Standard Specification JKR Road
Standard Specification JKR Road
Standard Specification JKR Road
KERAJAAN MALAYSIA
JABATAN KERJA RAYA MALAYSIA
STANDARD SPECIFICATION
FOR
ROAD WORKS
ADDENDUM NO. 1
This Addendum shall be made part of the ‘JKR Standard Specification For Roads Works’
1. Table 4.8 - Gradation Limit For Asphaltic Concrete Clause 4.2.4.2, page S4 – 21
should read as follows :
37.5 mm 100
20.0 mm 76 - 100 72 - 93
14.0 mm 64 - 89 58 - 82
10.0 mm 56 - 81 50 - 75
5.0 mm 46 - 71 36 - 58
3.35 mm 32 - 58 30 - 52
1.18 mm 20 - 42 18 - 38
425 um 12 - 28 11 - 25
150 um 6 - 16 5 - 14
75 um 4 - 8 3 - 8
2. Table 4.9- Design Bitumen Contents Clause 4.2.4.3, page S4 - 23 should read as follows :
ADDENDUM NO. 2
This Addendum shall be made part of the ‘JKR Standard Specification For Roads Works’
Sign faces for permanent traffic sign shall be as where shetting is applied to the extruded
shown on the Drawing and shall comply with section by pressure roller, it shall extend over
the Malaysian Standard Specification for the top and bottom edges of this sections by not
Reflective Sign Faces Materials (MS 1216). All less than 3 mm.
retro-reflective sheeting shall be fixed in accor-
dance with the manufacturer’s instruction. Any cut-outlet letters, numerals, symbols and
borders shall be of material compatible with the
Unless otherwise agreed by the S.O., sign sheeting to which they are applied. They shall
faces shall be formed from a single piece of be applied in accordance with the sheeting
retro-reflective sheeting. manufacturer’s instruction.
Where, with the aggrement of the S.O., more The finish of all sign faces shall be capable of
than one retro-reflective sheeting is used, the passing the tests described in MS 1216, and
number of sheets shall be kept to a minimum. and standard of fabrication and workmanship
All faces up to 1 m in size shall be produced shall be such that under normal conditions of
with a single sheet and no joint will be service and proper maintenance, the sign faces
accepted. shall last not less than 5 years without any
seriousblemishes or defects for Engineering
Only vertical and horizontal joint shall be per- Grade retro-reflective sheeting and 8 years for
mitted and all join in retro-reflective shetting High Intensity and prismatic retro-reflective
shall be overlapped by not less than 6 mm. The sheeting.
overlap in the horizontal joint shall be from the
top and the vertical joint shall be from the left; The Contractor shall furnish to the S.O. a letter
but joints will be only be accepted for prismatic of warranty for the specified period for all sign
retro-reflective sheeting. faces from the manufacturer of the sheeting or
the sign fabricator.
Retro-reflective sheeting shall be applied
evenly over the whole surface of the sign plate The retro-reflective sheeting manufacturer shall
and shall adhere fully. it shall be free from furnish the S.O. written warranty that the fluo-
twists, cracks, folds or cuts, air bubbles and rescent colours shall be durable for a minimum
other blemishes. 3 years for temporary signs.
ADDENDUM NO. 3
This Addendum shall be made part of the ‘JKR Standard Specification For Roads Works’
TABLE I
0.2 -4 200
0.2 +30 120
0.2 +50 50
1.5 -4 80
0.5 +30 50
0.5 +50 20
* The datum mark (arrow) imprinted on the face of the sheeting shall be the datum mark for test
purposes. For the specified 90° rotation angle, the sheeting shall be positioned on the goniometer
so that the direction of this datum mark is perpendicular to the observation plane (this geometry is
equivalent to a 90° orientation angle with a presentation angle of 0° in the measurement geometry
described in Fed. Test Method Standard 370).
i) Daytime Color
Color shall conform to the reqiurement The value shall be determined on a HunterLab
of Table II. Daytime color and Labscan 6000 0/45 spectrocolorimeter with
maximum spectral radiance factor (peak option CMR 559 [or approved equal 0/45
reflectance) of sheeting mounted on (45/0) instrument withcircumferential viewing
aluminium test panels shall be (illumination)]. Computation shall be done in
determined instrumentally in accordance accordance with ASTM E 308 for the 2°
with ASTM E 991. observer.
TABLE II
Color Specification Limit ** (Daytime)
Color 1 2 3 4 Reflectance
Limit Y (%)
X Y X Y X Y X Y Min. Max.
Orange .583 .416 .523 .397 .560 .360 .631 .369 30 -
(New)
Orange
.583 .416 .523 .397 .560 .360 .631 .369 20 45
(Weathered)
Maximum spectral radiance factor, new : 110%, min.
weathered : 60%, min.
** The four pairs of chromaticity coordinates determine the acceptable color in terms of the CIE
1931 standard colorimetric system measured with standard illuminatant D65.
Nighttime color of the sheeting applied to alumium test panel shall be determined
instrumentally in accordance with ASTM E 881 and calculated in the u’, v’ coordinate
system in accordance with ASTM E 308. Sheeting shall be measured at 0.33° observation
and - 4° entrance at 90° rotation. Color shall conform to the requirements of Table III.
TABLE II
Color Specification Limit ** (Nighttime)
Color 1 2 3 4
u’ v’ u’ v’ u’ v’ u’ v’
Orange
(New and .400 .540 .475 .529 .448 .522 .372 .534
Weathered)
v) Impact Resistance.
CONTENT PAGE
SECTION 1
GENERAL
SECTION 1 - GENERAL
Page
Page
ii) Unless stated to the contrary, any g) C.B.R. means California Bearing
dimension of material described means Ratio.
the finished or fully compacted
dimension. h) S.O. means Superintending Officer.
iii) All Standards and Codes of Practice i) B.Q. means Bill of Quantities.
referred to in this Specification shall be
deemed to be the editions current at the
time of Tender. If the Malaysian 1.3.3 Units of Measurement
Standard exists, which the S.O. deems to
be equivalent to the British or other All units of measurement used in this
Standard specified, then the Malaysian Specification and in the Bill of
Standard shall be followed. Quantities shall be in accordance with
the metric system unless otherwise
In the event of any discrepancy between stated.
the provision of this Specification and
the provision within the relevant Where British Imperial units are shown
Standards or Codes of Practice as or stated the following conversions shall
mentioned in this Specification, then the apply :-
provision of this Specification shall take
precedence.
If at any time it should appear to the Any costs incurred under this Section
S.O. that the actual progress of the shall be deducted from the Contract
Works does not conform to the approved Sum. No claim for loss of profit under
programme referred to herein before, the the conditions of this Contract shall be
Contractor shall submit for approval, a deemed to have arisen. No action taken
revised programme showing the under this Section shall in any way
modifications to the previously affect or modify the right of the
approved programme necessary to Government to claim for damages in the
ensure the completion of the whole event of the Contractor's failure to
Works within the time set for complete the Works by the agreed date.
completion.
1.7 MATERIALS OF MALAYSIAN
ORIGIN
1.5 LIMITATION OF SITE
Materials of Malaysian origin where
The Contractor shall ensure that all his available must be used by the Contractor
plants, materials, temporary workshops, to the exclusion of imported materials
stores and offices are kept within the and this requirement shall be allowed
Site at locations approved by the S.O. for in his tender.
Under no circumstances shall the Before the Works or any part thereof are
Contractor be permitted to use imported commenced, the Contractor shall verify
materials unless he can prove to the the levels of the existing ground surface
satisfaction of the S.O. that the within areas where earthworks are to be
materials are not available locally, or if performed and the locations and bed
available are not of an acceptable levels of water-courses. These may
standard. differ from the locations and levels
shown on the Drawings owing to
changes which could have taken place
1.8 SETTING OUT during the interval between the original
survey and construction.
Before commencing the Works at any
location, the Contractor shall provide The levels and dimensions taken by the
and install precast concrete reference Contractor jointly with the S.O. shall
beacons on both sides of the road form the basis of measurement of the
centre-line at a spacing of 300 metres. relevant work quantities.
The beacons shall be firmly sited at right
angles to the centre-line at a distance
from the centre-line of 15 metres or such 1.10 PROTECTION OF WORKS
other distance as directed by the S.O.
The beacons shall be not less than 75 From the commencement of the Works
mm square in plan and shall project at to the date the Works are taken over by
least 600 mm above the surrounding the Government, the Contractor shall
ground. Each beacon shall be clearly take full responsibility for the care there
marked with its chainage and elevation of together with all temporary works
above datum. and in case any damage, loss or injury
shall happen to the Works or to any part
The Contractor shall take all practicable thereof or to any temporary works from
steps to safeguard the beacons including any cause whatsoever, he shall at his
fencing and concreting-in where own cost repair and make good the
necessary in the opinion of the S.O. and same so that at completion, the Works
shall immediately replace any damaged shall be in good order and condition and
beacons. The Contractor shall give the in conformity in every respect with the
S.O. not less than 24 hours notice of his requirements of the Contract and the
intention to set out or give levels for S.O.'s instructions. The Contractor shall
any part of the Works in order that also be liable for any damage to the
arrangements may be made for Works occasioned by him in the course
checking. of any operations carried out during the
Defects Liability Period.
Such submission shall be made at least The Contractor shall provide the
two weeks before the temporary work is necessary attendance whenever required
scheduled to commence. by the S.O. or his representative.
Notwithstanding the approval by the
S.O., the Contractor is solely responsible Notwithstanding any tests which may
for the adequacy and safety of his work have been carried out off the Site, the
and for any necessary modification or S.O. shall be empowered to order
addition whenever found necessary by further tests of any materials or goods to
the S.O. be made on the Site and to reject such
materials or goods should they fail to
pass such tests on Site.
1.12 CONTRACTOR'S
SUPERINTENDENCE When required by the S.O., the
Contractor shall submit a copy of the
The Contractor shall provide all result of any quality control test carried
necessary superintendence during the out by the Contractor on his own during
execution of the Works and as long the progress of the Works.
thereafter as the S.O. may consider
necessary for the proper fulfillment of 1.14 COVERING UP OF WORK
the Contractor's obligations under the
Contract. Before any part of the Works is
permanently covered up, the Contractor
A competent Site Agent, whose shall give due notice to the S.O. for the
appointment shall be approved by the inspection and measurement of
S.O., shall be employed by the dimensions. The S.O. shall attend
Contractor for management on Site. without unreasonable delay for the
The Site Agent shall have the authority purpose of examination and
to receive instructions from the S.O. and measurement unless he considers it
to act on behalf of the Contractor. The unnecessary and advises the Contractor
Site Agent shall be stationed on Site for accordingly.
the whole duration of the Contract and
shall not be replaced without the 1.15 OFFICE ACCOMMODATION FOR
approval of the S.O. S.O. AND HIS STAFF
If the Site Agent needs to be absent from The Contractor shall provide and
Site for more than three (3) consecutive maintain a site office for the use of the
days, he shall give prior notice to the S.O. and his supervisory staff, all in
S.O. who may require the Contractor to accordance with the relevant Drawings
temporarily appoint another Site Agent. inclusive of all furniture and fittings as
shown on the Drawings.
1.13 INSPECTION AND TESTS
The Contractor is permitted to provide a
The S.O. or his representative may at relocatable site office as an alternative to
any stage of the Works carry out the JKR designed type shown on the
inspection, measurement and tests on Drawings.
any part of the Works to ensure
compliance with the requirements of this
Specification and of the Drawings.
Unless otherwise shown on the The Contractor shall arrange for the
Drawings, the site office is to be sited, installation of a telephone with a
constructed and positioned as approved separate connection to the telephone
by the S.O. exchange for the exclusive use of the
S.O. at all times. The telephone shall
The Contractor shall make proper also be be fitted with 4 extensions unless
arrangements for and pay all charges in not required by the S.O. The Contractor
connection with conservancy. The site shall be responsible for the connection
office shall comply with local building to such exchange and the payment of
by-laws. It shall be erected or provided rental for the telephone services but the
by the Contractor within four (4) weeks Government shall reimburse the
from the date of possession of Site. Contractor for the cost of making calls.
