Tata BlueScope Steel (BUTLER INDIA) Erection Manual
Tata BlueScope Steel (BUTLER INDIA) Erection Manual
Tata BlueScope Steel (BUTLER INDIA) Erection Manual
Erection, Installation
and
Maintenance Manual
Introduction
The Metal Building Erection, Installation and Maintenance
Manual has been prepared to assist builders in order to erect
buildings properly, quickly and safely.
The builders who refer to the contents of this manual must pay
regard to current regulations for site safety. The builders are
responsible for maintaining strictly the current legal regulations
of labour safety during erection of buildings.
1
1
Metal Building Terminology
ACCESSORY: An extra building component added to a basic CANTILEVER: A projecting beam that is supported and
BSL building, such as a door, window, ventilator, insulation, wire restrained at one end only.
mesh, translucent sheets etc.
CANOPY: An projecting roof structure, below the eave level,
ALUMINISED: Aluminum coated steel supported at one end only.
ASSEMBLY: Two or more components bolted together CAP PLATE: A plate located at the top of a column or end of a
beam. Also refer to as End plate.
ASTRAGAL: A bent plate fixed at door leaf to cover gap
CAPILLARY ACTION: The action of water rising to a higher
ANCHOR BOLTS: Bolts set in concrete, used to anchor
level due to surface tension.
structural members to concrete foundation.
CAT WALK: A narrow walk way used to provide access to
BASE ANGLE: A continuous angle secured to foundation to
mechanical equipment normally supported on roof platform.
support cladding
CAULKING: A sealant used in making watertight joints.
BASE PLATE: The end plate of a column which rests on the
supporting substructure surface CHECKERED PLATE: Flat hot rolled plate with raised
checkered design to prevent slipping; used for industrial
BASE CHANNEL: A light gauge cold formed channel which
equipment platform, catwalks, stair treads, etc
replaces the base angle when liner or double cladding partitions
are required CLEAR HEIGHT: The vertical dimension from the finished floor
level to the lowest underside point of the rafter.
BEAM: A horizontal structural member designed primarily to
resist moments CLEAR SPAN: A building without internal columns.
BAY: The space between the centre lines of frames or primary CLIP: A bent plate or angle used to fasten two or more members
supporting members in the longitudinal direction of the building. together.
Also called bay spacing or bay length
CLOSURE STRIP: Purpose-made from fillers to fit inside and
BEAD MASTIC: A sealant furnished in a continuous roll. outside profiles of roof and wall panels providing a weather tight
Normally used for sealing end laps of roof panels seal.
BENT PLATE: A plate bent to form an angle. COIL: A roll of steel sheet or wire.
BIRD MESH: Wire mesh used to prevent birds from entering the COLD-FORMED MEMBER: A light gauge structural member
building through the ventilators, louvers and roof monitors. produced from coiled steel stock formed to desired shape at
room temperatures.
BRACE RODS/CABLES: Rods or cables placed diagonally in
the roof and walls for the purpose of transferring wind loads to COLUMN: A vertical structural member used in a building to
the foundation and longitudinally stabilising the building. transfer loads from the roof beams, trusses or rafters to the
foundation.
BRACED BAY: The bay where bracing is provided
CONCRETE NOTCH: A rebate or notch formed along the edge
BRACKET: A structural support projecting from a column or
of the concrete floor slab or grade beam, allowing wall panels to
rafter to which another structural member is fastened.
end below the floor level thus preventing ingress of dust or water.
BUILT UP SECTIONS: A structural member usually an “I” shape
CONTINUOUS RIDGE VENT: Two or more ridge ventilators
made from individual plates welded together.
mounted on the building ridge that allows air circulation.
“C” SECTION: A member formed into a “C” shape profile by cold
roll-forming from coils.
2
Part 1 - Tata BlueScope Steel
CURB: Raised flashing around the roof opening to form EAVE STRUT: A structural member, located at the eave, used
waterproof opening. for supporting the roof panels and the wall panels.
CURVED EAVE: Curved panels provided at the eave. EAVE STRUT CLIP: A clip used to support the eave strut.
DAMPER: Baffle plate in a ridge ventilator that can be opened EAVE TRIM/ FLASHING: A sheet metal closure whose function
or closed using the cable catch assembly. is primarily to provide weather tightness at the eave between the
eave gutter and the wall panels.
DEAD LOAD: The self weight of the pre-engineered building
structure including all its components such as frame, floors, END BAY: The first or last bay in the building. It is spacing
secondary members, sheeting, bolts, etc between the outside face of the outer flange of the end wall
columns and the centre line of the interior column.
DESIGN CODES: Regulation developed by recognised
agencies establishing design loads procedures, and END LAP: A term used to describe the lap of roof sheet where
construction details for structure. Examples are, MBMA, AISI, the end of the one sheet overlaps the end of the other sheet
AISC, AWS, IS 800, IS 801 etc. below it.
DOOR GUIDE: An angle, channel or proprietary product used to END WALL: A term used to describe the entire frame structure
restrain a door leaf or curtain during its opening and closing. of a building at gable end.
DOOR STOPPER: A clip bolted to the vertical door member to END WALL COLUMN(S): A vertical member located at the
prevent opening beyond the door limit. endwall which supports the end wall rafter and girts.
DOUBLE CHANNEL: Double or back to back “C” sections END WALL ROOF EXTENSION: Roof cantilevered beyond the
stitched / bolted together. end wall steel line.
DOUBLE FACE TAPE: Used as an aid to fix fibreglass ERECTION DRAWINGS: Drawing and erection instructions
insulation. which identify all the individual components in sufficient detail to
permit the proper assembly of all parts of the metal building
DOUBLE SLIDING DOOR: Sliding door with two leaves.
systems.
DOWNSPOUT: Cold formed sheet metal section or PVC pipe
EWDS: Non-expandable double slope endwall
used to carry water from the gutter of a building to the ground or
storm drainage system. EWSS: Non-expandable single slope endwall
3
EWWX: Non-expandable WX endwall GABLE FLASHING / BARGE FLASHING: A flashing designed
to close the opening between the roof panels and end wall
EXDS: Expandable double slope endwall
cladding.
EXPANSION JOINT: A joint of building allowing for expansion
GAGE OR GAUGE: The distance between holes along the
and contraction
transverse axis of a plate.
EXSS: Expandable single slope endwall
GALVANISED: Steel coated with a layer of zinc for corrosion
EXWX: Expandable WX endwall resistance.
FASCIA: An accessory whose function is to enhance the GIRT: Secondary horizontal member attached to the main frame
appearance of a wall. Also used to cover the ridge or gable of a / endwall columns. Girts support wall cladding.
building
GLAZING: Surface glass
FIELD WORK: Modification or rectification carried out on site.
GROUT: Non-shrinking sand and cement based mixture used
FIN NECK BOLT OR ROUND HEADED BOLT: Flat dome under base plates to obtain a uniform bearing surface.
headed bolt used in framed openings, fascias, and the
GUSSET PLATE: Steel stiffner plate used to help distribute load
mezzanines.
at a connection.
FINISHED FLOOR: Top of the concrete slab or finished surface
HAND RAILS: Horizontal and vertical pipes fixed to the
FIXED BASE: A column that is designed to resist rotational as stringers, edges of mezzanine floors, openings in floors and
well as vertical and horizontal movement. platform walkways.
FLANGE BRACE: An angle member connecting to the inner HANGER DOOR: A large multi leaf door that is used in aircraft
flange of columns / rafters to girt / purlin to provide them with hangars or similar buildings.
lateral support and stability.
HAUNCH: Intersection of the column and rafter.
FLASHING: A sheet metal closure used to provide
HEADER: A horizontal member over an opening in a wall.
weather-tightness in a structure.
HIGH STRENGTH BOLTS: Any bolt made from steel having a
FLUSH MOUNTED: A girt system where the outside flanges of
tensile strength in excess of 690 megapascal (MPa). Some
girts and columns are flush. The girts are supported by the use
examples are: ASTM A 325 etc
of girt clips bolted to the column webs.
HILLSIDE WASHER: A washer having non parallel faces
FOUNDATION: The substructure which supports a building or
normally used on brace cables or rods. Also known as bevel
the other structure.
washer.
FRAMED OPENINGS: Framing (headers, sills and jambs) and
IMPACT LOAD: A dynamic load resulting from the motion,
flashing which surround an opening of a building. Usually
machinery, craneway, elevators and other similar moving forces
provided to accommodate field installed accessories such as
sliding doors, roll up doors, etc INSULATION: Any material used in building construction for
reduction of heat transfer.
GABLE: The triangular portion of the endwall of a building
directly under the sloping roof and above the eave height line. INTERIOR BAY: The distance between the centre lines of two
adjacent interior rigid frame.
GABLE ANGLE: An angle fastened to the purlins at rake for the
attachment of end wall cladding. JACK BEAM: A primary horizontal member used to support
another beam, truss or rafter.
4
Part 1 - Tata BlueScope Steel
JIB CRANE: A cantilever boom or horizontal beam with a hoist MRSS: Modular single slope frame with straight columns
and trolley.
MRST: Modular single slope frame with tapered columns
JOIST: A horizontal member for supporting the decking of floors
MULLION: A vertical bar or pier between panes or sections of
or roofs.
windows and screens.
LEAN TO OR WX: A structure dependent upon another
MULTI-GABLE BUILDING: Buildings consisting of two or more
structure for lateral stability and having only one slope or pitch
gables across the width of the building.
LINER PANEL: Interior wall or roof sheeting attached to the
MULTI-SPAN BUILDINGS: Buildings with interior columns.
inside flanges of the girts or purlins.
PART MARK: A number physically marked on a piece or
LIVE LOAD: Any variable load that results from intended use of
packing that identifies each component of the building for
structure during its life time.
erection and shipping purposes.
LMSW: Uses truss purlins with 7 _-inch end seats.
PEAK: The upper most point of a gable. Also called peak point
LONGITUDINAL: The direction parallel to the ridge line. or ridge point
LOUVER: A wall opening provided with slanted blades, fixed or PEAK PANEL: Also known as RIDGE PANEL. Used to link and
movable, to allow flow of air inside the building. weather-seal roof panels on opposite slopes.
LRF: Clearspan double slope frame with tapered columns PEAK SIGN: A sign attached to the peak of the building at the
endwall showing the name of the manufacture of building. Also
LRDS: Clearspan double slope frame with straight columns
called as RIDGE SIGN.
LRSS: Clearspan single slope frame with straight columns
PIN CONNECTION: A connection designed to transfer the axial
LRST: Clearspan single slope frame with tapered columns and shear forces between the connecting members but not
MACHINE BOLTS: Mild steel bolts conforming to ASTM A307 moments.
standard specification. POP RIVET: Used for joining flashings and light gauge metal
MEZZANINE: An intermediate floor within a building above the trims & also called as blind rivet.
ground floor that occupies all or part of the building floor area PORTAL FRAME (PORTF): Column and beam bracing used in
and consists of columns, beam, joists, deck panels and edge lieu of standard diagonal bracing rods to provide clear access.
trims to receive reinforced concrete.
