NRL2TRK2102
NRL2TRK2102
NRL2TRK2102
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
User information
This Network Rail standard contains colour-coding according to the following RedAmber
Green classification.
Red requirements no variations permitted
Where a requirement calls for the agreement of the RAM this shall be documented either as
a specification requirement in the Project Requirement Specification (or equivalent) and/or
recorded as a deviation to design standards in the Approval in Principle submission and
subsequently authorised by the RAM[Track].
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Page 2 of 105
Licensee=Capita Symonds to Capita property & infrastructur/5965831001
Not for Resale, 05/18/2016 04:44:17 MDT
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Issue record
Date
1
2
3
Feb 1996
Apr 1997
Aug 1998
Jun 2000
Feb 2002
June 2010
Dec 2015
Comments
New specification.
Various clarifications and amplifications
Various amendments including steel sleepers; ballast
shoulder widths; temporary rail joints; gauge widening on
curves.
Revised to allow for speeds above 125 mph and CEN 60
rail.
Inclusion of RT60 S&C; requirements for increase of
speed etc. on existing track; ballast gluing, rail
lubrication, securing of material for lineside safety;
transfer of some text from RT/CE/S/011
Reformat to Network Rail document, change of title to
Design and construction of track and renumbered to
NR/L2/TRK/2102. Job titles updated to reflect new
organisational structure. Inclusion and expansion of
requirements previously published in NR/SP/TRK/101
and GC/RT5021.
Scope of document limited to 140mph. Updated with the
addition of new requirements on; materials, forces,
requirements for CWR (from NR/L2/TRK/3011),
requirements for geometry design (from
NR/L2/TRK/2049), formation and track stiffness, guard
rails, structures, gradients, design and risk assessment
of S&C layouts, minimum radius of switches, rail depths
through level crossings, use of transition rails, ballast
compaction and shoulder removal, concrete bearers for
cable management, CWR on tight radius curved track,
maximum lengths of rail in jointed track, calculation of
joint closing temperatures, use of semi-fabricated
crossings, types of S&C to be used above 125 mph,
installation of bi-axle grids on S&C renewals, use of anticreep devices in S&C, use of bearer ties, maximum
lengths of rails in jointed S&C, conversion of jointed track
to CWR (from NR/L2/TRK/3011), types of S&C suitable
for speeds in excess of 125 mph, conversion of freight
lines to passenger use, decommissioning of redundant
assets.
Compliance
This Network Rail standard is mandatory and shall be complied with by Network Rail
and its contractors if applicable from 01 May 2016 or sooner when briefed.
When this standard is implemented, it is permissible for all projects that have
formally completed GRIP Stage 3 (Option Selection) to continue to comply with the
issue of any relevant Network Rail standards current when GRIP Stage 3 was
Page 3 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Issue
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
completed and not to comply with requirements contained herein, unless stipulated
otherwise in the scope of this standard.
Reference documentation
BS EN 13481, Railway applications Track Performance requirements for
fastening systems
NR/L2/TRK/001, Inspection and Maintenance of Permanent Way
NR/L2/TRK/0032, Joining Of Rails By Aluminothermic Welding
NR/L2/TRK/0132, Maintenance Arc Welding of Rails, Switches and Crossings
NR/L2/TRK/2049, Track Design Handbook
NR/L2/TRK/2500, Engineering Assurance Arrangements for Track Engineering
Projects
NR/L3/TRK/3011, Continuous Welded Rail (CWR) Track
NR/L2/TRK/3038, Longitudinal Timbers Design - Installation and Maintenance
NR/L2/TRK/3100. Topographic, engineering, land and measured building surveying
Strategy and general
NR/L2/TRK/3201, Management of Tight Clearances and Track Position
NR/L2/TRK/4040, Level Crossing Surface Systems
NR/L2/TRK/4100, Serviceable Concrete Sleepers for use in running lines and
sidings
NR/L2/TRK/4239, Track Bed Investigation, Design & Renewal
NR/L2/TRK/8100, Track Ballast and Stoneblower Aggregate
RT/CE/S/050, Process for Cold-Expanding New Fishbolt Holes by the Split Sleeve
Method
RT/CE/S/051, Process for Cold-Expanding Existing Fishbolt Holes by the Split
Sleeve Method
NR/L3/EBM/089, Asset Management Plan
NR/L3/CIV/005, Railway System Drainage Manual
NR/L3/TRK/4004, Switch & Crossing Assemblies
NR/PS/TRK/029, Wood Sleepers and Bearers and Longitudinal Timbers
NR/SP/CIV/044, Design & Construction of Undertrack Crossings (RT/CE/S/044)
NR/SP/OHS/069, Lineside Facilities for Personnel Safety (RT/CE/S/069)
NR/SP/SIG/19812, Cross Track Cable Management
NR/SP/TRK/9003, Installation and Maintenance of Longitudinal Timbers
RE/PW/572, RE/PW/590, RE/PW/759, RE/PW/2020. Drawings.
RE/PW/1600 and 2000 series drawings for NR56 and NR60 S&C respectively
Page 4 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Page 5 of 105
Licensee=Capita Symonds to Capita property & infrastructur/5965831001
Not for Resale, 05/18/2016 04:44:17 MDT
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Contents
1 Purpose ................................................................................................................. 11
2 Scope .................................................................................................................... 11
3 Definitions ............................................................................................................. 12
4 Track Design Policy Business Outputs, Systems & Materials ............................ 25
4.1 Business Outputs ............................................................................................... 25
4.2 Design of New Track Systems ........................................................................... 26
4.3 Materials ............................................................................................................. 27
5 Track System Specification ................................................................................... 28
5.1 General .............................................................................................................. 28
5.2 Track System Specification ................................................................................ 28
5.3 Track Gauge and Flangeways ........................................................................... 28
5.4 Rail Inclination .................................................................................................... 28
5.5 Forces ................................................................................................................ 29
5.6 Rail ..................................................................................................................... 29
5.7 Rail Fastenings................................................................................................... 30
5.8 Sleepers and Bearers......................................................................................... 30
5.9 Switches and crossings ...................................................................................... 31
5.10 Design of Continuous Welded Rail Track Systems .......................................... 33
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Page 7 of 105
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Page 8 of 105
Licensee=Capita Symonds to Capita property & infrastructur/5965831001
Not for Resale, 05/18/2016 04:44:17 MDT
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Page 10 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
1 Purpose
This standard is intended to control the risk of incorrect materials and components
being specified and to control the required quality of installation of track. It specifies
the design principles and minimum standards for the construction of new or relayed
track, including the materials to be used. It also specifies acceptance criteria for new
or relayed track in terms of workmanship and the track geometry requirements for
both newly installed and existing track.
2 Scope
This Network Rail standard specifies the requirements for the design and
construction of track with line speeds up to 140mph. This includes:
a. the construction of new sections of track, and routes;
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Page 11 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
3 Definitions
For the purpose of this standard, the following terms and definitions apply.
absolute track geometry
See managed track position
adjustment switch
scarf joint installed at the junction of continuous welded rail and jointed track to
accommodate the expansion and dissipate the thermal forces from the continuous
welded rail track.
NOTE Adjustment switches may also be used to permit some types of bridges to expand and
contract without impacting upon the track system, when adjustment switches are used in this
application they are referred to as expansion joints.
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
cant gradient
indicates the amount by which the designed cant (superelevation or crosslevel) is
increased in a given length of track, normally expressed as a rate e.g. 1 in 1200.
cascaded rail
rail that has previously been installed in track and is picked up as CWR and moved
directly to a new site.
Cast centre block
a crossing, the nose(s) and throat (knuckle) of which are made as one casting. The
leg end extensions are attached by flash butt welding and the non-load carrying wing
rails by multiple groove locking (MGL) pins, tension-controlled bolts or similar
devices.
cast crossings
cast crossings are manufactured from cast steel either as a complete unit (i.e.
monobloc) or as a cast centre block crossing with welded-on extension leg ends
NOTE: Some cast centre block crossings will have bolted wing rail extensions.
cast vee
crossing in which a cast nose-piece is flash butt welded to pearlitic rail legs and to
which the wing rails are attached by MGL pins, tension-controlled bolts or similar
devices.
catch points
trailing switches provided to derail vehicles running in the wrong direction.
NOTE: See also trap points.
CEN60 S&C
S&C using CEN60 rail, examples being RT60 & NR60.
check rail
rail or special section provided alongside a running rail at a specified dimension
inside gauge to provide a flangeway, to give guidance to wheelsets by restricting
lateral movement of the wheels.
circular curve
a curve of constant radius.
co-ordinate geometry design
Page 13 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
check gauge
distance between the running edge of a running rail and the bearing face of the
opposite check rail, measured at right angles to the rails in a plane 14 mm below
their top surface.
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
common crossing
cast or fabricated portion of the track layout that enables the rails of the two tracks to
cross each other, while still providing support and guidance for smooth passage of
the vehicle's wheels.
there are of four types:
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
a)
b)
c)
d)
compound curve
a curve formed of two similar flexure circular curves of differing radii, which should
normally be connected by a transition curve.
configuration
arrangement of rails, switches, crossings, baseplates, bearers and sleepers into a
standard design.
continuous welded rail (CWR)
rails installed in the track that have been welded together to form a single rail
greater than a nominal 36 m in length;
track constructed with continuous welded rail.
derailment containment kerb
arrangement to prevent a derailed rail vehicle or train coming in to contact with parts
of a structure that would be liable to severe damage if so struck or to prevent
vehicles falling from a major bridge or viaduct.
design speed
the speed in miles per hour for which a stretch of track or turnout in S&C is to be or
has been designed. Speeds will normally be governed by curvature and its
associated cant. Speeds can also be affected by clearances, signal sighting or other
engineering requirements.
Page 14 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
expansion joint
non-insulated fishplated which is designed to accommodate longitudinal
thermal expansion of the rails, also known as ordinary fishplated joint; or
scarf joint used to permit structures to expand and contract without impacting
upon the track system, see also adjustment switches.
Page 15 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
formation
material on which the ballast is placed, consisting of the subgrade plus blanket and
other protective layers (if present).
frangible platform
a platform that is designed to collapse in a controlled manner as a result of impact ,
usually from sliding or friction buffer stops.
free wheel passage (at check or wing entry)
dimension between the working face of the crossing check rail or wing rail and the
gauge face of the running rail opposite across the gauge measured at the entry to
check rail or wing rail respectively.
free wheel passage (at crossing nose)
dimension between the working face of the crossing wing rail and check rail opposite
across the gauge.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Page 16 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
handpoints
See unworked points.
high cant deficiency curves
curves where specific train fleets have permission to run at cant deficiencies in
excess of 150 mm.
jointed track
method of track construction where rails are joined together by ordinary fishplates,
with an expansion gap between rail ends and not exceeding 37m long.
kicking strap
a device attached to a switch rail near to the toe which passes under the stock rail of
a set of switches or under the wing rail of switch diamonds to prevent upward
movement of the switch rail.
lateral resistance plate
generic term applied to devices that are fitted to sleepers or bearers to enhance
lateral resistance to thermal and traffic forces.
length (of a track panel)
length of a track panel normally taken as 60ft or 18288 mm.
NOTE: Used in the context of the number of sleepers per length, 28/L being 28 sleepers per 60ft of
track.
level crossing
intersection at the same level of a road, footpath or bridleway and one or more
railway tracks.
Page 17 of 105
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
longitudinal timber
timber parallel to and supporting a running rail.
machined nose block
crossing where the vee is mechanically manufactured from a low alloy wrought steel
block, which is machined and subsequently heat treated. Pearlitic rail leg ends are
flash butt welded to the vee. Distance blocks are also welded directly onto the vee
prior to attaching wing rails by means of MGL pins, tension-controlled bolts or similar
devices.
managed (or fixed) track position
generic term for all systems (including the system of absolute track geometry
installed on West Coast Main Line) for the upkeep of track geometry and alignment
by reference to datum points fixed in space.
NOTE: It is used to monitor and control the position of the track, rather than the use of relative
geometry.
new construction
construction of a new railway or the construction of track on previously abandoned
formation.
non-ballasted track
track that is not supported on ballast, for example; concrete slab track, track on
longitudinal timbers and directly fastened track on bridges.
NR56 S&C
Network Rail design of S&C using CEN54 shallow depth rail & CEN56 rail sections,
NR56 is an updated version of BS113A Vertical S&C.
