The Norned HVDC Cable Link
The Norned HVDC Cable Link
ABSTRACT
The NorNed HVDC Cable Link is under
construction. The transmission connects the hydropower based Norwegian grid with fossil fuelled ac
system in The Netherlands. The 700 MW, 580 km
long link will be the longest cable transmission in
the world and will be in commercial operation
towards the end of 2007.
1.
INTRODUCTION
+450 kV
DC-cable
TECHNOLOGY
2.1
Transmission configuration
The main circuit configuration consists of a 12pulse converter 450 kV with the mid point
earthed and two cables. The arrangement is a very
attractive solution for a single converter block
scheme for extremely long cable transmissions. The
transmission voltage is effectively 900 kV giving
fairly low cable current and low losses. The total
losses are 3.7 % at 600 MW load. The DC link is
designed to operate continuously at 700 MW when
all converter cooling equipment is in operation.
The converter midpoint earth in Eemshaven
constitutes the zero DC Voltage potential reference
for the DC side. This is accomplished by a midpoint
reactor which also blocks 6-pulse harmonic currents
Eemshaven
-450 kV
Feda
Converter stations
Eemshaven
Two 110 Mvar filter banks each consisting
of one double-tuned 11th/13th filter branch
of 50 Mvar and one HP24 branch of 60
Mvar
Two shunt capacitor banks each of 106
Mvar.
2.3
Cable system
6
7
General
8
9
10
11
12
No.
Constituents
1
2
3
4
5
6
7
8
9
10
11
Nominal
diameter
(mm)
Conductor, copper
Conductor screen
Insulation
Insulation screen
Fabrick tape
Lead sheath, F3
Polyethylene sheath, MDPE
Bedding tape
Reinforcement
Bedding tape
Armour, galvanized steel wires,
two layers
Outer serving/PP yarn
12
Nominal
thickness
(mm)
Water depth
107
Burial depth
Thermal resistivity of the sea bottom
Annual variation of the sea bottom
temperature and sea water
3.
AC SYSTEM CHARACTERISTICS
3.1
Norway
The Netherlands
EC-6
HVDC
TR-1
Meeden-1
Meeden-2
TR-2
TWh/year
Actual production
Demand forecast
10% wet year inflow
140
120
100
90% dry year inflow
80
Total demand
Average hydro
power production
60
40
20
0
Year
1975 1980 1985 1990 1995 2000 2005 2010 2015 2020
5.
TRADING MECHANISM
Pris (kr/MWh)
400
Handelsinntekt
350
Vann
Termisk
300
Eksporter
Vannkraft
250
200
150
100
50
24
22
20
18
16
14
12
10
0
0
4.
UTILIZATION OF THE LINK
The development of the HVDC connection between
Norway and The Netherlands is strongly motivated
by differences in the power markets in both
countries. This difference imposes that the actual
power transmission in the NorNed link may change
several times a day.
Time
6.
CONCLUSIONS