Project Report On American Embassy School: Presented by

Download as pdf or txt
Download as pdf or txt
You are on page 1of 93
At a glance
Powered by AI
The project report discusses the civil and services works undertaken for the construction of American Embassy School. It details the mobilization, execution and quality measures adopted for the civil works. It also discusses the HVAC, BMS, electrical, firefighting and other services provided.

The major civil works involved excavation, shuttering, concrete works, reinforcement works, finishing works like flooring, wall finishes, false ceiling etc. It also discusses terrace waterproofing, quality measures and safety aspects.

The different types of flooring used are terrazo tiles, kota stone, ceramic tiles, IPS flooring. It details the specifications of each like thickness, pattern, joints etc. The flooring was chosen based on the area, traffic and aesthetics.

Project report on American Embassy School

Presented by:

Civil team: Deependra Vikram Singh


Shubham Asthana
Shivalika Anand
Pratibha Pathak

Services team: Amitesh Gothania


Deepak Mittal

Project Guide:

Mr. K. Stanley Unni


(Project Manager- American Embassy School)

1
ACKNOWLEDGEMENTS

Words are inadequate to express our heartfelt and sincere thanks to our guide Mr. K. Stanley
Unni for his precious advice, enthusiastic and constant encouragement and valuable suggestions
throughout the project period.

We also take this opportunity to express our indebtedness towards the invaluable guidance
offered by Mr. P.K Rakheja (Vice President Delhi Region) and Mr. M.K Dubey (Project Co-
ordinator American Embassy School) as a co-guide.

We also express our gratitude to the staff of American Embassy School for granting us
permission and helping us to collect the relevant data for our records and reference.

We will be failing in our duty if we do not thank adequately all the members of the SPCL staff
and collegues of the Delhi region for their help in completing the project work.

2
INDEX

PART – I CIVIL
Page No.
1. Introduction 9
2. Salient features and major works 11
3. Key Contract conditions 14
4. Mobilization 15
4.1 Site utilization Plan 15
4.2 Labour 16
4.3 Material 18
4.4 Machinery 19
4.5 Staff deployment 21
5. Execution 22
5.1 Excavation 22
5.1.1 Scope 22
5.1.1.1 Quantity 22
5.1.1.2 Dismantling / Demolition 23
5.1.3 Mode of measurement for Hard rock excavation 24
5.2 Shuttering 26
5.2.1 Repetitions 28
5.2.2 Shuttering Usage Ratio 28
5.2.3 Members 30
5.2.3.1 Columns 30
5.2.3.2 Cills and Lintels 30
5.3 Concrete 31
5.3.1 Scope 31
5.3.2 Challenges faced 32
5.4 Reinforcement 33
5.4.1 Scope 33
5.4.2 Equipments used 33

3
6. Finishing 34
6.1 Flooring 34
6.1.1 Terrazo tiles 34
6.1.2 Kota stone 35
6.1.3 Ceramic tiles 36
6.1.4 IPS flooring 37
6.2 Wall finish 37
6.3 False ceiling 37
6.4 Corian Stone partitions 38
6.5 External façade 39
6.5.1 Delhi Quartzite stone cladding 39
6.5.2 Grit wash 40
6.5.3 Terracota Jali work 41
7. Terrace Waterproofing 42
8. Quality 45
9. Safety 46
10. Learnings 49

PART – II SERVICES

1. Introduction 51
2. Scope of Work 52
3. HVAC (Heating, Ventilating and Air Conditioning) 53
3.1 HVAC Equipment 53
3.2 Sequence of HVAC work 56
3.3 Material Required 57
3.4 Specification of Main Items 61
3.5 Important point to be checked at the time of Installation 66
3.6 Working Principle of HVAC system 67

4
3.7 Refrigeration cycle description 68
3.7.1 Operation 68
3.2 Evaporator 69
3.7.3 Absorber 69
3.7.4 Generator 69
3.7.5 Heat Exchanger 69
3.7.6 Condenser 70
3.8 Valves 70

4. Green building 71
5. BMS (Building Management System) 73
5.1 Field Devices (Sensors) For BMS 73
5.2 Field Level Controllers 73
5.3 Supervisory Level 73
5.4 Fire Alarm System 75
5.5 Public Address System 76
6. Electrical 78
6.1 Electrical System 78
6.1.1 Source of power supply 78
6.2 Electrical Internal Wiring 82
6.3 Main LT Panel 84
6.4 Earthing 85
6.5 Important Points to be remembered 85
7. Fire Fighting 86-92

5
LIST OF FIGURES
Part 1 (Civil)
Fig 1 An artistic impression of the school 09
Fig 2 Octagonal shape of the structure 12
Fig 4.1.1 Uprooting of trees 15
Fig 4.1.2 Shifting of tree for transplant 16
Fig 4.2.1 Provision of Cold water for drinking 17
Fig 4.2.2 Toilets 17
Fig 4.3.1 Unloding of Reinforcement 18
Fig 4.3.2 Shifting of Reinforcement 19
Fig 5.1.2.1 Jack hammer 23
Fig 5.1.2.2 Rock breaker 24
Fig 5.1.3.1 Bucket excavator 25
Fig 5.1.3.2 Fissures being created manually 25
Fig 5.2.1 Cup Lock TITAN HV System 27
Fig 5.2.2 Easy De shuttering 27
Fig 5.2.3 Faster release of material 27
Fig 5.2.2.1 Deviation of Shuttering Usage Ratio 29
Fig 5.2.3.1.1 Making of Formwork for chamfered edges in columns 30
Fig 5.3.1.1 Exposed surfaces of Concrete 31
Fig 5.3.2.1 Exposed slab concrete 32
Fig 5.3.2.2 View of exposed concrete from the courtyard 33
Fig 6.1.1.1 Fixing of Tiles 34
Fig 6.1.2.2 Unpolished Kota Stone with inlay of 100mm Udaipur green marble 35
Fig 6.1.2.1 Polished Kota Stone 36
Fig 6.1.3.1 Flooring and dado with Ceramic tiles 36
Fig 6.3.1 Acoustic false ceiling 38
Fig 6.4.1 Pre Polished Corian Stone used in WC partitions 38
Fig 6.5.1.2 DQ stone cladding with SS angle after 4th layer of stone 40
Fig 6.5.2.1 Grit wash done by making panels using wooden beading 41
Fig 6.5.3.1 Terracota Jali used as an elevation feature 41

6
Fig 7.1 Layer of cold bitumen primer 42
Fig. 7.2 Polymetric mats laid for water protection 42
Fig 7.3 Expanded polystyrene with ship lap joints 43
Fig 7.4 Layer of Pee gravels 43
Fig7.5 Section of terrace waterproofing 44
Fig. 8.1 Quality lab on site 45
Fig 9.1 Graph for cumulative man hours worked v/s safe man hours 46
Fig 9.2 Fire drill program 47
Fig 9.3 Site barricading for clear passage way 48
Fig 9.4 Foam protection at the joints 48
Part 2 (Services)
Fig 1 Types of Services 52
Fig: 3.1 Vam Machine 53
Fig: 3.2 TFA (Treated Fresh Air) 54
Fig: 3.3 Cooling Tower 54
Fig: 3.4 Complete HVAC System Inside the building 55
Fig: 3.5 Pumps installation at site 56
Fig: 3.6 Schematic flow Diagram of HVAC System 67
Fig: 3.7 Li B r - H2O CYCLE 68
Fig: 5.1 Showing the location of all sensors and detector in a building. 74
Fig 5.2 BMS system Architecture 74
Fig: 6 Electrical Power Flow 78
Fig:6.1 TCG 2016 V 16 GAS GEN SET 79
Fig: 6.2 Piping Of GG 79
Fig: 6.3 Power Panel, Cabling and Bus Duct 80
Fig: 6.4 Main LT Panel 84
Fig: 7.1 Sprinkler heads 86
Fig: 7.2 Insight arrangement of fire door 87

7
PART I
(CIVIL)

8
CHAPTER 1
INTRODUCTION

Located on twelve acres in the heart of the diplomatic community of New Delhi, the American
Embassy School is one of the premier schools of Delhi imparting quality education to every
child. The buildings have been designed to blend into a small rocky hill and lend a friendly,
informal atmosphere to the school. This is a coeducational, independent day school, which offers
education from preschool to +2 level. At present, the New Delhi American Embassy school
enrolls more than 42 nationalities. It houses different facilities like libraries, centre for physical
education, modernized buildings and performing arts. Surrounding the American Embassy
School are the prestigious embassies of countries viz. Greece, Saudi Arab, Sultanate of Oman
and Qatar embassies.