1.16 VEHICLES FOR THE S.O.'S When instructed by the S.O., the
STAFF Contractor shall remove all such
buildings and appurtenant works from
The Contractor shall provide new the Site, clean up the area and restore it
vehicles as listed in the B.Q. and to its original condition.
Appendix 1C for the sole use of the S.O.
and his staff at all times. All necessary The Contractor shall provide adequate
fuel, oil and lubricants, general first aid facilities appropriate to the size
maintenance, comprehensive insurances and composition of his staff and labour
and roadtax shall be provided by the force. The Contractor shall afford the
Contractor together with a licensed and S.O.'s site staff full use of the services
competent driver for every vehicle. and facilities as and when required.
Replacement vehicles shall be provided
when normal vehicles are not available 1.18 MATERIAL TESTING
such as during periods of servicing, LABORATORY AND STAFF
maintenance or repair. The vehicles will
revert to the Contractor at the The Contractor shall provide and
completion of the Contract unless maintain a laboratory at the Site
otherwise stated in the B.Q. throughout the duration of the Contract.
Earthworks and pavement construction
1.17 CONTRACTOR'S OFFICE AND will not be permitted to commence until
ACCOMODATION the laboratory and necessary equipment
have been provided.
The Contractor shall provide and
maintain a suitable office for himself The said laboratory shall be in
and his staff in a position or positions to accordance with the Drawings and shall
be approved by the S.O. be equipped as indicated in Appendix
1D. It shall be maintained in a clean
In addition, the Contractor shall provide and tidy condition to the satisfaction of
and maintain temporary accomodation the S.O. The laboratory shall be
and living facilities, stores, workshops, adequately supplied with water and
etc., including all necessary services for electricity.
water supply, drainage and lighting for
his staff. Before any work can The laboratory shall be used exclusively
commence the Contractor shall submit by the S.O. and his staff. However the
to the S.O. details of the proposed Contractor shall provide helpers to assist
buildings and services and shall obtain the S.O. as and when requested.
the S.O.'s approval together with any
necessary approval in writing from the All laboratory equipment shall become
relevant statutory authority. the property of the Contractor on
completion of the Works.
The Contractor shall be responsible for
all fees and other charges or expenses On completion of the Works, the
incurred in connection with such office building shall be removed from the Site
and housing and shall keep the whole and the Site left in a neat and tidy
area in a clean, tidy and well drained condition.
condition.
The Contractor shall make good, at his 1.22 WATER AND ELECTRICITY
own expense, any damage caused by him SUPPLY
to the existing services to the approval of
and in accordance with the instruction of The Contractor shall provide at his own
the appropriate authority or owner risk and cost all water, lighting and
concerned, and shall keep the Government electric power where required for use in
indemnified at all times from all claims, the Works and shall pay all costs, fees
costs and expenses which may arise on and charges and comply with all safety
account of any damage (whether regulations and statutes in connection
permanent, temporary or recurring) to the therewith.
said services.
The Contractor shall also provide and
All such installations which are maintain temporary water storage
encountered in the course of the Works together with any distribution piping
shall be adequately supported, slung-up, which may be necessary.
strutted or otherwise protected from injury
to the satisfaction of the respective
authority. 1.23 PROJECT SIGNBOARD
The temporary diversion or relocation of The Contractor shall provide, erect and
any service within or outside the Works to maintain signboards at locations to be
permit the construction of the Works shall decided by the S.O. and pay all charges
be the responsibility of the Contractor. in connection with this, including
Where a service is required to be obtaining permission, licences and fees,
interrupted or relocated the Contractor etc. Each sign board shall comply with
shall inform and obtain the approval of the the design and specification as shown on
S.O. who shall notify the appropriate the Drawings. On completion of the
authority or owner of the required removal project, the Contractor shall dismantle
and/or relocation. and clear away the signboards as
directed by the S.O.
Temporary diversion shall mean works
involved in the diversion of services that 1.24 PHOTOGRAPHIC RECORD OF
will be reinstated to their original position WORKS
and condition on completion of the works
in the affected areas. In planning his work The Contractor shall provide a camera
for the diversion or relocation of services, of reasonable quality for the purpose of
the Contractor shall make reasonable taking record photographs and slides of
allowance for the time necessary to obtain the Works as and when directed by the
the S.O.'s approval for the work and for the S.O. The Contractor shall bear the costs
appropriate authorities or owners to of providing the film, development of
authorise the work, obtain the necessary film, printing two (2) copies of each
materials and carry out the work. exposure in 3R size and documenting
the photographs in suitable albums.
The Contractor shall not be entitled to any
extension of time due to his failure to The negatives of the photographs shall
allow for a reasonble period of time be the property of the Government and
necessary for obtaining approval and no prints from these negatives may be
completing the work. supplied to any person or persons except
with the approval of the S.O.
APPENDIX 1A
APPENDIX 1B
SCOPE OF WORKS
APPENDIX 1C
Type D - 2000 c.c. four-wheel-drive, air-conditioned Trooper or equivalent with hard top;
APPENDIX 1D
The Contractor shall provide and maintain the following testing laboratory equipment which shall
become the property of the Contractor at the end of the Contract :-
No.
(4) Atterberg limit machine calibrated with a grooving device as specified in B.S. 1377. 1
(8) 203 mm diameter B.S. sieves - 75 mm, 63 mm, 50 mm, 37.5 mm,
28 mm, 25 mm, 20 mm, 14 mm, 12.5 mm, 10 mm, 9.5 mm, 6.3 mm,
5 mm, 4.75 mm, 3.35 mm, 2.36 mm, 2 mm, 1.18 mm, 600 um,
425 um, 300 um, 212 um, 150 um, 75 um. Lid and pan together with
vibrating machine. 1 of each
(14) Standard compaction hammer, electric motor operated, as specified in B.S. 1377. 1
No.
(22) Compression machine suitable for laboratory and field C.B.R.'s with all
fittings necessary for field and laboratory operation as specified in B.S. 1377. 1
(23) C.B.R. moulds fitted with collars and base plates for compaction and soaking
and tripods for small measurement fitted with dial gauges having 0.01 mm
divisions and 25 mm travel as specified in B.S. 1377. 10
(26) Complete field density kit, sand replacement type suitable for volume
measurement of 0.005 cu.m to an accuracy of not less than 0.0001
cu.m as specified in B.S. 1377. 2
(27) Hand auger suitable for boring to depths of 3 m and supplied with 100 mm
diameter heads suitable for boring in cohesive and cohesionless soils. 1
(30) British Standard 1377 - "Methods of Test for Soils for Civil Engineering
Purposes", latest edition. 1
No.
(1) 152 mm x 152 mm x 152 mm standard concrete test cube steel moulds
as specified in B.S. 1881. 6
(1) Metal tray, 0.6 m square or similar suitable for measuring spray rates of
bituminous materials and spread rates of cover aggregate for surface dressing. 4
(2) Metal thickness gauge (or set of slotted sleeves) as specified in M.S. 30 for
determination of aggregate flakiness index. 1
(4) Steel moulds for Marshall test specimens (100 mm diameter) with base,
extension collar, extraction collar and extraction plate as specified in B.S. 598. 6
(5) Extractor for removing Marshall test specimens from moulds without distortion
or shock as specified in B.S. 598. 1
(6) Compaction hammer and automatic compactor for Marshall test specimens as
specified in B.S. 598. 1 of each
(7) Compaction pedestal and mould holder for Marshall test as specified
in B.S. 598. 1 of each
(9) Thermometers for use in laboratory and in asphaltic mixes for Marshall test as
specified in B.S. 598. 2 of each
No.
(13) Pavement coring machine of the thin-walled diamond bit type for
obtaining 100 mm diameter samples of bituminous surfacings. 1
(14) 100 mm diameter thin-walled diamond bits for use with pavement
coring machine. As needed
(16) Machine to rotate the bottles about their longitudinal axes at a speed of
between 10 rev/min to 30 rev/min as specified in B.S. 598. 1
(22) Pressure filter of appropriate size, air pump and funnel for extraction
of bitumen by direct determination as specified in B.S. 598. 1 of each
No.
Further items required for asphaltic concrete :-
(23) Wire basket of 6.5 mm or smaller mesh with wire hanger as specified in
M.S. 30, for determination of specific gravity and water absorption
of aggregates. 1
(30) Compression testing machine with proving ring, capable of applying loads of
up to at least 22 kN at a constant rate of strain of 50 mm + 3 mm per minute
and recording the maximum load achieved as specified in B.S. 598. 1
(31) Dial gauge and mounting assembly for measuring Marshall test flows of up to
10 mm with accuracy of + 0.1 mm as specified in B.S. 598. 1
Testing which is specifically required in the Contract and any test defined in quoted British
Standard Specifications which are required to ensure compliance with the Contract but cannot be
done in the Site testing laboratory shall be carried out at approved laboratories off the Site. These
tests shall be carried out as directed by the S.O. The cost incurred by the Contractor shall be
deemed to have been included in the tendered rates.
APPENDIX 1E
SURVEY EQUIPMENT
The Contractor shall provide and maintain the following instruments and equipment for the
purpose of measurements and setting out. These shall become the property of the Contractor at the
end of the Contract :-
Figure 1.1
SECTION 2
EARTHWORKS
SECTION 2 - EARTHWORKS
Page
Page
not to disturb the topsoil and the This work shall be considered
root systems of grasses and other incidental to the work of clearing,
surface vegetation. No topsoil grubbing and stripping topsoil,
shall be removed from such and shall not be measured for
areas, except as directed by the payment.
S.O., and any topsoil, grasses and
other surface vegetation other 2.1.2.3 Topsoil
wise removed or disturbed shall
be replaced and made good at the Topsoil to be stockpiled for the
Contractor's own expense, all to Works shall be sufficiently fertile
the satisfaction of the S.O. to promote and support the
growth of vegetation, and shall be
2.1.2.2 Areas To Be Cleared,Grubbed taken from such areas where
and Stripped Of Topsoil clearing, grubbing and stripping
topsoil is required as approved or
Except as otherwise shown on directed by the S.O. Before
the Drawings and/or directed by stockpiling, topsoil shall be
the S.O., clearing, grubbing and separated from objectionable
stripping topsoil shall be carried materials, all to the satisfaction of
out in all areas of roadway the S.O. The Contractor shall
excavation and in all areas where arrange for stockpile sites either
embankment is to be constructed, within or outside the road
except that grubbing and reserve, at his own expense, and
stripping topsoil shall not be all to the satisfaction of the S.O.
carried out in those areas where :-
Otherwise, topsoil removed
i) embankment is to be during grubbing and stripping
constructed on earth operations shall be separated
designated as swamp or soft from objectionable materials and
ground; spread within the road reserve or
borrow areas, or otherwise
ii) embankment is to be disposed of, as approved or
constructed to a height at the directed by the S.O.
centre-line of 1.50 metres or
more on ground with a 2.1.2.4 Timber
cross-slope of not more than 1
(vertical) to 30 (horizontal). The ownership of timber is
vested in the Government.
Clearing, grubbing and stripping topsoil shall Saleable timber shall be trimmed
be carried out to the extents deemed necessary and stacked in accordance with
and approved or directed by the S.O. in areas the requirements of the
both inside and outside the road reserve where appropriate Government agency,
channel excavation or other work is required. in accessible places within the
road reserve as approved or
Except where further excavation is required, directed by the S.O.
holes and cavities in the ground surface after
clearing, grubbing and stripping topsoil shall be The Contractor shall have the
filled with materials similar to the adjacent right to use unsaleable timber (or
ground, and such fill shall be compacted to a saleable timber when permission
dry density similar to that of the surrounding is granted in writing by the
material, all to the satisfaction of the S.O.
Cawangan Jalan, Ibu Pejabat JKR, K.L Page 36
FOR INTERNAL USE ONLY Standard Specification For Road Works
2.2.8.2 Turfing
2.2.8.3 Seeding
Turfing shall be carried out as
soon as practicable on all earth Seeding or hydroseeding shall be
slopes and other areas as shown carried out as soon as practicable
on the Drawings and/or where on slopes and other areas as
directed by the S.O. The type of shown on the Drawings and/or
turf shall be as indicated on the directed by the S.O.
