Uttarakhand PWD Schedule of Rate
Uttarakhand PWD Schedule of Rate
Uttarakhand PWD Schedule of Rate
Th
CIRCLE TEHRI
SCHEDULE OF RATES
FOR
TEHRI DISTRICT
ANNEXTURE 1
UNIT WEIGHT OF MATERIALS
Bitumen
Bricks
Cement
Mild steel
Cast iron
Ply Wood (1 mm thick)
Stone ballast
Shingle 3mm to 38mm
Sand
Chir Wood
Deodar wood
Sal Wood
Teak Wood
Sheet glass 1 mm thick
Stone for masonry
Sita Tax Low density particle board
Black plain iron sheet
17
0.63 mm thick (24 Guage)
18 do- 0.8 mm thick (22 Guage)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Approx
Approx
For Building and Bridge works water allowance @ 1.5% may be added on the
items where water is required and the contractor has borne the entire
expenditure on water arrangements. No water allowance is to be added if water
is available within 100 M free of cost.
J.E. (Tech.)
8th Circle PWD New Tehri
7 For T&P sundries and lump-sum items in the Skelton for the analysis of rates
the provision will be made 25 Times that of the provision made in 1962
Almora Distt. Schedule of rates and 30 Times for R.C.C. work for Buildings
and bridges and 20 times and 25 times on Lucknow Skelton made in 1973
accordingly.
8 With the Analysis of rates and while working out. R.M.R., a site plan showing
the location of site of work, quarry, place of issue of materials etc, and
minimum distance by pucca/unmetalled road/bridle road/foot track must
invariably be enclosed. The Divisional Engineer should record a certificate
that the distances for the cartage of different materials are correct and is by
shortest possible route and that the material of desired specification is not
available at a lesser distance.
9 The method of measurements shall be as per 1962 Almora distt. Schedule of
rates/latest detailed P.W.D. specifications/circulars issued by the chief
Engineer.
10 The rates include material for centering / shuttering, scaffolding, (unless
otherwise specifically mentioned in particular items), sundries, gurras, nails,
carborandum stone, mansion polish, oxalic acid, saw dust, brushes, wooden
gullies, small springs for fixing of glass pans etc.
11 Wherever the word fine sand occurs in this schedule of rate, it will mean the
sand of fineness modulus 1.25. Where as course sand shall be of fineness
modulus ranging between 1.7 to 2.3
12 If the rates of any item given in this schedule superceded by any authority
higher than S.E., the same shall be applicable for those items.
13 For items which are not part of the PWD Skeleton will be taken as per
Standard data book of MOSRTH(Items related to hotmix plant,sign
boards,crash barrier)
J.E. (Tech.)
8th Circle PWD New Tehri
CHAPTER - 1
Note:
The rates for item 2, 3, 38, 39 and 41 are quarry rates inclusive of royality but exclusive of sales tax and
Contractor's profit.
The rates for all others items are at nearst rail head inclusive of octroi, royalty, sales tax and also carriage
2
upto Municipal limit (except for item 1, 45 and 46) but exclusive of Contractor's profit.
Wastage @ 2% for grit, shingle and sand and @ 1% for stone ballast shall be applicable for preparing
3
RMR for road work.
No Voids shall be deducted while taking supply of stone ballast, grit and split boulder.
4
Five percent contractor's profit may be given while taking the supply through some agency other than
5
direct supplier.
No quarring charges shall be paid on item 2, 3, 38, 39, 41
6
Item No.
Material
Unit
Rate (Rs.)
1a)
Bricks M-100 (Standard size) At Rishikesh Rail Head
1000 No.
2700.00
1b)
Straight over burnt
1000 No.
1800.00
2
Ballast/grit (hard stone)
Graded/hand broken at quarry (road side)
(a) 20 M.M. size
Per Cum
400.00
(b) 20 M.M. to 40 M.M.
Per Cum
360.00
(c ) 40 mm size
Per Cum
330.00
(d) 53 to 22.40 M.M.
Per Cum
320.00
(e) 45 to 63 M.M.
Per Cum
275.00
(f) 90 to 45 M.M.
Per Cum
250.00
(g) Split Boulder 100-150 M.M.
Per Cum
155.00
(h) River boulder at quarry minimum weight 50 Kg.
