Introduction To Subsea Systems Networks Part4
Introduction To Subsea Systems Networks Part4
Introduction To Subsea Systems Networks Part4
Table of Contents
1.0 OVERVIEW OF FIELD DEVELOPMENT OPTIONS
1.1
1.2
1.3
1.4
INTRODUCTION
1
1
1.1.1
1.1.2
1.1.3
SUMMARY
ONSHORE DEVELOPMENT
1.2.1
1.2.2
OFFSHORE DEVELOPMENT
1.3.1
SUBMERSIBLE
1.3.2
JACKUP
1.3.3
1.3.4
FIXED PLATFORMS
1.3.5
COMPLIANT TOWERS
10
1.3.6
10
1.3.7
SPAR
11
1.3.8
11
1.3.9
12
1.3.10
13
1.3.11
SUMMARY
14
SUBSEA DEVELOPMENT
15
1.4.1
INTRODUCTION
15
1.4.2
MONOHULL FPSO
15
1.4.3
SUBSEA FLOWLINES
16
1.4.4
EXPORT OR TRUNKLINES
17
1.4.5
BUNDLES
17
1.4.6
17
1.4.7
RISERS
19
1.4.8
20
1.4.9
MANIFOLDS
21
1.4.10
TEMPLATES
21
1.4.11
22
1.4.12
24
1.4.13
24
1.5
1.6
1.4.14
TIE-BACKS
25
1.4.15
DIVERLESS INTERVENTION
25
FUTURE DEVELOPMENT
26
1.5.1
26
1.5.2
26
1.5.3
27
1.5.4
27
1.5.5
VIDEOS
28
1.5.6
28
28
30
2.1
INTRODUCTION
30
2.2
INFRASTRUCTURE OWNERSHIP
30
2.2.1
2.3
2.4
STAKEHOLDER INTERFACES
32
35
2.3.1
WHAT IS A STAKEHOLDER?
35
2.3.2
35
2.3.3
IMPORTANCE OF STAKEHOLDERS
37
LEGISLATION
38
2.4.1
UK ACTS
38
2.4.2
UK REGULATIONS
39
2.4.3
UK REGULATORY AUTHORITIES
40
2.4.4
US - ACTS
40
2.4.5
41
2.4.6
US REGULATORY AUTHORITIES
41
2.4.7
42
2.4.8
LAW INTERNATIONAL
43
2.5
MARITIME AUTHORITIES
44
2.6
45
2.6.1
LICENCES - UK
45
2.6.2
LEASES - USA
46
2.7
PERMITS/CONSENTS
46
2.8
SUMMARY
48
ii
3.2
3.3
3.4
INTRODUCTION
49
49
3.1.1
49
3.1.2
COMPLETION
52
53
3.2.1
53
3.2.2
55
3.2.3
55
3.2.4
57
3.2.5
58
3.2.6
BLOW-OUT PREVENTER
59
3.2.7
DRILLSTRING
61
3.2.8
DRILL BITS
62
3.2.9
DRILLING MUD
62
3.2.10
63
3.2.11
CASING DESIGN
65
3.2.12
66
3.2.13
WELL ECONOMICS
66
3.2.14
67
68
3.3.1
WELL MEASUREMENTS
68
3.3.2
OTHER MEASUREMENTS
69
3.3.3
SUMMARY
70
70
3.4.1
PERFORATION
70
3.4.2
SUBSEA TREE
71
3.4.3
SAFETY VALVE
72
3.4.4
PACKERS
72
3.4.5
SWABBING
73
3.4.6
73
3.4.7
74
3.4.8
74
iii
75
4.1
INTRODUCTION
75
4.2
TEMPLATE CONFIGURATION
75
4.3
CLUSTER CONFIGURATION
77
4.3.1
ADVANTAGES
78
4.3.2
DISADVANTAGES
79
4.3.3
SUMMARY
79
4.4
4.5
4.6
82
4.5.1
83
4.5.2
SUMMARY
83
SATELLITE CONFIGURATION
84
SATELLITE WELL
84
5.2
81
HYBRID CONFIGURATION
4.6.1
4.7
80
85
86
INTRODUCTION
86
5.1.2
88
5.1.3
SYSTEM INTERFACES
88
5.1.4
89
5.1.5
SUMMARY
90
SUBSEA TREES
91
5.2.1
INTRODUCTION
91
5.2.2
92
5.2.3
94
5.2.4
95
5.2.5
GUIDELINE OR GUIDELINELESS
96
5.2.6
GAS LIFT
97
5.2.7
CHEMICAL INJECTION
98
5.2.8
99
5.2.9
99
5.2.10
VALVE ACTUATORS
100
5.2.11
ROV INTERFACES
101
5.2.12
CHOKE VALVES