Fig 1 An artistic impression of the school


The Project was a part of the expansion works of the American Embassy school. The American
embassy school comprises of three different blocks viz. Elementary school, Primary School &

9
High school. It was SPCL who had constructed the Elementary school and Primary school. Thus
this project may be considered as a repeat order for SPCL.
The project comprised of the dismantling of the existing High school block which was a G+1
structure with a new LGF+GF+2 structure. The complete project constituted the demolition of
the existing structure, arrangement for the relocation of the students during the construction
phase, construction of the school building with finishing and services and followed by the
landscaping works.
Of the above, the construction of the new school building along with the complete finishes was
put into the scope of SPCL and also the demolition of the foundations of the old structure. SPCL
was later on awarded the Co-ordination of the Services.

The building comprised of the state of the art facilities for the students viz. with top class
interiors and exteriors with the most modern gadgets The school building produces its own
power and the power consumption is monitored and controlled by the latest BMS technology.
The cooling and heating is not only controlled by sensors but the entire design of the building is
such so as to absorb minimum heat and allow maximum natural light by way of its octagonal
shape with a open-to-sky courtyard within the building, large windows, tinted laminated glass on
south and east faces, terracotta jail work on shafts and a 150mm thick polystyrene insulation on
the terrace. State of the art insulations on the cooling towers and plant room restricts the
vibrations and sound levels to a near zero level. Natural materials like Kota stone, Delhi
Quartzite Stone cladding, Grit wash, Terracota, Marble puts the building in harmony with nature.
No wonder that this building is on its way for a Silver Rating LEEDS Certification.

Key Players

The work was awarded to SPCL by the American Embassy School who were thus the client for
SPCL. The conceptual design of the building was made by an American architect John Derik
but the entire work was executed with Arcop Associates Pvt. Ltd as the architect . Desman was
the Structural Consultant while Sanelac was the services consultant.

10
CHAPTER 2
SALIENT FEATURES & MAJOR WORKS

The main feature of the building was in the shape of the building which blended the existing
landscape and rocky terrain with the structural design. The building is an octagonal shape in plan
with an open courtyard in the centre. The structure foundations are at three different levels. The
first level is the raft for the basement which accommodates a compactly designed plant room
enclosed by RCC Retaining walls. The lower ground floor is the next level which is in the shape
of a “ C ” and accommodates the laboratories along with a lovely courtyard and a rocky wall
closing the floor on one side The third level of foundations is on the ground floor which
comprises of classrooms and a breakout space which opens out into the existing building.

Further the building is structurally connected to the existing building by a bridge on the first
floor which directly connects the two structures . In totality the building is a (Basement + LGF+
G+2 ) structure .

11
Fig 2 Octagonal shape of the structure

SPCL was initially awarded the Civil works for the project which comprised of the dismantling
of existing foundations, Structure works and finishing works comprising of Flooring,
waterproofing, Aluminium Doors and windows etc.

12
The quantity wise breakup of some major works as per contract was as follows:-

Earthwork 2655 cu.m


Filling 1500 cu.m
Shuttering 10000 sq.m
Reinforcement 305 MT
Concreting 2300 cu.m
Masonry 400 cu.m
Plaster 9500 sq.m
Terrazo tiles 3300 sq.m
Kota stone 1500 sq.m
Ceramic tiles 1150 sq.m
DQ Stone cladding 430 sq.m
Grit wash 600 sq.m
Painting 8800 sq.m
Structural steel 7 MT
False ceiling
Gypsum Board 1736 sq.m
Grid Ceiling 1076 sq.m
Aluminium works 60 Lacs.
Road works 6 Lacs.

Table 2

The LOA Issued to SPCL for the civil works including the finishes was of Rupees Ten crores
and fifty five lakhs. SPCL was further awarded the co-ordination of the services’ works. The co-
ordination amount was Rupees. The contract period was of Twelve months for the complete
execution and handing over.

13
CHAPTER 3
KEY CONTRACT CONDITIONS

The contract was an item rate contract with no provision for any escalation.
15% of the contract value was to be released as mobilization advance which was to be recovered
from the 2nd RA Bill in 10 equal installments.

SPCL had to submit Bank Guarantees against mobilization (15% of CV ), Performance (5% of
CV valid till 12 months from date of completion of work) & Retention (5% of RA Bill including
extra items)

Liquidated damages to be levied at 0.5% of CV per week to a maximum of 5% of CV .There was


also a provision for a Bonus of 0.25% of CV per week to a maximum of 5% of CV for early
completion.

Defect Liability Period was 12 months.

Allowable Quantity variation was 15% exceeding which the rates would be revised as per mutual
agreement.

Water and Electricity was to be supplied by client free of cost .

14
CHAPTER 4
MOBILIZATION

4.1 Site utilization plan

The mobilization process is a very vital step for any project . At the American Embassy school
project the difficulties compounded on various accounts. The work was to be executed in a VIP
area, in an existing working school campus, existing landscaping to be unaffected including
trees, rocks etc.
The site utilization plan was prepared taking into account the above restrictions and limitations.
The site was first and foremost isolated from the existing school campus by a complete
barricading. The shuttering and reinforcement yards were established at reasonably flat areas
without any damage to the undulating rocky terrain. The trees within the vicinity were uprooted
and transplanted elsewhere in the school premises.

Fig 4.1.1 Uprooting of tree


15
Fig 4.1.2 Shifting of tree for transplant

4.2 Labour

Due to space constraints the labour camp could not be accommodated at the site. Also since it
was a very VIP area, the installation of labour camp just outside the site was not possible. Thus
local labour was deployed.
Also rooms were hired for the transit labour in the nearby vicinity . Further arrangement of
accommodation was put into the scope of PRWs/ Sub-contractors. Labour welfare was one of the
prime concerns and various facilities were made available for the labour on site as:
• Toilets
• Cold water for drinking
• Canteen
• Safety Jackets
• Registration with labour departments and provision of identity cards

16
Fig 4.2.1 Provision of Cold water for drinking

Fig 4.2.2 Toilets

17
4.3 Material

Since there was an existing school running next to the site, movement of heavy machinery was
not possible during the school hours i.e upto 04:00 pm. Also being a VIP area, permissions and
statutory approvals from the concerned authorities for the movement of machinery was
mandatory. Due to lack of space and the site conditions stacking of material was difficult.
These limitations were overcome by a clear intimation to the suppliers regarding levels of
acceptance of materials and the quantity requirements, constant quality control checks before
unloading and construction of bins for material stacking and avoiding mixing of aggregates.
These restrictions led to the procurement of entire quantum of steel within 5 days. For this the
diameter wise breakup for the structure was calculated by the structural consultant. This 305 MT
of steel was shifted and stacked manually as initially the approach did not exist. This was a
herculean task and its successful completion boosted the morale of the SPCL staff at the very
start of the project.

Fig 4.3.1 Unloading of Reinforcement

18
Fig 4.3.2 Shifting of Reinforcement

4.4 Machinery

The machinery requirements at American Embassy School project was minimal on account of
the small quantities .Also the working of the equipments was to be timed in such a manner that
they did not disturb the surrounding school functioning.

19
The equipments deployed are listed below:

Air Compressor 1 No s

Builder Hoist 1 No s

Mono Block pump (5 HP) 3 No s

Mono Block pump (7.5 HP) 3 No s

Mini pump (1 HP) 1 No s

Electric vibrator (3 HP) 4 No s

M S Cutter m/c (10 amp) 2 No s

Hand Grinder (3.8 amp) 2 No s

Hammer drill m/c (3.9 HP) 1 No s

Chipping m/c (5.7 amp) 1 No s

Circular saw m/c (4.7 amp) 1 No s

Petrol vibrator (3000 RPM) 2 No s

Hand drill m/c (1250 RPM) 2 No s

Table 4.4.1 Machinery deployed at AES

20
4.5 Staff Deployment

The works were executed by a vibtrant, young and dedicated team of individuals. The organization
chart of the site clearly indicates the dedication and productivity of the team. The project was initially
commenced by the civil team who were later on joined by the collegues from the services co-ordination
team.

Asst.
Engineer
Stores-
QA &QC Mangilal
Time
Store keeper-
Keeper-
John Nepal Singh
Thomas
Engineer Foreman-
Project Neeraj Supervisor
Finishing
Manager- Sr.
RO K.Stanley.Unn Engineer
Support i Engineer Foreman- Supervisor-
Civil Works Kundan Piyush

Planning
Engineer- Electrician-
Richi gupta Surender
Coordinator
-M.K.Dubey P&M- Mechanic-
Dept. Ramesh
Engineer
Electrician-
QS-
Mohd.Fozir Chakrabort
y
Safety
Services Co- Officer- Safety
ordinator- Tejvir SP.Singh Steward
Singh Services
Engineer-
Noorul
Islam

21
CHAPTER 5
EXECUTION

5.1 Excavation

5.1.1 Scope

5.1.1.1 Quantity

The quantity to be excavated according to the BOQ was 4424 cu.m while the actual quantity excavated was
4424 cu.m. Within this, the quantity payable as under hard rock was 3200 cu.m and the rest 1224 cu.m was
payable under all kinds of soil.

