Power Scenario at A Glance - April 2010
Power Scenario at A Glance - April 2010
Power Scenario at A Glance - April 2010
1
2
LIST OF PROJECTS COMMISSIONED DURING 2007-2008 (XI TH PLAN) AS ON 31.03.2008
COMMISSIONING TOTAL
DATE/MONTH/ CAPACITY
PROJECT NAME YEAR REGION SECTOR STATE TYPE (MW)
THERMAL PROJECTS
SIPAT-II UNIT-4 500 (27/05/2007) WR C.S. CHAT COAL 500.00
PARAS UNIT-1 250 (31/05/2007) WR S.S. MAHA COAL 250.00
DHOLPUR CCGT UNIT-2 110 (16/06/2007) NR S.S. RAJ. GAS 110.00
BIRSINGPUR UNIT-5 500 (18/06/2007) WR S.S. M.P. COAL 500.00
DHUVRAN ST 40 (13/08/2007) WR S.S. GUJ. GAS 40.00
RAIGARH (JINDAL) U-I 250 (02/09/2007) WR P.S. CHAT COAL 250.00
MEJIA UNIT-6 250 (01/10/2007) ER C.S. DVC COAL 250.00
RATNAGIRI GAS 740 (28/10/2007) WR C.S. MAHA GAS 740.00
YAMUNA NAGAR UNIT-I 300 (01/11/2007) NR S.S. HAR. COAL 300.00
SANTALDIH UNIT-5 250 (07/11/2007) ER S.S. W.B. COAL 250.00
RAYALSEEMA UNIT-4 210 (20/11/2007) SR S.S. A.P. COAL 210.00
DURGAPUR DPL U-7 300 (24/11/2007) ER S.S. W.B. COAL 300.00
BELLARY UNIT-I 500 (03/12/2007) SR S.S. KAR. COAL 500.00
KORBA EAST EXTN.-1 250 (11/12/2007) WR S.S. CHAT COAL 250.00
SAGARDIGHI UNIT-1 300 (21/12/2007) ER S.S. W.B. COAL 300.00
BAKRESHWAR UNIT-4 210 (24/12/2007) ER S.S. W.B. COAL 210.00
DHOLPUR ST 110 (27/12/2007) NR S.S. RAJ. GAS 110.00
GHG TPS-II 250 (03/01/2008) NR S.S. PUN. COAL 250.00
RAIGARH (JINDAL) U-3 250 (10/02/2008) WR P.S. CHAT COAL 250.00
RAIGARH (JINDAL) U-2 250 (06/03/2008) WR P.S. CHAT COAL 250.00
KAHALGAON UNIT-6 500 (16/03/2008) ER C.S. BIH. COAL 500.00
YAMUNA NAGAR UNIT-I 300 (29/03/2008) NR S.S. HAR. COAL 300.00
SUB-TOTAL(THERMAL) 6620.00
HYDRO PROJECT
PURLIA PSS UNIT-4 (JV) 225 (18/07/2007)
PURLIA PSS UNIT-3 (JV) 225 (27/08/2007)
PURLIA PSS UNIT-2 (JV) 225 (23/11/2007)
PURLIA PSS UNIT-1 (JV) 225 (20/01/2008) ER S.S. W.B. HYDRO 900.00
3
LIST OF PROJECTS COMMISSIONED DURING 2007-2008 (XI TH PLAN) AS ON 31.03.2008
SUB-TOTAL(NUCLEAR) 220.00
TOTAL(THERMAL+HYDRO+NUCLEAR):-(2007-2008) 9263.00
COMMISSIONING TOTAL
DATE/MONTH/ CAPACITY
PROJECT NAME YEAR REGION SECTOR STATE TYPE (MW)
THERMAL PROJECTS
BHILAIEXN.TPPUNIT-1 250 (20/04/2008) WR C.S. CHAT COAL 250.00
VALUTHUR PH-II GTPP 59.8 (6/02/2009) SR S.S. TAM. GAS 59.8
AMARKANTAK U-5 210 (15/06/2008) WR S.S. M.P. COAL 210.00
RAIGARH (JINDAL) U-4 250 (17/06/2008) WR P.S. CHAT COAL 250.00
SAGARDIGHI U-2 300 (20/07/2008) ER S.S. W.B. COAL 300.00
GHGTPP-II,LEHAR MOB. 250 (31/07/2008) NR S.S. PUN. COAL 250.00
SIPAT ST-II U-5 500 (13/08/2008 WR C.S. CHAT COAL 500
VALUTHUR PH-II ST 32.4 (17/02//2009) SR S.S. TAM. GAS 32.4
SUGEN CCPP 382.5 (4/02/2009) WR P.S. GUJ GAS 382.5
* KUTCH LIGNITE 75 ( 22/10/2008) WR S.S. GUJ COAL
TROMBAY Extn. 250 (26.03.2009) WR P.S. MAH COAL 250
SUB-TOTAL(THERMAL) 2484.7
HYDRO PROJECT
GHATGHAR PSS 125 (13/05/2008) WR S.S. MAHA HYDRO 125.00
GHATGHAR PSS 125 (01/07/2008) WR S.S. MAHA HYDRO 125.00
JURALA PRIYA 39 (31/08/2008) SR S.S. A.P. HYDRO 39.00
BAGLIHAR UNIT-I 150 (19/09/2008) NR S.S. J&K HYDRO 150.00
BAGLIHAR UNIT-II 150 (26/10/2008) NR S.S. J&K HYDRO 150.00
BAGLIHAR UNIT-III 150 (14/11/2008) NR S.S. J&K HYDRO 150.00
VARAHI EXT.UNIT 1 115 (11/1/2009 SR S.S. KAR HYDRO 115.00
VARAHI EXT.UNIT 2 115 (09/2/2009 SR S.S. KAR HYDRO 115.00
SUB-TOTAL(HYDRO) 969.00
NUCLEAR PROJECT
SUB-TOTAL(NUCLEAR) 0.00
TOTAL(THERMAL+HYDRO+NUCLEAR):-(2008-2009) 3453.7
• UNITS COMMISSIONED , YET TO ACHIEVE COMMERCIAL OPERATION.
4
LIST OF PROJECTS COMMISSIONED DURING 2009-2010 (XI TH PLAN) AS ON 31.03.2010
COMMISSIONING TOTAL
DATE/MONTH/ CAPACITY
PROJECT NAME YEAR REGION SECTOR STATE TYPE (MW)
TORANGALLU U-1 (23.4.2009) SR P.S. KAR COAL 300
SUGEN –U2 (7.5.2009) WR P.S. GUJ GAS 382.5
GAUTAMI (3.5.2009) SR S.S A.P. GAS 464
KONASEEMA U-1 (3.5.2009) SR P.S. A.P. GAS 280
SUGEN U-3 ( 8.6.2009) WR P.S. GUJ GAS 382.5
LANCO AMAR U-1 (4.6.2009) WR P.S. CHATT COAL 300
BAKRESHWAR U-5 (7.6.2009) ER S.S WB COAL 210
BHILAI U-2 (12.07.2009) ER C.S CHATT COAL 250
KAHALGAON-II U-7 (31.03.2010 ) ER C.S BIHAR COAL 500
MUNDRA PH-I, U-I (4.8.2009) WR P.S. GUJ COAL 330
UTRAN (8.8.2009) WR S.S. GUJ GAS 240
TORANGALLU U-2 (24.8.2009) SR P.S. KAR COAL 300
SURATGARH U-7 (29.8.2009) NR S.S. RAJ COAL 250
KOTA U-7 (30.8.2009) NR S.S. RAJ COAL 195
BUDGE-BUDGE-EX (29.9.2009) ER P.S. WB COAL 250
KUTCH LIGNITE (1.10.2009) WR S.S. GUJ LIGNITE 75
U-IV
VIJAYWADA ST.IV (8.10.2009) SR S.S A.P. COAL 500
U-I
UTRAN CCPP-II (10.10.2009) WR S.S. GUJ COAL 134
JALIPA LIGNITE U-I (16.10.2009) NR P.S. RAJ LIGNITE 135
CHABRA U-I (30.10.2009) NR S.S RAJ COAL 250
CHANDRAPUR U-7 (4.11.2009) ER C.S. DVC COAL 250
Lanco Kondapalli (5.12.2009) SR P.S. A.P. GAS 233
St-II
NCTPP DADRI (29.01.2010) NR C.S. UP COAL 490
UNIT NO.5
NEW PARLI EXT (10.2.2010) WR S.S. MAH COAL 250
U2
ROSA ST-I U1 (10.2.2010) NR P.S. UP COAL 300
MUNDRA TPP,PH- (17.03.2010) WR P.S. GUJ COAL 330
I,U-2
LANCO (25.03.2010) WR P.S. CHAT COAL 300
AMARKANTAK TPS
U-2
PARAS TPS EXT. (27.03.2010) WR S.S. MAHA COAL 250
U2
CHANDRUPURA (31.03.2010) ER C.S. DVC COAL 250
RAJIV GANDHI (31.03.2010) NR S.S. HAR COAL 600
(HISSAR)
GIRAL LIGNITE NR S.S. RAJ LIGNITE 125
TOTAL THERMAL 9106
HYDRO PROJECTS
JURALA PRIYA U-3 (27.06.2009) SR S.S. A.P. HYDRO 39.0
TOTAL HYDRO 39.0
NUCLEAR PROJECT
RAPP U5 (4.02.2010) NR C.S. RAJ NUCLEAR 220
RAPP U6 (31.03.2010) NR C.S. RAJ NUCLEAR 220
TOTAL NUCLEAR 440
TOTAL (THERMAL+HYDRO+NUCLEAR )(2009-10) 9585
5
6
ALL INDIA
7
6. STATES LIKELY TO BE SURPLUS IN POWER AT THE END OF XIth PLAN CONSIDRING
CAPACITY ADDITION OF 62374 MW
8
POWER SCENERIO AT A GLANCE FOR ALL REGIONS
3. CAPACITY ADDITION DURING 11TH PLAN (AS PER PLANNING COMMISSION TARGET)
9
INSTALLED CAPACITY OF STATES AS ON 31.03.2010 figures in MW
10
NORTHERN REGION
9TH PLAN END 23200 21346 -1854 -8 150383 142410 -7973 -5.3
2002-03 24092 21889 -2203 -9.1 156610 144218 -12392 -7.9
2003-04 23817 22271 -1546 -6.5 161595 152743 -8852 -5.5
2004-05 26834 24125 -2709 -10.1 175498 159358 -16140 -9.2
2005-06 28154 25200 -2954 -10.5 188794 168611 -20183 -10.7
2006-07 31516 26644 -4872 -15.5 202125 179986 -22139 -11
2007-08 32462 29495 -2967 -9.1 219797 196147 -23650 -10.8
2008-09 33034 29504 -3530 -10.7 224218 199928 -24290 -10.8
APR,09-MAR10 37,159 31,439 -5,720 -15.4 253,803 224,447 -29,356 -11.6
MAR ,2010 31,253 26,843 -4,410 -14.1 20,956 18,734 -2,222 -10.6
NOTE :- PEAK DEMAND - 38021 MW , ENERGY REQUIREMENT - 239807 MU FOR THE YEAR 2008-2009(AS PER 17TH EPS