101
iv
5.3
5.4
5.5
5.2.13
CHOKE TRIMS
102
5.2.14
TREE FABRICATION
103
5.2.15
TREE FABRICATORS
104
5.2.16
SUMMARY
104
105
5.3.1
105
5.3.2
110
5.3.3
TOPSIDE EQUIPMENT
110
5.3.4
111
5.3.5
SUMMARY
112
SUBSEA MANIFOLDS
112
5.4.1
112
5.4.2
SCHIEHALLION MANIFOLD
113
5.4.3
MANIFOLD FABRICATION
117
5.4.4
LEAKING MANIFOLD
118
5.4.5
119
119
120
6.1
INTRODUCTION
120
6.2
120
6.3
6.2.1
INTRODUCTION
120
6.2.2
121
6.2.3
122
6.2.4
122
6.2.5
123
123
6.3.1
INTRODUCTION
123
6.3.2
124
6.3.3
126
6.3.4
SUBSEA COMPRESSORS
127
6.3.5
128
6.3.6
128
6.4
6.5
6.6
129
6.4.1
INTRODUCTION
129
6.4.2
130
6.4.3
TORDIS PROJECT
131
6.4.4
133
SUBSEA HIPPS
134
6.5.1
INTRODUCTION
134
6.5.2
135
6.5.3
136
6.5.4
136
137
138
7.1
INTRODUCTION
138
7.2
TEMPLATE DESIGN
138
7.3
7.4
7.2.1
TEMPLATE REQUIREMENTS
138
7.2.2
139
7.2.3
140
7.2.4
140
7.2.5
142
7.2.6
143
7.2.7
144
7.2.8
145
SEABED INTERFACE
146
7.3.1
SEABED DATA
146
7.3.2
MUD MAT
146
7.3.3
SKIRT
147
7.3.4
CONVENTIONAL PILE
148
7.3.5
SUCTION PILE
149
7.3.6
150
151
7.4.1
CONSTRUCTION MATERIALS
151
7.4.2
152
7.4.3
COATINGS AND CP
153
7.4.4
153
7.4.5
TESTING
154
vi
7.4.6
7.5
7.6
CASE STUDIES
155
156
7.5.1
TROIKA TEMPLATE
156
7.5.2
SHELL MENSA
157
7.5.3
159
7.5.4
159
160
161
8.1
INTRODUCTION
161
8.2
INSTALLATION ISSUES
161
8.3
8.4
8.2.1
INTRODUCTION
161
8.2.2
161
8.2.3
162
8.2.4
163
8.2.5
164
8.2.6
METOCEAN ISSUES
165
8.2.7
166
8.2.8
VESSEL STABILITY
167
8.2.9
168
INSTALLATION METHODS
168
8.3.1
INSTALLATION ON WIRES
168
8.3.2
DRUM WINCHES
170
8.3.3
170
8.3.4
HEAVE COMPENSATION
173
8.3.5
175
8.3.6
PENCIL-BUOY METHOD
176
8.3.7
INSTALLATION ON A TUBULAR
177
8.3.8
179
AT THE SEABED
179
8.4.1
SEABED PREPARATION
179
8.4.2
INSTALLING PILES
180
8.4.3
182
8.4.4
183
8.4.5
184
8.4.6
GUIDELINES
185
vii
8.5
8.6
8.4.7
HOT INSTALLATION
185
8.4.8
186
NEW TECHNOLOGY
187
8.5.1
PENDULAR INSTALLATION
187
8.5.2
188
8.5.3
SYNTHETIC ROPES
189
8.5.4
190
190
9.0 WORKOVER
191
9.1
INTRODUCTION
191
9.2
191
9.3
192
9.4
9.5
9.3.1
WIRELINE
192
9.3.2
194
9.3.3
COILED TUBING
195
9.3.4
DRILLSTRING WORKOVER
198
9.3.5
199
200
9.4.1
200
9.4.2
SAND REMOVAL
200
9.4.3
SAND PACKING
200
9.4.4
DEPOSITION
201
9.4.5
FRACTURING
202
9.4.6
ACID JOB
203
9.4.7
204
9.4.8
204
9.4.9
RESERVOIR REMEDIATION
205
9.4.10
206
9.4.11
FISHING
206
9.4.12
JARRING
208
9.4.13
SUMMARY
208
209
9.5.1
209
9.5.2
CASING FAILURE
209
9.5.3
CASING REPAIR
210
viii
9.6
9.5.4
SIDETRACKING
211
9.5.5
COMPONENT REPLACEMENT
211
9.5.6
SUMMARY
212
