87

Page 191
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Swat
Swat Saidu
Saidu Sharif
Sharif District Code: 66

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

509d GROUTED RIP RAP CLASS "A" CM 588.32 110.32 1,897.14 648.94 3,244.72

509e GROUTED RIP RAP CLASS "B" CM 566.85 88.25 1,736.52 597.90 2,989.52

509f GROUTED RIP RAP CLASS "C" CM 559.47 73.54 1,784.92 604.48 3,022.42

509g REINFORCED CONCRETE SLOPE PROTECTION (WITHOUT CM 817.55 381.27 4,403.91 1,400.68 7,003.41
REINFORCEMENT)

509h FILTER LAYER OF GRANULAR MATERIAL CM 47.88 207.33 354.56 152.44 762.21

510 DISMANTLING OF STRUCTURE AND OBSTRUCTIONS CM 108.17 421.95 - 132.53 662.65

511a1 DRY STONE PITCHING (15-20 cm Thick) SM 154.14 72.87 61.76 72.19 360.96

511a2 DRY STONE PITCHING (21-25 cm Thick) SM 197.29 93.28 79.05 92.40 462.02

511b1 GROUTED STONE PITCHING (15-20 cm Thick) SM 250.33 194.75 387.83 208.23 1,041.14

511b2 GROUTED STONE PITCHING (21-25 cm Thick) SM 312.91 243.44 484.79 260.28 1,301.42

601ai CONCRETE KERB IN PLACE NEW JERSY BARRIER FOR M 291.78 613.92 2,359.65 816.34 4,081.68
MEDIAN (DOUBLE FACE)

601di PRECAST REINFORCED CONCRETE KERB NEW JERSY M 976.66 711.97 4,353.63 1,510.56 7,552.81
BARRIER FOR MEDIAN (DOUBLE FACE)

601dii PRECAST KERB IN CONCRETE CLASS A-1 OF SIZE 450 X 150 MM M 141.70 97.09 456.08 173.72 868.59
INCLUDING CONCRETE BEDDING & HAUNCHING

603 BRICK EDGING M 8.52 - 42.11 12.66 63.28

604a METAL GUARD RAIL M 18.23 72.26 1,610.95 425.36 2,126.79

604b METAL GUARD RAIL END PIECES EACH 24.18 - 1,221.53 311.43 1,557.14

604d STEEL POST OF METAL GUARD RAIL EACH 85.49 996.27 3,851.83 1,233.40 6,166.98

605a CONCRETE BEAM GUARD RAIL M 69.70 31.44 606.30 176.86 884.30

605c CONCRETE POST FOR GUARD RAIL M 85.58 27.91 606.63 180.03 900.14

607a TRAFFIC ROAD SIGN CATEGORY 1 EACH 222.52 260.25 6,990.06 1,868.21 9,341.04

607b TRAFFIC ROAD SIGN CATEGORY 2 EACH 71.37 390.38 9,430.74 2,473.12 12,365.60

607c TRAFFIC ROAD SIGN CATEGORY 3 (a) EACH 222.52 552.72 12,104.56 3,219.95 16,099.76

607d TRAFFIC ROAD SIGN CATEGORY 3 (b) EACH 706.81 610.62 21,346.53 5,665.99 28,329.95

607e TRAFFIC ROAD SIGN CATEGORY 3 (c) SM 141.36 122.12 9,390.54 2,413.51 12,067.53

607f ADDITIONAL PANEL SIZE 60 X 30 cm EACH 275.09 - 1,329.94 401.26 2,006.29

607g ADDITIONAL PANEL SIZE 90 X 30 cm EACH 275.09 - 1,994.91 567.50 2,837.51

608b1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.78 5.98 16.49 6.31 31.56
LINES OF 15 cm WIDTH

608b2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.93 4.11 40.51 11.39 56.93
LINES OF 15 cm WIDTH

608c1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.78 5.98 22.00 7.69 38.45
LINES OF 20 cm WIDTH

Page 192
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Swat
Swat Saidu
Saidu Sharif
Sharif District Code: 66

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

608c2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.93 4.11 54.03 14.77 73.83
LINES OF 20 cm WIDTH

608d1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 72.11 5.32 159.35 59.19 295.97
4.0 M ARROWS

608d2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR 4.0 EACH 72.11 10.18 510.48 148.19 740.97
M ARROWS

608h1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.47 8.76 22.93 8.79 43.96
OF 15 cm WIDTH

608h2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.47 9.82 68.85 20.54 102.69
OF 15 cm WIDTH

608i1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.47 7.09 30.58 10.29 51.43
OF 20 cm WIDTH

608i2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.47 9.82 91.81 26.28 131.38
OF 20 cm WIDTH

608j1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR 4.0 M EACH 72.11 3.80 221.42 74.33 371.66
ARROWS

608j2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR 4.0 M EACH 72.11 8.06 868.22 237.10 1,185.48
ARROWS

608n1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 60.39 3.80 106.23 42.60 213.02
STOP

608n2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR EACH 60.39 8.06 340.84 102.32 511.60
STOP

608n3 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR STOP EACH 60.39 3.80 147.61 52.95 264.75

608n4 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR STOP EACH 60.39 8.06 579.69 162.03 810.17

609c REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 9.97 83.25 197.70 72.73 363.64
SINGLE)

609d REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 9.97 83.25 238.50 82.93 414.64
DOUBLE)

610b RIGHT OF WAY MARKER EACH 96.67 123.75 306.28 131.68 658.38

610c KILOMETRE POST (0.610 X 0.114 X 1.5 M) EACH 591.75 995.83 2,060.78 912.09 4,560.44

610d TEN KILOMETRE POST EACH 1,136.62 1,991.66 4,526.27 1,913.64 9,568.19

611a CHAIN LINK WIRE FABRIC FENCING 1500 MM HEIGHT M 133.38 95.67 984.00 303.26 1,516.32
WITH PRECAST PRESTRESSED R.C.C. POST

Page 193
.

Page 194
NATIONAL HIGHWAY AUTHORITY

COMPOSITE SCHEDULE OF RATES


January - 2009

SWABI
(66-A)

Shabir Associates
Quantity Surveying & Construction Cost Consultants

Page 195
.