PRIMARY FRAMING: The main load carrying members of a
MRF: Modular double slope frame with tapered columns structural system generally the columns, rafters, and/or other
MOMENT: The tendency of a force to cause rotation about a main support members.
point of axis. PRIMER PAINT: The initial coat of paint applied in the shop to
MOMENT CONNECTION: A connection designed to transfer the structural framing of a building for protection against
moment as well as axial and shear forces, between connecting environmental conditions during shipping and erection.
members. PURLIN: A horizontal secondary structural member, bolted to
MONORAIL BEAM: A single beam support for a material the rafters, which transfers the loads from the roof covering to
handling system. It is normally a hot rolled “I” beam. the primary frames.
MONO SLOPE: A building sloped in one direction. RAFTER: A primary beam member supported on columns.
5
RAKE: The intersection of the plane of roof and the plane of the SELF DRILLING SCREWS (SDS): Fasteners used for attaching
gable. panels and trims to girts and purlins, which drill their own holes
and eliminate the pre drilling operation.
REACTION: The resisting forces, at the column bases of a
frame, holding the frame in equilibrium under given loading SELF TAPPING SCREWS: Have same functions as SDS but
conditions. need pre drilled holes.
REVISION: A change that is made to the building design, SHEETING ANGLE: Angle used to support sheeting or cladding.
component details, location of accessories.
SHIMS: Small steel plates used for levelling base plates or for
RIDGE VENTILATOR: The ventilator used at the ridge line packing between structural members.
RIGID FRAME: A structural frame consisting of members joined SHIPPING LIST: A list that enumerates by part number or
together with rigid (or moments) connection as to render the description, each piece of material or assembly to be shipped
frame stable with respect to imposed loads, without the need for
SHOP DETAILS: Drawing details for fabrication of parts and
bracing in its plane.
assemblies.
RIGID FRAME ENDWALL: A system of endwall framing where
SKY LIGHT: Translucent panels used at the roof to transmit
the main interior frame is used at the end wall mostly for purpose
natural light. It is usually made of fibreglass or polycarbonate.
of future expansion.
SLEEVE NUT: A long nut normally used to join two brace rods of
RISERS: The vertical rise of the steps of a staircase.
the same diameter together & is also known as coupling.
ROLL UP DOOR: A door which opens vertically and supported
SLIDING DOOR: A single double leaf door which opens
on a shaft or drum and runs along vertical tracks.
horizontally by means of overhead trolleys or bottom wheels.
ROOF COVERING: The exterior roof skin consisting of panels or
SLOT: An elongated hole.
sheets, their attachments, and weather sealant.
SOFFIT: The underside covering of any exterior portion of the
ROOF CURB: Weatherproof flashing used on roofs to support
metal building such as canopies, fascia and wall roof extension.
power ventilators or ducting. Roof curbs can be of fibreglass or
sheet metal. SOIL PRESSURE: The load per unit area a structure will exert
through the foundation.
ROOF MONITOR: Raised gable, or portion of the main building,
located at the ridge, to allow lighting and ventilation. SPACE SAVER: Building with single gable clear span and
straight column. Wall girts are flush mounted.
ROOF SLOPE: The angle that a roof surface makes with the
horizontal usually expressed in units of vertical rise to 10 units of SPAN: Distance between the supports of beams, girders, or
before the installation of sheeting. dimensions, strength and other properties or a statement
defining performance expectations of material or devices.
SECONDARY FRAMING: Members which carry loads to the
primary framing .In metal buildings this term includes purlins, SPLICE: The connection between two structural members.
girts, eave strut, etc. STEEL LINE: The extreme outer limits of the structural framing
SEISMIC LOAD: The assumed lateral load acting in any system of a building to which cladding is attached.
horizontal direction on the structural system due to earthquakes STIFFNER: Plate welded to a member to increase strength of
6
Part 1 - Tata BlueScope Steel
7
2
Built Up Framing Systems
This basic framing illustration is designed as an aid in the sizes within the limits of the envelope. Material used in this frame
identification and location of the structural members and is optimised to the specific width and height requirements.
components used in the construction of building structures. Frame Specifications:-
There are a number of different types of structural systems LRF Columns: All columns are one piece tapered members with
available from Tata BlueScope Steel to provide a large range of the outside flange plumb. They can be ordered flush or with 8"
space, support and protection possibilities and in light, medium inset from the sidewall structural line as illustrated.
and heavy design loads. Generally, part references and usage LRF Roof Beams: Roof beam profiles may vary. The top flange
will follow a similar pattern for all buildings. of the roof beam will be straight to form the roof slope. The shape
of the web and bottom flange will vary as required to optimise the
Main Frame material used to manufacture the beam.
Main frames consist of two or more columns spanned by roof
beam which support the roof structurals. All wide span buildings
2. Frames - LRDS
are clear span structures with the exception of MRF buildings
which also require the use of interior columns.
Clearspan
The LRDS Envelope Frame has a clearspan double slope profile
Clearspan frames are available in straight or tapered columns for
with straight sidewall columns. It offers almost total flexibility in
double slope and single slope profiles, and are used with single
sizes within the limits of the envelope. Material used in this frame
slope width extensions (units supported by an adjacent unit, i.e.
is optimised to the specific width and height requirements.
WX frame).
LRDS Columns: All columns are one piece straight members
Double Slope Profiles -
with the outside flange plumb. They can be ordered flush or with
1. Frames - LRF an 8" inset from the sidewall structural line.
LRDS Roof Beams: Roof beam profiles may vary. The top
flange of the roof beam will be straight to form the roof slope. The
shape of the web and bottom flange will vary as required to
optimise the material used to manufacture the beam.
8
Part 1 - Tata BlueScope Steel
Built-Up Frames
1. Frames - MRF
The LRST Frame has a clearspan single slope profile with
tapered sidewall columns. Material used in this frame is
optimised to the specific width and height requirements.
LRST Columns: All columns are one piece tapered members
with the outside flange plumb. They can be ordered flush or with
8" inset from the sidewall structural line.
LRST Roof Beams: Roof beam profiles may vary. The top
The MRF Frame has a modular double slope profile with tapered
flange of the roof beam will be straight to form the roof slope.
sidewall columns. Material used in this frame is optimised to the
The shape of the web and bottom flange will vary as required to
specific width and height requirements.
optimise the material used to manufacture the beam.
MRF Columns: All columns are one piece tapered members
2. Frames - LRSS with the outside flange plumb. They can be ordered flush or with
8" inset from the sidewall structural line.
MRF Roof Beams: Roof beam profiles may vary. The top flange
of the roof beam will be straight to form the roof slope. The
shape of the web and bottom flange will vary as required to
optimise the material used to manufacture the beam.
LRSS Roof Beams: Roof beam profiles may vary. The top
flange of the roof beam will be straight to form the roof slope.
THE MRST FRAME has a modular single slope profile with
The shape of the web and bottom flange will vary as required to
tapered sidewall columns. Material used in this frame is
optimise the material used to manufacture the beam.
optimised to the specific width and height requirements.
9
MRST COLUMNS: All columns are one piece tapered members 3. Frames - WX
with the outside flange plumb. They can be ordered flush or with
8" inset from the sidewall structural line.
MRST ROOF BEAMS: Roof beam profiles may vary. The top
flange of the roof beam will be straight to form the roof slope.
The shape of the web and bottom flange will vary as required to
optimise the material used to manufacture the beam.
2. Frames - MRSS
The WX Frames has a clearspan single slope profile with a
straight sidewall column at the low side. WX frames are
designed to attach to the low eave of another unit so as to match
roof slope and eave elevation of the adjoined unit.
MRSS Roof Beams: Roof beam profiles may vary. The top WX Roof Beams Roof beam profiles may vary. The top flange
flange of the roof beam will be straight to form the roof slope. of the roof beam will be straight to form the roof slope. The
The shape of the web and bottom flange will vary as required to shape of the web and bottom flange will vary as required to opti-
optimise the material used to manufacture the beam. mise the material used to manufacture the beam.
4. Frames - ENDWALL
Endwall frames can be a pinned endwall frame or semi- rigid
endwall frame. In either case, the frames are designed only for
the loads on the endwall and are NOT designed for future expan-
sion. Both frames use an H-section roof beam.
10
Part 1 - Tata BlueScope Steel
Built-Up Frames
Future Expansion must be specified at the beginning of the proj-
ect in order to be considered in the design and highlighted on the
drawings.
5. Frames - MIXED
11
3
Roofing, Wall Cladding and Structural Decking
KLIP-LOK™ 770 • KLIP-LOK™ 770 profiled sheeting of 770 mm cover width 31 mm crests depth with 3
intermediate pan at 256mm distance
• Two longitudinal stiffeners between ribs makes it a strong profile
• Clip fixed system – no piercing on roof sheeting
• Visually striking bold rib makes a strong statement rising from the flat pans
• Concealed fix system controls thermal expansion and contraction most effectively
• On-site roll forming option to provide single length sheet from ridge to eave
• Economical design, easy installation and outstanding value
• Fixed on the specially designed clip - KL-77
• Manufactured from high strength steel ZINCALUME® steel and COLORBOND® steel
KLIP-LOK™ 700 • KLIP-LOK™ 700 profiled sheeting of 700 mm cover width 43 mm crests depth with
3 intermediate pan at 233 mm distance with cross micro flutes
• Clip fix system - no piercing on roof sheeting
• Cross micro-flutes makes it a strong profile
• Visually striking bold rib makes a strong statement rising from the flat pans
• Concealed fix system controls thermal expansion and contraction most effectively
• Economical design, easy installation and outstanding value
• Fixed on the specially designed clip - KL-70
• Manufactured from high strength steel ZINCALUME® steel and COLORBOND® steel
BR-II™ 900 • BR-II™ is a 900 mm wide coverage profile with 38.1mm deep ribs with pitch of
304.8 mm centre to centre and two stiffeners at every pan
• Specially designed end laps, with anti-capillary side lap, which makes to leak proof
• Strongest and fully tested roofing profile
• Available in factory punched option- to assure proper fit and alignment of each panel
joint ensuring weathertightness
• Pre-formed sealant grooves and guides promote accurate sealant placement between
panels
• Manufactured from high strength steel ZINCALUME® steel and COLORBOND® steel
12
Part 1 - Tata BlueScope Steel
TRIMDEK® 1015 • TRIMDEK® 1015 is 1015 mm wide coverage profile with 28.5 mm deep ribs with
subtle square fluting in the five pan at nominal 203 mm centre-to-centre
• Unique Anti-capillary side lap which makes it leak proof
• Excellent spanning capacity
• Covers large surface area
• Manufactured from high strength steel ZINCALUME® steel and COLORBOND® steel
SPANDEK® 935 • SPANDEK® 935 is 935 mm wide coverage profile with 24mm deep ribs at 93.5 mm
centre to centre
• Unique anti-capillary side-lap which makes it leak proof
• Bold and strong appearance
• Longer Spanning capability
• Strongest cladding can withstand high wind load, snow load or impact load
• Manufactured from high strength steel ZINCALUME® steel and COLORBOND® steel
SHADOWRIB™ • SHADOWRIB profile sheeting is 900 mm wide coverage profile with 38.1 mm deep
ribs at 300 mm center-to-center with two flutes in between the ribs
• Engineered to withstand high wind load and pressure
• Wide pan visibility gives an aesthetically pleasing look to the exterior of the building
• Fewer fasteners than most ribbed panels
• Fasteners are recessed deep in the corrugation, Shadowall panel gives walls an
attractive uniform pattern
• Manufactured from high strength steel ZINCALUME® steel and COLORBOND® steel
13
Profile Design Benefits
FLEXICLAD™ 1110 • FLEXICLAD™ profile sheeting is 1110 mm wide coverage profile with 11.6 mm deep
ribs at 222 mm center-to-center with three stiffeners in between the ribs.