Per Cum
150.00
(i) Brick ballast(over burnt 40mm gauge)
Per Cum
550.00
(j) Brick ballast(Class 100 25mm gauge)
Per Cum
680.00
3
(a) River shingle or stone girt quarried from Hill side at
Quarry
10 M.M. to 16 M.M.
Per Cum
290.00
16 M.M. to 22.40 M.M.
Per Cum
265.00
(b) For stone Crushed grit
(i) Sizes 10 MM to 16 Mm
Per Cum
425.00
(ii) Sizes 16 MM to 22.40 Mm
Per Cum
425.00
(iii) Sizes 5 MM to 10 Mm
Per Cum
410.00
(iv) Stone dust 2.60 MM or below
Per Cum
360.00
(v) Sizes 10 MM to 16 Mm (11.20 M.M. nominal size)
Per Cum
425.00
(vi) Sizes 16 MM to 22.40 Mm (13.20 M.M. nominal size)
Per Cum
425.00
(vii)Granular Sub base(G.S.B)Material of specified size.
Per Cum
360.00
(viii)River bed material
Per Cum
380.00
4
Bolt and nuts etc.
(a) upto 6 M.M. dia
Per Kg
70.00
(b) above 6 M.M. to 12 M.M dia
Per Kg
65.00
(c ) above 12 M.M. to 25 M.M. dia
Per Kg
60.00
5
Bolts and nuts 13 M.M. dia to 22 M.M. dia
Deleted
6
Bees Wax
Deleted
7
Bamboos
(a) 25 cm to 4 cm dia
Per R.M.
As per Van Nigam
(b) above 4 cm and upto 8 cm dia
Per R.M.
Rates
8 (A) Bellies Sal
(a) 8 cm (mean) dia
Per R.M.
(b) 10 cm (mean) dia
Per R.M.
As per Van Nigam
(c ) 12.5 cm (mean) dia
Per R.M.
Rates
(d) 15 cm (mean) dia
Per R.M.
(e) 20 cm (mean) dia
Per R.M.
8 (B) Eucalyptus Bellies
(a) 9 cm (mean) dia
Per R.M.
(b) 12 cm (mean) dia
Per R.M.
(c ) 15 cm (mean) dia
Per R.M.
As per Van Nigam
(d) 18 cm (mean) dia
Per R.M.
Rates
(e) 30 cm (mean) dia
Per R.M.
9
Cement port Land (43 Grade)
Per bag of 50 kg.
240.00
10
Cement (White)
Per bag of 50 kg.
618.00
1
J.E. (Tech.)
8th Circle PWD New Tehri
Item No.
Material
Unit
Rate (Rs.)
11
Coaltar
12
Caustic Soda
Per Kg.
36.00
13
Cinder
Deleted
14
Cotton Rope
Per Kg.
95.00
15
16
Glass ordinary
(a) 5.0 M.M. thick plain Best Quality cut to size
(b) 5.0 M.M. thick frosted including wastage
(c) 5.0 M.M. thick pin point
(d) 4.0 M.M. thick plain
(e) 4.0 M.M. thick frosted
(f) 4.0 M.M. thick pin point
(g) 3.0 M.M. thick plain
(h) 3.0 M.M. thick frosted
(i) 3.0 M.M. thick pin point
in 5 Kg. Tin
in 1.5 Kg. Packet
Per Sqm
Per Sqm
Per Sqm
Per Sqm
Per Sqm
Per Sqm
Per Sqm
Per Sqm
Per Sqm
350.00
360.00
215.00
220.00
285.00
180.00
230.00
250.00
160.00
Per R.M.
Per R.M.
Per R.M.
Per R.M.
7.00
4.50
4.50
4.00
Per Kg.
Per Kg.
6.00
4.50
19
Per Kg.
Per Kg.
Per Lit.
55.00
45.00
57.00
20
Per Qtl
Per Qtl
Per Qtl
Per Qtl
Per Qtl
Per Qtl
Per Qtl
3600.00
4300.00
3600.00
3550.00
3575.00
5400.00
4300.00
Per Qtl
4400.00
Per Qtl
4000.00
Per Qtl
Per Qtl
Per Qtl
Per Sqm
3600.00
3550.00
4000.00
160.00
18
J.E. (Tech.)