Page 196
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Swabi
Swabi District Code: 66-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

101 CLEARING AND GRUBBING SM 0.69 10.10 - 2.70 13.49

102a REMOVAL OF TREES 150 - 300 mm GIRTH EACH 6.83 173.32 1.17 45.33 226.65

102b REMOVAL OF TREES 301 - 600 mm GIRTH EACH 19.75 456.54 2.63 119.73 598.65

102c REMOVAL OF TREES 601 mm OR OVER GIRTH EACH 79.01 1,826.16 10.51 478.92 2,394.60

103 STRIPPING CM 2.36 93.22 - 23.89 119.47

104 COMPACTION OF NATURAL GROUND SM 0.34 9.91 0.76 2.75 13.76

106a EXCAVATE UNSUITABLE COMMON MATERIAL CM 4.05 135.76 - 34.95 174.76

106bi EXCAVATE UNSUITABLE HARD ROCK MATERIAL CM 115.80 316.30 50.82 120.73 603.65

106bii EXCAVATE UNSUITABLE MEDIUM ROCK MATERIAL CM 15.83 337.99 - 88.46 442.28

106biii EXCAVATE UNSUITABLE SOFT ROCK MATERIAL CM 10.38 262.40 - 68.19 340.96

106c EXCAVATE SURPLUS COMMON MATERIAL CM 3.31 120.27 - 30.90 154.48

106di EXCAVATE SURPLUS HARD ROCK MATERIAL CM 115.80 316.30 50.82 120.73 603.65

106dii EXCAVATE SURPLUS MEDIUM ROCK MATERIAL CM 18.42 316.03 - 83.61 418.07

106diii EXCAVATE SURPLUS SOFT ROCK MATERIAL CM 7.97 263.92 - 67.97 339.86

107a STRUCTURAL EXCAVATION IN COMMON MATERIAL CM 6.56 137.60 0.38 36.13 180.67

107b STRUCTURAL EXCAVATION IN COMMON MATERIAL BELOW CM 59.39 287.11 70.80 104.33 521.64
WATER LEVEL

107ci STRUCTURAL EXCAVATION IN HARD ROCK MATERIAL CM 102.35 427.01 33.88 140.81 704.06

107cii STRUCTURAL EXCAVATION IN MEDIUM ROCK MATERIAL CM 86.54 292.53 - 94.77 473.84

107ciii STRUCTURAL EXCAVATION IN SOFT ROCK MATERIAL CM 52.64 238.86 - 72.88 364.38

107d GRANULAR BACK FILL CM 32.30 137.14 348.31 129.44 647.19

107e COMMON BACK FILL CM 24.41 62.84 5.09 23.08 115.42

108a FORMATION OF EMBANKMENT FROM ROADWAY CM 6.24 174.71 5.09 46.51 232.54
EXCAVATION IN COMMON MATERIAL

108bi FORMATION OF EMBANKMENT FROM ROADWAY CM 18.59 482.48 54.04 138.78 693.89
EXCAVATION IN HARD ROCK MATERIAL

108bii FORMATION OF EMBANKMENT FROM ROADWAY CM 13.94 416.71 2.42 108.27 541.34
EXCAVATION IN MEDIUM ROCK MATERIAL

108biii FORMATION OF EMBANKMENT FROM ROADWAY CM 12.39 369.34 - 95.43 477.17


EXCAVATION IN SOFT ROCK MATERIAL

108c FORMATION OF EMBANKMENT FROM BORROW CM 7.21 177.46 7.94 48.15 240.76
EXCAVATION IN COMMON MATERIAL

108d FORMATION OF EMBANKMENT FROM STRUCTURAL CM 5.64 76.32 5.09 21.76 108.81
EXCAVATION IN COMMON MATERIAL

108e FORMATION OF EMBANKMENT FROM STRUCTURAL CM 13.35 110.29 3.03 31.67 158.33
EXCAVATION IN ANY TYPE OF ROCK MATERIAL

109a SUB GRADE PREPARATION IN EARTH CUT SM 1.27 27.34 1.46 7.52 37.58

Page 197
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Swabi
Swabi District Code: 66-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

109bi SUB GRADE PREPARATION IN EXISTING ROAD WITHOUT SM 0.92 18.21 0.77 4.98 24.88
ANY FILL

110 IMPROVED SUB-GRADE CM 9.08 120.02 57.78 46.72 233.59

114a DRESSING OF BERM WITHOUT EXTRA MATERIAL SM 0.79 15.26 0.79 4.21 21.05

114b DRESSING OF BERM WITH EXTRA BORROW MATERIAL SM 1.14 15.57 0.90 4.40 22.01

201 GRANULAR SUB-BASE CM 7.29 255.06 527.63 197.49 987.47

202 AGGREGATE BASE CM 8.35 326.54 765.72 275.15 1,375.77

203a ASPHALTIC BASE COURSE PLANT MIX (CLASS "A") CM 67.93 1,510.17 5,778.04 1,839.04 9,195.18

203b ASPHALTIC BASE COURSE PLANT MIX (CLASS "B") CM 70.07 1,510.17 6,174.12 1,938.59 9,692.94

203c ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "A") CM 75.10 1,577.28 5,768.48 1,855.22 9,276.08

203d ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "B") CM 75.10 1,571.31 6,316.97 1,990.85 9,954.23

204b CEMENT STABILIZED BASE CM 25.85 569.10 979.23 393.55 1,967.73

204d LIQUID ASPHALT FOR CURING SEAL, TYPE MC-250 TON 226.34 915.38 50,544.27 12,921.50 64,607.49

204e EMULSIFIED ASPHALT FOR CURING SEAL, TYPE SS-1 TON 226.34 915.38 48,966.14 12,526.97 62,634.83

205a GRADED CRUSHED AGGREGATE CRACK-RELIEF LAYER CM 91.45 112.80 877.87 270.53 1,352.66

205b ASPHALTIC OPEN-GRADED PLANT MIX CRACK-RELIEF CM 136.49 2,437.94 5,491.01 2,016.36 10,081.81
LAYER

206b WATER BOUND MACADAM BASE WITH COARSE CM 101.09 126.27 749.01 244.09 1,220.46
AGGREGATE CLASS B

207a DEEP PATCHING (0-15 cm) SM 1.59 45.04 1.26 11.97 59.85

207b DEEP PATCHING (16-30 cm) SM 1.59 39.67 1.26 10.63 53.15

208 REINSTATEMENT OF ROAD SURFACE SM 1.66 57.10 0.56 14.83 74.16

209a BREAKING OF EXISTING ROAD PAVEMENT STRUCTURE CM 1.95 110.61 0.68 28.31 141.55

209b SCARIFICATION OF EXISTING ROAD PAVEMENT SM 0.39 22.12 0.14 5.66 28.31

302a CUT-BACK ASPHALT FOR BITUMINOUS PRIME COAT SM 0.27 1.57 35.87 9.43 47.15

302b EMULSIFIED ASPHALT FOR BITUMINOUS PRIME COAT SM 0.26 1.57 40.04 10.47 52.35

303a CUT-BACK ASPHALT FOR BITUMINOUS TACK COAT SM 0.11 0.58 15.01 3.93 19.63

303b EMULSIFIED ASPHALT FOR BITUMINOUS TACK COAT SM 0.11 0.58 17.52 4.55 22.75

304a SINGLE SURFACE TREATMENT SM 0.70 7.57 71.00 19.82 99.09

304b DOUBLE SURFACE TREATMENT SM 1.02 14.15 137.28 38.11 190.57

304c TRIPLE SURFACE TREATMENT SM 1.72 19.94 156.59 44.56 222.81

304d SEAL COAT SM 0.65 4.12 50.41 13.80 68.98

Page 198
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Swabi
Swabi District Code: 66-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

305a ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 63.13 1,489.33 6,765.75 2,079.55 10,397.76
"A")