WORKOVER SUMMARY
212
213
10.1 INTRODUCTION
213
213
10.2.1
INTERNATIONAL REGULATIONS
213
10.2.2
214
10.2.3
US ABANDONMENT REGULATIONS
215
10.2.4
216
216
10.3.1
216
10.3.2
218
10.3.3
SUMMARY
218
219
10.4.1
SUMMARY
223
223
ix
9.0 Workover
9.1
Introduction
In this module we will learn about minor and major workover operations, and the equipment required
for these. We will look at the specific jobs which may be performed during a workover, and the reasons
for doing so.
9.2
If a zone has been depleted then it may be necessary to drill to a new level and activate
a new area for production.
Workover is performed from the surface by lowering tools on wirelines, coiled tubing or drillstrings.
Some methods require the well to be killed and some do not.
production, filling the well bore with drilling mud, and lifting out the production tubing,
To date it has not been possible to workover a well from subsea although research is being performed in
this field.
Page 191
9.3
9.3.1
Wireline
Wirelines are relatively weak, making them suitable for only light-weight well interventions.
No derrick required
E-Line is a wireline containing an insulated electrical conduit, which can be used to operate the tool
downhole.
Before a wireline is lowered from the vessel, a package is attached to the top of the subsea Christmas
tree. The package comprises a BOP at the bottom, with a lubricator and then a stuffing box attached to
it. The lubricator contains grease at a higher pressure than the well, and the stuffing box has rubber
seals which surround the wireline, preventing entry of seawater or loss of lubricator fluid.
A heave compensator in the vessel allows the tool to be lowered steadily despite vessel motion due to
swell.
Page 192
for
wireline
is
shown
below,
courtesy
of
leespecialities.com
The lubricator (right) is shown courtesy of Schlumberger.
The lubricator is for a wireline intervention with a riser,
where the lubricator and stuffing box are located at the
topsides and the BOP is located subsea.
Page 193
9.3.2
Riserless well intervention does not require a riser to be lowered from a drilling vessel. A much lighter
vessel may be used for the workover saving money.
The Island Frontier is a vessel built by FMC and Aker Kvaerner for riserless light well intervention
(RLWI). It is a monohull dynamically
positioned (DP) vessel with a 70
tonne (77 US ton) handling tower
and a 130 tonne (143 US ton) crane.