8th Circle PWD New Tehri
Item No.
Unit
Rate (Rs.)
Per Qtl
Per Qtl
Per Qtl
185.00
225.00
225.00
22
Marble dust
Per Qtl
210.00
23
Deleted
24
25
Nails (ordinary)
Nails (wire)
Per Kg.
Per Kg.
55.00
55.00
26
Per Lit
Per Lit
85.00
55.00
27
21
Material
Per Ltr.
Per Ltr.
Per Ltr.
Per Ltr.
Per Ltr.
Per Ltr.
Per Ltr.
Per Ltr.
Per Ltr.
Per Ltr.
(50 Kg. Drum)
As per actual
price list of
standard
Manufacturing Firm
Per Ltr.
Per Ltr.
Per Ltr.
28
Per Kg.
48.00
29
Per Kg.
225.00
30
31
32
33
Per R.M.
Per R.M.
Per R.M.
Each
Each
Each
Each
Each
Each
J.E. (Tech.)
8th Circle PWD New Tehri
Per RM
Per RM
Item No.
Material
34
Cast iron pipe (Rain water)
(a) Rose cowl 15 cm dia
(b) -do- but 10 cm dia
(c ) Head 5 cm dia
(d) -do- but 10 cm dia
(e) Shoe 5 cm dia
(f) -do- 10 cm dia
(g) Bend 5 cm dia
(h) -d- but 10 cm dia
Unit
Rate (Rs.)
Each
Each
Each
Each
Each
Each
Each
Each
35
Per Kg.
Per Kg.
Deleted
Deleted
Deleted
40.00
75.00
-
36
Per Kg.
Per Kg.
54.00
60.00
37
Deleted
38
Per Cum
500.00
39
Per Cum
400.00
40
Surkhi
Deleted
--
41
Stone
(a) Stone for building
(b) Stone for site development
Per Cum
Per Cum
300.00
250.00
42
Whiting
Deleted
--
43
100No's
100No's
28.00
18.00
44
Wood preservative
Per Ltr.
45
Per Cum
Per Cum
Per Cum
Per Cum
Per Cum
Per Cum
Per Cum
Per Cum
Per Cum
Per Cum
Per Cum
Per Cum
Per Qtl
Per Sqm
110.00
46
47
48
J.E. (Tech.)
8th Circle PWD New Tehri
300.00
CHAPTER - 2
LABOUR
0 la0
1
4
(a)
(b)
Ekn
vdq'ky Jfed&
csynkj] pkSdhnkj] okVjeSu] ekyh] etnwj] ySueSau] gSYij] Mkdjuj] lQkbZ uk;d iw.kZ
dkfyQ fHkf'r] VsyhQksu] ,sVsUMsV] gSejeeSau] iEi ,sVsUMsV
v)Z dq'ky Jfed%&
gkSy fMyj] jkWd dVj] OgkbV ok'kj] usikyh Jfed] [kku Jfed] ySc lgk;d] xst
jhMj] Dyhuj] odZ ,tsaV] esV] odZ lqijokbtj] feDlj vkijsVj] e'khu vkijsVj] iEi
vkijsVj] tujsVj dEizslj vkijsVj 10 KV rd dqd] Cyw fizaVj] QksVks LVsV e'khu
vkijsVj] foUp vkijsVj] twfu;j fQVj] LVksu dVj@Mslj] foVqfeu csynkj] dEizs'kj
vkijsVj] ,slhlsVsaV cksjjA
dq'ky Jfed%&
v feL=h] vehu
c eSlu] dkjisUVj] CySdfLEkFk] isUVj] IyEcj] Vslj] losZ;j] fjosVj] oSYMj] fQVj]
VuZj] bySfDVf'k;u] odZ lqijokbtj] Mkboj] dEIVwj vkijsVj] eksyMj] ekjdj]
eSdsfud] gS.MiEi cksjj] lk;jA
vU; yscj njsa%&
vkneh ,d [kPpj ds lkFk
vfrfjDr [kPpj gsrq
J.E. (Tech.)
8th Circle PWD New Tehri
Lohd`r nj
120.00
135.00
220.00
210.00
255.00
165.00
CHAPTER-3
CARTAGE OF MATERIALS
Note:1
Index for distance and height shall not be applicable to the cartage rates.
