Estimating &quantity Surveying
Estimating &quantity Surveying
Estimating &quantity Surveying
ESTIMATION AND
QUANTITY
SURVEYING
CONTENTS
1)
2)
3)
4)
DEFINITION
WHY QUANTITY SURVEYING IS REQUIRED
SCOPE OF WORK
QUANTITY SURVEYING SERVICES
5)
6)
7)
8)
9)
a)
b)
1)
PRE-TENDER PHASE
POST-TENDER PHASE
EARTHWORK
CONCRETE
FORMWORK
STEEL REINFORCEMENT
BRICKWORK
EXCAVATION/ EARTHWORKS
CEMENT CONCRETE WORKS
BRICKWORKS
PLASTERING
PAINTING
Quantity Surveying
1. DEFINE
To ascertain the
Commercial
Viability of such
project
if implemented
Preparation of
Initial
Estimated Cost
of Project
Certification of
Execution
Cost of
Project
Comparison of Estimated
vis--vis
Executed Cost
Data bank for future
similar Project
Analysis of reasons
for Variation
Derivation of the
Final Project
Cost
3. SCOPE OF WORK
Project Viability Study / Evaluation Stage
Owner / Employer
Architects
Financers
Engineers / Consultants
Quantity Surveyors
Contractors / Subcontractors
Insurers
Solicitors
Nodal Agencies
Statutory Authorities
Stage 2 :
During the supervision of the construction
Review and checking the payments submitted from the
contractor.
Preparation of the reports about the conformity of the
quantities items with contract documents.
During the implementation :
Review and checking the BOQ at the starting of the work.
Prepare the eng. Measurement for the quantities of the finished
works.
Prepare lists of the site needs (material, workers, technicians)
Calculate the remuneration of the subcontractors, workers,
equipments,etc.
Prepare the payment statements
Prepare the detailed reports describing the situation of the items
quantities, (plus or minus the contract BOQ)
Stage 3 :
Review and
check the
financial
payments.
into
Pre-Tender Phase
Feasibility and market studies.
Preliminary cost planning.
Procurement advice at concept design stage.
Cost management during design development.
Value Engineering.
Life cycle costing.
Preparation of tender documents.
Schedule of materials.
Contract administration.
Post-Tender Phase
Soliciting of competitive bids and offers with technical proposal.
Optimization of superior technical proposal, capability of bidders and price
evaluation.
Preparation of selected panel of preferred bidders.
Negotiation with preferred bidders.
Clients benefit from accurate interim valuations of the work in progress.
Settlement of rational interim payments to contracts for progress of work.
Projection of Timely financial statements.
Estimation of final revised cost to completion.
Settlement of the final account of contractors.
The process
Booking of Dimensions
The golden rule of booking dimensions is to record length first,
the breadth or width second and height / depth or thickness
third and last.
12
CENTRE LINE
2430
4030
TRENCH
3230
TRENCH
5430
6230
7030
6000
3000
BRICKWORK
IN CEMENT MORTAR (1:6)
1000
230
PCC (1:5:10)
200
800
SECTION
13
Description of Item
Unit No.
Length
Breadth /
Width
Height /
Depth
Quantity
1
2
3
Excavation in Trench
PCC (1:5:10)
Brickwork in CM 1:6
RM
RM
RM
2
2
6.23
3.23
12.46
6.46
18.92
Cum
Cum
Cum
1
1
1
18.92
18.92
18.92
0.80
0.80
0.23
1.00
0.20
0.80
15.14
3.03
3.48
11.25
3.89
15.14
2.25
0.78
3.03
2.38
1.10
3.48
Excavation in Trench
Cum
Cum
2
2
7.03
2.43
0.80
0.80
1.00
1.00
PCC (1:5:10)
Cum
Cum
2
2
7.03
2.43
0.80
0.80
0.20
0.20
Brickwork in CM 1:6
Cum
Cum
2
2
6.46
3.00
0.23
0.23
0.80
0.80
14
English Method:
1. Taking off (dimension from the drawings)
2. Grouping them
3. Billing or Bill of quantities
Timesing
2.