Drawings or other alternative
type as approved by the S.O. and The Contractor shall submit to
shall be free of lallang and the S.O. for his consideration and
essentially free of weeds. approval, at least four (4) weeks
in advance of the proposed work,
Turf shall be obtained in full details of his proposed
unbroken sods with a substantial method of seeding or
amount of topsoil and shall be hydroseeding. The information
approximately 250 mm x 250 submitted shall include, but not
mm in size and 100 mm thick, necessarily be limited to, a full
from an approved source, and description of the following
shall be placed in position as aspects of the work :-
soon as practicable after cutting.
iii) the types of grass and legume (if xiv) guarantees of the success of the
any) and strains of seed to be seeding work.
used, and the function, root and
growth characteristics of each All grass shall be regularly watered until
type; the vegetation is satisfactorily
established to the satisfaction of the S.O.
iv) the rates of application of the Any dead grass shall be replaced at the
grass and legume seeds; Contractor's own expense.
SECTION 3
DRAINAGE WORKS
Page
Page
Page
3.10.3 Excavation and Backfilling for Corrugated Metal Pipe Culverts S3-72
3.2.2.1 Excavation
TABLE 3.3 - GALVANISED WIRE SIZES Stone fill for gabions shall be
FOR GABIONS clean rough quarry stone, or pit
or river cobbles, or a mixture of
any of these materials, and shall
be essentially free from dust,
Type of Wire Minimum Diameter
clay, vegetative matter and other
deleterious materials. Individual
pieces of stone shall have least
Selvage (perimeter) wire 3.50 mm dimensions not less than 20 mm
larger than the gabion mesh
openings and greatest dimensions
Mesh wire 2.70 mm not more than 250 mm. The stone
shall be hard, tough, durable and
Tying and connecting 2.20 mm dense, resistant to the action of
air and water, and suitable in all
wire aspects for the purpose intended.
The material shall be approved
by the S.O.
10.0mm 100
5.0mm 90 - 100
2.36mm 75 - 100
1.18mm 55 - 90
600um 35 - 59
300um 8 - 30
150um 0 - 10
This work shall comprise the supply Type A bedding shall consist of
and installation of reinforced grade 20/20 concrete complying
concrete pipe culverts, inclusive of with Section 9 of this
excavation, backfilling, jointing, Specification.
bedding, construction of headwalls,
wingwalls, aprons and sumps and Type B bedding shall consist of
channel protection works, all in clean, natural sand or gravelly
accordance with this Specification sand of suitable gradation and
and the details shown on the quality, approved by the S.O.
Drawings. The material shall have a
maximum particle size of not
more than 12 mm.
3.9.3 Excavation and Backfilling for R.C. Where rock or other hard
Pipe Culverts unyielding foundation
material is encountered in the
3.9.3.1 Excavation trench, it shall be excavated to
a depth below the bottom of
(a) General pipe design levels of at least
300 mm or 12.5 mm per 300
Unless otherwise directed by mm of fill to be placed over
the S.O., prior to construction the top of the pipe, whichever
of a pipe culvert, the earth is greater, up to a maximum
works at the required location of 75% of the internal
shall have been constructed diameter of the pipe. The
to a level at least 600 mm hard material so excavated
above the top of culvert shall be replaced with suitable
design levels or to the top of material uniformly compacted
subgrade levels, whichever is in layers of not more than 150
lower. mm compacted thickness to
provide satisfactory support
Pipe culverts specified to be for the pipe, all to the
constructed in trench satisfaction of the S.O.
conditions shall be excavated
in accordance with Sub- (c) Open Ground Method
Section 3.9.3.1 (b) below.
Where existing ground levels
Where drainage conditions or are above top of bedding
other circumstances so material design levels and
require, the S.O. may direct firm foundation materials are
the Contractor to construct the encountered, excavation and
pipe culvert without first foundation preparation shall
constructing the earthworks to be similar to that described
the level specified above, in in the trench method above.
which case excavation and Otherwise a firm foundation
foundation preparation shall plane shall be prepared, which
be in accordance with Sub- shall be essentially free
Section 3.9.3.1 (c) below. draining along the line of the
culvert, by trimming the
(b) Trench Method existing ground, or such fill as
it is necessary to place and
The trench to receive a culvert compact, over a width
pipe shall be of sufficient sufficient to permit
width and depth to enable the satisfactory construction of
placing of bedding material the pipe bedding, all to the
and construction of pipe joints satisfaction of the S.O. Hard
in accordance with this materials shall be excavated
Specification, and the bottom from the pipe foundation over
of the trench shall be trimmed a width equal to the outside
to a suitably smooth plane diameter of the pipe to the
surface which shall be kept same depth as specified in the
free from water, all to the trench method, and shall be
satisfaction of the S.O. replaced with suitable
3.9.4.4 Spigot and Socket Pipe Culverts Care shall be taken to see that the
rubber ring is adequately
The pipes shall be laid on Type compressed to seal the joint. All
B bedding in conformity with the pipes shall be laid to the
dimensions shown on the satisfaction of the S.O.
Drawings. The bedding material
shall be accurately shaped by a 3.10 CORRUGATED METAL PIPE
template to fit the lower part of CULVERTS
the pipe exterior for a height of at
least 10% of the outside diameter 3.10.1 Description
of the pipe. Gaps shall be left in
the bedding material and recesses This work shall comprise the supply
dug in the earth foundation of and installation of bolted, corrugated
sufficient width and depth to metal pipe culverts inclusive of
accomodate the socket without it excavation, backfilling, jointing,
resting on the bottom of the bedding, construction of headwalls,
recess. The widths of the wingwalls, aprons and sumps and
recesses in the foundation and the channel protection works, all in
bedding shall both exceed the accordance with this Specification
width of the socket by more than and the details shown on the
50 mm. Drawings.
3.10.3 Excavation and Backfilling for placed along the entire length
Corrugated Metal Pipe Culverts of the culvert. The lining
shall be constructed after
Unless otherwise directed and/or completion of earthworks and
approved by the S.O., the pipe wingwalls.
culvert shall be laid in a trench
excavated in accordance with 3.11 PRECAST BOX CULVERTS
Sub-Section 3.9.3.1 (b).
3.11.1 Description
Where the open ground method
is approved, the work shall This work shall comprise the supply
comply with Sub-Section and installation of precast box
3.9.3.1 (c). culverts inclusive of excavation,
backfilling, jointing, bedding,
3.10.4 Installation of Corrugated Metal construction of headwalls,
Pipe Culverts wingwalls, aprons and sumps and
channel protection works, all in
3.10.4.1 General accordance with this Specification
and the details shown on the
The culvert sections shall be Drawings.
assembled, strutted, and
protected during construction 3.11.2 Materials
in accordance with the
manufacturer's instructions. 3.11.2.1 Precast Box Culverts
Special attention shall be
given to the sequence of Precast box culverts shall be of
tightening bolts and the approved manufacture complying
specified torque to be applied with Australian Standard
during assembly. After Specification 1597 Part 1, or any
assembly the bitumen coating equivalent alternative standard
shall, where damaged, be acceptable and approved by the
repaired and made good with S.O.
further application of the
bitumen coating. 3.11.2.2 Cement Mortar
SECTION 4
FLEXIBLE PAVEMENT
Page
Page
% Passing By Weight
B.S. Sieve
Size
A B C D
The top surface of the gravel iv) not less than 80% of particles
surfacing shall have the required retained on the B.S. 4.75 mm
shape, superelevation, levels and sieve shall have at least one
grades, and shall be everywhere fractured face;
within 10 mm of the required
plane or such higher, v) the weighted average loss of
approximately parallel plane, as weight in the sodium sulphate
the S.O. shall approve. soundness test (5 cycles)
when tested in accordance
4.1.4 Crushed Aggregate Roadbase with AASHTO Test Method
T 104 shall be not more than
4.1.4.1 Description 12%;
This work shall consist of vi) the material shall have a CBR
furnishing, placing, compacting value of not less than 80 when
and shaping crushed aggregate compacted to 95% of the
roadbase material on a prepared maximum dry density
and accepted subgrade or lower determined in the B.S. 1377
subbase or subbase in accordance Compaction Test (4.5 kg
with this Specification and the rammer method) and soaked
lines, levels, grades, dimensions for 4 days under a surcharge
and cross-sections shown on the of 4.5 kg;
Drawings and/or as required by
the S.O. vii)the gradation shall comply
with the envelope shown in
4.1.4.2 Materials Table 4.3 for the type
specified.
Crushed aggregate roadbase
material shall be crushed rock, or
crushed gravel, or a mixture of TABLE 4.3 - GRADATION LIMITS FOR
crushed and natural aggregates, CRUSHED AGGREGATE ROADBASE
which is hard, durable, clean and
essentially free from clay and
other deleterious materials. B.S. Sieve % Passing By Weight
Size
The material shall conform to the
Type I Type II
following physical and
mechanical quality requirements:-
50.0 mm 100 100
37.5 mm 95 - 100 85 - 100
i) the plasticity index shall be not - 70 - 100
28.0 mm
more than 6; 20.0 mm 60 - 80 60 - 90
10.0 mm 40 - 60 40 - 65
ii) the aggregate crushing value 5.0 mm 25 - 40 30 - 55
when tested in accordance with 2.36 mm 15 - 30 -
M.S. 30 shall be not more than 2.00 mm - 20 - 40
30; 600 um 8 – 22 -
425 um - 10 - 25
iii) the flakiness index when tested in 75 um 0–8 2 - 10
accordance with M.S. 30 shall be
not more than 30;
% Passing By Weight
B.S.
Sieve
Size Nominal Nominal Nominal Nominal
20 mm 14 mm 10 mm 6 mm
Chippings Chippings Chippings Chippings
25.0 mm 100 - - -
20.0 mm 85 - 100 100 - -
14.0 mm 0 - 20 85 - 100 100 -
10.0 mm - 0 - 20 85 - 100 100
6.3 mm - - 0 - 20 85 - 100
4.75 mm 0-5 0-5 0 - 10 0 - 25
2.36 mm 0-2 0-2 0-2 0 - 10
20.0 mm 76 - 100 72 - 93
14.0 mm 64 - 89 58 - 82
10.0 mm 56 - 81 50 - 75
5.0 mm 46 - 71 36 - 58
3.35 mm 32 - 58 30 - 52
1.18 mm 20 - 42 18 - 38
425 um 12 - 28 11 - 25
150 um 6 - 16 5 - 14
75 um 4-8 3-8
all in accordance with the A sample of each trial mix (i.e. each
manufacturer's instructions. In such a combination of trial gradation and
case, the agent shall be added to the bitumen content) shall be subject to a
bitumen binder used in the bitumen comprehensive Marshall method test
stripping tests in the appropriate amount and analysis as follows :-
and manner.
i) preparation of specimens for the
Aggregate which does not perform standard stability and flow test in
satisfactorily in the bitumen stripping accordance with AASHTO Test
tests, using the approved adhesion and Method T 245 using the 75
anti-stripping agent when appropriate, blows/face compaction standard;
shall not be used in asphaltic concrete.
ii) determination of the bulk
4.2.4.3 Asphaltic Concrete Mix Design specific gravity of the specimens
in accordance with AASHTO
(a) Job Mix Formulae Test Method T 166;
Voids in aggregate
filled with bitumen 75% - 85% 65% - 80%
vii)the bitumen content (by weight of As a result of the plant trials, the S.O.
total mix); may require amendments to the job mix
formulae, further tests and analyses,
viii)the dry and wet mixing times if a and possibly additional plant trials
batch plant is to be used, or the before finally approving the mixes for
mixing time if a continuous mix full scale production and use in the
plant is to be used; Works.
ix) the full results of the (c) Compliance with the Job Mix Formulae
comprehensive Marshall method
tests and analyses as described The S.O.'s final approval of the job mix
above for each trial mix used in formulae shall bind the Contractor to
determining the job mix formula. furnish asphaltic concrete mixes
meeting the precise gradations and
The S.O. may require changes of any bitumen contents specified in these
of the factors in each proposed job formulae within the tolerances set
mix formula and further tests and forth in Table 4.11.
analyses in order to attain optimum
quality of the asphaltic concrete Modifications to a job mix formula may
mixes. only be made with the approval of the
S.O. Should the S.O. at any time have
(b) Plant Trials reason to believe that the materials and
methods of mixing and laying are
After having received the S.O.'s different from those approved, he shall
preliminary approval of his proposed so advise the Contractor, and may order
job mix formulae, the Contractor that asphaltic concrete works be
shall arrange to mix, lay and compact discontinued pending further trials and
asphaltic concrete conforming to the testing.
proposed formula for each class of mix
required in the Works. A minimum of
10 tonnes of each mix shall be placed
in trial areas to demonstrate to the
satisfaction of the S.O. that the mixing,
laying and compacting equipment
conforms to the requirements of this
Specification, and that the proposed
mixes are satisfactory. The trial areas
shall not be part of the Contract Works
but shall be provided by the Contractor
at his own expense. They shall be
approved by the S.O.