2
The rates include contractor's profit except item no 141
The cartage rates are, for both side journey i.e. return journey cartage shall not be added in these
3
rates.
Unit
Rate (Rs.)
Item
Description
141
Cartage of materials like ballast, sand, grit, stone, coal, wood
(a)
(excluding fuel wood) etc. Including loading unloading goods tax
(if any) but excluding stacking
1st Km.
Per cum/km.
77.00
2nd and 3rd Km.
Per cum/km.
12.00
4th and 5th Km.
Per cum/km.
11.00
6th to 10th Km.
Per cum/km.
10.00
11th to 20th Km.
Per cum/km.
7.80
21st to 30th Km.
Per cum/km.
7.00
31st to 50th Km.
Per cum/km.
6.60
Beyond 50 Km.
Per cum/km.
5.80
141
Cartage of materials like cement, steel, fuel wood, lime etc.
(b)
including loading, unloading and good tax (if any) but excluding
stacking.
1st Km.
Per MT/km.
57.00
2nd and 3rd Km.
Per MT /km.
11.00
4th and 5th Km.
Per MT/km.
8.00
6th to 10th Km.
Per MT/km.
7.00
11th to 20th Km.
Per MT/km.
6.00
21st to 30th Km.
Per MT /km.
5.40
31st to 50th Km.
Per MT /km.
4.60
Beyond 50 Km.
Per MT/km.
3.70
141 (c) Same as item No. 141 (b) but for Cartage of maxphalt.(packed)
1st Km.
Per MT/km.
59.00
2nd and 3rd Km.
Per MT /km.
12.00
4th and 5th Km.
Per MT/km.
9.00
6th to 10th Km.
Per MT/km.
7.70
11th to 20th Km.
Per MT/km.
6.00
21st to 30th Km.
Per MT /km.
5.80
31st to 50th Km.
Per MT /km.
5.00
Beyond 50 Km.
Per MT/km.
4.10
As per tanker rate of I.O.C.L
141(d) For cartage of Bulk Bitumen
Condition for items 141 (a), 141 (b) and 141 (c)
1
2
3
The above rates are for pucca roads, for katcha roads 33% extra up to 5 km. and 20% extra beyond 5
km. is allowed. Roads up to soling stage to be treated as katcha road, inter coat and above to be taken
as pucca roads.
For cartage of 1000 Nos. of bricks multiply the rate of item no, 141 (a) by 2.40 times.
For cartage of Bridge Part (Unwieldy loads) 15% extra will be allowed on item 141(b)
142 (a) Cartage of stone boulder, ballast. Coal, sand and similar materials by head load including loading and
unloading but excluding stacking.
(i) up to 3 chains (90 m )
per cum/chain
15.00
(ii) Beyond 3 chain up to 10 chains (90 m to 300 M)
per cum/chain
11.50
143(a)
As in item No. 142 (a) above but for cement, steel, timber, wood and other such materials.
(i) up to 3 chains (90 m )
per qtl/chain
1.40
(ii) Beyond 3 chain up to 10 chains (90 m to 300 M)
per qtl/chain
1.10
J.E. (Tech.)
8th Circle PWD New Tehri
Item
Description
Unit
144 As in item no. 142 (a) and 143 (a) above but when mules are
used in cartage.
(i) Up to 0.5 Km.
Per qtl./0.5km.
(ii) Beyond 0.5 km.
Per qtl./0.5 km.
Rate (Rs.)
Unit
Item
Description
145 As in item no 142(a) and 143 above but for unwieldy loads
requiring cartage by more than two laborers simul tancously.
(a) For regular bridle roads.
Per qtl./0.5km.
(b) For foot tracks.
Per qtl./0.5km.
Rate (Rs.)
146
147
148
(a) Loading of materials like ballast, coal, grit etc. but excluding
stacking.
(b) Same as item 146 (a) above but like cement, maxphalt, steel,
lime etc.
(c) Loading of bricks into truck.
(d) Loading of unwieldy materials.
(e) Loading of hume pipe of NP-2
(i) Up to 30 cm. dia.
ii) Above 30 cm. but upto 90 cm. dia,
iii) Beyond 90 cm. dia.
(f) Loading of maxphalt drums.
(a) Unloading of materials like ballast, coal, grit, sand,
etc.
excluding stacking.