• Cover very wide surface area
• Quick, easy and economical to install
• Manufactured from high strength steel ZINCALUME® steel and COLORBOND® steel
Structural Decking
Profile Design Benefits
14
4
Part 2 - Metal Building Erection
Environment
We care for the environment. We are committed to the efficient
use of resources, reducing and preventing pollution, and product
stewardship.
Community
We strive to be valued corporate citizens in our communities. We
15
Hand Gloves (Electrical) Ear Mask Life Line (PP Rope)
16
Part 2 - Metal Building Erection
Erection Tools
List is based on an average size crew and may need to expand as required.
Bolt Bag 8
Brooms 2
17
Tool Name Qty. Remarks
Chisel 2
Chalk-Line 4
18
Part 2 - Metal Building Erection
D-Shackle 6
Dust Pans 2
19
Tool Name Qty. Remarks
20
Part 2 - Metal Building Erection
Open End Wrenches 2 Sets assorted sizes 12 mm to PPE and Erection Tools& Equipments
32 mm dia bolts
21
Tool Name Qty. Remarks
22
Part 2 - Metal Building Erection
Socket Wrenches 2 sets 12 mm (1/2inch) drive PPE and Erection Tools& Equipments
with assorted sockets and
ratchet drive handle
23
Tool Name Qty. Remarks
24
Part 2 - Metal Building Erection
25
Erection Tools and Equipments load of hoisting operations.
All tools and equipment used for installation must have test • All suspended load must have tag lines.
certificates and calibration certificates if required. The • Prior to start of any lifting work, the location for
concerned Product Consultant / Project Safety Officer / position of the cranes and materials laid down at the
Project Manager or competent person should check the erection areas shall be identified. Job safety and risk
certificates before using the equipments on site. analysis shall be done (you can also refer to
Customer Site Installation Safety Procedure). All
Mobile Equipment cranes and its safety devices and rigging equipment
• Mobile equipment includes delivery trucks, truck cranes, shall have appropriate certificates and suitable
hoists etc. capacities for the intended lifting operation. All crane
• Only certified mobile equipment and qualified operators are operators shall be experienced and have valid
permitted to enter the site. licenses from relevant government authorities. The
26
Part 2 - Metal Building Erection
Scaffolds
4.0 13
17500
17.0 16.0
12.0 3.3 1.34 1.6 12
11.0 13.0
15000
2.7
8.5 10.0 3.0 11
30.0 7.2 1.3 1.55
2.0 9
30.0 27.0 7.0
5.5 2.3
25.0 19.0
18.0 7
6
27
ELCB Box • Be sure the machine is inoperable before removing
• The electrical system for installation works at site requires safety guards when making repairs or adjustment.
having overload CB and ELCB. • Report all the frayed, broken equipment to team
• The ELCB box must be standardised leader.
including the sealed box, ELCB (30mA
- 60mA), 3 pin sealed plugs for outlets. Tips on
• For extended power supply distances Gas Cutting, Welding and Grinding
an ELCB box is required every 30 m.
Gas Cutting, Welding
• At least, 1 of ELCB shall be put on the
roof when doing the roof installation. • Only qualified, properly trained, and instructed
personnel are permitted to use oxygen, fuel gas, weld
Hand Tools equipment. The Project Safety Supervisor must
• All hand tools to be fixed with wrist lanyards for perform an initial check and record the document
• Tools are to be carried in purpose made tool belts • Keep oil and grease away from oxygen equipment.
with leather frogs for safe carriage. • All gas bottles must be stamped and approved.
• Use the right tools and Compressed gas cylinders shall be handled carefully.
never use hand tools for Avoid jarring, bumping or dropping them. Always
that for which they were • Cylinder shall be moved by cart, never rolled. Use a
intended. Never use cradle or holder when lifting cylinders with crane,
makeshift device. never use a magnet.
• All wrench, spanner • Protective caps shall be kept on cylinders when not in
required to have sockets. use and when being transported.
For fixing and • Oxygen cylinders in storage shall be separated from
pre-tension purpose, it's fuel gas cylinders by a minimum of 6m or a fire wall
recommended to use the 1.5 m high.
sash socket spanners. • Flash - back protection shall be provided by an
• Damaged tools, frayed or defective electric cords and approved device that will prevent flame from passing
unguarded machinery must never be used. into the fuel-gas system.
• Tools, equipment, or materials shall be checked to • Torches will not be used as a hammer to remove slag
ensure the gear, belts, or other moving parts of the or scale.
machinery will not endanger anybody and all guards are • Before burning, welding or heating, the worker shall
secured in place. be responsible for checking conditions on opposite
• Shut down and isolate the power source of machinery side or underside to see that all danger of fire or injury
and use extreme caution when cleaning or making is eliminated. A proper fire extinguisher shall be made
adjustments. available.
28
Part 2 - Metal Building Erection
• Never heat an object lying flat on a concrete floor. Be • Straight wheels shall be used on the circumference
sure there is an air space between the material and only, never on the sides.
floor as concrete will explode under extreme heat. • Banging a grinding wheel against the work will not
• Never leave a torch inside a vessel or closed clean the wheel and may cause the wheel to break.
container. A leak could be the start of a disastrous explosion. • Never force a wheel by using excessive pressure.
• When leaving the area, turn gas off at the • Handle grinders with care to prevent damage from
inlet to the hose first and then at the torch. Make dropping. If you drop a grinder, have it checked
certain that there are no leaks. before using. Do not handle grinder by electrical cord
• Inspect all torches, hoses, gauges and other burning or air hose.
equipment regularly. ALL GAUGES MUST BE Always stop the wheel on the work piece before setting the
MARKED FOR INTENDED SERVICE. grinder down. When you set a grinder down do not rest it on the
• Keep hoses clear of spark and hot slag area. wheel.
• All hose connections shall be screw/thread clamps.
No tie wire for connection shall be allowed.
Portable Grinders
• Only qualified, properly trained, and instructed personnel
are permitted to use a portable grinder. The Project Safety
Supervisor must perform an initial check and record the
document prior to permitting use.
• Grinders shall be equipped with guard at all times.
Guards shall not be removed or altered. Only use a
grinding disk for grinding and cutting disk for cutting.
29
5
Understanding
the Engineering Documents
Prior to commencement of erection work, it is essential to have III. Cross-Section
a clear understanding of the engineering documents. In the case
The cross-section is one of the most important drawings as it
of erection, we specifically refer to Erection drawings and
contains a lot of vital information. Columns and rafter references,
Shippers list.
purlins, girts, vertical and roof bracings, connection details, bolt
Erection drawings to be used at site should be 'ISSUED FOR schedules, flange brace schedules and other details as
CONSTRUCTION' and be the latest revision. 'FOR APPROVAL' applicable, such as strut tubes, flashing etc.
drawings should never be used for the works. The revision
In conjunction with the Erection drawing it is possible to find out
boxes at the bottom right corner of each sheet indicate the latest
the number of members required. This being essential during the
status, i.e. “For Approval,” “Issued for construction”, “Revised as
pre-planning stage of erection, and cross-checking to be done
Noted,” etc.
with the shipper list before receipt of material at site. The
cross-section drawing may be typical throughout in standard
I. Anchor Bolt Setting Plan
buildings or in more complex jobs, there may be several
This drawing shows the layout of all anchor bolts, normally on
cross-sections, identified by grid numbers.
one sheet, but for very large buildings, could be on two or more
sheets. Erection drawings are not to scale, so do not attempt to IV. Roof Sheeting Layout
scale any dimensions. The drawings are proportioned although
All roof panels are shown with length and part number. Panel lap
sometimes this can be misleading, and care is needed in
details are shown, also skylight and downspout positions.
reading drawings. All dimensions are in millimetres.
Standard details of fasteners, trims and insulation are included.
The anchor bolt layout contains an anchor bolt schedule, which It is very important to check the starting dimension of the
is in the form of a table showing quantities and sizes of anchor sheeting, from the steel line.
bolts.
The key plan shows center to center dimensions, bay spacing V. Sidewall Sheeting and Framing
dimensions, bolt setting details and critical dimensions for the Depending on the job, sidewall framing and sheeting may be on
span. The details show if grout is required under columns along one drawing or more. The framing elevation shows the position
with grout thickness and anchor bolt projection. Adherence to and part numbers of girts, eaves struts, bracing and sag rods.
anchor bolt setting tolerance is important and shall not exceed The sheeting elevation shows the panel positions with length
the deviation laid down in the standards. and part numbers. Eave trims, gutters and downspouts are
shown with part numbers. Standard details are included which
II. Roof Framing Plan
indicate the number, size and position of fasteners and other
The roof framing plan shows the purlins, bracing and trimming details. End-walls are detailed similarly.
miscellaneous details. Part numbers for purlins and bracing are
shown, also sag rods (where applicable), and strut tubes etc. VI. Other Drawings
The drawings should be studied very carefully otherwise it is Other drawings may include crane beam layouts and details;
quite possible to overlook critical details such as nested purlins, Mezzanine layouts and details; Accessories such as Sliding
strut purlins and strut clips. Doors, Roll-up doors, personnel doors, windows, louvers and
ventilators.
30
Part 2 - Metal Building Erection
31
6
Foundation and Anchor Bolt
If the foundation has been poured, check to see that it is square After setting the angle between two lines, measure distances
and level. If the floor slab has not been poured, check all and establish reference pillars as per grid lines given in the
elevations for column and post locations. Concrete should be drawing and close the transverse to confirm the correctness.
chipped or grouted where necessary to provide a level surface Same above procedure is to be followed at other corners of bldg
at the required elevations and establish reference pillars and mark centre lines of
remaining pedestals as per sketch given below. After marking
Guidelines for Setting of Anchor Bolts centrelines of all pedestals check diagonal between individual
• Anchor bolts shall be set in accordance with Tata BlueScope pedestals and anchor bolts.
Steel issued 'FOR CONSTRUCTION ANCHOR BOLT PLAN'.
• Finalise the FFL with the client or Consultant. Normally FFL is
X Y Z
bottom level of column base plate, in some cases it changes
as per customer requirement. 3 4 5
• Concreting has to be done finally 25 mm below the FFL level
6 8 10
(or as specified in civil drawing). This margin is for levelling
and grouting purpose. 9 16 25
• Establish the reference pillars at 3m away from intersections
of axis and grid lines at all four sides. Top level of reference
pillars should be kept 150 mm above the FFL. (Please refer
sketch)
• Mark the grid lines as indicated in AB setting plan on the
reference pillars and check whether foundation is square.