REPORT),OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) - JUNE, JULY & AUGUST
4. CAPACITY ADDITION DURING 11TH PLAN (AS PER PLANNING COMMISSION TARGET)
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12 (DEMAND AS PER 17TH EPS)
11
12
CHANDIGARH
NOTE :- PEAK DEMAND - 335 MW , ENERGY REQUIREMENT - 1802 MU FOR THE YEAR 2008-2009(AS PER 17TH EPS
REPORT),OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) - JUNE & JULY
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12 (DEMAND AS PER 17TH EPS)
13
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
NIL
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - CHANDIGARH
2004-05 – 30.37 %
2005-06 - 31.64 %
2006-07 - 25.13 %
PEAK ENERGY
YEAR
Requirment Actual Requirement Actual
as per Demand as Per 17th Requirement
EPS
17th EPS
2004-05 248 224 1295 1157
2005-06 267 240 1407 1260
2006-07 288 264 1528 1343
2007-08 311 275 1659 1446
2008-09 335 279 1802 1401
2009-10 361 1957
2010-11 389 2125
2011-12 420 2308
14
DELHI
NOTE :- PEAK DEMAND - 4877 MW , ENERGY REQUIREMENT - 28799 MU FOR THE YEAR 2008-2009(AS PER
17TH EPS REPORT ) , OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) -
DECEMBER
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
15
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
108
SUB TOTAL –Private sector
TOTAL - (DELHI) 1608
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - DELHI
16
8. T&D LOSSES
2003- 04 - 43.66 %
2004-05 – 45.40 %
2005-06 - 48.61 %
2006-07 - 33.00 %
9. ISSUES
SOME PROJECTS LIKE KODERMA, BADARPUR, JHAJJAR IDENTIFIED FOR COMMON WEALTH
GAMES DURING 2010-11 ARE CRITICAL. THESE PROJECTS ARE NOT LIKELY TO BE
COMMISSIONED BEFORE JUNE 2010 AND DELHI IS LIKELY TO FACE SHORTAGES TO THE TUNE
OF 1000 MW.
PEAK ENERGY
YEAR
Requirment as Actual Requirement as Actual
per 17th EPS Demand Per 17th EPS Requirement
17
18
HARYANA
CENTRAL SECTOR:
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
19
6.PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
CAPACITY LIKELY YEAR / DATE
S.NO. PROJECT AGENCY STATUS TYPE
(MW) OF COMMISSIONING
INDRA GANDHI TPS
1 NTPC Under Construction COAL 1500 2010-12
(JHAJJAR )JV
SUB TOTAL -Central sector 1500
2 YAMUNA NAGAR U-1,2 HPGCL Commissioned COAL 600 29.03.2008
RAJIV GANDHI (HISSAR)
3 HPGCL Commissioned COAL 600 31.03.210
TPS
RAJIV GANDHI (HISSAR)
HPGCL Under Construction COAL 600 2010-11
TPS
SUB TOTAL -state sector 1800
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - HARYANA
(MW)
CENTRAL-SECTOR
*PARBATI ST-III H U 520.00 520.00 28.00 (2011-2012)
*CHAMERA III H U 231.00 231.00 12.00 (2010-2012)
SEWA ST.II H U 120.00 120.00 7.00 (2010-2011)
*URI -II H U 240.00 240.00 13.00 (2010-2012)
INDAR GANDHI T U 1500.00 1500.00 750.00 (2010-2012)
(JHAJJAR)
*KOTESHWAR H U 400.00 400.00 17.00 (2010-2012)
RAPP U-5&6 N U 440.00 440.00 25.00 COMM 440.00 (31.03.2010 )
KAHALGAON 6,7 T C 1000.00 1000.00 23.00 COMM 1000.00 31.7.2009
CENTRAL-SECTOR TOTAL:- 875.00
STATE-SECTOR
YAMUNA NAGAR U 1,2 T C 600.00 600.00 600.00 COMM 600.00 29.03.2008
RAJIV GANDHI (HISSAR) T U 1200.00 1200.00 1200.00 COMM 600.00 31.03.2010
STATE - SECTOR TOTAL:- 1800.00
UMPP
ULTRA MEGA MUNDRA T U 4000.00 520.00 160.00 (2011-2012)
UMPP- TOTAL 160.00
WITH BEST EFFORTS
*RIHAND-III U-5 T U 1000.00 500.00 33.50 (2011-2012)
*KOLDAM H U 800.00 800.00 43.00 (2010-2011)
ULTRAMEGA SASAN T U 3960.00 660.00 74.0 (2011-2012)
TOTAL 150.50
GRAND-TOTAL:- 2985.5
NOTE :- U - UNDER CONSTRUCTION PROJECTS
C - COMISSIONED
* SHARES FROM CENTRAL SECTOR PROJECTS FOR WHICH M.O.P. ORDERS
ARE YET TO BE ISSUED ARE TENTATIVE
20
8.T&D LOSSES
2003-04 - 32.07 %
2004-05 – 32.11%
2005-06 - 30.51 %
2006-07 - 33.35 %
PEAK ENERGY
YEAR
Requirment as Actual Requirement Actual
per 17th EPS Demand as Per 17th EPS Requirement
21
22
HIMACHAL PRADESH
* Peak and Energy availability from all IPPs to be commissioned during 11th Plan are taken in the respective
state.
23
6.PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - HIMACHAL PRADESH
(MW)
Type
8.T&D LOSSES
24
2003-04 -22.76 %
2004-05 – 28.90 %
2005-06 – 23.55 %
2006-07 – 19.77 %
PEAK ENERGY
YEAR
Requirment as Actual Requirement Actual
per 17th EPS Demand as Per 17th EPS Requirement
25
26
JAMMU & KASHMIR
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
* Peak and Energy availability from all IPPs to be commissioned during 11th Plan are taken in the respective
state.
27
6.PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
LIKELY YEAR /
CAPACITY
S.NO. PROJECT AGENCY STATUS TYPE DATE OF
(MW)
COMMISSIONING
1 SEWA – II NHPC Under Construction HYDRO 120 2010-11
2 URI – II NHPC Under Construction HYDRO 240 2011-12
3 NIMOO BAZGO NHPC Under Construction HYDRO 45 2011-12
4 CHUTAK NHPC Under Construction HYDRO 44 2011-12
SUB TOTAL - Central sector 449
19.09.2008,
5 BAGLIHAR JKPDC Commissioned HYDRO 450 26.10.2008 &
14.11.2008
SUB TOTAL - state sector 450
TOTAL (J&K) 899
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - JAMMU & KASHMIR
(MW)
CENTRAL-SECTOR
*PARBATI ST-III H U 520.00 520.00 33.00 (2011-2012)
*CHAMERA III H U 231.00 231.00 15.00 (2010-2012)
SEWA ST.II H U 120.00 120.00 23.00 (2010-2011)
*URI -II H U 240.00 240.00 46.00 (2010-2012)
*KOTESHWAR H U 400.00 400.00 19.00 (2010-2012)
KAHALGAON 6,7 T C 1000.00 1000.00 29.00 COMM 1000.00 31.7.2009
*NIMOO BAZCO H U 45.00 45.00 45.00 (2011-2012)
*CHUTAK H U 44.00 44.00 44.00 (2011-2012)
CENTRAL-SECTOR TOTAL: - 254.00
STATE-SECTOR
BAGLIHAR H C 450.00 450.00 450.00 COMM 450.00 14.11.2008
TOTAL STATE SECTOR 450.00
WITH BEST EFFORTS
*KOLDAM H U 800.00 800.00 50.00 (2010-2011)
*RIHAND-III U-5 U 1000.00 500.00 39.50 (2011-2012)
TOTAL 89.50
GRAND TOTAL: - 793.50
NOTE :- U - UNDER CONSTRUCTION PROJECTS
C - COMISSIONED
* SHARES FROM CENTRAL SECTOR PROJECTS FOR WHICH M.O.P. ORDERS
8.T&D LOSSES
2003-04- 45.54 %
2004-05 – 41.08 %
2005-06 - 44.93 %
2006-07 - 51.98 %
28
9. PEAK & ENERGY TABLE
th
(As per 17 EPS Report vs Actual Achieved)
PEAK ENERGY
YEAR
Requirment as Actual Requirement Actual
per 17th EPS Demand as Per 17th EPS Requirement
29
30
PUNJAB
NOTE :- PEAK DEMAND - 9390 MW , ENERGY REQUIREMENT - 48347 MU FOR THE YEAR 2008-2009 (AS PER
17TH EPS REPORT), OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) –
DECEMBER
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
* Peak and Energy availability from all IPPs to be commissioned during 11th Plan are taken in the respective
state.