NOTE: The design is documented on the RE/PW/1600 series drawings
NR60 S&C
Network Rail design of S&C using CEN60 rail sections.
NOTE: It is based around the family of CEN60 rail sections, the design is documented on the
RE/PW/2000 series drawings.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
obtuse crossing
assembly to permit the passage of wheel flanges where two rails intersect at an
obtuse angle.
ordinary or expansion fishplates
non-insulated connection of two rails by means of fishplates designed so that when
assembled as a joint the rails are free to expand and contract within limits.
Page 18 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
P2 forces
P2 is a lower frequency peak force caused by the track being pushed down by the
passage of a vehicle generally below 100Hz.
parallel tamping
use of two or more specialist S&C tamping machines, working together to achieve
the simultaneous lining, lifting and packing of adjacent tracks.
part bearer
the portion (A, B or C) of a bearer that has been split into sections and joined
together with bearer ties.
permissible speed
the maximum speed over a section of line that applies to trains not travelling at
enhanced permissible speeds (i.e. not tilting trains).
plain line
track not incorporating switches and crossings.
NOTE The term plain line therefore excludes the through route of S&C.
Page 19 of 105
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
running line
line shown as a running line in Table A of the Sectional Appendix.
self-tensioning fastenings
fastening system that achieves the required tension through insertion without the
need for any post-tensioning through tightening of screws or nuts, etc.
semi fabricated crossing
semi fabricated crossings made by either:
a) machining and welding rolled rails to produce a crossing vee; or
b) using a cast vee;
which are then fastened to wing rails manufactured from rolled rail using bolts or
multi-groove locking pins.
serviceable rail
rail that has previously been installed in track but has been recovered and remanufactured, i.e. taken to a depot, examined, defects removed, and flash butt
welded back together.
slab track
track without ballast supported by continuous reinforced concrete slab.
sleeper
transverse beam that provides vertical and lateral support to plain line running rails,
rail fastenings and where appropriate check rails, guard rails, conductor rails and
ancillary operating equipment.
Page 20 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Sectional Appendix
document that contains details of all permissible and enhanced permissible speeds
for a particular route.
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
soleplate
a metal plate fitted at the toes of switches to fix the track gauge and, on power
operated points to control the position of the point operating mechanism relative to
the switch and stock rails.
standard deviation
measure that describes how a set of values are dispersed around the mean value.
NOTE: It is applied to the measurement of track geometry quality, the range of variation in top
(vertical alignment) and line (lateral alignment) over a fixed length, normally an eighth-mile, are set out
as standard deviations. These are then used to monitor the achievement of targets, by speed bands
or ranges.
Page 21 of 105
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`--
Page 22 of 105
Licensee=Capita Symonds to Capita property & infrastructur/5965831001
Not for Resale, 05/18/2016 04:44:17 MDT
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
trackbed
general term referring to the ballast, blanket and subgrade.
trackbed layers
general term referring to all layers placed between the subgrade and the underside
of sleepers or bearers.
train operated points
points that are designed for use in running lines with facing movements in the normal
position only.
NOTE: They are operated by the passage of trains in the trailing reverse direction. They are restored
to the normal position by the point operating mechanism after the passage of each train. Hydropneumatic self restored points are a type of train operated points.
transition beam
a connecting unit installed between ballasted track and track fastened directly to slab
track or to a bridge deck to provide a gradual change from the stiffness of one form
of construction to that of the other.
transition curve
curve of constantly varying curvature. It is normally provided between two lateral
circular curves of differing radii, or between a lateral circular curve and a straight. If
the variation is linear, the transition is in the form of a clothoid, often approximated by
a cubic parabola. Non-linear forms such as sine and cosine curves are also
available.
trap points
facing switches provided at an exit from a siding or converging/diverging line to derail
vehicles making an unauthorised movement, so protecting the adjacent line.
twist (design)
an intentional discontinuity in rail inclination between vertical and inclined track (twist
rail) or a cross level variation such as a cant transition curve above normal limits.
twist (fault)
a difference in crosslevel over a short distance (usually measured over 3m) that is
greater than a predetermined amount (usually 15mm).
Normally expressed either as an average gradient over 3m or as a dimension in
millimetres by which the crosslevel varies over 3m.
unworked points
points not controlled by the signalling system, other than train operated points.
NOTE: Hand points, runaway catch points and spring operated points are examples of unworked
points.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Page 23 of 105
Licensee=Capita Symonds to Capita property & infrastructur/5965831001
Not for Resale, 05/18/2016 04:44:17 MDT
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
vertical curve
curve joining two track gradients in their vertical alignment.
vertical S&C (CEN56)
design of S&C developed by British Rail and introduced in the mid-1960s to replace
earlier bullhead and flatbottom designs.
Current designs of CEN56 Vertical S&C are known as NR56.
NOTE: It is based around the BS113A rail section (now CEN56) and derives its name from all rails
being without any inclination (i.e. vertical).
virtual transition
the name given to the transition effect formed by the bogie centres of a vehicle
when traversing between two elements not joined by a transition. Normally taken as
being 12.2 m long, the bogie centres of a Mk 1 coach.
Welded cast monobloc
a crossing, all of the components of which (vees, wing rails, legs etc.), are cast as
one piece. The structure is made weldable into CWR by the incorporation of flash
butt welded leg end extensions using stainless steel inserts.
within S&C
S&C and closure panels with S&C bearers up to 18.288m beyond the switch fronts
and 36.566m beyond the last long bearer.
Page 24 of 105
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
To achieve the business outputs, new track systems, components, and track layouts shall be
developed taking account the interfaces with other railway infrastructure and systems and
Health and Safety considerations.
The following principles should be taken into account during the design
development:
a) be compliant with relevant statutory, legislative, and company standards
and other requirements;
b) be cost-efficient at construction and installation whilst considering the future
ease of maintenance, inspection, operation and upkeep and repair (in
accordance with the company ergonomics policy and standards). An optimal
solution should be targeted at achieving the lowest whole life cost within the
railway system whilst taking account of railway access constraints and costs;
c) have the designed capability and functionality informed by Asset and Route
policies;
d) have opportunities for change (enhanced or reduced capability or
functionality), and interdependencies with other asset types identified and
considered;
e) be capable of delivering improved reliability and minimising loss of
functionality, performance or capability;
f) minimise the need for human examination and intervention, and separate
these activities from train movements and live electrical equipment;
g) exploit, wherever practicable, standard or modular designs, products, and
layout configurations;
h) minimise the identification and application of new products and techniques
to avoid unnecessary diversity and complexities of training and competence
for constructors, operators and maintainers. Alternative products are only to
be used where there are business benefits that outweigh the risks and costs
of diversification;
i) have material specified from sustainable sources in accordance with the
company Corporate Responsibility Policy;
j) where practicable and where required by the route policy, be designed to be
installed in possessions of 8 hours duration;
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Page 25 of 105
Licensee=Capita Symonds to Capita property & infrastructur/5965831001
Not for Resale, 05/18/2016 04:44:17 MDT
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Risks to track workers are greatest when they are on or close to the track; therefore
the initiatives to reduce time on track, or at least when it is safer, will also reduce the
overall worker safety risk.
When reviewing systems for acceptance if the designed service life, inspection or
maintenance intervention frequency cannot be achieved the implications should be
recorded and the impact assessed.
4.2.2 Service lives
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
For product and systems approval, new designs of track and track components
should be developed with the aim of achieving the following service lives.
A design life for Sleepers, bearers, baseplates and rails in normal service conditions
of:
CEN60 track systems: the lesser of 1200 EMGT or 60 years for plain line and
1000 EMGT or 60 years for S&C;
Page 26 of 105
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
CEN56 track systems: the lesser of 1000 EMGT or 60 years for plain line and
800 EMGT or 60 years for S&C.
Sub-elements, e.g. ballast, rail pads, rail insulators, and rail fastenings, rail
lubricators, switches and crossings, switch rollers, and insulated rail joints may have
a design life of half of the sleepers, bearers and rails.
Formation treatment should have a design life of 60 years.
4.2.3 Inspection and maintenance intervention
A track system comprising of conventional CEN60 ballasted track should be
designed to be compatible with an inspection and maintenance regime as follows:
a) a four-weekly geometry recording;
b) a thirteen-weekly visual track inspection cycle; and
c) a two yearly possession of the line for component and mechanised
maintenance increasing to annual for the last 25% of the service life of the
system.
Switch and crossing systems may receive additional visual inspections, typically
four-weekly.
CEN56 ballasted track systems installed in lower category routes should be capable
of similar performance but with less frequent geometry recording, typically eightweekly, rising to six-monthly on Category 4, 5 and 6 track.
4.3 Materials
All materials and components used in the design of new track systems shall have
their performance assessed against an operating temperature range of -27 C to
+60 C.
Failure to achieve the required performance levels at the extremes of the
temperature range will not necessarily prevent acceptance. The impact on
performance should be recorded, its criticality assessed, and the need for additional
mitigation determined.
Components used in the track system shall be marked such that the identity of the
component, manufacturer and year of manufacture can be determined.
Identifying marks should be applied in a manner that will not damage the item or
impede its operation. They should be large enough and formed with sufficient clarity
to be readable over the life of the product. They should be positioned (as far as is
practicable) to be readable after installation.
Additional information such as month of manufacture, batch number or individual
serial number may be necessary depending on the criticality of the component.
Page 27 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Page 28 of 105
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Where rails in S&C are vertical, the rails in short lengths of adjacent plain line may
also be vertical.
Twist rails or twist transition baseplates shall be used to accommodate the change in
verticality from inclined track to vertical track.
5.5 Forces
The track system shall be designed to have performance characteristics capable of
sustaining the following forces:
a. a maximum static axle load of 250 kN (25.5 tonnes);
b. a vertical dynamic force, generated by the static wheel load and the low
frequency dynamic forces P2, of 350 kN per wheel and an occasional isolated
vertical load of 500 kN per wheel;
c. a lateral force generated by a train of 100 kN over a length of 2 m;
d. a lateral force on check rails of 135 kN over a length of 2 m and 50 kN at any one
mounting position;
e. a lateral force on guard rails of 100 kN over a length of 2 m;
f. a longitudinal force of 1200 kN per rail to allow for train acceleration and braking;
and
g. be capable of resisting thermal forces which may be expected to occur over a rail
temperature range of -14C to +53C, without distortion (equal to a tensile force
of 700 kN and a compressive force of 620 kN.
5.6 Rail
Rails shall be designed to provide support taking account of speed, axle load and
tonnage.
The rail section including the head profile shall have compatibility with sections
already existing in Network Rail's infrastructure and wheelset profiles in use.
The metallurgy and manufacturing process for rail shall be subject to acceptance by
Network Rail in order that:
a) the rails are capable of being butt welded together (using a Network Rail approved
process);
b) minimum actions (to be taken upon discovery of defects) can be defined; and
c) withdrawal criteria (for when rails reach their wear limits) can be defined.
NOTE: See RT/CE/S/002 and RT/CE/S/061 for the specification of rail.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Page 29 of 105
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Sleepers and bearers shall be designed with a soffit area, at the specified spacing, to
distribute loads to the ballast without overstressing the ballast, formation or
subgrade.
Sleepers and bearers shall have an end area to provide adequate lateral restraint to
the track.
Rail and baseplate pads in S&C should, as far as possible, replicate the stiffness of
plain line.
NOTE: See RT/CE/S/021, NR/PS/TRK/029 and RT/CE/S/030 for the specification of steel,
timber and concrete sleepers and bearers.
Page 30 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
S&C
Minimum opening at the toes of switches
100
1375
1391
1394
1350
1353
1360
38
Nominal flangeway width through check rails and wing rails (excluding
the knuckle area of obtuse crossings)
41
48
55
51
As specified in GM/RT2466
38
120
105
85
85
1375
NOTE 1: Where switch diamonds are operated by a rail clamp point lock mechanism (clamp lock), it is
permitted to reduce the opening at the toe to a minimum of 85 mm
NOTE 2: Gauge is measured 14 mm below the running surface.
NOTE 3: Manufacturing tolerances are given in NR/L3/TRK/4004, installation tolerances in Appendix
A.
NOTE 4: Cant deficiency at switch toes is measured using a 12.2m chord centred on the switch toe.