Squaring can be done by following methods. C. Theodolite Method
Buildings larger than 30m wide and 50m long should be squared
A. Diagonal Method
with the help of theodolite. Be sure to check condition and
The method is used when building width and length is less then
calibration of theodolite. Set the theodolite over corner
25 m or when diagonal of total building can be checked by
intersecting reference pillars. Sight along the building line mark
single measuring tape. In this, centre lines of four corner
on the reference pillar; swing theodolite through 90 degree to
pedestals can be marked by calculating diagonal length as per
establish adjacent building line and mark on reference pillars.
drawing. Diagonal 'A' and 'B' should be equal to calculated
Similarly shift theodolite and mark other lines on reference
length as per drawing. Tie the piano wire or thread on the
pillars.
reference pillars at all four side and mark the internal pedestal
1. Ensure rigidity of shuttering and reinforcement and make
centre line as per bay spacing given in the drawings.
sure cover blocks are in place.
B. Right Angle (3 - 4 - 5) Method
2. Place the anchor bolts in respective templates. Mark
The method is used when building width is less than 30m and
centrelines on template
length is less than 50m. In this case angle between two lines can
3. Check the level and projection of threaded portion of anchor
be set by chart given below. Mark a distance “x” along width and
bolts; it can adjusted by adjusting nut below and above the
distance “y” along length of building. Adjust two lines such that
template.
diagonal distance between points equal 'z' .Refer table.
32
Part 2 - Metal Building Erection
33
7
Material Management at Site
All materials are carefully inspected and crated before leaving materials to clarify name of project, location, building
Tata BlueScope Steel plant and accepted by the transportation number, type of materials, quantity, date of delivery, etc.
company as being complete and in first class conditions. It is the 3. Upon arrival of materials at the storage yard, the Builder's
carrier responsibility to deliver the shipment intact. material controller will match delivery notes and shall verify
It is the consignee responsibility to inspect the shipment for loss, the consignment. The material controller, then, reports to the
damage and shortage when it is delivered. Instructions for mate- site supervisor the received material list and quality
rial inspection and handling any resultant claims for damages or condition.
losses are thoroughly covered in a check sheet located in the 4. There should be an Appointed Person by Builder who will be
same packet containing the shipping manifest. having overall control of all lifting operations on site and the
Appointed Person must ensure that everyone in the crane
Handling and placement of material will vary according to size,
team has studied this manual and is aware of the correct
site conditions and equipment available. Whenever practical,
procedures to adopt in the cases not covered by this
located and stored in and around the building site where it is to
manual.
be used.
5. Planning the Lift
For example:
Planning the lifting operation is essential to ensure that the
- Rigid frame columns can be laid in position for raising;
lift is carried out safely and efficiently. The following points
- Roof beams / Rafters can be stacked for subassembly at
must always be considered:-
locations accessible for setting;
• Where the load is to be picked up from
- Secondary structural and braces can be divided and
• Where the load is to be placed
located according to requirement of each bay.
• What areas are to be passed over
Access area is plan such that crane / equipment can be fully
• Proximity of the other contractors workers
utilised and down time kept to a minimum. Most builders find it
• Any obstructions in the way
advantages to leave an access area at one end of the
• How the load is to be slung
building and running the full length of the building for
• How the slings are to be removed
maneuvering erection equipment.
• How the crane driver will be directed
Material that will not be used during the erection of the framing
• The weight of the load
should be stored in area that offer protection from physical dam-
• The weather
age and covered to provide protection from the weather.
6. The Lift
The Procedure
a) Before Lifting
1. Shipping department shall give the Product Consultant /
Only authorised slingers / signallers should sling the loads.
Builder sufficient advance notice for all site deliveries to
After slinging, but before lifting, the following must be
ensure there is a plan for unloading, so that Product
considered:
Consultant / Builder can mobilise suitable crane and
• Are the slings undamaged and properly attached to the
manpower for unloading of material.
load?
2. A delivery note is always enclosed with the supplied
34
Part 2 - Metal Building Erection
35
c) During the Lift e) After the Lift
The load can now be lifted and moved to its landing area.
Take care with bundles of tubes and similar items as they
While in the air avoid:
can collapse when landed, and pipes can roll, so make sure
• Passing over personnel working on the site suitable blocks are used to prevent this from happening.
• The public
• Power lines
• Projecting scaffolding
Make sure that all personnel are clear of the load moving path.
Never drag chains from beneath the load and jump down
from the moving trailer.
Do not stand where
a moving load could trap or crash you 7. Webbing slings, or any sling made from synthetic fibres,
should be examined before and after every lift as they are
d) Landing the Load vulnerable to being cut by sharp edges. If there is any sign
of a cut or fraying in the fabric, they should be taken out of
The load should be landed gently to ensure that it is not
use and examined by a competent person.
damaged, and that the crane does not receive any shock
loading. 8. All materials received onsite shall be visually inspected by
Before landing the load, check that; the site supervisor for any damage. Material Inspection
• The landing area will take the weight of the load
• There is sufficient space for the load
• There are strips of timber or similar supports on which to
land the load such that the slings can be easily removed by
hand.
The signaller must ensure that he is in a place of safety
when receiving the load, ensuring that he cannot be crushed
Report should
between the load and a fixed object or pushed over an open
be sent to HO / Factory on the same day.
edge.
Remedial works to the damage shall be undertaken
immediately, if possible, to avoid any delay to erection.
36
Part 2 - Metal Building Erection
Material Storage
1. Choose a firm and dry area for storage. distortion. Incorrect handling may break crates and
materials particularly sheeting may become beyond use..
2. The material shall be stored above ground level with timber
packing.
37
8
Frame Erection Procedure
Generally, most structures follow a basic sequence of erection shall be left in place as long as may be required for safety.
that enable you to utilise personnel and equipment as effective-
Where ever piles of material erection equipment or other loads
ly and efficiently as possible. For example, after several bays
are carried during erection, proper provision shall be made to
have been erected and plumbed and squared, work crew can
take care of stresses resulting from such loads.
start on other phases of the erection simultaneously as the fram-
The structural frames and other parts of the building can be
ing progresses; overhead and sliding door may be installed; side
erected in various ways which will depend on the following key
wall and end wall panels can be applied after several bays are
factors:
completed; overhang canopies and fascia can be installed after
• The type of structures such as: small clear span, large
the wall panel are up; roofing crews cab follow.
clear span, low rise building, high building, o p e n - w e b
Pre-lift checklist and Meeting structure, etc.
The required material, accessories, crane, tools, tackles and • The availability of equipment such as cranes, winch,
safety equipments shall be checked for availability at site and manually lift, etc.
ready to be used prior to starting of lift.
• In case of long rafters / members spreader bars multiple
A pre-lift meeting shall be held before lifting any structure to cranes should be used
ensure everybody at site understands the lifting method or step • The site conditions.
for the erection of the entire building. The Project Manager / • The experience level of the erectors
Product consultant of BSBS shall check details of the specifics
given in the check list attached in the annexure. Step 1 - Anchor bolt checking
Check the anchor bolt casted for compliance with details
Framing Sequence - provided in Anchor bolt setting plan. Check whether
The general sequence of framing is as follows: concerned template goes freely into bolts. If not, make the
1. The brace bay closest to the endwall, standard location for bolts vertical with the help of pipe without damaging the
brace rods is usually the first interior bay. Be sure to refer to treads of anchor bolts. This pre check is required to avoid
your erection drawings for specific bracing requirements. time lost during the actual correction.
until the structure is completed. shim packs are placed in the centre of bolt pattern. Buildings
without crane system generally do not require grout, but
Note: temporary bracing shall be introduced wherever necessary
variances in concrete levels may necessitate the use of
to take care of all loads to which the structure may be subjected,
shims. Level the base of RCC pedestal by keeping required
including equipment and the operation of same. Such bracing
shims, check the level with Dumpy level. Top level of all
38
Part 2 - Metal Building Erection
shims should be at same level. Shim plates should be repeating Step [2], Step [3] and Step [4].
39
• 50 mm thick wooden block to be used to support
members for assembling.
• Torque wrench to tighten hi-strength bolts with minimum
recommended torque (lookup in the torque table for
Hi-strength bolts.)
40
Part 2 - Metal Building Erection
41
• Temporary bracing at every 6m to hold the first rafter on Step 8 - Finish 100% the first braced bay
2 sides to anchor bolts groups by V shape cleats or any
1. Fully install struts, purlins, fly bracing - 100%
other immovable object
• Crane to pick up struts to roof.
• Release the crane slightly to check the stability of rafter
• Rope with safety-lock hook to pull up purlins
before fully releasing the crane.
manually.
• Sash socket spanner for M12 with normal torque.
42
Part 2 - Metal Building Erection
• Rafter can be aligned by loosening and Tightening cross the bolt remains in the same hole in which it was
43
1. The following figures show the allowable sequence for 2. Each part of the structure shall be aligned as soon as
bolt tightening at any joint. practicable after it's erection. Permanent connections
2. The tightening work shall be implemented in two rounds, shall not be made between members until a sufficient
the second being done to ensure all bolts are equally part of the structures have been aligned, leveled, plumb
stressed. and temporarily connected in such a manner that the
members will not be displaced during erection and
3. Allowable torque for bolt tightening and inspection
alignment of the remainder of the structure.
4. In the completed connection, all bolts shall have at least
the minimum torque applied on specified below when all
bolts in the bolt group are tightened.
c) Alignment Check
1. It is the responsibility of the team leader to do the
alignment inspection for 100% of the structure members
while the site supervisor needs to do the re-inspection
3. Tighten all anchor bolts
and officially report for one main frame and two end
frames. 4. Install the first rafter member to columns
• Attach fly bracing to rafters.
• Attach pipes D50 x 2 mm x 2 M and safety static
lines to rafters. Two pipes fixed to in-flange and
out-flange of rafters, one at 1m distance from eave
and the other right at top ridge of rafter end, this pipe
on top is used for both roof slopes. Static lines are
fixed from pipe to pipe by brackets at 800mm height
level from out flange.
44
Part 2 - Metal Building Erection
45
• Use abrasive paper and cloths to clean and touch • Scaffolds setup at each column.
up. • Tighten anchor bolt nuts.
• Lift the first rafter member into position at the top of • Plumb-line and take measurement.
column, hold rafters in place with crane. 3. Tighten all anchor bolts
4. Install the first rafter member to columns
• Attach fly bracing to rafters.
• Attach pipes D 50 x 2 mm x 2 M and safety static
lines to rafters. Two pipes fixed to in-flange and
out-flange of rafters, one at 1m distance from eave
and the other right at top ridge of rafter end, this pipe
on top is used for both roof slopes. Static lines are
fixed from pipe to pipe by brackets at 800 mm height
• Workers on scaffolds at columns to tighten bolts at
level from out flange.
rafter-column connection plates.
• Use abrasive paper and cloths to clean and touch
• Install 50% purlins lines from ridge to eave to hold up.
rafter in place.
• Lift the first rafter member into position at the top of
• Rope with safety-lock hook to pull up purlins column, hold rafters in place with crane.
manually. • Workers on scaffolds at columns to tighten bolts at
• Sash socket spanner for M12 with normal torque. rafter-column connection plates.