31
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
LIKELY YEAR /
CAPACITY
S.NO. PROJECT AGENCY STATUS TYPE DATE OF
(MW)
COMMISSIONING
1 GH TPP-II U-,3,4 PSEB Commissioned COAL 500 2007-09
SUB TOTAL -state sector
SUB TOTAL (PUNJAB) 500
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - PUNJAB
(MW)
CENTRAL-SECTOR
*PARBATI ST-III H U 520.00 520.00 41.00 (2011-2012)
*CHAMERA III H U 231.00 231.00 18.00 (2010-2012)
SEWA ST.II H U 120.00 120.00 10.00 (2010-2011)
*URI -II H U 240.00 240.00 19.00 (2010-2012)
*KOLDAM H U 800.00 800.00 63.00 (2010-2011)
*KOTESHWAR H U 400.00 400.00 24.00 (2010-2012)
RAPP U-5&6 N U 440.00 440.00 45.00 COMM 440.00 (31.03.2010)
KAHALGAON 6,7 T C 1000.00 1000.00 35.00 COMM 1000.00 31.7.2009
CENTRAL-SECTOR TOTAL:- 255.00
STATE-SECTOR
GHTPP-II,U3,4 T C 500.00 500.00 500.00 COMM 500.00 31.07.2008
STATE - SECTOR TOTAL:- 500.00
PRIVATE-SECTOR
GOINDWAL SAHIB T U 540.00 540.00 540.00 (2011-2012)
PRIVATE-SECTOR TOTAL:- 540.00
UMPP
32
8. T&D LOSSES
2003-04 – 25.96 %
2004-05 – 25.42 %
2005-06 - 27.56 %
2006-07 - 26.61 %
PEAK ENERGY
YEAR
Requirment Actual Requirement Actual
as per Demand as Per 17th EPS Requirement
17th EPS
33
34
RAJASTHAN
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
35
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
CAPACITY LIKELY YEAR / DATE
S.NO. PROJECT AGENCY STATUS TYPE
(MW) OF COMMISSIONING
1 BARSINGSAR LIG NLC Under Construction LIGNITE 250 2010-11
2 RAPP U5&6 NPC Commissioned NUCLEAR 440 31.03.2010
SUB TOTAL - Central sector 690
1 CHABRA TPS-I RRVUNL commissioned COAL 250 30.10.2009
CHABRA TPS-2 RRVUNL Under Construction COAL 250 2009-10
2 KOTA U7 RRVUNL commissioned COAL 195 31.03.2010
3 SURATGARH EXT U 6 RRVUNL Commissioned COAL 250 29.08.2009
4 DHOLPUR GT2+ST RRVUNL Commissioned GAS/LNG 220 27.12.2007
5 GIRAL U-2 RRVUNL Commissioned LIGNITE 125 2009-10
SUB TOTAL -state sector 1290
1 JALIPA LIGNITE IPP Commissioned LIGNITE 135 16.10.2009
JALIPA LIGNITE IPP Under Construction LIGNITE 945 2010-12
SUB TOTAL -Private sector 1080
TOTAL - (RAJASTHAN) 3060
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - RAJASTHAN
Project Name Installed Capacity Benefits Commissioned/ Last Unit
Capacity Addition During Shares of slipped during Commissioning Date/
Status
Status
36
8. T&D LOSSES
2003-04 – 43.74 %
2004-05 – 44.68 %
2005-06 – 39.92 %
2006-07 – 35.60 %
PEAK ENERGY
YEAR
Requirment Actual Requirement Actual
as per Demand as Per 17th Requirement
17th EPS EPS
37
38
UTTAR PRADESH
NOTE :- PEAK DEMAND - 11024 MW , ENERGY REQUIREMENT - 66725 MU FOR THE YEAR 2008-2009(AS PER
17TH EPS REPORT),OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) -
DECEMBER & MARUARY
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
39
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
LIKELY YEAR /
CAPACITY
S.NO. PROJECT AGENCY STATUS TYPE DATE OF
(MW)
COMMISSIONING
1 RIHAND-III U-5 NTPC Under Construction COAL 500 20011-12
2 DADRI EXT U-5, 6 NTPC COMM 490 MW COAL 980 29.01.2010
SUB TOTAL - Central sector 1480
1 PARICHHA EXT U-5,6 UPRVUNL Under Construction COAL 500 2010-11
2 HARDUAGANJ EXT U-5,6 UPRVUNL Under Construction COAL 500 2010-11
3 ANPARA-D UPRVUNL Under Construction COAL 500 2011-12
SUB TOTAL -state sector 1500
1 ANPARA-C LANCO Under Construction COAL 1200 2010-12
ROSA COMM 300 MW
2 ROSA ST-I COAL 600 2010-11
POWER
ROSA Under Construction
3 ROSA ST-II COAL 600 2009-11
POWER
SUB TOTAL - private sector 2400
TOTAL (UP) 5380
Linkage required for Anpara D U2, 500 MW.
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - UTTAR PARDESH
Project Name Installed Capacity Benefits Commissioned/ Last Unit
Capacity Addition During Shares of slipped during Commissioning Date/
(MW) XIth Plan state 2007-2012 (Likely Date of
Status
Status
CENTRAL-SECTOR
*PARBATI ST-III H U 520.00 520.00 110.00 (2011-2012)
*CHAMERA III H U 231.00 231.00 49.00 (2010-2012)
SEWA ST.II H U 120.00 120.00 27.00 (2010-2011)
*URI -II H U 240.00 240.00 51.00 (2010-2012)
DADRI EXT U-5&6 T U 980.00 980.00 98.00 COMM 490 29.01.2010
*KOTESHWAR H U 400.00 400.00 152.00 (2010-2012)
RAPP U-5&6 N U 440.00 440.00 101.00 COMM 440.00 (31.03.2010)
KAHALGAON 6,7 T C 1000.00 1000.00 100.00 COMM 1000.00 31.7.2009
CENTRAL-SECTOR TOTAL:- 688.00
STATE-SECTOR
HARDUAGANJ EXT 5,6 T U 500.00 500.00 500.00 (2010-2011)
PARICHHA EXTN 5,6. T U 500.00 500.00 500.00 (2010-2011)
STATE - SECTOR TOTAL:- 1000.00
PRIVATE-SECTOR
ROSA I T U 600.00 600.00 600.00 COMM 300 (2009-2011)
$ ANPARA 'C' T U 1200.00 1200.00 1200.00 (2010-2012)
PRIVATE-SECTOR TOTAL:- 1800.00
UMPP
ULTRA MEGA SASAN T U 3960.00 660.00 82.50 (2011-2012)
TOTAL-UMPP 82.5
WITH BEST EFFORTS
ROSA TPP PH- I I T U 600.00 600.00 600.00 (2010-2011)
*RIHAND-III U-5 T U 500.00 500.00 132.00 (2011-2012)
*KOLDAM H U 800.00 800.00 169.00 (2010-2011)
ANPARA 'D' T U 1000.00 500.00 500.00 (2011-2012)
TOTAL 1401.00
GRAND-TOTAL:- 4971.50
2003-04 - 35.17 %
2004-05 – 34.39 %
2005-06 - 32.63 %
2006-07 - 33.49 %
PEAK ENERGY
YEAR
Requirement Actual Requirement Actual
as per Demand as Per 17th EPS Requirement
17th EPS
41
42
UTTARAKHAND
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
* Peak and Energy availability from all IPPs to be commissioned during 11th Plan are taken in the respective
state.
43
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
LIKELY YEAR /
CAPACITY
S.NO. PROJECT AGENCY STATUS TYPE DATE OF
(MW)
COMMISSIONING
1 KOTESHWAR THDC Under Construction HYDRO 400 2010-12
SUB TOTAL -Central sector 400
2 MANERI BHALI UJVNL Commissioned HYDRO 304 10.03.2008
SUB TOTAL -state sector 304
3 SRINAGAR GVK Under Construction HYDRO 330 2011-12
SUB TOTAL -private sector 330
TOTAL (UTTARAKHAND) 1034
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - UTTRAKHAND
CENTRAL-SECTOR
*PARBATI ST-III H U 520.00 520.00 20.00 (2011-2012)
*CHAMERA III H U 231.00 231.00 9.00 (2010-2012)
SEWA ST.II H U 120.00 120.00 5.00 (2010-2011)
*URI -II H U 240.00 240.00 9.00 (2010-2012)
*KAHALGAON II U,67 T C 1000.00 1000.00 19.00 COMM 1000.00 31.7.2009
KOTESHWAR H U 400.00 400.00 64.00 (2010-2012)
CENTRAL-SECTOR TOTAL:- 126.50
STATE-SECTOR
MANERI BHALI H C 304.00 304.00 304.00 COMM 304.00 10.03.2008
STATE - SECTOR TOTAL:- 304.00
PRIVATE-SECTOR
UMPP
ULTRA MEGA SASAN H U 3960.00 660.00 8.00 (2011-2012)
TOTAL-UMPP 8.00
WITH BEST EFFORTS
*KOLDAM H U 800.00 800.00 30.00 (2010-2011)
SRINAGAR HEP H U 330.00 330.00 330.00 (2011-2012)
*RIHAND-III U-5 T U 500.00 500.00 23.50 (2011-2012)
TOTAL- 383.50
GRAND-TOTAL:- 821.50
44
8. T&D LOSSES
2003-04 – 49.23 %
2004-05 – 39.30 %
2005-06 – 35.96 %
2006-07 – 34.48 %
PEAK ENERGY
YEAR
Requirment as Actual Requirement Actual
per 17th EPS Demand as Per 17th EPS Requirement
45
46
WESTERN REGION
NOTE :- PEAK DEMAND - 39513 MW ,ENERGY REQUIREMENT - 256075 MU FOR THE YEAR 2008-2009 (AS PER