305b ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 63.13 1,438.23 7,297.74 2,199.78 10,998.88
"B")

307a DENSE GRADED HOT BIT-MAC CM 153.74 379.77 5,576.99 1,527.63 7,638.13

307b OPEN GRADED HOT BIT-MAC CM 153.74 379.77 5,417.72 1,487.81 7,439.03

308a RECYCLING OF ASPHALT CONCRETE (0 - 60 mm THICK) CM 25.54 590.65 2,005.61 655.45 3,277.24

308b BITUMEN BINDER GRADE (40 - 50, 60 - 70, 80 - 100) TON 24.55 650.70 42,549.52 10,806.19 54,030.96

309a COLD MILLING, 0 - 30 mm SM 0.86 24.99 8.68 8.63 43.17

309b COLD MILLING, 0 - 50 mm SM 1.44 41.65 14.46 14.39 71.94

309c COLD MILLING, 0 - 70 mm SM 2.16 62.48 21.69 21.58 107.91

401a1i CONCRETE CLASS "A1" (Underground) CM 489.47 1,059.94 3,906.42 1,363.96 6,819.78

401a1ii CONCRETE CLASS "A1" (On ground) CM 489.47 1,059.94 4,183.89 1,433.33 7,166.63

401a1iii CONCRETE CLASS "A1" (Elevated) CM 489.47 1,059.94 4,738.84 1,572.06 7,860.31

401a2i CONCRETE CLASS "A2" (Underground) CM 489.47 1,059.94 4,284.42 1,458.46 7,292.28

401a2ii CONCRETE CLASS "A2" (On ground) CM 489.47 1,059.94 4,561.89 1,527.83 7,639.13

401a2iii CONCRETE CLASS "A2" (Elevated) CM 489.47 1,059.94 5,116.84 1,666.56 8,332.81

401a3i CONCRETE CLASS "A3" (Underground) CM 489.47 1,059.94 4,662.42 1,552.96 7,764.78

401a3ii CONCRETE CLASS "A3" (On ground) CM 489.47 1,059.94 4,939.89 1,622.33 8,111.63

401a3iii CONCRETE CLASS "A3" (Elevated) CM 489.47 1,059.94 5,494.84 1,761.06 8,805.31

401b CONCRETE CLASS "B" CM 635.43 805.93 3,121.10 1,140.62 5,703.08

401ci CONCRETE CLASS "C" (Underground) CM 490.97 500.55 3,447.73 1,109.81 5,549.07

401cii CONCRETE CLASS "C" (On ground) CM 490.97 500.55 3,566.07 1,139.40 5,696.99

401ciii CONCRETE CLASS "C" (Elevated) CM 490.97 500.55 3,802.76 1,198.57 5,992.85

401d CONCRETE CLASS "D1" CM 767.27 1,265.57 5,248.73 1,820.39 9,101.96

401e CONCRETE CLASS "Y" CM 1,091.04 500.55 4,700.16 1,572.94 7,864.68

401f LEAN CONCRETE CM 422.79 507.52 2,391.41 830.43 4,152.15

401gi(1) PRECAST CONCRETE CLASS "A-1" CM 1,696.86 947.15 4,904.66 1,887.17 9,435.84

401gi(3) PRECAST CONCRETE CLASS "A-3" CM 1,696.86 947.15 5,660.66 2,076.17 10,380.84

401gii PRECAST CONCRETE CLASS "B" CM 1,696.86 947.15 4,644.46 1,822.12 9,110.59

401giii(1) PRECAST CONCRETE CLASS "D1" CM 1,696.86 947.15 6,038.66 2,170.67 10,853.34

Page 199
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Swabi
Swabi District Code: 66-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

401giii(2) PRECAST CONCRETE CLASS "D2" CM 1,696.86 947.15 6,416.66 2,265.17 11,325.84

401giii(3) PRECAST CONCRETE CLASS "D3" CM 1,696.86 947.15 6,794.66 2,359.67 11,798.34

404a REINFORCEMENT AS PER AASHTO M. 31 GRADE 40 TON 1,485.94 781.47 59,888.00 15,538.85 77,694.27

404b REINFORCEMENT AS PER AASHTO M. 31 GRADE 60 TON 1,485.94 781.47 67,238.00 17,376.35 86,881.77

404h REINFORCEMENT (STRUCTURAL SHAPES) AS PER ASTM-A- TON 1,194.94 5,393.81 56,028.38 15,654.28 78,271.42
36

405a PRE-STRESSING WIRE STRAND 3/8" - 1/2" DIA COMPLETE IN TON 2,485.02 15,659.05 133,861.53 38,001.40 190,007.00
ALL RESPECT

405b LAUNCHING OF GIRDER TON 58.52 532.52 - 147.76 738.80

406a PREMOULDED JOINT FILLER 12 mm THICK WITH SM 108.69 - 301.89 102.65 513.23
BITUMASTIC JOINT SEAL

406b NEOPRENE RUBBER JOINT FILLER 12 mm THICK WITH SM 108.69 - 300.97 102.41 512.07
BITUMASTIC JOINT SEAL

406c STEEL EXPANSION JOINTS KG 9.01 26.40 90.90 31.58 157.89

406d WATER STOPS 6" SIZE M 88.89 - 472.62 140.38 701.88

406e ELASTOMERIC BEARING PADS (ACCORDING TO SIZE AND ccm 0.02 - 2.12 0.53 2.67
THICKNESS)

406f ASPHALT FELT (3 PLY) SM 42.16 - 2,960.92 750.77 3,753.85

406g STEEL OR METAL BEARING DEVICES KG 19.35 69.68 117.72 51.69 258.45

407d1 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 320.97 1,654.04 815.01 697.51 3,487.53
(BORING ONLY) IN NORMAL SOIL

407d2 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 481.45 2,481.06 1,222.52 1,046.26 5,231.30
(BORING ONLY) IN GRAVEL STRATA

407d3 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 481.45 2,481.06 916.20 969.68 4,848.39
ONLY) IN NORMAL SOIL

407d4 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 802.42 4,135.11 1,099.96 1,509.37 7,546.86
ONLY) IN GRAVEL STRATA

407d5 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 687.79 4,884.94 1,292.09 1,716.21 8,581.03
ONLY) IN NORMAL SOIL

407d6 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 1,203.63 6,909.78 1,409.73 2,380.79 11,903.93
ONLY) IN GRAVEL SOIL

407h PILE LOAD TEST UP TO 120 TON EACH 22,611.50 45,769.30 92,271.26 40,163.02 200,815.08

407i PILE LOAD TEST UP TO 240 TON EACH 42,307.39 45,769.30 184,542.52 68,154.80 340,774.01

407j PILE LOAD TEST UP TO 360 TON EACH 62,003.27 50,188.38 276,813.78 97,251.36 486,256.80

407k CONFIRMATORY BORING (NX SIZE) M 190.29 1,582.02 6.37 444.67 2,223.35

410 BRICK WORK CM 342.65 282.72 3,189.01 953.60 4,767.98

411a STONE MASONRY RANDOM DRY CM 285.39 107.96 628.81 255.54 1,277.69

411b STONE MASONRY RANDOM WITH MORTAR CM 308.64 166.68 1,655.14 532.62 2,663.08

411c STONE MASONRY DRESSED UNCOURSED DRY CM 375.66 107.96 696.80 295.10 1,475.52

411d STONE MASONRY DRESSED UNCOURSED WITH MORTAR CM 444.05 166.68 1,734.18 586.23 2,931.13

Page 200
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Swabi
Swabi District Code: 66-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