It is capable of performing wireless
intervention and workover in water
depths up to 500 m (1640 ft) and
Page 194
9.3.3
Coiled Tubing
Coiled tubing is a metal tube, which can be wound onto a drum, and unwound into the well bore for
performing workover jobs. It has a few advantages over wireline intervention:
Coiled tubing can push as well as pull objects inside the well.
Compressive strength
Fluid pumped through tubing and back to surface through production tubing
Multitude of uses
Log onto the modules WebCT site and watch the video entitled Coiled Tubing Manufacture
at > Resources > Video Files > Coiled Tubing Manufacture
This video (courtesy of Precision Tubing) shows how coiled tubing is manufactured from steel
strip using high frequency induction welding and wound onto spools. Once fabricated the
internal diameter of the coiled tubing is validated by blowing a steel gauge ball through the
tubing. The tubing is then hydrotested to 90% of specified minimum yield strength and
purged with nitrogen to remove water vapour.
Page 195
9.3.3.1
9.3.3.2
Coiled tubing can be run through a top tension riser, a conductor or a workover riser. The coiled tubing
unit is usually supplied as a compact unit with fully integrated services in order to save time.
Shown in the picture below is a GeoFlo flow remediation tool. It is attached to coiled tubing and
inserted down a flowline to clear blockages. It is very similar to a jet wash tool, which is used with
coiled tubing to clean well bores.
Page 196
Temperature
Pressure
Loading
9.3.3.3
Coiled tubing is inspected after each deployment as it is spooled back onto the reel. The inspection
techniques need to determine if the coiled tubing has elongated or become distorted during the
unreeling process. It is also important to inspect for gouges and other marks on the coiled tubing
surface where the tubing has been in contact with the production tubing, since these marks can result in
crack growth.
The inspection results are stored on a computer and compared with the previous inspection, based on a
tube position reference, to identify any deterioration in defects.
Ultrasonic array
Cracking
Diameter gauges
Ovality
Gouges, flats, scuffs
Inspection data over entire length retained for comparison over life of tubing
Page 197
9.3.4
Drillstring Workover
For major jobs such as replacing large pieces of equipment, or the deeper drilling of a well, it may be
necessary to use a drillstring workover. This is because a drillstring can carry more weight, and transmit
more torque to the tool. Using a drillstring is the most expensive form of well workover.
A Mobile Offshore Drilling Unit (MODU) is required for this job, as the production tubing must be
removed, and a riser installed. A MODU has a derrick, which is used to lower the workover riser in
single, double or triple joints, depending upon its height. It is worth noting that a workover riser does
not need to be as wide as a drilling riser, as it is not required to accommodate casing.
If the BOP is installed at the topsides then a high pressure workover riser must be used. The use of a
riser and a drillstring allows full communication with the well, as fluids may be pumped through the
drillstring and the annulus.
An advantage of drillstring workover is that in the case that the intervention fails, the MODU is already
in place to facilitate further drilling.
Major workover
Jackup MODU
Page 198
9.3.5
Wireline is lowered from a reel on a small vessel. It may contain an electrical conduit for powering
equipment (E-line). Wireline may be used in riserless well intervention.
Coiled tubing is also deployed from a reel onboard a small vessel. It is more versatile than wireline for
two reasons:
necessary for replacing some subsea equipment, and sometimes the deeper drilling of a well.
Page 199
9.4
9.4.1
A minor workover is performed using wireline or coiled tubing on a live well. It may be done with or
without a workover riser and can be performed using a light intervention vessel, which saves money.
9.4.2
Sand Removal
Coiled tubing
o
9.4.3
Sand Packing
A weak formation with crumbling sand may impede production. One solution is to pump resin slurry
(sand and resin) through the coiled tubing. The resin hardens to form a matrix which oil and gas, but
not sand can pass through. Once the resin has hardened it is common to drill a small pilot hole using a
mud motor on the end of the coiled tubing. This eases the flow of hydrocarbons.
Gravel packing is another, similar method used to achieve this, whereby gravel is used instead of sand.