17TH EPS REPORT), OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) –
DECEMBER
4. CAPACITY ADDITION DURING 11TH PLAN (AS PER PLANNING COMMISSION TARGET)
47
48
CHHATTISGARH
CENTRAL SECTOR
* SHARE OF CENTRAL SECTOR PROJECTS INCLUDED IN ITEM NO. 1
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
49
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
LIKELY YEAR /
CAPACITY
S.NO. PROJECT AGENCY STATUS TYPE DATE OF
(MW)
COMMISSIONING
1 SIPAT–II, U-4 NTPC Commissioned COAL 500 2007-08
2 SIPAT–II, U-5 NTPC Commissioned COAL 500 2008-09
3 SIPAT-I NTPC Under Construction COAL 1980 2010-12
4 BHILAI JV U-1 NTPC Commissioned COAL 250 2008-09
5 BHILAI JV U-2 NTPC Commissioned COAL 250 2009-10
6 KORBA-III, U-7 NTPC Under Construction COAL 500 2010-11
SUB TOTAL-Central sector 3980
1 KORBA EAST EXT. U2 CSEB Commissioned COAL 250 2007-08
SUB TOTAL-state sector 250.00
1 O.P.JINDAL ,U1,U2, U-3 JIN. POWER Commissioned COAL 750 2007-08
2 O.P JINDAL, U-4 JIN. POWER Commissioned COAL 250 2008-09
3 LANCO(AMARKANTAK) U1 LANCO-IPP Commissioned COAL 300 4.6.2009
4 LANCO(AMARKANTAK) U2 LANCO-IPP Under Construction COAL 300 2009-10
SUB TOTAL-private sector 1600.00 2450
TOTAL (CHG) 5830.00
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - CHATTISGARH
(MW)
CENTRAL-SECTOR
SIPAT STPS II T C 1000.00 1000.00 158.00 COMM 1000.00 27.12.2008
BHILAI JV T C 500.00 500.00 50.00 COMM 500.00 12.7.2009
*KORBA ST.-III T U 500.00 500.00 81.00 (2010-2011)
KAHALGAON 6,7 T C 1000.00 1000.00 20.00 COMM 1000.00 31.7.2009
CENTRAL-SECTOR TOTAL:- 309.00
STATE-SECTOR
KORBA EAST EXTN U2 T C 250.00 250.00 250.00 COMM 250.00 11.12.2007
STATE - SECTOR TOTAL:- 250.00
PRIVATE-SECTOR
LANCO (AMARKANTAK) T U 600.00 600.00 600.00 COMM 300.00 4.6.2009
O.P.JINDAL T C 1000.00 1000.00 1000.00 COMM 1000.00 17.06.2008
PRIVATE-SECTOR TOTAL:- 1600.00
WITH BEST EFFORTS
*VINDHYACHAL IV U-11 T U 1000.00 500.00 31.5 (20011-12)
SIPAT I T U 1980.00 1980.00 313.00 (2010-2012)
MAUDA TPPU-I T U 1000.00 500.00 31.5 (20011-12)
PRIVATE-SECTOR TOTAL:- 376.00
GRAND-TOTAL:- 2535.00
50
8. T&D LOSSES
2003-04 – 42.55 %
2004-05 – 28.06 %
2005-06 – 31.06 %
2006-07 – 31.71 %
51
52
GUJARAT
NOTE :- PEAK DEMAND - 12422 MW, ENERGY REQUIREMENT - 73497 MU FOR THE YEAR 2008-2009 (AS PER
17TH EPS REPORT), OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) -
OCTOBER
53
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
CAPACITY LIKELY YEAR / DATE
S.NO. PROJECT AGENCY STATUS TYPE
(MW) OF COMMISSIONING
1 SURAT LIGNITE EXT U 3,4 GIPCL Under Construction LIGNITE 250 2010-11
2 KUTCH LIGNITE TPS GSECL Commissioned LIGNITE 75 01.10.2009
4 DHUVRAN ST GSECL Commissioned GAS/LNG 40 2007-08
5 UKAI EXT U6 GSECL Under Construction COAL 490 2011-12
6 UTRAN CCPP GSECL Commissioned GAS/LNG 374 10.10.2009
7 HAZIRA GSEG EXT GSEG Under Construction GAS/LNG 351 2010-11
8 PIPAVAV JV CCGT GPPC Under Construction GAS/LNG 702 2010-12
SUB TOTAL-state sector 2282
1 SUGEN TORR. BLOCK I TORRENT Commissioned GAS/LNG 382.5 04.02.2009
2 SUGEN TORR. BLOCK II& III TORRENT Commissioned GAS/LNG 765 8.6.2009
ADANI POWER PVT LTD-
3 ADANI Commissioned 660 MW COAL 1320 17.03.2010
MUNDRA Ph-I
ADANI POWER PVT LTD-
4 ADANI Under Construction COAL 1320 2011-12
MUNDRA Ph-II
TATA
5 MUNDRA UMPP U1 & U2 Under Construction COAL 1600 2011-12
POWER
ADANI
6 MUNDRA- III,U1,2,3 Under Construction COAL 1980 2011-12
POWER
SUB TOTAL-private sector 7367.5
TOTAL (GUJARAT) 9649.5
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - GUJARAT
Project Name Installed Capacity Benefits Commissioned/ Last Unit
Capacity Addition Shares of slipped during Commissioning Date/
(MW) During XIth state 2007-2012 (Likely Date of
Status
Status
(MW)
CENTRAL-SECTOR
SIPAT STPS II T C 1000.00 1000.00 273.00 COMM 1000.00 27.12.2008
*KORBA ST.-III T U 500.00 500.00 120.00 (2010-2011)
KAHALGAON 6,7 T C 1000.00 1000.00 94.00 COMM 1000.00 31.07.2009
CENTRAL-SECTOR TOTAL:-487 .00
STATE-SECTOR
KUTCH LIGNITE TPS T U 75.00 75.00 75.00 COMM 75.00 (1.10.2009)
DHUVRAN ST G C 40.00 40.00 40.00 COMM 40.00 13.08.2007
SURAT LIGNITE U3,4 T U 250.00 250.00 250.00 (2010-2011)
UTRAN CCPP G U 374.00 374.00 374.00 COMM 374.00 (10.10.2009)
UKAI EXT. T U 490.00 490.00 490.00 (2011-2012)
HAZIRA GSEG CCGT G U 351.00 351.00 351.00 (2010-2011)
PIPAVAV GAS G U 702.00 702.00 702.00 (2010-2012)
STATE - SECTOR TOTAL:- 2282.00
PRIVATE-SECTOR
SUGEN AKHAKHOL G C 1147.50 1147.50 1147.50 COMM 1147.5 08.06.2009
ADANI POWER MUNDRA-I T U 1320.00 1320.00 1320.00 COMM 660.00 (17.03.2010)
ADANI MUNDRA-2,3 T U 1320.00 1320.00 1320.00 (2011-2012)
MUNDRA-III,U-1,2, T U 1980.00 1980.00 660.00 (2011-2012)
TOTAL-PRIVATE-SECTOR 4447.5
UMPP
MUNDRA UMPP U1 T U 4000.00 800.00 380.00 (2011-2012)
UMPP- TOTAL:- 380.00
WITH BEST EFFORTS
*VINDHYACHAL IV U-11 T U 1000.00 500.00 31.5 (20011-12)
SIPAT I T U 1980.00 1980.00 313.00 (2010-2012)
MAUDA TPP U-I T U 1000.00 500.00 120.00 (20011-12)
MUNDRA-III,U- 2,,3 T U 1980.00 1980.00 1320.00 (2011-2012)
MUNDRA UMPP U,2 T U 4000.00 800.00 380.00 (2011-2012)
TOTAL:- 2164.50
GRAND-TOTAL:- 9761.0
NOTE :- U - UNDER CONSTRUCTION PROJECTS C - COMMISSIONED
* SHARES FROM CENTRAL SECTOR PROJECTS FOR WHICH M.O.P. ORDERS
54
8. T&D LOSSES
2003-04 – 24.20 %
2004-05 – 30.43 %
2005-06 – 27.91 %
2006-07 – 24.87 %
PEAK ENERGY
YEAR
Requirment as Actual Requirement Actual
per 17th EPS Demand as Per 17th EPS Requirement
55
56
MADHYA PRADESH
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
* Peak and Energy availability from all IPPs to be commissioned during 11th Plan are taken in the respective
state.
57
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - MADHYA PRADESH
(MW)
CENTRAL-SECTOR
OMKARESHWAR H C 520.00 520.00 520.00 COMM 520.00 04.11.2007
SIPAT STPS II T C 1000.00 1000.00 143.00 COMM 1000.00 27.12.2008
*KORBA ST.-III T U 500.00 500.00 78.00 (2010-2011)
KAHALGAON 6,7 T C 1000.00 1000.00 49.00 COMM 1000.00 31.7.2009
CENTRAL-SECTOR TOTAL:- 790.00
STATE-SECTOR
BIRSINGPUR EXT. T C 500.00 500.00 500.00 COMM 500.00 18.06.2007
AMARKANTAK U-5 T C 210.00 210.00 210.00 COMM 210.00 15.06.2008
STATE - SECTOR TOTAL:- 710.00
PRIVATE-SECTOR
MAHESHWAR H U 400.00 200.00 200.00 (2011-2012)
PVT.SEC-TOTAL 200.00
8. T&D LOSSES
2003-04 – 41.44 %
2004-05 – 41.30 %
2005-06 – 40.07 %
58
2006-07 – 39.24 %
PEAK ENERGY
YEAR
Requirment as Actual Requirement Actual
per 17th EPS Demand as Per 17th EPS Requirement
59
60
MAHARASHTRA
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
Period Peak Peak Peak Peak Energy Energy Energy Energy
Demand Met eficit/ Deficit/ Requi- Avail- Deficit/ Deficit/
(MW) (MW) Surplus Surplus rment ability Surplus Surplus
(MW) (%) (MU) (MU) (MU) (%)
2011-12 21954 18322 -3632 -16.5 125661 125486 -175 -0.1
* Peak and Energy availability from all IPPs to be commissioned during 11th Plan are taken in the respective
state.