Bitumen. + 0.2%
Fractions of combined
aggregate passing 5.0 mm
and larger sieves. + 5.0%
Fractions of combined
aggregate passing 3.35 mm + 4.0%
and 1.18 mm sieves.
Fractions of combined
aggregate passing 425 um + 3.0%
and 150 um sieves.
Fraction of combined
aggregate passing 75 um + 2.0%
sieve.
4.2.4.4 Equipment
Road cleaning equipment will be The mixing plant shall have a capacity
required where asphaltic concrete is suited to the Works and sufficient to
to be laid on a surface which is not enable the paver to operate more or less
to receive a tack coat. The continuously when paving at normal
equipment shall be the same as that speeds at the required thicknesses. The
required for preparing a surface for plant shall be so designed as to enable
a tack coat, and shall include a consistent production of asphaltic
power broom and compressed air
concrete mixes within the tolerances The plant shall be provided with
prescribed in this Specification, all to accurate mechanical means for
the satisfaction of the S.O. uniformly feeding the aggregates into
the dryer so that uniform production and
Scales for all weigh boxes or hoppers temperature of the heated aggregates
shall be of the springless dial type, will be obtained. A separate feed bin
accurate to within 0.5% of the with an adjustable gate opening shall be
maximum load that may be required. provided for each aggregate to be
Scale dials and pointers shall be easily included in the combined aggregate for
read from their operator's normal the mix; normally four bins will be
position without significant parallax required. The feed bins and gates shall
errors. Scales shall be substantially be so constructed and equipped that they
constructed so that they shall maintain shall be readily accessible for calibrating
their accuracy after initial adjustment. at all times, and shall provide for a
The Contractor shall furnish not less continuous and uniform flow of each
than ten 25 kg test weights at the plant aggregate required in the mix.
for checking, adjusting and calibrating
scales. The plant shall have a rotary drum dryer
of satisfactory design for drying and
Tanks for storage of bitumen shall have heating the combined aggregate so that
a capacity suited to the proposed rate of its temperature will be at the required
utilization of the material and the level at the time it is mixed with the
method and frequency of its delivery to bitumen. The burner shall be so
the Works, all to the satisfaction of the designed that complete combustion of
S.O. The tanks shall be provided with the fuel will be obtained, and the
means of measuring the volume of their aggregate will remain clean and not
contents at all times and of drawing off become coated with soot or oil.
samples of the contents. The bitumen
feeding system shall provide for The plant shall be equipped with four
continuous circulation of hot binder (or more) screens, the smallest of which
through the system and back into the shall generally be not more than 3.2
feed tank. The end of the return line mm. The screens shall have a normal
discharging into the feed tank shall capacity slightly in excess of the
always be kept submerged in the maximum output of the mixing plant.
bitumen in the tank in order to prevent The screens shall be readily accessible
oxidation of the returning hot binder. for inspection.
The storage tanks, and where necessary
barrel decanters, and all elements of the The plant shall include four (or more)
bitumen feeding system shall be storage bins for screened aggregates,
equipped with heating systems or each with a capacity of not less than
insulating jackets as necessary to twice the pugmill dead load capacity.
provide for effective and positive control The bins shall be arranged so as to
of the temperature of the bitumen at all provide separate dry storage for each
times up to the temperature required for screened fraction of the aggregate. Each
utilisation. . The method of heating bin shall be provided with an overflow
shall be such that neither flames nor the pipe of such size and location as to
products of combustion shall come into prevent any backing up of material into
direct contact contact with the bitumen other bins. Each bin shall be so
or the casing of its immediate container, constructed that representative aggregate
and such that no portion of the bitumen samples can be readily obtained, and
shall be subject to overheating.
Cawangan Jalan, Ibu Pejabat JKR, K.L Page 106
FOR INTERNAL USE ONLY Standard Specification For Road Works
shall have means for observing the the truck loading area, which shall be
aggregate level. Separate dry storage kept free from drippings from the mixer.
shall be provided for mineral filler, and
the plant shall be satisfactorily equipped Special Requirements for Batch Plants
to feed filler into the mixer.
Each storage bin for screened aggregate
Satisfactory means by either weighing shall be provided with a bottom outlet
or metering shall be provided to obtain gate so constructed as to prevent leakage
the prescribed amount of bitumen in the when closed. These gates shall have a
mix within the specified tolerance. quick and complete closing action.
Means shall be provided for checking
the quantity or flow rate of binder The plant shall be equipped with a
entering the mixer. Suitable means shall weigh box or hopper for accurately
be provided for maintaining the weighing out aggregate from each of the
prescribed temperature of the bitumen in screened aggregate storage bins. The
the pipelines, weigh bucket or flow weigh box or hopper shall be
meter, and spray bars. suspended from its scale's lever
mechanism and shall be sufficiently
An armoured thermometer with a large to hold a full batch equal to the
range of 30 oC to 200 oC shall be fitted pugmill capacity without hand raking or
in the bitumen feed line at a suitable spilling of the aggregate. The discharge
location near the discharge valve at the gate shall be so constructed as to allow
mixer unit. Suitable dial-scale mercury rapid and complete emptying of the
actuated thermometers, electric weigh box or hopper into the mixer, and
pyrometers or other thermometric prevent leakage when closed.
instruments shall be fitted at the
discharge chute of the dryer and in each The plant shall be equipped with a
hot aggregate storage bin to indicate the binder weigh bucket which shall be
temperatures of the heated aggregates. charged through a fast acting non-drip
valve in the binder feed pipe located
The plant shall be equipped with a dust directly over the bucket. The bucket
collector so constructed as to waste the shall be suspended from its scale's lever
material collected or feed it uniformly to mechanism and shall have a capacity
the heated aggregate. sufficient to weigh out binder up to 20%
of the weight of the pugmill dead load
The plant shall be equipped with capacity. The bucket shall have a
adequate and safe stairways to the discharge mechanism which shall
mixing platform and sampling locations, provide for rapid and complete
and guarded ladders and cat-walks shall emptying of the bucket in a thin uniform
provide access to all other positions as sheet or multiple sprays over the full
necessary for proper operation, length and width of the mixer. The
inspection and maintenance of the plant, dicharge mechanism shall not leak or
all to the satisfaction of the S.O. All drip when closed.
gears, pulleys, chains, sprockets and
other dangerous moving parts shall be The batch mixer shall be a suitable
properly guarded and protected. Ample twinshaft pugmill, with a capacity of at
and unobstructed space shall be least 500 kg of asphaltic concrete,
provided on the mixing platform, and capable of producing a thoroughly
clear and unobstructed passage shall be homogeneous mixture. The clearance of
maintained at all times in and around the paddle blades from all fixed and
moving parts of the mixer shall be not producing an accurate and continuous
more than 20 mm. If the pugmill is not blend of the individual aggregate sizes
enclosed it shall be equipped with a dust from the cold feed compartment.
hood to prevent loss of fines from the
mixture. The discharge gate shall be so The drum mixer shall be of an inclined,
constructed as to allow rapid and oil-fired and parallel flow type in which
complete emptying of the mixer, and the aggregates and exhaust gases flow in
prevent leakage of any mix constituent the same direction. The drum mixer
when closed. length to diameter ratio shall be such as
to ensure efficient drying and intimate
The mixer shall be equipped with an mixing of aggregate, filler and binder
accurate time lock system for over the full range of rated operating
controlling the operations of a complete efficiencies. A bypass chute shall be
mixing cycle. It shall lock the aggregate incorporated for sampling of cold
weigh box or hopper gate after charging aggregate.
the mixer with aggregate, until the
closing of the mixer gate at the Freshly mixed material shall be
completion of the mixing cycle; it shall delivered and stored in a surge silo
lock the binder weigh bucket discharge through a proper conveyor system.
mechanism during the dry mixing and
wet mixing periods. (The dry mixing Special Requirements for Continuous
period is defined as the interval of time Mix Plants
between the opening of the aggregate
weigh box or hopper gate and the start Each storage bin for screened aggregate
of discharging the binder weigh bucket. shall be provided with an accurately
The wet mixing period is defined as the controlled variable orifice gate
interval of time between the start of discharging on to an aggregate feed
discharging the binder weigh bucket and mechanism. The discharge orifice shall
the opening of the mixer gate.) The dry be rectangular with one dimension
and wet mixing periods shall both be variable by means of an adjustable and
adjustable in increments of not more lockable gate, which shall have an
than 5 seconds from zero to not less than indicator showing the distance it is open.
120 seconds total for dry and wet These gates shall be used for accurately
mixing. proportioning the screened aggregates
for the mix.
Special Requirements for Drum Mix
Plants The plant shall have means of
calibrating the aggregate bin discharge
The cold material feeder unit shall gate openings by weighing test samples
consist of not less than 5 compartments obtained by diverting the aggregate fed
with suitable heaped capacity out of each bin into a suitable test box.
appropriate for the plant. Each bin shall Test boxes shall have a capacity of not
be provided with a control gate and less than 100 kg each.
measuring feeder suitable for accurate
blending of the aggregates on to the cold The plant shall have satisfactory means
feed collecting conveyor. The cold feed of effecting positive interlocking control
system shall incorporate a device for between the flow of screened aggregates
moisture compensation capable of from the storage bins and the flow of
binder from the meter or other
proportioning device. This control shall
The aggregates shall be fed into the For each batch the screened hot
dryer at a uniform rate proportioned in aggregates shall be weighed out into
accordance with the appropriate job mix the aggregate weigh hopper in
formula. The rate of feed for each accordance with the proportions
aggregate shall be maintained within prescribed in the appropriate job mix
10% of the rate prescribed, and the formula; the sequence of weighing
total rate of feed shall be such that out shall commence with the largest
the plant's screens shall never be sized aggregate and progress down
overloaded. to the fines, unless the S.O. shall
otherwise approve. Mineral filler
The aggregates shall be dried and heated shall be weighed out into the filler
so that when delivered to the mixer they weigh hopper, where this is
shall be at a temperature in the range provided, or added last to the
150ºC to 170ºC. aggregate weigh hopper, in
accordance with the job mix formula
Immediately after heating, the proportions.
aggregates shall be screened into four
(or more) fractions which shall be The hot binder shall be weighed out
separately stored in the hot aggregate into the binder weigh bucket in
storage bins in readiness for mixing. ccordance with the proportions
prescribed in the job mix formula.
The hot aggregates and filler shall be shall be as prescribed in the job mix
discharged into the pugmill and formula; this shall be sufficient so
mixed dry for the dry mixing time that all particles of aggregate are
prescribed in the job mix formula, uniformly coated with bitumen, and
which shall usually be in the range 5 shall usually be 45 seconds or more
to 10 seconds. The hot binder shall for dense graded mixtures.
then be added and wet mixing per
formed for the wet mixing time The plant shall be so adjusted as to
prescribed in the job mix formula; maintain the level of mixture in the
this shall be sufficient so that all pugmill such that the tips of the
particles of aggregate are uniformly paddle blades just break out of the
coated with bitumen, and shall mixture at the height of their action.
usually be 45 seconds or more for
dense graded mixtures. (f) Transportation of Asphaltic
Concrete
The volume of each batch shall be
such that the tips of the pugmill Asphaltic concrete shall be
paddle blades just break out of the transported from the mixing plant to
mixture at the height of their action. the site of the paving works in loads
of not less than 5 tonnes using
After the completion of wet mixing, tip-trucks as specified in
each batch of asphaltic concrete shall
be discharged from the pugmill Sub-Section 4.2.4.4 (c). Except
either into a storage hopper or where asphaltic concrete is to be
directly into a truck for hauling to hand laid, it shall be discharged
the paving site. Care shall be taken directly into the paver hopper, as
that no segregation of the mix required, from the tip-trucks. Care
occurs. shall be taken in the truck loading,
hauling and unloading operations to
Mixing in Continuous Mix Plants prevent segregation of the mix.