The maximum construction depth (bearers, soleplates, baseplates, pads and rail) for
new designs of S&C shall be 405mm.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Page 31 of 105
Licensee=Capita Symonds to Capita property & infrastructur/5965831001
Not for Resale, 05/18/2016 04:44:17 MDT
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Where the point operating mechanism is positioned on the bearer ends the soleplate
(or steel bearer) shall extend to fix the relative position of the drive and detection
equipment relative to the switch and stock rails.
Stretcher bars and soleplates shall be insulated to meet signalling requirements.
5.9.7 Point operating system
In running lines, the switch rails of turnouts, switch diamonds and the noses of swing
nose crossings shall be equipped with means of detecting that the movable rails are
in their correct position and are locked.
Provision for temporarily securing both the open and closed switch out of use shall
be provided.
5.10 Design of continuous welded rail track systems
5.10.1 Design of CWR - General
Continuous Welded Rail (CWR) shall be stressed to a target Stress Free
Temperature (SFT) of 27 C.
a) the minimum SFT shall be 21 C;
b) the target SFT, achieved by tensor or thermal stressing, shall be 27 C;
c) the target SFT achieved by natural stressing shall be between 24 and 30 C
when clipped down.
CWR on Crimp ended steel sleepers shall have a minimum SFT of 26 C, be
stressed to a target SFT of 32 C and natural stressing clipped down between 29
and 35 C.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Page 33 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Units installed with tight-joint fishplates may be subject to limited expansion and
contraction. They should be assumed to experience and withstand the same thermal
forces as units that are welded in.
S&C shall not be present within the stress transition length at the end of a section of
CWR. S&C not isolated from CWR by adjustment switches shall be fully stressed.
Any stress transition length shall commence clear of the S&C.
S&C units not approved for use in CWR, shall be isolated from adjacent CWR by
adjustment switches positioned not more than 40m from the S&C (switch front or last
long bearer).
The distance from the S&C should be taken as the distance from the switch fronts or
the weld / joint at the back of the crossing to the nearest machined section of the
adjustment switch
5.10.5 Switch designs suitable for use in CWR
CWR-compatible Switch designs are of two types with:
1. stress transfer blocks and bolts connecting the switch to the stock rail. Eight
25.4mm (1) diameter High Tensile Steel (HTS) bolts, tightened to a torque of
880 Nm allow transfer of 70-tonne thermal force; and
NOTE: Only those heel blocks with two bolts, or two pairs of bolts, are deemed to be stress transfer
blocks.
2. creep monitors. Thermal forces in the stock rails are accommodated as in plain
rail, and those in the closure rails are deemed to dissipate in the same manner as
at the free end of a length of CWR. Longitudinal thermal movement occurs at the
heel of the switch rail; this is indicated by a ball-and-claw creep monitor device,
which is not intended to transfer more than 20% of the maximum thermal force.
The following designs of switch are suitable for use in CWR:
a)
b)
c)
-
Page 34 of 105
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Page 35 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
5.10.11 Short lengths (less than 180m) of plain line between items of S&C
Plain line between S&C if welded or fitted with tight-joint or insulated fishplates shall
be stressed.
S&C suitable for use with CWR can be used as part of an anchor length (but not
within a stress transition length) for stressing the length of plain line. If the
recommended anchor lengths are not available the length of track shall be stressed
naturally.
6 Design and construction of the track system
NOTE: Compliance to clause 6 onwards will enable the construction of a compliant asset.
Page 36 of 105
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
A new drainage system shall be installed where the existing drainage arrangements
are inadequate in any new or renewed track.
NOTE 2: See NR/L3/CIV/005 for drainage policy, design and practice.
6.3 Ballast
6.3.1 General
Sufficient depth and width of ballast should be specified to:
a) distribute dead and live loads to the formation, subgrade and structures without
overstressing them;
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Page 37 of 105
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
6.3.2 Construction
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ballast shall be profiled so that no vertical face of any sleeper is visible. Where
sleepers of adjacent tracks are at different levels the ballast shall be heaped at the
end of the higher sleeper.
Ballast shall be kept clear of rails, fastenings, slide chairs/baseplates, flangeways,
electrification equipment, signalling equipment.
Ballast shall be profiled so as to be clear of conductor rail, and of collector shoes.
Ballast should only be heaped in the four-foot as a temporary measure and be no
higher than the plane of the rails when the line is open to traffic.
Arrangements shall be made to re-profile excess ballast to clear the top of the
sleepers and fastenings particularly where the OmniVision PLPR system is utilised to
replace the manual basic visual inspection, BVI regime.
Unless approved otherwise by the RAM [S&T], ballast shall be kept clear of surface
cable troughing routes.
In S&C, ballast between bearers containing stretcher bars or drive equipment may
be kept 100mm below the top of the bearer.
6.3.3 Ballast profile - CWR
The minimum ballast shoulder profiles shown in table 2 shall be applied to CWR
track in the open.
Open CWR track refers to all track including the first 40m into any tunnel.
Table 2 Dimensions of ballast shoulders
Minimum width of
shoulder a
mm
Height of
shoulder above
sleeper top
mm
450
375
Location
Straight track, curves over
2000 m radius
450
450
600
The width of the ballast shoulder is measured outside the sleeper ends, at sleeper-top level.
Discontinuities include insulated joints, adjustment switches, abutting toes of S&C, and catch points. The
wider shoulder should apply over not fewer than 10 bays each side of the discontinuity.
c
No greater than 200mm. A minimum clearance of 50mm must be maintained around conductor rail and
insulator pots.
b
Page 38 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
The position of the track shall be monitored at weekly intervals until records show
four consecutive readings with no movement. The monitoring frequency shall then
be monthly for six months. Subsequent monitoring frequencies shall be determined
by the Track Maintenance Engineer.
Page 39 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Page 40 of 105
Licensee=Capita Symonds to Capita property & infrastructur/5965831001
Not for Resale, 05/18/2016 04:44:17 MDT
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
At the approach end, the parallel portion of guard rails shall extend 18 m beyond the
face of the abutment (or the location at risk) and include a set of gathering rails.
Where guard rails already exist and they are removed, the justification for their
removal shall be recorded.
A derailment containment kerb should extend at least 300 mm above rail level. It
should comprise:
j) a structural metallic member; or
k) not less than 450 mm width of brickwork; or
l) not less than 300 mm width of reinforced concrete.
Guard rails should not increase the risk of track buckling.
6.5.4 Track on swing or lifting bridges - design
New swing and lifting structures shall not be installed in Category 1A to 4 track.
The provision of rail joints without fishplates between fixed and moving structures,
typically long steel bridges and swing bridges, shall require site specific design and
acceptance in accordance with NR/L2/TRK/2500.
The rail gap at the ends of swing or lifting bridges shall accommodate the thermal
movement of the structure, typically 15 - 40 mm wide for a span of 40 m.
A maximum permissible speed of 40 mph shall apply for joints wider than 15mm.
Gaps or line speeds in excess of 40mm or 40mph shall require approval from the
Professional Heads [Track] & [Civils].
Page 41 of 105
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Rail joints between fixed and moving sections of track shall be square to each other
at initial construction 5 mm unless specified otherwise.
Abutting rails, when designed without fishplates, shall be limited to a maximum 2 mm
difference in rail head longitudinal profile when unloaded with the movable span in
the closed position.
Vertical differences in rail level greater than 2 mm may be corrected by shimming. A
maximum of only two shims may be used at any single rail support point between the
structure and the rail.
Design calculations should be retained by the RAM [Civils].
6.5.5 Thermal effects on structures - design
Structures with expansion switches shall have site-specific design and acceptance in
accordance with NR/L2/TRK/2500 and NR/SP/CIV/003.
Standard rail expansion switches shall be positioned to be clear of the moving end of
any structure. They shall be positioned and designed so that the rail fastenings toe
load per rail from the end of the movable portion of the structure and the machined
section of the expansion switch does not exceed 450kN.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
The design should take account of the transition arrangements between the structure
and adjoining track and the potential increased loading that this can induce.
6.5.8 Loads on embankments - design
Track position on embankments should not compromise the cess or overload the
embankment.
6.6 Surveying
On major projects (route enhancements, major remodelling or new construction), a
primary and secondary survey grid shall be used in accordance with the crossdiscipline engineering survey requirements in NR/L2/TRK/3100.
Surveys shall be tied into existing primary or secondary Survey grids. Where no grid
is in place, as part of the survey, permanent ground markers shall be established
which can subsequently be incorporated into a route grid.
Line and level survey for S&C renewals shall extend a minimum of 200 m into
adjacent track. All designs shall finish within a straight or regular circular curve.
6.7 Minimum clearances - design
Horizontal and vertical alignments shall be designed to afford normal structural and
passing clearances (as defined in GC/RT5212) for all vehicles and vehicle gauges
currently published for the route. Vehicles and vehicle gauges envisaged to operate
in the future, as specified in the Gauge Capability Database, shall be considered in
compliance with NR/L2/TRK3201. At platforms, heights and offsets (as specified in
GI/RT7016) shall be achieved. Coping stones shall be adjusted as necessary.
In platform cases, clearances and stepping may be compromised to achieve the
requirements of GI/RT7016. The detail of this compromise shall be agreed with the
Network Rail Senior Gauging Engineer.
Additional clearances for future overhead electrification shall be confirmed with the
Electrification Engineer.
Where it is not practicable to achieve the above requirements, clearances should be
agreed between the RAM [Track] and the Gauging Engineer.
6.7.1 Minimum clearances track lowering
Where track is to be lowered to increase clearances, the design shall provide normal
structural and passing clearances. Reduced clearances shall only be allowable by
exception and where future maintainability has been taken into account.
Geometry element lengths shall comply with 8.4.
6.8 Switch and crossing layouts - design
Layouts shall be risk assessed using the S&C Design Risk Ranking Tool.
Page 43 of 105
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Schemes should be developed and designed using the minimum number of S&C
units. Existing S&C that is rarely used should be recovered wherever possible.
Layouts should be designed using standard designs and the preferred geometries
of S&C. The use of non-preferred, obsolescent or withdrawn S&C units should be
justified.
Wherever practicable, designs should avoid switches and crossings being placed at
the following locations:
a) bottoms of gradients;
b) within through platforms;
c) on bridges, especially of the longitudinal-timbered type;
d) on horizontal curves, especially transition curves;
e) where there would be negative cant or where the cant exceeds 110 mm;
f) where the turnout radii would be below the exceptional minimum radii for
passenger lines;
g) on vertical curves;
h) within tunnels; and
i) below overbridges.
6.8.1 Switch and crossing layouts minimum radius
1 in 7 and 1 in 7 slips shall only be installed on straight track.
Any through line radius applied to 1 in 8 and 1 in 10 slips shall not result in a slip
radius of less than 176 metres.
S&C (of any type or design) shall not be installed on track with a through line radius
of less than 150m.
S&C installed on track with a through line radius between 175 and 150m shall be
subject to a risk assessment.
The risk assessment shall consider as a minimum the:
a) direction of traffic;
b) tonnage;
c) speed;
d) wheel / rail interaction;
e) provision or absence of gauge widening;
f) provision or absence of continuous check rails;
g) inspection regime;
h) environment;
i) access; and
j) consequential risks.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Page 44 of 105
Licensee=Capita Symonds to Capita property & infrastructur/5965831001
Not for Resale, 05/18/2016 04:44:17 MDT
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Where standard fixed buffer stops are installed, designs including rear bracing rails
(as specified in RE/PW/590) or an approved equivalent shall be used.
The design of buffer stops on passenger lines shall take the following factors into
account:
a) type of rolling stock and buffing arrangements;
b) minimum and maximum train weights;
c) maximum likely impact speed (not less than 10 km/h);
d) average retardation rate of 0.15 g with a maximum of 0.25 g;
e) availability for movement of buffers to absorb energy from impact;
f) track adhesion conditions;
g) approach gradient;
h) station or other structures behind the buffer stops;
i) frangible platforms; and
The design of buffer stops on freight lines shall take the following into account:
k) the type of rolling stock and buffing arrangements; and
l) any structures behind the buffer stops.
The overall design of the end-of-track arrangements may also include speed control
and/or train stop devices, permanent speed restrictions, warning lights and/or
improved illumination to the buffer stops to achieve the required protection.