Dimensions
Squaring
Descriptions on
of items
PWD Method
1. Taking out (dimensions from the relevant drawings )
2. Squaring the dimensions
3. Abstracting
17
English Method
Structural
Works
Substructure
Superstructure
Civil Works
Envelope/
Enclosures
Internal/Extern
al Finishes
Water Proofing
Joinery
Architectural
Elements
External
Works
Land
development/Site
Grading
Landscaping/
Horticulture
Storm Water
Drainage/ Harvesting
Roads/Pavements
Water Supply
Sewer Network
Area Lighting
Boundary Protection
MEP
Mechanical
System
Electrical
System
Plumbing
System
Fire System
Security
System
(LV) Systems
HVAC
Heating
Ventilation
Air
Conditioning
Air Cooling
Interiors
Internal
Furnishing
Suspended
Ceiling
Acoustics
Illumination
Decision
Issued Drawings from Owner / Consultant / Architect
Incorporate
in drawings
Discuss in
Clients
local
office
Discrepancies of
minor nature
Review
Refer to
Owner /
No Discrepancy
Ready for Quantity
take off
Discrepancies of
serious nature
Take off of Quantity from
corrected drawings
Consultant /
Architect
7. Abstracting
7. Abstracting
Item
Description of Item
Unit No. Length
Number
1
Excavation .
For Office Building
In Foundation
Cum
For Septic Tank
Cum
For Soak Pit
Cum
Total
Cum
2
PCC (1:5:10)
For Office Building
In Foundation
Cum
For Septic Tank
Cum
For Soak Pit
Cum
Total
Cum
3
Brickwork in CM 1:6 upto Ground Level
For Office Building
In Foundation
Cum
For Septic Tank
Cum
For Soak Pit
Cum
Total
Cum
4
Backfilling
For Office Building
Excavation quantity
Cum
Less for PCC 1:5:10
Cum
Less for Brickwork
Cum
Total
Cum
Breadth /
Width
Height /
Depth
Quantity
Remarks
15.25
12.23
4.65
32.13
From Sheet # 1
From Sheet # 7
From Sheet # 8
3.05
2.45
0.93
6.43
From Sheet # 1
From Sheet # 7
From Sheet # 8
3.39
2.72
1.03
7.14
From Sheet # 2
From Sheet # 8
From Sheet # 9
32.13
6.43
7.14
18.56
From Item # 1
From Item # 2
From Item # 3
25
8. Billing
Rate
In Rs
Quantity
Total
Upto
Upto-Date Previous
Bill
This Bill
This Bill
27
8. Billing
Purpose of BOQ
1.
2.
3.
4.
5.
6.
29
1. EARTHWORK
Each dimension shall be measured to nearest 0.01 mtr, where any
dimension is more than 25 mtr it should be measured to the nearest 0.1
mtr.
The measurement of earthwork shall be done in cubic metres, unless
otherwise mentioned.
Dead men or tell-tales may be left at suitable intervals to determine the
average depth of excavation, where the excavation is in trenches or from
borrow pits is being done in fairly uniform ground.
Where the ground is not uniform, levels shall be taken before the start,
after site clearance and after the completion of the work and the quantity
of excavation in cutting computed from these levels.
30
EARTHWORK (contd.)
a)
b)
c)
d)
e)
f)
Where soft soil and hard rock are mixed, the measurement for the total
quantity shall be made. The hard rock excavated shall be stacked and
measured in stack. The quantity of the hard rock excavated shall be
arrived at by applying pre-accepted deductions for voids. From the total
quantity of the mixture, the quantity of hard rock excavated shall be
deducted to work out the quantity of soft soil.
31
EARTHWORK (contd.)
In case of the following works, authorized quantities (calculated on the
basis of authorized working space) or those actually excavated,
whichever are less, shall be measured :
EARTHWORK (contd.)