During transportation, the asphaltic
The screened hot aggregates and concrete shall be protected from
filler shall be fed continuously from contamination by water, dust, dirt
their storage bins in accordance with and other deleterious materials.
the proportions prescribed in the
appropriate job mix formula, The temperature of asphaltic
combined in the plant, and fed concrete immediately before
continuously into the mixer. The hot unloading from the truck either into
binder shall be sprayed on to the the paver hopper or on to the road
combined aggregate as it enters the for hand spreading shall be not less
pugmill at the rate required to than 125ºC. Any load which has
achieve the bitumen content pre cooled below the specified
scribed in the job mix formula. The temperature in the truck shall be
materials shall then be carried rejected for use in the Works and
through the pugmill and in the removed from the Site of the Works.
process be thoroughly mixed by
the action of the paddles and dis (g) Laying Asphaltic Concrete
charged over the dam into the stor
age hopper. The mixing time (as The sequence of laying operations
defined in Sub-Section 4.2.4.4 (b) shall be planned in advance by the
Contractor and approved by the S.O.
Cawangan Jalan, Ibu Pejabat JKR, K.L Page 112
FOR INTERNAL USE ONLY Standard Specification For Road Works
Generally each paving layer shall and before laying restarts after each
have a compacted thickness of not interruption of the paving operation.
less than twice the nominal
maximum aggregate size of the As far as is practicable, the paver
mixture, and not more than 100 mm. shall be operated continuously and
Where applicable, e.g. on the supply of bituminous mix shall
superelevated sections and on be regulated so as to enable
carriageways with cross-slope in one continuous paving. Transverse joints
direction only, laying shall in a paving lane shall be kept to a
commence along the lower side of practicable minimum, and
the carriageway and progress to the intermittent stopping and restarting
higher side. Laying shall not be of the paver shall be avoided as far
carried out in a downhill direction as is practicable.
along any section of road.
Care shall be taken that no
As far as is practicable, laying shall bituminous mix is placed on
be carried out using a paver expansion joints at bridges,
approved by the S.O. Hand-casting inspection covers for utilities ducts,
of bituminous mix on to the machine drainage and sewerage manholes and
finished surface shall be kept to the the like, and that catchpits, drainage
practicable minimum necessary for openings through kerbs, etc., remain
correcting blemishes and properly open and serviceable.
irregularities. In any areas During laying operations, such areas
inaccessible to the paver, laying shall and openings shall be protected by
be carried out by hand methods suitably shaped and secured boards
using rakes, lutes and other hand or other materials approved by the
tools, all to the satisfaction of the S.O., and compaction of mix in the
S.O. All laying of bituminous mix immediately surrounding or adjacent
shall be such that after compaction areas shall be completed by hand
by rolling the specified course or methods, all to the satisfaction of
layer thickness and surface profile the S.O. Alternatively, bituminous
shall be achieved. Care shall be mix shall be laid and compacted by
taken to achieve a uniform surface hand methods as necessary around
texture free from indentations, surfacing discontinuities of these
ridges, tear marks or other types, all to the satisfaction of the
irregularities, and to prevent S.O.
segregation of the mix.
(h) Construction Joints
At the commencement of initial
rolling the temperature of asphaltic Existing bituminous surfacing which
concrete shall be not less than new bituminous mix is to adjoin
110ºC. Material which has cooled shall be cut back to present a
below the specified temperature straight, vertical edge not less than
before laying shall not be used and 25 mm deep and a smooth transition
shall be removed from the Site of the section not less than 0.5 metre long
Works. The Contractor shall provide against which to lay the new
accurate thermometers at the paving material. The specified thickness of
site at all times, and shall check the the new surfacing shall be built up
temperature of asphaltic concrete in gradually from the vertical joint to
the paver hopper at regular intervals avoid any bumps or ridges across the
carriageway.
Cawangan Jalan, Ibu Pejabat JKR, K.L Page 113
FOR INTERNAL USE ONLY Standard Specification For Road Works
heavy vehicle shall be allowed to the average thickness over any 100
stand on newly laid bituminous mix metre length shall be not less than
before compaction has been the required thickness, and the
completed and the material has minimum thickness at any point
thoroughly cooled and set. Rolling shall be not less than the required
shall continue as long as is necessary thickness minus 5 mm.
to achieve the appropriate
requirement as follows :- The top surface of a wearing or
binder course shall have the required
Type of Pavement Required Compacted
shape, superelevation, levels and
Layer Density
grades, and shall be everywhere
Wearing course 98 - 100% Marshall within the tolerances specified in
density Sub-Section 4.4.
Binder course 95 - 100% Marshall
density (k) Opening to Traffic
Binder 3.5 " 4.0 " 5.1 " 4.7 " 4.7 " 5.0 " 4.9 "
Content
± ± ± ± ± ± ±
0.5% 0.5% 0.5% 0.6% 0.6% 0.5% 0.5%
Class SR2 40 18 4 2 8 mm
Class SR3 60 27 4 3 12 mm
The class of Surface Regularity for each portion of the Works shall be as stated on
the Drawings or in the Bills of Quantities.
SECTION 5
PORTLAND CEMENT
CONCRETE PAVEMENT
Page
Page
Hardness. IRHD 55 + 5
- hardness IRHD 0 to + 10
- tensile strength % - 20
- elongation at break. % - 25
Forms shall be cleaned and oiled form paving plant. (Each guide
immediately before each use. wire shall be at a constant height
The rails or running surfaces shall above and parallel to the required
be kept clean in front of the edges of the slab within a vertical
wheels of any paving machines. tolerance of ±3 mm. In addition,
The forms shall be straight within one of the wires shall be at a con
a tolerance of 3 mm in 3 m. stant horizontal distance from the
required edge of the pavement
The forms shall be bedded on within a lateral tolerance of ±10
low moisture content cement mm.
mortar and set to the pavement
surface level as described in the The guide wires shall be
Contract within a tolerance of ±3 supported from stakes not more
mm. The bedding shall not than 8 m apart by connectors
extend under the slab. There capable of fine horizontal and
shall be no vertical step between vertical adjustment. The guide
the ends of adjacent forms greater wire shall be tensioned on the
than 3 mm. The horizontal stakes so that a 500 gramme
alignment for forms shall be to weight shall produce a deflection
the required alignment of the of not more than 20 mm when
pavement edge as described in suspended at the mid-point
the Contract within a tolerance of between any pair of stakes. The
±10 mm. The mortar or ends of the guide wires shall be
concrete bedding shall be broken anchored to fixing points which
out after use. shall be not closer to the edge of
the slab than the row of stakes
Prior to concreting, the forms and in no circumstances shall a
shall be approved by the S.O. guide wire be anchored to a
stake.
Forms shall not be removed
earlier than 6 hours after the The stakes and guide wires shall
completion of the construction of be checked and approved by the
the slab. Care shall be taken to S.O. prior to concreting.
prevent damage to the concrete
and any projecting tie bars during 5.4.2.2 Construction by Fixed Form
the removal of the forms. If the Paving Machine
removal of forms results in any
damage to the concrete the period A fixed form paving train shall
of 6 hours shall be increased to consist of separate powered
that which is necessary to avoid machines which spread, compact
further damage and the and finish the concrete in a
Contractor shall make good the continuous operation.
damaged areas.
Concrete shall be discharged
b) Guide Wires without segregation into a hopper
spreader which is equipped with
Unless otherwise agreed by the the means to control its rate of
S.O., a guide wire shall be deposition on to the subbase or
provided along each side of the on to the lower layer. . The con
slab to be constructed by slip crete shall be spread in each layer
A slip form paving train shall Slip form paving machines shall
consist of powered machines have vibration of variable output,
which spread, compact and finish with a maximum energy output
the concrete in a continuous of not less than 2.5 kW per metre
operation. of slab per 300 mm depth of slab
for a laying speed of up to 1.5 m
A slip form paving machine shall per minute or pro rata for higher
compact the concrete by internal speeds. The machines shall be of
vibration and shape it between sufficient mass to provide
sliding side forms or over fixed adequate reaction on the traction
side forms by means of either a units to maintain forward
conforming plate or by vibrating movements during the placing of
and oscillating finishing beams. concrete in all situations.
area of the slab, and adjacent to the As soon as surplus water has risen to
side forms or the edge of a the surface, the pavement shall be
previously constructed slab. given a broomed finish.
The surface shall be regulated and 5.4.4.1 Side Forms for Manual
finished to the level of the top of the Construction
forms or adjacent slab or pavement
layer by using an approved portable All side forms shall be made of
hand screed. The screed shall be at steel and be sufficiently robust
least 600 mm longer than the width and rigid to withstand
of the slab to be struck off and construction forces. Timber
compacted. It shall be of approved forms shall only be used for work
shape, sufficiently rigid to retain its which is less than 200 m in
shape and constructed either of metal length.
or of other material shod with metal.
The forms shall comply with
Compaction shall be attained by other requirements of Sub-
raising and dropping the screed in Section 5.4.2.1 as appropriate.
successive positions until the
required compaction and reduction 5.5 JOINTS
of surface voids is secured.
Joints shall be constructed as specified
The screed shall then be placed on herein and/or as directed or approved by
the forms and slid along them, with the S.O. Before any joint materials are
out lifting, in a combined set in place, the underlying pavement
longitudinal and transverse shearing course at those locations shall have been
motion moving always in the approved by the S.O.
direction in which the work is
progressing. If necessary, this shall Preformed expansion joint filler shall be
be repeated until the surface is of placed around each structure which
uniform texture, true to grade and extends into or through the pavement
contour, and free from porous areas. over the full interface with the concrete
pavement slab before concrete is placed.
After the concrete has been struck
off and compacted, it shall be further 5.5.1 Transverse Expansion Joints
smoothed, screeded and compacted
by means of a longitudinal hand float The components for each transverse
or other equipment as approved by expansion joint shall be assembled in
the S.O. advance and placed in position as a
unit.
Details of joints shall be as shown on
the Drawings. Joint grooves shall be Each assembly shall consist of an
constructed in compliance with Sub- installing template, preformed joint
Section 5.5. Any irregularities at wet filler of the required dimensions in a
formed joint grooves shall be single piece, dowel bars and sleeves
rectified by suitable means approved of the required sizes and lengths at
by the S.O. the required locations, and spacing
and supporting elements for the
The concrete shall be cured in dowel bars, as shown on the
compliance with Sub-Section 5.8. Drawings.
compound, and the joint faces shall units and power to complete the
be clean and surface dry when the sawing with a water-cooled diamond
seal is applied. edge saw blade, or an abrasive
wheel, to the required dimensions
The sealing material shall be applied and at the required rate. The
in accordance with the dimensions Contractor shall provide at least one
shown on the Drawings or as stand-by saw in good working order.
directed by the S.O. An ample supply of saw blades shall
be maintained at the site of the work
Sealing material to be applied hot at all times during sawing operations.
shall be stirred during heating so that The Contractor shall provide
localized overheating does not occur. adequate artificial lighting facilities
The pouring shall be done in such a for night sawing. All of this
manner that the material will not be equipment shall be on the job before
spilled on to the exposed surfaces of and continuously during concrete
the concrete. Any excess material on placement.
the surface of the concrete pavement
shall be removed immediately and 5.6 SURFACE TEXTURE
the pavement surface cleaned. The
use of sand or similar material as a 5.6.1 Texture of Running Surfaces
cover for the seal will not be
permitted. After the final regulation and before
the application of the curing
Preformed compression seals for membrane, the surfaces of concrete
sealing joints shall be of the cross- slabs to be used as running surfaces
sectional dimensions shown on the shall be brush-textured in a direction
Drawings. Seals shall be installed at right angles to the centre line of
using suitable tools, without the carriageway.
elongation, and secured in place with
an approved adhesive which shall The type of brush and method of
cover both sides of the concrete application for surface texturing shall
joints. The seals shall be installed in be approved by the S.O. based on
a compressed condition and shall at trial brushing to be conducted by the
time of placement be below the level Contractor.
of the pavement surface by
approximately 5 mm. The seals The texture depth shall be
shall be in one piece for the full determined by the sand patch test as
width of each transverse joint. described herein.