411g ROLL POINTING SM 73.88 11.74 43.75 32.34 161.72

412a STONE MASONRY DRESSED COURSED WITH MORTAR CM 601.35 264.08 1,639.37 626.20 3,131.00

501a R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 310 mm M 224.62 437.48 643.39 326.37 1,631.87

501b R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 380 mm M 219.04 577.19 834.17 407.60 2,037.99

501c R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 460 mm M 211.49 935.96 1,069.85 554.33 2,771.63

501d R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 610 mm M 222.11 1,146.39 1,598.23 741.68 3,708.41

501e R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 760 mm M 254.21 1,078.41 2,297.87 907.62 4,538.11

501f R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 910 mm M 314.06 1,331.30 3,614.54 1,314.98 6,574.88

501g R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1070 mm M 406.44 1,481.41 4,680.50 1,642.09 8,210.43

501h R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1220 mm M 476.92 1,798.85 5,964.68 2,060.11 10,300.57

501i R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1520 mm M 568.40 2,098.66 9,213.95 2,970.25 14,851.27

501j R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 310 mm M 224.62 507.33 722.10 363.51 1,817.56

501k R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 380 mm M 219.04 577.19 852.99 412.30 2,061.52

501l R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 460 mm M 207.06 935.96 1,044.43 546.86 2,734.32

501m R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 610 mm M 222.11 1,146.39 1,743.69 778.05 3,890.23

501n R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 760 mm M 254.21 1,078.41 3,316.03 1,162.16 5,810.82

501o R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 910 mm M 314.06 1,331.30 4,871.85 1,629.30 8,146.52

501p R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1070 mm M 406.44 1,481.41 6,808.93 2,174.19 10,870.96

501q R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1220 mm M 476.92 1,798.85 9,234.95 2,877.68 14,388.41

501r R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1520 mm M 568.40 2,098.66 12,992.82 3,914.97 19,574.84

502a GRANULAR MATERIAL IN BED TO CONCRETE PIPE CM 86.90 118.93 315.27 130.27 651.36
CULVERT

502b CONCRETE CLASS "B" IN BEDDING AND ENCASEMENT OF CM 712.01 612.95 3,471.10 1,199.01 5,995.06
CONCRETE PIPE CULVERT

507a STEEL WIRE MESH FOR GABIONS KG 5.18 - 109.50 28.67 143.35

507b ROCK FILL IN GABIONS CM 94.05 - 352.92 111.74 558.71

508a BRICK PAVING (SINGLE COURSE) SM 112.10 32.70 259.21 101.00 505.01

508b BRICK PAVING (DOUBLE COURSE) SM 202.38 32.70 515.58 187.66 938.32

509a RIP RAP CLASS "A" CM 489.74 - 534.00 255.93 1,279.67

509b RIP RAP CLASS "B" CM 472.76 - 529.73 250.62 1,253.11

509c RIP RAP CLASS "C" CM 476.95 - 534.00 252.74 1,263.68

Page 201
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Swabi
Swabi District Code: 66-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

509d GROUTED RIP RAP CLASS "A" CM 597.66 102.14 1,926.98 656.70 3,283.48

509e GROUTED RIP RAP CLASS "B" CM 577.71 81.72 1,778.01 609.36 3,046.80

509f GROUTED RIP RAP CLASS "C" CM 571.70 68.10 1,823.85 615.91 3,079.56

509g REINFORCED CONCRETE SLOPE PROTECTION (WITHOUT CM 774.65 353.02 4,039.99 1,291.92 6,459.59
REINFORCEMENT)

509h FILTER LAYER OF GRANULAR MATERIAL CM 46.27 191.97 348.49 146.68 733.42

510 DISMANTLING OF STRUCTURE AND OBSTRUCTIONS CM 102.55 390.69 - 123.31 616.55

511a1 DRY STONE PITCHING (15-20 cm Thick) SM 152.15 67.48 86.78 76.60 383.00

511a2 DRY STONE PITCHING (21-25 cm Thick) SM 194.75 86.37 111.07 98.05 490.24

511b1 GROUTED STONE PITCHING (15-20 cm Thick) SM 249.46 180.32 372.92 200.68 1,003.38

511b2 GROUTED STONE PITCHING (21-25 cm Thick) SM 311.83 225.40 466.15 250.84 1,254.22

601ai CONCRETE KERB IN PLACE NEW JERSY BARRIER FOR M 259.57 572.25 2,189.96 755.45 3,777.23
MEDIAN (DOUBLE FACE)

601di PRECAST REINFORCED CONCRETE KERB NEW JERSY M 931.32 670.54 4,035.66 1,409.38 7,046.89
BARRIER FOR MEDIAN (DOUBLE FACE)

601dii PRECAST KERB IN CONCRETE CLASS A-1 OF SIZE 450 X 150 MM M 135.38 90.27 423.54 162.30 811.48
INCLUDING CONCRETE BEDDING & HAUNCHING

603 BRICK EDGING M 8.75 - 41.76 12.63 63.14

604a METAL GUARD RAIL M 17.41 70.84 1,579.36 416.90 2,084.52

604b METAL GUARD RAIL END PIECES EACH 23.81 - 1,197.58 305.35 1,526.74

604d STEEL POST OF METAL GUARD RAIL EACH 80.29 976.73 3,776.31 1,208.33 6,041.66

605a CONCRETE BEAM GUARD RAIL M 73.86 30.82 589.31 173.50 867.50

605c CONCRETE POST FOR GUARD RAIL M 90.69 27.36 589.04 176.77 883.87

607a TRAFFIC ROAD SIGN CATEGORY 1 EACH 230.86 255.15 6,846.99 1,833.25 9,166.25

607b TRAFFIC ROAD SIGN CATEGORY 2 EACH 67.23 382.72 9,233.84 2,420.95 12,104.75

607c TRAFFIC ROAD SIGN CATEGORY 3 (a) EACH 230.86 541.89 11,846.66 3,154.85 15,774.25

607d TRAFFIC ROAD SIGN CATEGORY 3 (b) EACH 760.60 598.64 20,895.12 5,563.59 27,817.96

607e TRAFFIC ROAD SIGN CATEGORY 3 (c) SM 152.12 119.73 9,196.07 2,366.98 11,834.90

607f ADDITIONAL PANEL SIZE 60 X 30 cm EACH 271.93 - 1,302.95 393.72 1,968.60

607g ADDITIONAL PANEL SIZE 90 X 30 cm EACH 271.93 - 1,954.43 556.59 2,782.95

608b1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.59 5.86 16.16 6.15 30.76
LINES OF 15 cm WIDTH

