Production and Process Validation
Production and Process Validation
validation
17 January 2006
by...Wiriya charoenkunathum
References:
2
GMP
3
GMP
are aimed primarily at diminishing the
risks inherent in any pharmaceutical
production
• Cross –contamination; unexpected
contaminants
• Mix-ups; confusion (false labels)
4
Good practices in production
• Principle: production operations must
follow clearly defined procedures in
accordance with manufacturing and
marketing authorizations, with the
objective of obtaining products of the
requisite quality.
5
Production of Vaccine GMP
Inoculum
Media/Cell culture
Single harvest
Excipients
Validation Pool/Concentrated material
- process
- method Purified/Bulk material
Stability studies
7
Good practices in
production:General
• Any deviation from instructions or
procedures should be avoid as far as
possible.
– If deviations occur: should be done in
accordance with an approved procedure
– approved in writing by a designated
person
8
Good practices in
production:General
• Checks on yields and reconciliation of
quantities to ensure that there are no
discrepancies outside acceptable limits.
9
Good practices in
production:General
• Operation on different products should
not be carried out simultaneously or
consecutively in the same room or area
unless there is no risk of mix-up or
cross-contamination.
10
Good practices in
production:General
• At all time during processing
– all materials
– bulk containers
– major items of equipment
– rooms
– packaging lines
• being used should be labeled or identified
11
Good practices in
production:General
• Access to production premises should be
restricted to authorized personnel.
• Non-medicinal products should not be
produced in areas or with equipment
destined for the production of
pharmaceutical products.
12
Good practices in
production:General
• In-process controls are usually
performed within the production area.
– The performance should not have any
negative effect on the quality of the product
or another product.
13
Good practices in production: Prevention of cross-
contamination during production
14
Good practices in production: Prevention of
cross-contamination during production
15
Good practices in production: Prevention of
cross-contamination during production
16
Good practices in production: Prevention of
cross-contamination during production
17
Good practices in production: Prevention of
cross-contamination during production
18
Good practices in production:
Processing operations
19
Good practices in production:
Processing operations
Any necessary in-process controls and environmental
controls should be carried out and recorded
Indicate the failures of equipment or services (e.g. water,
gas) to equipment
defective EQ withdrawn
after use, production EQ
• cleaned without delay,
• stored under clean and dry conditions in separate area
20
Good practices in production:
Processing operations
Time limits for storage of EQ after
cleaning and before use
Containers for filling should be cleaned
before filling
Any significant deviation from the
expected yield
recorded and investigated
21
Good practices in production:
Processing operations
Checks
pipelines and other pieces of EQ used for
transportation of products
Pipe used for conveying distilled or
deionized water
sanitized and stored according to written
procedures (action limits for
microbiological contamination and
measures
22
Good practices in production:
Processing operations
EQ and instruments
serviced and calibrated at prespecified interval
records maintained
checked daily or prior to use
clearly indicated the date of calibration and
servicing, recalibration (label attached to
instrument)
Repair and maintenance operations
not present any hazard to the quality of the
products
23
GMP for biological products
:Production
• SOP for manufacturing operations:
available, up date
• Starting material: source, origin,
method of manufacture, QC
• Media and culture shall be added to
fermenter and other vessels under
carefully controlled conditions, avoid
contamination
24
GMP for biological products
:Production
• Media should be sterilized in situ. In line
sterilizing filters for routine addition of gases,
media, acids, alkalis, deforming agents, etc.
to fermenter should be used where possible.
• Validation of sterilization.
• Inactivation process: measures should be
taken to avoid risk of cross-contamination
between treated and untreated products.
25
GMP for biological products
:Production
• A wide equipment used for
chromatography
– should be dedicated to purification of one
product
– should be sterilized or sanitized between
batches
– define the life span of columns and the
sterilization method
26
• In-process controls play a specially
important role in ensuring the consistent
quality of biological products because
certain deficiencies may not be revealed
by testing the finished product.
– Tests that are crucial for quality control but
that cannot be carried out on the finished
product shall be performed at an
appropriate stage of production.
27
• Samples of intermediate and final products
shall be retained in sufficient amount and
under appropriate storage conditions to allow
the repetition or confirmation of a batch
control.
• Certain operations require the continuous
monitoring of data during a production
process e.g.monitoring and recording of
physical parameters during fermentation.
28
Validation: Definition
Validation is the documented act of proving
that any procedure, process, equipment,
material,activity or system actually leads to
the expected result.
29
Validation studies
analytical test
equipment
facility systems (air, water, steam, process;
manufacturing processes, cleaning,
sterilization, sterile filling, lyophilization)
31
Type of validation
Prospective
• pre-planned protocol
Concurrent
• base on data collected during actual performance of a process
already implemented in a manufacturing facility
• suit manufacturers of long standing, have well-controlled
manufacturing process
Retrospective
• for production for a long time, but has not been validated
according to a prospective protocol and concurrent validation is
not realistic option
• is not generally accepted
32
Type of validation
Laboratory-and pilot-scale validations
• some production processes cannot be carried out
in production facility
33
Facility systems and equipment:
Stage of validation
Design qualification (DQ)
Installation Qualification (IQ)
Operational Qualification (OQ)
Performance Qualification (PQ)
34
Facility systems and equipment
Design qualification (DQ)
• necessary when planning and choosing EQ or
systems to ensure that components selected will
have adequate capacity to function for the
intended purpose, and will adequately serve the
operations or functions of another piece of EQ or
operation.