Notwithstanding the above, all The average texture depth for each
sealants shall be applied or installed set of 10 tests shall not be less than
in accordance with the 0.75 mm and not more than one test
manufacturer's instructions or of each set shall show a texture depth
recommendations. of less than 0.65 mm. In no case
shall the maximum texture depth
5.5.6 Concrete Saw exceed 2 mm.
5.6.2 Measurement of Texture Depth : 31000 where D is the diameter of the of the
Sand Patch Method D x D patch in mm.
The compound shall form a uniform, In addition, the entire surface shall be
continuous, coherent film that shall not protected from the effects of solar
crack or peel and shall be free from pin radiation by the use of frames
holes or other imperfections. If covered with material with heat and
discontinuities, pin holes or abrasions rain deflecting properties for not less
exist, an additional coat shall be applied than 4 hours after application of the
within 30 minutes to the affected areas. curing compound.
Necessary precautions shall be taken to
ensure proper curing at the joints and Notwithstanding the foregoing, concrete
that none of the curing compound enters surfaces which are subjected to heavy
joints which are to be sealed with joint rainfall within 3 hours after the curing
sealing compounds. Rope of moistened compound has been applied shall be
paper, fibre or other suitable material resprayed, all as specified above at no
shall be used to seal the top of the joint additional cost.
opening, and the concrete in the region
of the joint shall be sprayed with curing Concrete liable to be affected by running
compound immediately after the rope water shall be adequately protected from
seal has been installed. damage during the setting period.
SECTION 6
ROADSIDE FURNITURE
Page
Page
Where top and bottom light spill Only vertical and horizontal
screens are required as shown on joints shall be permitted and all
the Drawings, these shall extend joints in plastic sheeting shall be
for the whole width of the sign, overlapped by not less than 6
be fabricated out of the same mm. The overlap in the
material as the sign plate and horizontal joints shall be from the
shall have corners cut to the same top and the vertical joints shall be
radius as the other corners of the from the left; butt joints in plastic
sign plate. sheeting will not be accepted.
Plastic sheeting shall be applied
Top and bottom light spill screens evenly over the whole surface of
shall be considered part of the the sign plate and shall adhere
sign plate and any stiffeners and fully. It shall be free from twists,
mounting fittings shall be cracks, folds or cuts, air bubbles
designed to accommodate the and other blemishes.
combined size.
All plastic sheetings used on the
6.2.5.5 Sign Faces same sign shall be carefully
matched for colour to produce a
Sign faces for permanent traffic uniform appearance both by day
signs shall be as shown on the and by night. Non-uniform
Drawings and shall comply with shades of colour on any one sign
the `Draft Malaysian Standard will not be accepted.
Specification for Reflective Sign
Face Materials' (SIRIM The edges of all plastic sheeting
Reference D111 [ISCF]), and on shall be sealed. Edge sealing shall
replacement of this draft, the be continuous and uniform and
respective Malaysian Standard shall also be applied to all bolt
Specification. and rivet holes.
Where purlins are adopted, they before final installation and they
shall be attached to each vertical and their anchorages shall be
member of the backing frame and installed so as to achieve the
the sign stiffening and framing loadings, torque settings and
shall be continuous in the vertical requirements shown on the
direction. Unless otherwise Drawings.
permitted by the S.O., purlins
shall be spaced equally apart. Sign plates shall be connected to
Connections shall be made at posts by a method approved by
every point where a purlin the S.O.
crosses a post.
Banding systems shall be of
Where purlins are not adopted, stainless steel.
the sign stiffening and framing
shall be continuous in the Where ferrous components are
horizontal direction. permitted, any drilling of such
components shall be completed
All rivets and other devices used before the application of any
in the fixing of sign plates to their finish.
stiffeners or backing frames, or
those used in the construction of Any hole drilled to accommodate
housings, shall be of a material rivets or bolts in plates with
compatible with the materials plastic sheeting shall,
being joined. immediately prior to the
insertion of the rivet or bolt,
Spacing of rivets or other devices have a clear lacquer, as
used in the fixing of sign plates to recommended by the
their stiffeners or backing frames manufacturer of the plastic
shall be uniform and shall not sheeting, applied to its edge to
exceed 150 mm around the prevent the ingress of moisture.
outside edge of any sheet or The surfaces of rivets or bolts
section of a sheet, and shall not exposed on the sign face shall be
exceed 300 mm on cross braces. coloured by a material approved
Hollow rivets shall be filled with by the S.O. to match that part of
a plastic plug flush with the head the face.
of the rivet.
Traffic signs to be erected on
An additional washer of road lighting columns shall have
neoprene, nylon or other material fixings compatible with the
approved by the S.O. shall be column cross-section and finish.
used against the sign face to Unless otherwise permitted by
protect it from the effects of any the S.O., columns shall not be
metal nuts, bolts, washers and/or drilled and wiring shall be
screws. contained in approved external
conduits.
Where traffic signs, including
external lighting luminaires or In addition to the requirements of
their supports, are required to this Specification, variable
have holding down bolt fixings, message traffic signs shall be of a
the bolts shall be lightly greased type approved by the relevant
authorities.
Cawangan Jalan, Ibu Pejabat JKR, K.L Page 150
FOR INTERNAL USE ONLY Standard Specification For Road Works
6.3.4 Preparation of Material on Site specified. When more than one coat
is used, the succeeding coat shall not
(a) Thermoplastic Material be applied until the previous coat has
fully set.
Thermoplastic material shall be
supplied in block or powder form. If Road markings of a repetitive nature
the material is supplied in block other than centre lines, lane lines,
form it shall be broken into pieces, etc., shall, unless otherwise decided
each weighing not more than 4 kg, by the S.O., be set out with stencils
which shall be melted in a heater which comply with the size and
fitted with a mechanical stirrer to spacing requirements as shown on
prevent local overheating. the Drawings.
Centre lines, lane lines and edge The determination of thickness shall
lines shall be marked by approved be in accordance with B.S. 3262
mechanical means or as directed by Part 3, Appendices B and C.
the S.O. Other markings shall be
applied by brush, spray, screed,
hand-propelled or self-propelled
machine according to the marking
configuration and the type of
marking material approved for use.
The rate of application of the
marking material for each coat shall
be that recommended by the
manufacturer unless otherwise
TABLE 6.1 - CLASS `A' GLASS BEADS : PARTICLE SIZE DISTRIBUTION, ROUNDNESS
AND DEFECTS
1.18 mm 0 to 3
850 um 0 to 10 70 30
425 um 90 to 100
850 0 to 5
800 5 to 20
300 30 to 75 80 20
180 10 to 30
Below 0 to 15
180
SECTION 7
STREET LIGHTING
page
7.4 FEEDER-PILLARS S7 - 14
7.2.10 Cable Laying and Installation (a) Cable Laid Direct In Ground
All cables shall be handled, laid Before any cable is laid, the
and installed according to this trench shall be thoroughly
Specification, the latest edition of inspected and any debris and
the IEE Wiring Regulations, the other sharp objects shall be
cable manufacturer's removed. The bottom of the
recommendations and ERA trench shall be covered with a
Reports, using proper installation layer of clean sand 75 mm thick.
equipment, all to the satisfaction The cables shall then be laid on
of the S.O. this bedding in an orderly manner
without overlapping and crossing
All cables shall be supplied in each other. 75 mm of clean sand
complete lengths to suit the shall cover the laid cables and
circuits they serve and no straight shall be spread over the trench
through joints shall be used. before placing the cable
Straight through joints in the protective covers.
cable shall only be permitted in
very exceptional circumstances Cable protective covers shall be
such as those arising from of clay bricks. The bricks shall be
unavoidable limitations in new, well burnt and in complete
manufactured length. Where pieces. They shall be laid
straight through joints or other lengthwise from end to end along
approved joints are permitted by the entire route of the
the S.O., the cost of such joints underground cable if the cable
shall be borne by the Electrical size is not more than 120 sq.mm.
Contractor. No joints in the cable For cable sizes in excess of 120
will be allowed unless approved sq.mm, more than one row of
in writing by the S.O. bricks shall be laid. Each cable
shall be seperately protected by
The minimum bending radius of these bricks and the cover shall
the cables shall be in accordance have at least 25 mm overhang on
with Table 52 C of the latest each side of the cable.
edition of the IEE Wiring
Regulations. Wherever cables are The trench shall then be
cut, the ends shall be immediately backfilled with earth and shall be
sealed in an approved manner compacted in layers of 150 mm
unless it is intended to proceed using a mechanical rammer. An
with cable jointing or termination orange coloured multi-strand
immediately. nylon rope of minimum 6 mm
diameter shall be laid at a depth
Unless otherwise permitted by of 300 mm along the trench to
the S.O., no cable shall be laid identify the cable route. At every
and/or covered up in the absence 10 m interval, an extra 2 m of
of the S.O. nylon rope shall be coiled and
laid. The finished surface shall be
left proud by 50 mm to allow for
subsidence and the Electrical
blown towards the other portion The lamps supplied shall have a
of the luminaire or the column mortality rate not greater than
arm. If independent reflectors are 10% at 5,000 switched operating
incorporated in the luminaire, hours and shall not take longer
such reflectors shall be of high than 4 minutes after the initial
purity aluminium mirrors, "switch on" to attain 80% of their
chemically anodised to yield guaranteed output at the rated
optimum reflection of light voltage of 200/250 V and
distribution. Full details of the frequency 50 Hz. The reignition
luminaire and accessories shall be period after an interruption of the
furnished as required in the supply shall not be longer than 1
Appendices to this Specification. minute to attain 80% of the
lumens output.
7.3.2.2 Lamps
The case of the unit shall carry a The door of the feeder-pillar shall be
label showing the connections rigidly reinforced and hinged internally
and listing the appropriate to prevent unauthorised access. The
voltage. feeder-pillar shall be lockable with either
wedge-type locks protected by screw
plugs or some other secret locks copper tape, precast concrete earth
approved by the S.O. The feeder- chambers with covers, etc.
pillar shall be self-ventilated and
weather proof and such ventilation 7.4.6 Time Switches
openings shall be protected by wire
mesh to prevent the entry of vermin, Time switches supplied for the
rodents and birds. control of luminaires, etc., shall be of
the synchronous/step-by-step motor-
A baseboard made of tufnol or wound handset dial plug-in type.
other approved treated hardwood They shall incorporate a 24-hour
of at least 16 mm thickness shall spring reserve or a battery back-up
be included to mount equipment system. Time switches shall be rated
such as time switches, contactors, as specified in the Drawings and
etc. shall be operational on a 220/240 V,
50 Hz supply.
7.4.3 Factory Inspection
7.4.7 Contactors
The Electrical Contractor shall make
arrangements to witness the Contactors shall comply with B.S.
electrical tests and for joint 5424 with uninterrupted ratings,
inspection to be carried out at the mechanical duty Class 2 and a
factory prior to transportation to the utilisation category of at least AC3.