Authorized working space shall be specified in each case. Where
authorized space is not so specified the following shall apply :
o 60 cm measured from the face of structure (including protective
measures, if any) at lowest level. In addition for item c above the
extra length at each end shall be 1.50 mtr.
ACTUAL
EXCAVATION
LINE IN
SLOPE
EXCAVATION
PAY LINE
FOUNDATION
33
CONCRETE WORKS
Dimensions shall be measured to nearest 0.01 mtr except for the
thickness of slab which shall be measured to nearest 0.005 mtr.
Unless otherwise stated all concrete work shall be measured in cubic
metres.
Unless otherwise stated formwork shall be measured separately.
Unless otherwise stated reinforcement shall be measured separately.
Columns shall be measured from top of column base to underside of first
floor slab and subsequently from top of floor slab to underside of floor
slab above.
34
FORMWORK
Formwork shall be measured in square meters
as the actual surfaces in contact with the
concrete or any other material requiring
formwork.
No deductions shall be made for opening up
to 0.4 m2. No deduction shall be made for any
opening / cut-outs when slip form technique is
used.
Formwork to secondary beams shall be
measured up to the sides of main beams, but
no deduction shall be made from the formwork
of the main beam, where the secondary beam
intersects it.
Formwork to beam shall be measured up to
sides of column, but no deductions shall be
made from the formwork to stanchion or
column casings at intersections of beam.
36
STEEL REINFORCEMENT
Bar reinforcement shall be measured by weight in kilogram and shall
include cutting to lengths, hooked ends, cranking or bending (straight or
spiral). Authorized overlaps, chairs / separators shall be measured.
When welding of joints is authorized it shall be described; Joints butt
welded shall be measured in numbers and lap welded shall be measured
in running metres of the length welded.
Binding wire for fixing reinforcement shall not be measured, but shall be
included in description of item.
No deduction shall be made for opening not exceeding 1m2
37
BRICKWORK
Shall be measured in sqm
Brickwork 1 brick thick (20 cm) or less shall be measured separately in
sqm
No deduction shall be made if
Abstracting
The process by means of which the quantities of items of identical character and description are
collected from take off sheets, totaled and deduction made in order to arrive at the net total
quantities of respective items and in trade-wise order is called abstracting.
Billing
It is a claim for the amount of work done or supply. It consists of :a) Work Order or Agreement Number.
b) Item Number.
d) Unit of Item.
DETAILED SPECIFICATIONS
Nature of work
Gives description of work in a detailed manner
signifying type /category of work.
At different levels places structures buildings
etc
Eg. Masonry in ..., plaster., Flooring...,
Cladding... Etc for the material used.
DETAILED SPECIFICATIONS
Materials involved
Lists out various materials which are used in work
specifying
Name,
Class or grade,
Type,
Category.
Tolerances
DETAILED SPECIFICATIONS
Material specification
Work procedure
Method of measurement
METHOD OF PAYMENTS
Specifies procedures /rules governing terms of payments, stages
of payments, and modus - operandi for payments of various kinds
of works.
the job.
Quantity
As per
drawing
Rate
Amount
Actual as
per Site
Material
Least of the
two
or as per
Contract
condition
Equipment,
Plant &
Tools
Labour
Others
Piece rate
basis
Supply
basis
Overhead,
Profit &
Contingency
Agency
Commission
Misc. Expenses
Material
Ingradient A
Ingradient B
Ingradient C
Coefficient / Unit
Equipment
Quantity / Unit
+
Cost of
Hire
Charges /
Depreciation
Cost of
Operator
& Helper
Cost of
P.O.L.
+
Rate / Unit
+
X
Duration of Deployment
+
Cost of
Maintenance
& Spares
Cost of
Foundation and
Mobilization &
Demobilization
b)
Labour costs,
c)
d)
Contingencies,
e)
f)
Profit.
b)
Labour costs,
c)
d)
Contingencies,
e)
f)
Profit.