The document provides a checklist of 37 items to ensure equipment layout drawings are complete and contain all necessary information. The checklist includes verifying the title block contains things like the drawing number, project name, plan/section identification, and revision number. It also includes checking that key equipment details are shown like tag numbers, elevations, structural components, accessways, and requirements for cranes, ladders, platforms and ducting. The goal is to make sure the piping department provides other engineering departments all needed information in the equipment layout to support their design and construction work.
The document provides a checklist of 37 items to ensure equipment layout drawings are complete and contain all necessary information. The checklist includes verifying the title block contains things like the drawing number, project name, plan/section identification, and revision number. It also includes checking that key equipment details are shown like tag numbers, elevations, structural components, accessways, and requirements for cranes, ladders, platforms and ducting. The goal is to make sure the piping department provides other engineering departments all needed information in the equipment layout to support their design and construction work.
The document provides a checklist of 37 items to ensure equipment layout drawings are complete and contain all necessary information. The checklist includes verifying the title block contains things like the drawing number, project name, plan/section identification, and revision number. It also includes checking that key equipment details are shown like tag numbers, elevations, structural components, accessways, and requirements for cranes, ladders, platforms and ducting. The goal is to make sure the piping department provides other engineering departments all needed information in the equipment layout to support their design and construction work.
The document provides a checklist of 37 items to ensure equipment layout drawings are complete and contain all necessary information. The checklist includes verifying the title block contains things like the drawing number, project name, plan/section identification, and revision number. It also includes checking that key equipment details are shown like tag numbers, elevations, structural components, accessways, and requirements for cranes, ladders, platforms and ducting. The goal is to make sure the piping department provides other engineering departments all needed information in the equipment layout to support their design and construction work.
Equipment layout is a critical input from piping department to all other departments such as Civil Engineering, Structural Engineering, Electrical Engineering, Process Engineering, Construction etc. It need to be checked properly with utmost care to make sure that no information is missing. A typical checklist to check equipment layout is as follows : Sr. Description Done 1 Title Block : Drawing Number properly specified. 2 Title Block : Area code specified. 3 Title Block : Project Name and Number Specified. 4 Title Block : Plan or Section Specified 5 Title Block : For Plans, Elevation level specified. 6 Title Block : For Sections, Section Grid Numbers Specified. 7 Title Block : Revision Number Specified. Sidebar : List of Equipments with Tag numbers and Equipemnt Description included in 8 Side bar. 9 Sidebar : Top of foundation elevation specified for Pumps. 10 Sidebar : Bottmon Tanline elevation specified for Towers and Vertical Vessels. 11 Sidebar : Centreline elevations specified for Horizontal Vessels, Exchangers 12 Sidebar : List of all holds included 13 Sidebar : List of reference documents included 14 Sidebar : Key plan included with patterned area indicating location of this drawing. 15 Drawing : North direction specified along with prevailing wind direction. 16 Drawing : All applicable structural grids marked. Drawing : All applicable structural components shown including small platforms, 17 ladders etc. 18 Drawing : TOS elevation of all platforms specified. 19 Drawing : All equipments located in both EW and NS directions. 20 Drawing : All structural cutouts shown. 21 Drawing : Requirement for curb wall for chemical handling pumps, tanks in shown. 22 Drawing : Foundation elevation of pumps shown in elevation drawing. 23 Drawing : BTL Elevation of vertical vessels shown in elevation drawing. Drawing : Centerline elevation of horizontal vessels and exchangers shown in elevation 24 drawings. 25 Drawing : Operator and maintenance accessways marked. 26 Drawing : Davit requirements and drop zones marked. 27 Drawing : Floor cutouts to remove agitator assemblies if any marked. 28 Drawing : Monorails, Overhead travelling crane requirements shown. 29 Drawing : Staircase requirements shown. 30 Drawing : Location of Manholes shown (Orientation,Elevation). 31 Drawing : Equipment platforms and ladders shown. 32 Drawing : Ducting work if any is shown.
33 Drawing : Tube bundle removal area shown for Heat exchangers.
34 Drawing : Manhole cover swing area shown. 35 Drawing : Maintenance area for plate heat exchanger, spiral heat exchanger is shown. Drawing : Locaton of fixed saddle for horizontal shell and tube heat exachangers is 36 shown. 37 Drawing : Pumps located in plan based on centre of their discharge.