Site. The contactor coils shall be fully
tropicalised and wound for
7.4.4 Foundation continuous operation for a 220/240
V, 50 Hz supply. The contacts of the
The Site of the foundation of the contactor shall be rated for the
feeder-pillar shall be filled where breaking capacity of the connected
required, compacted and levelled load.
before the reinforced concrete base
of minimum 250 mm height above 7.4.8 By-Pass Switches and Selector
the finished earth level is Switches
constructed. Cable entry ducts shall
also be provided. Single or three-phase by-pass
switches as applicable shall be
7.4.5 Earthing connected in parallel with the
contactors for use in the event of the
The earthing system for the feeder- failure of the contactors. These shall
pillar shall comply with the Rules be manufactured to B.S. 5419 and
and Regulations of the Supply shall be capable of breaking the load
Authority, The British Code of connected to the contactors without
Practice C.P. 1013, the relevant undue ageing or damage.
sections of the latest edition of the
IEE Wiring Regulations and the A four-position selector switch shall
Contract Drawings. be provided to select the mode of
operation and shall be appropriately
Each feeder-pillar shall be effectively labelled.
earthed using 4.8 mm x 16 mm
diameter steel core copper-jacketted
earth electrodes, 25 mm x 3 mm
SECTION 8
TRAFFIC SIGNALS
Page
8.1 GENERAL
8.1.9 Documentation
8.1.9.1 General S8-186
8.1.9.2 Hardware, Software and maintenance Manual S8-186
Page
Page
Page
8.8 ROADWORKS
An as-built plan showing the The Contractor shall carry out any
final wiring diagrams, pole repair within 24 hours of being
locations, controller locations, informed of the damages. Upon
detector placement, conduit runs failure to do so, the S.O. has the
and timing plan shall be option to appoint another party for
included in each controller repair and the cost thus incurred will
cabinet. be borne by the Contractor.
8.4 SIGNAL POSTS AND MAST 8.4.3 Connecting Facilities for Cables
ARMS
Provision shall be made for the
8.4.1 Standard Requirements connection of terminating and inter
connecting cables coming from
All signal posts, signal mast arms within the post or mast arm and of
and mountings of signal lanterns cables from the traffic signal
shall be as shown on the Drawings. lanterns.
The posts and mast arms shall be so
designed and constructed as to 8.4.4 Location and Erection
provide adequate support and
stability for the signal head assembly. The posts and mast arms shall be
erected at the approximate locations
All signal posts shall be of tubular as shown on the Drawings. On
hollow section of steel with a roadways whose edges are defined
nominal diameter of 100 mm and by a raised kerb, the posts shall be
fitted with a weather-proof cap to erected so that no part of the signal
prevent ingress of water. head other than overhead signals
projects over the roadway.
Mast arms shall be tubular hollow
sections of steel of a generally Where possible, the signal should
tapered form mounted on a baseplate have a clearance of 300 mm to 450
as shown on the Drawings. mm behind the kerb line. The post
shall be at a distance not less than 1
Every post shall be provided with metre before the edge line.
one nickel-plated brass earthing
screw located within the post, 25 In areas where there is no kerb, the
mm below the top. steel posts should be erected so that
the signal head is clear of the
The posts and mast arms shall be shoulder (or usable area) and
capable of having holes drilled in the should not be less than 2 m nor
vertical section, 1 metre above the more than 3 m from the edge of the
ground, for the mounting of one nearest traffic lane.
pedestrian push-button assembly in
accordance with Sub-Section 8.5. All posts and mast-arms shall have
their exact location determined by
8.4.2 Cable Entry the S.O. and recorded on the as-built
Drawings.
Buried posts shall incorporate a
cable-entry aperture as shown on the 8.4.5 Finish
Drawings. Baseplate-mounted posts
shall provide for entry of the cable Unless otherwise specified, the
into the interior of the post through a interior and exterior of steel posts
hole in the baseplate having a shall be protected by a finish
diameter not less than the inside complying with the requirements of
diameter of the post. M.S. 740.
The controller shall be suitable for When the pedestrian indications are
operation at 240 V + 6%, 50 Hz + allowed an exclusive phase, the
1%, single phase A.C. supply. pedestrian steady green shall be
controlled by the appropriate control
8.6.4 Facility Switch command and followed by the
flashing green pedestrian signal. The
A facility switch shall be provided to intergreen periods shall be inserted
switch the signal lanterns to ON, before the pedestrian steady green
OFF or FLASH or other facilities and between the end of the flashing
such as manual operation. The green and the start of the next
switch shall only control the signal vehicle phase green. It shall be
lamps and flashing yellow circuits possible to operate the pedestrian
while leaving the control equipment phase with or without pedestrian
fully operative. detection. This shall be selected by a
switch or other methods within the
Access to this facility shall be via a controller, subject to the approval of
separate locked door or some other the S.O.
means which does not give access to
the controller. The facility shall be 8.6.6 Logic Module
located not less than 1 metre from
the ground level. Arrangement of the microprocessor
based logic module shall be subject
8.6.5 Pedestrian Facilities to the approval of the S.O.
and conditional features, shall be The clock shall derive its timing
contained in the reprogrammable from two sources, either from the
ROM. 50 Hz mains supply or a crystal
oscillator. When the mains
Time settings may be stored by supply is normal, the 50 Hz
means of :- mains frequency shall provide the
time. The crystal reference signal
i) reprogrammable ROM; and shall be phase locked to the
mains frequency by a digital
ii) battery back-up RAM. phase locked loop. The real time
clock shall provide time in
The RAM settings shall be such seconds, minutes, hours and
that they may be changed by days to the microprocessor via a
means of a detachable keyboard data bus.
while the controller is
functioning. The reprogrammable 8.6.6.4 Operator Interface and Controller
ROM shall be separate from the Display
CPU and its associated circuitry
to facilitate field servicing. A keyboard display unit shall be
provided as an operator interface
8.6.6.2 Input/Output Interfaces with the controller logic module.
Visual indicators shall be
The Contractor shall provide for provided to indicate the status of
the approval of the S.O., detailed various traffic parameters such as
technical information on the the phase currently running, base
input and output interfaces. phase step for each phase,
Inputs include those from vehicle demand for each phase, pedestri
detectors, pedestrian push an demands recorded, etc.
buttons and signal links. The
output shall be to the vehicle When operated in link mode, the
signal lamps, pedestrian lamps, display shall be able to provide
wait indicators and signal all traffic parameters associated
linking. with the appropriate link mode.
All equipment, its construction and The Contractor shall carry out all
performance, shall be in accordance necessary roadworks in connection
with A.S. 2703 unless otherwise with the installation of the system.
specified herein. Any deviation from These shall include any roadworks
A.S. 2703 shall be at the request of associated with :-
or subject to the approval of the
S.O. i) installation of Local Controller
and Detector Recording
8.7.2 Number of Traffic Lanes housings;
The loop detector shall sense traffic ii) installation of signal poles and
flow on one to four traffic lanes heads;
depending on where it is installed. It
shall sense traffic moving in one iii) installation of cable ducting;
direction only and detection on a two
way road shall be achieved by using
two sets of detectors so that the
information obtained for each
direction is separate.
Cawangan Jalan, Ibu Pejabat JKR, K.L Page 197
FOR INTERNAL USE ONLY Standard Specification For Road Works
8.8.4.8 Vehicles
SECTION 9
CONCRETE
SECTION 9 - CONCRETE
Page
Page
Page
9.8.2 Finishes
9.8.2.1 Formed Surfaces S9-235
9.8.2.2 Unformed Surfaces S9-236
9.8.2.3 Remedial Treatment of Surfaces S9-236
14.0 - - 90 - - - - 85 - 100 -
100
10.0 10- 35 25 - 55 - 0-5 0 - 20 0 - 45 85 - 100
40 - 85
5.0 0- 5 0 - 10 0 - - 0-5 0 - 10 0 - 20
0 – 10
2.36 - - - - - - -
-
The grading of fine aggregate shall be analysed as described in M.S. 30 and shall be with
in the limits of one of the grading zones given in Table 9.2.
600 um 15 - 34 35 – 59 60 – 70 80 – 100
300 um 5 - 20 8 – 30 12 – 40 15 – 50
150 um 0 - 10 0 – 10 0 - 10 0 - 15
B.S 1377
Sulphate Content Test 9 not exceeding 0.4% be
weight of SO3
9.3.2 Requirements for Designed Mixes Where there are insufficient data
to satisfy (i) or (ii) above, the
9.3.2.1 Target Mean Strength margin for the initial mix design
shall be taken as 7.5 N/sq.mm
The concrete mix shall be for concrete of grade 15 and 12
designed to have at least the N/sq.mm for concrete of grade
required minimum cement 20 or above. This margin shall
content and to have a target mean be used as the current margin
strength greater than the required only until sufficient data are
characteristic strength by at least available to satisfy (i) or (ii)
the current margin. above. However, subject to the
approval of the S.O., when the
The current margin for each specified characteristic strength
particular type of concrete shall approaches the maximum
be determined by the Contractor possible strength of concrete
and shall be taken as the lesser made with a particular aggregate,
of :- a smaller margin not less than 5
N/sq.mm for concrete of grade 15
i) 1.64 times the standard or 7.5 N/sq.mm for concrete of
deviation of cube tests on at grade 20 or above may be used
least 100 separate batches of for the initial mix design.
concrete of nominally similar
proportion of similar materials
and produced over a period
not exceeding 12 months by
the same plant under similar
supervision, but not less than
2.5 N/sq.mm for concrete of
grade 15 or 3.75 N/sq.mm
for concrete of grade 20 or
above;
Total aggregate
(kg) 1850 1750 1800 1750
Fine aggregate 25 - 35 25 – 40 25 – 40 20 - 45
(%)
1) surface protected
by a water-proof
membrane;
3) surfaces continuously
buried and/or submerged
under water.
1) soffits;
2) surfaces exposed to
driving rain, alternate
wetting and drying 320 350 320 350 270 300 0.50
e.g.in contact with
backfill.
1) surfaces exposed to
the action of sea
water with abrasion 350 350 380 320 350 0.45
having a pH of 4.5 380
or less.
Reinforced Concrete
made with cement complying
with M.S. 522.
0.35 for 95%
of test results
with no result
Plain Concrete greater than 0.50.
containing embedded metal
and made with cement complying
with M.S. 522.
ii) Each individual sample test result For determining the cube strength of
shall be at least 85% of the prestressed concrete before transer or
specified characteristic strength. of concrete in a member before
striking formwork, sampling shall be
If any one sample test result fails to at the point of placing and the cubes
meet the second requirement (ii), shall be stored as far as possible
then that result may be considered to under the same conditions as the
represent only the particular batch of concrete in the members.
concrete from which the sample test
cubes were taken. The extra cubes shall be indentified
at the time of making and shall not
If the average strength of any group be used for the normal quality
of four consecutive sample test control or compliance procedures.
results fails to meet the first
requirement (i), or more than one 9.5 PRODUCTION OF CONCRETE
sample test result in a group fails to
meet the second requirement (ii), 9.5.1 Supervision
then all the concrete in all the
batches represented by all such The Contractor shall ensure the
sample test results shall be deemed required standard of control over
not to comply with the strength materials and workmanship. The
requirements. S.O. shall be afforded all reasonable
opportunity and facility to inspect the
For the purpose of this Sub-Section, materials and the production of
batches of concrete represented by concrete, to take any samples and to
groups of four consecutive sample make any test.
test results shall include the batches
from which samples were taken to 9.5.2 Batching and Mixing
obtain the first and the last sample
results in the group of four, together The quantities of cement, fine
with all the intervening batches. aggregate and various sizes of coarse
aggregate shall be measured by
weight unless otherwise approved
by the S.O. A separate weighing
machine shall be provided for
weighing the cement. Alternatively
the cement may be measured by
using a whole number of bags in
each batch. The quantity of water
The Contractor shall maintain an iii) the tremie pipe shall be large
experienced steel fixer at the site enough with due regard to the
of reinforced concrete works size of aggregate. For 20 mm
during the placing of concrete to aggregate the tremie pipe
reposition any reinforcement shall be of diameter not less
which may be displaced during than 150 mm and for larger
the work. aggregate, larger diameter
tremie pipe shall be required;
v) the tremie pipe shall always Unless otherwise agreed by the S.O.,
penetrate well into the concrete shall be thoroughly
concrete with an adequate compacted by vibration and
margin of safety against thoroughly worked around the
accidental withdrawal if the reinforcement, tendons, or
pipe is surged to discharge the duct formers, around embedded
concrete; fixtures and into corners of the
formwork to form a dense
vi) the concrete shall be homogenous mass free from voids
deposited wholly by tremie and which will have the required
and the method of deposition surface finish when the formwork is
shall not be changed part way removed. Vibration shall be applied
up to prevent the laitance continuously during the placing of
from being entrapped within each batch of concrete until the
the structure; expulsion of air has practically
ceased and in a manner which does
vii)all tremie pipes shall be not promote segregation of the
scrupulously cleaned after ingredients.
use.