Page 200
Resin slurry
o
Hardens
o
Drilled
o
9.4.4
Deposition
Paraffins and asphaltenes are long-chain polymers which are known to solidify in the production tubing,
reducing the possible production flowrates.
A paraffin scratcher may be lowered on a wireline to remove the deposits mechanically. This requires
production to be temporarily stopped.
A permanent solution to deposition is a magnetic fluid conditioner (MFC), which can be installed
downhole. High-energy, permanent magnets alter the cloud point, viscosity, pour point, surface tension
and deposition temperatures of the oil, and make paraffin and asphaltene deposition less likely.
Page 201
9.4.5
Low
Fracturing
permeability
in
the
formation
can
be
The proppant must be hard enough to hold the crack open once the pressure is
reduced, but not so hard that it fractures the formation and allows the crack to close around it.
9.4.5.1
Fracturing Procedures
When performing a fracturing operation the well bore must be first cleaned so that debris does not clog
the fissures which are supposed to be widened. Packers can be inserted above and (if necessary) below
the perforated zone.
The pressure is monitored during the process, to determine when the job is
complete.
Pressure monitored
Page 202
9.4.6
Acid Job
An acid job is similar to hydrostatic pressure fracturing, in that a fluid is pumped down coiled tubing to
increase the permeability of the formation. Special equipment must be used, such as lined pipes and
processing equipment, as acid corrodes metal.
Hydrochloric acid is cheap and suited to dissolving limestone or dolomite formations. Hydrofluoric acid
is more expensive but necessary to dissolve the quartz that is the main constituent of sandstone. There
are associated health hazards because acid is harmful to the skin and respiratory system.
Surfactants are injected with the acid to stop it forming an emulsion with crude oil, and sequestering
agents prevent precipitation of minerals from the acid solution. As the acid eats away rather than props
open the cracks, proppants are not required.
Limestone or dolomite
o
Hydrochloric acid
Sandstone
o
Hydrofluoric acid
Health hazard
Additives
o
Corrosion inhibitor
Surfactants
Sequestering agents
Page 203
9.4.7
Coiled tubing can be used to clean the production tubing and perforations
using high pressure water or solvents.
insert and remove inflatable packers and in-line valves to isolate sections of
the production tubing.
9.4.8
Wire scratchers
Jet washers
Inflatable packers
In-line valves
After a well has become depleted it may be necessary to close off production and begin extracting from
another layer. The new zone may be higher or lower than the original.
Squeeze cementing is used to fill up the
perforations.
The
Page 204
Sidetracking involves isolating the old zone, and then drilling off at an angle from the well bore at a
higher point.
If further drilling is necessary then a full workover using drillstring would be necessary. Moving the
production zone upwards can be done using only coiled tubing.
9.4.9
Squeeze cementing
Sidetracking
Reservoir Remediation
Fracturing
o
Perforation guns
Explosive shaped-charges
fracture formation and maximise
contact area of well bore with
formation
Acidising
o
Perforating tool
Page 205
9.4.10
Drilling is carried out by a slimline bit which is driven by the flow of mud through the
coiled tubing or an electric motor, supplied from an internal electrical cable. Material
removed during drilling, fines, is returned to the surface with the drilling mud through the
annulus. The mud is then filtered to remove the fines before being pumped down the
coiled tubing again. The diagram shows a coiled tubing drilling assembly courtesy of
Schlumberger.
Drill bit
Slimline bit
o
Motorhead Unit
9.4.11
Fishing
Page 206
Watch an animated flash movie of this process on the modules WebCT site. You can find the
file at > Resources > Lecture Note Animations > Fishing
Page 207
9.4.12
Jarring
9.4.13
Summary
Removal of sand from the wellbore, and sand packing to increase production rates.
Removal of scale and deposits from the inside of the production tubing.