608b2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.86 4.03 39.65 11.14 55.68
LINES OF 15 cm WIDTH

608c1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 2.59 5.86 21.56 7.50 37.51
LINES OF 20 cm WIDTH

Page 202
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Swabi
Swabi District Code: 66-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

608c2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 0.86 4.03 52.89 14.44 72.22
LINES OF 20 cm WIDTH

608d1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 74.48 5.22 156.16 58.96 294.81
4.0 M ARROWS

608d2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR 4.0 EACH 74.48 9.98 499.68 146.03 730.17
M ARROWS

608h1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.23 8.59 22.48 8.57 42.87
OF 15 cm WIDTH

608h2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.23 9.63 67.50 20.09 100.46
OF 15 cm WIDTH

608i1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.23 6.95 29.97 10.04 50.19
OF 20 cm WIDTH

608i2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.23 9.63 90.01 25.72 128.59
OF 20 cm WIDTH

608j1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR 4.0 M EACH 74.48 3.73 217.02 73.80 369.02
ARROWS

608j2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR 4.0 M EACH 74.48 7.90 851.20 233.39 1,166.97
ARROWS

608n1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 61.79 3.73 104.11 42.41 212.03
STOP

608n2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR EACH 61.79 7.90 333.62 100.83 504.14
STOP

608n3 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR STOP EACH 61.79 3.73 144.68 52.55 262.75

608n4 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR STOP EACH 61.79 7.90 568.32 159.50 797.52

609c REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 8.69 81.62 193.80 71.03 355.14
SINGLE)

609d REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 8.69 81.62 233.80 81.03 405.13
DOUBLE)

610b RIGHT OF WAY MARKER EACH 101.91 121.33 298.33 130.39 651.96

610c KILOMETRE POST (0.610 X 0.114 X 1.5 M) EACH 632.56 976.31 1,999.97 902.21 4,511.04

610d TEN KILOMETRE POST EACH 1,214.38 1,952.61 4,397.63 1,891.15 9,455.77

611a CHAIN LINK WIRE FABRIC FENCING 1500 MM HEIGHT M 127.74 91.00 948.31 291.76 1,458.81
WITH PRECAST PRESTRESSED R.C.C. POST

Page 203
.

Page 204
NATIONAL HIGHWAY AUTHORITY

COMPOSITE SCHEDULE OF RATES


January - 2009

TANK
(70-A)

Shabir Associates
Quantity Surveying & Construction Cost Consultants

Page 205
.

Page 206
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Tank
Tank District Code: 70-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

101 CLEARING AND GRUBBING SM 0.81 10.10 - 2.73 13.64

102a REMOVAL OF TREES 150 - 300 mm GIRTH EACH 8.02 173.32 1.17 45.63 228.13

102b REMOVAL OF TREES 301 - 600 mm GIRTH EACH 23.27 456.54 2.63 120.61 603.04

102c REMOVAL OF TREES 601 mm OR OVER GIRTH EACH 93.07 1,826.16 10.51 482.44 2,412.18

103 STRIPPING CM 2.74 93.22 - 23.99 119.95

104 COMPACTION OF NATURAL GROUND SM 0.39 9.91 0.76 2.76 13.82

106a EXCAVATE UNSUITABLE COMMON MATERIAL CM 4.53 135.76 - 35.07 175.35

106bi EXCAVATE UNSUITABLE HARD ROCK MATERIAL CM 131.49 316.30 50.82 124.65 623.27

106bii EXCAVATE UNSUITABLE MEDIUM ROCK MATERIAL CM 18.24 337.99 - 89.06 445.29

106biii EXCAVATE UNSUITABLE SOFT ROCK MATERIAL CM 11.82 262.40 - 68.55 342.77

106c EXCAVATE SURPLUS COMMON MATERIAL CM 3.70 120.27 - 30.99 154.97

106di EXCAVATE SURPLUS HARD ROCK MATERIAL CM 131.49 316.30 50.82 124.65 623.27

106dii EXCAVATE SURPLUS MEDIUM ROCK MATERIAL CM 20.88 316.03 - 84.23 421.14

106diii EXCAVATE SURPLUS SOFT ROCK MATERIAL CM 9.18 263.92 - 68.27 341.37

107a STRUCTURAL EXCAVATION IN COMMON MATERIAL CM 7.42 137.60 0.38 36.35 181.75

107b STRUCTURAL EXCAVATION IN COMMON MATERIAL BELOW CM 67.61 287.11 70.80 106.38 531.91
WATER LEVEL

107ci STRUCTURAL EXCAVATION IN HARD ROCK MATERIAL CM 116.01 427.01 33.88 144.23 721.13

107cii STRUCTURAL EXCAVATION IN MEDIUM ROCK MATERIAL CM 98.27 292.53 - 97.70 488.51

107ciii STRUCTURAL EXCAVATION IN SOFT ROCK MATERIAL CM 59.66 238.86 - 74.63 373.16

107d GRANULAR BACK FILL CM 37.16 137.14 348.64 130.74 653.68

107e COMMON BACK FILL CM 28.66 62.84 5.09 24.15 120.74

108a FORMATION OF EMBANKMENT FROM ROADWAY CM 7.14 174.71 5.09 46.73 233.67
EXCAVATION IN COMMON MATERIAL

108bi FORMATION OF EMBANKMENT FROM ROADWAY CM 21.41 482.48 54.04 139.48 697.41
EXCAVATION IN HARD ROCK MATERIAL

108bii FORMATION OF EMBANKMENT FROM ROADWAY CM 16.06 416.71 2.42 108.80 543.98
EXCAVATION IN MEDIUM ROCK MATERIAL

108biii FORMATION OF EMBANKMENT FROM ROADWAY CM 14.27 369.34 - 95.90 479.52


EXCAVATION IN SOFT ROCK MATERIAL

108c FORMATION OF EMBANKMENT FROM BORROW CM 8.30 177.46 7.94 48.42 242.12
EXCAVATION IN COMMON MATERIAL

108d FORMATION OF EMBANKMENT FROM STRUCTURAL CM 6.48 76.32 5.09 21.97 109.86
EXCAVATION IN COMMON MATERIAL

108e FORMATION OF EMBANKMENT FROM STRUCTURAL CM 15.46 110.29 3.03 32.19 160.97
EXCAVATION IN ANY TYPE OF ROCK MATERIAL

109a SUB GRADE PREPARATION IN EARTH CUT SM 1.46 27.34 1.46 7.56 37.81

Page 207
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Tank
Tank District Code: 70-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

