Identifying Pitfalls in The Arc Flash Calculation Process
Identifying Pitfalls in The Arc Flash Calculation Process
com/arc-flash/identifying-pitfalls-arc-flash-calculation-process
Why arc flash hazard assessments and analysis results aren’t always foolproof?
An electrical arc flash can occur when someone is verifying the presence of
voltage, checking the balance of current, operating a switch, inspecting an
energized cable or bus connections during routine maintenance, or simply
standing in the vicinity of energized equipment. This is a reason to perform an
arc flash hazard assessment study — to discern the degree of arc flash hazard
present and the level of PPE required at a given location on the power
distribution system. In addition, this type of study helps determine the possible
means to reduce the energy through time and/or distance adjustments. Many
times, however, this requires you to run through a series of calculations using
available commercial engineering software or lengthy hand calculations.
However, mistakes can be made during the calculations process. That’s why it’s
critical for you to understand the limitations of these methodologies.
The basics
Arc flash studies require input from short circuit and coordination analysis to
calculate incident energy based upon bolted and arcing fault current levels,
arcing time duration, and distance to arc. Arcing faults are the result of current
passing through the air. At a particular point in the distribution system, this
current is always less than that possible for a bolted fault, which is a result of
the direct metallic connection between conductors. The incident energy created
during an arcing fault is calculated in the form of calories per square centimeter
(cal/cm2).
The objective of any arc flash assessment is to calculate the incident energy
and determine the arc flash boundary distance. The arc flash boundary is
defined as the approach limit, at a distance from exposed live parts, within
which a person could receive a second-degree burn if an electrical arc flash
were to occur. The reliability of overcurrent protective devices is critical to
escalation of an arc flash to higher levels than expected, so system
maintenance is very important.
Required data
An arc flash hazard assessment requires the following input data about the
distribution system:
• Single-line diagram of the power distribution system from the electric utility
source to the low-voltage panelboards and motors (50 hp and larger).
• Electric utility source data, indicating minimum and maximum available bolted
fault current, X/R ratio, and supply voltage.
• Feeder cable material (Cu/Al), sizes and lengths and raceway material
(magnetic / non-magnetic).
Example scenario
Let’s begin with a 500A, 5kV fuse, which is about 240% of primary FLA. There
are cables connecting the 480/277V wye transformer secondary with a solidly
grounded neutral to a main power circuit breaker in 480V switchgear. The
secondary FLA of the transformer is 1,804A. Again, according to the NEC, a
protective device could be sized up to 250% (in supervised locations), but a
125% limit (for unsupervised locations) is more common and useful for arc
flash considerations. So 1.25 × 1,804A = 2,255A. However, because there is
not a device of that rating, let’s begin with a 2,400A power circuit breaker. This
main breaker could be set with a long time pick-up of 0.9 or 2,160A to properly
protect the transformer and possibly the secondary conductors. One of the
feeders from this switchgear is an 800A power circuit breaker feeding an 800A
rated MCC. Finally, there is a 600A fused switch in the MCC serving a
downstream panel load.
Once the available fault level is obtained from the electric utility, you can use
the above data to evaluate the available fault levels at the switchgear and the
MCC. In addition, when the equipment manufacturer and types of breakers are
determined, a TCC can be prepared reflecting the operating conditions of this
system (Fig. 2). Then, with the push of a button, if using commercially
available software, the arc flash incident energy and arc flash boundary can be
determined. But do you really have the necessary information for safe operation
of the equipment at that point?
Other considerations
There are many locations within the power distribution system that are critical
to appropriately understanding the exposure to arc flash energies. First, a
device cannot protect itself. Thus, to evaluate the incident energy at any point,
you must look upstream from the point of the fault to the protective device
ahead of the point being evaluated. Second, to use the main to protect the bus
during an arc flash, it must be physically isolated from the bus and from the
downstream feeders.
In the past, it was useful to consider an infinite electric utility short circuit
current and then, from the transformer size and impedance, evaluate the
maximum available bolted fault current. This was — and still is — helpful for
ensuring the equipment has suitable short circuit withstand ratings. However,
with arcing current being a lower current than the bolted fault current, it is also
important to consider the actual or minimum available electric utility fault
capacity. Compare the secondary available bolted fault current of a 10,000MVA
source to a 90MVA source supplying a 480V, 1,500kVA transformer. Note that
instead of a 31kA bolted fault, you could be looking at 24kA (Fig. 4). If you
would plot a series of available source MVA versus transformer secondary
faults, you could arrive at results depicted in Fig. 5.
Fig. 5. Transformer 480V secondary fault vs. source MVA.
However, it is not the bolted fault but the arcing fault that is important. It is
well known that an arcing fault is lower in value than the available bolted fault
for any point in a circuit. Using IEEE Std 1584 Equation 1 for under 1,000V, you
can calculate that 480V equipment arcing faults are roughly between 40% and
60% of the available bolted fault current level. For quick calculations, a value of
50% can be used. For 208V equipment, arcing faults are roughly between 20%
and 35% of the available bolted fault. For quick estimated calculations, a value
of 25% can be used.