The concrete maintained between the
9.5.5 Temperature Requirements two walls of formwork shall be
compacted by vibrating of the
During hot weather, additional internal type and concrete in slabs
precautions shall be taken to prevent with no formwork on its upper
premature setting and loss of water surface shall be compacted either by
during placing of concrete in the vibrators of the pan type or by a
formwork. These precautions shall vibrating screed.
include :-
The internal vibrators shall be
i) no concrete having an internal inserted and withdrawn slowly and at
temperature exceeding 33ºC a uniform pace of approximately
shall be deposited; 100 mm per second. Compaction
shall be deemed to be completed
ii) concrete shall not be placed in when cement mortar appears in an
formwork or around annulus around the vibrator. Over
reinforcement whose temperature vibration leading to segregation of
exceeds 36ºC; the mix must be avoided. The
internal vibrators shall be inserted at
iii) newly placed concrete shall be points judged by the area of mortar
protected from direct sunlight and showing after compaction, with a
from loss of moisture by certain allowance made for
covering, shading or other means; overlapping, and they shall not be
allowed to come into contact with
9.6.3.1 Manufacture Off the Site Items shall be lifted only at points
described in the Contract or
After the method of manufacture otherwise agreed by the S.O. and
has been approved, no changes shall be handled and placed
shall be made without the consent without impact. The method of
of the S.O. lifting, the type of equipment and
transport to be used, and the
The Contractor shall inform the minimum age of the items to be
S.O. in advance of the date of handled shall be subject to the
commencement of manufacture approval of the S.O.
and casting of each type of item.
9.6.3.4 Assembly and Erection
When the S.O. requires tests to
be carried out, no items to which The method of assembly and
the tests relate shall be dispatched erection described in the Contract
to the Site until the tests have shall be strictly adhered to on
been satisfactorily completed and Site.
the results approved by the S.O.
Immediately a unit is in position,
All items shall be indelibly and before the lifting equipment
marked to show the item mark as is removed, temporary supports
described in the Contract, the or connections between items, as
production line on which they necessary, shall be provided.
were manufactured, the date on The final structural connections
which the concrete was cast and, shall be completed as soon as is
if they are of symmetrical practicable.
section, the face that will be
uppermost when the member is 9.6.3.5 Forming Structural Connections
in its correct position in the
Works. No structural connections shall be
made until approval has been
9.6.3.2 Storage given by the S.O.
When items are stored, they shall Unless otherwise agreed by the
be firmly supported only at the S.O., the composition and
points described in the Contract. water/cement ratio of the in situ
The accumulation of trapped concrete or mortar used in any
water and deleterious matter in connection and the packing of
the units shall be prevented. Care joints shall be in accordance with
shall be taken to avoid rust the assembly instructions.
staining and efflorescence.
Levelling devices shall only be
Items shall be stacked in such a released or removed with the
manner that their removal in cor approval of the S.O.
rect order of age is facilitated.
be rejected by the S.O. and shall, if it Special care shall be taken that
fails to meet the Specification, the overall length of bars with
require its removal from the Works multiple bends is accurate and
Site. that after bending and fixing in
position the bars remain in place
Steel reinforcement shall be stored in without wrap or twist.
clean and dry conditions. When
placed in the Works it shall be clean 9.7.3.2 Fixing of Reinforcement
and free from loose rust, mill scale,
oil, grease, paint, dirt or anything The number, size, length, form
which may reduce its bond with and position of all reinforcing
concrete. bars, links, stirrups, spacer bars
and other parts of the steel
If directed by the S.O., the steel reinforcement, shall be in
shall be brushed or otherwise accordance with the Drawings.
cleaned before use, at the
Contractor's expense. Reinforcement shall be secured
against displacement. Unless
9.7.3 Construction Methods specified otherwise, the actual
concrete cover shall be not less
9.7.3.1 Cutting and Bending of than the required nominal cover
Reinforcement minus 5 mm. In a member
where the nominal cover is
Bars shall be of their correct dimensioned to the links, spacers
lengths and bent to the exact between the links and formwork
shapes required before being shall be of the same dimension as
fixed in the work. the nominal cover.
SECTION 10
PILING WORKS
Page
Page
10.4.2 Materials
10.4.2.1 Concrete S10-250
10.4.2.2 Reinforcement S10-250
10.4.2.3 End Plates S10-250
10.4.2.4 Pile Shoes S10-250
page
Page
The piling rig shall be set and Any unexpected driving or boring
maintained to attain the required conditions shall be noted in the
rake. The maximum permitted records.
The materials and workmanship Mild steel straps cast into the
shall be as specified under shoes shall be as shown on the
Section 9 of this Specification. Drawings. Rock shoes where
The grade of concrete and the required shall consist of wrought
details of reinforcement to be iron shoes and mild steel straps
used shall be as shown on the cast into "Chilled-hardened" cast
Drawings. iron blocks, as shown on the
Drawings.
10.3.2.2 Reinforcement
10.3.3 Manufacture and Storage of Precast
The main reinforcing bars in piles Reinforced Concrete Piles
not exceeding 12 m in length
shall be in one continuous length 10.3.3.1 Casting
unless otherwise approved by the
S.O. The length of piles to be cast
shall be as shown on the
In piles exceeding 12 m long, Drawings, subject to revision by
joints shall be permitted in main the S.O. Based on the results of
longitudinal bars at 12 m nominal pile driving resistance and/or load
intervals. Joints in adjacent bars tests carried out on piles driven
shall be staggered at least 1 m on the site, the S.O. may from
apart along the length of the pile. time to time order the lengths of
Joints shall be butt welded as piles to be modified.
specified in Sub-Section 9.7.5 of
this Specification.
A set shall be taken only in the driving. If a pile has been driven
presence of the S.O. unless to the required set or depth but
otherwise approved. The sound concrete of the pile is
Contractor shall provide all below cut-off level, the pile shall
facilities to enable the S.O. to be made good to the cut-off level
check driving resistances. The as described above.
final set of a pile other than as
friction pile, shall be recorded as 10.3.4.4 Lengthening of Piles
the penetration in millimeters per
10 blows. The temporary Where piles have to be
compression of the pile shall be lengthened, other than by means
recorded if required. of welding of steel plates as
detailed on the Drawings, the
Piles shall be driven in an reinforcement shall be stripped of
approved sequence to minimise all surrounding concrete for a
the detrimental effects of heave distance equal to thirty times the
and lateral displacement of the diameter of the main
ground. When required, careful reinforcement measured from the
levelling from a datum unaffected pile head for spliced joints and
by the piling shall be made on 300 mm for butt welded joints
the pile heads already driven, and all lateral reinforcement shall
before and after driving be removed. The lengthening
subsequent piles. Piles which bars shall butt on the exposed
have been displaced as a result bars in true alignment and shall
of driving adjacent piles shall be be butt welded as specified or
redriven to the required shall be spliced with bars of the
resistance. same diameter as the main pile
bars, 60 diameters in length and
10.3.4.3 Repair of Damaged Pile Heads lapping the main bars for a
distance of 30 diameters above
If a pile is to be subjected to and below the joint, and shall be
further driving, concrete in the securely bound with 1.63 mm
damaged pile head shall be cut soft annealed iron wire. New
off square at sound concrete, binders of similar size shall be
and all loose particles shall be provided and spaced at half the
removed by wire brushing, fol centres of the binders in the main
lowed by washing with water. body of the pile and shall be
Care shall be exercised to ensure securely bound with 1.63 mm
that the reinforcement in the pile soft annealed iron wire and the
head is not in any way damaged. pile extended by concreting in
Any damaged reinforcement properly constructed mounds to
shall be made good to the the length required.
satisfaction of the S.O. The head
shall be replaced with concrete of
an approved grade. The new
head shall be cast truly in line
with the remainder of the pile and
be properly cured and allowed to
harden sufficiently to develop
the strength necessary for further
The root edge or root face lengths Unless otherwise approved, the
of piles that are to be butt welded deviation from straightness shall
shall not differ by more than 25% not exceed 1/600 of a length not
from the thickness of piles not exceeding 10 m. When two or
exceeding 12 mm in thickness; or more such lengths are joined, the
by more than 3 mm for piles deviation from straightness shall
exceeding 12 mm in thickness. not exceed 1/960 of the
When piles of unequal thickness completed length.
are to be butt welded together, the
thickness of the thinner material 10.7.3.5 Fabrication of Piles on Site
shall be the criterion.
When pile lengths are to be made
Pile lengths shall be set up so that up on Site, all test procedures and
the differences in dimensions are dimensional tolerances shall
matched as evenly as possible. conform to the Specification
for the supply of pipe materials.
The length of piles to be supplied Adequate facilities shall be
shall be as shown on the provided for supporting and
Drawings subject to revision by aligning the lengths of pile.
the S.O. Based on the results of
pile driving resistance and/or load 10.7.3.6 Handling and Storage
tests carried out on piles driven
on the Site, the S.O. may from All piles within a stack shall be in
time to time order the lengths of groups of the same length and on
piles to be modified. approved supports. All
operations such as handling,
10.7.3.3 Matching of Pile Lengths transporting and pitching of piles
shall be carried out in a manner
Longitudinal seam welds and such that damage to piles and
spiral seam welds of lengths of their coatings is minimised. Piles
pipe piles forming a completed that are damaged during handling
pile shall, whenever possible, be and transporting shall be replaced
evenly staggered. However, if in by the Contractor at his own
order to obtain a satisfactory expense. All damaged and
match of the ends of piles or the rejected piles shall be removed
specified straightness, the from the Site forthwith.
longitudinal seams or spiral
seams are brought closely to one 10.7.3.7 Marking of Piles
alignment at the joint, then they
shall be staggered by at least Each pile shall be clearly marked
100 mm. with white indeletable marking
showing its reference number and
overall length. In addition, each
pile shall be marked at intervals
of 0.5 metre along its length
before being driven.
This work shall comprise the drilling The Contractor shall submit to
of a hole, placing of reinforcement the S.O. details of drilling
unit and subsequently filling the hole equipment and drilling procedure
with grout to form micropiles, all in for approval before
accordance with this Specification commencement of works.
and to the details shown on the Drilling operations shall be
Drawings. carried out in accordance with the
relevant requirements of Sub-
10.8.2 Materials Section 10.5.3.
ii) the total settlement under the Bakau piles shall be tested to
Working Load exceeds 12.50 failure by the Maintained Load
mm; or Test as described hereinbefore.
The load on the pile group shall
iii) the total settlement under be applied in 2 to 4 equal
twice the Working Load increments as directed by the
exceeds 38.0 mm, or 10% of S.O. until the failure load is
pile diameter/width whichever reached. The failure load (i.e.
is the lower value. ultimate load) is that load at
which the piles continue to settle
10.11.8 Load Testing of Bakau Piles at a constant rate without further
increase of applied load.
In general, all relevant Sub-Sections
stated hereinbefore shall apply to the For each increment of load, the
load testing of bakau piles, except settlement readings shall be
that what is understood as single test recorded at 15 minute intervals
piles in these Sub-Sections shall until the rate of settlement is less
mean a group of test piles for bakau than 0.25 mm per hour. The load
piles. at each increment shall be
maintained at a constant value
The load testing of bakau piles shall throughout the test.
be carried out on a group of nine
bakau piles, made up of three rows Graphs of time-settlement, load-
of piles, three in a row. time and load-settlement, to a
suitable scale, shall be plotted
An approved reinforced concrete pile and submitted to the S.O. with all
cap with a loading pedestal shall be records of the readings.
cast centrally over the group of piles
to be tested. The loading pedestal
shall be short to ensure stability, and
it shall have an approved mild steel
bearing plate cast on top. The load
shall be applied centrally on to the
steel plate.