5.1.1.2 Dismantling / Demolition

The existing buildings and structures within the boundary of the site had to be
demolished. The demolition of the super structure was not in the scope of SPCL but the demolition of the
foundation members was . The debris had to be transported from the site on a daily basis due to lack of space.
All the approvals from the local Government Authorities and the necessary deposits was in the scope of SPCL.

22
5.1.2 Methodology adopted

The American Embassy School is built on a rocky terrain. Since Blasting was strictly prohibited, and different
methods were adopted for the excavation depending on the type of rock. The different methods adopted for
the excavation works are described in brief:-
Bucket excavaters (Poclain)- These were deployed effectively for the excavation in loose soil, hard soil and
loose rocks.
Jack hammers were used to dismantle the the foundations of the old building and soft rocks and hard rocks
with fissures.
Tractor mounted compressors with typical drill bits were used to drill holes in hard rocks without any fissures
so as to create an artificial crack and breaking later on.
In case of hard rocks without fissures highly skilled rock cutters were deployed who would work diligently
and dismantle rocks which were then removed from site.

Fig 5.1.2.1 Jack hammer

23
Fig 5.1.2.2 Rock breaker

5.1.3 Mode of measurement for Hard rock excavation

The ground level was recorded at a maximum of 5 meters interval. Average of these readings was taken as the
average ground level and depth of excavation in cutting was computed from these spot levels.
Bottom width excavation was measured as given in foundation drawings and details showing the width of the
bedding concrete only and hence the side clearance was covered in the rates.
Where soil, soft rock and hard rock were mixed, the measurements for the entire excavation were computed
from the levels and dimensions taken.
Excavated materials from ‘HARD ROCK’ and ‘SOFT ROCK’ were stacked separately and measurement was
reduced by 50% to allow for voids to arrive at the quantity payable under ‘hard rock’ and ‘soft rock’
respectively.

24
The difference in the entire excavation (worked out from levels) and the quantities payable under ‘hard rock’
and ‘soft rock’ were paid as excavation in all kinds of soil.

Fig 5.1.3.1 Bucket excavator

Fig 5.1.3.2 Fissures being created manually


25
5.2 Shuttering

The type of shuttering used at American Embassy School was Cup Lock TITAN HV System.

Fig 5.2.1 Cup Lock TITAN HV System

The advantages of Cup lock Titan HV system:

• Allows fast and systematic erection and dismantling.


• Uses light weight aluminium beams.
• Drop heads allow easy de shuttering of the ply on infill beams.
• Requires Minimal space for storage.
• Provides easy accessibility.

26
The structural work at AES
was initially planned for 8
months which was later
brought down to 6 months
due to various delays i.e the
start of structure works was
delayed by almost 2 months.
To cover up with this loss of
time, work at every possible
front was started.

Fig 5.2.2 Easy De shuttering

Fig 5.2.3 Faster release of material

27
5.2.1 Repetitions

It is the number of times the shuttering material is utilized (repeated). Average number of repetitions achieved
at AES was (16945 / 2547) = 6.7 repetitions.

The reasons for low repetitions are : (1) The time span for the structure to be completed was very short. This
did not allow the material to be fully utilized (repeated). (2) The clients requirement of exposed concrete
meant that the shuttering material that was being used was supposed to be in the best of the condition. (3) Due
to the delay in start of the structure part maximum available fronts had to be covered, which meant utilization
of more material than that was planned.

5.2.2 Shuttering usage ratio (SUR)

The shuttering usage ratio is defined as the Quantity of shuttering done / Total Quantity of shuttering material
available. Due to the technicality of the structure (i.e octagonal shape & requirement of exposed concrete) the
SUR planned as per PSE was 1.13 while the achieved SUR was 0.73. Various reasons attributed to low SUR
such as: (1). The initial material procured was 1444 sq.m while the material consumed was only 580 sq.m. (2).
The requirement of exposed concrete asked for the formwork to be in the best condition at all times. Re-usage
of shuttering material was done with utmost care. (3). After the major portion of structure was over the
material could not be dispatched to the store or any other site.

28
Shuttering Usage Ratio

1.4

1.28
1.24
1.2 1.21

1.05
1
0.96

0.8 0.81
SUR

0.73

0.6

0.46 SUR
0.4 0.4

Avg. Planned
0.2 0.19 0.13

0
Dec Jan Feb Mar Apr May Jun Jul Aug sep

Fig 5.2.2.1 Deviation


Monthsof Shuttering Usage Ratio

29
5.2.3 Mem
mbers

5.2.3.1 Coolumns

The columnns were expposed and had chamfered edges ass shown belo
ow.

Shuttering
g Board

Chaamfered edgge

Shutttering Boarrd

Fig 5.2.3.1.1 Maaking of Forrmwork for chamfered edges in coolumns

5.2.3.2 Ciills and Lintels


L

The cills annd lintels weere also expposed and were


w projectting outwardds approxim
mately 100m
mm.

30
5.3 Concrete

5.3.1 Scope

The planned concreting that was to be done as per BOQ was 2655 cu.m while the actual quantity of concrete
that was consumed was 2640 cu.m.

Due to the acute space constraint and very less concrete quantity it was not feasible to install a batching plant
on the project. The concrete production on the project was from a single RM-800 for the casting of irregular
pours viz. columns, mullions, parapets etc and Ready Mixed Concrete for major pours in slabs

Fig 5.3.1.1 Exposed surfaces of Concrete

31
5.3.2 Challenges faced

Since the requirement was of exposed concrete, there was absolutely no room for repairs on the surface of
concrete. This led to the use of extra supporting in shuttering, involvement of more labour and time, just an
appropriate use of vibrator was very vital for the concrete surfaces to be free from honeycombing. Also, as
concreting requires the use of vibrators which creates noise pollution, this activity could not be performed
during the day time, as there were restrictions on the timings due to the running of school in the nearby
vicinity.

Fig 5.3.2.1 Exposed slab concrete

32
Fig 5.3.2.2 View of exposed concrete from the
courtyard

5.4 Reinforcement

5.4.1 Scope

Quantity according to the BOQ was 305 MT which was procured at the start of the project, while the actual
quantity executed was 304.26 MT. This is a variance of 0.74 MT i.e 0.24%.

5.4.2 Equipments used

For cutting and bending of reinforcement one cutting machine and one bending machine were deployed at the
site.

33
CHAPTER 6
FINISHES

The entire finishing was in the scope of SPCL Except for the interior decorations/loose furniture.

6.1 Flooring

The flooring package comprised of different types of flooring for different areas viz:-

• Terrazo Tiles flooring in classrooms and laboratories.


• Kota stone flooring on corridors and staircases.
• Ceramic Tiles in Toilets.
• IPS Flooring in Electrical rooms and Plant room.
• Grit wash flooring around the building
• Mosaic flooring in courtyard.

6.1.1 Terrazo tiles flooring

The tiles were unpolished precast Terrazo tiles


purchased from NITCO (Northern India Tile
Company) of regular size 300mm x 300mm x
25mm. These tiles were laid over an average bed
thickness of 20mm of cement mortar 1:4 with
utmost care given to produce perfect joints and
edges. These joints were then grouted, followed by
grinding and polishing. For the protection of this
finished flooring, Plaster Of Paris was laid over a
polythene sheet.

Fig 6.1.1.1 Fixing of Tiles

34
6.1.2 Kota stone flooring

Kota stone was procured as per approved sample. Initially rough kota stone was laid which was later on
changed to polished kota for which polishing was done after first handover. The regular size of the stone was
550mm x 500mm interspaced with 100mm strips and inlay of 100mm Udaipur green marble bands. Kota stone
was also laid on the staircases with treads and risers of a single stone having moulded edges with nosing. The
skirting was projecting outwards and had chamfered edges.

Fig 6.1.2.2 Unpolished Kota Stone with inlay of 100mm Udaipur


green marble

35
Fig 6.1.2.1
6 Polisshed Kota Stone
S
6.1.3 Cerramic tiless in Toiletts

mic tiles were


The Ceram w laid in
n the toiletts of “Glaccier white”” shade purrchased fro
om ORIEN
NT TILES.
Thee size of thee tiles was 300mm
3 x 30
00mm and
wass used in fllooring and dado. The height of
the Dado was 22.4mts.
tiless in the toileets.

Fig 6.1.3
3.1 Flooringg and dado with Ceram
mic tiles

36
6.1.4 IPS Flooring

Indian Patent Stone Flooring was done in the plant rooms and Electrical rooms. Thickness was of 40mm and it
was laid in two layers, the first layer was 28mm thick while the second layer was 12mm thick.