Let’s recap what we’ve discussed so far. The electric utility is asked to provide
an estimate of the fault current at the point in its system where the equipment
that is being evaluated is said to exist (the position of which is an estimate).
You use the manufacturer’s estimate of the transformer impedance, which
varies from no load to full load — and with temperature. The conductor size and
length are chosen, and, as a result, its impedance is estimated — again, as it
varies with temperature. Calculations provide an estimate of the bolted fault
current and subsequently estimate the arcing fault current. Manufacturers’
estimated TCCs depict how a properly maintained protective device is expected
to respond to the bolted and arcing fault current. In other words, our resulting
calculation is a reasonable approximation of what is expected to occur.
Expanding our facility distribution system to include bolted and arcing fault
levels, it should be realized that the fault current also has an impact on the
conductors’ ability to transmit that level of fault current. If a fault current of
24kA is available at the transformer secondary, then a conductor rated to
normally carry a full load current could experience a lower fault current at a
distance from the source to an estimated point by as much as 200 ft (Fig. 6).
With a 24kA available bolted fault, an 800A feeder circuit of 100 ft for the MCC
would only see 83% of that available fault, or 20kA; and the arcing fault would
be roughly 50%, or 10kA. The 85% point is 8.5kA. So what started as 24kA is
now seen as 8.5kA. This certainly has an impact on the setting of the circuit
protective device.
Fig. 6. Bolted fault vs. feeder length for 480V, 24,000A fault.
Mitigation
What can be adjusted to affect the arc flash incident energy in a system? The
fault level from the electric utility can’t be modified by the facility distribution
system. The transformer size and impedance can be adjusted, especially for
large units, but this may not allow for the appropriate total capacity of service
to the facility. The location of equipment could be adjusted, but other factors
generally have the principal impact on equipment location. The electrical
protective devices and their settings can be selected and have the greatest
effect on the available incident energy at points throughout the distribution
system.
Looking back at the initial system TCC (Fig. 2), can anything be adjusted to
reduce the arc flash incident energies in the system? The primary fuse could be
resized. This would still allow for transformer inrush and full load capability. In
general, medium-voltage fuses do not provide a real means to reduce incident
energy, especially on the low-voltage side of the transformer.
For the 1,500kVA transformer with a 90MVA source, there is 12.5kA bolted fault
current at 4,160V. The medium-voltage arcing fault is roughly 1% to 2% less
than the bolted fault per Equation 2 of IEEE Std 1584. Then, looking at 85%,
the 4,160V arcing fault level is approximately 10.6kA. A 500A fuse would
respond in about 0.02 sec, yielding an arc flash energy at the transformer
primary of less than 1cal/cm2. The secondary 24.3kA of bolted fault at 480V
would have about 12kA of arcing fault and 10.3kA of reduced arcing fault. The
medium-voltage fuses respond much too slowly, resulting in energy above 50
cal/cm2. However, looking at Fig. 7, the short-time pickup (STPU) of the
secondary main could be reduced from 5 to 3. This would reduce the reaction
time for the main breaker from 12 sec to 0.31 sec and thus, the arc flash
incident energy from 50 cal/cm2 (for 2 sec maximum) to 12 cal/cm2. The MCC
feeder STPU could be reduced from 9 to 5 to maintain coordination with the
main. This would overlap the 600A fuse, but if the fuse size could be reduced to
400A, coordination would be maintained.
Fig. 7. Revised TCC 1,500kVA unit substation.
During this design, you could use other protective devices, such as a 2,000A
secondary main fuse. When large low-voltage fuses are used, they respond in
about 1 sec to a fault at seven to eight times their FLA rating and in about 0.01
sec to about 15 times their FLA rating. Keeping in mind that the arcing fault
level is less than the bolted fault level (about 10kA for our example), a 2,000A
secondary Class L fuse would respond to the arcing fault in about 7 sec. In fact,
smaller fuses (even of the same current rating) of different types have differing
responses at various current levels.
It should be noted, with experience, that 480V equipment reaction times over
approximately 0.5 sec for bolted fault values above 42kA — and reaction times
of 1 sec for bolted fault values above 22kA — result in PPE Class 4 protective
clothing level or higher.
• Add an arc mitigation relay that senses a flash of light from an arcing fault
and the rate of rise of the current from the fault.
• Use zone selective interlocking to recognize and localize a fault more quickly.
In many situations, the above may require an alternate scenario to the original
design.
• Install arc resistant switchgear (Note: This equipment is only arc resistant
when the doors are closed).
• Insulate the bus, which reduces the probability for single-phase and 3-phase
arcs.
Conclusion
Although arc flash is a serious workplace hazard, there are means to evaluate
its intensity and to mitigate the affect on electrical workers. IEEE Std 1584 and
NFPA-70E provide mechanisms to calculate its intensity and to recommend
appropriate PPE. Engineers should also be encouraged to determine other
effective mitigation techniques such as providing barriers, increasing working
distance from an arc, and reducing the time an arc would exist.