35
Facility systems and equipment
Installation Qualification (IQ)
• written for critical processing EQ and systems
• list all the identification information, location, utility
requirements, and any safety features of EQ
• verify that the item matches the purchase
specifications
36
Facility systems and equipment
Operational Qualification (OQ)
• outlines the information required to provide evidence that all
component of a system or of a piece of EQ operate as
specified.
• should provide a listing of SOPs for operation, maintenance
and calibration
• define the specification and acceptance criteria
• include information on EQ or system calibration, pre-
operational activities, routine operations and their
acceptance criteria
37
Facility systems and equipment
Performance Qualification (PQ)
• performed after both IQ and OQ have been completed,
reviewed and approved
• describes the procedures for demonstrating that a system
or piece of EQ can consistently perform and meet required
specification under routine operation and, where
appropriate, under worst case situations
• include description of preliminary procedures required,
detailed performance tests to be done, acceptance criteria
• other supporting EQ used during qualification have been
validated.
38
Facility systems and equipment
pH meter, incubator, centrifuge, freezer; IQ,OQ
39
Process validation
A process is a series of interrelated functions and
activities using a variety of specified actions and
EQ which is designed to produce a defined result.
40
Process validation studies
examine a process under normal operating
conditions to prove that the process is in control
re-validation
modification to the process
problems occur
EQ or systems are changed
41
Process validation
To validate the reproducibility and consistency of a
process
full defined process is carried out using validated EQ
at least 3 times, under established procedure
process must successfully and consistently meet all acceptance
criteria at all steps throughout the procedure at least 3 times
consecutively
Validated process
43
Process validation
specific process clearly described in Master
formula or in SOP
all EQ; identity, code number, construction, operation
capacity, actual operating range
processing parameter; sufficiently detailed to permit
complete reproducibility (time period, pH, volume,
temp.etc.)
specification at each step
44
Process validation
Very important
specifications for a process undergoing validation be
pre-determined
all critical processing parameters for which
specifications have been set, there must be equipment
to measure all of those parameters during the
validation study
45
Typical content requirements for
process validations
Cleaning, Fumigation,
Sanitization Process As relevant to the
collecting liquid and swab cleaning process
samples for testing of residual
product
residual protein
All analytical tests must
endotoxin tests
be validated before
microbial tests (bioburden)
chemical tests (chlorine and
phosphoric acid)
residual cleaning agents
conductivity tests
pH
46
Typical content requirements for
process validations
Sterilization
sterilization filtration of solutions
microbial challenge
filter integrity tests
performance tests
47
Typical content requirements for
process validations
Depyrogenation process (dry heat, column
chromatography, other)
endotoxin content reduction of 3 logs
48
Typical content requirements for
process validations
Sterile filling
test filling process
perform filling process with nutrient media
run at full scale for at least one fill size
worst case; large volume and number of vials
filled vials incubated, observed and test for contamination by
validated sterility test
must be sterile for 3 consecutive runs
media fill performed twice a year
size of run must be large enough to detect low levels of
contamination e.g. contamination rate of 1/1000, 3000 units are
needed to provide 95% confidence
49
Typical content requirements for
process validations
Mock fermentation
full scale fermentation of a representative fermentation
process
to validate the parts of process involving connections,
sampling, and additions of nutrients etc.
fermentor prepared and operated in simulated process with
uninoculated nutrient media
process follow the full fermentation process
3 consecutive runs at each stage
50
Typical content requirements for
process validations
Production processes(fermentation, bulk
production, purification, filling, lyophilization)
run according to approved Master formula including all
raw material, personnel, equipment, and facility
preparations, in-process tests, processing, through to
final testing of the batch lot.
all facility systems must be monitored
3 consecutive lots must be produced and all facility,
EQ, support systems, product spec, and process
being validated must pass at all steps
51
Validation: Type of Documentation
Validation master plan (VMP)
Validation protocol (VP)
Validation reports (VR)
Standard operating procedures (SOPs)
52
Master validation plan (MVP)
is a document pertaining to the whole facility
that describes which EQ, systems, methods
and processes will be validated and when
they will be validated.
provide the format required for each
particular validation document (IQ, OQ, PQ
for EQ and systems; process validation,
analytical assay validation)
53
Master validation plan (MVP)
indicate what information is to be contained
within each document
indicate why and when revalidations will be
performed
who will decide what validations will be
performed
order in which each part of the facility is
validated
54
Master validation plan (MVP)
indicate how to deal with any deviations
state the time interval permitted between
each validation
55
Validation: VMP
Enables overview of entire validation project
List items to be validated with planning
schedule as its heart
like a map
56
Validation: In summary, VMP
should contain at least
Validation policy
Organizational structure
Summary of facilities, systems, equipment,
processes to be validated
Documentation format for protocols and reports
Planning and scheduling
Change control
Training requirements
57
Validation: Protocol
Objectives of the validation and qualification
study
Site of the study
Responsible personnel
Description of the equipment
SOPs
Standards
Criteria for the relevant products and
processes
58
Validation: Report
Title
objective of the study
Refer to the protocol
Details of material
Equipment
Programmes and cycles use
Details of procedures and test methods
59
Validation: changes that require
revalidation
Software changes; controllers
Site changes; operational changes
Change of source of material
Change in the process
Significant equipment changes
Production area changes
Support system changes
60