6.1.5 Wall Finish

The wall finishing comprised of plaster with a 6-8mm layer of POP Punning which was painted as per the
approved shade. Different types of paints were used for different areas viz:-
Plastic Emulsion paint of “Berkeshire white shade” from Dulux was used for the interior walls i.e inside the
classrooms etc.

Apex Emulsion paint was used for the exterior walls i.e along corridors.
Synthetic Enamel paint was applied on the Door frames and Railings.

6.2 False Ceiling

The American Embassy school had two different types of false ceiling viz. Acoustic tiles & Gypsum board
false ceiling especially designed to cater to the minimum/maximum lux levels and also maintain efficient
cooling and noise insulation.

1) Acoustic Tiles of Armstong make were used in the project. The material i.e tiles and grid material was
procured by the client so as to avail the exemptions available to the embassies and the installation was
done by SPCL.
2) Gypsum Boards of India Gypsum were used along with jointing tapes and compound which were fixed
onto GI members supported from the ceiling by Fasteners.

37
Fig 6.2.1 Acoustic false ceiling

6.3 Corian Stone partitions in Toilets

Corian Stone is actually not a stone but is an


acrylic polymer sheet which is readily washable
and easy to maintain.
The toilets of the AES were of Corian stone
partitions mounted over SS Fittings. Corian stone
of 12mm was used with SS Channels and fixtures.

Fig 6.3.1 Pre Polished Corian Stone used in


WC partitions 38
6.4 External Façade

The Architect made it a point to design the building in such a manner so as to blend not only with the existing
school buildings but also the terrain. Also special attention was made to make the use of natural materials as
far as possible as per the norms of DUAC (Delhi Urban Architectural Committee). The external Façade
comprised of :-

• Delhi Quartzite stone Cladding


• Grit wash.
• Terracota Jali work
• Exposed Concrete finish

6.4.1 Delhi Quartzite stone cladding

DQ Stone which was locally available was dressed to the required shape and size with a thickness of 75mm -
100mm and fixed with a mortar backing of 120mm. SS angles of size 90x90x8mm were anchored with
fasteners on to RCC members at every 4th layer of stone so as to prevent and falling of stone from heights.

39
Fig 6.4.1.2 DQ stone cladding with SS angle after 4th layer of stone

6.4.2 Grit wash


Grit wash was done using locally available aggregate of size 10mm and downsize. Panels were
made using wooden beading.

40
Fig 6.4.2.1 Grit wash done by making panels using wooden beading

6.4.3 Terracota Jali work

Terracota Jali was used to enclose staircase


and shafts. Terracota tiles of approved design
and size of 15mmx 150mm were used. These
were reinforced by using 3mm thick GI wire
at every 3 layer of tile.

Fig 6.4.3.1 Terracota Jali used as an elevation feature

41
CHAPTER 7
TERRACE WATERPROOFING

An exceptional feature at AES was the Terrace waterproofing. The typical features adopted for resisting water
leakages inside the building sets it class apart from the general methodology used. Thermal insulation
provided in the roof slab isolates the building from the precarious climate and helps retain the temperature of
the building, saving an accountable amount of energy from the external sources.

Over the RCC slab, PCC 1:4:8 was applied with


a slope and having an average thickness of
75mm. A layer of cold bitumen primer was
applied at 0.3 lt/sq.m over the entire surface to
cater to the requirement of a base for
waterproofing.

Fig 7.1 Layer of cold bitumen


primer
A layer of APP Polymetric mats (in the form of
sheets) 3 mm thick was overlapped on one
another and the joints welded in such a manner so
as to generate a smooth flow of water into the
drain along the periphery.
For providing extra protection from the
penetration of water inside the building, another
layer of polymetric mats was laid in the
perpendicular direction in the same manner.

Fig. 7.2 Polymetric mats laid for water protection


42
These layers were succeeded by three
layers of extended polystyrene 50mm
each were laid to provide thermal
insulation. This 150mm thick layer
granted absolute isolation from the
outside atmosphere. A layer of
DRENTEX 40 drainage mat was laid to
prevent water from penetrating inside
the polystyrene layers

Fig 7.3 Extended polystyrene with ship lap joints

A Geo textile layer, Terram


1500 was laid over DENTREX
40. A 100m thick layer of Pee
Gravel was laid on the top so
that the voids that are created
by these gravels which add to
the thermal insulation which is
a Green building concept. Also
the rain water percolates
through this layer and leaves
the other unwanted materials
(leaves and stems etc.) on the
surface only and the Pee
gravels resist the flying off of

Fig 7.4 Layer of Pee gravels the geo textile layer.

A MOPLY mineral membrane 4 kg/sqm was applied on the vertical surfaces on the terrace.

43
Fig7.5 Section of terrace waterproofing

44
CHAPTER 8
QUALITY

The quality standards maintained at the American Embassy School was remarkable. Apart from
the requirements of high quality standards by the clients, SPCL itself ensured an exalted check
on the quality in every possible aspect. In accomplishing an exceptional degree of quality, inspite
of space constraints a Quality Lab was installed on the site.

The laboratory was headed by a Quality Engineer who inspected and conducted tests on
concrete, concrete ingredients, soil and other construction materials for their strength and other
parameters. Visible tests were conducted at the time of unloading of the materials only, and no
deficient material was carried into the site premises. To adhere to our motto of delivering a
quality product we shared our knowledge on a weekly basis in the weekly meetings conducted
on site.

Fig. 8.1 Quality lab on site


45
CHAPTER 9
SAFETY

1400000

1200000

1000000

800000 cumulative man 
hrs
600000 First Aid 
400000
Safe Man Hours 
200000 Worked 

Fig 9.1 Graph for cumulative man hours worked v/s safe man hours

The graph above shows the exceptional performance by SPCL wherein the cumulative man hours
overlaps the safe man hours worked, i.e not a single hour was lost due to unsafe reasons.

A commendable job was performed by the safety personnel at the American Embassy School. The
SPCL employees paid great attention towards safety and helped in maintaining a safe working
environment at the site. This was a 100% safe site and such exemplary standard was achieved by various
steps taken towards educating the labour and the staff like the Daily tool box meeting and fire drill
program etc.

46
Fig 9..2 Fire drilll program

Also variouus other meeasures weree taken likee maintenannce of safetyy records, thhird party teesting of alll the
lifting equippments, barrricading the required area
a and prooviding a clear passagee in all areass.

Safety preccautions werre taken meeticulously and


a in everyy feasible asspect for e.gg. even the junctions
j off the
G.I sheet ussed for makking boundaaries were protected
p byy applying fooam.

47
Fig 9.3 Site barricading for clear passage way

Fig 9.4 Foam protection at the joints 48


CHAPTER 10
LEARNINGS

Every single day in SPCL has taught us something or the other. Comparing ourselves from the day we
joined SPCL to this day we find an immense increase in the level of confidence and knowledge. The
theoretical knowledge obtained in the colleges has come to its practical application. To summarize our
learnings in a very broad sense we can segregate them as:

• Functioning of the company and the requirement of each department (HO, RO & the Site)
• Further sub divisions of the departments in the RO & the site.
• Co ordination between each department
• Work procedure to be followed from the very start i.e. :
o Selecting a suitable tender
o Bidding for the tender after rate analysis and arriving at a competitive tender cost
o Contractual conditions applicable
o Mobilization at the site
o Various statutory approvals
o Execution according to the technical specifications and scope of each department at the site
o Cost as well as progress monitoring
o Importance of maintenance of records and correspondences
o Handing over of the site

49
PART – II
(SERVICES)

50
CHAPTER 1
INTRODUCTION

Civil gives a firm building but it breaths through services. Service gives life to the building. Except
Structure all other facilities comes in services. Air conditioning, electrical, Building management
system, lift, plumbing, fire fighting these are common services which we generally find in building
services.