6.11 Level crossings and road-rail vehicle access points
Proprietary decking systems installed at level crossings and road-rail vehicle access
points (RRAP) shall be installed in accordance with the manufacturers' instructions
which include specific arrangements for the track system.
Track alignment designers shall consider the road profile at level crossings, they
shall conform to the appropriate regulations and requirements.
Flangeways of 60 mm (nominal) width shall be provided at level crossings and roadrail machine access points. Where flangeways of less than 60 mm are used, an entry
and exit flare shall be provided.
See 1.1 for the requirements on depths of serviceable rails through level crossings.
NOTE: See NR/L3/TRK/2049 E4 for the selection of level crossing systems and road profiles
across level crossings.
Page 46 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
j) track circuiting.
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
6.12 Sidings
The requirements for the layout and geometry of sidings shall be as specified in
NR/L2/TRK/2049 A 6.5.
7 New construction design
The requirements shown below are in addition to those for track renewals.
7.1 Horizontal alignment new construction
New construction shall make use of normal design values.
The through alignment should be optimised with no virtual transitions.
The minimum preferred radii for plain line running lines shall be 500 m with an
absolute minimum of 400m.
7.1.1 Modelling of geometry new construction
The curving characteristics, speed and kinematic envelope of vehicles intended to
use the track shall be modelled to determine the optimum combination of cant and
cant deficiency.
7.2 Vertical alignment new construction
Design of track gradients for new construction shall take account of:
b) position of signals and operational regime (e.g. the likelihood of a train being
required to start on the gradient or stop at a station or signal);
c) predicted rail adhesion conditions, including the effect of weather; and
d) the combined effect of gradient and horizontal curvature where the gradient
coincides with a small radius horizontal curve;
The normal limiting design values for track gradient for new construction shall be 1 in
80 (12.5 mm/m).
The exceptional limiting design values for track gradient for new construction shall
be:
e) 1 in 50 (20 mm/m) for sections up to 1.9 miles (3 km) in length;
f) 1 in 28.6 (35 mm/m) for sections up to 0.3 miles (0.5 km) in length where
trains are not intended to stop and start in normal operation; and
g) 1 in 28.6 (35 mm/m) for passenger only lines where:
i. i) The slope of the moving average profile over 6.2 miles (10 km) is less
than or equal to 25 mm/m; and
ii. ii) The maximum length of continuous 35 mm/m gradient does not
exceed 3.7 miles (6 km).
Page 47 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
The operation of engineering trains shall be taken into account during the design
stage.
When designing the new alignment the combined effect of gradient and curvature on
the drawbar capacity and tractive effort of the proposed services should be
considered. The required tractive effort should not be greater than those listed in
static load tables.
Modelling shall be undertaken to confirm the design where either:
a) static load tables show the trailing loads for current and future trains are within
10% of the maximum; or
b) calculations show that forces in the vehicle couplings are within 10% of the
maximum; or
c) where no performance characteristics currently exist for either the type of train
or the proposed design (i.e. combination of gradient and curve)
Modelling shall be undertaken on a system which has been reviewed and endorsed
by Professional Head [Traction & Rolling Stock].
7.3 Switch and crossing design new construction
S&C should be positioned on straight track with standard track intervals (6 & 10).
Only preferred geometries shall be used.
Slips and tandems shall not be used in running lines except in sidings.
A or B switches shall not be used in running lines except in sidings or as trap / catch
points.
The use of C & D switches on running lines should be restricted to lightly used
turnouts to reduce the likelihood of switch wear, the need for subsequent repairs and
the associated derailment risk.
Consideration shall be given to the relative positioning of S&C units with respect to
ease of inspection and mechanised maintenance.
7.4 Stiffness of the track system new construction
A target stiffness value of 160 MN/m shall be used for the track system.
The formation for ballasted track shall be designed to achieve a target formation
stiffness of 45 MN/m.
Values for non-ballasted track systems may be different and need to be appropriate
for the specific design of system selected.
Page 48 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
8 Geometry design
8.1 Speeds
8.1.1 Permissible speeds
The permissible speed on a curve shall be calculated taking into account the
following:
a) radius of the curve;
b) applied cant;
c) permitted values of cant deficiency;
d) permitted values of rates of change of cant and cant deficiency on the transition
curves either side of the circular curve; and
e) available structural and passing clearances and ability to control track position.
No upward rounding of permissible speed is allowed and values shall be rounded
down to nearest 5mph increment.
ERTMS (ETCS) measures speed in kilometres per hour (km/h); the Rule Book
presently only refers to speed in miles per hour (mph).
Where ECTS is being implemented and speeds shall be converted from km/h to mph
using the values in table 3.
mph
5
10
15
20
25
30
35
40
45
50
55
60
65
km/h
10
15
25
30
40
50
55
65
70
80
90
95
105
mph
70
75
80
85
90
95
100
105
110
115
120
125
km/h
115
120
130
135
145
155
160
170
175
185
195
200
Table 3 Miles per hour (mph) conversion to kilometres per hour (km/h)
NOTE: There could be reasons other than track geometry design that restrict the permissible
speed, e.g. the ability to maintain the track to sufficiently high track quality standards, the type
of track installed, the nature of the signalling system, or the strength of structures.
Page 49 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
This can result in speeds that are not rounded down. The speeds shall still remain
within the limiting values.
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
Parameter / Constraints
Rate of Change of Cant
(EPS Tilt)
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Maximum
Exceptional
Maximum
Exceptional
75 mm/sec
95 mm/sec
75 mm/sec
95 mm/sec
265 mm
300 mm
225 mm
225 mm
110 mm/sec
150 mm/sec
110 mm/sec
150 mm/sec
Page 50 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Page 51 of 105
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
Exceptional
Passenger
200
150
Non-passenger
150
125
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Where the existing track has been designed and constructed to radii tighter than that
in table 4, the existing horizontal radii should be improved and not worsened. Where
Page 52 of 105
Licensee=Capita Symonds to Capita property & infrastructur/5965831001
Not for Resale, 05/18/2016 04:44:17 MDT
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
site constraints make it not reasonably practicable to comply, the existing horizontal
radii may be retained subject to agreement by the RAM(T).
8.3.3 Tight radius reverse curves
In the design of track layouts, the risk of buffer locking on reverse curves should be
reduced by introducing as much straight track as possible between the two curves.
If one hand of a reverse curve has a radius of less than 160 m, a minimum 3 m
straight should be provided between the curves.
8.4 Vertical alignment
On running lines, vertical alignments shall consist of lengths of track at constant
gradient connected by vertical curves.
Each element (constant gradient) should be as long as possible and not less than 2
seconds at the maximum line speed unless agreed otherwise by the RAM [Track].
Vertical curves shall be at least 25m long.
Changes in vertical alignment shall not be coincidental with changes in horizontal
alignment.
Vertical Curves may be omitted by agreement of RAM [Track] where the change in
gradient is less than 2mm/m.
See 6.7 for the requirements for minimum clearances.
Each S&C unit should sit on one continuous gradient, extending for at least 20m
beyond the last bearer of that unit. Gradient changes should not be within S&C and
by exception can be within the through bearers subject to their being a vertical curve
of 10,000m minimum radius. Switches should be on one continuous gradient and
may by exception be on concave vertical curves. Switches should not be on convex
curves.
8.4.1
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
c) tamping machines shall use the low rail on canted track as the datum rail for
lifting.
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Where the speed requirements cannot be met by using normal design values,
maximum design values should be used.
Where the speed requirements cannot be met by using maximum design values,
exceptional design values may be used. The reason and implications for their use
shall be justified. They shall be approved in accordance with NR/L2/TRK/2500.
8.5.1 Curving design values cant
Maximum/minimum values for cant shall be as shown in table 6 and for cant
gradients in table 7.
Each track of a double (or multiple) line shall be treated separately.
On steep gradients slow moving freights might restrict the cant that can be applied.
NOTE: In exposed places, where high winds might be experienced, it is undesirable to apply cant to
the maximum value.
Cant is normally applied to the high rail but may be split between high and low rails
(if the low rail can be lowered).
On curves designed for Enhanced Permissible Speeds that have high cants and
deficiencies consideration should be given to applying the cant by both raising the
high rail and lowering the low rail to avoid rapid changes in mean longitudinal level.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Page 54 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Table 6 Cant
Normal Design
Value
Maximum (or
Minimum) Design
Value
Exceptional Design
Value (where
different from Max.)
150 mm
150 mm
in platforms
110 mm
110 mm
110 mm
110 mm
(R-50)/1.5
(R-50)/1.5
150 mm
150 mm
0 mm
0 mm
in Other S&C
110 mm
110 mm
110 mm
110 mm
0 mm
0 mm
0 mm
80 mm
Parameter / Constraints
Notes:
1. Cants in excess of 150 mm are only permitted where they existed before 1st July 1999.
2. Cants in excess of 110 mm in platforms are only permitted if platforms are to gauge and level.
3. Complex S&C is as listed in NR/L3/TRK/2049. A maximum design value of 50 mm of cant may
be applied on AV or BV(S) switches.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Page 55 of 105
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
Maximum (or
Minimum) Design
Value
Exceptional Design
Value (where
different from Max.)
0 - 60 mph
1 in 600
1 in 500
1 in 400
65 - 95 mph
1 in 800
1 in 600
1 in 400
1 in 1000
1 in 800
1 in 400
Switch Toes
None
None
1 in 800
None
None
1 in 1200
1 in 600
None
1 in 1200
1 in 1500
1 in 2500
Parameter / Constraints
Maximum Cant Gradients:-
Notes:
1. Bearer rake and baseplate thickness shall remain constant through the crossing
In the exceptional case of curves without transitions, the change of cant shall be
applied over the length of the virtual transition.
On transitions between reverse curves with no intervening straight, the point of zero
cant shall coincide with the reverse point (point of zero curvature).
Virtual transitions should only be used by exception and not in through alignments.
They should only be necessary for the design of track in and around S&C.
Where possible, the rates of change of cant, cant deficiency and curvature should be
the same on either side of the reverse.
Where speed changes occur the design should consider the achievable speeds
limited by breaking and acceleration as well as the theoretical linespeed at these
locations.
For permissible speeds up to 50 mph and enhanced permissible speeds up to
70 mph, design of transitions should normally be based upon cant gradient rather
than rate of change of cant.
NOTE: These guideline speeds are based on maximum design values.
Page 56 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Table 8 Transitions
Normal Design
Value
Maximum (or
Minimum) Design
Value
30 m
25 m
35 mm/sec
55 mm/sec
85 mm/sec
35 mm/sec
75 mm/sec
95 mm/sec
140 mm/sec
180 mm/sec
200 mm/sec
Parameter / Constraints
Minimum Length of Transition (See
Note 1)
Exceptional Design
Value (where
different from Max.)
Notes:
1. Minimum transition lengths are necessary to support the manual control of tampers.
2. Transitions generally need to be designed to accommodate conventional trains travelling at
permissible speeds. They should be checked for tilting trains at enhanced permissible speeds.
3. Maximum rate of rotation is irrespective of vehicle type.
Page 57 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Maximum (or
minimum) design
value
Exceptional design
value (where
different from max.)
Jointed track
90 mm
90 mm
110 mm
110 mm
Parameter / Constraints
CWR for Enhanced Permissible Speed (EPS) on datum plated curves of radius (see note 3):
700 m and over
265 mm
265 mm
400 to 699 m
150 mm
225 mm
under 400 m
110 mm
110 mm
Adjustment switches
110 mm
110 mm
300 mm
Notes:
1. Applies to passenger type bogie rolling stock with air suspension, maximum 13 tonne axle
weight, all seats full.
2. Applies to passenger type bogie rolling stock, light engines and class 140 to 144 trains
provided that no spring catch point, level crossing, direct fastening structure or other feature
that is likely to contribute to lateral misalignment is situated on the curve or transition where
110 mm cant deficiency is exceeded. Differential speeds may be required to limit the speed of
freight traffic.
3. Enhanced permissible speeds apply to specific trains only. Speeds must be calculated using
cant deficiencies which do not exceed the maximum operating cant deficiency of the particular
train. All values of cant deficiency in excess of 150 mm must also take into consideration the
effects of wind on curves (See GC/RC5521).
Page 58 of 105
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Maximum design
value
Exceptional design
value (where
different from max.)