Page 208
9.5
9.5.1
A major workover requires that production be stopped and the well killed. The well is killed by pumping
heavy mud into the annulus. The production tubing must be lifted. This is more easily done in a
horizontal tree, which can remain in place during removal. If a vertical tree is in place over the well
then the tree must be removed before the production tubing can be lifted. A BOP is installed either
subsea or at the surface. If a surface BOP is used then a high pressure riser is necessary. A subsea
BOP does not require the use of a riser at all.
A drilling rig is necessary for a major workover, which is more costly than a light intervention vessel.
Trees
o
Horizontal
Vertical
9.5.2
BOP
o
Surface or subsea
Drill rig
Casing Failure
A failure in the casing may cause fluids to leak into the formation or vice versa. Casing failures may be
caused by corrosion of the metal by acids, water or carbon dioxide which may all be present in the
drilling mud and the produced oil. Acid jobs may have caused failure of the casing through corrosion.
Abrasion and erosion from produced fluids and gas lift may cause wear and rupture the casing.
A collapse of the formation around the casing may cause it to rupture or buckle inwards.
Corrosion
o
Abrasion
Mechanical collapse
Page 209
9.5.3
Casing Repair
When the casing has been damaged one of the following courses of action must be taken:
Page 210
9.5.4
Sidetracking
A retractable milling tool is lowered and used to mill out the casing
directly above the blockage. Cement is then poured onto a basket or
removable packer to block up the well.
A whipstock (which is a
Cement plug
Insert whipstock
Drill
A Whipstock
9.5.5
Component Replacement
Some pieces of subsea equipment require a major workover to be performed for replacement.
Some subsea safety valves require a major workover and some do not.
The removal of an electric submersible pump (ESP) usually requires a major workover to be performed,
but wireline retrieval is possible.
Page 211
Some wells are fitted with a gas lift, whereby gas is injected via a valve from the annulus to the
production tubing. The gas decreases the density of the well fluids, thus increasing the production
rates. It is necessary to periodically replace the gas-lift valves, and this may be done during a minor
workover, but sometimes requires a major workover.
9.5.6
Summary
Major workover is necessary if the casing becomes damaged, or some components need replacing. It is
often necessary when a wireline or coiled tubing workover has failed to do the job.
9.6
Casing failure
Component replacement
Workover Summary
In this module we first looked at the reasons for performing a workover on a well:
Stimulate production
Remediation
Workover operations
Page 212
Then we looked at
10.0
10.1 Introduction
This module explains the requirements for decommissioning and abandoning of subsea systems. It
focuses primarily on the abandonment of wells since this is a complex operation compared to the
retrieval of subsea equipment.
International Regulations
Article 5 of the Geneva convention was the first international regulation for removal of marine
structures. At this time no one has envisaged the requirement for deep sea structures. In 1982 article
5 of the Geneva convention was superceded by the United Nations convention on the law of the seas
(UNCLOS), article 60(3) of which permitted partial removal of offshore structures provided the
International Maritime Organisation (IMO) criteria were met. This convention entered into force in 1994
and was ratified in the UK in 1997.
The IMO published its first guidance on decommissioning in 1989 which required the complete removal
of offshore structures in water less than 75 m (246 ft). This was increased to 100 m (328 ft) in 1998.
Page 213
10.2.2
OSPAR is the name given to the Oslo and Paris convention for the protection of the marine environment
of the north-east Atlantic. It comprises the following members:
Belgium
Ireland
United Kingdom
Denmark
Netherlands
European Union
Finland
Norway
Luxembourg
France
Portugal
Switzerland
Germany
Spain
Iceland
Sweden
Page 214
Installation
(excluding
topsides)
Weight
(tonnes)
Complete
removal to
land
Partial
removal to
land
Leave wholly
in place
Re-use
Disposal at
sea
<10,000
>10,000
Any
Any
Any
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
No
No
No
No
Yes
No
No
Yes
Yes
Yes
Yes
Yes
No
No
Yes
No
No
Fixed Steel
Fixed Steel
Concrete gravity
Floating
Subsea
As can be seen from the above, all subsea structures must be completely removed or re-used.