HVAC

R.O. System Electrical

Services

BMS Plumbing

Fire
Fighting

51
CHAPTER 2
SCOPE OF WORK

SPCL was awarded the co-ordination work of the various services within the school premises. The
agencies were nominated by AES whose working was to be co-ordinated by SPCL. The various
agencies involved have been listed below:-

S. No. Name of Subcontractors Type of works Contract Amount


original revised
1 M/s Ronsan Electrical Rs. 1,23,11,700.00 Rs.     1,61,77,804.00
2 M/s Firepro System Pvt. Ltd. Fire fighting Rs. 24,24,708.00 Rs.        23,81,290.00
3 M/s Quality Conscious ContrcPlumbing Rs. 66,40,535.00 Rs.        90,96,454.00
4 M/s Sanvik Engineers (I) Pvt.  HVAC Rs. 1,89,61,344.00  Rs.    1,95,13,647.00 
5 M/s Johnson Control India Pv BMS Rs. 19,67,900.00 Rs.        20,20,431.00
6 M/s Schindler India Pvt. Ltd. Lift  Rs. 24,53,074.00 Rs.        24,53,074.00
7 M/s Adwyn Chemicals Pvt. LtdR.O. System Rs. 30,00,000.00 Rs.        25,66,630.00
8 M/s Bright Insulations Insulation Rs. 35,97,846.00 Rs.        33,95,807.00
9 M/s Green Power InternationGas generator Rs. 1,42,83,000.00 Rs.     1,41,49,126.00
10 M/s Adarsh steel fabricators Fabrication Work Rs. 13,03,049.00 Rs.        17,56,799.00
11 M/s Adleck Systems Pvt. Ltd. Panels Rs. 23,33,660.00 Rs.        38,79,193.00
12 M/s Hilti India Pvt Ltd. Fire proof Material Rs. 7,23,404.00 Rs.          7,23,404.00
13 M/s Concrete Solutions Application of Fire Proof Mate Rs. 1,97,473.00 Rs.          2,60,344.00
14 M/s Shri Ram Electrical Work Electrical Rs. 21,99,724.00 Rs.        24,73,743.00
15 M/s Indersons Supply of Armoured cable Rs. 12,46,613.00 Rs.        12,46,613.00
16 M/s South Asian Enterprises Lightning Arrestor Rs. 3,30,312.00 Rs.          3,13,896.00
17 M/s Anand Control System UPS Supply Rs. 14,61,640.00 Rs.        14,61,640.00
18 M/s Cosmos System Cylinder Refiling Rs. 25,650.00 Rs.              25,650.00
19 M/s System Split AC Rs. 97,096.00 Rs.              97,096.00
20 M/s Sharp Air Cool Ducting Work Rs. 2,84,788.00 Rs.          4,24,029.00
21 M/s HZ insulator Insulation Rs. 1,33,025.00 Rs.          1,33,025.00
22 M/s Telecraft E solution EPABX Rs. 10,38,362.00 Rs.        10,38,362.00
23 M/s Lokpal Chain Block Rs. 93,138.00 Rs.              93,138.00

Total  Rs.7,71,08,041.00   Rs. 8,56,81,195.00  

Service Coordination Fee as per Contract   Rs.  87,80,000.00  
Add Service Tax and VAT   Rs.  10,37,227.00  
Total Coordination Fee   Rs.  98,17,227.00  
Total project cost   Rs.  9,54,98,422.00  

Table: 1

52
CHAPTER 3
HVAC

Heating, ventilating, and air conditioning (HVAC) is based on the principles of thermodynamics, fluid
mechanics, and heat transfer. The three functions of heating, ventilating, and air-conditioning are closely
interrelated. All seek to provide thermal comfort, acceptable indoor air quality, and reasonable
installation, operation, and maintenance costs. HVAC systems can provide ventilation, reduce air
infiltration, and maintain pressure relationships between spaces.

3.1 HVAC equipment


1. Vapour absorption machine (VAM):
Vapour absorption machines work on low-pressure steam or hot water as heat source. A
negligible amount of electrical energy is required to operate them.

Fig:3.1 VAM Machine

53
2. TFA (Treated Fresh Air)

Fig: 3.2 TFA (Treated Fresh Air)

3. Cooling tower

Fig: 3.3 Cooling Tower

54
4. FCU (Fan Coil Unit)
5. Chilled water pipe line
6. Diffuser
7. Fresh air duct
8. Exaust air duct
9. Plenum
10. Flexible connection
11. Drain

Fig: 3.4 Complete HVAC System Inside the building


12. Piping
13. Secondary chilled water pump
14. Primary chilled water pump
15. Condenser pump

55
Fig: 3.5 Pumps installation at site
16. Valves
17. Variable-frequency drive, for fine control of pumps
3.2 Sequence of HVAC work
Equipment Installation
( i.) VAM Installation
( ii.) TFA installation
( iii.) Primary, secondary and condenser pump installation
( iv.) Cooling Tower Installation

Accessories Installation
( i.) FCU installation
( ii.) Chilled water pipe line installation
( iii.) Hydro pressure testing of chilled water pipe line
( iv.) Duct installation and silicon filling
( v.) Smoke testing of duct
( vi.) Insulation of Duct and chilled water pipe lines
( vii.) Aluminum Cladding of Chilled water pipe lines( Inside the Building)
( viii.) Cement Cladding of chilled water pipe lines (at terrace)
( ix.) Valves fitting for:

56
(a.) CHW pumps
(b.) Condenser water pump
(c.) Cooling tower
(d.) FCU
( x.) Copper fitting
( xi.) FCU Canvass connection
( xii.) FCU Plenum fixing
( xiii.) Drain installation and insulation

3.3 Material Required

1. FCU installation:
( i.) Drill
( ii.) Fisher/Anchor fastener
( iii.) Stud
( iv.) Nut
( v.) FCU unit
( vi.) Electricity supply ( Panel, Board )

2. Chilled water pipe line installation


(a.) Chilled water pipe line for supply from CHW secondary pump
(b.) Chilled water pipe line for supply from CHW primary pump

( i.) Pipe
( ii.) Elbow
( iii.) Welding machine
( iv.) Welding rods
( v.) Gloves
( vi.) Screen

57
( vii.) Welding goggles
( viii.) Wooden Blocks
( ix.) Gas Cutter (oxygen and DA (Dissolve acetylene) cylinder)

Supports
( i.) Wooden blocks
( ii.) Fastener
( iii.) Drill Machine
( iv.) Angle
( v.) Stud

(d.) Man power (Fitter, welder, and rigger)

3. Hydro pressure testing of chilled water pipe line


( i.) Hydraulic pressure machine
( ii.) water supply

4. Duct installation and silicon filling


( i.) Fabricated Duct
( ii.) Gas Kit
( iii.) Clamp
( iv.) Silicon Paste (adhesive material)
( v.) Silicon filling pump (Silicon gun)

Supports:-
( vi.) Angle
( vii.) Drill machine
( viii.) Fastener
( ix.) Stud

58
5. Insulation
(a.) Duct Insulation
( i.) CPRX Solution
( ii.) Glass Wool with foil
( iii.) Belt
( iv.) Gas Kit (Rubber Pieces)
( v.) Cello Tape
( vi.) Aluminum Foil Tape

(b.) Pipe Insulation (Cladding)


(i.) Thermocol section
(ii.) Aluminum Sheet
(iii.) Screw
(iv.) Belt
(v.) Strip Puncture
(vi.) Polythene
(vii.) CPRX solution

6. Smoke testing of duct


(i.) Smoke bomb

7. Valve Fitting
(i.) Valves
¾ Balancing Valve
¾ Motorised Valve
¾ Drain Valve
¾ Strainer Valve
(ii.) Wrench
(iii.) Holdtight Solution
(iv.) Threads

59
8. Copper Fitting
(i.) Cu Pipe and elbow
(ii.) Brazing rod
(iii.) Gas Cylinders

9. Flexible connection
(i.) Canvass
(ii.) Aluminum
(iii.) Wooden Hammer
(iv.) Drill
(v.) Bolt Nut
(vi.) Gas kit

10. Plenum Fixing


(i.) Duct
(ii.) Fastener
(iii.) Drill Machine
(iv.) Hammer
(v.) Duct Lining
(vi.) Gas Kit
(vii.) Nut
(viii.) Bolt

11. Drain installation and insulation


(i.) PVC Pipe
(ii.) 90o elbow
(iii.) 450 elbow
(iv.) Holdtight.
Support:-

60
(i.) Stud
(ii.) Bolt
(iii.) Angle
(iv.) Drill machine
(v.) Fastener

3.4 Specification of Main Items


1. CHILLER (VAM):
S.No. DESCRIPTION
1. MANUFACTURER Thermax Ltd.
2. TYPE VAM
3. CAPACITY 310TR
4. REFRIGERANT Lithium Bromide
CONDENSER:
1. MANUFACTURER Thermax Ltd

2. PRIMARY CHILLED WATER PUMPS:

DESCRIPTION VALUES
A GENERAL
2. Manufacturer SUZHOU Teco Elec & Mech. Corp
B PERFORMANCE DATA
1. Rated Flow (USGPM) 1.12 mm /s
2. Head (ft WC/m WC) 66ft
3. Selected Drive Motor Induction Motor
4. Pump Rated Speed (rpm) 1460
5. Pump Efficiency >75%
C MATERIAL OF CONSTRUCTION
1. Casing CI

61
2. Impellor SS
D DRIVE MOTOR
1. Motor Type S1 / Induction
2. Rating (kW) 11 KW
3. Rated Current 20.7 Amp
4. Rated Voltage 415 V
5. Frequency 50 Hz
6. Power factor 0.83
Motor Full load
7. 90.1%
Efficiency