• Release the crane slightly to check the stability of • Install 50% purlins lines from ridge to eave to hold
the rafter before fully releasing the crane. rafter in place.
• Rope with safety-lock hook to pull up purlins
STEP 11 - Install all remaining columns, rafters
and roof purlins manually.
• Sash socket spanner for M12 with normal torque.
1. Install all side and internal columns and Girts at line 4, 5
and 6. • Release the crane slightly to check the stability of
the rafter before fully releasing the crane.
2. Adjust alignment, position and level
• Scaffolds setup at each column.
• Put shims under the base plates as required and
tighten the anchor bolt nuts.
• Plumb-line and take measurement.
3. Repeat the same [step 6] and [step 7] for all rafters and
roof purlins
46
Part 2 - Metal Building Erection
Final Inspection
1. The draft final inspection shall be done between the
Product consultant and Builder to ensure the quality
compliance and planning for repair, clean and touchup.
The record must be signed-off and documented as a part
of contract.
2. The official final inspection shall be completed with a
witness of client's representative. The record must be
signed-off and documented as a part of the contract.
47
MRF Buildings
4. Install temporary bracing. And then release the crane.
For MRF buildings repeat Step - 1, Step - 2,
Step - 3, Step - 4 and Step - 5 given in Step - 8 Erect the rafter 2C
the LRF structure. Attach temporary bracing at every 6m on both the sides and then
Step - 6 Install central columns C2, C3 and release the crane.
central rafter
Step 9 - Erect the rafter 3C
1. Install columns C2 and C3 and tie column with temporary
1. Install all the purlins and fly braces.
bracing.
2. Install rod bracing
2. If possible, assemble central rafter piece and column on 3. Release the crane.
ground and then erect.
3. Erect central rafter piece 2B on column C2. Tighten the Step - 10 Erect the rafter 2A and attach
anchor bolt. temporary bracings
4. Tie the rafter with at least 6 temporary bracings on both Step - 11 Erect the rafter 3A and install purlins
the sides.
5. Release the crane slowly to check the stability of rafter. Step - 12 Finish 100 % of the braced bay
48
Part 2 - Metal Building Erection
49
50
Part 2 - Metal Building Erection
51
52
Part 2 - Metal Building Erection
Purlin
Simple span purlin connection - when simple span purlin are
used, purlin clips are used at purlin - to - roof beam connections.
Clips may be preassembled to the purlins before installation
Girts
Simple span girts terminate at the centreline of the columns and
attach directly to the columns. Continuous girts are assembled to
the columns in the same manner as continuous purlins to the
roof beam. Adjacent ends of girts must be lapped and bolted to
the columns at the same line.
53
End Wall Erection Field notch end-wall girt at corner post location and connect
Beam and post endwalls can be erected in sections preassem- between corner post and end wall post girt clip. Intermediate
bled on the ground including posts, roof beams sections, and Girts do not require cutting.
girts. Because of common connections between sections, Attach roof beam sections between posts. A clip is used to attach
reassembly is usually limited to alternating sections. the roof beam to the corner post and a splice plate at inside post
Layout the structurals in the relative position in which they will be connections. If double end-wall posts are used, the splice plate
assembled. is not required.
Raise the corner endwall section into position and hold in place
with crane until secured to the foundation and sufficient second-
End wall posts may be either single sections or double sections ary structurals are installed to stabilise the sections.
(two post bolted back to back). If double post construction is
Install sidewall girts, eave struts and purlin.
required, bolt these sections together first.
Finish the endwall by raising alternate sections and filling in
Attach girts clips to endwall posts.
secondary structurals and roof beam sections.
54
Part 2 - Metal Building Erection
Erect the intermediate rigid frame at the endwall location and fill
in secondary structurals.
Preassembled base clips, girt clips and clips for attaching end
55
Purlin clips to purlins bracing connections are shown below and it will be necessary to
Purlin clips are used to attach the purlins to the endwall roof refer to the erection drawing for specific location and application
beam. The clips can be pre-assembled to the roof beam before of these components.
raising the end wall sections.
If the building has a flat roof beam section the purlin clips loca-
tions on the endwall roof beam is varied to maintain the proper
roof slope. Clip locations are determined from the erection
drawings. ALTERNATE ATTACHMENT TO COLUMN
Complete bracing Brace rod are required in the sidewall and roof at braced bay
Proper use of bracing is extremely important in the structure to locations. Endwall bracing in used only at beam and post end-
provide strength and rigidity and for frame alignment. Typical wall locations. They are not required with intermediate frame
endwall.
Alternative attachment at column
56
Part 2 - Metal Building Erection
Flange brace assembly Gable angle may require filed cutting at the ridge in which case
the cutting dimensions will be indicated on the gable angle erec-
tion drawing.
57
necessary because of design requirements or to satisfy local The adjacent sag angle is used between the eave strut and first
building code, sag angles are optional and furnished with the purlin. This angle bolt to the web of the eave strut and threaded
building as ordered. rod on the opposite end passes through the purlin web. Two
nuts, one located on each side of the purlin web, are adjusted to
As a general rule sag angle is installed at the top location on the
pull the eave member into alignment with the purlin.
Purlin when ordered for erection alignment of roof structurals
and in the bottom location when required for bracing. Start the On building with a width extension or canopy, a sag rod is used
sag angle installation at the ridge and work towards the eave. instead of a sag angle between the eave strut and the adjacent
canopy or width extension purlin. The two nuts at each end of the
sag rod are adjusted to align the purlin with the eave strut.
The ridge sag angle bolts between the ridge purlins and must be
installed so the short leg of the angle is always at the bottom.
Intermediate sag angle are installed by inserting the tab on the
end of the angle into the slot in the web of the purlin and bend-
ing the tab to lock the angle into position. Tab may be bent down
with a hammer. If the sag angles are installed in the top of the
purlin, the leg of the angle and the tab should face downward. If
the sag angle are located in the bottom of the purlin, the leg of
the angle and bent tab should face upward.
58
9
Part 3 - Sheet Installation
• Erect scaffolds with handrails, midrails and platforms. They closure only and is not effec-
shall be supported from falling by pipe D50 x 2mm x 6M to tive where a light - tight condi-
ground. The scaffolds shall be tightened on the top to the tion is required or where con-
• The scaffold system shall be used to install all the items on Foam closure: a foam closure
the wall cladding completely such as girts, wall sheets, can be used in lieu of or in addi-
gutters, down-pipes, louvers, doors, windows, etc. which tion to the metal base flashing to
are above 2 m from the ground. They can only be moved effect better light or air closure.
after finishing the installation for above items at the area. The closure is not opaque so
complete light closure should not
• Another scaffolding system should be setup ready for the
be expected.
next walling area so that the installation will not be
interrupted due to the movement of the scaffolding system.
• Workers shall directly attach the safety harness to the
scaffolds or handrails.
59
Notched foundation: a Installation of Roof Panels
notched foundation edge may
Pull Up the Roof Sheets to Roof
be used in lieu of or in addition
1. Fix the anchor pipe to ground
to either closure method to pro-
vide a base of wall closure. • Anchor pipe D 50 x 2 mm, 500 mm long fixed at a 300 mm
depth into the ground at parallel 6m distance from each
Before installing insulation / other, and at 45 degree angle opposite to the building
wall panels, level the girts with
• Turn buckle attached to the top end of the anchor pipe
the wooden blocks. Keep the blocks until the panels to structure
fasteners are installed. The general practice is to install the wall
panel in sequence with the insulation. Align the first panel with
building structural as shown below. Apply the panel over the
insulation and drill required holes in the structural members for
the self-tapping screws. Install the wall panel fasteners and
remove clamps. Trim excess insulation and raise the next pre-
cut run of insulation.
It is extremely important that the first wall panel be installed
plumb. Use a spirit level or transit on each panel.
Adjoining panels are installed with overlapping rib toward the last
erected panel. Position panel to structural making sure that it is
kept plumb. Drill structural members if required and install fas- 2. Install the anchor pipe and static line on the rafter
teners at lapped rib. Use a chalk line to mark the girt location and
• Pipes D 50 x 2 mm x 5 M fixed to the out-flanges and
maintain a straight line of screws, thus avoiding mis-drilling and
in-flanges of the end rafter at a spacing of 6m from each
possible leakage. The preferred procedure is to complete all wall
other and aligned with the anchor pipes on the ground
sheeting before starting the roof sheeting, for smoother fixing of
• Static line to be fixed from pipe to pipe by brackets at
eaves flashing, closures and eaves gutter.
800 mm height level above the out-flange of rafters
60
Part 3 - Sheet Installation
alignment for the ridge panel. Check for the proper coverage as
the sheeting progresses. One can follow the panel-sheeting as
good visual tightness check. Always use the proper tool to install
shown below.
fasteners. A fastener driver (screw gun) should be used for self-
drilling screws. Discard worn sockets, these can cause the fas-
tener to wobble during installation.
When lifting sheets onto the roof frame ready for laying and fas- Preparing the Eave
tening, care should be taken to make sure all sheets are the cor- Prepare the eave for the first panel by applying tape mastic
rect way up with the overlapping side towards the edge of the along the eave (outside of the insulation, if any) and leaving
roof from which installation will commence. Otherwise, sheets release paper in place. Mastic must be applied in a straight line
will have to be turned over and/or turned end for end. Sheet bun- and with out voids.
dles should be placed over or near purlin supports, not at mid
Do not stretch the mastic. Use a knife to cut if necessary. Cut an
span of the purlins.
inside closure strip as shown above and place starter piece on
Fastener Installation top of the mastic. Align the major rib of the closure with the edge
Correct fastener installation is one of the most critical steps of the endwall roof line. Splice a full closure to the starting clo-
when installing roof panels. Be sure the fasteners are installed at sure and apply along the top of the eave mastic.
61
purlin location and maintain straight line of screws, thus avoiding
mis-drilling and possible leakage. Secure the panel to the struc-
ture with appropriate fasteners. If the building requires more than
the one panel per run, do not install fasteners at the purlin locat-
ed at the upslope end of the panel. These fasteners will be
installed after the overlapping is installed.
press firmly along the length of the mastic to insure proper adhe-
sion. In removing the protective paper from the mastic, care
should be taken not to pull the mastic away from the panel.
Install the adjoining panel positioning the overlapping rib with
care. Drill, at the center of the clearance holes in the overlapping
panel, required size pilot holes for the lap fasteners. Stitch the
lap with the self-fastening fasteners supplied with the screw line.
Never allow the mastic to be placed to the inside of the screw
line.
62
Part 3 - Sheet Installation
Skylight Installation
One of the simplest methods of getting natural light through a
steel roof is the inclusion of translucent sheets which match the
steel profiles.