(b)Unloading of materials like cement, steel, maxphalt, lime etc.
but excluding stacking.
(c) Unloading of bricks including stacking
(d) Unloding of unwieldy materials.
(e) Unloading of hume pipe.
(i) Up to 30 cm. dia.
ii) Above 30 cm. but upto 90 cm. dia,
iii) Beyond 90 cm. dia.
(f) i) Unloading of cement, steel, and other items from Railway
wagon and stacking on the plate from
ii) Same as above but for Maxphalt.
(a) Stacking of stone ballast, grit, and stone boulders etc.
(b) Same as item 148 (a) but for cement, coal and maxphalt, lime
etc.
(c) Stacking of maxphalt drums including shifting up to 30 mtr.
(d) Stacking of bricks.
J.E. (Tech.)
8th Circle PWD New Tehri
10.00
5.00
33.00
44.00
Per Cum
14.00
Per M.T.
Per%0
Per M.T.
13.00
30.00
30.00
Each
Each
Each
Per M.T.
9.80
18.70
23.00
45.00
Per cum
11.30
Per M.T.
Per%0
Per M.T.
10.00
20.00
25.00
Each
Each
15.00
20.00
40.00
Per M.T.
Per M.T.
28.00
25.30
Per cum
Per M.T.
13.00
13.00
Per M.T.
Per %0
16.00
15.00
CHAPTER - 4
EARTH WORK
Item No.
Material
151
Earthwork in cutting or in embankment in ordinary soil
excavation to be in the form of regular pits not exceeding
1/2 meter (20") in depth and earth work in embankment
to be in 20 cm (8") layers including ramming dressing the
surface to required level and slopes and also including
1.5 meter (5") lifts and 30 meter (100 ft.) lead, the earth
from cutting to be used in making embankment or to be
deposited as soil bank with in 30 mtrs (100 ft) distance
as directed by the Engineer in Charge.
152
153
154
155
156
157
158
159
160
161
Unit
Rate (Rs.)
Per % cum
3600.00
Per % cum
3600.00
Per % cum
3000.00
Per % cum
3800.00
Per % cum
4500.00
Per % cum
7000.00
Per % cum
12000.00
Per % cum
4000.00
Per % cum
Deleted
Per % cum
Deleted
Per % cum
600.00
Per cum
33.00
Or
Hill side cutting in ordinary soil including removal and
disposal of surplus excavated material and debris upto a
distance of 30mtr from road side as directed by E.I.C
make the Roadway as per plan and L section and as per
P.W.D specification and also including cost of all
labour,T&P and machinery etc required for proper
completion of the work.
As in item (151) above but excavation in soil mixed with
moorum shingle etc. required the use of special T&P
such as pickaxes, sabbals etc.
162
deleted
163
Per cum
250.00
Hand packed stone filling (As directed by Engineer-inCharge.)including cost of material,royalty,T&P etc
complete.
Per cum
125.00
164
J.E. (Tech.)
8th Circle PWD New Tehri
Item No.
Material
165
Excavation in foundation in all types of soil including lift
upto 1.5 meter and lead upto 30 meters and including
filling watering and ramming of excavated earth into the
trenches or into the space between the building and the
sides of foundation trenches or into the plinth and
removal and disposal of surplus earth as directed by the
Engineer-in-charge upto a distance of 30 meters form
the foundation trenches.
(a) For building and bridge work
(b) For road work
165. (a) Same as in item No. 165 but excavation in soil mixed
with gravel and boulders.
Unit
Rate (Rs.)
Per cum
Per cum
50.00
40.00
Per cum
60.00
Per cum
Per cum
55.00
50.00
Per cum
45.00
Per cum
50% extra
New item.
1
Condition:
Item No 152 to 160 will be allowed only after 100% personal verification & classification & quantities
checked by Asistant Engineer,and 5% personal verification by the Executive Engineer and also after
recording a certificate to this effect.
J.E. (Tech.)
8th Circle PWD New Tehri
CHAPTER - 5
ROAD WORK
Item No.
491
492
493
494
494(B)
494
495
495(B)
496
496(B)
497
498(A)
498(B)
499
500
500(B)
501
501(B)
Unit
Rate (Rs.)
