TIMELINE FOR CONSTRUCTION OF SUPP
ROAD NAME LIMITS RESPONSIBILITY STATUS
1 Skylark Road
1a MD 27 to just east of Walnut Greenway Village completed OPEN TO TRAFFIC
Haven Drive
1b Walnut Haven Drive to County CIP Participation with completed
Persimmon Ridge Road/Park Greenway Village OPEN TO TRAFFIC
entrance
1c Persimmon Ridge Road/Park Greenway Village pending on land
entrance to Piedmont Road acquisition
2 Stringtown Road
East of I 270 to Gateway Center Montgomery County CIP completed OPEN TO TRAFFIC
2a
Dr.
2b Gateway Center Dr. to MD 355 County CIP Participation with completed OPEN TO TRAFFIC
U.S. Homes
2c MD 355 to St. Clare Rd./Overlook CTC/Highlands at Clarksburg completed OPEN TO TRAFFIC
Park Dr. plus transition
2d Overlook Park Dr. to Snowden CTC/Clarksburg Village
Farm Parkway (A305)
construction of 2 lanes south side UNDER PERMIT
of Stringtown Rd - FALL 07
construction of 2 lanes north side
of Stringtown Rd - WINTER
07/SPRING 08
culvert construction - FALL 08
3 Clarksburg Road
3a MD 355 to Spire Street SOUTH CTC is responsible for the under design
HALF southern half including turn
lane improvement near the
MD355 intersection.
NORTH need County CIP to improve
HALF the northern half
3b Spire Street to approx.1500’ west SOUTH CTC is responsible along its site under permit DPS IS COORDINATING WITH DEVE
of intersection with Snowden HALF frontage for the southern half
Farm Pkwy (A305)
NORTH Clarksburg Ridge, Catawba
HALF Manor and Parkside are joinly
responsible for their frontage on
the north side
3c Remaining Clarksburg Road to SOUTH CTC is responsible for the under design
intersection with A305 and HALF southern half
approx. 450 feet beyond the
intersection
NORTH need County CIP to improve CONTINGENT UPON COUNTY CIP I
HALF the northern half
4 Foreman Blvd
Snowden Farm Parkway to Clarksburg Village/Greenway under
existing Foreman Blvd Village design/construction
5 Little Seneca Parkway (A302)
5a Westernmost access point of Clarksburg Heights is open to traffic
Clarksburg Heights to MD 355 responsible for constructing the
two outside lanes
OPEN TO TRAFFIC
5b MD 355 to Snowden Farm Clarksburg Village/Greenway under design
Parkway Village
5c Snowden Farm Parkway (A305) Clarksburg Village/Greenway under design
to MD 27 Village
6 Snowden Farm Parkway (A305)
6a MD 355 to Clarksburg Road Wood Crest subdivision under design
6b Clarksburg Road to Stringtown Clarksburg Town Center completed
Road
OPEN TO TRAFFIC
6c Stringtown Road to Foreman Blvd Clarksburg Village/Greenway under permit
Village
6d Foreman Blvd. to Little Seneca Clarksburg Village/Greenway under design
Pkwy (A302) Village
6e From A302 to MD 27 Clarksburg Village/Greenway under design
Village
7 Ridge Road MD 27
7a Observation Drive to MD 355 Clarksburg Village/Greenway completed
Village
OPEN TO TRAFFIC
7b MD 355 to Brink Road Clarksburg Village/Greenway completed
Village
OPEN TO TRAFFIC
7c Brink Road to A305 Snowden Clarksburg Village/Greenway
Farm Parkway Village
LEGEND
ESTIMATED CONSTRUCTION DURATION
ROAD CLOSURE ESTIMATED ROAD CLOSURE DURATION
STATUS UNCERTAIN, DEPENDENCE ON SITE PLAN APPROVAL BY MNCPPC
OPEN TO TRAFFIC
ON OF SUPPORTING ROADS IN CLARKSBURG AREA
SUMMER 2007 FALL 2007 WINTER 2007 SPRING 2008 SUMMER 2008 FALL 2008
TO TRAFFIC
TO TRAFFIC
OPEN TO TRAFFIC
ONE LANE TRAFFIC MAINTENANCE DURING CONSTRUCTION.