61
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
LIKELY YEAR /
CAPACITY
S.NO. PROJECT AGENCY STATUS TYPE DATE OF
(MW)
COMMISSIONING
1 RATNAGIRI (DHABOL)CCGT NTPC Commissioned Gas/LNG 740 28.10.2007
2 MAUDA TPS NTPC Under Construction COAL 500 2011-12
SUB TOTAL –central sector 1240
1 GHATGHAR PSS GOMID Commissioned HYDRO 250 01.07.2008
2 NEW PARLI EXT U-2 MAHA GEN Commissioned COAL 250 2009-10
3 PARAS EXT U1 MAHA GEN Commissioned COAL 250 31.05.2007
4 PARAS EXT U2 MAHA GEN Commissioned COAL 250 27.03.2010
5 KHAPER KHEDA EXT MAHA GEN Under Construction COAL 500 2010-11
6 BHUSAWAL TPP MAHA GEN Under Construction COAL 1000 2010-12
SUB TOTAL -state sector 2500
1 TROMBAY TPS TATA POWER Commissioned COAL 250 26.03.2009
2 JSW ENERGY RATNAGIRI JSW Under Construction COAL 1200 2010-11
ADANI
3 TIRODA TPP PH-I,U1,2 Under Construction COAL 1320 2011-12
POWER
ADANI
4 TIRODA TPP PH-II ,U1, Under Construction COAL 660 2011-12
POWER
SUB TOTAL –private sector 3430
TOTAL (MAHARASHTRA) 7170
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - MAHARASTRA
Project Name Installed Capacity Benefits Commissioned/ Last Unit
Capacity Addition Shares of slipped during Commissioning Date/
(MW) During XIth state 2007-2012 (Likely Date of
Status
Status
(MW)
SIPAT STPS II T C 1000.00 1000.00 258.00 COMM 1000.00 27.12.2008
DABHOL RATNAGIRi G C 740.00 740.00 740.00 COMM 740.00 28.10.2007
*KORBA ST.-III T U 500.00 500.00 135.00 (2010-2011)
KAHALGAON 6,7 T C 1000.00 1000.00 99.00 COMM 1000.00 31.7.2009
CENTRAL-SECTOR TOTAL:- 1232 .00
STATE-SECTOR
GHATGHAR PSS H C 250.00 250.00 250.00 COMM 250.00 01.07.2008
KHAPERKHEDA EX T U 500.00 500.00 500.00 (2010-2011)
BHUSAWAL T U 1000.00 1000.00 1000.00 (2010-2012)
NEW PARLI EXT U-2 T U 250.00 250.00 250.00 COMM 250.00 (2009-2010)
PARAS EXT U-1&2 T U 500.00 500.00 500.00 COMM 500.00 27.03.2010
STATE – SECTOR TOTAL:- 2500.00
PRIVATE-SECTOR
TROMBAY EXTN. T U 250.00 250.00 250.00 COMM 250.00 (26.03.2009)
JSW RATNAGIRI T U 1200.00 1200.00 1200.00 (2010-2011)
PVT. – SECTOR TOTAL 1450.00
UMPP
UMPP-MUNDRA T U 4000.00 800.00 160.00 (2011-2012)
UMPP –TOTAL 160.00
WITH BEST EFFORTS
*VINDHYACHAL IV U-11 T U 1000.00 500.00 31.5 (20011-12)
SIPAT I T U 1980.00 1980.00 313.00 (2010-2012)
TIRODA TPP PH-I,U1,2 T U 1320.00 660.00 660.00 (2011-2012)
TIRODA TPP PH-II ,U1 T U 660.00 660.00 660.00 (2011-2012)
UMPP-MUNDRA T U 4000.00 800.00 160.00 (2011-2012)
MAUDA TPP U-I T U 1000.00 500.00 185.00
TOTAL:- 2009.50
GRAND-TOTAL:- 7351.50
62
NOTE :- U - UNDER CONSTRUCTION PROJECTS
C - COMISSIONED
* SHARES FROM CENTRAL SECTOR PROJECTS FOR WHICH M.O.P. ORDERS
ARE YET TO BE ISSUED ARE TENTATIVE
8. T&D LOSSES
2003-04 - 34.12 %
2004-05 – 32.40 %
2005-06 – 31.60 %
2006-07 – 31.64 %
PEAK ENERGY
YEAR
Requirment as Actual Requirement Actual
per 17th EPS Demand as Per 17th EPS Requirement
63
64
GOA
NOTE :- PEAK DEMAND - 551 MW , ENERGY REQUIREMENT - 3425 MU FOR THE YEAR 2008-2009(AS PER
17TH EPS REPORT), OCCURENCE OF PEAK AS PER ACTUAL
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
65
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
NIL
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - GOA
Status
Status
Plan (MW) (MW) Commissioning)
Type
(MW)
CENTRAL-SECTOR
SIPAT STPS II T C 1000.00 1000.00 10.00 COMM 1000.00 27.12.2008
*KORBA ST.-III T U 500.00 500.00 6.00 (2010-2011)
CENTRAL-SECTOR TOTAL:- 16.00
8. T&D LOSSES
2003-04 - 45.05 %
2004-05 – 35.97 %
2005-06 – 19.68 %
2006-07 – 20.90 %
PEAK ENERGY
YEAR
Requirment as Actual Requirement t Actual
per 17th EPS Demand as Per 17th EPS Requirement
66
DAMAN & DIU
NOTE :- PEAK DEMAND - 374 MW , ENERGY REQUIREMENT - 2038 MU FOR THE YEAR 2008-2009(AS PER
17TH EPS REPORT), OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) -
OCTOBER , NOV.& DEC.
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
67
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
NIL
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - DAMAN & DIU
(MW)
CENTRAL-SECTOR
SIPAT STPS II T C 1000.00 1000.00 4.00 COMM 1000.00 27.12.2008
*BHILAI JV T C 500.00 500.00 100.00 COMM 500.00 12.7.2009
*KORBA ST.-III T U 500.00 500.00 2.00 (2010-2011)
KAHALGAON 6,7 T C 1000.00 1000.00 1.00 COMM 1000.00 31.7.2009
CENTRAL-SECTOR TOTAL:- 107.00
WITH BEST EFFORTS
SIPAT I T U 1980.00 1980.00 8.00 (2011-2012)
*VINDHYACHAL IV U-11 T U 1000.00 500.00 2.00 ( 2011-2012 )
MAUDA TPP U-I T U 1000.00 500.00 2.00 ( 2011-2012)
TOTAL : 12.00
GRAND TOTAL:- 119.00
8. T&D LOSSES
2003-04 – 16.88 %
2004-05 – 15.56 %
2005-06 – 21.58 %
2006-07 – 22.09 %
PEAK ENERGY
YEAR
Requirment as Actual Requirement Actual
per 17th EPS Demand as Per 17th EPS Requirement
68
DADRA AND NAGAR HAVELI
CENTRAL SECTOR
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
69
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
NIL
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - DADRA & NAGAR HAVELI
(MW)
CENTRAL-SECTOR
SIPAT STPS II T C 1000.00 1000.00 4.00 COMM 1000.00 27.12.2008
*BHILAI JV T C 500.00 500.00 70.00 COMM 500.00 12.7.2009
KAHALGAON 6,7 T C 1000.00 1000.00 2.00 COMM 1000.00 12.7.2009
CENTRAL-SECTOR TOTAL:- 76.00
WITH BEST EFFORTS
SIPAT I T U 1980.00 1980.00 9.00 (2011-2012)
*VINDHYACHAL IV U-11 T U 1000.00 500.00 3.00 ( 2011-2012 )
MAUDA TPP U-1 T U 1000.00 500.00 3.00 ( 2011-2012 )
TOTAL : 15.00
GRAND-TOTAL:- 91.00
8. T&D LOSSES
2003-04 – 15.10 %
2004-05 – 16.00 %
2005-06 – 19.94 %
2006-07 – 11.22 %
PEAK ENERGY
YEAR
Requirment as Actual Requirement as Per Actual
per 17th EPS Demand 17th EPS Requiremen
70
SOUTHERN REGION
4. CAPACITY ADDITION DURING 11TH PLAN (AS PER PLANNING COMMISSION TARGET)
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
71
72
ANDHRA PRADESH
NOTE :- PEAK DEMAND - 11388 MW , ENERGY REQUIREMENT - 69775 MU FOR THE YEAR 2008-2009(AS PER
17TH EPS REPORT),OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) -
MARCH & APRIL
* Peak and Energy availability from all IPPs to be commissioned during 11th Plan are taken in the respective
state.
73
6. PROJECTS PLANNED FOR XITH PLAN (STATE/PRIVATE/CENTRAL SECTOR) INCLUDING BEST
EFFORT PROJECTS
LIKELY YEAR /
CAPACITY
S.NO. PROJECT AGENCY STATUS TYPE DATE OF
(MW)
COMMISSIONING
1 SIMHADRI-EXT U-3,4 NTPC Under Construction COAL 1000 2010-12
SUB TOTAL –Central sector 1000
1 JURALA PRIYA U1,2 APGENCO Commissioned HYDRO 78 31.08.2008
2 JURALA PRIYA U,3 APGENCO Commissioned HYDRO 39 07.06.2009
3 JURALA PRIYA U 4-6 APGENCO Under Construction HYDRO 117 2010-11
4 NAGARJUNA SAGAR TR APGENCO Under Construction HYDRO 50 2010-12
5 PULICHINTALA APID Under Construction HYDRO 120 2010-12
6 RAYALSEEMA U4 APGENCO Commissioned COAL 210 2007-08
7 RAYALSEEMA ST III U5 APGENCO Under Construction COAL 210 2010-11
8 VIJAYWADA TPP ST-IV,U1 APGENCO Commissioned COAL 500 8.10.2009
9 KOTHAGUDEM ST-V APGENCO Under Construction COAL 500 2011-12
10 KAKTIYA TPP APGENCO Under Construction COAL 500 2010-11
SUB TOTAL –state sector 2324
1 KONASEEMA OAKWELL Commissioned GAS/LNG 280 3.5.2009
2 KONASEEMA OAKWELL Under Construction GAS/LNG 165 2010-11
3 GAUTAMI GAUTAMI POW Commissioned GAS/LNG 464 3.5.2009
4 KONDAPALLI PH II LANCO Commissioned GAS 233 5.12.2009
KONDAPALLI PH II LANCO Under Construction LNG 133 2010-11
SUB TOTAL -private sector 1275
TOTAL (AP) 4719
Coal linkage required for Simhadri Ext U2 500 MW
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - ANDHRA PRADESH
(MW)
CENTRAL-SECTOR
*SIMHADRI ST-II T U 1000.00 1000.00 384.00 (2010-2012)
*ENNORE JV COST T U 1000.00 1000.00 129.00 (20110-2012)
KAIGA U-3 & 4 N U 440.00 440.00 123.00 COMM 220.00 11.04.2007
*KALPAKKAM PFBR N U 500.00 500.00 142.00 (2010-2011)
CENTRAL-SECTOR TOTAL:- 778.00
STATE-SECTOR
NAGAR SAGAR TR H U 50.00 50.00 50.00 (2010-2012)
VIJAYWADA TPP T U 500.00 500.00 500.00 COMM 500.00 ( 8.10.2009 )
KOTHAGUDEM ST-V T U 500.00 500.00 500.00 (2011-2012)
JURALA PRIYA H U 234.00 234.00 234.00 COMM 117.00 27.06.2009
RAYALSEEMA 4&5 T U 420.00 420.00 420.00 COMM 210.00 20.11.2007
PULICHINTALA H U 120.00 120.00 120.00 (2011-2012)
KAKTIYA TPP T U 500.00 500.00 500.00 (2010-2011)
STATE - SECTOR TOTAL:- 1824.00
PRIVATE-SECTOR
KONASEEMA CCGT G U 445.00 445.00 445.00 COMM 280.00 (3.5.2009)
GAUTAMI CCGT G C 464.00 464.00 464.00 COMM 464.00 (3.5.2009)
KONDAPALLI CCPP G U 233.00 233..00 233.00 COMM 233.00 (5.12.2009)
KONDAPALLI CCPP T U 366.00 366.00 133.00 (2010-2011)
74
8. T&D LOSSES
2003-04 – 27.73 %
2004-05 – 23.96 %
2005-06 – 20.06 %
2006-07 – 18.65 %
75
76
KARNATAKA
NOTE :- PEAK DEMAND - 7442 MW, ENERGY REQUIREMENT - 44709 MU FOR THE YEAR 2008-2009(AS PER
17TH EPS REPORT), OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) -
MARCH & APRIL
LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
* Peak and Energy availability from all IPPs to be commissioned during 11th Plan are taken in the respective
state.