10.2.3
US Abandonment Regulations
In the US the approach is more pragmatic, partially due to the number of subsea structures in deep
water, and allows those subsea structures in water depth greater than 800 m (2624 ft) to be left in
place.
Re-use
Subsea equipment
o
Page 215
10.2.4
The requirements for abandonment of subsea systems are laid down in international conventions. The
EU and USA have their own regulations which clarify the IMO and UNCLOS requirements.
This section focuses on the abandonment of platforms in the North Sea, however, a similar situation has
developed in other mature offshore markets such as the Gulf of Mexico.
The first structure to be abandoned in the North Sea was the Piper
Alpha platform (right) in 1988 following the catastrophic fire. This
was toppled over onto an unused part of the seabed.
The next milestone was the decommissioning of the Brent spar in
1995. Although adhering to international regulations at the time by
applying to sink the spar, a public outcry led to the spar being cut up
and used in a quay construction.
The next big milestone in the North Sea was the removal of the
Maureen platform.
Page 216
Brent Spar
Maureen platform
Piper Alpha
o
Brent Spar
o
1988 - Toppled
1995 to 1999 Reused in quay
Maureen
o
The first North Sea subsea development to be abandoned was the Crawford field in 1991. This was
removed using a heavy lift vessel and returned to shore to be scrapped. The Blair field is the only field
to date where the subsea equipment has been re-used.
Crawford
o
Blair
o
Ardmore
o
Frigg
o
1992 - Reused
Staffa
o
Page 217
10.3.2
The graph below is taken from the UK Department of Industry website and represents the historical and
predicted number of abandonments in the North Sea up to 2030. It can be seen that the number of
subsea fields which require abandonment is increasing and will peak at about 2015.
10.3.3
Summary
International and national regulations have been developed for abandoning offshore structures. In the
UK and EU these typically require the removal of all subsea structures, in the USA subsea structures can
be left on the seabed if they are in a water depth of 800 m (2624 ft) or more.
Page 218
the field is remote from the drilling vessel base, however, they
can usually abandon a well fairly quickly and most of the
subsea equipment can also be retrieved on the drill string.
Multi-service vessels are much cheaper than drilling vessels
and recent developments now allow complete abandonment to
be undertaken from them using a combination of coiled tubing
Drilling Rig
and wireline.
The process of abandoning the well is similar for both types of
vessel and is described in the following slides.
Vessels
o
Drilling rig
Expensive
Quick
Use drill string to kill and plug wells and to remove subsea equipment
Cheaper
Shut-in production at the tree. The production to the flowline must be isolated before
disconnection.
Depressurise flowline. The flowline is blow down to remove as much of the contents as
possible.
Page 219
Hydrotest plug.
Page 220
The
and
provides
secondary
barrier.
retrieved.
Page 221
Watch an animated flash movie of this process on the modules WebCT site. You can find the
file at > Resources > Lecture Note Animations > Abandonment of Subsea Wells
Log onto the modules WebCT site and watch the video entitled Abandonment at
> Resources > Video Files > Abandonment
The video is courtesy of Norse Cutting & Abandonment. It shows how subsea casing is
retrieved to the surface during the decommissioning of a well.
The casing and concrete is cut using a high-pressure water-cutter run in on coiled tubing
(shown below):
The picture below shows the horizontally-mounted drill, which is used to bore through the
pipe so that a pin may be inserted. Once the pin is in place, a cutter slices the pipe so that
the upper section may be lifted out and removed.
Page 222
The picture below shows lengths of casing that have been removed using this method. The
cement between the conductor and the casing can be seen in the cross section, as well as
the pin which was used to hold the inner tubing in place.
10.4.1
Summary
Abandonment of subsea wells is a complex operation that is traditionally carried out by drilling vessels,
however, new methods have been developed which use multi-service vessels at much cheaper day
rates.
Complex operation
Page 223