109bi SUB GRADE PREPARATION IN EXISTING ROAD WITHOUT SM 1.05 18.21 0.77 5.01 25.04
ANY FILL

110 IMPROVED SUB-GRADE CM 10.60 120.02 54.09 46.18 230.90

114a DRESSING OF BERM WITHOUT EXTRA MATERIAL SM 0.91 15.26 0.79 4.24 21.21

114b DRESSING OF BERM WITH EXTRA BORROW MATERIAL SM 1.33 15.57 0.90 4.45 22.24

201 GRANULAR SUB-BASE CM 8.36 255.06 564.15 206.89 1,034.47

202 AGGREGATE BASE CM 9.66 326.54 739.55 268.94 1,344.70

203a ASPHALTIC BASE COURSE PLANT MIX (CLASS "A") CM 79.77 1,510.17 6,311.32 1,975.31 9,876.57

203b ASPHALTIC BASE COURSE PLANT MIX (CLASS "B") CM 82.13 1,510.17 6,759.22 2,087.88 10,439.39

203c ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "A") CM 87.67 1,577.28 6,300.90 1,991.46 9,957.32

203d ASPHALTIC LEVELLING COURSE PLANT MIX (CLASS "B") CM 87.67 1,571.31 6,910.49 2,142.37 10,711.83

204b CEMENT STABILIZED BASE CM 30.03 569.10 1,076.33 418.87 2,094.33

204d LIQUID ASPHALT FOR CURING SEAL, TYPE MC-250 TON 252.16 915.38 55,731.63 14,224.79 71,123.96

204e EMULSIFIED ASPHALT FOR CURING SEAL, TYPE SS-1 TON 252.16 915.38 54,153.50 13,830.26 69,151.30

205a GRADED CRUSHED AGGREGATE CRACK-RELIEF LAYER CM 108.26 112.80 968.33 297.35 1,486.73

205b ASPHALTIC OPEN-GRADED PLANT MIX CRACK-RELIEF CM 159.20 2,437.94 5,949.21 2,136.59 10,682.94
LAYER

206b WATER BOUND MACADAM BASE WITH COARSE CM 119.69 126.27 716.25 240.55 1,202.77
AGGREGATE CLASS B

207a DEEP PATCHING (0-15 cm) SM 1.83 45.04 1.26 12.03 60.15

207b DEEP PATCHING (16-30 cm) SM 1.83 39.67 1.26 10.69 53.45

208 REINSTATEMENT OF ROAD SURFACE SM 1.94 57.10 0.56 14.90 74.51

209a BREAKING OF EXISTING ROAD PAVEMENT STRUCTURE CM 2.17 110.61 0.68 28.37 141.83

209b SCARIFICATION OF EXISTING ROAD PAVEMENT SM 0.43 22.12 0.14 5.67 28.37

302a CUT-BACK ASPHALT FOR BITUMINOUS PRIME COAT SM 0.31 1.57 39.55 10.36 51.80

302b EMULSIFIED ASPHALT FOR BITUMINOUS PRIME COAT SM 0.30 1.57 44.15 11.51 57.53

303a CUT-BACK ASPHALT FOR BITUMINOUS TACK COAT SM 0.12 0.58 16.55 4.31 21.57

303b EMULSIFIED ASPHALT FOR BITUMINOUS TACK COAT SM 0.12 0.58 19.31 5.00 25.02

304a SINGLE SURFACE TREATMENT SM 0.80 7.57 79.17 21.89 109.43

304b DOUBLE SURFACE TREATMENT SM 1.16 14.15 153.59 42.23 211.13

304c TRIPLE SURFACE TREATMENT SM 1.94 19.94 175.27 49.29 246.44

304d SEAL COAT SM 0.74 4.12 55.73 15.15 75.74

Page 208
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Tank
Tank District Code: 70-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

305a ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 73.82 1,489.33 7,424.24 2,246.85 11,234.24
"A")

305b ASPHALTIC CONCRETE FOR WEARING COURSE (CLASS CM 73.82 1,438.23 8,021.83 2,383.47 11,917.34
"B")

307a DENSE GRADED HOT BIT-MAC CM 183.61 379.77 6,203.46 1,691.71 8,458.56

307b OPEN GRADED HOT BIT-MAC CM 183.61 379.77 6,023.39 1,646.69 8,233.47

308a RECYCLING OF ASPHALT CONCRETE (0 - 60 mm THICK) CM 31.25 590.65 2,146.11 692.00 3,460.01

308b BITUMEN BINDER GRADE (40 - 50, 60 - 70, 80 - 100) TON 28.14 650.70 47,890.96 12,142.45 60,712.24

309a COLD MILLING, 0 - 30 mm SM 1.00 24.99 8.68 8.67 43.34

309b COLD MILLING, 0 - 50 mm SM 1.67 41.65 14.46 14.45 72.23

309c COLD MILLING, 0 - 70 mm SM 2.51 62.48 21.69 21.67 108.35

401a1i CONCRETE CLASS "A1" (Underground) CM 563.03 1,059.94 3,990.87 1,403.46 7,017.30

401a1ii CONCRETE CLASS "A1" (On ground) CM 563.03 1,059.94 4,268.34 1,472.83 7,364.14

401a1iii CONCRETE CLASS "A1" (Elevated) CM 563.03 1,059.94 4,823.29 1,611.56 8,057.82

401a2i CONCRETE CLASS "A2" (Underground) CM 563.03 1,059.94 4,368.87 1,497.96 7,489.80

401a2ii CONCRETE CLASS "A2" (On ground) CM 563.03 1,059.94 4,646.34 1,567.33 7,836.64

401a2iii CONCRETE CLASS "A2" (Elevated) CM 563.03 1,059.94 5,201.29 1,706.06 8,530.32

401a3i CONCRETE CLASS "A3" (Underground) CM 563.03 1,059.94 4,746.87 1,592.46 7,962.30

401a3ii CONCRETE CLASS "A3" (On ground) CM 563.03 1,059.94 5,024.34 1,661.83 8,309.14

401a3iii CONCRETE CLASS "A3" (Elevated) CM 563.03 1,059.94 5,579.29 1,800.56 9,002.82

401b CONCRETE CLASS "B" CM 726.57 805.93 3,220.55 1,188.26 5,941.31

401ci CONCRETE CLASS "C" (Underground) CM 562.20 500.55 3,553.89 1,154.16 5,770.80

401cii CONCRETE CLASS "C" (On ground) CM 562.20 500.55 3,672.24 1,183.75 5,918.73

401ciii CONCRETE CLASS "C" (Elevated) CM 562.20 500.55 3,908.92 1,242.92 6,214.59

401d CONCRETE CLASS "D1" CM 887.96 1,265.57 5,327.23 1,870.19 9,350.94

401e CONCRETE CLASS "Y" CM 1,247.79 500.55 4,774.73 1,630.77 8,153.84

401f LEAN CONCRETE CM 491.67 507.52 2,490.72 872.48 4,362.38

401gi(1) PRECAST CONCRETE CLASS "A-1" CM 1,925.20 947.15 4,996.03 1,967.10 9,835.48

401gi(3) PRECAST CONCRETE CLASS "A-3" CM 1,925.20 947.15 5,752.03 2,156.10 10,780.48

401gii PRECAST CONCRETE CLASS "B" CM 1,925.20 947.15 4,751.80 1,906.04 9,530.20

401giii(1) PRECAST CONCRETE CLASS "D1" CM 1,925.20 947.15 6,130.03 2,250.60 11,252.98

Page 209
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Tank
Tank District Code: 70-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