TO TRAFFIC
TO TRAFFIC
TO TRAFFIC
ROAD CLOSURE 4 to 5
MONTHS
ROAD CLOSURE is CONTINGENT UPON THE COMPLETION OF SKYLARK ROAD IN ITS ENTIRETY AS WELL AS THE AVAILABILITY OF OT
OVERLOOK PARK DRIVE MUST BE OPEN TO TRAFFIC TO SERVE AS DETOUR ROUTE FOR ACCESS TO MD355 FOR THE TOWN CENTER
OPEN TO TRAFFIC
CONTINGENT UPON COUNTY CIP IMPROVEMENT AND LAND ACQUISITION PRIOR TO
CONSTRUCTION
COORDINATING WITH DEVELOPERS FOR THE ENTIRE ROADWAY OPEN TO TRAFFIC
OPEN TO TRAFFIC
NGENT UPON COUNTY CIP IMPROVEMENT, NEEDS MAJOR LAND ACQUISITION FOR ROAD IMPROVEMENT
ROAD DESIGN UNDER REVIEW BY DPS, EXPECT CONSTRUCTION START FALL 2009
CONSTRUCTION MUST BEGIN AT 3500 DU FOR CLARKSBURG VILLAGE/GREENWAY VILLAGE COMBINED
ROAD DESIGN UNDER REVIEW BY DPS. SITE PLAN APPROVED BY MNCPPC JUST SHORT OF THE INTERSECTION WITH A305. EXPECT CONSTRUCTION START FALL 2009 (DEPENDENCE ON H
CONSTRUCTION MUST BEGIN AT 1900 DU FOR CLARKSBURG VILLAGE/GREENWAY VILLAGE COMBINED
THIS SECTION OF A305 WILL BEGIN CONSTRUCTION FROM MD 355 TOWARDS CLARKSBURG ROAD. THE ACTUAL CONNECTION TO THIS INTERSECTION WILL HINGE UPON THE NEEDED RIG
THE TIE IN AT CLARKSBURG ROAD WILL NEED TO COORDINATE WITH THE RECONSTRUCTION OF CLARKSBURG ROAD/BURNT HILL ROAD INTERSECTION UNDER SECTION 3C
OPEN TO TRAFFIC
SECTIONS OF A305 ROAD DESIGN UNDER REVIEW BY DPS, EXPECT CONSTRUCTION START FALL/WINTER2007
CONSTRUCTION MUST BEGIN AT 1900 DU FOR CLARKSBURG VILLAGE/GREENWAY VILLAGE COMBINED
SECTIONS OF A305 ROAD DESIGN UNDER REVIEW BY DPS, NO INFORMATION ON EXPECTED CONSTRUCTION START DATE
CONSTRUCTION MUST BEGIN AT 2401 DU FOR CLARKSBURG VILLAGE/GREENWAY VILLAGE COMBINED
CONSTRUCTION WILL COORDINATE WITH THE SITE PLAN APPROVAL OF THE REST OF CLARKSBURG VILLAGE/GREENWAY VILLAGE
AS OF SEPTEMBER 2007
WINTER 2008 SPRING 2009 SUMMER 2009
SURE 4 to 5 OPEN TO TRAFFIC
AS WELL AS THE AVAILABILITY OF OTHER MAJOR ARTERIALS IN CLARKSBURG
S TO MD355 FOR THE TOWN CENTER AREAS
FFIC
NEEDS ROAD CLOSURE DURING THE ROAD OPEN TO TRAFFIC
RECONSTRUCTION EFFORT. CLOSURE
OPEN TO TRAFFIC
START FALL 2009 (DEPENDENCE ON HOME SALES) AND CLARKSBURG VILLAGE PHASE II SITE PLAN APPROVAL BY MNCPPC
WILL HINGE UPON THE NEEDED RIGHT-OF-WAY FROM ADJOINING PROPERTIES
ON UNDER SECTION 3C