3. SECONDARY CHILLED WATER PUMPS:

DESCRIPTION VALUES
A. GENERAL
2. Manufacturer ITT Bell Gossett
B. PERFORMANCE DATA
1. Rated Flow (USGPM) 1408
2. Head (ft WC/m WC) 66 ft
3. Selected Drive Motor Induction Motor
4. Pump Rated Speed (rpm) 1460
5. Pump Efficiency >75%
C. MATERIAL OF CONSTRUCTION
1. Casing CI
2. Impellor SS
D. DRIVE MOTOR
2. Motor Type S1 / Induction
3. Rating (kW) 15 KW
4. Rated Current 27.6 Amp
5. Rated Voltage 415 V

62
6. Frequency 50Hz
7. Power factor 0.83
8. Motor Full load Efficiency 90.1%

4. CONDENSER WATER PUMPS - VAM


DESCRIPTION VALUES
A. GENERAL
1. Type Split casting centrifugal Pump
2. Manufacturer ITT Bell Gossett
3. Quantity 2 No.
B. PERFORMANCE DATA
1. Rated Flow (USGPM) 1408
2. Head (ft WC/m WC) 66 ft
3. Selected Drive Motor Induction Motor
4. Pump Rated Speed (rpm) 1450
5. Pump Efficiency >75%
C. MATERIAL OF CONSTRUCTION
1. Casing CI
2. Impellor SS
D. DRIVE MOTOR
2. Motor Type Induction / S1
3. Rating (kW) 22 KW / 30HP
4. Rated Current 39.1 Amp
5. Rated Voltage 415 V
6. Frequency 50Hz
7. Power factor 0.83
8. Motor Full load Efficiency 90.1%

63
5. CONDENSER WATER PUMPS - GG
DESCRIPTION VALUES
A. GENERAL
1. Type Split casting centrifugal Pump
2. Manufacturer ITT Bell Gossett
3. Quantity 2 No.
B. PERFORMANCE DATA
1. Rated Flow (USGPM) 1408
2. Head (ft WC/m WC) 66 ft
3. Selected Drive Motor Induction Motor
4. Pump Rated Speed (rpm) 1450
5. Pump Efficiency >75%
C. MATERIAL OF CONSTRUCTION
1. Casing CI
2. Impellor SS
D. DRIVE MOTOR
2. Motor Type Induction / S1
3. Rating (kW) 10Kw
4. Rated Current 39.1 Amp
5. Rated Voltage 415 V
6. Frequency 50Hz
7. Power factor 0.83
8. Motor Full load Efficiency 90.1%

6. COOLING TOWER
DESCRIPTION VALUES
A. GENERAL
1. Capacity 310TR
2. Quantity 1 No

64
3. Type Induce Draft
4. Manufacturer Bell Cooling Tower
B. PERFORMANCE DATA
1. Flow Rate 1408 USGPM
Leaving Water Temperature 88 Deg F
2.

C. FAN DATA
1. Fan Speed 960rpm
2. Fan motor HP 7.5KW
3. Fan Motor Speed 960rpm

7. FAN COIL UNITS


S. No. Model No. TR Qty
1 SRC-400-SW-PF-4C 1.0 8
2 SRC-400-HW-PF-4C 1.5 5
3 SRC-600-HW-PF-4C 2.0 9
4 SRC-800-HW-PF-4C 2.5 8
5 SRC-1200-HW-PF-4C 3.0 28
6 SRC-1400-HW-PF-4C 3.5 39

8. Air Washer
S. No Description Data
1 Fan RPM 746
2 Motor Rating 18.5KW / 4 pole
3 Speed 43000 CFM
4 Static Pressure 40 Mwg

9. Exhaust Fan (Plant Room)


S. No Description Data
1 Fan RPM 746

65
2 Motor Rating 15KW / 4 pole
3 Speed 30000 CFM
4 Static Pressure 40 mWG

10. Treated Fresh Air (TFA) Units


S. No Description Data
1 Capacity 43 TR
2 Motor Rating 10 KW / 3 KW
3 CFM 11524

3.5 Important Point to be checked at the time of installation

• Wooden Support should not be above FCU.

• Supports should be at proper distance.

• Strainer Valve should be properly aligned otherwise it would not filter the CHW pipe line water
which might cause blockage in FCU.

• Valve should be fitted inside the tray.

• Tapping from main header line should have proper space to carry out the insulation work.

• Valve should be tight using hold tight solution.


 
• FCU alignment should be at 1800 angle.

66
3.6 Working Principle of HVAC system

Fig: 3.6 Schematic flow Diagram of HVAC System

67
3.7 Refrigeration cycle description

3.7.1 OPERATION
Vapour absorption machine consists of two sections in one shell. The lower section houses the
evaporator and the absorber. The upper section houses the generator
and the condenser. The pressure in the lower section is of the order of 6 mm Hg (abs) while the pressure
in the upper section is about 70 mm Hg(abs). LiBr-Water combination is used in the operation of vapour
absorption cycle. Water acts as the refrigerant and LiBr as the absorbent. Solution pump, refrigerant
pump, heat exchanger, purge unit and the control panel complete the machine.

Fig: 3.7 Li B r - H2O CYCLE

68
3.7.2 EVAPORATOR

Refrigerant pump sprays the water over the evaporator tube bundle. The water to be chilled that is
circulating in the evaporator tubes, gets cooled as the refrigerant water in the shell evaporates because of
extremely low pressure in the evaporator shell.

3.7.3 ABSORBER

The refrigerant water vapour goes to the absorber through a mist eliminator. Concentrated LiBr-Water
solution is sprayed over the absorber tube bundle. The refrigerant vapour
is absorbed by the strong solution being sprayed and heat of absorption is removed by cooling water
passing through the absorber tubes. The weak solution form the absorber is sent by the solution pump to
the generator for recovering the refrigerant water vapour.

3.7.4 GENERATOR

Weak solution from absorber is heated in the generator with the help of low pressure steam / hot water.
The refrigerant water vapour is evaporated and goes to the condenser. The strong solution is sent down
to the absorber for further absorption of water vapour.

3.7.5 HEAT EXCHANGER

To recover the heat energy form the strong solution returning to absorber a heat exchanger is used. The
cold weak solution being pumped from the absorber picks up excess heat from the strong solution. This
improves cycle efficiency.

69
3.7.6 CONDENSER

The water vapour evaporated in the generator at a higher temperature and pressure is condensed to liquid
form in the condenser where the heat of condensation is picked up by the cooling water from the
absorber inlet circulating in the condenser tubes. The condensed refrigerant water is returned to the
evaporator through an expansion device.

3.8 Valves

™ Ball valve: - This valve is use for isolating the FCU unit from main header line. Generally it is
used in return side in FCU unit.

™ Strainer Valve: - Two purposes are fulfilled by this valve. First it is used for isolating the FCU
unit and second it is also used for straining dust and rust from FCU unit.

™ Balancing Valve: - Flow of chilled water into FCU unit is controlled by balancing valve eg. 1
TR cooling required 2.4 GPM (Gallon Per minutes) water supplies. Generally it is used in return
side so that we can ensure about the water supply into FCU unit.

™ Motorized Valve: - It is very important valve to automatically regulate the conditioning.

70
CHAPTER 4
GREEN BUILDING

Green Building involves design and construction practices that significantly reduce or eliminate the
negative impact of buildings on the environment and occupants in five broad areas:

1. Sustainable site planning


2. Safeguarding water and water efficiency
3. Energy efficiency and renewable energy
4. Conservation of materials and resources
5. Improving Indoor environmental quality

The American Embassy School has been so designed so as to obtain a “Green Building” certification
from LEEDS. With the existing system the AES is a strong contender to obtain a silver rating.

Various initiatives have been adopted in the school so as to obtain the same. Some of them are as:-

1) The design of the building itself is such to as obtain maximum natural light and requires
minimal cooling. This has been done by the Octagonal shape with an open-to-sky courtyard in
the centre.

2) The Air-conditioning system incorporates a Vapour Absorption Machine which intakes the
waste exhausts from the gas generator and utilises them to generate cooling.

3) The roofing comprises of 150mm layer polystyrene boards which provide adequate insulation
from the scorching sun. Also on the roof is a 300mm thick layer of pea gravel which as acts an
insulation.

71
4) The architectural design takes into account the blending of the building with the existing
landscaping and utilizes maximum amount of natural materials viz. Delhi Quartzite Stone,
Terracota Jali, Grit wash, Kota Stone, etc.

5) Special Initiatives were adopted by AES to reduce the noise and vibrations to a
near zero level by enclosing the entire plant room by a thick layer of acoustic insulation, placing
Resistoflex Anti vibration pads below heavy equipment foundations, insulating the cooling tower
in a canopy etc.

6) The equipment foundation mainly GG and DG foundation has floating foundation with a base of
resistoflex anti vibration pad layer and insulated from the side with 75 mm air gap.