Permissible speed
35 mm/s
55 mm/s
70 mm/s
35 mm/s
110 mm/s
150 mm/s
Parameter / Constraints
Notes:
1. These figures are the maximum permitted. Not all trains might be able to run at these values.
2. These rates should be calculated based on a vehicle which has no tilt lag [i.e. ignoring effects
on the leading vehicle(s)]. For transitions where cant deficiency exceeds the value at which
maximum tilt occurs, the average rate of change of cant deficiency over the length of a clothoid
or cubic parabola transition shall be used.
3. See table 3 for vehicle restrictions.
Page 59 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
NOTE: Tilting trains generally run 20% faster on curved track than non-tilting trains.
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Page 60 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
If the turnout is of contrary flexure, the cant to be applied to the main or through line
shall not cause the maximum permitted value of negative cant to be exceeded on the
turnout.
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
Maximum (or
minimum) design
value
90 mm
90 mm
110 mm
110 mm
50 mm
50 mm
Parameter / constraints
Exceptional design
value (where
different from max.)
150 mm
(see notes 1 & 2)
125 mm
75 mm
90 mm
110 mm
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Notes:
1. Cant deficiency above 110 mm in S&C may only be applied when:
a) The S&C is CEN60;
b) the main line radius is flatter than 400 metres;
c) high speed flares have been provided on the check rails and on the facing wing rails on
crossings installed on the low rail;
d) there are no longitudinal bearers, level crossings or direct fastening structures within 20m of
the approach to or exit from the S&C; and
e) and the following have been considered and the assessment recorded with the design
information; degree of track fixity, changes in cant deficiency on the approach to or exit from
the S&C, maintenance regime.
2. The exceptional cant deficiency on the through route of S&C with swing nose crossings is 200
mm.
3. Enhanced permissible speeds are not applicable on the turnout route of S&C.
4. On leads which have been designed as split equal, both routes must be regarded as turnout
routes.
5. Complex S&C is as listed in NR/L2/TRK/2049.
Page 61 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Maximum design
value
Exceptional design
value (where
different from max.)
Permissible speed
35 mm/sec
55 mm/sec
70 mm/sec
35 mm/sec
110 mm/sec
150 mm/sec
BS95RBH S&C
55 mm/sec
55 mm/sec
55 mm/sec
55 mm/sec
80 mm/sec
80 mm/sec
80 mm/sec
80 mm/sec
Parameter / constraints
Through route of S&C
93.33 mm/sec
Notes:
1. These figures are the maximum permitted, not all trains are able to run at these values.
2. These rates should be calculated based on a vehicle which has no tilt lag [i.e. ignoring effects
on the leading vehicle(s)].
3. See table 3 for vehicle restrictions.
4. In NR60 transitioned turnouts an exceptional value of 93.33 mm/sec may be applied to the
transitioned part of the turnout line between the heel of the switch and the IP of the crossing.
The two running rails of the track shall be of the same nominal section.
Page 62 of 105
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
NOTE 2: if serviceable or cascaded rail is being used, BS110A and BS113A sections may be
regarded as matching
NOTE 3: BS113A rail and CEN56E1 are considered to be fully interchangeable.
Historic rail sections (for example BS95RBH) may be used where either existing
fastenings cannot accommodate rail sections specified in 10.2 or a short section of
track is being relaid in an area of track with historic rail profiles.
9.2 Welding
A solid phase process e.g. mobile flash-butt welding or gas pressure welding, should
be employed when practicable and cost effective in preference to aluminothermic
welds for site welding.
NOTE: See NR/L2/TRK/0032, NR/L2/TRK/0132, RT/CE/S/130, and RT/CE/S/131 for the
specification of rail welding.
Transition rails shall be used when changing from CEN56 to CEN60, or from
BS95RBH (Bullhead) to CEN56 in track categories 1A to 4.
9.5 Level crossings
Where serviceable or cascaded rail shall be used at level crossings. Any head loss
shall be limited to 5 mm at installation so as not to expose the crossing surface to
damage.
See 10.14 & 10.16 for the requirements for joints in level crossings.
10 Specification of plain line
10.1 Track gauge
Track gauge for new straight track and curved track over 200 m radius shall be 1435
mm nominal measured at right angles across the track and between the heads of the
rails in a plane 14 mm below their top surface.
Where serviceable concrete sleepers are used 1432 mm nominal gauge is
permitted.
Tolerances shall be as specified in Appendix A.
Page 63 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
NOTE: Although referred to as 1435 mm nominal, new sleepers are designed to give gauges
of 1436 (+2/-1) mm for CEN56 rail and 1438 (+2/-1) mm for CEN60 rail.
Up to 20
25 to 60
65 to 95
100 to 125
6 mm
5 mm
4 mm
3 mm
3.0 m
3.6 m
4.5 m
6.0 m
NOTE 1: 5F40 & 5EF28 sleepers have a designed gauge of 1435mm (+/-2 mm).
NOTE 2: G44 sleepers configured for CEN56E1 track have a designed gauge of 1436 mm (+2/1mm).
NOTE 3: G44 sleepers configured for CEN60E1/E2 track have a designed gauge of 1438mm (+2/-1
mm).
Gauge (mm)
200 - 176
1438
47
175 - 151
1441
50
150 - 126
1444
53
125 - 101
1447
56
100
1450
59
1. Gauge widening may be less than shown in this table where approved by Network Rail.
2. Rate of change in gauge and flangeway widening shall not exceed 1 in 400, e.g. 3 mm in
1200 mm (or two sleepers).
3. The dimension from the running edge of the non-checked rail to the inner flangeway face
of the check rail (check gauge) shall be 1391 (+1/-3) mm.
4. Achievement of check gauge shall take precedence over check flangeway (subject to a
minimum 38mm flangeway).
Gauge widened shall be achieved by moving the inner rail away from the designed
track centre line.
Curves fitted with continuous check rails shall be limited to 30mph.
Page 64 of 105
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Rails
ab
Minimum
ballast
depths
mm
1A, 1
300
250
(concrete)
200 (steel)
200
(concrete)
150 (steel)
4&5
200
(concrete)
150 (steel)
200, 150
(steel only)
200
Page 65 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Where a geotextile, grid or geocomposite is associated with a new sand blanket, the
minimum ballast depth below sleeper bottom shall be 250 mm on track categories 2
to 6, and 350 mm on track categories 1A and 1 where future reballasting will be
carried out with ballast cleaners.
Compaction of ballast
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Page 67 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
a) using approved vibrating plates, in a single layer for ballast depths up to 480 mm,
or where ballast depths under the sleeper are greater than 480 mm in layers not
exceeding 200 mm;
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Page 68 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
c) GV54 bearers shall only be installed in vertical S&C layouts with the same
sleeper soffit depth (including NR56V).
Limitations on the use of fabricated or cast hollow steel sleepers for cables are as
follows:
a) Cast or fabricated hollow steel sleepers shall not be installed:
i. for the conveyance of earth bonds or traction power cables; or
ii. in third rail DC electrified tracks except for the housing of point operating
equipment (POE) or hot axle box detector (HABD) equipment;
b) in steel sleepered track;
c) no more than two cast or fabricated hollow steel sleepers shall be installed
consecutively and not less than six normal sleepers shall be provided between
subsequent runs of hollow sleepers;
d) not be installed within two sleepers of an insulated, fishplated or welded rail joint.
e) shallow depth designs shall only be used in softwood sleepered areas where the
line speed is less than 60 mph with the agreement of the RAM [Track].
The choice of bearer should be determined by sleeper type, fastening type,
construction depth (full or shallow depth) and whether a bearer with a removable top
cover is required to install the existing cable runs.
Care should be taken to check that the soffit level of hollow sleepers is consistent
with the adjacent sleeper type.
There is no requirement to provide four timber sleepers to separate hollow steel
bearers from adjacent concrete sleepers, longitudinal bearers or S&C.
NOTE: For more information on the management of cables routes, see NR/SP/SIG/19812.
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Page 70 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
NOTE: In tunnels more than 180 m long (excluding the 40 m at each end), and where a limited
temperature range exists, there is no lower limit on track radius.
10.11.1 CWR in curved track - concrete and timber sleepers and timber bearers
On concrete and timber sleepers and timber bearers, lateral resistance plates may
be installed to avoid adjustments to CRT values. Lateral resistance plates should be
capable of being adjusted to permit tamping and re-alignment, in line with the
manufacturer's instructions.
Where installed, lateral resistance plates on concrete and timber sleepers and timber
bearers shall be configured as follows on curves with a radius between:
a) 500 to 351 m, one lateral resistance plate on alternate sleepers or bearers;
and
b) 350 to 250 m, one lateral resistance plate on each sleeper or bearer.
When installing lateral resistance plates, the sequence of work should be:
a) tamp to the correct line and level;
b) fit lateral resistance plates;
c) consolidate the ballast around the resistance plates; and
d) stress the track.
Lateral End Resistance Plates (LERP) to drawing RE/PW/736 shall not be used for
track renewals or new construction.
10.11.2 CWR in curved track - steel sleepers
Steel sleepers installed on curves with radii below 500 m shall be installed:
a) at 600 mm spacing:
b) with a 600 mm-wide ballast shoulder; and
c) without any discontinuity within the curve.
NOTE: Discontinuities includes a change of sleeper material (timber, concrete etc.), adjustment
switches and level crossings.
Where steel sleepers are installed on curves with radii between 350 m and 250 m
the following additional requirements and conditions may be applied to avoid
adjustments to CRT values:
d) steel sleepers with additional housings in the four-foot for strengthening rails (as
for guard rails) should be used;
e) sleepers should be installed with the extra housing for strengthening rails
alternating from side to side except around joints in the strengthening rails where
the two sleepers either side of the joint should have housings;
f) two strings of strengthening rails (made up of serviceable rails nominally 18 m
long) should be provided in the four-foot with joints staggered by 9 m;.
g) rail pads and insulators should be used with the strengthening rails; and
Page 71 of 105
--`,`,,,,,`,`,,,,`
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
The standard length of rails in jointed track is 18.288 m and installed with fishplated
expansion joints.
10.12.3 Minimum rail length - permanent situation
The minimum length of rail in plain line between any type of rail joint shall be not less
than:
a) 18 m where the linespeed is 90 mph or more;
b) 9 m below 90mph; or
c) in accordance with table 16 where site constraints make this unachievable.
Table 16 Minimum rail lengths
Between and
Track radius below 600 m
Welded
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Fishplated
Adjustment switch
Welded
m
Insulated a
m
Fishplated b
m
9.0 c
4.5 c
4.5
4.5 c
4.5
9.0
4.5
9.0
9.0
4.5
4.5
4.5
5.0 d e
Page 72 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
Ref:
Issue:
Date:
Compliance date:
d
e
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
This distance does not include the machined length of the switch.
Only permitted during construction.
NOTE: See table 17 for the maximum speeds where the rail gap is, or has opened up, over 50 mm.
Page 73 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
Maximum speed
Time limit
90 mph
125 mph if tight-jointed at both
ends and in CWR
80mph
7 days
Back-hole bolted
50 mph
Clamped a b
Joints fitted with emergency clamped fishplates and a Network Rail-approved clamping system
shall be limited to 50 mph.
b
The speed shall not exceed 20 mph unless all of the following apply:
a) both rail ends have been sawn or disc cut;
b) abutting rail heads are in line;
c) the gap between rail ends does not exceed 10mm (Note that, in order to control the gap, if
the rail temperature changes, it might be necessary to impose more frequent inspection or, in
CWR, to install temporary adjustment switches);
d) there are no voids under the two sleepers each side of the joint (that is four sleepers total);
e) the clamping system is approved by Network Rail for use at 50mph. (G-clamps shall only be
used with emergency fishplates for the clamping of defective welds and rails); and
f) the fishplates are correct in terms of rail section and lift.
c
Any extension beyond 14 days for backhole joints or 7 days for clamped joints shall be subject to
approval by the RAM [Track]. Approval shall be dependent upon either:
a) removal being planned and dated, and additional controls being implemented and
documented; or
b) speed being reduced to 20 mph for the duration of the extension period.
d
Fishplates and clamps shall be specifically approved for operation at 80mph. The joint shall be
installed and inspected in accordance with the procedure for their use.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Page 74 of 105
Licensee=Capita Symonds to Capita property & infrastructur/5965831001
Not for Resale, 05/18/2016 04:44:17 MDT
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
A speed of 50 mph may be applied if the rail is fitted with fully-bolted fishplated joints
at both ends.