77
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
LIKELY YEAR /
CAPACITY
S.NO. PROJECT AGENCY STATUS TYPE DATE OF
(MW)
COMMISSIONING
1 KAIGA U-3 NPC Commissioned NUCLEAR 220 2007-08
2 KAIGA U-4 NPC Under Construction NUCLEAR 220 2009-10
SUB TOTAL -Central sector 440
1 VARAHI EXTN KPCL Commissioned HYDRO 115 11.1.2009
2 VARAHI EXTN KPCL Commissioned HYDRO 115 09.02.2009
3 BELLARY U-1 KPCL Commissioned COAL 500 2007-08
4 BELLARY U-2 KPCL Under Construction COAL 500 2011-12
5 RAICHUR U 8 KPCL Under Construction COAL 250 2010-11
SUB TOTAL -state sector 1480
1 TORANGALLU U1, JINDAL Commissioned COAL 300 23.4.2009
TORANGALLU U,2 JINDAL Commissioned COAL 300 24.8.2009
NPC–
2 UDUPI TPP Under Construction COAL 1015 2010-11
LANCO
SUB TOTAL -private sector 1615
TOTAL (KARNATAKA) 3535
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - KARNATAKA
(MW)
CENTRAL-SECTOR
NEYVELI II MC X T U 500.00 500.00 110.00 (2010-2012)
*SIMHADRI ST-II T U 1000.00 1000.00 176.00 (2010-2012)
*ENNORE JV COST T U 1000.00 1000.00 80.00 (2010-2012)
KAIGA U-3 & 4 N U 440.00 440.00 119.00 COMM 220.00 11.04.2007
KUDANKULAM 1&2 N U 2000.00 2000.00 442.00 (2009-2010)
*KALPAKKAM PFBR N U 500.00 500.00 88.00 (2010-2011)
CENTRAL-SECTOR TOTAL:- 1015.00
STATE-SECTOR
BELLARY U-1 & 2 T U 1000.00 1000.00 1000.00 COMM 500.00 03.12.2007
VARAHI EXT. H C 230.00 230.00 230.00 COMM 230.00 09.02.2009
RAICHUR U-8 T U 250.00 250.00 250.00 (2010-2011)
STATE - SECTOR TOTAL:- 1480.00
PRIVATE-SECTOR
UDUPI LANCO T U 1015.00 1015.00 1015.00 (2010-2011)
TORANGALLU T C 600.00 600.00 600.00 COMM 600.00 24.08.2009
PRIVATE-SECTOR TOTAL:- 1615.00
GRAND-TOTAL:- 4110.00
78
8. T&D LOSSES
2003-04 – 23.29 %
2004-05 – 26.08 %
2005-06 – 29.77 %
2006-07 – 25.91 %
PEAK ENERGY
YEAR
Requirment as Actual Requirement as Per Actual
per 17th EPS Demand 17th EPS Requirement
79
80
KERALA
NOTE :- PEAK DEMAND - 3058 MW , ENERGY REQUIREMENT - 16266 MU FOR THE YEAR 2008-2009(AS PER 17TH EPS
REPORT), OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) - MARCH & DECEMBER
* ACTUAL DEMAND HAS ALREADY EXCEEDED THE DEMAND FORCAST OF 17TH EPS FOR THE YEAR 2008-2009 IN THE
MONTH OF JULY,2008.
CENTRAL SECTOR
* SHARE OF CENTRAL SECTOR PROJECTS INCLUDED IN ITEM NO. 1
STATE SECTOR: NIL
PRIVATE SECTOR: NIL
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
81
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - KERALA
(MW)
CENTRAL-SECTOR
NEYVELI II MC X T U 500.00 500.00 70.00 (2010-2012)
*SIMHADRI ST-II T U 1000.00 1000.00 81.00 (2010-2012)
*ENNORE JV COST T U 1000.00 1000.00 37.00 (2011-2012)
KAIGA U-3 & 4 N U 440.00 440.00 35.00 COMM 220.00 11.04.2007
KUDANKULAM 1&2 N U 2000.00 2000.00 266.00 (2009-2010)
*KALPAKKAM PFBR N U 500.00 500.00 40.00 (2010-2011)
CENTRAL-SECTOR TOTAL:- 529.00
STATE-SECTOR
KUTIYADI EXT. H U 100.00 100.00 100.00 (2010-2011)
STATE - SECTOR TOTAL:- 100.00
GRAND-TOTAL:- 629.00
NOTE :- U - UNDER CONSTRUCTION PROJECTS
C – COMMISSIONED
* SHARES FROM CENTRAL SECTOR PROJECTS FOR WHICH M.O.P. ORDERS
ARE YET TO BE ISSUED ARE TENTATIVE
8. T&D LOSSES
2003-04 – 21.63 %
2004-05 – 22.48 %
2005-06 – 23.50 %
2006-07 – 19.11 %
82
TAMIL NADU
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
83
* Peak and Energy availability from all IPPs to be commissioned during 11th Plan are taken in the respective
state.
(MW)
CENTRAL-SECTOR
NEYVELI II MC X T U 500.00 500.00 230.00 (2010-2012)
*SIMHADRI ST-II T U 1000.00 1000.00 198.00 (2010-2012)
*VALLUR (ENNORE) JV T U 1000.00 1000.00 750.00 (2011-2012)
KAIGA U-3 & 4 N U 440.00 440.00 91.00 COMM 220.00 11.04.2007
KUDANKULAM 1&2 N U 2000.00 2000.00 925.00 (2009-2010)
*KALPAKKAM PFBR N U 500.00 500.00 149.00 (2010-2011)
CENTRAL-SECTOR TOTAL:- 2343.00
STATE-SECTOR
BHAWANI BARRAGE H U 60.00 60.00 60.00 (2011-2011)
METTUR EXT. T U 600.00 600.00 600.00 (2011-2012)
VALUTHUR EXTN T C 92.20 92.20 92.20 COMM 92.20 06.05.2008
NORTH CHENNAI EXT T U 600.00 600.00 600.00 (2011-2012)
STATE - SECTOR TOTAL:- 1352.20
GRAND-TOTAL:- 3695.2
8. T&D LOSSES
2003-04 – 17.16 %
2004-05 – 19.28 %
2005-06 – 18.66 %
2006-07 – 19.54 %
84
9.PEAK & ENERGY TABLE
th
(As per 17 EPS Report vs Actual Achieved)
PEAK ENERGY
YEAR
Requirment as Actual Requirement Actual
per 17th EPS Demand as Per 17th EPS Requirement
85
86
PUDUCHERRY
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
* Peak and Energy availability from all IPPs to be commissioned during 11th Plan are taken in the respective
state.
87
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
NIL
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - PUDUCHERRY
(MW)
CENTRAL-SECTOR
NEYVELI II MC X T U 500.00 500.00 15.00 (2010-2012)
*SIMHADRI ST-II T U 1000.00 1000.00 11.00 (2010-2012)
*ENNORE JV COST T U 1000.00 1000.00 5.00 (2011-2012)
KAIGA U-3 & 4 N U 440.00 440.00 6.00 COMM 220.00 11.04.2007
KUDANKULAM 1&2 N U 2000.00 2000.00 67.00 (2009-2010)
*KALPAKKAM PFBR N U 500.00 500.00 5.00 (2010-2011)
CENTRAL-SECTOR TOTAL:- 109.00
GRAND-TOTAL:- 109.00
8. T&D LOSSES
2003-04 – 11.60 %
2004-05 – 18.15 %
2005-06 – 18.48 %
2006-07 – 18.76 %
PEAK ENERGY
YEAR
Requirment as Actual Requirement as Actual
per 17th EPS Demand Per 17th EPS Requiremen
88
EASTERN REGION
NOTE :- PEAK DEMAND - 14037 MW , ENERGY REQUIREMENT - 84601 MU FOR THE YEAR 2008-2009(AS PER
17TH EPS REPORT), OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) -
MARCH
4. CAPACITY ADDITION DURING 11TH PLAN (AS PER PLANNING COMMISSION TARGET)
Sector Hydro Thermal Nuclear Wind Total
Coal Gas Diesel Total
STATE 1050.0 1820.0 0.0 0.0 1820.0 0.0 0.0 2870.0
PRIVATE 1299.0 850.0 0.0 0.0 850.0 0.0 0.0 2149.0
CENTRAL 802.0 11390.0 0.0 0.0 11390.0 0.0 0.0 12192.0
TOTAL 3151.0 14060.0 0.0 0.0 14060.0 0.0 0.0 17211.0
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
Period Peak Peak Peak Peak Energy Energy Energy Energy
Demand Met eficit/ Deficit/ Requi- Avail- Deficit/ Deficit/
(MW) (MW) Surplus Surplus rment ability Surplus Surplus
(MW) (%) (MU) (MU) (MU) (%)
2011-12 19088 19015 -73 -0.4 111802 126510 14708 13.2
* Peak and Energy availability from all IPPs to be commissioned during 11th Plan are taken in the respective
state.