401giii(2) PRECAST CONCRETE CLASS "D2" CM 1,925.20 947.15 6,508.03 2,345.10 11,725.48

401giii(3) PRECAST CONCRETE CLASS "D3" CM 1,925.20 947.15 6,886.03 2,439.60 12,197.98

404a REINFORCEMENT AS PER AASHTO M. 31 GRADE 40 TON 1,733.04 781.47 61,478.00 15,998.13 79,990.64

404b REINFORCEMENT AS PER AASHTO M. 31 GRADE 60 TON 1,733.04 781.47 68,828.00 17,835.63 89,178.14

404h REINFORCEMENT (STRUCTURAL SHAPES) AS PER ASTM-A- TON 1,393.24 5,393.81 57,035.76 15,955.70 79,778.52
36

405a PRE-STRESSING WIRE STRAND 3/8" - 1/2" DIA COMPLETE IN TON 2,848.15 15,659.05 133,847.57 38,088.69 190,443.47
ALL RESPECT

405b LAUNCHING OF GIRDER TON 67.39 532.52 - 149.98 749.89

406a PREMOULDED JOINT FILLER 12 mm THICK WITH SM 127.30 - 310.06 109.34 546.70
BITUMASTIC JOINT SEAL

406b NEOPRENE RUBBER JOINT FILLER 12 mm THICK WITH SM 127.30 - 308.96 109.06 545.32
BITUMASTIC JOINT SEAL

406c STEEL EXPANSION JOINTS KG 10.39 26.40 91.90 32.17 160.86

406d WATER STOPS 6" SIZE M 109.05 - 469.14 144.55 722.73

406e ELASTOMERIC BEARING PADS (ACCORDING TO SIZE AND ccm 0.02 - 2.12 0.53 2.67
THICKNESS)

406f ASPHALT FELT (3 PLY) SM 42.69 - 3,078.56 780.31 3,901.56

406g STEEL OR METAL BEARING DEVICES KG 21.96 69.68 118.12 52.44 262.21

407d1 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 371.93 1,654.04 898.40 731.09 3,655.46
(BORING ONLY) IN NORMAL SOIL

407d2 CAST IN PLACE CONCRETE PILES UP TO 0.76 M DIA M 557.89 2,481.06 1,347.60 1,096.64 5,483.20
(BORING ONLY) IN GRAVEL STRATA

407d3 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 557.89 2,481.06 995.75 1,008.68 5,043.38
ONLY) IN NORMAL SOIL

407d4 CAST IN PLACE CONCRETE PILES 0.80 - 1.4 M DIA (BORING M 929.82 4,135.11 1,171.54 1,559.12 7,795.59
ONLY) IN GRAVEL STRATA

407d5 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 796.99 4,884.94 1,347.88 1,757.45 8,787.26
ONLY) IN NORMAL SOIL

407d6 CAST IN PLACE CONCRETE PILES 1.5 -2.0 M DIA (BORING M 1,394.73 6,909.78 1,482.79 2,446.83 12,234.13
ONLY) IN GRAVEL SOIL

407h PILE LOAD TEST UP TO 120 TON EACH 26,707.83 45,769.30 90,203.26 40,670.10 203,350.49

407i PILE LOAD TEST UP TO 240 TON EACH 50,208.71 45,769.30 180,406.52 69,096.13 345,480.66

407j PILE LOAD TEST UP TO 360 TON EACH 73,709.58 50,188.38 270,609.78 98,626.94 493,134.68

407k CONFIRMATORY BORING (NX SIZE) M 223.34 1,582.02 6.37 452.93 2,264.66

410 BRICK WORK CM 352.35 282.72 2,929.04 891.03 4,455.14

411a STONE MASONRY RANDOM DRY CM 304.78 107.96 385.27 199.50 997.51

411b STONE MASONRY RANDOM WITH MORTAR CM 325.65 166.68 1,430.40 480.68 2,403.41

411c STONE MASONRY DRESSED UNCOURSED DRY CM 398.75 107.96 414.30 230.25 1,151.26

411d STONE MASONRY DRESSED UNCOURSED WITH MORTAR CM 466.61 166.68 1,465.77 524.76 2,623.82

Page 210
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Tank
Tank District Code: 70-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

411g ROLL POINTING SM 74.31 11.74 44.06 32.53 162.64

412a STONE MASONRY DRESSED COURSED WITH MORTAR CM 633.67 264.08 1,370.97 567.18 2,835.90

501a R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 310 mm M 258.71 437.48 643.98 335.04 1,675.22

501b R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 380 mm M 252.58 577.19 834.87 416.16 2,080.80

501c R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 460 mm M 242.26 935.96 1,070.67 562.22 2,811.12

501d R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 610 mm M 255.85 1,146.39 1,599.19 750.36 3,751.78

501e R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 760 mm M 293.01 1,078.41 2,298.83 917.56 4,587.81

501f R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 910 mm M 359.49 1,331.30 3,615.93 1,326.68 6,633.40

501g R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1070 mm M 465.22 1,481.41 4,681.88 1,657.13 8,285.64

501h R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1220 mm M 550.00 1,798.85 5,966.36 2,078.80 10,394.02

501i R.C.C PIPE CULVERT AASHTO M 170 CLASS II DIA 1520 mm M 648.30 2,098.66 9,215.91 2,990.72 14,953.59

501j R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 310 mm M 258.71 507.33 723.27 372.33 1,861.65

501k R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 380 mm M 252.58 577.19 853.69 420.86 2,104.32

501l R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 460 mm M 235.80 935.96 1,045.25 554.25 2,771.27

501m R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 610 mm M 255.85 1,146.39 1,744.43 786.67 3,933.34

501n R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 760 mm M 293.01 1,078.41 3,317.10 1,172.13 5,860.65

501o R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 910 mm M 359.49 1,331.30 4,873.24 1,641.01 8,205.04

501p R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1070 mm M 465.22 1,481.41 6,810.31 2,189.23 10,946.17

501q R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1220 mm M 550.00 1,798.85 9,236.63 2,896.37 14,481.86

501r R.C.C PIPE CULVERT AASHTO M 170 CLASS IV DIA 1520 mm M 648.30 2,098.66 12,994.77 3,935.43 19,677.17

502a GRANULAR MATERIAL IN BED TO CONCRETE PIPE CM 101.72 118.93 287.07 126.93 634.64
CULVERT

502b CONCRETE CLASS "B" IN BEDDING AND ENCASEMENT OF CM 830.63 612.95 3,570.55 1,253.53 6,267.65
CONCRETE PIPE CULVERT

507a STEEL WIRE MESH FOR GABIONS KG 5.81 - 113.36 29.79 148.97

507b ROCK FILL IN GABIONS CM 110.95 - 388.21 124.79 623.95

508a BRICK PAVING (SINGLE COURSE) SM 119.42 32.70 226.96 94.77 473.84

508b BRICK PAVING (DOUBLE COURSE) SM 213.39 32.70 451.31 174.35 871.75

509a RIP RAP CLASS "A" CM 513.10 - 290.46 200.89 1,004.45

509b RIP RAP CLASS "B" CM 496.10 - 288.14 196.06 980.30

509c RIP RAP CLASS "C" CM 498.68 - 290.46 197.29 986.43

Page 211
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Tank
Tank District Code: 70-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