These requirements are subject to a time limit of 48 hours, with a 24-hourly
inspection during that period.
10.13.4 Temporary joints - fly-fished and wide gap joints
The maximum permitted speeds for fly-fished and wide gaps joints shall be as shown
in table 18.
Maximum speed
Clamped
5 mph
20 mph with Watchman,
Line to be blocked
2.5 m a
4.5 m a
4.5 m b
In the case of a skew bridge this distance may be taken along the centre of the four-foot.
May be reduced within a bridge, where two timbers abut. The joint should be at least 2
m from the ends of the timbers wherever practicable.
b
Page 75 of 105
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
On lower category track and lower cant deficiencies insulated joints should be of a 6hole shop prepared glued units type wherever practicable.
Where dry insulated joints are installed at an existing joint, the condition of the rail
ends and the holes should be suitable for continued use.
10.15.3 Tight fishplated joints in CWR
Tight fishplated joints in CWR shall be assembled with the correct:
a) fishplates for the rail sections (allowing for any differential rail wear); and
b) assembly of bolts, nuts and washers.
Page 76 of 105
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
There shall be no gap between the rail ends when the rail is drilled.
Fishbolts shall be tightened to the torque values given in table 20.
Torque to be applied
880 Nm
1020 Nm
Gap opening
mm
-4 to 2
3 to 7
8 to 13
14 to 18
19 to 27
635
641
648
654
660
125
119
112
106
100
Where the gap openings(s) are inconsistent with the overlap dimension, the overlap dimension
takes precedent.
Page 77 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
New adjustment switches shall be welded so that the distance from the machined
portion of the switch to the nearest fishplated joint is not less than 9 m.
Adjustment switches shall not be installed as a permanent feature to overcome
staging or planning difficulties.
Adjustment switches should ideally be sited on straight track. They should be laid
with strap rails and the inside tongues trailing to the dominant direction of traffic.
Lengths of CWR exceeding 120 m should be provided with an adjustment switch at
both ends.
10.17.2 Temporary adjustment switches
When CWR is being extended week by week under cover of a temporary speed
restriction, adjustment switches may be temporarily fishplated to the CWR.
10.17.3 Fastening toe loads stress transition length
The toe load of clips used in the stress transitioned length approaching an
adjustment switch shall be equal to or less than the toe load of the fastenings in the
first 130 m of the stressed length.
See table 22 for toe loads of commonly used rail fastenings.
Table 22 Fastening Toe Loads
Clip Type
Mills
<6.5
SHC
6.5
PR400 series
6.5
e1800 series
9.0
Fastclip
10.0
Vossloh W14
10.0
e2000 series
12.5
e-plus series
12.5
Values are per clip, and assume all components are in a as new condition.
Page 78 of 105
Licensee=Capita Symonds to Capita property & infrastructur/5965831001
Not for Resale, 05/18/2016 04:44:17 MDT
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Rail temperature
C
Expansion gap
mm
Below 10
10
10 - 23
24 - 37
38 or above
In an insulated joint, the gap shall suit the thickness of the end-post.
Where rails with differential sidewear are fishplated together the step in the running
edge shall be blended in by grinding as follows:
a) blended length shall be 1.5 m from the joint;
b) the sidewear angle of the more sideworn rail shall be maintained throughout the
blended length;
c) the gauge corner shall be rounded throughout the blended length; sharp or square
edges are not permitted; and
d) a fully-supported grinder (that is mounted on both rails) shall be used; manual
support alone is not permitted.
The centre of the joint shall be located mid-way between sleepers.
Joints shall normally be located opposite each other in the same bay. They may be
located in different bays with the agreement of the RAM [Track].
If joints have been formed at a rail temperature lower than 0 C or greater than 45 C
a joint closure temperature survey shall be carried out as soon as practicable when
the rail temperature falls within the range of 10 to 37 C.
NOTE 1: See also 10.13 for reference to restrictions regarding temporary joints, and section 13 for
reference to cold expansion of bolt holes.
Page 79 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
NOTE 2: See NR/L2/TRK/001 for the requirements for joint closure temperature surveys.
NOTE 2: When measuring track gauge within the machined area of the switches, the undercut
on the stock rail will give a false reading when measured with a conventional track gauge. If in
doubt determine the gauge by using the field face of the stock rail as reference point.
Page 80 of 105
Licensee=Capita Symonds to Capita property & infrastructur/5965831001
Not for Resale, 05/18/2016 04:44:17 MDT
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
Bearers
Minimum
ballast
depths c
mm
Recommended extent
of associated Plain
line d, e
1A g & 1
Concrete
300
Concrete
300
Concrete
300
Concrete
300
5&6
Running
Lines
Concrete,
hardwood
250
5&6
Sidings
Concrete,
hardwood
200
See NR/L3/TRK/2049 for the Maximum speeds through short switches and complex S&C.
Approved hollow bearers shall be used within switch panels as dictated by the choice of Point
Operating Mechanism.
c
Depths are measured below bearer.
d
Extent of associated plain line may be reduced if the existing track has not yet reached its half life.
e
See 10.3.3 for the requirements for ballast ramps.
f
See RT/CE/S/063.
g
Only S&C manufactured using CEN60 rails with concrete bearers shall be installed where line
speeds exceed 125 mph.
b
Hardwood timbers may be used with CEN56 Vertical S&C where physical
constraints prevent the use of concrete bearers
New or serviceable RT60 or NR60 S&C may be used as appropriate.
Page 81 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Track
category
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
BR109 inclined or bullhead may be used when renewing leads on a like for like basis
on lower category lines.
Renewal of rail and sleepers within the ramp is dependent upon their condition.
11.3.1 S&C - CWR
Where installed in CWR track, S&C units shall be of a CWR-compatible design and
be welded and stressed on installation.
Crossings without welded-on leg-ends shall be joined to the adjacent rails with tight
fishplated joints.
NOTE: See 0 for details of CWR-compatibility of S&C and 11.8 for requirements on the use of
adjustment switches with S&C.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Page 82 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
11.4 Switches
11.4.1 Switches - general
The switch rail, stock rail and baseplates in both half-sets shall be a matched set.
They shall comply with RE/PW drawings.
In CWR track switches (other than in switch diamonds) fitted with an anti-creep
device (ball & claw) should be specified in preference to stress transfer blocks.
See 6.8.1 for the minimum radius for switches.
11.4.2 Restrictions on designs of switches
Shallow depth switches shall not be used with handpoints (unworked points) or
mechanical point operation.
Full depth switches (excluding switch diamonds) shall not be installed where the line
speed exceeds 90 mph.
Straight-cut or inset switches shall not be installed in a trailing situation without
approval by the Head of Track.
NOTE: See 17.2 regarding the lubrication of new switches.
A "kicking strap" and soleplate (or steel bearer) shall be provided at the toe position.
Page 83 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
The number of stretcher bars (or approved equivalent) shall be as shown on the
relevant standard drawings.
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
shall
be
configured
according
to
the
manufacturer's
11.5 Crossings
Crossings shall not be located on bearers that change rake through the length of the
crossing.
Tight jointed fishplates in diamonds and insulated rail joints are the only types of
fishplated joint permitted on the welded-on extension legs of cast crossings.
11.5.1 Crossings - hardness
Austenitic cast manganese steel crossings installed on category of 1A, 1 or 2 track
shall be pre-hardened to a minimum hardness of 320BHN on the running surface
over the full length of the casting.
NOTE: 320BHN is normally achieved by Explosive Depth Hardening (EDH). EDH crossings
need to be specifically ordered and have a longer lead time.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Roller baseplates and plastic insert (slippers) shall not be used on train operated
points (for example spring points and hydro-pneumatic points) or handpoints
(unworked points).
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
1 in 5.5 or less
1 in 6
1 in 6.5
1 in 7
1 in 7.5
1 in 8
Any track radius through an obtuse crossing shall extend for a minimum of 8 m
beyond each end of the crossing unit.
Raised check rails in obtuse-angle crossings shall not be used in slips or scissors
crossovers in third or fourth rail electrified areas if they could foul collector shoes.
1 in 8 obtuse crossings installed with a similar flexure through alignment shall be
provided with raised check rails. A switch diamond shall be provided if the raised
check would foul third or fourth rail collector shoes.
1 in 8.69 obtuse crossings shall be installed with raised check rails. They shall only
be used in NR60 E12.5 double junctions where the through alignment is either
straight or contraflexure. They shall only be used with the approval of the Head of
tTrack.
Fixed obtuse crossings shall be cast manganese monobloc or cast manganese
centre block in track categories 1A to 4.
Spare obtuse crossings should be provided as directed by the RAM [Track] for
locations where performance is deemed to be critical.
11.5.4 Grinding of crossings following installation
When new crossings are installed they shall be inspected at the frequencies shown
below. They shall be ground or weld repaired if there are signs of damage or wear:
a) 6 weeks (but not more than 8 weeks);
b) 13 weeks (but not more than 15 weeks);
c) 26 weeks (but not more than 30 weeks); and
d) 52 weeks (but not more than 56 weeks).
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Page 85 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
11.6 Bearers
11.6.1 Bearers - general
Bearer for turnouts and crossovers shall be in accordance with the relevant RE/PW
drawing.
For more complex layouts, the following requirements additionally apply:
a) bearer positions shown on RE/PW drawings for turnouts, crossovers, diamonds
and junctions shall be used wherever possible;
b) ends of timber bearers shall normally extend 200 mm from the edge of the nearest
chair, baseplate or conductor rail support; this distance shall never be less than 50
mm;
c) bearers may be gapped in the four-foot provided the adjacent bearers in that fourfoot maintain gauge;
Timber and concrete bearers shall only be mixed in the same unit with the
agreement of the RAM [Track].
Concrete bearers shall not normally be drilled on site to accept rail or baseplate
fastenings, these holes being formed during manufacture. Site drilling shall only be
undertaken where the work has been assessed by the bearer manufacturer and
undertaken by the manufacturer or their approved suppliers.
Concrete bearers may be drilled on site for signalling equipment or other
attachments. Drilling shall be subject to the use of:
a) a template approved by the bearer manufacturer;
b) an approved method of drilling that shall not cause damage to the bearer; and
c) fastenings which will not crack or shatter the concrete.
NOTE: See NR/L3/TRK/4130 for requirements.
Page 86 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
d) bearers supporting fixed crossing noses shall not be gapped in the adjacent fourfoot;
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Wherever practicable, cant deficiency should be maximised to avoid the need for two
levelling.
Two levelling, with the crossing either higher or lower, affects the wheel transfer
between wing rail and crossing nose; in most cases leading to high impact forces
which worsen with increasing speed. The effect is more pronounced for sharper
angle crossings.
NOTE: See NR/L3/TRK/2049 for requirements.
Page 87 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
S&C units which are not CWR-compatible (see 0) shall be isolated from CWR by
adjustment switches.
Page 88 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
CWR
Requirement for
adjustment switch in
front of toes
Optional a
Requirement for
adjustment switch
behind crossing
Optional b
Jointed
Optional b
CWR
Mandatory
Mandatory
Mandatory
Optional b
Not required
Jointed
Optional b
CWR
Not required
Not required
Not required
a
Optional becomes Mandatory if the distance from the crossing joint or weld to the first fishplated
joint in front of the toes exceeds 37 m.
b
Optional becomes Mandatory if the distance between the last stress transfer block and the first
fishplated joint in the extension of the stock rail past the crossing exceeds 37 m.
Table 27 Use of adjustment switches at S&C with anti creep devices (ball and
claw)
Type of track in
front of toes
Jointed
CWR
Requirement for
adjustment switch in
front of toes
Optional c
Requirement for
adjustment switch
behind crossing
Optional c
Jointed
Optional c
CWR
Mandatory
Mandatory
Mandatory
Optional c
Not required
Jointed
Mandatory d
CWR
Not required
Not required
Not required
c
Optional becomes Mandatory if the length of rail, without expansion gaps, of which the stock rail
forms part exceeds 37 m.
d
The length of welded rail, of which the stock rail forms part, shall extend from the switch heel for a
minimum distance of one stress transition length prior to the adjustment switch. If an anchor point
occurs within this distance then the adjustment switch may be omitted.
