Project Gantt Chart Report - Month
2010
Western Wireless, LLC. Aug Sep Oct Nov Dec
Start End
Task or Milestone Planned Planned
WBS Name % Actual Actual
iConfigure Webinar Series 8/23/10 8/27/10
100%
8/30/10 9/3/10
Remote Configuration/Consulting 8/30/10
27% 9/24/10
9/1/10
Daptiv S2L Implementation 8/16/10
29% 12/23/10
8/16/10
Project Milestones 8/17/10
0% 12/23/10
8/17/10
Subscribe to Live - SC Consulting/Configuration/Training Sessions 8/23/10
42% 12/22/10
8/30/10
2 Role Based Trainings (Train the Trainer) 0% 9/27/10 9/28/10
3 Days Onsite Consulting 9/8/10 9/9/10
100%
9/8/10 9/9/10
WI Report Development 0% 9/14/10 9/24/10
Seattle ARB Training (attendees) 0% 10/27/10 10/29/10
ARB Training (select event) 0% 10/27/10 11/1/10
Analytics Development & Coaching 0% 11/1/10 11/1/10
WI Report Coach for Seattle ARB 0% 11/1/10 11/1/10
Solutions Assurance - 3 month checkup 0% 12/22/10 12/22/10
Create Daptiv PPM Enterprise 8/16/10 8/16/10
100%
8/16/10 8/16/10
Kick-Off Meeting 8/19/10 8/19/10
100%
8/19/10 8/19/10
Send Welcome Packet to Customer 8/17/10 8/17/10
100%
8/17/10 8/17/10
Configuration Validated 0% 9/13/10 9/13/10
Training Complete 0% 9/29/10 9/29/10
Go Live 0% 10/1/10 10/1/10
Implementation Closeout 0% 10/7/10 10/7/10
Post Implementation Survey 0% 11/16/10 11/16/10
Deliverables Complete 0% 12/23/10 12/23/10
-1- Run Date: Sep 16, 2010 12:58
PM PDT