Calculating Concrete Rebars Quantities
Calculating Concrete Rebars Quantities
Concrete Lecture
Footings Fnd / Slabs / Tilt ups
Ftg's & Fnd's
Modified 02-14-05
CSI Codes
03 20 00 Concrete Reinforcing
03 30 00 Cast in place Concrete
Even though the CSI codes do not breakdown concrete work any further into footing/foundation/slabs etc, we will break it down further for the assignement.
Rebar
Rebar Diameter in inches = Rebar Size /8 (For bar sizes 8 and smaller. For larger bars reference a table for the exact diameter.)
IE #4 Bar / 8 = 1/2" diameter
Lap
Suppose that you have 100' of footings with 2 runs of #4 rebar. The overlap is 30 bar diameter and the rebar comes in 20'pieces. What is the total LBs of rebar
for this footing?
First draw a picture of what the problem looks like that you are trying to solve.
____ ____ ____
------ ----- ---
Laps
To find out how much the laps add, take the number of laps * length of a lap.
The number of laps= total LF / length of the rebar pieces. 100'/20' = 5 laps
The length of the lap = Bar Diameter lap * (Rebar Size/8) /12 =
30 * (4/8) /12 = 1.25'
The length of the lap is often given in the Structural Notes. Sometimes, you may need to dig for the lap length. The following is an example of how to find the
lap length when it is not given easily in the structural notes.
First, in the Structual Notes on S-01 the following is given under Rebar Lap.
Now the Typical Reinforcing Bar Splice Detail needs to be found. It is found on Sheet S-03, which is still part of the Structural Notes pages.
http://www.et.byu.edu/groups/cmfac/miller/cm411/notes/ConcNotes/Concrete.html 1/9/2010
Concrete Lecture Page 2 of 5
From the above tables, first analyze are the bars in Tension or Compression. Footings are in Tension. Then, what is the PSI of concrete being used.
To find the PSI of concrete, refer back to sheet S-01, and the following is found.
All footings are 3000 PSI. Now refer back to the Typical Reinforcing Bar Splice Detail. Now the grade of rebar needs to be found. Referring back to S-01 the
following is found.
Since the rebar is larger than #4, grade 60 rebar is to be used. Now refer back to the Typical Reinforcing Bar Splice Detail and use the Notes in the detail to
determine the length of the lap.
Footings
Types of footings
Spread / Spot
Continuous
Grade Beams
Mat / Raft
Forming (SFCA)
Forming materials
2 x Lumber
Plywood
Symons
Gang
Slip
For this class, both sides of all footings and foundations must be formed.
To calculate the SFCA of the continuous footing forms = footing length' * footing height' * 2 sides. Assume the ends of the continuous footings continue on in
a footing of a different size.
100' * 12"/12 * 2 = 200 SFCA
To calculate the SFCA of the spread footing forms = ((footing length' + footing width') * 2) footing height'.
((5' + 5') *2) * 12"/12 = 20 SFCA
http://www.et.byu.edu/groups/cmfac/miller/cm411/notes/ConcNotes/Concrete.html 1/9/2010
Concrete Lecture Page 3 of 5
Placing
Placing costs cover the labor cost of getting the concrete from the truck to the location of placing the concrete. Many times the abbreviation of P/P/F
will be used for the description of placing the concrete. P/P/F means prep/pour/finish.
To calcuate the CY of concrete = (footing length' * footing height' * footing width' / 27)
(100' * (12"/12("/ft)) * 3') /27 = 11.11 CY
Pumping
When the concrete cannot be placed directly from the truck chute, a concrete pump or some other means may be needed to place the concrete. Other
methods of transporting the concrete from the concrete truck would include, a crane and a bucket, or a conveyor systems.
Foundations
To calculate the length of the Dowel, find the footing/wall height, then add half the width of the footing. This provides the approximate length of the dowel.
Step 1
Reference the footing schedule to find the width and height of the footing shown in the detail. For this example assume the width to be 30" and the height of 12"
for the footing.
Step 2
Calculate the height of the foundation wall. The section states that the footing must be a minimum of 2'6" below exterior finish grade. For this example, assume
that the exterior grade is 6" below the finish slab elevation.
Therefore the height of the wall is:
2' 6"
- 1' 0" Height of the footing
+ 0' 6" difference between exterior grade and Top of slab elevation
2' 0" Wall Height.
Notice in the wall section that the dowel does not go to the exterior surface of the concrete, therefore the concrete coverage needs to be subtracted
from the height of the wall. Three varying conditons for concrete coverage exist in this wall. Each condition is labeled with a red number above.
The following table taken from the structural notes describes the differing conditions.
http://www.et.byu.edu/groups/cmfac/miller/cm411/notes/ConcNotes/Concrete.html 1/9/2010
Concrete Lecture Page 4 of 5
OR
Condition 1
The top condition vertical component of the dowel is essentially a formed surface Exposed to outside weather requiring 1 1/2" of concrete coverage.
Condition 2
The bottom condition of the vertical component of the dowelis an unformed surface in contact with the earth so it requiring 3" of concrete coverage.
Condition 3
The horizontal end component of the dowel is a formed surface in contact with the earth requiring 2" of concrete coverage.
Step 4
The vertical length of the dowel becomes:
24" Wall height coverted to inches
- 1.5" Top concrete coverage
+ 12" Depth of footing
- 3" Bottom concrete coverage
31.5 "
Step 5
The horizontal length of the dowel becomes
30" / 2 = 15" because the dowel leg is only through half the footing.
Then
15"
- 2" of concrete coverage
13"
Step 6
31.5" + 13" = 44.5" or 3.708' Vertical + Horizontal components
Cost Adders
Anything not listed above will add cost to the work. Items to look for are: Waterstop, Keyways, Expoxy Rebar, Chamfer Strips, Blockouts, Haunches,
Architectural Finishes, Concrete Additives, Weather Conditions, Access Issues, ETC.
Remember, the prices give above are standard prices that I use. The pricing may go up or down depending on job conditions.
PICTURES
Slabs
The slab takeoff will use crews to determine the pricing of the labor.
Slab Types
Reinforcing
Rebar [All]
http://www.et.byu.edu/groups/cmfac/miller/cm411/notes/ConcNotes/Concrete.html 1/9/2010
Concrete Lecture Page 5 of 5
Mesh [All]
Fiber Mesh [more typical SOG]
PT Cable [SS]
Forming
Not all slabs will need to be formed. Often walls are inplace before the slab is poured and can be used to form the perimeter of the slabs.
The size of the slab will affect the pricing. Also, super flat floors will be more expensive.
Concrete Material
Watch for additives into the concrete. Most additives will add to the cost of the material.
Thickened Edges
Thickened Slabs
Pour Strips
Dowels
Column Diamonds
The column diamonds occur at each column in the slab. This allows for the column to be placed after the the slab is poured and also guides cracking to the
joints instead of going randomly throughout the slab.
Waste
Pumping
Costs
Fiber Mesh
PT Cable
Shoring
Depending on requirements pricing will vary, starting range would be $3.00/sf to $6.00/sf.
Pictures
Tilt up
Process
Casting Process
Forming
Embeds
Hoisting
Pour Strips
Pictures
http://www.et.byu.edu/groups/cmfac/miller/cm411/notes/ConcNotes/Concrete.html 1/9/2010