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
See 11.6.3 for the requirements for bearer ties and AWS magnets, TPWS equipment
and axle counters.
Concrete sleepers
a) cast-in housings
b) converted F10 sleepers, with PR401A or e clips
c) Pan9 conversion of E1 sleepers, with PR401A clips
d) converted F16 sleepers, with PR401A or e clips
e) E1 sleepers with BH chairs and steel keys (but use wood keys in
tunnels)
Page 91 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
The minimum radius for the conversion of jointed track by site welding to CWR shall
be 500 m.
Jointed rails converted to CWR should have a minimum of 5 years residual life.
12.2.1 Conversion by aluminothermic welding
In track categories 1A, to 3 rails shall be cropped to remove fishbolt holes. In track
categories 4, to 6, bolt holes may remain, providing the weld geometry requirements
can be met.
NOTE: See NR/L2/TRK/3410 for proximity requirements when cropping rails.
Page 92 of 105
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
13 Holes in rails
13.1 General
Where required, holes in rails shall comply with RT/CE/S/008 and be:
a) as shown on relevant RE/PW drawings; or
b) as otherwise specified. .
Flame-cut holes are not permitted.
All permanent fishbolt holes factory drilled or site drilled in CWR shall be cold
expanded (see RT/CE/S/050).
Where bond holes are required, they shall not be drilled less than 525 mm from the
rail end, or within 30 mm of a weld. They shall not be closer than 75 mm centres and
shall be located wholly within +15 mm of the level of the fishbolt hole centreline.
Where rails are cropped, bond holes within 525mm of the new cut rail end should
also be removed.
13.2 Retention of bolt holes in CWR
New CWR plain line in track categories 1A, 1 and 2 shall be planned to be installed
without redundant holes greater than 15 mm diameter.
Where the creation of fishplate backholes is unavoidable, they shall be:
a) ultrasonically inspected prior to welding and be free of cracking;
b) cold bolt hole expanded;
c) agreed by the RAM [Track]; and
In track categories 3 to 6, and within S&C in all track categories, fishplate backholes
shall be:
a) ultrasonically inspected prior to welding and be free of cracking; and
b) ultrasonically inspected as fishplated joints once within the first twelve months
after welding as specified in NR/L2/TRK/001.
For track categories 3 to 6 and the turnout routes of S&C, backholes satisfying these
requirements do not need to be cold expanded.
Redundant front bolt holes shall not be retained in any track category.
NOTE: These requirements do not apply when jointed track is converted to CWR by site
welding of existing rails. Such conversions require site-specific approval by the RAM [Track]:
see NR/L3/TRK/3011.
Page 93 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
d) ultrasonically inspected as fishplated joints for the first six months after welding as
specified in NR/L2/TRK/001.
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
The designer shall calculate the design alignment standard deviation for each
alignment string using software agreed by Head of Track.
15 Tamping and dynamic track stabilisers
15.1 Tamping S&C
S&C shall only be tamped by machines suitable for the unit being installed. As a
minimum, machines with a third lifting point and extending tamping banks shall be
used.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Parallel tamping shall be used on S&C with bearers through two tracks where
insufficient access is available for the layout to be tamped by a single machine in
one possession, or where machines with a third lifting point are not available.
15.2 Geometry chart recorders
Where fitted, geometry chart recorders shall be used to measure the track geometry
at spate and quality tamps on both plain line and S&C. The data recorders shall be
set up to record the following channels in the following order:
a) cross-level;
b) 3 m twist;
c) track gauge;
d) horizontal geometry (as horizontal versines using lining chord on tamper); and
e) vertical geometry (as vertical versines using lining chord on tamper).
In addition, where geometry chart recorders are fitted to DTS or combinations of
DTS and tampers and regulators:
f) measurement of the increased lateral stability by action of the DTS; and
g) measurement of the vertical load applied by the DTS.
Where the DTS is the last machine to be used prior to the track being opened to
traffic, it shall be applied in Automatic mode.
16 Marking of geometry details on site
The start, finish and length of each transition curve and the cant in 5 mm steps shall
be marked permanently on the sleepers. The radius of curvature shall be marked at
the end of the transition. The cant shall be marked at intervals throughout the circular
curve. The lettering shall be black on a yellow background.
Datum marks related to the design alignment, level and cant of new/relaid track shall
be provided:
a) in accordance with NR/L2/TRK/3201, to every structure such as overbridge
abutments and underbridge parapets, platforms, walls etc., where kinematic
vehicle/structure clearances are below 200 mm (up to 3300 mm above rail level)
or 250 mm (above 3300 mm above rail level);
Page 95 of 105
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
b) at each overhead line mast and, where practicable, other contact wire supports
on overhead-electrified lines;
c) at suitable intervals to enable maintenance of track geometry on high cant
deficiency curves (i.e. where the cant deficiency might exceed 150 mm); and
d) on all S&C renewal sites by approved monuments.
Datum marks shall be resistant to disturbance. Details of the datum marks and their
offsets shall be supplied to Network Rail Maintenance.
16.1 High cant deficiency curves
High cant deficiency curves (deficiency >150 mm) shall be installed by machines
capable of achieving the design vertical and horizontal alignments and of producing
a post-installation record of the alignment.
All such curves and adjacent transitions shall be marked every 200 m and at each
milepost on the sleeper in the four-foot with a blue plate with the words HCD in
white.
17 Rail flange lubrication
17.1 Provision of lubricators
Existing rail flange lubricators shall be reinstated or replaced when track is renewed
or rerailed.
NOTE 1: Where rail flange lubricators are needed to address a series of curves an electric rail
flange lubricator should be provided.
Where no lubricators exist and the track is to be renewed or rerailed, lubrication shall
be specified on all curves:
a) with a radius of 1000 m or less;
b) exhibiting sidewear;
c) with a history of sidewear; or
d) that have been identified as at risk due to the introduction of new rolling stock.
All curves fitted with a check rail shall have lubricators fitted and commissioned to
both the high (outer) running rail and the check rail rubbing face.
Lubricators shall be commissioned and working within two weeks of track being
opened to traffic.
NOTE 2: Working is defined as a minimum of of the grease distribution unit ports clear and
expelling fresh grease upon manual activation and with grease visually observed where wheel
contact is apparent into the main body of the curve/s being served.
Page 96 of 105
Licensee=Capita Symonds to Capita property & infrastructur/5965831001
Not for Resale, 05/18/2016 04:44:17 MDT
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
b) a history of Rolling Contact Fatigue (RCF) (in order to help preserve a satisfactory
rail profile); or
c) a history of noise complaint (low rail damage = low rail noise/squeal. Possible low
rail friction management required).
NOTE 3: On long or back-to-back reverse curves, either more than one conventional flange
lubricator or an electric lubricator installation might be needed.
Any dimensions, datums, or numbering of stations etc. created for the construction
or renewal shall be removed from structures upon the completion of the works. They
shall be replaced as necessary with permanent datum markers.
Datum Plates to RE/PW/572 or an approved equivalent system shall be used for
displaying offsets, levels and cants on OLE masts, platforms walls and other
structures.
Marker plates shall be used for the permanent marking of chainages or stations on
platform walls, retaining walls or other structures. They shall be installed at a
consistent height relative to rail level. Stencils shall be used for painting chainages or
stations on cable troughs.
The permanent marking of dimensions, datums, station numbers (metres, chains, or
miles), and cant data etc. shall not be free hand painted onto platform walls,
retaining walls or any other structure.
NOTE: See 16 for the requirements regarding the marking of track geometry details on site.
Page 97 of 105
Copyright Network Rail
Provided by IHS under license with Network Rail
No reproduction or networking permitted without license from IHS
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
Restriction
Rail
Rail
60 mph
Rail
BR98lb FB
Rail
BR109
90 mph
Sleepers
Sleepers
75 mph
75 mph
Longitudinal timbers
Restriction
Jointed track
90 mph
75 mph
75 mph
Steel sleepers
60 mph
Page 98 of 105
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
Restriction
60 mph
Bullhead CWR on hardwood or concrete sleepers, and flatbottom CWR with Mills, RNB, AD, RD, CS3 or BJB
fastenings,
75 mph
105 mph
Restriction
75 mph
90 mph
90 mph
Timber bearers
125 mph
125 mph
as specified in
NR/L3/TRK/2049
Restriction
Page 99 of 105
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Curves below 200 m radius shall be fitted with continuous check rails in accordance
with section 10.10
21 Decommissioning of redundant assets
Redundant S&C in running lines at locations and on tracks where track renewal or
enhancement works are being undertaken shall be plain lined.
All scrap and waste materials shall be removed.
Strategic spares shall be recovered to the extent specified by the RAM [Track]
The associated signalling controls shall be recovered to the extent specified by the
RAM [S&T].
All associated overhead line electrification and direct current third and fourth rail
electrification shall be recovered to the extent specified by the RAM [E&P].
21.2 Redundant plain line
Rails and sleepers in redundant plain line track shall be assessed and categorised
as either serviceable or scrap. They shall be disposed of as specified by the RAM
[Track].
21.3 Redundant insulated joints
Redundant insulated rail joints generated by track or signalling renewal projects and
enhancement schemes shall be removed from track to the timescales specified in
table 34.
All replacement rails shall conform to the minimum lengths as specified in 10.12.3.
They shall be stressed when installed in CWR.
Table 34 Timescales for removal of redundant insulated rail joints
Track category
Timescale
1A, 1, 2
3&4
5, 6
No action necessary
NOTE: Timescales for the removal of shop repaired glued 6 hole insulated rail joints may be
extended with the agreement of the RAM [Track].
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Records shall be retained in the Health and Safety file as required by the CDM
Regulations.
In particular, records of track geometry (for new and relaid track) shall be created
and maintained electronically as follows.
1) Horizontal curves:
a. location of tangent points;
b. radius;
c. cant;
d. transition lengths;
e. cant gradients;
f. permissible speed;
h. the maintenance tolerances on cant and radius used to calculate enhanced
permissible speeds (where appropriate).
2) Vertical curves:
a. location of tangent points; and
b. minimum radius.
3) Gradients. Records of all gradients on running lines shall be maintained.
4) Residual health and safety risks and non-compliances should be recorded and
retained in the Health and Safety file.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
Table A.35 Geometrical track tolerances for ballasted track, track supported
by longitudinal timbers and short lengths of track with direct fastenings and
embedded rails
Parameter
Up to 20
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
In platforms and where other tight clearances apply, the track shall be placed within
the vertical, lateral and cross level tolerances set by the designer on the Form B.
These tolerances shall replace these values and shall be approved by the Network
Rail Gauging Engineer.
over 125
+0, -30
+0, -30
+0, -30
+0, -30
+0, -30
+0, -30
15
25
10
15
8
13
6
10
5
7
2
3
15
15
15
15
10
10
15
10
10
8
(1 in 375)
8
(1 in 375)
8
(1 in 375)
7
(1 in 428)
6
(1 in 500)
6
(1 in 500)
5
(1 in 600)
5
(1 in 600)
5
(1 in 600)
5
(1 in 600)
3
(1 in 1000)
3
(1 in 1000)
1435 - 41
1435 - 41
1435 - 41
1435 - 41
1435 - 40
1435 - 40
1435 - 38
1431 - 35
1435 - 38
1431 - 35
1435 - 38
1431 - 35
1435 - 38
1431 - 35
1435 - 38
1432 - 35
1435 - 37
-
1431 - 35
6
1431 - 35
5
1431 - 35
5
1431 - 35
4
1432 - 35
3
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
Vertical deflection under
load
Notes:
a
b
c
d
This applies at any point where vertical curvature reverses without an intervening constant gradient.
In curved track the versine shall not be of opposite hand to the design versine.
Any gauge widening on sharp curves should be added to these values (see 9.1.2).
The lower limit may be reduced to 1432 mm if serviceable concrete sleepers of nominal 1432 mm gauge are used.
Table A.36 Geometrical track tolerances for slab track and track not
included in Table A.1
Parameter
Up to 20
over 125
+0, -15
+0, -15
+0, -10
+0, -5
+0, -5
+0, -5
4
6
4
6
3
5
2
3
2
3
2
3
6
(1 in 500)
6
(1 in 500)
5
(1 in 600)
3
(1 in 1000)
3
(1 in 1000)
3
(1 in 1000)
4
(1 in 750)
4
(1 in 750)
3
(1 in 1000)
2
(1 in 1500)
2
(1 in 1500)
2
(1 in 1500)
1435 - 37
2
1435 - 37
2
1435 - 37
2
1435 - 38
1435 - 38
1435 - 38
3
3
3
No visible movement during passage of trains
a
b
c
d
This applies at any point where vertical curvature reverses without an intervening constant gradient.