89
90
BIHAR
NOTE :- PEAK DEMAND - 2177 MW , ENERGY REQUIREMENT - 12874 MU FOR THE YEAR 2008-2009(AS PER
17TH EPS REPORT),OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) -
MAR. , AUGUST & OCTOBER
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
91
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - BIHAR
(MW)
CENTRAL-SECTOR
TEESTA ST.V H C 510.00 510.00 55.00 COMM 510.00 28.03.2008
KAHALGAON 6,7 T C 1000.00 1000.00 126.00 COMM 1000.00 31.7.2009
*FARAKKA ST-III T U 500.00 500.00 63.00 (2010-2011)
CENTRAL-SECTOR TOTAL:- 244.00
STATE-SECTOR
GRAND-TOTAL:- 244.00
NOTE :- U - UNDER CONSTRUCTION PROJECTS
C – COMMISSIONED
* SHARES FROM CENTRAL SECTOR PROJECTS FOR WHICH M.O.P. ORDERS
ARE YET TO BE ISSUED ARE TENTATIVE
8. T&D LOSSES
2003-04 – 36.66 %
2004-05 – 38.88 %
2005-06 – 43.96 %
2006-07 – 50.67 %
92
D.V.C.
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
* Peak and Energy availability from all IPPs to be commissioned during 11th Plan are taken in the respective
state.
93
6. PROJECTS PLANNED FOR XITH PLAN (CENTRAL SECTOR) INCLUDING BEST EFFORT
PROJECTS
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - D.V.C.
Project Name Installed Capacity Benefits Commissioned/ Last Unit
Capacity Addition Shares of slipped during Commissioning Date/
(MW) During XIth state 2007-2012 (Likely Date of
Status
Status
(MW)
CENTRAL-SECTOR
MEJIA UNIT-6 T C 250.00 250.00 250.00 COMM 250.00 01.10.2007
CHANDRAPURA 7,8 T U 500.00 500.00 500.00 COMM 250.00 31.03.201
DURGAPUR STEEL T U 500.00 500.00 500.00 (2010-2012)
MAITHON RBC T U 1050.00 1050.00 1050.00 (2010-2012)
TEESTA ST.V H C 510.00 510.00 44.00 COMM 510.00 28.03.2008
*FARAKKA ST-III T U 500.00 500.00 40.00 (2010-2011)
*RAGHUNATHPUR I T U 1200.00 1200.00 1200.00 (2011-2012)
CENTRAL-SECTOR TOTAL:- 3584.00
GRAND-TOTAL:- 3584.00
NOTE :- U - UNDER CONSTRUCTION PROJECTS
C – COMMISSIONED
* SHARES FROM CENTRAL SECTOR PROJECTS FOR WHICH M.O.P. ORDERS
ARE YET TO BE ISSUED ARE TENTATIVE
8. PEAK & ENERGY TABLE (As per 17th EPS Report vs Actual Achieved)
94
JHARKHAND
NOTE :- PEAK DEMAND - 3089 MW , ENERGY REQUIREMENT - 16974 MU FOR THE YEAR 2008-2009(AS PER
17TH EPS REPORT), OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) -
NOVEMBER & DECEMBER
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
95
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
NIL
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - JHARKHAND
(MW)
CENTRAL-SECTOR
TEESTA ST.V H C 510.00 510.00 40.00 COMM 510.00 28.03.2008
KAHALGAON 6,7 T C 1000.00 1000.00 19.00 COMM 1000.00 31.7.2009
*FARAKKA ST-III T U 500.00 500.00 41.00 (2010-2011)
CENTRAL-SECTOR TOTAL:- 100.00
GRAND-TOTAL:- 100.00
8. T&D LOSSES
2003-04 – 25.35 %
2004-05 – 19.62 %
2005-06 – 26.82 %
2006-07 – 26.21 %
PEAK ENERGY
YEAR
Requirment as Actual Requirement Actual
per 17th EPS Achieved as Per 17th EPS Achieved
96
ORISSA
NOTE :- PEAK DEMAND - 3327 MW , ENERGY REQUIREMENT - 20431 MU FOR THE YEAR 2008-2009(AS PER
17TH EPS REPORT),OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) -
MARCH
4. CAPACITY ADDED DURING XTH PLAN:
* Peak and Energy availability from all IPPs to be commissioned during 11th Plan are taken in the respective
state.
97
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - ORISSA
(MW)
CENTRAL-SECTOR
TEESTA ST.V H C 510.00 510.00 105.00 COMM 510.00 28.03.2008
KAHALGAON 6,7 T C 1000.00 1000.00 49.00 COMM 1000.00 31.7.2009
*FARAKKA ST-III T U 500.00 500.00 104.00 (2010-2011)
CENTRAL-SECTOR TOTAL:- 258.00
STATE-SECTOR
BALIMELA ST-2 U 7,8 H C 150.00 150.00 150.00 COMM 150.00 27.03.2008
STATE - SECTOR TOTAL:- 150.00
PRIVATE-SECTOR
STERLITE ENERGY,U2 T U 2400.00 600.00 600.00 (2010-2011)
PRIVATE-SECTOR TOTAL:- 600.00
WITH BEST EFFORTS
STERLITE T U 2400.00 1200.00 1200.00 (2010-2011)
ENERGY,U3,4
TOTAL:- 1200.00
GRAND-TOTAL:- 2208.00
NOTE :- U - UNDER CONSTRUCTION PROJECTS
C – COMISSIONED
* SHARES FROM CENTRAL SECTOR PROJECTS FOR WHICH M.O.P. ORDERS
ARE YET TO BE ISSUED ARE TENTATIVE
8. T&D LOSSES
2003-04 – 57.09 %
2004-05 – 44.02 %
2005-06 – 45.56 %
2006-07 – 40.86 %
98
9. PEAK & ENERGY TABLE
th
(As per 17 EPS Report vs Actual Achieved)
99
100
SIKKIM
NOTE :- PEAK DEMAND - 71 MW , ENERGY REQUIREMENT - 264 MU FOR THE YEAR 2008-2009(AS PER
17TH EPS REPORT), OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) -
MARUARY
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - SIKKIM
(MW)
CENTRAL-SECTOR
TEESTA ST.V H C 510.00 510.00 67.00 COMM 510.00 28.03.2008
KAHALGAON 6,7 T C 1000.00 1000.00 3.00 COMM 1000.00 31.7.2009
*FARAKKA ST-III T U 500.00 500.00 6.00 (2010-2011)
CENTRAL-SECTOR TOTAL:- 76.00
PRIVATE-SECTOR
CHUJACHEN H U 99.00 99.00 99.00 (2010-2011)
PRIVATE-SECTOR TOTAL:- 99.00
WITH BEST EFFORTS
TEESTA ST-III H U 1200.00 1200.00 600.00 (2011-2012)
TOTAL:- 600.00
GRAND-TOTAL:- 775.00
NOTE :- U - UNDER CONSTRUCTION PROJECTS
C – COMISSIONED
* SHARES FROM CENTRAL SECTOR PROJECTS FOR WHICH M.O.P. ORDERS
ARE YET TO BE ISSUED ARE TENTATIVE
8. T&D LOSSES
2003-04 – 54.99 %
2004-05 – 50.49 %
2005-06 – 10.73 %
2006-07 – 23.10 %
9. PEAK & ENERGY TABLE
th
(As per 17 EPS Report vs Actual Achieved)
102
WEST BENGAL
NOTE :- PEAK DEMAND - 6099 MW , ENERGY REQUIREMENT - 34058 MU FOR THE YEAR 2008-2009(AS PER
17TH EPS REPORT), OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) -
MARCH & APRIL
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
* Peak and Energy availability from all IPPs to be commissioned during 11th Plan are taken in the respective
state.
103
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
4. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - WEST BENGAL
(MW)
CENTRAL-SECTOR
*TEESTA ST.V H C 510.00 510.00 122.00 COMM 510.00 28.03.2008
TEESTA L.D. III H U 132.00 132.00 132.00 (2010-2011)
TEESTA L.D. IV T U 160.00 160.00 160.00 (2011-2012)
KAHALGAON 6,7 T C 1000.00 1000.00 55.00 COMM 1000.00 31.7.2009
*FARAKKA ST-III T U 500.00 500.0 0 171.00 (2010-2011)
CENTRAL-SECTOR TOTAL:- 640.00
STATE-SECTOR
BAKRESHWAR 4 T C 210.00 210.00 210.00 COMM 210.00 24.12.2007
BAKRESHWAR 5 T U 210.00 210.00 210.00 2009-2010
PURLIA PSS JV H C 900.00 900.00 900.00 COMM 900.00 20.01.2008
SAGARDIGHI U I & II T C 600.00 600.00 600.00 COMM 600.00 20.07.2008
SANTALDIH EXT,5,6 T C 500.00 500.00 500.00 COMM 500.00 01.04.2009
DURGAPUR DPL T C 300.00 300.00 300.00 COMM 300.00 24.11.2007
STATE - SECTOR TOTAL:- 2720.00
PRIVATE-SECTOR
BUDGE-BUDGE EXT T U 250.00 250.00 250.00 COMM 250.00 (29.09.2009)
PRIVATE-SECTOR TOTAL:- 250.00
GRAND-TOTAL:- 3610.00
104
8. T&D LOSSES
2003-04 – 31.01 %
2004-05 – 28.54 %
2005-06 – 24.84 %
2006-07 – 23.64 %
PEAK ENERGY
YEAR
Requirment as Actual Requirement Actual
per 17th EPS Demand as Per 17th EPS Requirement
105
106
NORTH-EASTERN REGION
NOTE :- PEAK DEMAND - 1888 MW , ENERGY REQUIREMENT - 10193 MU FOR THE YEAR 2008-2009(AS PER
17TH EPS REPORT),OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) -
MARUARY
4. CAPACITY ADDITION DURING 11TH PLAN (AS PER PLANNING COMMISSION TARGET)
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
* Peak and Energy availability from all IPPs to be commissioned during 11th Plan are taken in the respective
state.