It is preferable to use profiled translucent cladding in single
widths so that they can overlap, and be supported by, the steel
overhang and panel coverage. Stitch the major ribs of the two
cladding on both sides. It is also preferable to position the
panels together and attach panels to the purlins.
lengths of translucent cladding at the top of a roof run so the high
Sealing the Eave end can lap under the capping or flashing and the low end can
Mastic location at the eave is critical. To insure a weather tight overlap a steel sheet. This is because the translucent cladding
seal, the sidelap mastic must extend down from the top of the rib will readily overlap a steel sheet but the reverse is difficult.
to the mastic on the eave closure. The mastic extension must Skylight panels are also installed using the same procedures as
splice into the eave mastic. a steel panel (Subjected to skylight manufacturers
recommendations). Care should be taken when installing
fasteners in the skylights to avoid cracking the material.
Ridge Installation
Ridge panels are to be installed as each side of the roof is sheet-
ed. This will aid in keeping both sides of the roof aligned. After
having installed a run of panels on each side of the roof, apply
mastic to the panels. Set ridge panel in place and install lap and
purlin fasteners. Apply mastic along the top of the leading rib to
prepare for the next sidelap.
Sealing the endlaps
At the panel endlaps, place a run of mastic across the full panel
width 25 mm below the fastener line. The panel endlaps have a
63
Tape Sealant Application at
Ridge Flashing
Apply panel sidelap tape sealant as shown for building with ridge
flashing and outside closures. The mastic is placed along the
inside edge of the major rib from the ridge purlin web line to the
upper end of the panel.
64
10
Part 3 - Sheet Installation
however, to maximised watertightness, always place roof screws Prevailing weather Direction of laying
through the crests. For walling, you may fix through either the Lay sheets towards prevailing weather
crest or valley.
Place bundles of sheets over or near firm supports, not at mid
Always drive the screws perpendicular to the cladding, and in the
The following procedures are described for roofs, but the same Position first sheet
general principles apply to walls. With particular care, position the first sheet before fixing
to ensure that it is correctly located in relation to other parts
General installation procedure of the building. Check that the sheet:
Crest fixing Valley fixing • Is aligned with the end-wall (or its barge or fascia),
bearing in mind the type of flashing or capping treatment to
(roofs & walls) (walls only)
be used; and
• Aligns correctly at its ends in relation to the gutter
Crest and valley fixing
and ridge (or parapet or transverse wall). Roof sheets should
overhang at least 50 mm into gutters
Fix the sheet as described later in this chapter
65
Check alignment occasionally • clamp theORB
CUSTOM laptowith
steela support
pair of vice grips;
Occasionally check that the sheets are still parallel with the first • at the top of the sheet: nestle the side lap snugly,
sheet, by taking two measurements across the width of the fixed check alignment, and fix the sheet with a fastener.
cladding.
At about half way through the job, perform a similar check but TRIMDEK HI-TEN to timber support
take the measurements from the finishing line to aim for the final
CUSTOM ORB to
Typical also of steel support
INTEGRITY (see detail)
• fix the other edge of the sheet, placing the fasteners slightly Sealing
Pierce-fixing onRoofing
valleys
Detail of INTEGRITY
was no error.
connection Adhesive layer on
After fixing the first sheet, place the next (and subsequent) Typical valley fixing (for walls only)
sheet with its side lap snugly over the previous sheet. Secure the
sheet firmly in place until each end of the sheet has been fixed.
You can do this easily by: However, when valley-fixed, the cladding needs a side-lap
• align the bottom edge accurately by a measurement from the fastener in all laps, at each support. You will find it more
end of the sheet to the fascia or purlin at the gutter; economical in labour, time and cost of fasteners to use a crest
66
Part 3 - Sheet Installation
fastener at each side lap in place of the lap fastener and adja-
cent valley fastener.
Alternative valley fixing with crest fixing at side laps (for walls only)
Pierce-fixing on side-laps
67
11
Installing concealed-fixed cladding
Concealed-fixing is the method of fixing sheets using fasteners Preparation
which do not pass through the sheet. Instead, the cladding is As described in General installation procedure:
held in place with clips. This is different from the alternative • check flatness, slope and overhang;
method called pierce-fixing. The method of fixing you use is
• orient the sheets before lifting. Note the overlapping rib
determined by the cladding profile you are using.
is towards the end of the building where you start;
Concealed-fixing is used for: • Check that the overhang of the sheets from the clips,
• KLIP-LOK™ 700 at both eaves and ridge, is not less than the minimum
• KLIP-LOK™ 770
Position the first sheet
Very steep pitches With particular care, position the first sheet before fixing,
to ensure that it will correctly locate in relation to other parts
To prevent concealed-fixed cladding from sliding downward in
of the building. Check that the sheet:
the fixing clips, on very steep pitches, you should pierce-fix
through each sheet under the flashing or capping, along the top • is aligned with the end-wall (or its barge or fascia),
of the sheets. bearing in mind the type of flashing or capping treatment
to be used; and
Installing KLIP-LOK™ roofs • aligns correctly at its ends in relation to the gutter and
ridge (or parapet or transverse wall). Roof sheets should
Use the same general procedure described in general
overhang at least 50 mm into gutters.
installation procedure. However, at the start of installing
KLIP-LOK™ 700 and KLIP-LOK™ 770, a row of clips is fixed to Fix the first clips
the supports before the first sheet is located over them and KLIP-LOK™
locked in position.
Starting method 1. Cut the 1st clip 25 mm from the centre of the
Clips second tower (as shown). The first tower on the cut clip locates
For KLIP-LOK™ 700 use KL70 clips in the 1st rib of the first sheet. This method is preferred because
For KLIP-LOK™ 770 use KL77 clips you don’t have to reach so far to fix the remote end of the clip.
Starting method 2. The first tower on the first clip locates in the
first rib of the first sheet. The clip fixes the edge of the first sheet,
Fixing screw but you must fix two clips at the start, and thus reach out further
for the first and all subsequent sheets.
through each tower
Dir
The following description is for Method 1.
ect
iono
f la
yin
Fix the first clip on the purlin nearest the gutter, with the clip
KLIP-LOK 700
KL65 Using a string line (or the first sheet as a straight edge) to align
Dire
ctio the clips as you fix a clip to each purlin working towards the high
end of the roof.
n of
layin
g
KL65 fixing clip
for KLIP-LOK 406
68
Part 3 - Sheet Installation
Overlapping
rib
cut here
Discard
25 mm Underlapping rib
KLIP-LOK 700
Standard flashing
Standard flashing
Underlapping rib
1. FixKLIP-LOK
the next row
406 of clips, one to each support. Be sure the
KLIP-LOK 700HS: Starting method 2
& 700
KLIP-LOK 700
1. (KL65
Locateclips
the shown)
first sheet over the fixed clips
KLIP-LOK 406 & 700
fascia or purlin, position the sheet so that it overhangs the KLIP-LOK 700
straight line.
sheet must be fully engaged
the spur with a rubber mallet to allow the clip to sit down over
in shoulder of top sheet.
all KLIP-LOK™ profiles: Fully engage the sheet with the the rib
clips, using vertical foot pressure on all the ribs over each
2. As before, place the next sheet over its clips also engaging
clip.
the edge of the preceding sheet
3. Accurately
KLIP-LOKposition
406 the sheet so that it overhangs the
desired amount into the gutter. It is important that you keep
69
the gutter-end of all sheets in a straight line Place the last sheet
KLIP-LOK™ 700: If the final space is less than the full width
4. Fully engage the two sheets along the overlapping rib.
of a sheet, you can cut a sheet along its length and shorten
You can do this by walking along the full length of the sheet
the clips as appropriate.
with one foot in the centre pan of the previous sheet and the
other foot applying vertical pressure to the top of the
interlocking ribs at regular intervals. It is important that you Installing KLIP-LOK™ walls
don’t walk in the unsupported pan beside the overlap. A The installation procedure for walls is similar to that described
rubber mallet may help engagement of laps on long spans for roofs. To engage clips, use a rubber mallet (instead of foot
pressure to the top of the other ribs over each clip. To prevent KLIP-LOK™ from sliding downward in the fixing clips,
It is essential that the sheets interlock completely. It is important you should pierce-fix through each sheet under the flashing or
that your weight is fully on the sheet you are installing. capping, along the top of the sheets.
At about half way through the job, perform a similar check but
take the measurements from the finishing line to aim for the final
sheet to be parallel with the end of the roof. If the measurements
are not close enough, lay subsequent sheets very slightly out of
parallel to gradually correct the error. To allow this to happen,
flatten the tabs on the base of subsequent clips - the slot in the
clip will allow the clips to be fixed out of standard pitch.
70
12
Part 3 - Sheet Installation
End of Sheets
This chapter describes how you can treat the ends of sheets to Turning-up KLIP-LOK™
maximised waterproofing, or to stop vermin entering. You get the best results by first cutting off the corner of the
down-pointing leg of each female rib. Do this before you place
Turn-ups the sheets on the roof.
At the high end of roofing, wind can drive water uphill, under the
• With the hinged turn-up tool open: position the tool on the
flashing or capping, into a building. To minimise this problem,
sheet with the locating pins hard against the end of the
you turn up the valleys (or pans) at the high end of roofing. The
sheet.
process is called turning-up (or stop-ending).
• Hold the handles together to clamp the tool onto the tray, and
All roofing on slopes below 1 in 2 (25°) should be turned-up.
pull them to turn-up the tray 90°.
You can turn-up sheets before or after they are fixed on the roof.
If you do the latter, you must have sufficient clearance for the
turn-up tool at the top end of the sheets (about 50 mm).
Slide the turn-up tool onto the end of the sheet as far as it will go.
Holding the tool against the end of the sheet, pull the handle to
turn up the tray about 80°.
'Ear' flattened
'Ear' awaiting
flattening
71
usually of no consequence because the turn-up is completely SPANDEK® overlaps
covered by a flashing or capping. However, if you want the ribs When SPANDEK® is laid on slopes of 5 degrees or less, cut back
not to protrude past the turn-up, you can make a flush turn-up. the corner of the under-sheet, at the downhill end of the sheet,
You need an extra 40 mm in sheet length for flush turn-ups. to block capillary action.
1. Cut the top of each rib before turning-up the pans. Turn-up
the pans as described before.
2. Position the backing tool in the tray and hold it hard against
the turn-up with a foot. Approx. Approx.
5 mm 5 mm
3. With a rubber mallet, fold the protruding ‘ears’ flush against Cut back corner
Infill strips
Closed-cell, foam-plastic infill strips are available to match the
top or bottom profile of our roof cladding.
or capping.
72
Part 3 - Sheet Installation
processes, sheet lengths can be supplied up to the limits of See Table 10.4
transport regulations which are frequently long enough to cover
.1
• Concealed-fixed sheets
You can either pierce-fix through the crests or the valleys (in
Figure a and b), or use clips near the lap (in Figure c).
73
13
Flashings
Flashings and cappings are strips of metal formed to weather- Longitudinal flashings
proof the edges of roofing and walling. For the purposes of this Longitudinal flashings run parallel to the pans or valleys, and are
chapter, only the term flashing is used. made to suit the sheet profile. They should have an edge turned-
Similar methods of flashing are used for different cladding-pro- down to dip into the pan or valley.
files. You can adapt the principles to suit your application.
In all cases it is important to have ample cover provided by the
flashing and proper turn-up of the cladding underneath.
Be careful when moving between supports. Do not walk in the
pan immediately adjacent to flashings or translucent sheeting. Fix at 600 mm centres
Walk at least one pan away.