Per % cum
2500.00
Per % cum
3000.00
Per % cum
4500.00
Per Cum
Per Cum
Per Cum
77.00
145.00
60.00
Per Cum
Per Cum
80.00
155.00
Per Cum
Per Cum
74.00
140.00
Per K.M.
700.00
Per R.M.
22.00
Per Sqm
675.00
Per Cum
18.00
Per Sqm
Per Sqm
10.00
13.50
Per Sqm
Per Sqm
5.50
9.00
J.E. (Tech.)
8th Circle PWD New Tehri
Item No.
503
Deleted
504
Material
Unit
Rate (Rs.)
Per Sqm
11.00
505
506
Deleted
507
Per K.M.
1550.00
Joint filling in C.C. surface lengths (after raking out the joint
and removing the old tar or other materials) with suitable
materials as directed by the Engineer-In-Charge (labour rate
only)
Per K.M.
500.00
Per Cum
250.00
Per Cum
1000.00
Per Cum
850.00
Per Sqm
13.00
17.00
1035.00
508
509
510
510(A)
511
511(A)
512
513
513(A)
514
514(A)
J.E. (Tech.)
8th Circle PWD New Tehri
Per Cum
Per Sqm
Per Sqm
4.20
6.10
15.00
18.00
Item No.
Material
Unit
Rate (Rs.)
515
Per Sqm
Per Cum
325.00
Per Cum
Per Cum
220.00
320.00
Per Cum
220.00
Per Cum
300.00
Per Cum
220.00
Each
40.00
Per Cum
180.00
Per Cum
600.00
516
516(a)
517
517(a)
518
518(a)
519
520
521
Deleted
522
523
Deleted
524
525
Per Cum
125.00
Per Cum
deleted
526
Per R.M.
300.00
527
Per R.M.
250.00
Unit
Rate (Rs.)
Item No.
J.E. (Tech.)
8th Circle PWD New Tehri
Material
530
531
532
533
534
535
536
As
per
actual
measurements and
quantities
Per R.M.
Per R.M.
Each
Each
Each
1200.00
750.00
Per Km.
5500.00
Per Km
Per Km
Per Km
4800.00
3500.00
2000.00
Per Km
400.00
Per Km
Per Km
3000
Deleted
Per Km
3000.00
Per Km
1000.00
3
4
5
6
Per Km
14000.00
Per Km
Per Km
6000.00
13000.00
Per Km
1000.00
Total
38000.00
Part-B
Per Km
5000.00
2
3
Per Km
2000.00
Per Km
5000.00
Total
12000.00
Per Km
2000.00
J.E. (Tech.)
8th Circle PWD New Tehri
Bridge
New item Bridge 01:-Supply & fabrication of steel truss(girder)
Bridge/Suspension Bridge as per detailed drawing. Supply of all structural steel
confirming to I.S.226-1969 required for proper completion of bridge including ground
erection of the bridge and including one coat of approved quality anticorrosive red
oxide paint conforming I.S.5660 as per specification & drawing.including all T&P etc.
nuts and bolts,Washers and also including supply and fixing of shop rivets reffered as
per drawing. The rates shall include ground erection in the workshop and its
dismantling after inspection,approval and removing of defects,match marking of all
parts,numbering and proper stacking in the premises of workshop before cartage to
site of work.The work shall be executed in accordance with I.S. 1915-1961 and its
latest revision shall be applicable. The rates shall include cost of all material,its
wastage,cutting,bending if required,welding,making holes,shop riveting ,labor T&P etc.
and also including proper stacking after dismantling of ground erection. All required
equipment should be arranged by the contractor at his own cost, which shall be taken b
by the contractor after satisfactory execution of the job.Also including supply of all
material T&P etc .required for proper completion of work,as per direction of Engineerin-charge.
Sl.
SPAN
NET RATE
No.
COST OF STEEL
+ FABRICATION
(including Wastage)
Steel Truss(girder)Bridge
Upto 30 m
Rs. 55500.00 Per M.T.
Above 30 m and upto
Rs. 57000.00 Per M.T.
60m
Rs. 58500.00 Per M.T.
Above 60m
Upto 60 m
Suspension Bridge
Rs. 55500.00 Per M.T.
Above 60m
1
2
Sl.
SPAN
J.E. (Tech.)
8th Circle PWD New Tehri