509d GROUTED RIP RAP CLASS "A" CM 627.51 102.14 1,695.19 606.21 3,031.05

509e GROUTED RIP RAP CLASS "B" CM 604.33 81.72 1,546.95 558.25 2,791.24

509f GROUTED RIP RAP CLASS "C" CM 597.58 68.10 1,591.28 564.24 2,821.19

509g REINFORCED CONCRETE SLOPE PROTECTION (WITHOUT CM 869.39 353.02 4,132.53 1,338.74 6,693.68
REINFORCEMENT)

509h FILTER LAYER OF GRANULAR MATERIAL CM 54.62 191.97 348.64 148.81 744.04

510 DISMANTLING OF STRUCTURE AND OBSTRUCTIONS CM 120.28 390.69 - 127.74 638.72

511a1 DRY STONE PITCHING (15-20 cm Thick) SM 163.28 67.48 47.20 69.49 347.44

511a2 DRY STONE PITCHING (21-25 cm Thick) SM 209.00 86.37 60.42 88.95 444.73

511b1 GROUTED STONE PITCHING (15-20 cm Thick) SM 263.28 180.32 351.87 198.87 994.34

511b2 GROUTED STONE PITCHING (21-25 cm Thick) SM 329.10 225.40 439.83 248.58 1,242.92

601ai CONCRETE KERB IN PLACE NEW JERSY BARRIER FOR M 298.65 572.25 2,234.22 776.28 3,881.40
MEDIAN (DOUBLE FACE)

601di PRECAST REINFORCED CONCRETE KERB NEW JERSY M 1,055.20 670.54 4,116.24 1,460.49 7,302.47
BARRIER FOR MEDIAN (DOUBLE FACE)

601dii PRECAST KERB IN CONCRETE CLASS A-1 OF SIZE 450 X 150 MM M 153.09 90.27 432.59 168.99 844.93
INCLUDING CONCRETE BEDDING & HAUNCHING

603 BRICK EDGING M 9.67 - 36.48 11.54 57.69

604a METAL GUARD RAIL M 20.05 70.84 1,579.36 417.56 2,087.81

604b METAL GUARD RAIL END PIECES EACH 27.89 - 1,197.58 306.37 1,531.84

604d STEEL POST OF METAL GUARD RAIL EACH 91.71 976.73 3,776.31 1,211.19 6,055.94

605a CONCRETE BEAM GUARD RAIL M 84.45 30.82 599.67 178.74 893.68

605c CONCRETE POST FOR GUARD RAIL M 103.70 27.36 600.77 182.96 914.79

607a TRAFFIC ROAD SIGN CATEGORY 1 EACH 258.99 255.15 6,867.24 1,845.35 9,226.73

607b TRAFFIC ROAD SIGN CATEGORY 2 EACH 76.04 382.72 9,265.98 2,431.19 12,155.93

607c TRAFFIC ROAD SIGN CATEGORY 3 (a) EACH 258.99 541.89 11,900.41 3,175.32 15,876.60

607d TRAFFIC ROAD SIGN CATEGORY 3 (b) EACH 877.48 598.64 20,983.30 5,614.86 28,074.28

607e TRAFFIC ROAD SIGN CATEGORY 3 (c) SM 175.50 119.73 9,225.46 2,380.17 11,900.85

607f ADDITIONAL PANEL SIZE 60 X 30 cm EACH 300.66 - 1,306.05 401.68 2,008.39

607g ADDITIONAL PANEL SIZE 90 X 30 cm EACH 300.66 - 1,959.07 564.93 2,824.67

608b1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 3.05 5.86 16.18 6.27 31.37
LINES OF 15 cm WIDTH

608b2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 1.02 4.03 39.87 11.23 56.15
LINES OF 15 cm WIDTH

608c1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR M 3.05 5.86 21.59 7.63 38.13
LINES OF 20 cm WIDTH

Page 212
CSR - January 2009
National Highway Authority Construction Shabir Associates
Islamabad Quantity Survying & Construction Cost Consultants

District: Tank
Tank District Code: 70-A

CODE DESCRIPTION UNIT MANPOWER EQUIPMENT MATERIAL OH-PROFIT RATE

608c2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR M 1.02 4.03 53.18 14.56 72.78
LINES OF 20 cm WIDTH

608d1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 82.69 5.22 156.37 61.07 305.35
4.0 M ARROWS

608d2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR 4.0 EACH 82.69 9.98 502.46 148.78 743.92
M ARROWS

608h1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.81 8.59 22.50 8.73 43.63
OF 15 cm WIDTH

608h2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.81 9.63 67.50 20.24 101.19
OF 15 cm WIDTH

608i1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR LINES M 3.81 6.95 30.00 10.19 50.96
OF 20 cm WIDTH

608i2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR LINES M 3.81 9.63 90.01 25.86 129.32
OF 20 cm WIDTH

608j1 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR 4.0 M EACH 82.69 3.73 217.23 75.91 379.56
ARROWS

608j2 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR 4.0 M EACH 82.69 7.90 851.20 235.45 1,177.24
ARROWS

608n1 PAVEMENT MARKING IN NON-REFLECTIVE CR PAINT FOR EACH 69.16 3.73 104.25 44.28 221.42
STOP

608n2 PAVEMENT MARKING IN NON-REFLECTIVE TP PAINT FOR EACH 69.16 7.90 335.48 103.14 515.68
STOP

608n3 PAVEMENT MARKING IN REFLECTIVE CR PAINT FOR STOP EACH 69.16 3.73 144.82 54.43 272.14

608n4 PAVEMENT MARKING IN REFLECTIVE TP PAINT FOR STOP EACH 69.16 7.90 568.32 161.35 806.73

609c REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 9.89 81.62 193.82 71.33 356.66
SINGLE)

609d REFLECTORIZED PAVEMENT STUD (RAISED PROFILE TYPE - EACH 9.89 81.62 233.82 81.33 406.66
DOUBLE)

610b RIGHT OF WAY MARKER EACH 119.12 121.33 303.51 135.99 679.94

610c KILOMETRE POST (0.610 X 0.114 X 1.5 M) EACH 704.70 976.31 2,049.32 932.58 4,662.90

610d TEN KILOMETRE POST EACH 1,370.99 1,952.61 4,495.94 1,954.89 9,774.43

611a CHAIN LINK WIRE FABRIC FENCING 1500 MM HEIGHT M 146.16 91.00 953.85 297.75 1,488.76
WITH PRECAST PRESTRESSED R.C.C. POST

Page 213
.