(See Chapter 3
for fasteners)
Materials
It is very important that flashings be made from materials that are
compatible with the cladding.
Typical longitudinal flashings
Lead flashing is not recommended, however it will usually be
retained when re-roofing, because it is usually cemented into the
Transverse
Soft aluminium orflashings
structure. In these cases:
Approx
zinc . 600 mm
Transverse flashings
to followrun across the pans or valleys. They
for all profi
over-flashing, stepped les
74
Part 3 - Sheet Installation
Flashings
The turn-down for transverse flashings for CUSTOM ORB® and
custom blue orb can be either notched, scribed to match the
corrugations, or lightly dressed into the valleys. Scribing or
Horizontal notching tool
(KLIP-LOK 406 shown)
Notching tools
(KLIP-LOK 406 shown)
• Repeat for all ribs, checking in each case that the flashing is
correctly positioned.
75
14
Insulation
There are many types of insulation installed in the steel build- It is recommended that both sides of the ridge of a building be
ings. However, fibreglass, rockwool blanket insulation is com- insulated and sheeted simultaneously.This will keep the insula-
mon type used, and these instructions pertaining to this type tion covered for the maximum amount of time and panel ribs can
only. One side of the blanket insulation should have proper bar- be kept in proper alignment for ridge cap.
rier that must face the inside of the building regardless of
whether the insulation is for heating or cooling.
76
Part 3 - Sheet Installation
Insulation
bottom girt. Cut the fibreglass from vapour barrier on excess
1.
length and fold up to seal the ends.
3.
4.
5.
77
15
General care, safety and
handling
Safety Handling cladding on site
It is commonsense to work safely, protecting yourself and work- On large building projects you can reduce handling time by lift-
mates from accidents on the site. Safety includes the practices ing bundles with a crane direct from the delivery truck onto the
you use; as well as personal protection of eyes and skin from roof frame. Use a spreader bar for long sheets. For small to
sunburn, and hearing from noise. medium size projects, without mechanical handling facilities, you
Occupational health and safety laws enforce safe working con- can unload sheets by hand and pass them up to the roof one
ditions in most locations. Laws in every state require you to have at a time.
fall protection which includes safety mesh, personal harnesses For personal safety, and to protect the surface finish, wear clean
and perimeter guardrails. We recommend that you aquatint your- dry gloves. Don’t slide sheets over rough surfaces or over each
self with all local codes of safe practice and you adhere strictly other. Always carry tools, don’t drag them.
to all laws that apply to your site.
Where possible do not leave If stacks cannot be kept under cover, When you walk parallel to the ribs:
uncovered stacks of sheets lying barricade the stack and cover it with
in the open. a waterproof tarpaulin, but leave
space between the cover and the
• for ribbed roofing walk on at least two ribs or
sheets to allow air to circulate.
corrugations (CUSTOM ORB®, and SPANDEK®);
• for pan-type roofing walk in the pans (KLIP-LOK™,
TRIMDEK®).
Store off the ground and on a slope Inspect the storage site regularly When you walk across the ribs, walk over or close to the roofing
so that if rain should to ensure that moisture has not
penetrate the covering, penetrated the stock. supports.
water will drain away.
78
Part 3 - Sheet Installation
Be careful when moving between supports. Do not walk in the Reciprocating nibblers are also widely used in the roofing trade,
pan immediately adjacent to flashings or translucent sheeting. and they produce an excellent cut. The resulting small, sharp
Walk at least one pan away. scraps can rust and damage finishes; and they can cause per-
sonal injury. Take special care to collect these scraps.
Always take particular care when walking on wet or newly laid
sheets - particularly on steeply pitched roofs. Making holes
If there will be heavy foot traffic on a roof, provide a temporary Holes are often made by drilling or cutting by hole saw or jig saw.
walkway or working platform to minimise damage. Mask the area around the hole to protect paint from damage by
swarf.
Never step on the Skylight panel or translucent panel.
Cutting
Where possible, you should minimise site-work by using sheets
cut to length in the factory. Swarf Cleaning
For cutting thin metal on • Sweep or hose all metallic swarf and other debris from roof
site, we recommend that areas and gutters at the end of each day and at the comple-
you use a power saw with tion of the installation.
a metal-cutting blade • If swarf has become stuck on a finish, it can be removed.
because it produces Take great care not to remove the paint or the metal coat-
fewer damaging hot ings.
metal particles and leaves less resultant burr than does a car- • For critical applications inspect the job two weeks after com-
borundum disc. pletion, when rain or condensation will have caused any
Cut materials over the ground and not over other materials remaining swarf to rust, and thus highlight affected areas.
where hot particles can fall and cause damage to finishes -
Warn other contractors
especially COLORBOND® steel prepainted finishes. It is best to
Many stains arising from swarf do so, not from the work of roof-
have the exterior colour finish of a COLORBOND® prepainted
ing-installers, but from other contractors working on the job.
sheet facing down, however you must then protect the paint fin-
Similarly, problems can arise from contact with incompatible
ish from scratching by your work supports.
materials, like copper piping or chemically treated timber. Acid
If you have to cut materials near sheets already installed, mask cleaning of bricks can also be a problem. Architects and builders
them or direct the stream of hot particles away. need to be aware of this, and warn contractors accordingly.
79
Sealants Seams sealed with sealant should be mechanically fixed for
Neutral-cure silicone sealants have been successfully used with than 50 mm.
the range of steel finishes on our roofing and walling; and on The sealant does not require significant adhesive strength in
flashings, cappings, and gutters made from the same materials itself, but it must bond positively to all the surfaces it is to seal.
as the cladding. To ensure complete sealant cure, the width of sealant in a lap
• have good adhesion to the clean surface of all our roofing Applying sealant
and walling;
Always apply the bead of sealant in a continuous line along the
• are water resistant and non-corrosive;
centreline of the fastener holes. This ensures that, when com-
• are resistant to extreme of heat and cold while retaining pressed, the sealant positively seals the fastener.
good flexibility;
Be careful not to entrap air when applying sealant. Especially,
• provide high resistance to ultra-violet rays (sunlight); and
don’t place a ring of sealant around fastener holes because
• have a long service life.
entrapped air compresses during tightening of fasteners, and
It is important that only neutral-cure silicone be used with sheet
may blow a channel through the sealant, which could prevent the
steel. Other silicone sealants, often have a vinegar or ammonia
fastener from being sealed.
smell, and give off aggressive by-products during curing which
are detrimental to sheet steel. Fasteners
If in doubt, look for a message on the sealant package like: Use solid or sealed fasteners, otherwise you have to apply
Suitable for use with galvanised and ZINCALUME steel products.
® sealant to the hollow centre of open blind rivets.
To preserve the life of your cladding, is very important that
Cleaning surfaces
fastener materials are compatible with the cladding.
For effective bonding, all surfaces must be clean, dry and free
from contaminants such as old sealant or oil. Procedure
The preferred procedure for lap fabrication is:
Mineral turpentine is suitable for cleaning the surfaces but care
must be taken to completely remove all residual solvent with a 1. Assemble, clamp and drill;
clean dry cloth. White spirits is an alternative. 2. Separate components and remove drilling debris;
Sealant must be applied on the same day as the surface is 3. Clean joint surfaces as recommended above;
cleaned. 4. Apply bead(s) of sealant;
Joint strength 5. Relocate components and fix;
Sealant 6. Externally seal each fastener if hollow blind rivets are used.
To prevent premature curing (which causes poor bonding), finish
25 mm max.
lowed.
Sealant clean up
Typical joints with sealant
80
Part 3 - Sheet Installation
With practice you will be able to judge the size of beads thus areas where high levels of industrial fallout occur. Avoid
avoiding squeeze-out and the subsequent need to clean up. accumulation of salty deposits or industrial dirt.
Uncured sealant can be removed with a clean, dry rag and any Establish a regular routine for washing COLORBOND ®
excess then removed with a cloth lightly dampened with mineral steel products. Often garage doors can be washed with clean
turpentine or white spirits. Excess cured sealant is best removed water at the same time as your car is being washed. Guttering
with a plastic spatula to avoid damage to the surface finish of and eaves can be hosed down when windows are being
the metal. cleaned. Walls can be hosed down while watering the garden.
Avoid any unnecessary smearing of sealant on
Where regular maintenance doesn’t remove all the dirt, wash the
surfaces intended for painting as silicone can affect adhesion of
surface with a mild solution of pure soap or non-abrasive non-
paint. Smeared sealant may be treated by lightly abrading the
ionic kitchen detergent in warm water. Use a sponge, soft cloth
area with a non-metallic scouring medium.
or soft bristle nylon brush; be gentle to prevent shiny spots.
Thoroughly rinse off the detergent with clean water.
Maintenance
81
16
Claims
B. Damaged Materials
1. Material damaged in transportation and unloading, which
cannot be rectified at site.
C. Detailing Error
1. Material mentioned in the drawing but not listed in the
shipper list.
rials cannot be defined as claims and will be treated as an order
2. There could be surplus or shortage in any item due to an
or straight sale.
error in preparing the shipper.
Cost of items lost or damaged due to irresponsibility of builder or
3. Missing holes / wrong location of holes on any member to
customer has to be borne by the concerned builder or customer.
connect other member.
82
Part 4 - Building Maintenance and Recommendations
Claims
All erection work will as per procedures mentioned in the Final claim: The final claim in writing shall be forwarded by the
American Institute of Steel construction code of standard prac- builder /customer to the Tata BlueScope Steel office within ten
tices for steel buildings. days of completion of corrective work authorised by Tata
BlueScope Steel office. The final claim shall include:
The correction of minor misfits by the use of drift pins to draw the
component into line, shimming moderate amount of reaming, 1. Actual numbers of man-hours by date of direct labour use
chipping and cutting and the replacement of minor shortages of on corrective work and actual hourly rates of pay.
material are a normal part of erection and are not subject to 2. Authorisation from Tata BlueScope Steel office for correc-
claim. tive work.
3. Taxes and insurance on total actual direct labour.
Claims for Corrective Repair Work
4. Other direct cost on actual direct labour.
In cases where installer believes there are errors in shop fabri-
cation that prevent the proper assembling and fitting of parts by 5. Cost of material purchased from other than Tata
use of drift pins, reaming, chipping or cutting the installer shall BlueScope Steel office including copies of main invoices.
immediately report to the local BSBS office or Product consult- 6. Total actual direct cost of corrective work (sum of 1, 2, 3,
ant for initial claim and 4) the final claim shall be signed by the builder.
Initial claim: In the event of error, the Builder / Customer 7. Cost of equipment (rental or depreciation), small tools,
shall promptly make a written “Initial Claim” to the Tata supervision overhead and profit are not subject to claim.
BlueScope Steel for correction of design, drafting or fabrica-
The Tata BlueScope Steel office is not liable for any claim result-
tion error. The initial claims include:
ing from use of drawings or literature not specifically released for
1. Description of nature and extent of the errors including construction for the project.
quantities, part marks etc.