In curved track the versine shall not be of opposite hand to the design versine.
Any gauge widening on sharp curves should be added to these values (see 9.1.2).
The values shall be reduced to 1432 mm to 1435 mm if vertical S&C with a designed gauge of 1432 is to be used.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Notes:
Ref:
Issue:
Date:
Compliance date:
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Speed
mph
Band 1 a
Band 2 a
WT35
AL 35
MT 70
AL 70
WT35
AL 35
MT 70
AL 70
Q1
10
2.0
1.7
2.6
1.8
Q1
15
2.0
1.7
2.6
1.8
Q1
20
2.0
1.7
2.6
1.8
Q2
25
2.0
1.7
2.6
1.8
Q2
30
2.0
1.7
2.6
1.8
Q3
35
2.0
1.7
2.6
1.8
Q3
40
2.0
1.7
2.6
1.8
Q4
45
2.0
1.7
2.6
1.8
Q4
50
2.0
1.7
2.6
1.8
Q5
55
1.7
1.3
2.1
1.4
Q5
60
1.7
1.3
2.1
1.4
Q6
65
1.7
1.3
2.1
1.4
Q6
70
1.7
1.3
2.1
1.4
Q7
75
1.4
1.1
1.6
1.2
Q7
80
1.4
1.1
2.1
1.7
1.6
1.2
2.4
1.9
Q8
85
1.4
1.1
2.1
1.7
1.6
1.2
2.4
1.9
Q8
90
1.4
1.1
2.1
1.7
1.6
1.2
2.4
1.9
Q8
95
1.4
1.1
2.1
1.7
1.6
1.2
2.4
1.9
Q9
100
1.3
0.9
2.0
1.6
1.4
1.0
2.1
1.7
Q9
105
1.3
0.9
2.0
1.6
1.4
1.0
2.1
1.7
Q9
110
1.3
0.9
2.0
1.6
1.4
1.0
2.1
1.7
Q10
115
1.3
0.8
1.8
1.5
1.4
1.0
2.0
1.6
Q10
120
1.3
0.8
1.8
1.5
1.4
1.0
2.0
1.6
Q10
125
1.3
0.8
1.8
1.5
1.4
1.0
2.0
1.6
Q11
130
1.0
0.7
1.3
1.1
1.1
0.9
1.5
1.2
Q11
135
1.0
0.7
1.3
1.1
1.1
0.9
1.5
1.2
Q11
140
1.0
0.7
1.3
1.1
1.1
0.9
1.5
1.2
The design alignment standard deviation value when added to the appropriate value above shall not exceed
the equivalent value for Good track quality in NR/L2/TRK/001.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
NOTE: These values are based on recordings by approved Network Rail track recording vehicles.
a
See 13.
NR/L2/TRK/2102
7
05/12/2015
01/05/2016
Ref:
Issue:
Date:
Compliance date:
Sp
Cat 1A
100
90
80
Cat 1
70
60
Cat 2
50
40
Cat 3
30 Cat 5
20
Cat 4
10 Cat 6
0
0
10
20
30
40
50
60
25/05/2010 - Version 1
Issue: 7
Compliance Date: 01/05/2016
Purpose:
Scope:
NR/L2/TRK/2102 required and has received a fundamental review and update of its structure and
contents. The key changes are as follows:
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
25/05/2010 - Version 1
Affected documents:
Reference
Impact
NR/L2/TRK/2102 ISSUE 6
Superseded
Briefing requirements: Where Technical briefing (T) is required, the specific Post title is indicated. These posts have specific responsibilities
within this standard and receive briefing as part of the Implementation Programme. For Awareness briefing (A) the Post title is not mandatory.
Please see http://ccms2.hiav.networkrail.co.uk/webtop/drl/objectId/09013b5b804504da for guidance.
Post
Team
Function
All Regions/Programmes
Investment Projects
RAM (T)
Track
Routes
Track
Routes
Principal Engineers
Track/RVE
STED
Senior Engineers/Engineers
Track/RVE
STED
Principal Engineers
Systems Engineering/M&E
STED
External
Track
Routes
Track
Routes
Briefing
(A-Awareness/
T-Technical)
*NOTE: Contractors are responsible for arranging and undertaking their own Technical and Awareness Briefings in accordance with their own processes and procedure
o
o
Sections 2 to 6 no change.
New Section 7 New Construction - Design.
New Section 8 Geometry Design (transferred from 2049).
Previous section 7, 8, & 9 renumbered to 9, 10 & 11.
New Section 12 Conversion of Jointed Track to CWR (transferred from 3011)
Previous section 10 renumbered to 13.
Three new sections 14, 15 & 16 on Geometry Targets & Tolerances, Tamping and
Dynamic Track Stabilisers and Marking of Geometry Details on site have been
created from the previous section 11.
Previous sections 12, 13 & 14 renumbered 17, 18 & 19.
New Section 20 on Decommissioning of Redundant Assets.
Section 2 - Scope
The scope of the document has been amended to restrict it to track with line speeds up
to and including 140mph (currently the standard has no upper speed limit). The
restriction to 140mph is in line with Railway Group Standards and specifically 5021
Track System Requirements.
The Infrastructure Technical Specification for Interoperability applies above 140mph.
Section 3 - Definitions
The definitions have been updated, changes and additions to definitions have not been
marked as a change.
Section 4 - Policy
Minor change only:
4.1 Business Outputs
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Sub clause (i) time to change components reduced to 4 hrs. This reflects
feedback from routes on the likely possession times for maintenance on the core
routes.
New clause - when reviewing systems for acceptance if the designed service life,
inspection or maintenance intervention frequency cannot be achieved the
implications shall be recorded and its impact assessed. This reflects the changes
made to clause 4.3.
4.3 - Materials
A temperature range of -27 C to +60 C has been set for all materials used in the
track system. Previously the only reference to temperature was in the section on
forces where -14 to + 53 was quoted.
Guidance added to the effect that failure to achieve the required performance
levels at the extremes of the temperature range should not prevent acceptance,
but the impact on performance shall be recorded, its criticality assessed and the
need for additional mitigation considered.
Cross reference to the new requirements for the conversion of jointed track.
Rails less than 37 m long shall be considered to be jointed track
5.5 Forces, figures quoted for the designed loading on check rails (taken from EN
13481-7) and for guard rails from recent research and review of existing systems.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Values included for the maximum cant deficiency at switch toes from GC/RT5021.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
6.3.2 - Construction
Requirement that ballast may only be heaped in the four foot as a temporary
measure and at no time shall it be higher than the plane of the rails.
6.3.4 Ballast Profile Jointed Track
In jointed track, the minimum width of ballast outside the sleeper ends shall be 300
mm for rails less than 37 m long and 375 mm for rails longer than 37 m.
Where rails are longer than 37m and where extra lateral resistance is required
CWR-type shoulders shall be provided.
6.4 Ballast Gluing
Section expanded to allow the use of ballast gluing for designed transitions.
Ballast gluing may only be used for increasing the lateral fixity of track where
clearances are restricted or as part of a designed transition between different track
constructions or at structures, it may only be used with the agreement of the
RAM[Track].
The design should include the transitional arrangements from normal to glued track.
6.5.3 Guard Rails
Existing requirements for placing of guard rails on the approach to structures
clarified. Where they are required on a structure they shall commence 18m from
the face of the abutment and include a set of gathering rails.
Further work is required on the criteria for installing guard rails and the
standard designs of guard rails. In due course new RE/PW drawings will
need to be prepared and published.
movable portion of the structure and the machined section of the expansion joint
does not to exceed 450kN.
The requirement is necessary with the move to high toe load fastenings, otherwise
there is a danger that the expansion joint will not work as designed.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
the designed gauge widening. The limitations for slip switches were previously
published in 2049.
1 in 7 and 1 in 7 slips shall only be installed on straight track.
Any through line radius applied to 1 in 8 and 1 in 10 slips shall not result in a slip
radius of less than 176 metres.
S&C (of any type or design) shall not be installed on track with a through line
radius of less than 150m.
S&C installed on track with a through line radius between 175 and 150m shall be
subject to a risk assessment, the assessment shall consider as a minimum:
Direction of traffic
Tonnage
Speed
Wheel / rail interaction
The provision or absence of Gauge widening
The provision or absence of continuous check rails
Inspection regime
Environment
Access
Consequential risks
Note that the requirements do not differentiate between running lines and sidings.
Slips are subject to tighter controls as only a very limited amount of gauge
widening can be provided and checking is not possible.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Existing 2049 data sheets have been split into a number of smaller tables:
B.1.1 definitions have been included in section 3 Definitions.
B.2.1 Curving Design Values Cant & Rate of Change of Cant split into:
Table 4 table included to cover cant and cant deficiency limits for tilting trains
Table 6 Cant
Table 7 - Cant gradients.
Table 8 Transitions
Table 9 - Cant Deficiency Plain Line & Adjustment Switches.
B.2.3 Curving Design Rules Rate of Change of Cant Deficiency split into:
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Where the adjacent track is not to be renewed the excavation shall extend to
the centre line of the six foot (to a maximum of 1300 mm from the 6 rail).
10.3.5 - Compaction of ballast
Section revised around compaction of ballast layers;
For plain line track categories 1A, 1 and 2, compaction may be achieved as
follows:
a) using approved vibrating plates, in a single layer for ballast depths up to 480
mm, or where ballast depths under the sleeper are greater than 480 mm in
layers not exceeding 300 mm
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Text amended to include the requirement that when temporary rails are replaced in
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Existing clause split into three; Provision and Siting, Temporary Adjustment
Switches, Fastening toe Loads Stress Transition length.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
AWS, TPWS and axle counters have not been checked to confirm that
the mass of the bearer tie does not interfere with the signalling
equipment.
Where bearers are split into three parts the centre section must contain at
least one pair of rails across track gauge.
Helps the achievement of relative levels across the width of the
layout.
Amber requirements:
S&C containing bearer ties shall have the cant and longitudinal levels designed
so that tracks connected by tied bearers have no difference in the plane of the
rails or a change in gradient within 18 m of a tied bearer.
Ensures that the track is co-planer on the approach to the ties.
Bearer ties shall be positioned as shown on RE/PW general arrangement
drawings.
For geometries where general arrangement drawings with bearer ties are not
available ties shall be positioned in line with the principles shown below:
The reminder of the requirements are guidance for the use of ties in
non-standard layouts:
a) The number of ties shall be kept to a minimum, short ended bearers shall
be used to reduce the number of ties.
b) Bearers are to be shortened on the turnout or crossover route before being
shortened on the through route.
c) Where possible ties are to be positioned in the 6 rather than the 4.
d) Where ties have to be positioned in the 4 they shall be installed on the
turnout or crossover line in preference to the through route.
e) The number of part bearers supporting only one rail shall be kept to a
minimum.
f)
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
AWS magnets, TPWS equipment and axle counters shall not be installed in
beds with bearer ties.
75mm.
g) In crossovers spanning parallel tracks (with matching geometry on sides)
the position of bearer ties and bearer lengths shall be mirrored either side of
the mid point of the crossover.
11.6.5 Two-levelling in S&C
New clause giving guidance on whether to utilise two-levelling. This has been
included in response to the problems encountered at Shalford Junction.
The rules for two-levelling remain in 2049.
Wherever practicable cant deficiency shall be maximised to avoid the need for
two levelling.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Two levelling, with the crossing either higher or lower, affects the wheel transfer
between wing rail and crossing nose; leading to higher impact forces - which
worsen with increasing speed. The effect is more pronounced on shorter
angled crossings.
OLE & DC 3rd rail electrification to be recovered to the extent specified by the
RAM(E&P).
Redundant plain line to be assessed for use as serviceable and recovered as
specified by the RAM(Track).
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---
Section 22 - Records
Minor amendment calling for projects to include amendments to the records of other
assets as a result of knowledge gained during site surveys, investigations or
construction work.
Deletions
Nothing significant.
--`,`,,,,,`,`,,,,`,,,,``,,,```-`-`,,`,,`,`,,`---