107
108
ARUNACHAL PRADESH
NOTE :- PEAK DEMAND - 94 MW , ENERGY REQUIREMENT - 284 MU FOR THE YEAR 2008-2009(AS PER 17TH EPS
REPORT), OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) - MARCH
* ACTUAL DEMAND HAS ALREADY EXCEEDED THE DEMAND FORCAST OF 17TH EPS FOR THE YEAR 2008-2009 IN THE
MONTH OF JULY,2008.
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
109
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
NILL
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - ARUNACHAL PRADESH
(MW)
CENTRAL-SECTOR
BONGAIGAON EXT T U 500.00 500.00 25.00 (2011-2012)
CENTRAL-SECTOR 25.00
TOTAL:-
WITH BEST EFFORTS
BONGAIGAON EXT T U 250.00 250.00 12.00 (2011-2012)
TOTAL 12.00
GRAND-TOTAL:- 37.00
NOTE :- U - UNDER CONSTRUCTION PROJECTS
C – COMMISSIONED
* SHARES FROM CENTRAL SECTOR PROJECTS FOR WHICH M.O.P. ORDERS ARE YET TO BE ISSUED
ARE TENTATIVE
$-The entitled home state share would be allowed as soon as the state Regulatory Commission is set up
in the in the state.
8. T&D LOSSES
2003-04 – 47.54 %
2004-05 – 42.96 %
2005-06 – 49.72 %
2006-07 – 57.79 %
110
ASSAM
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
111
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - ASSAM
(MW)
STATE-SECTOR
LAKWA W.H. G U 37.20 37.20 37.20 (2010-2011)
BONGAIGAON EXT T U 500.00 500.00 254.00 (2011-2012)
STATE - SECTOR TOTAL:- 291.2
WITH BEST EFFORTS
BONGAIGAON EXT T U 250.00 250.00 127.00 (2011-2012)
NAMRUP G U 100.00 100.00 100.00 (2011-2012)
TOTAL 227
GRAND-TOTAL:- 518.2
NOTE :- U - UNDER CONSTRUCTION PROJECTS
C – COMMISSIONED
* SHARES FROM CENTRAL SECTOR PROJECTS FOR WHICH M.O.P. ORDERS
ARE YET TO BE ISSUED ARE TENTATIVE
8. T&D LOSSES
2003-04 – 39.31 %
2004-05 – 51.76 %
2005-06 – 40.34 %
2006-07 – 33.69 %
112
MANIPUR
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
113
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
NIL
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - MANIPUR
(MW)
CENTRAL-SECTOR
BONGAIGAON EXT T U 500.00 500.00 31.00 (2011-2012)
CENTRAL-SECTOR 31.00
TOTAL:-
WITH BEST EFFORTS
BONGAIGAON EXT T U 250.00 250.00 16.00 (2011-2012)
TOTAL 16.00
GRAND-TOTAL:- 47.00
2003-04 – 65.18 %
2004-05 – 70.61 %
2005-06 – 63.12 %
2006-07 – 53.47 %
PEAK ENERGY
YEAR
Requirment as Actual Requirement as Actual
per 17th EPS Demand Per 17th EPS Requirement
114
MEGHALAYA
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
* Peak and Energy availability from all IPPs to be commissioned during 11th Plan are taken in the respective
state.
115
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - MEGHALAYA
(MW)
STATE-SECTOR
MYNTDU ST-1 H U 84.00 84.00 84.00 (2010-2011)
MYNTDU ST-1 add H U 42.00 42.00 42.00 (2011-2012)
BONGAIGAON EXT T U 500.00 500.00 35.00 (2011-2012)
STATE - SECTOR TOTAL:- 161
WITH BES EFFORTS
NEW UMTRU H U 40.00 40.00 40.00 (2011-2012)
BONGAIGAON EXT T U 250.00 250.00 18.00 (2011-2012)
TOTAL 58
GRAND-TOTAL:- 219.00
NOTE :- U - UNDER CONSTRUCTION PROJECTS
C – COMMISSIONED
* SHARES FROM CENTRAL SECTOR PROJECTS FOR WHICH M.O.P. ORDERS
ARE YET TO BE ISSUED ARE TENTATIVE
8. T&D LOSSES
2003-04 - 16.73 %
2004-05 – 28.35 %
2005-06 – 40.19 %
2006-07 – 35.34 %
116
MIZORAM
NOTE :- PEAK DEMAND - 93 MW , ENERGY REQUIREMENT - 318 MU FOR THE YEAR 2008-2009(AS PER
17TH EPS REPORT), OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) -
MAY & DECEMBER
* ACTUAL DEMAND HAS ALREADY EXCEEDED THE DEMAND FORCAST OF 17TH EPS FOR THE YEAR 2008-
2009 IN THE MONTH OF JULY,2008.
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
* Peak and Energy availability from all IPPs to be commissioned during 11th Plan are taken in the respective
state.
117
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
NIL
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - MIZORAM
Project Name Installed Capacity Benefits Commissioned/ Last Unit
Capacity Addition Shares of slipped during Commissioning Date/
(MW) During XIth state 2007-2012 (Likely Date of
Status
Status
Plan (MW) (MW) Commissioning)
Type
(MW)
CENTRAL-SECTOR
BONGAIGAON EXT T U 500.00 500.00 21.00 (2011-2012)
CENTRAL-SECTOR 21.00
TOTAL:-
WITH BEST EFFORTS
BONGAIGAON EXT T U 250.00 250.00 10.00 (2011-2012)
TOTAL 10.00
GRAND-TOTAL:- 31.00
8. T&D LOSSES
2003-04 - 55.54 %
2004-05 – 66.14 %
2005-06 – 39.19 %
2006-07 – 38.18 %
PEAK ENERGY
YEAR
Requirment as Actual Requirement Actual Achieved
per 17th EPS Achieved as Per 17th EPS
118
NAGALAND
NOTE :- PEAK DEMAND - 112 MW , ENERGY REQUIREMENT - 505 MU FOR THE YEAR 2008-2009(AS PER
17TH EPS REPORT), OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) -
SEPTEMBER & DECEMBER
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
119
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
NIL
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - NAGALAND
(MW)
CENTRAL-SECTOR
BONGAIGAON EXT T U 500.00 500.00 21.00 (2011-2012)
CENTRAL-SECTOR 21.00
TOTAL:-
WITH BEST EFFORTS
BONGAIGAON EXT T U 250.00 250.00 11.00 (2011-2012)
TOTAL 11.00
GRAND-TOTAL:- 32.00
8. T&D LOSSES
2003-04 – 55.00 %
2004-05 – 48.26 %
2005-06 - 58.99 %
2006-07 – 54.79 %
PEAK ENERGY
YEAR
Requirment Actual Requirement Actual
as per Demand as Per 17th Requirement
17th EPS EPS
2004-05 74 74 330 330
2005-06 82 90 367 408
2006-07 91 79 408 343
2007-08 101 91 454 377
2008-09 112 95 505 475
2009-10 124 562
2010-11 137 626
2011-12 152 698
120
TRIPURA
NOTE :- PEAK DEMAND - 240 MW , ENERGY REQUIREMENT - 966 MU FOR THE YEAR 2008-2009(AS PER
17TH EPS REPORT),OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) -
JUNE & SEPTEMBER
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
121
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
NILL
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - TRIPURA
(MW)
CENTRAL-SECTOR
BONGAIGAON EXT T U 500.00 500.00 37.00 (2011-2012)
CENTRAL-SECTOR 37.00
TOTAL:-
WITH BEST EFFORTS
BONGAIGAON EXT T U 250.00 250.00 19.00 (2011-2012)
TOTAL 19.00
GRAND-TOTAL:- 56.00
8. T&D LOSSES
2003-04 – 46.44 %
2004-05 – 59.54 %
2005-06 - 41.11 %
2006-07 – 34.75 %
122
A&N ISLANDS
NOTE :- PEAK DEMAND - 56 MW , ENERGY REQUIREMENT - 248 MU FOR THE YEAR 2008-2009(AS PER
17TH EPS REPORT),OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) -
APRIL
4. CAPACITY ADDED DURING XTH PLAN:
CENTRAL SECTOR: NIL
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
* Peak and Energy availability from all IPPs to be commissioned during 11th Plan are taken in the respective
state.
123
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
NIL
8. T&D LOSSES
2003-04 – 25.95 %
2004-05 – 12.63 %
2005-06 – 24.32%
2006-07 – 23.10 %
PEAK ENERGY
YEAR
Requirment as Actual Requirement Actual
per 17th EPS Demand as Per 17th EPS Requirement
124
LAKSHDWEEP
NOTE :- PEAK DEMAND - 9 MW , ENERGY REQUIREMENT - 31 MU FOR THE YEAR 2008-2009(AS PER 17TH
EPS REPORT),OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) - APRIL &
MAY
5. LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
125
6. PROJECTS PLANNED FOR XITH PLAN (STATE SECTOR/PRIVATE SECTOR/CENTRAL SECTOR)
INCLUDING BEST EFFORT PROJECTS
NIL
7. LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
FOR THE STATE : - LAKSHADWEEP
NILL
NOTE :- U - UNDER CONSTRUCTION PROJECTS
C – COMMISSIONED
* SHARES FROM CENTRAL SECTOR PROJECTS FOR WHICH M.O.P. ORDERS
ARE YET TO BE ISSUED ARE TENTATIVE
8. T&D LOSSES
2003-04 – 11.85 %
2004-05 – 10.20 %
2005-06 – 11.19 %
2006-07 – 12.87 %
PEAK ENERGY
YEAR
Requirment Actual Requirement Actual
as per 17th Demand as Per 17th EPS Requirement
EPS
2004-05 7 22
2005-06 7 6 24 24
2006-07 8 6 26 25
2007-08 8 6 28 24
2008-09 9 6 31 24
2009-10 10 34
2010-11 11 37
2011-12 11 40
126