Tata BlueScope Steel is not liable for any claim resulting from
2. Description of nature and extent of proposed corrective
use by the erector/customer of any improper material or
work including estimated man hours
material containing defects which can be detected by visual
3. Material to be purchased from the other than the Tata inspection. Cost of disassembling such improper or defective
BlueScope Steel office including estimated quantities and material and cost of erecting replacement material are not
cost. subject to claim.
4. Maximum total cost of proposed corrective work and
material to be purchased from other than purchased.
83
17
Tolerances
84
Part 4 - Building Maintenance and Recommendations
Tolerances
85
Built-up Structural Member
86
Part 4 - Building Maintenance and Recommendations
Span A = 9.52 mm 6 mm / 6m
Straightness B = 9.52 mm 6 mm / 6m
Elevation C = 9.52 mm 6 mm / 6m
Beam to
Beam Top D = 9.52 mm 6 mm / 6m
Running
Beam to
Beam E = 9.52 mm 6 mm / 6m
Underhung
Tolerances
Adjacent F = 9.52 mm 6 mm / 6m
Beams
87
Workmanship Accuracy Permitted Deviations of
of Erected Steelork Erected Components
Foundation Inspection Positions of column at base
The steelwork contractor shall inspect the prepared foundations Deviation of section centreline from the specified position
and holding down bolts for position and level not less than seven
days before erection of steelwork starts. He shall then inform the
employer if he finds any discrepancies which are outside the
deviations specified in this specification guide, requesting that
remedial work be carried out before erection commences.
Foundation Level
Deviation from Exact Level
Vertical Wall
Deviation from exact position at steelwork support point
88
Part 4 - Building Maintenance and Recommendations
Beam Alignment
Horizontal deviation relative to an adjacent beam above or below
Alignment of Adjacent Perimeter Columns
Deviation relative to next column on a line parallel to the grid
line when measured at base or splice level.
89
Built-up Structural Members
Tolerances
Dimensions
+ -
Geometry a 30 - 6.35 Max 30 - 6.35 Max
b 6.35 6.35
d 4.76 4.76
e 3.18 3.18
c D / 1800 mm
f D / 1800 mm
Hole Location E1 3.18 3.18
E2 3.18 3.18
E3 3.18 3.18
S1 1.59 1.59
S2 1.59 1.59
F 3.18 3.18
Length (L) 3.18 3.18
90
Part 4 - Building Maintenance and Recommendations
Minimum Thickness
42 4135 5880
91
18
Building Maintenance and Recommendations
A preventive maintenance program is a key factor in maximizing engineered steel buildings. We suggest that you develop a pre-
the life expectancy and dependability of the roof system. It is ventive maintenance schedule for your buildings based on the
important to carryout periodic maintenance of your building to guidelines given below and considering any special conditions
ensure trouble free service and extend the life span of the that are specific to your project.
92
Part 4 - Building Maintenance and Recommendations
gutters sand and dirt should be washed off with clean water a hose, including high ends of gutters possibly protected by
and a soft nylon brush. Clean from top to bottom and give overhangs, rain heads, water spouts and overflow locations.
a final rinse with water when completed. Ensure no water • If significant fungal growth is found it should be identified and removed.
is trapped anywhere. • Any metallic staining should be investigated to determine
4. If building is in an area of high industrial pollution or close to whether the cause is from a metallic deposit on the surface,
marine environment then water alone may not be enough. Salt or from the breakdown of the coating. Metallic deposits on
and other deposits build up at formed corners of panels and the surface should be completely removed immediately.
quickly breakdown the paint and zinc layers and finally corrode Breakdowns in the coating would generally result from poor
the base metal. As such deposits build up, the hardness of the maintenance techniques and scratching.
layers increases making removal more difficult. In these cases
Downtake Pipe Maintenance
the period between maintenance operations should be short-
The downtake pipes and stormwater disposal pipes are to be
ened and a mild detergent should be added to the initial wash-
inspected for cleanliness and free flow of water. Growth of fun-
ing water.
gus and other matter and collected debris at the inlet and outlet
Gutter Maintenance locations is to be noted. Complete testing of the system for
Twigs, dust, leaves and fungal matter (debris) should be blockage at each downpipe is recommended. Record and docu-
removed using the following recommended procedure, taking ment the observations of the inspections.
care to ensure no damage occurs to the gutter during debris • Downpipes made from BlueScope Steel products should be
removal. We recommend that the following procedure be adopt- cleaned using a pressure water hose directed down each of
ed to remove the dust, debris and fungal matter. the downpipes.
• The hose should then be fed into the pipe from the inlet down
to the outlet, to ensure there are no obstructions.
• Constrictions in the downpipe system may make it necessary
Building Maintenance
to access the pipe from inspection points downstream of the
downpipe inlet location.
A typical gutter clogged with leaf litter Wear correct protection when
prior to cleaning clearing leaves and twigs
• Any noted blockages should be removed immediately, to
avoid water back-up in the gutters.
93
• The area should then be washed down with a pressure hose. The following is suggested solution
Care should be taken to ensure that debris is not lodged a. 1/3 cup detergent (e.g. tide)
between sheets or the sheeting and flashing and that water
b. 1/3 tri-sodium phosphate(eg soilex)
from the pressure hose is not driven into the building.
c. 1 quart sodium hypochlorite-5% solution (e.g.chlorox)
• Stubborn stains and dirt not removed in the hosing can be
d. 3 quarts water.
removed by application of soaps and detergents which are
Wash down the panel with the above solution and soft nylon
detailed in this document.
brush. A final rinse with clean water should follow.
Roof Sheeting Maintenance
Caulking compounds, oil grease, tar wax or similar substances
All cladding are to be inspected for the deposition of any debris,
can be removed with mineral spirit. Follow this by cleaning with
dust, pollutants or organic growth. In particular, care is to be
detergent solution and clean water rinse.
taken in the inspection of cladding for these points:
AVOID SOLVENT AND ABRASSIVE TYPE CLEANERS AS
• Staining of cladding at possible ponding locations
THEY CAN DO MORE HARM THAN GOOD BY WEARING
• Build up of dust and debris
AWAY BOTH THE PAINT AND ZINC LAYERS
• Metallic staining of the gutter, surface rust
5. Check the base of wall panels to ensure the ground level is at
• Record and document the observations of the inspections.
least 11/2” below the bottom of panels. If wind blown soil has
Maintenance built up at the base of the wall, it should be removed. If
Twigs, dust, leaves and fungal matter (debris) should be plants/shrubs etc. are around the building, make sure they are
removed using the following recommended procedure, taking not touching the wall panels, particularly thorn-type bushes.
care to ensure no damage occurs to the cladding during debris
6. Check all equipment which is located through or adjacent to
removal. We recommend that the following procedure be adopt-
any panel (Roof or Wall). Ensure there is no moisture build up on
ed to remove the dust, debris and fungal matter.
or near the panel; if there is, then corrosion is inevitable. If this
• Sweep debris into a pile using a stiff, soft bristled brush condition exits, then modifications are required to avoid it.
(shovels or hard tools should not be used).
The following situations are examples of conditions to be avoided.
• Place debris into a receptacle and lower to the ground.
a. Water run-off from water services or air conditioners.
• The whole roof and gutter should then be washed down with b. Copper pipes fastened directly to the steel panel.
a hose, including high ends of gutters possibly protected by
c. Open water storage tanks or ponds adjacent to the
overhangs, rain heads, water spouts and overflow locations.
panels.
• If significant fungal growth is found it should be identified and 7. Standard gutter and valley gutters:
removed.
a. Regular checks should be made and all rubbish and
• Investigate metallic staining of the roof or gutter to determine sand should be removed.
if it is caused by a metallic deposit, or by breakdown of the
b. Flush the gutters with water.
coating on the cladding. If it is a metallic deposit, completely
c. Check the downspouts are clear.
remove it immediately.
d. Check the downspouts have adequate drainage away
Breakdowns in coating would generally result from poor mainte-
from the building.
nance techniques and scratching.
8. If minor damage occurs to the sheeting or trims and paint
94
Part 4 - Building Maintenance and Recommendations
touch is required, then the following procedure should be fol- c. Crane rails checking to be done every 3 months for the
lowed: weldments.
a. Abrade the effected area. d. End stoppers to be checked once every 3 months.
b. Clean down with a solvent (e.g. sigma 9053)
C.Safety Precautions
c. If base metal is exposed, apply one coat of zinc chromate
primer. If base metal is not exposed, then primer is not
Roofs
required. Extreme caution should be exercised when working on roofs:
d. Apply one coat touch up paint available from BlueScope a. Only use ladders which are long enough to reach one
steel. meter above the step off.
b. Always secure the ladder to the building and make sure it
B.Maintenance of Accessories is on a firm base.
Personal Doors c. Do not step on a skylight panels.
a. Occasionally lubricate the hinges and locksets. d. When walking on the roof, step on low corrugations,
b. Remove any dirt or grit from the threshold. walking on high corrugation can damage the sheets. Walk
on screw line wherever possible.
c. Make sure the door is not allowed to swing back against
the wall; this can spring the hinges, and damage the Overhead Cranes
panels. a. When maintaining overhead or associated parts, lockout
Sliding Doors the electricals on the crane before commencing work.
Regular cleaning of bottom door guide by removal of stones and b. After the days work, the overload crane should be placed
sand will ensure smooth running. always between the two rafters / truss i.e. never below a
rafter or a truss.
Roll Up Doors
Building Maintenance
c. Whenever the building is close to any road curve / access
a. Occasionally clean and lubricate and chain and reduction curve, “Ballard Foundation” should be provided to avoid
drive gears vehicle striking the building
b. Lightly grease the vertical guides
Power Vents
Periodically clean the blades to avoid build-up of dust and dirt.
Check electrical connections and check tightness of all
fasteners.
95
19
Annexure
Building:
Satisfactory
No. Items Type Qty. Position
Yes No
1 Anchor point of temporary bracings
2 Temporary bracings
3 Permanent bracings
4 Struts
5 Girts
6 Purlins
7 Fly Bracings
8 Alignment
9 Rafter & Column
10
11
12
13
14
15
16
17
18
19
20
Remarks / Proposals:
-The authorised person (Project Manager) must follow this braced framed checklist to approve and sign off before allowing the team to continue to install other
frames.
96
Annexure
Building:
Minimum No. of Bolts Satisfactory
No. Member No.1 Member No.2 Line Bolt Dia. Torque Required Inspected Yes No
Annexure
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Remarks / Proposals:
97
Frame Alignment Check
Project:
Building:
Satisfactory
No. Checked Points Line Deviation X Deviation Y Deviation H
Yes No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Remarks / Proposals:
98
Annexure
Building:
No. Description SWL Date of Testing Validity Test Certificate Calibration Certificate Identity Marks
1 Mobile Crane
Annexure
2 Hydra
3 Slings
4 D-Shackles
5 Double Hook Lanyard
6 Chain Blocks
7 Harness System
8 Torque Wrench
9 Fall Arrestor
10 Spreader bar
11 Temporary Bracings
12 Any Other
13
14
15
16
17
18
19
20
Remarks / Proposals:
99
100
Annexure
Annexure
101
102
Annexure
Annexure
103
104
Annexure
Annexure
105
106
Annexure
Annexure
107