72
CHAPTER 5
BUILDING MANAGEMENT SYSTEM (BMS)

Building management system is a tool that is used to monitor and control various mechanical systems
and/or electrical systems in a building.
Monitoring and control of various parameters are achieved through inputs and outputs.

There are two types of Inputs /Outputs:

Analog: The analog input/output changes continuously in a definable manner in relation to the measured
property.

Digital/Binary: The digital input/output is the one that has a value representing one state or another.
Typical values are "on/off", alarm or normal, 0 or 1, high or low

5.1 Field Devices (Sensors) For BMS


AI - Analog Input
BI / DI – Binary / Digital Input
AO – Analog Output
BO / DO – Binary / Digital Output

5.2 Field Level Controllers:


• RCU (Room control Unit)
• DDC Controllers
• MIG – Controller (Plantroom)

5.3 Supervisory Level:


• NAE Controller
• ADS Software (UI)
• Field Sensors

73
Fig: 5.1 Showingg the locatio
on of all sennsors and deetector in a building.

Fig 5.2 BMS


B system
m Architectuure

74
LIST OF ALL THE COMMISSIONED SYSTEMS
Building Management System (BMS)

S.  Input 
No.  Equipment  Manufacturer  Quantity  Type  Power 
1  RCU Johnson controls 44  Controller  24 V AC 
2    Occupancy Sensor  Johnson controls 36  Sensor  12 V DC 
Duct  Temperature  Sensor(All 
3  Rooms)  Johnson controls 46  Sensor  NA 
Immersion Temperature Sensor
4  (CHW & CDSW Temp.) Johnson controls 4  Sensor  NA 
Duct  Temperature  &  RH 
5  Sensor (TFA)  Johnson controls 3  Sensor  15 V DC 
Outside Air Temperature &
6  RH Sensor Johnson controls 1  Sensor  15 V DC 
Air Differential Pressure
7  Switch for Run status (TFA) Johnson controls 1  Sensor  NA 
Air Differential Pressure
8  Switch for Filter status (TFA) Johnson controls 1  Sensor  NA 
Tank Level Sensor
9  (Plantroom) Veksler 6  Sensor  NA 
Cooling Tower Tank Level
10  Sensor (Terrace) Veksler 2  Sensor  NA 
Oil Tank Level Sensor
11  (Plantroom) Veksler 1  Sensor  24 V DC 
12  DDC Panel            
   (A) General Johnson controls 3 Controller 24 V AC 
   (B) Expansion Panel MX50 Johnson controls 2  Controller 24 V AC 
   (C )Expansion Panel MX55 Johnson controls 1  Controller 24 V AC 
   (D) Expansion Panel MX54 Johnson controls 1  Controller 24 V AC 

75
   (E) Expansion Panel MX25 Johnson controls 1  Controller 24 V AC 
13  MIG – Controller (Plantroom) Johnson controls 1  Controller 24 V AC 
NAE – Supervisory Controller
14  (BMS Room) Johnson controls 1  Controller 24 V AC 
Chilled Water Flow Meter
15  Sensor (Plantroom) Johnson controls 1  Controller 25 V AC 

Manufacture Quantit Input 


S. No.  Equipment  r  y  Type  Power 
Johnson 24 V 
1  RCU controls 44 Controller  AC 
Johnson 12 V 
2    Occupancy Sensor  controls 36 Sensor  DC 
Johnson
3  Duct Temperature Sensor(All Rooms)  controls 46 Sensor  NA 
Immersion Temperature Sensor (CHW & Johnson
4  CDSW Temp.) controls 4 Sensor  NA
Johnson 15 V 
5  Duct Temperature & RH Sensor (TFA)  controls 3 Sensor  DC 
Johnson 15 V 
6  Outside Air Temperature & RH Sensor controls 1 Sensor  DC 
Air Differential Pressure Switch for Run Johnson
7  status (TFA) controls 1 Sensor  NA 
Air Differential Pressure Switch for Filter Johnson
8  status (TFA) controls 1 Sensor  NA 
9  Tank Level Sensor (Plantroom) Veksler 6 Sensor  NA
Cooling Tower Tank Level Sensor
10  (Terrace) Veksler 2 Sensor  NA 
24 V 
11  Oil Tank Level Sensor (Plantroom) Veksler 1 Sensor  DC 
12  DDC Panel   
Johnson 24 V 
   (A) General controls 3 Controller AC 
Johnson 24 V 
   (B) Expansion Panel MX50 controls 2 Controller AC 
Johnson 24 V 
   (C )Expansion Panel MX55 controls 1 Controller AC 
Johnson 24 V 
   (D) Expansion Panel MX54 controls 1 Controller AC 
Johnson 24 V 
   (E) Expansion Panel MX25 controls 1 Controller AC 
13  MIG – Controller (Plantroom) Johnson 1 Controller 24 V 

76
controls AC 
NAE – Supervisory Controller (BMS Johnson 24 V 
14  Room) controls 1 Controller AC 
Johnson 25 V 
15  Chilled Water Flow Meter Sensor (Plantroom) controls 1 Controller AC 

5.4 Fire Alarm System (FAS)


S. 
No.  Equipment  Manufacturer  Quantity Type  Input Power
Fire Alarm Panel (BMS
1 Room) Johnson controls 1 Controller 240 V AC
Fire Detector – Detector
2 Multicriteria (Rooms) Johnson controls 74 Addressable 15- 32 V DC
Fire Detector – Photo Detector
3 electric (Rooms) Johnson controls 46 Addressable 15- 32 V DC
Control Module (Lobby
4 area) Johnson controls 10 Module addressable 15- 32 V DC
Monitor Module (Flow
5 switch) Johnson controls 8 Module addressable 15- 32 V DC

Hooter with Horn/Strobe


6 (Lobby area) Johnson controls 10 Hooter 24 V DC
Manual Call Point (Lobby
7 area) Johnson controls 9 MCP Addressable 24 V DC

5.5 Public Address System (PAS)


S.  Input 
No.  Equipment  Manufacturer  Quantity Type  Power 

77
1  Speakers (All Rooms)  Noti fire 44  Ceiling Speaker 24 V AC 
DVC  Digital  Voice 
Command (Fire Panel, BMS 
2  Room)  Johnson controls 1  Controller 24 V DC 
DAA Digital Audio Amplifier 
3  (Fire Panel, BMS Room)  Johnson controls 2  Amplifier 240 V AC 

78
CHAPTER 6
ELECTRICAL

 Source of 
power 
 Supply 
/

Main LT  Capacitor 
Panel  Panel 

Electrical 
HVAC Panel  Floor  Plumbing Panel  Lift Panel 
 Panels 

Fig: Electrical Power Flow

6.1 ELECTRICAL SYSTEM

6.1.1 Source of Power Supply

(a.) In AES site the source of electrical power supply is Gas Generator.

(b.) Standby Diesel Generator


Rating of Diesel Generator
Electrical output: 1010 KVA

(c.) NDMC supply 440 volts

79
6.1.1.1 GAS GENERATOR

Fig: 6.1 TCG 2016 V 16 GAS GEN SET

Fig: 6.2 Piping Of GG

80
Fig: 6.3 Power Panel, Cabling and Bus Duct

Gas Generator

Rating of Gas Generator

Genset Data Load


100% 75% 50% Unit
Calculated Fuel Gas Flow Per Unit 179 138 96 Nm3/h

Electrical Output 774 581 385 KW

S. No.  Description  Particulars 


Gas Engine 
1  Manufacturer  Deutz 
2  Type  Natural Gas Based 
3  Capacity  774 KW 

81
4  Gas pressure  Input  3.0 bar 
5  Lube Oil Quantity  600 ltr. 
6  Coolant Type  Wt Supra 

Alternator 
1  Manufacturer  Marellimotori 
2  Type  3 Phase alternator 
3  KVA  1300 
4  PF  0.8 
5  Amp  1820 A 
6  RPM  1500 
7  Exciting Voltage  22 V DC 
8  Exciting Current  6.5 A 
9  Ambt Temp.  40.0 Cent. 

Pump Detail using in Gas Generator Plant

O/L
S.No. Description Make HP KW Amp Volts Realy
1 Blower N/A 18.50 415
2 Pump N/A 12.50 9.30 16.80 415 15.00
3 Condenser water pump-1 Bell& Gossett 10.50 7.50 14.30 415 16.00
4 Condenser water pump-2 Bell& Gossett 10.50 7.50 14.30 415 16.00
5 Cooling Tower Fan N/A 7.30 5.50 17.00 415 11.00
6 HT Pump LOWARA 12.30 9.20 16.8-9.69 415 14.50
7 Hot Water sec. pump LOWARA 7.30 5.50 10.1-5.85 415 10.00
8 LT Pump LOWARA 4.50 3.00 11.1-6.38 415 4.50
9 D M Water KRILOSKER NA 0.75 2.10 415 2.10
10 Lube Oil Transfer ABB 0.50 0.37 1.10 415 0.90
11 Pre Lubrication Pump Robert Birkenbeul NA 0.37 2-3.3 415 2.65

82
6.1.2 ELECTRICAL INTERNAL WIRING
• First of all our priority should be given for completing layout and distribution within the
building.
• It is necessary to freeze all electrical single line diagrams.
• Then carryout the laying of cable trays, cabling, conduiting, wiring and fixing of points.
• Checking is required simultaneously to get the quality of job.
• All necessary formalities should be taken to complete well in advance with proper
documentation.

