86% found this document useful (14 votes)
17K views

Rate Analysis - Shuttering

The document provides a rate analysis for centering and shuttering work. It includes 3 items: 1) Material costs which accounts for steel plates, angles, bolts, and salvage value after use totaling Rs. 6251.81 per square meter. 2) Cost of using the material once which is Rs. 156.30 per use assuming the material can be used 40 times. 3) Labour costs of Rs. 449.67 per square meter including fitters, beldars, shuttering oil, overhead and profit. The total rate is Rs. 104.00 per square meter.

Uploaded by

d-fbuser-26913051
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
86% found this document useful (14 votes)
17K views

Rate Analysis - Shuttering

The document provides a rate analysis for centering and shuttering work. It includes 3 items: 1) Material costs which accounts for steel plates, angles, bolts, and salvage value after use totaling Rs. 6251.81 per square meter. 2) Cost of using the material once which is Rs. 156.30 per use assuming the material can be used 40 times. 3) Labour costs of Rs. 449.67 per square meter including fitters, beldars, shuttering oil, overhead and profit. The total rate is Rs. 104.00 per square meter.

Uploaded by

d-fbuser-26913051
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 1

Rate Analysis for centering & shuttering

Rate Amount
Sl. No. Description Unit Qty.
(in Rs.) (in Rs.)
Centering & shuttering with plywood or steel sheets including strutting, propping,
bracing bothways with wooden members and removal of formwork upto 4.50 mtr.
1 Height above ground level, for suspended floors, roofs, landings, staircase, balconies,
girders, cantilevers, bands, copings, bed plates, anchor blocks, sills chajjas, etc.

Unit = Sq.m.
Taking output = 1 Sq.m
A Material
Steel Plate 3.15 mm thick @ 24.73 kg/m2
(2.88x24.73) = 71.22 kg
Supporting Angle (35x35x5) @ 2.6 kg/m
kg 113.86 60.00 6831.60
(16.4x2.6) = 42.64 kg
Total Weight = 113.86 kg
(including welding, nuts & bolts ect.)
Add for maintenance @ 10 % 683.16
Cost of Supporting Material
Ballies 100 mm,75mm 3m long No 5 60.00 300.00
Total 7814.76
Less salvage value after full use of material @
20 % on A -1562.95
Total - Part A 6251.81
Assuming shuttering of material will become
unservicable after use of 40 times
Cost for using once Once 1/40 156.30
Carriage LS 15.00

B Labour
Fitter Nos 0.75 150.00 112.50
Beldar Nos 1.5 80.00 120.00
Shuttering oil LS 5.00
408.80
Add Overhead & Contractor's Profit 10 % 40.88
Total 449.67
Cost per Sqm 104.21
Say 104.00