Electrical Civil Work Schedule

This document outlines a civil works schedule for 33kV substations over 29 days from November 13 to December 15. It involves excavation, foundation construction, flooring, curing and installation of walls, shutters and fences at multiple substation sites. The work is broken down into tasks with assigned durations and start/finish dates.

Uploaded by

Shaikh Ahamed
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views1 page

Electrical Civil Work Schedule

This document outlines a civil works schedule for 33kV substations over 29 days from November 13 to December 15. It involves excavation, foundation construction, flooring, curing and installation of walls, shutters and fences at multiple substation sites. The work is broken down into tasks with assigned durations and start/finish dates.

Uploaded by

Shaikh Ahamed
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 1

ID Task Name Duration Start Finish

Civil Work for 33 K.V substations.


38 Civil Work for Site 32 days Fri 12-11-10 Fri 17-12-10

39 Escavation for structural Foundations 3 days Fri 12-11-10 Sun 14-11-10


40 Excavation for Transformer 5 days Fri 12-11-10 Tue 16-11-10
41 Excavation for the Soak pit 5 days Fri 12-11-10 Tue 16-11-10
42 Construction of Foundation for the Structures 3 days Mon 15-11-10 Wed 17-11-10
43 Construction of Foundation for the Transformer 4 days Wed 17-11-10 Sat 20-11-10
44 Construction of Soak pit 4 days Wed 17-11-10 Sat 20-11-10
45 Construction of Dike wall around Transformer 3 days Thu 09-12-10 Sat 11-12-10
46 Fencing of Switchyard 8 days Thu 09-12-10 Fri 17-12-10
47 Installation of Gates 2 days Thu 09-12-10 Fri 10-12-10
48 Laying of Blue metal 3 days Sat 11-12-10 Tue 14-12-10
49 Curing the foundations 15 days Thu 18-11-10 Sat 04-12-10

211 Civil Works 29 days Sat 13-11-10 Wed 15-12-10

212 Main Substation and SS # 6 23 days Sat 13-11-10 Wed 08-12-10

213 Levelling of floor and compacting 3 days Sat 13-11-10 Mon 15-11-10
214 Excavation for Trenches. 2 days Tue 16-11-10 Wed 17-11-10
215 Preperation for Flooring 3 days Thu 18-11-10 Sat 20-11-10
216 Curing of Floors & Trenches 15 days Mon 22-11-10 Wed 08-12-10
217 Installation of Side Walls 8 days Mon 22-11-10 Tue 30-11-10
218 Installation of Rolling Shutters, Doors & Windows 3 days Wed 01-12-10 Fri 03-12-10

219 SS # 1 23 days Tue 16-11-10 Sat 11-12-10

220 Levelling of floor and compacting 3 days Tue 16-11-10 Thu 18-11-10
221 Excavation for Trenches. 2 days Fri 19-11-10 Sat 20-11-10
222 Preperation for Flooring 3 days Mon 22-11-10 Wed 24-11-10
223 Curing of Floors & Trenches 15 days Thu 25-11-10 Sat 11-12-10
224 Installation of Side Walls 8 days Thu 25-11-10 Fri 03-12-10
225 Installation of Rolling Shutters, Doors & Windows 5 days Sat 04-12-10 Thu 09-12-10

226 SS # 4 & 5 23 days Fri 19-11-10 Wed 15-12-10

227 Levelling of floor and compacting 3 days Fri 19-11-10 Mon 22-11-10
228 Excavation for Trenches. 2 days Tue 23-11-10 Wed 24-11-10
229 Preperation for Flooring 3 days Thu 25-11-10 Sat 27-11-10
230 Curing of Floors & Trenches 15 days Mon 29-11-10 Wed 15-12-10
231 Installation of Side Walls 8 days Mon 29-11-10 Tue 07-12-10
232 Installation of Rolling Shutters, Doors & Windows 5 days Wed 08-12-10 Mon 13-12-10

233 Main Substation and SS # 3 & 2 26 days Tue 16-11-10 Wed 15-12-10
234 Levelling of floor and compacting 3 days Tue 23-11-10 Thu 25-11-10
235 Excavation for Trenches. 2 days Tue 16-11-10 Wed 17-11-10
236 Preperation for Flooring 3 days Thu 18-11-10 Sat 20-11-10
237 Curing of Floors & Trenches 15 days Mon 22-11-10 Wed 08-12-10
238 Installation of Side Walls 8 days Mon 22-11-10 Tue 30-11-10
239 Installation of Rolling Shutters, Doors & Windows 3 days Wed 01-12-10 Fri 03-12-10
240 Installation of Hume Pipe Across the Road 3 days Mon 13-12-10 Wed 15-12-10