6.1.3 SEQUENCE OF WORK


• Laying cable trays (power & data) with proper support.
• Laying of cable(power & data)
• Laying copper strip
• Cables should be tie up
• Proper ferruling
• Light fixing with proper support
• Fixing of points
• Termination

6.1.4 MATERIALS USED


• Copper plate for earth grid • 220v power cable
• Anchor fastener • Tie up thread
• Threaded rod • Copper strip
• Nut bolt • Numbering & Marking
• Cable tray • Distribution box
• Data cable • Floor panels
• 110v power cable

83
6.1.5. MAIN LT PANEL

Fig: 6.4 Main LT Panel

3.1.2.1 Main LT panel is fed by 1600 Ampere BUS DUCT from GG. Main LT panel
feed all other panels through different size of cables according to their current
ratings which is shown in Fig
3.1.2.2 Bus duct is connected GG and Main LT panel through flexible connection.
3.1.2.3 Incoming & outgoing from panel is provided with thermal relay for overload
Short circuit and earth fault protection.(Manufactured: L&T, Areba)
3.1.2.4 Floor panel is fed by 1000 Amp. Bus duct.

84
6.1.6. EARTHING

In AES site we provide 8 earth pit and these all connected with 2 more earth pit which are in existing
building in circular connection.

Earth resistance should be at 0 to 4 ohm for providing proper protection.

4.1.7 Important Points to be remember

™ MCB rating should always be 1.5 times or more than actual load.
™ Relays should be set at 10 % access of full load current. e.g. If full load current of motor is 10 A
than relay should be fixed at 11 A.
™ 4 core cables is used where we required neutral. As if we want to feed any panel than we should
used 4 core cable.
™ 3 core cables used in delta start motors.
™ Cable size is decided by using electrical handbook. Firstly we calculate the total amp. load than
we see in electrical handbook and take sufficiently oversized cable.
™ Load should be equally distributed on each phase.
™ Earthing should be properly done.
™ In star/ delta connection of motor 2 runs are coming from panel.
™ In DOL starting motor are fed by single cable.

85
CHAPTER 7
FIRE FIGHTING

In AES site Fire fighting system installed in two parts. Each part covers half of building. There are two
way to protect the building from fire.
(a.) Sprinkler system
(b.) Hydrant system

(a.) Sprinkler system


Equipments used in Sprinkler system
¾ Mild steel pipe
¾ Sprinkler heads

Fig: 7.1 Sprinkler heads

¾ Flow switches
¾ Sprinkler alarm
¾ Valves

The sprinkler system consist of 2 nos. of riser connected to 2 nos. of sprinkler alarm valves incoming of
which is from pump room delivery line and headers are tapped off in each floor.

The header at each floor will be provided with branches for proper distribution of water. Sprinkler bulbs
are also located to see the level of water.

(b.) Hydrant system


In the case of any fire hazard, hydrant valves installed inside and /or outside the building will be
operated thereby resulting a fall in pressure in the system.

86
Equipments used in Hydrant system
¾ Mild steel pipe
¾ Flanges
¾ Elbow
¾ Fire hose reel
¾ Fire Hydrant
¾ Hose Pipe

Fig: 7.2 Insight arrangement of fire door

1. RRL Hose:
S. No DESCRIPTION

1. MANUFACTURER Newage
2 TYPE Reinforced Rubber
3 BRUST PRESSURE 30 Kg / sqcm

87
4 WORKING PRESSURE 14 Kg / sqcm
5 Size of Coupling 63 mm x 63 mm
Pair of male / Female
6 End Connection Instantaneous coupling
IS-903
7 Length 15 mtr
8 Inside Diameter 63 mm

2. GM HYDRANT VALVE SINGLE:

DESCRIPTION VALUES
A. GENERAL
1 Manufacturer Newage
2 Type Screw Type BSP
3 Size 80 mm NB
Out Let 63 mm Instantaneous coupling with pull
4
out spring lock type as per IS 5290 type-A
5 Blank Cap Rubber IS : 937
6 Hydrostatic Pressure Test 20 Kg/sqcm
8. Motor Full load Efficiency
9. Motor No

3. 20 MM RUBBER HOSE:

DESCRIPTION DETAIL
1. Type Wall Mounting Swingly(180 C)
2. Manufacturer Padmini
4. Specification As per IS-444 for Rubber Hoses
5. Size 20mm dia x 36.5m long
6 Working Pressure 10kg/cm2

88
4. Preesure Gauge
Type Head Bourden Type Pressure Vaccum
1.
Compound Gauge
2. Manufacturer H Guru
3. Accuracy +-1% of FSD
4. Size of dia 100mm
5. Range 0-15kg/cm2
6. Connection size 3/8 inch BSP
7. Burdon Materials SS-316
8. Test Pressure 25kg/cm2

4. CONTROL VALVE

DESCRIPTION VALUES
1. Manufacturer H.D.Fire
2. Approval UL Listed
3. Size 100-80NB
4. Working Pressure 12.3kg/cm2
5. Hydro Testing Pressure 25kg/cm2
6. Rubber Clamp SS-304
7. Seat & Cover Bronze IS 318 LTB-2
Variable Pressures Trim With
8. Trim Type Rotard Chamber & Sprinkler
Alarm
9. Housing & Cover Cast Iron

5. G.M. Ball Valve

DESCRIPTION VALUES
1. Manufacturer Zoloto

89
2. Standard IS-778/1980
3. End Type Threded
4. Tested Pressure 25 Bar
5. Body Forged Brass

6. Flow Switch

1. Manufacturer System Sensor


2. Type Vane Type
3. Model WFD Series
4. Size 80/65 mm
5. Operating Range 0-49 ºc
6. Approvel UL / FM

7. Branch Pipe

1. Manufacturer Newage
2. Nozzle IS-318 LTB-2
3. Washer Rubber to IS-937 Type B
4. Size 30 mm
5. Nozzle Dia 20 mm
6. Hydro Static Pressure Test 21kg/cm2

8. Hose Reel Drum.

S.No. Description Detail


1 Manufacturer Newage
2 Type Wall Mounting swinging Type
3 Drum Mild Steel

90
4 Size 230 mm wide x 550 mm dia
5 Hose Size 20 mm dia x 36.5 mtr long

9. 10. 5 Kg ABC Type Fire Extinguisher.

S.No. Description Detail


1 Manufacturer Mini Max
2 Type ABC Type dry Chemical powder
3 Capacity 5 Kg
4 Operation Vertical
5 Test Pressure 30 bar
6 Charge Pressure 14 bar
7 Jet Range 4 to 5 mtrs
8 Discharge time 15 to 25 second
10. Butterfly Valve:

S.No. Description Detail


1 Manufacturer Intervalve
2 Type Central disc design butterfly valve
with a single pcs rubber boddy
3 Actuator Hand lever
4 Size 50 NB to 150 NB
5 Pressure Rating PN – 1.6
6 Hydro Static Pressure 14 Kg/sqcm

11. Sprinkler:

S.No. Description Detail


1 Manufacturer Tyco

91
2 Series TY-B
3 Model TY3251 pendent type
4 Bulb Operating Temparature 68dec C
5 End Connection 1/2” NPT
6 Color of Bulb Liquid Red
7 Frame Bronze
8 Bulb Glass
9 Deflector Copper
10 Approval UL-Listed

12. SS-304 Flexible Dropper:

S.No. Description Detail


1 Manufacturer Easy Flax
2 Standered UL-Listed
3 Model & Size EFB – 236 & 914mm
4 Connection To Branch Line (inlet) 25 mm NPT
male threaded to sprinkler head
(outlet) 15 mm NPT female threaded
5 Working Pressure 200 PSI / 1375 KPA
6 Test Pressure 1000 psi / 6875 kpa
7 Temperature Rating 300 deg F (149 deg C)

13. MS Pipe 25 NB to 150NB:

S.No. Description Detail


1 Make Jindal Hissar
2 Specification IS-1239 Heavy Class C ERW black plain ends
3 Hydro Test 16 Kg/sqcm
4 Spark Test Rapping and coating shall be tested with spark test / holiday test

92
93

You might also like